Municipal Authority

The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.

 

The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.

  • Five members, serving five-year terms
  • Meetings are on the 2nd Monday of the month at 7:00 P.M.
  • All township meetings are held at the Township Building and open to the public
Authority Members Term Expiration Date
Kevin Cummings, Chairman 2026
John Stipe, Vice Chairman
2029
Dana Pizzarro, Secretary 2026
Sean Ellsworth, Assistant Secretary/Treasurer 2028
Walter Wujcik, Treasurer 2028
Pennoni Associates, Engineer
Patrick M. McKenna, Esq.
Peter Hicks, BoS Liaison
Kevin Miller, Staff Liaison

 

Municipal Authority Genealogy

Audits

Documents

Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.

EAST GOSHEN MUNICIPAL AUTHORITY

July 14, 2014
Monday 7:00 PM

  1. CALL TO ORDER/PLEDGE OF ALLEGIANCE/MOMENT OF SILENCE Ask if anyone will be taping the meeting?
  2. CHAIRMAN’S REPORT/OTHER MEMBERS REPORTS
  3. SEWER REPORTS Director of Public Works Report; Pennoni Engineer’s Report; Big Fish Environmental Inc. Report with DMR’s; East Goshen Township Flows for June 2014
  4. APPROVAL OF MINUTES June 9, 2014
  5. APPROVAL OF INVOICES Pennoni      Invoice #594993      $ 309.00; Pennoni      Invoice #594994      $ 430.00; Pennoni      Invoice #594995      $1,521.25; Gawthrop      Invoice #121393      $2,000.00; Maillie      Invoice #1000036708      $10,800.00
  6. LIAISON REPORTS
  7. FINANCIAL REPORTS June 2014 Report; 2013 Audit Report from Maillie
  8. OLD BUSINESS
  9. GOALS Review current mission statement and provide the Board of Supervisors with changes, if needed – June 1, 2014 May 8 – The MA does not have a current mission statement. A first draft is included in the packet. June 9 – Changed “lease” to “leasee” Approved by MA on June 9 - Completed; Submit an article for each newsletter – Due date for newsletter Need by 1/31/14 – Dana Completed Need by 4/30/14 – Jack Completed

F:\Data\Shared Data\Agendas\Municipal Authority4-14-14 -.doc

Need by 7/1/14 - Kevin
Need by 10/31/14

  1. Obtain PA DEP approval for the Act 537 Plan revision for the Reservoir Road Pump Station – December 31, 2014 May 8 - Revisions submitted to EGMA, EGPC, WGSTP, CCHD, and CCPC July 14 – BOS scheduled to adopt resolution at their meeting on August 19
  2. Develop a recommendation on covers for the SBRs – August 1, 2014 May 8 – Draft memo distributed. June 9 – Final memo in packet - Completed
  3. Attend West Goshen Meetings quarterly – more often if needed. 1 st Quarter (March) – Jack- Completed 2 nd Quarter (June) – Ed- Completed 3 rd Quarter (September) 4 th Quarter (December)
  4. Respond to capacity requests in 45 days or less. 211 Ellis Lane – 1 EDU existing house, 195 Wyllpen Place – 1 EDU existing house
  5. Continue to implement I & I Plan April 14 – Status Report received
  6. Operate RCSTP in compliance with NPDES Permit January, February, March, May,
  1. NEW BUSINESS
  2. CAPACITY REQUESTS 3 Lucas Lane - Willistown Township (44 EDUs)
  3. ANY OTHER MATTER
  4. CORRESPONDENCE AND REPORTS OF INTEREST Minor Act 537 Plan Update Revision
  5. PUBLIC COMMENT
  6. ADJOURNMENT

F:\Data\Shared Data\Agendas\Municipal Authority4-14-14 -.doc

AREA CODE 610
692-7171

EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP

1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

July 11, 2014

To: Municipal Authority
From: Mark Miller
Re: June 2014 Monthly Report

Meters: All meters were read on a daily basis. We are waiting on Allied Control to schedule the installation of the portable meters.

C.C. Collection: The pump stations were visited on a daily basis. All pumps were pulled for routine maintenance at each station. Ashbridge pump station was on emergency power for 3 days.

R.C. Collection: The Hunt Country pump station was on emergency power for three days due to a power failure.

R.C. Plant: We reinstalled pump 3 at the list station. Apple Brook pumps were turned on last week.

INI: Pipe Data View will be in the last week of July to clean and televise.

Alarms: We responded to 37 alarms for the month of May.

PA One Calls: We received 119 PA One calls in May.

EGMA 1401

Pennoni

MEMORANDUM

TO: East Goshen Municipal Authority Board
Rick Smith, Township Manager

FROM: Michael Ellis, P.E.
Authority Engineer

DATE: July 10, 2014

SUBJECT: Engineer’s Report

Invoices

  • Invoices with summaries are provided under separate cover.

Reserve Pump Station Elimination

  • We coordinated with the contractor to perform the outstanding site-work punchlist items: removal of the filter sock along the creek and re-topsoiling & re-seeding the lawn area at the old pump station driveway and building. We performed an inspection of the work after it was completed. We are still awaiting resubmission of as-built plans with surveyed manhole elevations.

Reservoir Road Pump Station Act 537 Plan

  • We revised the construction schedule (see attached) in the Act 537 Plan to address West Goshen’s comments for compliance with the intermunicipal agreement.
  • We received Act 537 Plan review forms from the East Goshen Municipal Authority, East Goshen Township Planning Commission, and Chester County Health Department. We are awaiting Act 537 Plan review forms to be completed and returned from the West Goshen Township Planning Commission and Chester County Planning Commission. Reviews were due by July 9.
  • It is our understanding that the West Goshen Sewer Authority approved the Act 537 at their meeting on July 3 and that they will be sending an approval letter.
  • We received feedback from the U.S. Fish & Wildlife Service (USFWS) on the Phase 1 bog turtle habitat survey report. To address their comments, we revised the plans and Act 537 narrative to propose the Chester Creek stream crossing be constructed via open cut instead of the previously proposed directional drilling. We provided the plans to Conestoga-Rovers & Associates to resubmit to USFWS for approval. We expect to receive USFWS approval the week of July 14-18.

Page 1 of 2

P:\Projects\EGMA\Memos to Board4\Memo to EGMA Board 2014-07-10.docx

EGMA 1401

  • Tentative Act 537 Planning schedule: Milestone Estimated Date County and Township Agency Review Comments Due July 9, 2014 Complete Plan Revisions to Address Agency Comments July 14, 2014 Begin 30-Day Public Comment Period July 17, 2014 USFWS Bog Turtle Habitat Formal Approval/Comments July 18, 2014 End 30-Day Public Comment Period August 15, 2014 East Goshen Township Adoption August 19, 2014 Submission to PADEP August 22, 2014 PADEP Review and Approval (120 days) December 21, 2014

New Sewer Connections

  • We completed a review of the revised design plans and report submission for a new private wastewater pump station for Acero Precision at 1340 Enterprise Drive, issued a comment letter, and discussed comments with the design consultant.

Fairway Village Manhole Lining

  • Abel Recon performed the construction demonstration of the SprayWall monolithic polyurethane interior manhole lining system on June 10, 2014.

Sewer Ordinance and Detail Updates

  • We prepared draft updates to the Township’s building sewer/lateral connection detail and sanitary sewer ordinance text.

Page 2 of 2

P:\Projects\EGMA\Memos to Board4\Memo to EGMA Board 2014-07-10.docx

East Goshen Township, Chester County
Minor Act 537 Plan Update Revision
Reservoir Road Pump Station

Section N - Project Implementation Schedule

East Goshen Municipal Authority proposes the implementation schedule in Table N.1 with milestone dates for system design and permitting. The dates for bidding, construction, and activation of the pump station will be determined based upon actual future flows in order to maintain compliance with the intermunicipal agreement with West Goshen Township.

Table N.1 - Implementation Schedule

Project Milestone Tentative Dates
Submit Act 537 Plan Update Revision to PADEP August 2014
PADEP Approval of Act 537 Plan Update Revision December 2014
Submit WQM Part II Application to PADEP August 2015
PADEP Approval of WQM Part II Permit December 2015
Construction Bidding TBD (1)
Award Construction Contract 2 months after bidding
Begin Construction 3 months after bidding
Complete Construction 9 months after bidding
Pump Station Activation TBD (2)

(1) The construction contract bidding period will occur no sooner than after two consecutive quarters in which East Goshen Township’s average daily flow to West Goshen Township (as measured at the Westtown Way Meter in the Chester Creek Interceptor) exceeds 950,000 gpd. Initiation of bidding and construction at an average daily flow of 950,000 gpd is projected to put East Goshen in position to have a pump station that is fully constructed and ready for operation when flows exceed 1,000,000 gpd.

(2) The pump station will not be permanently activated and placed into service until the intermunicipal flow exceeds 1,000,000 gpd.

EGMA1307

40

2013 FLOWMETERS

2014 JUNE 2ND QUARTER- METERS FROM WEST GOSHEN - CC COLLECTION

Precip WESTTOWN WAY ELLIS LANE PAOLI PIKE WILSON DRIVE SUMMIT NET
1000 10 10 10
Inches DATE READING GPD READING GPD READING GPD READING GPD GPD FLOWS
0.00 06/01/14
0.00 06/02/14 1,706,811 1,152,667 5,367,565 130,953 3,222,535 70,443 1,632,900 57,350 24,000 893,920
0.05 06/03/14 1,707,972 1,161,000 5,380,517 129,520 3,229,749 72,140 1,640,698 77,980 24,000 881,360
0.05 06/04/14 1,709,166 1,194,000 5,393,270 127,530 3,237,012 72,630 1,649,376 86,780 24,000 907,060
0.05 06/05/14 1,710,323 1,157,000 5,406,264 129,940 3,244,167 71,550 1,658,528 91,520 24,000 863,990
0.00 06/06/14 1,711,468 1,145,000 3,251,013 68,460 1,667,560 90,320 24,000 986,220
0.00 06/07/14 24,000 0
0.12 06/08/14 24,000 0
0.20 06/09/14 1,714,724 1,085,333 3,271,213 67,333 1,694,851 90,970 24,000 927,030
0.15 06/10/14 1,715,868 1,144,000 5,415,188 17,848 3,277,853 66,400 1,706,522 116,710 24,000 943,042
0.12 06/11/14 24,000 0
0.60 06/12/14 1,718,153 1,142,500 5,439,886 123,490 3,291,418 67,825 1,728,617 110,475 24,000 840,710
0.17 06/13/14 1,719,366 1,213,000 5,454,638 147,520 3,298,831 74,130 1,740,151 115,340 24,000 876,010
0.00 06/14/14 24,000 0
0.00 06/15/14 24,000 0
0.00 06/16/14 1,722,683 1,105,667 5,494,367 132,430 3,319,059 67,427 1,770,648 101,657 24,000 804,153
0.00 06/17/14 1,723,814 1,131,000 5,506,577 122,100 3,325,434 63,750 1,782,706 120,580 24,000 824,570
0.25 06/18/14 1,724,887 1,073,000 5,518,234 116,570 3,331,883 64,490 1,794,399 116,930 24,000 775,010
0.08 06/19/14 1,726,042 1,155,000 5,531,700 134,660 3,338,532 66,490 1,805,824 114,250 24,000 839,600
0.00 06/20/14 1,727,187 1,145,000 5,544,845 131,450 3,344,925 63,930 1,816,499 106,750 24,000 842,870
0.00 06/21/14 24,000 0
0.00 06/22/14 24,000 0
0.00 06/23/14 1,730,270 1,027,667 5,579,070 114,083 3,363,655 62,433 1,841,224 82,417 24,000 768,733
0.00 06/24/14 1,731,352 1,082,000 5,590,313 112,430 3,370,098 64,430 1,851,246 100,220 24,000 804,920
0.50 06/25/14 1,732,408 1,056,000 5,600,958 106,450 3,376,192 60,940 1,860,837 95,910 24,000 792,700
0.00 06/26/14 24,000 0
0.00 06/27/14 1,734,579 1,085,500 5,625,043 120,425 3,388,429 61,185 1,878,444 88,035 24,000 815,855
0.00 06/28/14 24,000 0
0.00 06/29/14 24,000 0
0.00 06/30/14 1,737,518 979,667 5,657,722 108,930 3,406,232 59,343 1,898,475 66,770 24,000 744,623
Day Avg 1,117,632 118,019 66,596 96,366 24,000 556,289
3.69 Day Tot 21,235,000 2,006,330 1,265,330 1,830,963 696,000 16,132,377
Day Count 19 17 19 19 29 29
EG TWP
MONTH TO DATE 3.69
NORMAL MONTH TO DATE
YEAR TO DATE 32.39
NORMAL YEAR TO DATE

f:/data/users/joanna/2003 flowmeters      7/9/201410:19 AM

2013 FLOWMETERS

2014 JUNE 2ND QUARTER- METERS FROM WEST GOSHEN - CC COLLECTION

HERSHEY'S MILL ASHBRIDGE HICKS METER RESERVOIR BARKWAY
10 100 10 10 10
DATE READING GPD READING GPD READING GPD READING GPD READING GPD
06/01/14
06/02/14 13,892,766 844,980 1,910,960 76,933 12,383,130 241,827 49,382,773 704,277 3,244,928 12,740
06/03/14 13,973,302 805,360 1,911,711 75,100 12,411,738 286,080 49,459,286 765,130 3,246,139 12,110
06/04/14 14052321 790,190 1,912,449 73,800 12,440,349 286,110 49,535,210 759,240 3,247,376 12,370
06/05/14 14,129,920 775,990 1,913,150 70,100 12,469,339 289,900 49,610,455 752,450 3,248,470 10,940
06/06/14 14,205,349 754,290 1,913,865 71,500 12,498,042 287,030 49,685,285 748,300 3,249,650 11,800
06/07/14
06/08/14
06/09/14 14,429,353 746,680 1,915,988 70,767 12,569,804 239,207 49,878,763 644,927 3,253,282 12,107
06/10/14 14,501,388 720,350 1,916,687 69,900 12,601,110 313,060 49,955,075 763,120 3,254,427 11,450
06/11/14
06/12/14 14,644,497 715,545 1,918,055 68,400 12,664,772 318,310 50,109,804 773,645 3,256,723 11,480
06/13/14 14,714,182 696,850 1,918,750 69,500 12,698,765 339,930 50,196,110 863,060 3,257,833 11,100
06/14/14
06/15/14
06/16/14 14,931,790 725,360 12,776,731 259,887 50,410,235 713,750 3,261,331 11,660
06/17/14 15,002,196 704,060 1,921,496 68,650 12,806,383 296,520 50,485,347 751,120 3,262,443 11,120
06/18/14 15,070,442 682,460 1,922,141 64,500 12,837,547 311,640 50,562,434 770,870 3,263,467 10,240
06/19/14 15,139,453 690,110 1,922,805 66,400 12,869,040 314,930 50,642,831 803,970 3,264,417 9,500
06/20/14 15,209,999 705,460 1,923,485 68,000 12,899,149 301,090 50,720,081 772,500 3,265,379 9,620
06/21/14
06/22/14
06/23/14 15,414,318 681,063 1,925,408 64,100 12,972,787 245,460 50,919,687 665,353 3,268,612 10,777
06/24/14 15,480,065 657,470 1,926,059 65,100 13,003,948 311,610 50,995,650 759,630 3,269,699 10,870
06/25/14 15,546,727 666,620 1,926,680 62,100 13,033,905 299,570 51,068,672 730,220 3,270,746 10,470
06/26/14
06/27/14 15,678,404 658,385 1,927,951 63,550 13,091,867 289,810 51,218,623 749,755 3,272,784 10,190
06/28/14
06/29/14
06/30/14 15,864,974 621,900 1,929,802 61,700 13,160,040 227,243 51,415,330 655,690 3,275,780 9,987
718,059 68,339 287,327 744,579 11,081
13,643,123 1,230,100 5,459,213 14,147,007 210,530
19 18 19 19 19

f:/data/users/joanna/
2003 flowmeters      7/9/201410:19 AM

2014 SUMMARY OF METER READINGS

WESTTOWN WAY ELLIS LANE PAOLI PIKE WILSON DRIVE SUMMIT HERSHEY MILL ASHBRIDGE HICKS RESERVOIR BARKWAY
JANUARY 1,120,955 112,631 63,436 80,890 24,000 255,116 795,376
FEBRUARY 1,249,173 138,449 68,472 88,803 24,000 287,831 881,433
MARCH 1,182,533 126,933 67,479 84,197 24,000 860,074 75,186 291,520 827,109 28,696
APRIL 1,242,798 143,329 76,736 88,674 24,000 1,029,229 79,139 300,256 806,253 12,331
MAY 1,542,161 175,112 95,766 94,501 24,000 1,337,536 117,391 357,808 937,139 20,786
JUNE 1,117,632 118,019 66,596 96,366 24,000 718,059 68,339 287,327 744,579 11,081
JULY
AUGUST
SEPTEMBER
OCTOBER
NOVEMBER
DECEMBER
Total Flows
Monthly Ave 1,242,542 135,746 73,081 88,905 24,000 986,225 85,014 296,643 831,982 18,224
To West Goshen 944,811

2014 flowmeters -all-stations separate month worksheets.xlsxSUMMARY

June Precip. 3.69 - 2014

Chart, printed rotated 90 degrees: a 3-D vertical bar chart titled “June Precip. 3.69 - 2014”. The vertical axis is labeled “Precip.” with values from 0 to 0.6. The horizontal axis is labeled “snow/rain” with categories numbered 1 through 33 representing days of the month.

Day Approximate bar value
1 to 3no bar
4about 0.50
5about 0.50
6about 0.50
7 to 8no bar
9about 0.12
10about 0.20
11about 0.15
12about 0.12
13about 0.60
14about 0.17
15 to 18no bar
19about 0.25
20about 0.08
21 to 25no bar
26about 0.50
27 to 33no bar

Legend: June (blue).

2013
Monthly Precipitation

Chart, printed rotated 90 degrees: a 3-D bar chart titled “2013 Monthly Precipitation”. The value axis runs from 0 to 8 in increments of 1. The category axis lists January through December. Only January through June have bars; July through December are empty.

Month Approximate bar value
Januaryabout 3.9
Februaryabout 2.9
Marchabout 3.7
Aprilabout 7.6
Mayabout 4.7
Juneabout 3.8
July to Decemberno bar

Legend: Series1 (blue).

Flowmeters June 2014

Chart, printed rotated 90 degrees: a line chart with diamond markers titled “Flowmeters June 2014”. The horizontal axis is labeled “Day of the Month” (1 to 29); the value axis is labeled “Flow's” and runs from 0 to 1200000 in steps of 200000. The line alternates between zero and peaks around 800,000 to 1,000,000.

  • Peaks (approximate): days 1 to 3 about 880,000 to 910,000; day 4 about 860,000; day 5 about 980,000; days 8 to 9 about 925,000 to 945,000; days 11 to 12 about 840,000 to 875,000; days 15 to 19 about 775,000 to 845,000; days 22 to 24 about 770,000 to 805,000; day 26 about 815,000; day 29 about 745,000.
  • Zero flow on days 6, 7, 10, 13, 14, 20, 21, 25, 27, and 28.

Legend: June (blue line with diamond marker).

Monthly Totals 2012 Jan-Dec

Chart, printed rotated 90 degrees: a vertical clustered column chart titled “Monthly Totals 2012 Jan-Dec” on a light blue plot area. The value axis is labeled “Flowmeters” and runs from 0 to 2500000 in steps of 500000. The category axis is labeled “Month” and lists January through December. January through June each contain a cluster of thin bars (one per day), mostly between about 700,000 and 1,200,000, with the highest bars occurring in May (around 2,000,000 and 2,200,000). June bars range from approximately 750,000 to 1,000,000. July through December are empty. No legend is printed.

draft

EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
MEETING MINUTES
June 9, 2014

The East Goshen Township Municipal Authority held their regular public meeting on Monday, June 9, 2014 at 7:00 pm at the East Goshen Township building. Members in attendance were: Chairman Jack Yahraes, Kevin Cummings, Dana Pizarro, and Ed McAssey. Also in attendance were: Rick Smith (Township Manager), Carmen Battavio (Supervisor), Patrick McKenna (Attorney), Mark Miller (Director of Public Works), Scott Towler (BFES), and Mike Ellis (Pennoni).

COMMON ACRONYMS:

BFES – Big Fish Environmental Services MA- Municipal Authority
BOS – Board of Supervisors NPDES – National Pollutant Discharge Elimination System
CB – Conservancy Board PC – Planning Commission
DEP – Department of Environmental Protection PR – Park & Recreation Board
EPA – Environmental protection Agency RCSTP – Ridley Creek Sewer Treatment Plant
HC – Historical Commission SBR – Sequencing Batch Reactor
I&I – Inflow & Infiltration SSO – Sanitary System Overflow
LCSTP – Lockwood Chase Sewer Treatment Plant WAS – Waste Activated Sludge

Call to Order & Pledge of Allegiance

Jack called the meeting to order at 7:00 pm and led those present in the Pledge of Allegiance. There was a moment of silence to remember the troops and all veterans. Jack asked if anyone would be recording the meeting and there was no response.

Chairman's Report/Other Members' Reports

Ed attended the West Goshen meeting. There was discussion about the East Goshen Reservoir Road Pump Station. West Goshen feels that 1 million gpd is the minimum under the contract. Ed explained that East Goshen is concerned about the growth in West Goshen and the 25% penalty, if they go over 1m gpd.

Sewer Reports

1. Director of Public Works
Mark Miller reported for April 2014:
Meters: All meters were read on a daily basis. The two portable meters have not arrived yet. As they come in we will get them installed. The new meters have the capabilities of sending out the reading thru the internet. Mark has asked Allied to give a cost to modify the meters to allow us to get the readings over the internet for the 2015 budget.
CC Collection: The pump station wet wells were cleaned last week. The wet well at Barkway pump station had several leaks. We packed the leaks and pumped 60 gallons of grout into them to seal the leaks. The pumps are scheduled to be pulled for routine maintenance next week. We repaired a broken lateral on Red Maple Lane. Last Monday the lateral line sheared off which was allowing heavy inflow into the system.
RC Collection: The Hunt Country pump station was visited on a routine basis with no problems to report. The wet well was cleaned last week.

F:\Data\Shared Data\Minutes\Municipal Authority\2014\MA 6-9-14 draft.doc      1

RC Plant: The wet well was cleaned last week. We are scheduled to re-install the lift station pump next week and pull another for routine maintenance.
Alarms: We responded to 21 alarms for the month of May.
PA One Calls: We received 116 PA calls in May.
Mark is concerned about the meter numbers. He is not sure if it is due to the new software.

2. Pennoni Engineer's Report
Mike Ellis gave the following report:
Invoices: Invoices with summaries are provided under separate cover.
Ridley creek Sewage treatment Plant (RCSTP): Pennoni continues to provide operations assistance as needed. No operational issues were brought to our attention in May.
Reserve Pump Station Elimination: There are three outstanding punch list items at the time of this report: removal of the filter sock along the creek, re-seeding/re-topsoiling the lawn area at the old pump station driveway and building, and resubmission of as-built plans with surveyed manhole elevations. The contractor has informed us that they have visited the site to evaluate the work to be performed, and they are hopeful to complete the work by June 13.
Reservoir Rd Pump Station Act 537 Plan: We are awaiting Act 537 Plan review forms to be completed and returned from the East Goshen Township Planning Commission, West Goshen Township Planning Commission, Chester County Planning Commission, Chester County Health Department and West Goshen Sewage Treatment Plant operator. Reviews are due by July 9, 2014.
Based upon the revised force main routing and additional information that we submitted, the PA Dept. of Conservation and Natural Resources (DCNR) retracted their requirement for a field botanical survey of potential threats to certain plant species.
We are awaiting feedback from the U.S. Fish & Wildlife Service on the Phase 1 bog turtle habitat survey report that was submitted by Conestoga-Rovers & Assocs. in late April.
Tentative Act 537 Planning schedule (assuming no Phase 2 bog turtle screening):

Estimated Date
USFWS Bog Turtle Habitat Coordination June 30, 2014
County & Township Agency Review Comments Due July 9, 2014
Revisions per agency comments July 14, 2014
30-Day Public Comment Period August 15, 2014
East Goshen Twp. Adoption August 19, 2014
PADEP Review and Approval (120 Days) December 21, 2014

New Sewer Connections
We completed a review of the design plan and report submission for a new private wastewater pump station for Acero Precision at 1340 Enterprise Drive, issued a comment letter, and discussed comments with the design consultant.
Fairway Village Manhole Lining
Abel Recon will perform the demonstration of the SprayWall monolithic polyurethane interior manhole lining system on June 10, 2014. The demonstration will begin at 11:00am at the site.
RCSTP Tank Covers
We completed the evaluation of tank cover alternatives and forwarded an updated summary memo to the Township.

F:\Data\Shared Data\Minutes\Municipal Authority\2014\MA 6-9-14 draft.doc      2

RESERVOIR ROAD PUMP STATION

The Authority members reviewed a letter from the Consulting Engineers for the West Goshen Sewer Authority. West Goshen does not want to lose revenue. East Goshen is not at 1 million gpd yet. West Goshen wants us to wait to do the diversion until we reach 1 million gpd. Anything over 1 million gpd is a 25% additional fee. The capacity at West Goshen is 6 million gpd. They are around 5 million gpd. West Goshen will be impacted when the total goes over 6 million gpd. Rick wants to continue the process of getting permits, etc. He suggested that construction start when East Goshen gets to 950,000 gpd. He will write a response to West Goshen.

3. Big Fish Environmental Services – The following is Scott's report for May 2014:
Treatment Process Operation- During April 2014, there were one exceedance of the final effluent discharge limitations for Outfall 001 and no discharge from Outfall 002. The exceedance reported was a total phosphorus monthly average concentration of 0.54 mg/L as compared to the permitted limitation of 0.50 mg/L.
The monthly average total phosphorus concentration was 0.54 mg/L as compared to the discharge limitation of 0.5 mg/L. During the month, the final effluent total phosphorus concentration discharged ranged from 0.30 mg/L to 0.68 mg/L with an average of 54.3 gallons per day of aluminum sulfate solution.
There was no discharge to Applebrook, Outfall 002, during April 2014.
During the month of April 2014, the total phosphorus concentrations at the final effluent outfall 001 were slightly elevated at or above the permitted discharge limitation of 0.5 mg/L.
Aluminum sulfate feed rates were increased as the month progressed to assist with total phosphorus removal. Periodically, the influent flow rate and volume to the SBRs resulted in “Filled Decants.” The Filled Decant condition results in diverting a mixture of influent wastewater and treated effluent directly to the post flow equalization basins, disc filters and disinfection prior to discharge through outfall 001.
During the month of May 2014, there was no discharge to Applebrook.
The influent wastewater pollutant concentrations and loading entering the wastewater treatment facility remained within the design concentrations and loadings. Composite samples are collected at the influent doghouse manhole and influent wet well. The influent flow meter reading is collected from the influent flow meter located prior to the Screening Building, excluding the internal recycle flows.
Sequencing batch reactors (SBRs) 1, 3 and 4 were in service during the month of May. Process monitoring of each SBR included ammonia as N, Nitrite as N, Nitrate as N, COD, SSV, MLSS and total phosphorus. Foam concentrations remain reduced during the month of April. Increased sludge wasting was continued to maintain lower the MLSS concentrations. SBRs 3 & 4 were observed to have a maximum of approximately 5% to 10% of the surface area covered with a medium brown colored foam. Adjustments to the treatment process to lower the MLSS concentrations and raise the F:M ratio within the target range of 0.045 to 0.06 were ongoing during the month. Process adjustments to manage the foam included adjustments for achieving the lower ammonia as nitrogen discharge concentration of 2.5 mg/L as compared to the 7.0 mg/L during April.
Daily monitoring of the influent and final effluent 24-hour composites samples for total phosphorus is ongoing. Daily analysis of the final effluent flow equalization grab sample total

F:\Data\Shared Data\Minutes\Municipal Authority\2014\MA 6-9-14 draft.doc      3

phosphorus is ongoing. Sample collection and analysis of the influent wastewater collected at the influent pump station wet well is ongoing.
Addition of aluminum sulfate solution to the SBRs to assist with phosphorus removal continued. The volume of aluminum sulfate solution to the SBRs was increased from a daily average of 54.3 gpd during April to 82.6 gpd during May to assist with total phosphorus removal. Increased aluminum sulfate dosages prior to filtration were increased during the month. The increase in alum addition resulted in an increase in soda ash addition. During May the daily average soda ash addition was 439 lbs/day as compared to the Paril daily average of 308 lbs/day. The increase in soda ash was to assist towards maintaining pH concentrations above 7.0 standard units continued during the month.
SBR #2 remains out of service as a treatment unit, however, partially filled with MLSS which is continuously mixed and aerated. The majority of the contents were transferred to the sludge holding tanks. This SBR was periodically placed in service to assist with managing peak flows to reduce the impact of Filled Decant conditions.
The decanter for SBR 3 was occasionally observed as being slightly tilted within the water level. The effluent knife valve was routinely closed and the decanter filled with water to assist with lowering the decanter within the water level. The frequency of occurrence varied during the month. The SBR is planned for removal from service during late June for inspection.
Solids Dewatering and Disposal: May 2014
During the month, sludge wasting to the sludge holding tanks and decanting of the sludge holding tanks was ongoing. Process monitoring included pH, total alkalinity and total solids.
Sludge holding tank #1 was in service. The level at the beginning of the month was 7.44 feet and the level at the end of the month was 11.72 feet. The initial total solids concentration was 0.62% and ended the month as 0.73% total solids. The average pH concentration was 7.30 S.U. and total alkalinity of 386 mg/L. No supernatant was decanted during the month. A total of 1,000 pounds of soda ash were added during the month for pH adjustment.
Sludge holding tank #2 was in service. The level at the beginning of the month was 14.39 feet and the level at the end of the month was 13.99 feet. The initial total solids concentration was 0.97% and ended the month as 0.80% total solids. The average pH concentration was 7.38 S.U. and total alkalinity of 490 mg/L. 83,626 gallons of supernatant were decanted during the month. A total of 100 pounds of soda ash were added during the month for pH adjustment.
Significant storm/hydraulic Loading Events – None were experienced past May 2, 2014.
Minor Repairs and Preventive Maintenance
1. Replaced the Inlet air filters for blowers B1A, B1B, B1C and B2.
2. Replaced the suction and pump tubing for the influent samplers and final effluent sampler. The final effluent suction tubing is replaced monthly.
3. Replaced the pump hose on alum feed pump.
4. Cleaned and calibrated SBR LDO probes.

Approval of Minutes

Kevin moved to accept the minutes of May 12, 2014 as corrected. Dana seconded the motion. The motion passed unanimously.

Approval of Invoices

1. Dana moved to approve payment of the following Pennoni invoices:
    a. Pennoni #591749 $ 691.75

F:\Data\Shared Data\Minutes\Municipal Authority\2014\MA 6-9-14 draft.doc      4

    b. Pennoni #591750 $ 5,761.25
    c. Pennoni #591751 $ 1,766.75
    d. Pennoni #591752 $ 1,238.00
Ed seconded the motion. The motion passed unanimously.
2. Dana moved to approve payment of the Gawthrop invoice #119419 for $1,300.00. Ed seconded the motion. The motion passed unanimously.

Liaison Reports

Board of Supervisors – Carmen reported that they are becoming a party to the proceedings for Sunoco.

Financial Reports

1. Jon Altshul's June 5, 2014 Financial Report for May 2014:
The Municipal Authority recorded $6,847 in revenues (primarily from tapping fees) and $15,570 in expenses in May, a difference of -$8,723. The fund balance is now $1,589,282.

Goals

1. Rick provided a draft mission statement with the correction that was requested. After review of the draft, Ed moved to adopt the mission statement. Kevin seconded the motion. The motion passed unanimously. This 2014 goal is complete.
2. The members reviewed the additional information on tank covers. It appears that as of this date the cost will be about $1 million. This 2014 goal is completed.
3. Dana made a motion to authorize the Chairman to sign the Sewer Connection Agreement for 195 Wyllpen Place in Willistown Township. Kevin seconded the motion. The motion passed unanimously.

Any Other Matter

1. Jack complimented Rick on the letter to the residents about the demonstration project on the manhole at the entrance to Fairway Village.

Adjourment

There being no further business, Rick moved to adjourn the meeting. Jack seconded the motion. The motion passed unanimously. The meeting was adjourned at 8:00 pm.

Respectfully submitted,

Ruth Kiefer
Recording Secretary

F:\Data\Shared Data\Minutes\Municipal Authority\2014\MA 6-9-14 draft.doc      5

INVOICE

Pennoni Associates Inc., Consulting Engineers (logo). Newark, DE. 302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # :594993
Invoice Date :06/20/2014
Project :EGMA1306
Project Name :Reserve PS Diversion Construction

For Services Rendered through: 6/15/2014

Continued coordination with contractor to schedule punchlist work, and Sr. Engineering Tech met with contractor on-site to discuss scope of punchlist work. Authority Eng reviewed and signed notarized hard copy of Invoice #3 and forwarded to Township, and emailed CAD files to contractor for use in preparation of as-built plans

Phase : **** -- Professional Services

Total Phase : **** -- Professional Services

Labor :309.00
Expense :0.00
Phase Total :309.00

Amount Due This Invoice: $309.00

Fee :20,000.00
Prior Billings :15,057.50
Current Billings :309.00
Total Billings :15,366.50

Phase : **** – Professional Services

Labor ClassHours/UnitsRateAmount
Authority Engineer2.00113.00226.00
Senior Engineering Technician1.0083.0083.00
Labor Total:3.00309.00
Total Phase : **** – Professional Services — Labor :$309.00
Total Phase : **** – Professional Services — Expense :$0.00
Total Project : EGMA1306 – Reserve PS Diversion Construction — Labor :$309.00
Total Project : EGMA1306 – Reserve PS Diversion Construction — Expense :$0.00

Handwritten note in blue ink: "ok RS 7/11"

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority
EGMA1306 Invoice Summary
Invoice Date 06/20/2014

Project:EGMA1306
Pennoni Job No.:Reserve PS Diversion Construction P
Invoice No:594993
Invoice Period:5/12/2014to6/15/2014
Initial Authorization:$ 20,000.00Date:6/20/2014
Contract Amount:$ 20,000.00
Previously Invoiced:$ 15,057.50
Current Invoice:$ 309.00
Invoiced to Date ($):$ 15,366.50
Invoiced to Date (%):77%
Remaining Budget ($):$ 4,633.50
Remaining Budget (%):23%

Budget by Phase:

Phase Name:Reserve PS Diversion Construction Phase
Phase Budget:$ 20,000.00
Previously Invoiced:$ 15,057.50
Current Invoice:$ 309.00
Invoiced to Date ($):$ 15,366.50
Invoiced to Date (%):77%
Remaining Budget ($):$ 4,633.50
Remaining Budget (%):23%

Comments: Continued coordination with contractor to schedule punchlist work, and Sr. Engineering Tech met with contractor on-site to discuss scope of punchlist work. Authority Eng reviewed and signed notarized hard copy of Invoice #3 and forwarded to Township, and emailed CAD files to contractor for use in preparation of as-built plan.

INVOICE

Pennoni Associates Inc., Consulting Engineers (logo). Newark, DE. 302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # :594994
Invoice Date :06/20/2014
Project :EGMA1307
Project Name :Reservoir Rd PS Act 537 Planning

For Services Rendered through: 6/15/2014

Coordinated with DCNR to eliminate requirement for a botanical survey; reviewed West Goshen Sewer Authority's (WGSA) comment letter, reviewed intermunicipal agreement diversion provisions, evaluated scheduling revisions to Act 537 Plan to comply with agreement provisions, reviewed WGSTP's recent monthly flow data, and assisted with preparation of response letter to WGSA.

PhaseLaborExpensePhase Total
Phase : 02 -- Existing Conditions Survey27.500.0027.50
Phase : 03 -- Act 537 Plan Update21.250.0021.25
Phase : 04 -- Additonal Meetings381.250.00381.25

Amount Due This Invoice: $430.00

Handwritten note in blue ink: "ok RS 7/11"

Continued on next page...

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

Project : EGMA1307 -- Reservoir Rd PS Act 537 Planning

Invoice # : 594994

...Continued from previous page

Phase : 02 -- Existing Conditions Survey

Labor ClassHours/UnitsRateAmount
Authority Engineer0.25110.0027.50
Labor Total:0.2527.50

Total Phase : 02 -- Existing Conditions Survey. Labor : $27.50. Expense : $0.00.

Phase : 03 -- Act 537 Plan Update

Labor ClassHours/UnitsRateAmount
Senior Environmental Scientist0.2585.0021.25
Labor Total:0.2521.25

Total Phase : 03 -- Act 537 Plan Update. Labor : $21.25. Expense : $0.00.

Phase : 04 -- Additonal Meetings

Labor ClassHours/UnitsRateAmount
Authority Engineer3.25110.00357.50
Project Engineer0.2595.0023.75
Labor Total:3.50381.25

Total Phase : 04 -- Additonal Meetings. Labor : $381.25. Expense : $0.00.

Total Project : EGMA1307 – Reservoir Rd PS Act 537 Planning. Labor : $430.00. Expense : $0.00.

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

Pennoni Associates Inc. — Page: 2

East Goshen Municipal Authority
EGMA1307 Invoice Summary
Invoice Date 06/20/2014

Project:EGMA1307
Pennoni Job No.:Reservoir Rd PS Act 537 Planning
Invoice No:594994
Invoice Period:5/12/2014to6/15/2014
Initial Authorization:$ 77,400.00Date:6/20/2014
Contract Amount:$ 84,900.00
Previously Invoiced:$ 69,855.50
Current Invoice:$ 430.00
Invoiced to Date ($):$ 70,285.50
Invoiced to Date (%):83%
Remaining Budget ($):$ 14,614.50
Remaining Budget (%):17%

Budget by Phase:

Phase Name:Reservoir Rd PS Act 537 Planning
Phase Budget:$ 84,900.00
Previously Invoiced:$ 69,855.50
Current Invoice:$ 430.00
Invoiced to Date ($):$ 70,285.50
Invoiced to Date (%):83%
Remaining Budget ($):$ 14,614.50
Remaining Budget (%):17%

Comments: Coordinated with DCNR to eliminate requirement for a botanical survey; reviewed West Goshen Sewer Authority's (WGSA) comment letter, reviewed intermunicipal agreement diversion provisions, evaluated scheduling revisions to Act 537 Plan to comply with agreement provisions, reviewed WGSTP's recent monthly flow data, and assisted with preparation of response letter to WGSA.

INVOICE

Pennoni Associates Inc., Consulting Engineers (logo). Newark, DE. 302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # :594995
Invoice Date :06/20/2014
Project :EGMA1401
Project Name :2014 General Services

For Services Rendered through: 6/15/2014

Prepared June Engineer's Report; attended May and June Municipal Authority meetings; finalized and submitted RCSTP tank cover alternatives memo Update #1; coordinated pre-construction matters with contractor and Township for SprayWall manhole lining demonstration for Fairway Village manhole and traffic control, and Sr. Engineering Tech provided on-site coordination and construction observation during the manhole lining work.

Phase : **** -- Professional Services

Total Phase : **** -- Professional Services

Labor :1,521.25
Expense :0.00
Phase Total :1,521.25

Amount Due This Invoice: $1,521.25

Fee :10,300.00
Prior Billings :5,580.00
Current Billings :1,521.25
Total Billings :7,101.25

Phase : **** -- Professional Services

Labor ClassHours/UnitsRateAmount
Authority Engineer9.00113.001,017.00
Project Engineer2.2595.00213.75
Senior Engineering Technician3.5083.00290.50
Labor Total:14.751,521.25
Total Phase : **** -- Professional Services — Labor :$1,521.25
Total Phase : **** -- Professional Services — Expense :$0.00
Total Project : EGMA1401 – 2014 General Services — Labor :$1,521.25
Total Project : EGMA1401 – 2014 General Services — Expense :$0.00

Handwritten note in blue ink: "ok RS 7/11"

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority
EGMA1401 Invoice Summary
Invoice Date 06/20/2014

Project:EGMA1401
Pennoni Job No.:2014 General Services
Invoice No:594995
Invoice Period:5/12/2014to6/15/2014
Initial Authorization:$ 10,300.00Date:6/20/2014
Contract Amount:$ 10,300.00
Previously Invoiced:$ 5,580.00
Current Invoice:$ 1,521.25
Invoiced to Date ($):$ 7,101.25
Invoiced to Date (%):69%
Remaining Budget ($):$ 3,198.75
Remaining Budget (%):31%

Budget by Phase:

Phase Name:2014 General Services
Phase Budget:$ 10,300.00
Previously Invoiced:$ 5,580.00
Current Invoice:$ 1,521.25
Invoiced to Date ($):$ 7,101.25
Invoiced to Date (%):69%
Remaining Budget ($):$ 3,198.75
Remaining Budget (%):31%

Comments: Prepared June Engineer's Report; attended May and June Municipal Authority meetings; finalized and submitted RCSTP tank cover alternatives memo Update #1; coordinated pre-construction matters with contractor and Township for SprayWall manhole lining demonstration for Fairway Village manhole and traffic control, and Sr. Engineering Tech provided on-site coordination and construction observation during the manhole lining work.

Gawthrop Greenwood, PC Attorneys at Law (logo)

Gawthrop Greenwood, PC
Attorneys at Law
17 East Gay Street, Suite 100
West Chester, PA 19381-0562
(p) 610-696-8225
(f) 610-344-0922
gglaw@gawthrop.com
www.gawthrop.com

East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380

Page:1
Date:06/30/2014
Client No:6604-001M
Invoice No.121393

General Authority Services

Fees

Date Timekeeper Description Hours
06/09/2014 PMM Review and analyze meeting packet; attend meeting. 2.00
06/10/2014 PMM Emails from R Smith regarding agreement with West Goshen Township. 0.30
06/11/2014 PMM Review and analyze WGSA treatment plant agreement regarding diverting flows and reserved capacity; long email to R Smith and EGMA members regarding interpretation of same; reply from R Smith; review and analyze all addendums (7) to plant agreement. 1.50
06/12/2014 PMM Email from M Ellis regarding interpretation of agreement with West Goshen; email from R Smith regarding same; reply from M Ellis; email from D Pizzaro regarding same; email from R Smith regarding revised draft letter to West Goshen; reply. 1.40
06/16/2014 PMM Numerous emails from E McAssey, K Cummings and R Smith regarding West Goshen capacity; reply. 1.20
06/17/2014 PMM Emails from K Cummings and E McAssey regarding interpretation of agreement with West Chester. 0.40
06/18/2014 PMM Emails from R Smith regarding West Goshen plant capacity and expansion agreement. 0.60
For Current Services Rendered 7.40

Amount: 1,480.00

Recapitulation

Timekeeper Hours Hourly Rate Total
Patrick M. McKenna 7.40 $200.00 $1,480.00

East Goshen Municipal Authority

Page:2
Date:06/30/2014
Client No:6604-001M
Invoice No.121393

General Authority Services

Handwritten note in blue ink: "PAID on 7/7/11"

Previous Balance$520.00
Total Current Charges1,480.00
Balance Due$2,000.00

Handwritten note in blue ink: "ok RS 7/11 $2,000.00"; the balance due is circled.

To ensure proper credit, please write client number on your check when returning payment. Thank You.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.

Maillie
Expertise Beyond The Numbers
PO Box 680, Oaks, PA 19456-0680
Phone: 610-935-1420
E-mail: firm@maillie.com
Web: www.maillie.com

[Stamp: RECEIVED]

Client Number: 2500
Invoice: 1000036708

East Goshen Municipal Authority
Attn: Mr. Rick Smith
1580 Paoli Pike
West Chester, PA 19380-6107

Date: 06/30/2014
Due Date: 07/30/2014

Description Amount
For examination of the financial statements of the Authority for the year ended December 31, 2013, and assistance with preparation of Management Discussion and Analysis report, including additional work related to new bond issue and various construction projects $10,800.00
Billed Time & Expenses $10,800.00
Invoice Total $10,800.00
06/30/2014 05/31/2014 04/30/2014 03/31/2014 02/28/2014+ Total
10,800.00 0.00 0.00 0.00 0.00 $10,800.00

Please return this portion with payment.

Invoice: 1000036708
ID: 2500
East Goshen Municipal Authority
610-692-7171

Date: 06/30/2014
Due Date: 07/30/2014
Amount Due: $10,800.00
Amount Enclosed: $ _________

Finance charges of 1 1/2% per month will be added to the unpaid balance of accounts over 30 days from invoice date. Annual percentage rate of 18%.

ok RS 7-7-14

Memo

To: Municipal Authority
From: Jon Altshul
Re: MA June Financial Reports
Date: July 8, 2014

The Municipal Authority recorded $130 in revenues (interest) and $17,429 in expenses in June, a difference of -$17,299. The fund balance is now $1,571,983. June expenses included the quarterly administrative charge back ($8,043), engineering services ($3,005) and engineering services on the Reservoir Road Pumping Station ($5,761).

A complete list of all year-to-date expenses and revenues is provided.

EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
June 2014

Account Title Acct # Annual Budget Month To Date Actual Year To Date Actual
MUNICIPAL AUTHORITY BEGINNING FUND BALANCE 1,589,281.93
RCSTP BUDGET
REVENUE
INTEREST EARNED - RCSTP EXPANSION 07341 1020 2,000.00 129.00 792.00
GRANT REVENUE 07392 0800 0.00 0.00 0.00
TOTAL REVENUE 2,000.00 129.00 792.00
EXPENSES
R.C.-CAP. PROJ.-ENGINEER 07424 7451 0.00 0.00 0.00
R.C. CAP EXPANSION GEN'L CONTRACTOR 07424 7452 0.00 0.00 0.00
R.C. CAP EXPANSION - ELECTRICAL 07424 7453 0.00 0.00 0.00
R.C. CAP EXP CONTINGENCY CAPITAL 07424 7454 0.00 0.00 0.00
R.C. CAP EXP CONTINGENCY ONGOING 07424 7455 0.00 0.00 0.00
R.C. CAP EXP ADDITIONAL CONTINGENCY 07424 7456 0.00 0.00 0.00
TRANSFER TO SEWER SINKING FUND 07492 0550 0.00 0.00 0.00
TRANSFER TO AUTHORITY CAP FUND 07492 0990 0.00 0.00 0.00
TOTAL EXPENSES 0.00 0.00 0.00
RCSTP NET RESULT 2,000.00 129.00 792.00

U:\bmccool\2014\Municipal Authority\2014 - 06 - Municipal Authority Report.xlsx Page 1 of 3 07/03/14

EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
June 2014

Account Title Acct # Annual Budget Month To Date Actual Year To Date Actual
OPERATING BUDGET
REVENUE
INTEREST EARNINGS 07341 1000 27.00 0.75 6.48
C.C. TAPPING FEES 07364 1100 124,000.00 0.00 22,000.00
R.C.TAPPING FEES 07364 1110 21,444.00 0.00 10,288.80
CONNECTION FEES - SEWER 07364 1130 0.00 0.00 1,127.52
MISCELLANEOUS REVENUE 07380 1000 0.00 0.00 564.48
TRANSFER FROM SEWER OPERATING 07392 0500 0.00 0.00 21,000.00
TOTAL REVENUE 145,471.00 0.75 54,987.28
EXPENSES
ADMINISTRATIVE WAGES 07424 1400 32,768.00 8,043.02 16,086.04
MISCELLANEOUS EXPENSE 07424 3000 4,000.00 0.00 1,450.00
MUNIC.AUTH.-AUDITING 07424 3110 10,800.00 0.00 0.00
ENGINEERING SERVICES 07424 3130 35,525.00 3,004.75 25,290.25
LEGAL SERVICES 07424 3140 7,000.00 0.00 3,760.00
M.C.-DVRFA-DEBT SERVICE 07471 1000 22,120.00 0.00 0.00
M.C.-DVRFA-INTEREST PAYMN 07472 1000 5,115.00 0.00 0.00
M.C.-DVRFA-INTEREST PAYMN 07472 1010 0.00 0.00 0.00
TOTAL EXPENSES 117,328.00 11,047.77 46,586.29
OPERATING NET RESULT 28,143.00 (11,047.02) 8,400.99

U:\bmccool\2014\Municipal Authority\2014 - 06 - Municipal Authority Report.xlsx Page 2 of 3 07/03/14

EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
June 2014

Account Title Acct # Annual Budget Month To Date Actual Year To Date Actual
CAPITAL BUDGET
REVENUE
LOAN PROCEEDS-SEWER PROJECT 07393 1001 0.00 0.00 0.00
TRANSFER FROM SEWER CAP RESERVE 07392 0900 0.00 0.00 0.00
TOTAL REVENUE 0.00 0.00 0.00
EXPENSES
MARYDELL PUMP STATION - ENGINEER 07425 1000 0.00 0.00 0.00
MARYDELL PUMP STATION -CONSTRUCTION 07425 2000 0.00 0.00 0.00
MANHOLE COVER REPLACEMENTS 07424.7405 0.00 0.00 0.00
C.C. CAPITAL - COLLECTION 07424.7420 0.00 0.00 0.00
LOCHWOOD ABANDONMENT ENGINEER 07424 7475 0.00 0.00 0.00
LOCHWOOD ABANDONMENT CONSTRUCTION 07424 7476 0.00 0.00 0.00
LOCHWOOD ELIMINATION PHASE 2 07424 7477 0.00 0.00 0.00
HERSHEY MILL STATION - ENGINEER 07426 1000 0.00 0.00 0.00
HERSHEY MILL STATION - CONSTRUCTION 07426 2000 0.00 0.00 0.00
RESERVE PUMP STATION - ENGINEER 07427 1000 0.00 619.75 817.00
RESERVE PUMP STATION - CONSTRUCTION 07427 2000 0.00 0.00 0.00
RESERVOIR PUMP STATION - ENGINEER 07428 1000 75,000.00 5,761.25 34,663.50
RESERVOIR PUMP STATION CONSTRUCTION 07428 2000 0.00 0.00 0.00
TOTAL EXPENSES 75,000.00 6,381.00 35,480.50
CAPITAL NET RESULT (75,000.00) (6,381.00) (35,480.50)
MUNICIPAL AUTHORITY ENDING FUND BALANCE 1,571,982.91

U:\bmccool\2014\Municipal Authority\2014 - 06 - Municipal Authority Report.xlsx Page 3 of 3 07/03/14

East Goshen Township General Ledger
Report Date 07/03/14
GL Transaction Details
PAGE 1
MGRP18 run by BRIAN 3 : 12 PM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
07341-1000 INTEREST EARNINGS 0.00
1401 JE 41027 0.58 02/04/14 INTEREST INTEREST EARNED JANUARY 2014
07 FUND
0.00 0.58 -0.58
1402 41391 1.33 03/04/14 INTEREST INTEREST EARNED FEBRUARY 2014
07100.1000
0.00 1.33 -1.91
1403 41840 1.71 04/01/14 INTEREST INTEREST EARNED MARCH 2014
07 FUND
0.00 1.71 -3.62
1404 42321 1.21 05/02/14 INTEREST INTEREST EARNED APRIL 2014
07100.1000
0.00 1.21 -4.83
1405 42739 0.90 06/02/14 INTEREST INTEREST EARNED MAY 2014
07100.1000
0.00 0.90 -5.73
1406 43211 0.75 07/01/14 INTEREST INTEREST EARNED JUNE 2014
07100.1000
0.00 0.75 -6.48
0.00 6.48 -6.48
07341-1020 INTEREST EARNED - RCSTP EXPANSION 0.00
1401 41028 137.33 02/04/14 INTEREST INTEREST EARNED JANUARY 2014
07 CONSTRUCTION FUND
0.00 137.33 -137.33
1402 41392 123.56 03/04/14 INTEREST INTEREST EARNED FEBRUARY 2014
07 CONSTRUCTION FUND
0.00 123.56 -260.89
1403 41841 136.07 04/01/14 INTEREST INTEREST EARNED MARCH 2014
07 CONSTRUCTION FUND
0.00 136.07 -396.96
1404 42322 131.45 05/02/14 INTEREST INTEREST EARNED APRIL 2014
CONSTRUCT.FUNDS
0.00 131.45 -528.41
1405 42740 134.59 06/02/14 INTEREST INTEREST EARNED MAY 2014
07 FUND - CONSTRUCTION
0.00 134.59 -663.00
1406 43212 129.00 07/01/14 INTEREST INTEREST EARNED JUNE 2014
07 CONSTRUCTION FUNDS

East Goshen Township General Ledger
Report Date 07/03/14
GL Transaction Details
PAGE 2
MGRP18 run by BRIAN 3 : 12 PM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
0.00 129.00 -792.00
0.00 792.00 -792.00
07364-1100 C.C. TAPPING FEES 0.00
1401 CR 40976 12,600.00 01/31/14 3034 8069 1 GOSHEN MEADOWS INVESTORS L.P.
0.00 12,600.00 -12,600.00
1402 41258 5,400.00 02/24/14 3553 8069 1 GOSHEN MEADOWS INVESTORS L.P.
RE 41263 2,000.00 02/24/14 41263 1 TAP IN FEE - 211 ELLIS LANE
0.00 7,400.00 -20,000.00
1405 42661 2,000.00 05/29/14 42661 1 TAP IN FEE FOR 195 WYLLPEN PL
0.00 2,000.00 -22,000.00
0.00 22,000.00 -22,000.00
07364-1110 R.C.TAPPING FEES 0.00
1402 41280 2,000.00 02/25/14 41280 1 TAP IN FEE-903 SORELL HILL LT2
0.00 2,000.00 -2,000.00
1403 41553 2,000.00 03/13/14 41553 1 TAP IN FEE FOR 909 SORRELL LT4
41608 2,000.00 03/17/14 41608 1 TAP IN FEE-905 SORRELL LOT 3
0.00 4,000.00 -6,000.00
1405 CR 42355 4,288.80 05/06/14 130 6499 1 BOWER, JUDITH
0.00 4,288.80 -10,288.80
0.00 10,288.80 -10,288.80
07364-1130 CONNECTION FEES - SEWER 0.00
1402 41044 423.00 02/04/14 350 8035 1 JACOBS, ROBERT & CHERYL
41124 423.00 02/14/14 774 8033 1 GEORGE SMITH & CHRISTINA CONLE
JE 41045 141.12 02/04/14 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
41125 141.12 02/14/14 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
282.24 846.00 -563.76
1403 CR 41402 423.00 03/04/14 2307 8034 1 STOFFLET, MICHAEL
JE 41407 141.12 03/04/14 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
141.12 423.00 -845.64
1405 CR 42378 423.00 05/07/14 1021 8036 1 PAPPANO, JOSEPH & PATRICIA
JE 42380 141.12 05/07/14 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
141.12 423.00 -1,127.52
564.48 1,692.00 -1,127.52

East Goshen Township General Ledger
Report Date 07/03/14
GL Transaction Details
PAGE 3
MGRP18 run by BRIAN 3 : 12 PM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
07380-1000 MISCELLANEOUS REVENUE 0.00
1402 41045 141.12 02/04/14 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
41125 141.12 02/14/14 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
0.00 282.24 -282.24
1403 41407 141.12 03/04/14 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
0.00 141.12 -423.36
1405 42380 141.12 05/07/14 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
0.00 141.12 -564.48
0.00 564.48 -564.48
07392-0500 TRANSFER FROM SEWER OPERATING 0.00
1401 40674 1,000.00 01/08/14 DEPOSIT DEPOSIT $ INTO MA GENERAL
FROM 05 FUND
40747 20,000.00 01/14/14 XFER XFER $ FROM SEWER TO MA TO
COVER EXPENSES
0.00 21,000.00 -21,000.00
0.00 21,000.00 -21,000.00
07424-1400 ADMINISTRATIVE WAGES 0.00
1403 CD 41815 8,043.02 03/31/14 2237 425 EAST GOSHEN TOWNSHIP - GENERAL
1ST QTR.2014 MUN.AUTH. REIMBURSM
8,043.02 0.00 8,043.02
1406 43192 8,043.02 06/30/14 2243 425 EAST GOSHEN TOWNSHIP - GENERAL
2ND QTR.2014 MUN. AUTH.REIMBURSM
8,043.02 0.00 16,086.04
16,086.04 0.00 16,086.04
07424-3000 MISCELLANEOUS EXPENSE 0.00
1401 40597 500.00 01/06/14 2228 2737 DEP - COMMONWEALTH OF PA
NPDES PERMITS - CHAPTER 92A 2014
950.00 01/06/14 2229 2132 PENNSYLVANIA MUNICIPAL AUTHORITIES ASSOC
2014 ACTIVE MEMBERSHIP DUES
*** 1,450.00 0.00 ***
1,450.00 0.00 1,450.00
1,450.00 0.00 1,450.00
07424-3130 ENGINEERING SERVICES 0.00
40653 -663.75 01/06/14 2224 1052 PENNONI ASSOCIATES INC.
VOID CK. DUE TO PRINTER PROBLEM

East Goshen Township General Ledger
Report Date 07/03/14
GL Transaction Details
PAGE 4
MGRP18 run by BRIAN 3 : 12 PM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
07424-3130 1401 CD 40743 663.75 01/14/14 2230 1052 PENNONI ASSOCIATES INC.
SERVICES THRU 12/8/13 GENERAL S
JE 40746 1,845.00 01/14/14 REFUND PENNONI REFUND DUE TO
DUPLICATE PAYMENT
0.00 1,845.00 -1,845.00
1402 CD 41103 2,236.50 02/11/14 2233 1052 PENNONI ASSOCIATES INC.
SERVICES THROUGH 1/12/14 GEN.SER
2,236.50 0.00 391.50
1403 41540 6,887.25 03/12/14 2236 1052 PENNONI ASSOCIATES INC.
SERVICES THRU 2/9/14 2013 CHAP.
6,887.25 0.00 7,278.75
1404 42153 8,808.25 04/23/14 2239 1052 PENNONI ASSOCIATES INC.
SERVICES THRU 3/16/14 CHAP.94 RE
8,808.25 0.00 16,087.00
1405 42462 6,198.50 05/14/14 2241 1052 PENNONI ASSOCIATES INC.
SERVICES THRU 4/13/14 2013 CHAP.
6,198.50 0.00 22,285.50
1406 42952 3,004.75 06/12/14 2242 1052 PENNONI ASSOCIATES INC.
SERV.THRU 5/11/14 2014 SEMI-ANN
3,004.75 0.00 25,290.25
27,135.25 1,845.00 25,290.25
07424-3140 LEGAL SERVICES 0.00
1402 41310 800.00 02/27/14 2234 528 GAWTHROP GREENWOOD & HALSTED
LEGAL SERVICES - NOV.2013 GEN.AU
800.00 0.00 800.00
1403 41540 700.00 03/12/14 2235 528 GAWTHROP GREENWOOD & HALSTED
LEGAL SERVICE - FEB.2014 GEN.AUT
700.00 0.00 1,500.00
1404 42074 960.00 04/16/14 2238 528 GAWTHROP GREENWOOD & HALSTED
LEGAL SERVICE - MARCH 2014 GEN.A
960.00 0.00 2,460.00
1405 42462 1,300.00 05/14/14 2240 528 GAWTHROP GREENWOOD & HALSTED
LEGAL SERVICE APRIL 2014 GEN.AUT
1,300.00 0.00 3,760.00
3,760.00 0.00 3,760.00
07424-7460 LOCHWOOD - CAPITAL -STP 0.00

East Goshen Township General Ledger
Report Date 07/03/14
GL Transaction Details
PAGE 5
MGRP18 run by BRIAN 3 : 12 PM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
1401 CD 40739 1,290.00 01/14/14 10012 2695 BRICKHOUSE ENVIRONMENTAL
LOCHWOOD CHASE PROJECT - DEC.201
40744 -1,290.00 01/14/14 10012 2695 BRICKHOUSE ENVIRONMENTAL
VOID CK. - INCORRECT CASH ACCT.U
40745 1,290.00 01/14/14 2231 2695 BRICKHOUSE ENVIRONMENTAL
LOCHWOOD CHASE PROJECT - DEC. 20
JE 40820 1,290.00 01/22/14 DEPOSIT DEPOSIT TO REIMBURSE 07 MA
FOR 05 EXPENSE
1,290.00 1,290.00 0.00
1,290.00 1,290.00 0.00
07427-1000 RESERVE PUMP STATION - ENGINEER 0.00
1405 CD 42462 197.25 05/14/14 2241 1052 PENNONI ASSOCIATES INC.
SERV.THRU 4/123/14 RESERVE PS
197.25 0.00 197.25
1406 42888 7,316.82 06/11/14 10019 3133 SMITH INC., RONALD
APPLIC.# 3 RESERVE PS DIVERSION
42952 619.75 06/12/14 2242 1052 PENNONI ASSOCIATES INC.
SERVICE THRU 5/11/14 RESERVE PS
43217 -7,316.82 06/30/14 10019 3133 SMITH INC., RONALD
VOID CK.10019 PAYMENT AMT.TO BE
REDUCED
619.75 0.00 817.00
817.00 0.00 817.00
07428-1000 RESERVOIR PUMP STATION - ENGINEER 0.00
1402 41107 10,687.50 02/11/14 10013 1052 PENNONI ASSOCIATES INC.
SERV.THROUGH 1/12/14 RESERVE PS
10,687.50 0.00 10,687.50
1403 41541 4,431.25 03/12/14 10014 1052 PENNONI ASSOCIATES INC.
SERV.THRU 2/9/14 RESERV.RD. PS
4,431.25 0.00 15,118.75
1404 42154 5,909.00 04/23/14 10015 1052 PENNONI ASSOCIATES INC.
SERVICES THRU 3/16/14 RESERV.RD
5,909.00 0.00 21,027.75
1405 42463 4,724.50 05/14/14 10016 1052 PENNONI ASSOCIATES INC.
SERV. THRU 4/13/14 RESERVOIR RD.
42514 3,150.00 05/16/14 10017 3312 CONESTOGA & ASSOCIATES
PROF.SERVICE THRU 3/30/14 RESERV
RD. PS - BOG TURTLE HABITAT
7,874.50 0.00 28,902.25

East Goshen Township General Ledger
Report Date 07/03/14
GL Transaction Details
PAGE 6
MGRP18 run by BRIAN 3 : 12 PM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
07428-1000 1406 CD 42888 5,761.25 06/11/14 10018 1052 PENNONI ASSOCIATES INC.
SERV.THRU 5/11/14 RESERVOIR RD.
5,761.25 0.00 34,663.50
34,663.50 0.00 34,663.50
Beg Bal 0.00 85,766.27 59,478.76 26287.51

Maillie
Expertise Beyond The Numbers
P.O. Box 3068, West Chester, PA 19381-3068 | 610.696.4353 | Fax: 610.430.8811 | www.maillie.com

Partners
D. Scott Detar
James M. Powers
Glenn B. Bachman
Raymond T. Mock
Robert L. Caruso
Edward J. Furman
Robert L. Boland
Donald J. Pierce
Richard A. Flanagan, IV
Craig S. Springer
Robert C. Hershey, Jr.
Gregory J. Shank
Laurie E. Harvey

Principals
Edward Fronczkowski
S. Mark Fuga
James E. Yiaski
William Breslawski Jr.
Shawn M. Cahill
Kathleen A. Wileczek

June 23, 2014

To the Members of the Board
East Goshen Municipal Authority
West Chester, Pennsylvania

We have audited the financial statements of the East Goshen Municipal Authority as of and for the year ended December 31, 2013, and have issued our report thereon dated June 10, 2014. Professional standards require that we advise you of the following matters relating to our audit.

OUR RESPONSIBILITY IN RELATION TO THE FINANCIAL STATEMENT AUDIT

As communicated in our engagement letter dated October 16, 2013, our responsibility, as described by professional standards, is to form and express an opinion(s) about whether the financial statements that have been prepared by management with your oversight are presented fairly, in all material respects, in conformity with accounting principles generally accepted in the United States of America. Our audit of the financial statements does not relieve you or management of your respective responsibilities.

Our responsibility, as prescribed by professional standards, is to plan and perform our audit to obtain reasonable, rather than absolute, assurance about whether the financial statements are free of material misstatement. An audit of financial statements includes consideration of internal control over financial reporting as a basis for designing audit procedures that are appropriate in the circumstances, but not for the purpose of expressing an opinion on the effectiveness of the entity's internal control over financial reporting. Accordingly, as part of our audit, we considered the internal control of the East Goshen Municipal Authority solely for the purpose of determining our audit procedures and not to provide any assurance concerning such internal control.

We are also responsible for communicating significant matters related to the audit that are, in our professional judgment, relevant to your responsibilities in overseeing the financial reporting process. However, we are not required to design procedures for the purpose of identifying other matters to communicate to you.

PLANNED SCOPE AND TIMING OF THE AUDIT

We conducted our audit consistent with the planned scope and timing we previously communicated to you.

Certified Public Accountants and Business Consultants

Maillie
Expertise Beyond The Numbers

To the Members of the Board
East Goshen Municipal Authority
- 2 -
June 23, 2014

COMPLIANCE WITH ALL ETHICS REQUIREMENTS REGARDING INDEPENDENCE

The engagement team, others in our firm, as appropriate, our firm and our network firms have complied with all relevant ethical requirements regarding independence.

QUALITATIVE ASPECTS OF THE ENTITY'S SIGNIFICANT ACCOUNTING PRACTICES

Significant Accounting Policies

Management has the responsibility to select and use appropriate accounting policies. A summary of the significant accounting policies adopted by the East Goshen Municipal Authority is included in Note A to the financial statements. There have been no initial selection of accounting policies and no changes in significant accounting policies or their application during the year. No matters have come to our attention that would require us, under professional standards, to inform you about (1) the methods used to account for significant unusual transactions and (2) the effect of significant accounting policies in controversial or emerging areas for which there is a lack of authoritative guidance or consensus.

Significant Accounting Estimates

Accounting estimates are an integral part of the financial statements prepared by management and are based on management's current judgments. Those judgments are normally based on knowledge and experience about past and current events and assumptions about future events. Certain accounting estimates are particularly sensitive because of their significance to the financial statements and because of the possibility that future events affecting them may differ markedly from management's current judgments.

Financial Statement Disclosures

The financial statement disclosures are neutral, consistent and clear.

SIGNIFICANT DIFFICULTIES ENCOUNTERED DURING THE AUDIT

We encountered no significant difficulties in dealing with management relating to the performance of the audit.

Certified Public Accountants and Business Consultants

Maillie
Expertise Beyond The Numbers

To the Members of the Board
East Goshen Municipal Authority
- 3 -
June 23, 2014

UNCORRECTED AND CORRECTED MISSTATEMENTS

For purposes of this communication, professional standards require us to accumulate all known and likely misstatements identified during the audit, other than those that we believe are trivial, and communicate them to the appropriate level of management. Further, professional standards require us to also communicate the effect of uncorrected misstatements related to prior periods on the relevant classes of transactions, account balances or disclosures and the financial statements as a whole. Management has corrected all identified misstatements.

In addition, professional standards require us to communicate to you all material, corrected misstatements that were brought to the attention of management as a result of our audit procedures. The attached schedule of material misstatements that we identified as a result of our audit procedures was brought to the attention of, and corrected by, management.

DISAGREEMENTS WITH MANAGEMENT

For purposes of this letter, professional standards define a disagreement with management as a matter, whether or not resolved to our satisfaction, concerning a financial accounting, reporting, or auditing matter, which could be significant to the East Goshen Municipal Authority's financial statements or the auditors' report. No such disagreements arose during the course of the audit.

REPRESENTATIONS REQUESTED FROM MANAGEMENT

We have requested certain written representations from management, which are included in the management representation letter dated June 10, 2014.

MANAGEMENT'S CONSULTATIONS WITH OTHER ACCOUNTANTS

In some cases, management may decide to consult with other accountants about auditing and accounting matters. Management informed us that, and to our knowledge, there were no consultations with other accountants regarding auditing and accounting matters.

OTHER SIGNIFICANT MATTERS, FINDINGS OR ISSUES

In the normal course of our professional association with the East Goshen Municipal Authority, we generally discuss a variety of matters, including the application of accounting principles and auditing standards, operating and regulatory conditions affecting the entity and operational plans and strategies that may affect the risks of material misstatement. None of the matters discussed resulted in a condition to our retention as the East Goshen Municipal Authority's auditors.

Certified Public Accountants and Business Consultants

Maillie
Expertise Beyond The Numbers

To the Members of the Board
East Goshen Municipal Authority
- 4 -
June 23, 2014

This report is intended solely for the information and use of the Members of the Board and management of the East Goshen Municipal Authority and is not intended to be and should not be used by anyone other than these specified parties.

Very truly yours,

Maillie LLP

MAILLIE LLP
Certified Public Accountants and
Business Consultants

Certified Public Accountants and Business Consultants

Maillie
Expertise Beyond The Numbers

6/23/2014
2:37 PM

Client: 2500 - East Goshen Municipal Authority
Engagement: 2013 - East Goshen Municipal Authority
Period Ending: 12/31/2013
Trial Balance: TB-Municipal Authority
Workpaper: 3510MA05 - Adjusting Journal Entries Report

Account Description W/P Ref Debit Credit
Adjusting Journal Entries JE # 101 PY
To record prior year cumulative accrual balances and agree net assets.
07-100-1900 Lease payment receivable 8,986,000.00
07-279-1000 FUND BALANCE 22,609.00
07-200-2000 ACCOUNTS PAYABLE 16,654.00
07-200-2500 Note payable - DVRFA 518,000.00
07-200-2501 Note Payable - 2008 8,468,000.00
07-200-3000 Accrued interest payable 5,955.00
Total 9,008,609.00 9,008,609.00
Adjusting Journal Entries JE # 102 PY
To reverse prior year accounts payable
07-200-2000 ACCOUNTS PAYABLE 16,654.00
07-424-3130 ENGINEERING SERVICES 3,265.00
07-424-3140 LEGAL SERVICES 3,289.00
07-424-7475 LOCHWOOD ABANDONMENT ENGINEER 512.00
07-425-1000 MARYDELL PUMP STATION - ENGINEER 5,494.00
07-426-1000 HERSHEY MILL STATION - ENGINEER 2,047.00
07-427-1000 RESERVE PUMP STATION - ENGINEER 2,047.00
Total 16,654.00 16,654.00
Adjusting Journal Entries JE # 103 PY
To reverse prior year accrued interest payable
07-200-3000 Accrued interest payable 5,955.00
07-100-1910 RESERVE FOR FUTURE CAPITAL EXPENDITURES 5,955.00
Total 5,955.00 5,955.00
Adjusting Journal Entries JE # 104 5100MA01
To record current year accounts payable
07-424-3130 ENGINEERING SERVICES 2,133.00
07-424-7460 LOCHWOOD - CAPITAL -STP 1,290.00
07-428-1000 RESERVOIR PUMP STATION - ENGINEER 7,023.00
07-200-2000 ACCOUNTS PAYABLE 10,446.00
Total 10,446.00 10,446.00
Adjusting Journal Entries JE # 105 5300MA01
To adjust lease payment receivable for principal payment received from Township
07-492-0500 TRANSFER TO SEW.OPERATING 358,000.00
07-100-1900 Lease payment receivable 358,000.00
Total 358,000.00 358,000.00
Adjusting Journal Entries JE # 106 5300MA01
To gross up Lease Rental Collections
07-200-2500 Note payable - DVRFA 74,000.00
07-200-2501 Note Payable - 2008 284,000.00
07-472-1000 M.C.-DVRFA-INTEREST PAYMN 365,972.00
07-364-4200 Lease rental collections 723,972.00
Total 723,972.00 723,972.00
Adjusting Journal Entries JE # 107 5300MA05
To record current year accrued interest
07-100-1910 RESERVE FOR FUTURE CAPITAL EXPENDITURES 6,986.00
07-200-3000 Accrued interest payable 6,986.00
Total 6,986.00 6,986.00

Certified Public Accountants and Business Consultants
1 of 2

Maillie
Expertise Beyond The Numbers

6/23/2014
2:37 PM

Client: 2500 - East Goshen Municipal Authority
Engagement: 2013 - East Goshen Municipal Authority
Period Ending: 12/31/2013
Trial Balance: TB-Municipal Authority
Workpaper: 3510MA05 - Adjusting Journal Entries Report

Account Description W/P Ref Debit Credit
Adjusting Journal Entries JE # 108 4200MA05
To record net investment in lease related to 2013 note issuance
07-100-1900 Lease payment receivable 2,500,000.00
07-100-1910 RESERVE FOR FUTURE CAPITAL EXPENDITURES 2,500,000.00
Total 2,500,000.00 2,500,000.00
Adjusting Journal Entries JE # 109 4200MA05
To adjust for capital costs capitalized on Sewer Operating Fund (Township)
07-100-1910 RESERVE FOR FUTURE CAPITAL EXPENDITURES 601,758.00
07-426-1000 HERSHEY MILL STATION - ENGINEER 23,303.00
07-426-2000 HERSHEY MILL STATION - CONSTRUCTION 167,013.00
07-428-1000 RESERVOIR PUMP STATION - ENGINEER 7,023.00
07-428-1000 RESERVOIR PUMP STATION - ENGINEER 38,447.00
07-472-1000 M.C.-DVRFA-INTEREST PAYMN 365,972.00
Total 601,758.00 601,758.00
Adjusting Journal Entries JE # 110 9554MA
To record note payable and loan fees for 2013 issuance
07-393-1001 LOAN PROCEEDS-SEWER PROJECT 2,477,000.00
07-424-5850 Loan fees 23,000.00
07-200-2502 NOTE PAYABLE - 2013 2,500,000.00
Total 2,500,000.00 2,500,000.00

Certified Public Accountants and Business Consultants
2 of 2

8. GOALS

  1. Review current mission statement and provide the Board of Supervisors with changes, if needed – June 1, 2014 May 8 – The MA does not have a current mission statement. A first draft is included in the packet. June 9 – Changed “lease” to “leasee” Approved by MA on June 9 - Completed
  2. Submit an article for each newsletter – Due date for newsletter Need by 1/31/14 – Dana Completed Need by 4/30/14 – Jack Completed Need by 7/1/14 - Kevin Need by 10/31/14
  3. Obtain PA DEP approval for the Act 537 Plan revision for the Reservoir Road Pump Station – December 31, 2014 May 8 - Revisions submitted to EGMA, EGPC, WGSTP, CCHD, and CCPC July 14 – BOS scheduled to adopt resolution at their meeting on August 19
  4. Develop a recommendation on covers for the SBRs – August 1, 2014 May 8 – Draft memo distributed. June 9 – Final memo in packet - Completed
  5. Attend West Goshen Meetings quarterly – more often if needed. 1 st Quarter (March) – Jack- Completed 2 nd Quarter (June) – Ed- Completed 3 rd Quarter (September) 4 th Quarter (December)
  6. Respond to capacity requests in 45 days or less. 211 Ellis Lane – 1 EDU existing house, 195 Wyllpen Place – 1 EDU existing house
  7. Continue to implement I & I Plan April 14 – Status Report received
  8. Operate RCSTP in compliance with NPDES Permit January, February, March, May,

F:\Data\Shared Data\Agendas\Municipal Authority\2014\7-14-14 -.doc

INTEGRATED LAND MANAGEMENT, INC.

July 9, 2014

Mr. Louis F. Smith
Township Manager
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380-6199

RE: Proposed Tie-in to East Goshen Sewers,
Troutbeck Farm, Willistown Township

Dear Mr. Smith,

I am writing on behalf of the Chance Family Trust and Estate, of which I am a member. Pursuant to our conversation last year, I am writing to make a formal request to East Goshen Township for the provision of Sewer Services to the above captioned property. As shown on the enclosed Location Plan, our property comprises approximately 68 acres.

It is located 1,100 feet east of Hickory Lane, which is where the Willow Pond Subdivision is located. Presently treated by East Goshen Township, 13 lots of this subdivision are actually located in Willistown. Being in the Ridley Creek watershed, I understand that these lots are treated by the Ridley Creek WWTP.

Given the current inter-township arrangements for the Willow Pond lots, there is ample precedent for bringing in additional Willistown properties in the same watershed. We would request to bring on line an additional 44 D.U., of which 4 presently exist. The balance represents platted vacant lots or proposed lots. At 275 gpd per D.U., this represents 12,100 gpd. When we spoke, East Goshen had approximately 50,000 gpd in surplus allocation, so I trust that this request will be favorably received.

As you mentioned, there is the meeting of the Board on Monday when this request will be considered, and I will be able to attend to answer any questions. In the meantime, please let me know if you need any more information at this time. I thank you in advance for your consideration.

Regards,

William Lucas

cc: Gerald Lucas
Lillie Chance

3 LUCAS LANE, MALVERN, PA 19355
o: 610-644-0606 f: 610-644-6583 c: 484-995-6840

Aerial photograph with parcel lines and parcel labels showing a red-outlined subject property of mostly open field and woods, with a blue line along a road ending at a red arrow.

Annotations and Labels:
Subject Property 43 D.U. (red boxed label)
Tie into ex. MH (red boxed label with arrow, at the end of the blue sewer line)
Streets: Salisbury LA, Stonehenge LA, Frost Pond LA, Druid LA, Skyline DR, Quarterwood RD, Tiburon LA, Willow Pond RD, Tramore Ct
Parcel labels include: 54-2-41.4A (23.43 AC.), 54-2-41.4 (10.4 AC.), 54-2-1 (28.87 AC.), 54-2-41.4E (1.13 AC.), 54-2-41.4D (1.07 AC.), 54-2-41.4C (1.07 AC.), 54-2-41.4B (1.07 AC.), 54-2-41.6B (1.1 AC.), 54-2-41.6C (1.1 AC.), 54-2-41.5A (1.1 AC.), 54-2-1.2 (3 AC.), 54-2-41.1 (2.1 AC.), 54-2-41.3E (1.71 AC.), 54-2-41.3D (1.07 AC.), 54-2-41.3C (1 AC.), 54-2-41.3B (1 AC.), 54-2-41.3A (1.52 AC.), 54-2-70.1 (2.1 AC.), 54-2-70.2 (2.9 AC.), 54-2-70.3 (2.3 AC.), 54-2-70.10 (2 AC.), 54-2-70.11 (2 AC.), 54-2-71 (2.1 AC.), 54-2F-23 (3.0 AC.), and many smaller parcels too small to read reliably.

[Seal: SEAL OF CHESTER COUNTY PENNSYLVANIA]      [Seal: CHESTER-WILLIAM PENN PROPRIETOR AND GOVENOR]

THE COUNTY OF CHESTER

COMMISSIONERS
Ryan Costello
Kathi Cozzone
Terence Farrell

JEANNE CASNER, MPH, PMP
County Health Director

CHESTER COUNTY HEALTH DEPARTMENT
Water and Sewage Division
Chester County Government Services Center
601 Westtown Road, Suite 288
West Chester, PA 19380-0990
610-344-6526 FAX: 610-344-5934
www.chesco.org/health

[Stamp: RECEIVED JUL 01 2014]

June 23, 2014

East Goshen Township Municipal Authority
East Goshen Township Building
1580 Paoli Pike
West Chester, PA 19380

RE: East Goshen Township
Minor Act 537 Plan Update Revision
Reservoir Road Pump Station

Dear Mr. Yahraes,

The Chester County Health Department (CCHD) is in receipt of the above noted Act 537 Plan Revision document. This Minor Revision was prepared by Pennoni Associates and dated May, 2014. It was received by CCHD on May 12, 2014 and has been reviewed in accordance with Title 25, Environmental Protection, Chapter 71, Administration of Sewage Facilities Planning Program, Chapter 71 § 71.31.(b.). We offer the following comments:

  1. The Reservoir Road Pump Station, as described in this plan update, is the final phase of an ongoing plan to divert sewage from the Chester Creek Interceptor to the Ridley Creek Sewage Treatment Plant. This diversion will reduce wastewater flow from East Goshen to the West Goshen Sewage Treatment Plant.
  2. This pump station was included in the design of recent upgrades to the Ridley Creek Sewage Treatment Plant and will increase operating efficiency and improve plant function, among other advantages.
  3. Additional sewage treatment capacity to satisfy future needs in areas continuing to be served by the Chester Creek Interceptor will become available.
  4. PA DEP had no objections to this diversion scheme and approved the Plan of Study on August 9, 2013.

CCHD has no objection to East Goshen Township Municipal Authority implementing the provisions of this plan.

“Protecting You and Your Environment”

East Goshen Municipal Authority
Minor Act 537 Plan Update Revision
Reservoir Road Pump Station
June 23, 2014

Thank you for the opportunity to review this Act 537 Plan Update Revision. Please do not hesitate to contact me with any questions at 610-344-6239

Sincerely,

[Signature: Ralph E. DeFazio]

cc: Rick Smith, East Goshen Township Manager
Michael J. Ellis, East Goshen Municipal Authority Engineer
Elizabeth Mahoney, PA DEP
CCPC
file

“Protecting You and Your Environment”

AREA CODE 610
692-7171

EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP

1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

June 16, 2014

John M. Scott, Plant Manager
West Goshen Wastewater Treatment Plant
848 South Concord Road
West Chester, PA 19382

Re: Act 537 Plan Revision
Reservoir Road Pump Station
East Goshen Township, Chester County, PA

Dear John:

I am in receipt of Max Stoner’s letter of June 9, 2014. Mike Ellis and I discussed your concerns with the East Goshen Municipal Authority at their meeting on June 9, 2014 and in response would offer the following:

The 1977 Agreement between the two Townships and two Authorities has two sections that are relevant.

Section 3.03a Delivery of Sewage Wastes states “...no Sewage Wastes from any parties Sewage Collection System shall be diverted directly or indirectly, to another treatment facility until the Reserved Capacity is reached; provided, however, that any flows from portions of the East Goshen collection System, originating outside the drainage basin of the Chester Creek may be diverted at any time at the sole options of East Goshen Authority or East Goshen as Lessee, upon giving 90 days written notice of such diversion to West Goshen and West Goshen Authority.”

Section 10.01 Penalty of the Agreement notes that if one of the parties exceeds their Reserved Capacity the operator of the receiving facility may impose a penalty of 25% of the costs. The penalty increases to 50% after 120 days.

In 2013 our average daily flow to West Goshen was 827,646 gpd. However, the monthly average for February of 2013 was 1,004,657 gpd and in June of 2013 it was 1,057,984 gpd. The average for the first quarter of 2014 is 873,715 gpd.

My concern is that East Goshen does not want to be in a position in which we are over our 1,000,000 gpd limit at West Goshen for an extended period of time and therefore be subject to the penalty set forth in Section 10.01.

We estimate that it would take nine months to bid and construct the Reservoir Road Pump Station.

Our plan is to obtain the Act 537 Plan approval and the other permits required for the Reservoir Road Pump Station. Once we have these in hand we would then wait to construct the Pump Station until if and when it looks like we will exceed 1,000,000 gpd at West Goshen. Since you invoice us quarterly, I would suggest that we begin the construction process when there are two consecutive quarters in which the “average daily flow” exceeds 950,000 gpd. The pump station will not be placed in service until we have reached 1,000,000 mgd. If this is acceptable to you I will have Mike revise the project schedule to reflect this.

I would add that it is less expensive for us to treat wastewater at West Goshen than at Ridley, so we do not intend to divert flow until we absolutely have to and, we would not want to divert more than needed in order to keep us under 1,000,000 gpd.

With respect to the other projects in Max’s letter both New Kent Apartments and the homes served by Hershey Mill Pump Station are outside of the Chester Creek drainage basin so the diversions are permitted pursuant to Section 3.03.

The homes served by the Marydell Pump Station were in the Chester Creek drainage basin and we appreciate your cooperation with that project. The pump station was literally on its last legs when we took it out of service.

If you have any questions, or think it would be helpful, Jack Yahraes, Authority Chairman; Mike Ellis and I would be happy to attend your Authority meeting on July 2, 2014

Sincerely,

[Signature: Rick]
Louis F. Smith, Jr.
Township Manger

F:\Data\Shared Data\ABC'S\Municipal Authority\Projects\Reservoir Road PS\Act 537 Plan\Letter to West Goshen 061614.docx