Paoli Pike Trail: Construction Begins May 27

Work will commence on the Paoli Pike Trail Project from Reservoir Road to Rt. 352 on Wednesday, May 27. As part of this work, Allen Myers will install temporary striping on Paoli Pike from Boot Rd to Route 352  from 8:00 pm until 5:00 am on May 27. The rain date will be May 28 if needed.

A new long-term traffic control pattern, approved by PennDOT, will be implemented during the overnight hours of Thursday, May 28.  This new traffic pattern will begin at the Goshen Village Shopping Center entrance on Paoli Pike and continue to the intersection of Rt. 352.  This traffic pattern will remain in effect from May 28 until approximately August 28. Construction operations for this segment of the Paoli Pike Trail Project will continue throughout the summer, commencing sometime in the Fall of 2020.

In addition, the township will also have road restrictions on Paoli Pike the week of May 26 between Vista Dr. and Route 352 for the island construction 8:00 am to 4:00 pm.