Municipal Authority

The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.

 

The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.

  • Five members, serving five-year terms
  • Meetings are on the 2nd Monday of the month at 7:00 P.M.
  • All township meetings are held at the Township Building and open to the public
Authority Members Term Expiration Date
Kevin Cummings, Chairman 2026
John Stipe, Vice Chairman
2029
Dana Pizzarro, Secretary 2026
Sean Ellsworth, Assistant Secretary/Treasurer 2028
Walter Wujcik, Treasurer 2028
Pennoni Associates, Engineer
Patrick M. McKenna, Esq.
Peter Hicks, BoS Liaison
Kevin Miller, Staff Liaison

 

Municipal Authority Genealogy

Audits

Documents

Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.

EAST GOSHEN MUNICIPAL AUTHORITY

May 12, 2014
Monday 7:00 PM

  1. CALL TO ORDER/PLEDGE OF ALLEGIANCE/MOMENT OF SILENCE Ask if anyone will be taping the meeting?
  2. CHAIRMAN’S REPORT/OTHER MEMBERS REPORTS
  3. SEWER REPORTS Director of Public Works Report; Pennoni Engineer’s Report; Big Fish Environmental Inc. Report with DMR’s; East Goshen Township Flows for April 2014
  4. APPROVAL OF MINUTES April 21, 2014
  5. APPROVAL OF INVOICES Pennoni      Invoice #587993      $ 197.25; Pennoni      Invoice #587994      $4,724.50; Pennoni      Invoice #587995      $ 992.00; Pennoni      Invoice #587996      $4,562.25; Pennoni      Invoice #587997      $ 644.25
  6. LIAISON REPORTS
  7. FINANCIAL REPORTS April 2014 Report
  8. OLD BUSINESS
  9. GOALS Review current mission statement and provide the Board of Supervisors with changes, if needed – June 1, 2014 May 8 – The MA does not have a current mission statement. A first draft is included in the packet.; Submit an article for each newsletter – Due date for newsletter Need by 1/31/14 – Dana Completed Need by 4/30/14 – Jack Completed Need by 7/1/14 Need by 10/31/14

F:\Data\Shared Data\Agendas\Municipal Authority\2014\5-12-14.doc

  1. Obtain PA DEP approval for the Act 537 Plan revision for the Reservoir Road Pump Station – December 31, 2014 May 8 - Revisions submitted to EGMA, EGPC, WGSTP, WGPC, CCHD, and CCPC
  2. Develop a recommendation on covers for the SBRs – August 1, 2014
  3. Attend West Goshen Meetings quarterly – more often if needed. 1 st Quarter (March) - Jack 2 nd Quarter (June) - Ed 3 rd Quarter (September) 4 th Quarter (December)
  4. Respond to capacity requests in 45 days or less. 211 Ellis Lane – 1 EDU existing house, 195 Wyllpen Place – 1 EDU existing house
  5. Continue to implement I & I Plan April 14 – Status Report received
  6. Operate RCSTP in compliance with NPDES Permit January, February, March,
  1. NEW BUSINESS Authorize Chairman to execute Reservoir Road PS Act 537 Revision
  2. CAPACITY REQUESTS None
  3. ANY OTHER MATTER
  4. CORRESPONDENCE AND REPORTS OF INTEREST
  5. PUBLIC COMMENT
  6. ADJOURNMENT

F:\Data\Shared Data\Agendas\Municipal Authority\2014\5-12-14.doc

AREA CODE 610
692-7171

EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP

1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

May 9, 2014

To: Municipal Authority

From: Mark Miller

Re: April 2014 Monthly Report

Meters: All meters were read on a daily basis. After the heavy rain last week we walked the interceptor line and pulled manholes to do a visual inspection. The new portable meters have been ordered and the others were sent for calibration.

C.C. Collection: All pumping stations were visited on a daily basis. We did not incur any problems during the month. We assisted West Goshen last Wednesday night into Thursday morning; they had to shut down the Westtown Way Pump Station for repairs. We had to plug the interceptor line thru out the night to regulate the flow.

R.C. Collection: The pumping stations were visited on a routine basis with no problems to report.

We have been repairing laterals on both systems from missing caps to broken stack pipes.

R.C. Plant: All the wet well pumps have been pulled out for routine maintenance; we will now begin to pull the SBR pumps for maintenance.

Alarms: We responded to 73 alarms for the month of April.

PA One Calls: We received 123 PA One calls in April.

EGMA 1401

[Pennoni logo]

MEMORANDUM

TO: East Goshen Municipal Authority Board
Rick Smith, Township Manager

FROM: Michael Ellis, P.E.
Authority Engineer

DATE: May 8, 2014

SUBJECT: Engineer’s Report

Invoices

  • Invoices with summaries are provided under separate cover.

Ridley Creek Sewage Treatment Plant (RCSTP)

  • Pennoni continues to provide operations assistance as needed. No operational issues were brought to our attention in April.

Reserve Pump Station Elimination

  • The contractor has provided all of the required contract closeout documents; however, we have not yet reviewed the as-built plans as of the date of this memo. We intend to review the plans prior to the May 12 Municipal Authority meeting. There are two outstanding punchlist items that still need to be addressed: removal of the filter sock along the creek and re-seeding/re-topsoiling the lawn area at the old pump station driveway and building. We have reviewed the other submitted closeout documents and final payment request. We have certified the final payment request and forwarded it to the Township with a recommendation that payment be approved but the check not be issued until the as-built plans have been reviewed and the punchlist work has been completed to the Township’s satisfaction.

Reservoir Road Pump Station Act 537 Plan

  • Conestoga-Rovers & Associates (CRA) finalized the Phase 1 bog turtle habitat assessment report and submitted it to the U.S. Fish & Wildlife Service (USFWS) in late April.
  • We finalized the Act 537 Plan report and plot plans. The Act 537 Plan was submitted the East Goshen Township Planning Commission, West Goshen Township Planning Commission, Chester County Planning Commission, Chester County Health Department, and West Goshen Sewage Treatment Plant operator on May 8, 2014. The agencies are allotted 60 days to review and provide comments per PADEP Act 537 guidelines. A copy was also submitted to the Municipal Authority to sign Section K of Component 3m.

Page 1 of 2

P:\Projects\EGMA\Memos to Board\2014\Memo to EGMA Board 2014-05-08.docx

EGMA 1401

  • As previously reported, the PA Department of Conservation and Natural Resources (DCNR) is requiring a field botanical survey of potential threats to four special concern plant species. We have discussed whether the survey is still required with DCNR given the revised force main routing and revised PNDI search that returned no DCNR conflicts. We have submitted documentation of the revised force main routing to DCNR, and we expect to receive feedback from them by May 12.
  • Tentative Act 537 Planning schedule (assuming no botanical survey or Phase 2 bog turtle screening): Milestone Estimated Date Submit to County and Township Agencies May 8, 2014 USFWS Bog Turtle Habitat Coordination June 22, 2014 60-day County and Township Review Period July 8, 2014 Revisions per Agency Comments July 11, 2014 30-Day Public Comment Period August 11, 2014 East Goshen and West Goshen Township Adoption August 19, 2014 PADEP Review and Approval (120 days) December 20, 2014

New Sewer Connections

  • We reviewed a design plan and report submission for a new private wastewater pump station for Acero Precision at 1340 Enterprise Drive, discussed comments and questions with the PW Director, and forwarded comments to the design consultant.

Fairway Village Manhole Lining

  • We coordinated scheduling of the SprayWall monolithic polyurethane interior manhole lining system with the contractor including attending a pre-construction field meeting. They tentatively plan to perform the work the week of June 10, 2014.

RCSTP Tank Covers

  • We continued the evaluation of flexible tank cover alternatives and forwarded a DRAFT updated summary memo to the Township. We are still awaiting feedback and pricing from a couple of vendors before finalizing the memo. The memo will be finalized by the June Municipal Authority meeting.

Page 2 of 2

P:\Projects\EGMA\Memos to Board\2014\Memo to EGMA Board 2014-05-08.docx

[Big Fish Environmental Services Inc. logo]

Monthly Operations Report: April 2014

Treatment Process Operation

During March 2014, there were no exceedances of the final effluent discharge limitations for outfall 001 and no discharge from Outfall 002. Table 1 illustrates the final effluent composite sample data reported for the March 2014 eDMR.

Table 1

March 2014 - Final Effluent - Out Fall 001

NPDES Permit Discharge Limitations Flow CBOD5 TSS NH4-N Phosphorus, Total , mg/L Fecal Coliform
MGD Average mg/L lbs/month mg/L lbs/month mg/L lbs/month mg/L lbs/month Geo Mean Geo Mean
0.75 20 125 21 131 7 44 0.5 3 200 1,000
Instantaneous Maximum 40 42
Sample Date
March 4, 2014 0.454 2.1 8.0 3 11 3.08 11.66 0.25 0.95 1 0.0000
April 11, 2014 0.528 7.5 33.0 7 31 3.88 17.09 0.63 2.77 1 0.0000
March 18, 2014 0.424 2.2 7.78 2 7 5.59 19.77 0.24 0.85 1 0.0000
March 25, 2014 0.473 4.4 17.4 3 12 1.51 5.96 0.41 1.62 1 0.0000
Average 0.4698 4.1 16.5 4 15 3.515 13.62 0.38 1.55 1 0.0000
Minimum 0.4240 2.1 7.8 2 7 1.510 5.96 0.24 0.85 1 0.0000
Maximum 0.5280 7.5 33.0 7 31 5.590 19.77 0.63 2.77 1 0.0000

The monthly average total phosphorus concentration was 0.38 mg/L as compared to the discharge limitation of 0.5 mg/L. During the month, the final effluent total phosphorus concentration discharged ranged from 0.24 mg/L to 0.63 mg/L with an average of 44.4 gallons per day of aluminum sulfate solution.

There was no discharge to Applebrook, Outfall 002, during March 2014.

Table 2 illustrates the influent wastewater pollutant loadings for March 2013. The influent loadings remained within the treatment facility design loadings.

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 1 of 9

[Big Fish Environmental Services Inc. logo]

Table 2

March 2014 - Influent Wastewater

Design Basis Flow BOD5 TSS NH4-N TKN, mg/L Phosphorus, Total, mg/L
mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day
MGD Average 335 2,098 320 2,001 32 200 48 301 9.1 57
Sample Date
March 4, 2014 0.464 160 619 136 526 25.9 100 36.1 140 4.8 19
April 11, 2014 0.562 177 685 224 867 25.3 98 39.6 153 4.0 15
March 18, 2014 0.446 124 480 44 170 22.4 87 35.7 138 4.3 17
March 25, 2014 0.592 184 712 132 511 27.4 106 39.0 151 4.5 17
Average 0.5160 161 624 134 519 25.3 98 37.6 146 4.4 17
Minimum 0.4460 124 480 44 170 22.4 87 35.7 138 4.0 15
Maximum 0.5920 184 712 224 867 27.4 106 39.6 153 4.8 19

During the month of April 2014, the total phosphorus concentrations at the final effluent outfall 001 were slightly elevated at or above the permitted discharge limitation of 0.5 mg/L. Aluminum sulfate feed rates were increased as the month progressed to assist with total phosphorus removal. During April, especially during 3 of the 4 scheduled sampling events, the influent wastewater flow to the SBRs ranged from 12% to 43% above the March monthly average. Periodically, the influent flow rate and volume to the SBRs resulted in “Filled Decants.” The Filled Decant condition results in diverting a mixture of influent wastewater and treated effluent directly to the post flow equalization basins, disc filters and disinfection prior to discharge through outfall 001. The preliminary data indicates that the final effluent total phosphorus concentration is likely to slightly exceed the permitted concentration of 0.50 mg/L. The mass loading permit limitation is anticipated to remain below the monthly average of 3.0 lbs per day.

Table 5 presents a summary of the final effluent flow total and number of filled decant conditions observed during the April 2014 compliance sampling events.

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 2 of 9

[Big Fish Environmental Services Inc. logo]

Table 5

Final Effluent Outfall 001 24 Hr Composite Sample Collection Flow recorded on Sample Collection End Date Number of Filled Decants Recorded During Sample Collection Period
Start Date End Date MGD each
3/31/14 4/1/14 0.512 1
4/7/14 4/8/14 0.508 2
4/14/14 4/15/14 0.692 7
4/21/14 4/22/14 0.458 0
4/28/14 4/29/14 0.549 0

Improvement management for total phosphorus during periods of elevated flow rates to the SBRs resulting in Filled Decant conditions include the following actions:

  • Utilize the polymer feed system which provided polymer prior to filtration to assist with coagulation/flocculation of solids and total phosphorus. Coordination with Aqua Aerobics for a compatible product for the filter media is strongly recommended.
  • Provide for the capability of addition of aluminum sulfate to the influent wastewater during a Filled Decant condition.
  • Evaluate utilizing poly aluminum chloride (PAC) solution prior to filtration in place of aluminum sulfate solution. Higher dosages of aluminum sulfate solution contribute to elevated TSS concentrations and turbidity whereas PAC has negligible impacts.
  • Re-evaluate the use of real time control loop system for integrating aluminum sulfate feed rates with disc filter and/or SBR influent flow rates.

Table 3 presents the final effluent data for the month of April 2014.

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 3 of 9

[Big Fish Environmental Services Inc. logo]

Table 3

April 2014 - Final Effluent - Out Fall 001

NPDES Permit Discharge Limitations Flow CBOD5 TSS NH4-N Phosphorus, Total , mg/L Fecal Coliform
MGD Average mg/L lbs/month mg/L lbs/month mg/L lbs/month mg/L lbs/month Geo Mean Geo Mean
0.75 20 125 21 131 7 44 0.5 3 200 1,000
Instantaneous Maximum 40 42
Sample Date
April 1, 2014 0.512 4.2 17.9 8 34 1.39 5.94 0.49 2.09 1 0.0000
April 8, 2014 0.508 4.9 20.8 10 42 0.12 0.53 0.68 2.88 1 0.0000
April 15, 2014 0.692 3.5 20.20 8 46 0.25 1.45 0.50 2.89 1 0.0000
April 22, 2014 0.458 4.3 16.42 7 27 0.55 2.10 0.39 1.49 1 0.0000
April 29, 2014 0.549
Average 0.544 4.2 18.8 8 37 0.579 2.50 0.52 2.34 1 0.0000
Minimum 0.458 3.5 16.4 7 27 0.124 0.53 0.39 1.49 1 0.0000
Maximum 0.692 4.9 20.8 10 46 1.390 5.94 0.68 2.89 1 0.0000

During March 2014, there was no discharge to Applebrook.

The influent wastewater pollutant concentrations and loading entering the wastewater treatment facility remained within the design concentrations and loadings. Composite samples are collected at the influent doghouse manhole and influent wet well. The influent flow meter reading is collected from the influent flow meter located prior to the Screening Building, excluding the internal recycle flows.

Table 4 presents the available pollutant data for the influent wastewater collected at the doghouse manhole.

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 4 of 9

[Big Fish Environmental Services Inc. logo]

Table 4

April 2014 - Influent Wastewater

Design Basis Influent Flow SBR Flow BOD5 TSS NH4-N TKN, mg/L Phosphorus, Total, mg/L
MGD MGD mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day
335 2,098 320 2,001 32 200 48 301 9.1 57
Sample Date
April 1, 2014 0.517 0.581 89.3 346 64 248 20.8 80 25 97 3.2 12
April 8, 2014 0.553 0.600 125 484 120 464 17.4 67 25.7 99 3.5 14
April 15, 2014 0.737 0.739 140 542 128 495 28.0 108 63.6 246 4.8 19
April 22, 2014 0.462 0.481 156 604 132 511 24.4 94 40.1 155 4.9 19
April 29, 2014 0.558 0.625
Average 0.565 0.605 128 494 111 430 22.7 88 38.6 149 4.1 16
Minimum 0.4620 0.4810 89 346 64 248 17.4 67 25.0 97 3.2 12
Maximum 0.7370 0.7390 156 604 132 511 28.0 108 63.6 246 4.9 19

Sequencing batch reactors (SBRs) numbered 1, 3 and 4 were in service during the month of April.

Process monitoring of each SBR included ammonia as N, nitrite as N, Nitrate as N, COD, SSV, MLSS and total phosphorus. Foam concentrations remain reduced during the month of April. Increased sludge wasting was continued to maintain lower the MLSS concentrations. SBRs numbered 3 and 4 were observed to have a maximum of approximately 5% of the surface area covered with a medium brown colored foam. Adjustments to the treatment process to lower the MLSS concentrations and raise the F:M ratio within the target range of 0.045 to 0.06 were ongoing during the month.

Daily monitoring of the influent and final effluent 24-hour composites samples for total phosphorus is ongoing. Daily analysis of the final effluent flow equalization grab sample is total phosphorus is ongoing. Sample collection and analysis of the influent wastewater collected at the influent pump station wet well is ongoing.

Addition of aluminum sulfate solution to the SBRs to assist with phosphorus removal continued. The volume of aluminum sulfate solution to the SBRs was increased from 45 gpd to as high as 90 gpd during April to assist with total phosphorus removal. Increased aluminum sulfate dosages prior to filtration were

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 5 of 9

[Big Fish Environmental Services Inc. logo]

increased during the month. Soda ash addition to the SBRs to assist with maintain desired pH concentrations above 7.0 standard units continued during the month. Soda ash addition to the SBRs during April averaged 308 pounds per day.

SBR No. 2 remains out of service as a treatment unit, however, partially filled with MLSS which continuously mixed and aerated. The majority of the contents were transferred to the sludge holding tanks. This SBR was periodically placed in service to assist with managing peak flows to reduce the impact of Filled Decant conditions.

The decanter for SBR 3 continued to be periodically observed as being slightly tilted within the water level. The effluent knife valve was routinely closed and the decanter filled with water to assist with lowering the decanter within the water level. The frequency of occurrence ranged from one to several occurrences during the month. The SBR is planned for removal from service during late May or early June for inspection.

Flow data:

Flow Meter Location April 2014
Total Volume for Month, MGD Average Daily Flow, gpd Daily Maximum Flow, gpd
Influent Wastewater to Screening Building 14.467 466,898 937,340
Influent Wastewater to SBRs 16.000 516,147 1,367,000
Internal Recycle 1.623 49,248 429,230
Treated Effluent to Disc Filters 15.488 516,258 1,334,206
Final Effluent Discharge 14.705 495,774 1,325,000
Applebrook Golf Course 0 0

Chemical Usage:

Chemical April 2014
Daily Average Total Monthly
Soda Ash 308 9,250
Magnesium Hydroxide 0 0
Aluminum Sulfate solution 54.3 1,630
Polymer (centrifuge) 0.86* 14 gallons

*Sixteen (16) days of centrifuge operation

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 6 of 9

[Big Fish Environmental Services Inc. logo]

Solids Dewatering and Disposal: April 2014

Sludge Dewatering Summary
Gallons of sludge dewatered 241,796 gallons
Average Dewatered Total Solids, % 18.95%
Wet Tons 41.96
Dry Tons 7.965
Number of dumpsters 4

*A total of four (4) dumpsters were filled and five (5) dumpsters were removed during April.

During the month, sludge wasting to the sludge holding tanks and decanting of the sludge holding tanks was ongoing. Process monitoring included pH, total alkalinity and total solids.

Sludge holding tank No. 1 was in service. The level at the beginning of the month was 12.55 feet and the level at the end of the month was 7.11 feet. The initial total solids concentration was 1.21% and ended the month as 0.625% total solids. The average pH concentration was 6.98 S.U. and total alkalinity of 325 mg/L. No supernatant was decanted during the month. A total of 650 pounds of soda ash were added during the month for pH adjustment.

Sludge holding tank No. 2 was in service. The level at the beginning of the month was 5.81 feet and the level at the end of the month was 13.78 feet. The initial total solids concentration were 0.69% and ended the month as 0.85% total solids. The average pH concentration was 7.05 S.U. and total alkalinity of 319 mg/L. 207,013 gallons of supernatant were decanted during the month. A total of 400 pounds of soda ash were added during the month for pH adjustment.

Significant Storm/Hydraulic Loading Events

On April 15, 2014, the influent flows arte to the SBRs continuously exceed 100% of the hydraulic design rate from 9:43 through 22:11 (approximately 13 hours). A total 7 Filled Decant and 1 Filled settle condition were observed for a total of 302 minutes (5.03 hours). The effluent clarity remained good with no bulking or excessive solids present within the discharge at outfall 001. Figure 1 presents the influent flow rate to the SBRs as indicated by the black colored line on the graph.

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 7 of 9

Big Fish Environmental Services Inc.

Figure 1

[Screenshot of Ridley Creek WWTP SCADA Trend Chart window dated April 30, 2014 (Node Name: EGT_STP_CTRL, Operator: scott, Level: 9999). Navigation buttons on left: Log On, Log Off, Legend, SBR Overview, SBR Setpoints, Chem Pumps Setpoints, Alarms & Events, Alarm Database, Trend Chart, Data Extraction, ETMs/Flow Totals. Chart controls: 00:00:00, Zoom In, 1d 22h, Zoom Out, 22:00:00; 4 hours, 1 hour, Minutes, 30 minutes, 10 minutes. Time axis spans Apr 15 00:00:00, Apr 15 11:30:00, Apr 15 23:00:00, Apr 16 10:30:00, to Apr 16 22:00:00; time cursors at 09:43:44 and 22:11:42. Left Y-axis scale: 0 to 10,000 (0, 1,250, 2,500, 3,750, 5,000, 6,250, 7,500, 8,750, 10,000). Right Y-axis SBR states: Waste Sludge, Filled Decant, Decant, Filled Settle, Settle, Vacflush, React, React DeNit., Filled DeNit., Aerated Fill, Mixed Fill, Static Fill, Aerated Idle, Idle, Off, Failed Off. Legend items at bottom: SBR1DO (SBR1 dissolved oxygen: 0.00, 3.00), SBR2DO (SBR2 dissolved oxygen: 0.00, 3.00), SBR4DO (SBR4 dissolved oxygen: 0.00, 3.14), calculated_flow (Calculated Influent Flow: 100.40, 1000.00), SBR1Step (SBR1 step number: 6.00, 11.00), SBR2Step (SBR2 step number: 8.00, 9.00), SBR4Step (SBR4 step number: 11.00, 6.00), calculated_gpm (Calculated Influent Flow: 527.28, 561.60). Bottom right buttons: Print, Help, Alarm Acknowledge.]

On April 30th through May 1st, the influent flows arte to the SBRs continuously exceed 233% of the hydraulic design rate from 13:30 through 2:24 (approximately 12 hours). A total of 11 Filled Decant and Filled settle conditions were observed for a total of 805 minutes (13.4 hours). The effluent clarity remained good with no bulking or excessive solids present within the discharge at outfall 001. Figure 2 presents the influent flow rate to the SBRs as indicated by the black colored line on the graph.

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 8 of 9

Big Fish Environmental Services Inc.

Figure 2

[Screenshot of Ridley Creek WWTP SCADA Trend Chart window dated May 1, 2014 (Node Name: EGT_STP_CTRL, Operator: scott, Level: 9999). Navigation buttons on left: Log On, Log Off, Legend, SBR Overview, SBR Setpoints, Chem Pumps Setpoints, Alarms & Events, Alarm Database, Trend Chart, Data Extraction, ETMs/Flow Totals. Chart controls: 00:00:00, Zoom In, 1d 6h, Zoom Out, 06:00:00; 4 hours, 1 hour, Minutes, 30 minutes, 10 minutes. Time axis spans Apr 30 00:00:00, Apr 30 07:30:00, Apr 30 15:00:00, Apr 30 22:30:00, to May 01 06:00:00; time cursors at 13:30:00 and 02:24:00. Left Y-axis scale: 0 to 10,000 (0, 1,250, 2,500, 3,750, 5,000, 6,250, 7,500, 8,750, 10,000). Right Y-axis SBR states: Waste Sludge, Filled Decant, Decant, Filled Settle, Settle, Vacflush, React, React DeNit., Filled DeNit., Aerated Fill, Mixed Fill, Static Fill, Aerated Idle, Idle, Off, Failed Off. Legend items at bottom: SBR1DO (SBR1 dissolved oxygen: 0.00, 0.00), SBR2DO (SBR2 dissolved oxygen: 0.00, 0.00), SBR4DO (SBR4 dissolved oxygen: 1.90, 0.00), calculated_flow (Calculated Influent Flow: 233.60, 230.40), SBR1Step (SBR1 step number: 6.00, 11.00), SBR2Step (SBR2 step number: 11.00, 11.00), SBR4Step (SBR4 step number: 9.00, 14.00), calculated_gpm (Calculated Influent Flow: 1212.96, 1313.68). Bottom right buttons: Print, Help, Alarm Acknowledge.]

Minor Repairs and Preventative Maintenance

  • Replaced a ballast in UV bank Number 2.

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 9 of 9

2013 FLOWMETERS

2014 APRIL 2ND QUARTER- METERS FROM WEST GOSHEN - CC COLLECTION

Precip Inches DATE WESTTOWN WAY READING WESTTOWN WAY GPD ELLIS LANE READING ELLIS LANE GPD PAOLI PIKE READING PAOLI PIKE GPD WILSON DRIVE READING WILSON DRIVE GPD SUMMIT GPD NET FLOWS
0.0004/01/141,625,6431,475,5004,430,173180,6082,714,52080,8431,118,70382,65424,0001,131,396
0.1004/02/141,626,9231,280,0004,444,398142,2502,721,88573,6501,126,77680,73024,000983,370
0.1204/03/141,628,1211,198,0004,456,903125,0502,728,92570,4001,135,52087,44024,000915,110
0.0504/04/141,629,4211,300,0004,470,724138,2102,736,98080,5501,144,83493,14024,000988,100
0.0004/05/140
0.0004/06/140
0.3004/07/141,632,9611,180,0004,509,845130,4032,758,13970,5301,164,34665,04024,000914,027
0.0004/08/141,634,2131,252,0004,524,182143,3702,766,07479,3501,173,03686,90024,000942,380
0.0004/09/141,635,4441,231,0004,537,832136,5002,773,09470,2001,182,23591,99024,000932,310
0.0004/10/141,636,5571,113,0004,549,292114,6002,781,20081,0601,190,76385,28024,000832,060
0.0004/11/141,637,7771,220,0004,562,404131,1202,789,17279,7201,199,14983,86024,000925,300
0.0004/12/140
0.0004/13/140
0.0804/14/141,641,0931,105,3334,599,323123,0632,811,51874,4871,217,31060,53724,000847,247
2.1504/15/141,642,2131,120,0004,611,505121,8202,818,86573,4701,226,98096,70024,000828,010
0.0004/16/141,644,1041,891,0004,637,189256,8402,829,482106,1701,238,509115,29024,0001,412,700
0.0004/17/141,645,4281,324,0004,654,629174,4002,837,64481,6201,246,89583,86024,000984,120
0.0004/18/140
0.0004/19/140
0.0004/20/140
0.0004/21/141,651,4561,507,0004,725,754177,8132,874,15791,2831,282,07887,95824,0001,149,948
0.0504/22/140
0.0004/23/140
0.0004/24/141,653,692745,3334,750,70483,1672,888,49547,7931,303,50371,41724,000542,957
0.5004/25/141,654,8681,176,0004,763,670129,6602,895,97574,8001,314,338108,35024,000863,190
0.0304/26/140
0.0004/27/140
0.0504/28/141,658,1831,105,0004,803,363132,3102,917,87773,0071,342,44593,69024,000805,993
0.6004/29/141,659,2931,110,0004,815,443120,8002,924,99971,2201,354,343118,98024,000799,000
3.5004/30/141,660,5731,280,0004,831,570161,2702,932,78277,8301,363,44290,99024,000949,910
Day Avg1,242,798143,32976,73688,67424,000591,571
7.53Day Tot23,613,1672,723,2531,457,9821,684,805456,00017,747,127
Day Count191919191930
Metric E.GOSHEN
MONTH TO DATE7.53
NORMAL MONTH TO DATE
YEAR TO DATE19.09
NORMAL YEAR TO DATE

2014 flowmeters -all-stations separate month worksheets.xlsAPR
5/2/20148:50 AM

2013 FLOWMETERS

2014 APRIL 2ND QUARTER- METERS FROM WEST GOSHEN - CC COLLECTION

DATE HERSHEY'S MILL READING HERSHEY'S MILL GPD ASHBRIDGE READING ASHBRIDGE GPD HICKS METER READING HICKS METER GPD RESERVOIR READING RESERVOIR GPD BARKWAY READING BARKWAY GPD
04/01/146,742,3801,134,7951,854,511105,85010,605,847304,85044,364,379980,6633,139,63614,543
04/02/146,865,9551,235,7501,855,30579,40010,635,942300,95044,451,951875,7203,140,85112,150
04/03/146,981,1651,152,1001,855,99468,90010,666,519305,77044,533,930819,7903,141,95711,060
04/04/147,106,4201,252,5501,856,82282,80010,699,020325,01044,620,807868,7703,143,11711,600
04/05/14
04/06/14
04/07/147,460,6201,180,6671,859,20979,56710,775,626255,35344,840,592732,6173,147,04713,100
04/08/147,565,1441,045,2401,859,98377,40010,807,391317,65044,922,399818,0703,148,11310,660
04/09/147,671,4481,063,0401,860,73975,60010,838,840314,49045,002,222798,2303,149,31612,030
04/10/147,766,569951,2101,861,39966,00010,868,543297,03045,074,239720,1703,150,42911,130
04/11/147,867,4701,009,0101,862,18178,20010,899,290307,47045,152,953787,1403,151,68212,530
04/12/14
04/13/14
04/14/148,156,596963,7531,864,33771,86710,974,752251,54045,355,138673,9503,155,43312,503
04/15/148,245,758891,6201,865,02468,70011,004,253295,01045,427,557724,1903,156,49810,650
04/16/148,359,7811,140,2301,866,318129,40011,045,424411,71045,550,6701,231,1303,158,24917,510
04/17/148,461,7211,019,4001,867,09577,70011,077,015315,91045,638,671880,0103,159,47012,210
04/18/14
04/19/14
04/20/14
04/21/148,988,0801,315,8981,871,205102,75011,211,895337,20046,013,605937,3353,166,07516,513
04/22/14
04/23/14
04/24/149,174,590621,7001,872,55845,10011,269,498192,01046,154,303468,9933,168,2367,203
04/25/149,269,475948,8501,873,29673,80011,300,079305,81046,228,064737,6103,169,49912,630
04/26/14
04/27/14
04/28/149,542,023908,4931,875,43571,30011,374,095246,72046,432,133680,2303,173,05611,857
04/29/149,625,044830,2101,876,10567,00011,403,684295,89046,505,954738,2103,174,23011,740
04/30/149,714,127890,8301,876,92882,30011,436,134324,50046,590,553845,9903,175,49812,680
Day Avg1,029,22979,139300,256806,25312,331
Day Tot19,555,3461,503,6335,704,87315,318,808234,298
Day Count1919191919

2014 flowmeters -all-stations separate month worksheets.xlsAPR
5/2/20148:50 AM

2014 SUMMARY OF METER READINGS

WESTTOWN WAY ELLIS LANE PAOLI PIKE WILSON DRIVE SUMMIT HERSHEY MILL ASHBRIDGE HICKS RESERVOIR BARKWAY
JANUARY1,120,955112,63163,43680,89024,000255,116795,376
FEBRUARY1,249,173138,44968,47288,80324,000287,831881,433
MARCH1,182,533126,93367,47984,19724,000860,07475,186291,520827,10928,696
APRIL1,242,798143,32976,73688,67424,0001,029,22979,139300,256806,25312,331
MAY
JUNE
JULY
AUGUST
SEPTEMBER
OCTOBER
NOVEMBER
DECEMBER
Total Flows
Monthly Ave1,198,865130,33669,03185,64124,000944,65277,163283,681827,54320,514

To
West Goshen 913,858

2014 flowmeters -all-stations separate month worksheets.xlsxSUMMARY

April Precip. 7.53-2014

[Bar chart displaying daily precipitation for April 2014.]

  • Y-axis label: precip. (scale: 0, 0.5, 1, 1.5, 2, 2.5, 3, 3.5)
  • X-axis label: snow/rain (categories: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33)
  • Legend: April

2013 Monthly Precipitation

[Bar chart displaying monthly precipitation totals for January through December.]

  • Y-axis scale: 0, 1, 2, 3, 4, 5, 6, 7, 8
  • X-axis categories: January, February, March, April, May, June, July, August, September, October, November, December
  • Legend: Series1

Flowmeters April 2014

[Line chart displaying daily flowmeter totals for April 2014.]

  • Y-axis label: Flow's (scale: 0, 200000, 400000, 600000, 800000, 1000000, 1200000, 1400000, 1600000)
  • X-axis label: Day of the Month (categories: 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31)
  • Legend: April

Monthly Totals 2012 Jan-Dec

[Bar chart displaying daily flowmeter readings grouped by month from January through December.]

  • Y-axis label: Flowmeters (scale: 0, 200000, 400000, 600000, 800000, 1000000, 1200000, 1400000, 1600000)
  • X-axis label: Month (categories: January, February, March, April, May, June, July, August, September, October, November, December)

draft

EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
MEETING MINUTES
April 21, 2014

The East Goshen Township Municipal Authority held their regular public meeting on Monday, April 21, 2014 at 7:00 pm at the East Goshen Township building. Members in attendance were: Chairman Jack Yahraes, Fran Beck, Dana Pizarro, Kevin Cummings and Ed McAssey. Also in attendance were: Rick Smith (Township Manager), Bob Adams (Attorney), Mark Miller (Director of Public Works), Scott Towler (BFES), Mike Ellis (Pennoni), and Walter Wujcik, Conservancy Board.

COMMON ACRONYMS:

BFES – Big Fish Environmental Services MA- Municipal Authority
BOS – Board of Supervisors NPDES – National Pollutant Discharge Elimination System
CB – Conservancy Board PC – Planning Commission
DEP – Department of Environmental Protection PR – Park & Recreation Board
EPA – Environmental protection Agency RCSTP – Ridley Creek Sewer Treatment Plant
HC – Historical Commission SBR – Sequencing Batch Reactor
I&I – Inflow & Infiltration SSO – Sanitary System Overflow
LCSTP – Lockwood Chase Sewer Treatment Plant WAS – Waste Activated Sludge

Call to Order & Pledge of Allegiance

Jack called the meeting to order at 7:00 pm and led those present in the Pledge of Allegiance. There was a moment of silence to remember the troops and all veterans. Jack asked if anyone would be recording the meeting and there was no response.

Chairman’s Report/Other Members’ Reports

None

Approval of Minutes

Fran moved to accept the minutes of March 10, 2014 as corrected. Dana seconded the motion. The motion passed unanimously.

Approval of Invoices

  1. Dana moved to approve payment of the following Pennoni invoices: Pennoni #584215 $ 5,909.00; Pennoni #584216 $ 1,610.25; Pennoni #584218 $ 7,198.00 Fran seconded the motion. The motion passed unanimously.
  2. Kevin moved to approve payment of the following Gawthrop invoices: Gawthrop #118753 $ 960.00; Gawthrop #117715 $ 700.00 Fran seconded the motion. The motion passed unanimously.

F:\Data\Shared Data\Minutes\Municipal Authority\2014\MA 4-21-14 draft.doc

1

Liaison Reports

Conservancy Board – Walter reported that the CB is having their spring planting on Saturday, June 14, 2014 at East Boot Road. They will fill in some more trees. Keep East Goshen Beautiful Day was not as well attended because of the trip to Washington DC and the Electronics Recycling event at East Goshen Park. He mentioned that the CB still has 2 vacancies.

Financial Reports

  1. Jon Altshul’s April 3, 2014 Financial Report for March 2014: The Municipal Authority recorded $4,561 in revenues and $20,062 in expenses in March, a difference of -$15,501. Engineering expenses and the quarterly administrative overhead chargeback represented the bulk of expenses, while revenues came primarily from Tapping Fees for two lots in Sorrell Hill. The fund balance is now $1,613.549.
  2. 1 st Quarter Municipal Authority chargeback expenses: ABC services (preparing & distributing packets) $1,771.38; Secretarial services (taking & preparing minutes) $ 210.00; Director of Finance/Treasurer $1,166.62; Staff Accountant $ 886.34; Director of Public Works $1,873.56; Manager $2,135.12 Total $8,043.02 Ed made a motion to approve payment of the chargeback expenses. Dana seconded the motion. The motion passed unanimously.

Old Business

None

Goals

  1. Rick provided copies of the By-Laws but was unable to find a Mission Statement. Jack will check his files.
  2. Jack will submit an article for the next newsletter which is due 4/30/14.
  3. BOS Goal - Obtain PA DEP approval for the Act 537 Plan revision for the Reservoir Road Pump Station by Dec. 31. 2014. Ready to submit to the County. See Pennoni’s report for details.
  4. BOS Goal -Develop a recommendation on covers for the SBRs – August 1. 2014. A brief study will be ready for review at the May meeting.
  5. Respond to capacity request in 45 days or less: 211 Ellis Lane – 1 EDU existing house; 195 Wyllpen Place – 1 EDU existing house.
  6. Continue to implement I&I - Mark Miller has started the smoke testing.
  7. RCSTP was in compliance with NPDES permit January, February and March

New Business

  1. Bog Turtle Habitat Assessment was done by Conestoga-Rovers at the negotiated price of $3,150. Mike walked the area with them. Several wetlands near the plant contain habitat suitable to support bog turtles. An alternate access route will be to build a temporary bridge over the creek from Bow Tree. If we avoid these wetlands, then Phase 2 survey/Phase 3 trapping will likely not be required.

F:\Data\Shared Data\Minutes\Municipal Authority\2014\MA 4-21-14 draft.doc

2

  1. Portable Meters – Mark Miller requested approval to replace two of the portable flow meters. They have been used for 7 years and parts are no longer available. The quote from North East Technical Sales is $5,941 for two portable meters, which includes software and USB cables. Ed made a motion to approve the purchase of 2 portable meters for $5,941. Fran seconded the motion. The motion passed unanimously.

Capacity Requests

None

Sewer Reports

1. Mark Miller, Director of Public Works - March 2014 monthly report.
Meters: All meters were read on a daily basis. We pulled the portable meters. They were sent out for calibration.
C.C. Collection: We televised 2000 feet of pipe in Supplee Valley along the creek. We also repaired a dozen cleanout pipes that were damaged over the winter.
We visited all pump stations on a daily basis. We experienced a problem at the Hershey Mill Pump Station when the main controller malfunctioned. In order to keep the station operational, we had to operate the VFD’s in the bypass mode.
R.C. Collection: The Hunt Country pump station was visited on a routine basis with no problems to report.
R.C. Plant: We started pulling the wet well pumps out for routine maintenance. Two are completed and the final one will be pulled this week. Once they are done, we will begin to pull the SBR pumps.
Alarms: We responded to 27 alarms for the month of March.
PA One Calls: We received 78 PA One calls in March.
Ashbridge Force Main – Mark reported that on 3/16/14 the Police Department called to report water coming up thru Manley Road. When he arrived at the intersection of Manley Road and Pheasant Run Road, it was apparent that the 6” force main was broken. They called in a PA One call and began to saw cut the roadway. The roadway was 12” thick. They dug most of the day but were unable to locate the problem. They barricaded the area and came back on Monday. Pump trucks were brought in to pump and haul through the night. On Monday, they located the break and made repairs. The Force Main was put back in service at 2:30 pm.

2. Pennoni – Mike Ellis gave the following report for March:
RCSTP – Pennoni continues to provide operations assistance as needed. No operational issues were brought to our attention in March.
Reserve PS Elimination – The contractor has provided two of the required contract closeout documents including a letter from the geotechnical engineer confirming adequate backfill compaction within the detention basin berm and a final payment request. We have notified the contractor that they still need to provide as-built plans, written notification that they will return in the spring to remove the filter sock along the creek (or removal of the filter sock now that it is spring), contractor’s release, statement of surety, and maintenance bond confirmation before final payment can be made.

F:\Data\Shared Data\Minutes\Municipal Authority\2014\MA 4-21-14 draft.doc

3

Chapter 94 Annual Reports – We completed the reports for the Ridley Creek STP, West Goshen Service Area, and Westtown Service Area and submitted them to PADEP on March 26, 2014.

Reservoir Road Pump Station Act 537 Plan – We coordinated with Conestoga-Rovers & Associates (CRA) to perform the Phase 1 bog turtle habitat assessment, and we were on-site during the field assessment. CRA submitted a summary memo to the Township on March 20, 2014. CRA will also submit a report to the U.S. Fish & Wildlife Service (USFWS) and coordinate project requirements with them due to presence of bog turtle habitat in certain isolated areas within the project limits. We do not expect that a Phase 2 or Phase 3 bog turtle study will be needed.
Following the bog turtle habitat assessment, we revised the force main routing and construction access route to avoid bog turtle habitat and wetlands. The force main is now proposed to run around the perimeter of the pond in Bow Tree instead of through an existing sewer easement behind Achom Way. The construction access route to the connection point at the Ridley Creek Interceptor is now proposed to be around the Bow Tree pond and across the Ridley Creek with a temporary bridge (instead of accessing the site from the RCSTP). We anticipate one new sewer easement will be needed for this revised routing through a residential property on the north side of the Bow Tree pond.
We prepared plot plans for the revised routing including existing conditions from available topographic and parcel GIS data, Bow Tree Land Development Plans, and in-field wetlands and treeline observations (no field survey was performed). We completed the proposed plot plans for the currently proposed project extents.
We are completing the Act 537 Plan report, and we anticipate making submissions to the East Goshen Township Planning Commission, West Goshen Township Planning Commission, Chester County Planning Commission, Chester County Health Department, and West Goshen Sewage Treatment Plant operator by April 18, 2014.
As previously reported, the PA Department of Conservation and Natural Resources (DCNR) is requiring a field botanical survey of potential threats to four special concern plant species. We have prepared photo documentation of the revised force main routing, and we will be coordinating with the DCNR in an effort to eliminate this requirement. If a field botanical survey still ends up being required, it will likely need to be performed in May, during the spring growing season.

Tentative Act 537 planning schedule (assuming no botanical survey of Phase 2 bog turtle screening):

Estimated date
• Submit to County & Township Agencies April 18, 2014
• USFWS Bog Turtle Habitat Coordination June 18, 2014
• 60-day County and Township Review period June 18, 2014
• Revisions per Agency Comments June 25, 2014
• 30-day Public Comment Period July 28, 2014
• East Goshen & West Goshen Twp. Adoption August 8, 2014
• PADEP Review & Approval (120 days) December 15, 2014

Semi-Annual I/I Report – We analyzed portable and permanent meter data for the past six-month period, and we met with Rick Smith and Mark Miller to discuss the findings and recommendations for investigations and metering in the next six months. We also updated our Township-wide sewer mapping based upon the Township’s GPS-surveyed manhole locations. We completed and submitted the semi-annual report.

F:\Data\Shared Data\Minutes\Municipal Authority\2014\MA 4-21-14 draft.doc

4

New Sewer Connections – We reviewed additional sketch plan information for a new grinder pump and low pressure sewer lateral at 211 Ellis Lane, and we discussed the project scope and comments with the contractor. We also forwarded comments to the Township.
We received a design plan and report submission for a new private wastewater pump station for Acero Precision at 1340 Enterprise Drive, and the documents are currently under review.
Fairway Village Manhole Lining – We coordinated with a contractor to obtain a cost proposal and schedule for a demonstration installation of the SprayWall monolithic polyurethane interior manhole lining system to remedy deterioration within the former Reserve Pump Station force main discharge manhole. We forwarded a summary memo to the Municipal Authority for consideration.
RCSTP Tank Covers – The evaluation of flexible tank cover alternatives and preparation of a brief study report will be completed and submitted prior to the May Municipal Authority meeting.

3. Big Fish Environmental Services – The following is a summary of Scott’s report for March 2014:
Treatment Process Operation- During February 2014, there were no exceedances of the final effluent discharge limitations for Outfall 001 and Outfall 002.
The monthly average total phosphorus concentration was 0.31 mg/L as compared to the discharge limitation of 0.5 mg/L. During the month, the final effluent total phosphorus concentration discharged ranged from 0.11 mg/L to 0.50 mg/L.
There was no discharge to Applebrook, Outfall 002, during February or March 2014.
The influent wastewater pollutant concentrations and loading entering the wastewater treatment facility remained within the design concentrations and loadings. Composite samples are collected at the influent doghouse manhole and influent wet well. The influent flow meter reading is collected from the influent flow meter located prior to the Screening Building, excluding the internal recycle flows.
SBRs #1, 3 and 4 were in service during the month of February.
Process monitoring of each SBR included ammonia as N, Nitrite as N, Nitrate as N, COD, SSV, MLSS and total phosphorus. Foam concentrations remain reduced during the month of March. Increased sludge wasting was continued to maintain lower the MLSS concentrations. The slight increase in wastewater SBR temperatures has contributed to lowering the final effluent ammonia as nitrogen concentration during the last week of March. The effluent remains in compliance with the NPDES Permit discharge parameters.
Daily monitoring of the influent and final effluent 24-hour composites samples for total phosphorus is ongoing. Daily analysis of the final effluent flow equalization grab sample total phosphorus is ongoing. Sample collection and analysis of the influent wastewater collected at the influent pump station wet well is ongoing.
Addition of aluminum sulfate solution to the SBRs to assist with phosphorus removal continued. The volume of aluminum sulfate solution to the SBRs has remained consistent during March.
The addition of soda ash to the SBRs to assist with maintaining desired pH concentrations above 7.0 standard units continued during the month. Soda ash addition to the SBRs during March remained consistent around 273 pounds per day.
SBR #2 remains out of service as a treatment unit, however, partially filled with MLSS which is continuously mixed and aerated. The majority of the contents were transferred to the sludge holding tanks.

F:\Data\Shared Data\Minutes\Municipal Authority\2014\MA 4-21-14 draft.doc

5

The decanter for SBR 3 continued to be periodically observed as being slightly tilted within the water level. The effluent knife valve was routinely closed and the decanter filled with water to assist with lowering the decanter within the water level. The frequency of occurrence ranged from one to several occurrences during the month. The SBR is planned for removal from service during May for inspection.

Solids Dewatering and Disposal: March 2014
During the month, sludge wasting to the sludge holding tanks and decanting of the sludge holding tanks was ongoing. Process monitoring included pH, total alkalinity and total solids. Sludge holding tank #1 was in service. The level at the beginning of the month was 12.17 feet and the level at the end of the month was 12.91 feet. The initial total solids concentration was 0.81% and ended the month as 1.20% total solids. 340,465 gallons of supernatant were decanted during the month. A total of 350 pounds of soda ash were added during the month for pH adjustment.
Sludge holding tank #2 was in service. The level at the beginning of the month was 12.40 feet and the level at the end of the month was 5.37 feet. The initial total solids concentration was 0.98% and ended the month as 0.67% total solids. No supernatant was decanted during the month. A total of 1,200 pounds of soda ash were added during the month for pH adjustment.

Significant storm/hydraulic Loading Events – On Saturday and Sunday, March 29th and 30th, the area experienced continuous rainfall. The facility exceeded the average daily design flow of 0.750 MGD on Sunday, March 30th through recording an effluent flow of 0.795 MGD through outfall 001. The Effluent clarity remained good and compliance samples collected on April 1, 2013 are within permit discharge limitations.

Minor Repairs and Preventive Maintenance

  1. Replaced a ballast in UV bank #2
  2. Replaced the spider gear coupling for disc filter #1
  3. Removed containment tank wall from the soda ash feed tank area within the blower/laboratory building.
  4. Township staff installed influent pump #1. Pump was returned to service.
  5. Township staff removed influent pump #3 for inspection and seal replacement.

Any Other Matter

  1. In a letter dated April 16, 2014, Mike explained that the effort to prepare the Act 537 Plan Update report and plot plans has exceeded the budget of Phase 3 “Act 537 Plan Update” of the approved Act 537 Plan proposal due to the extra routing of the force main to the interceptor and unexpected regulatory agency coordination. The additional effort is expected to be approximately $7,500 to complete this phase of the project. They are requesting extra funding. Fran moved to increase the Phase 3 budget by $7,500. Dana seconded the motion. The motion passed unanimously.
  2. In a memo dated April 17, 2014 regarding SprayWall® Mike explained that the former discharge manhole of the Reserve Pump Station force main was found to have interior deterioration during the pump station diversion project. The manhole is located at the entrance to Fairway Village. They have coordinated with a contractor, Abel Recon, to obtain discounted pricing to rehabilitate the manhole interior with the proprietary SprayWall® a spray-on manhole coating system. Abel Recon is the only local contractor approved by the manufacturer to install this product. Abel Recon has proposed to perform the lining as a product demonstration for

F:\Data\Shared Data\Minutes\Municipal Authority\2014\MA 4-21-14 draft.doc

6

$2,500. This pricing is based upon the Township providing any required traffic control. Mike provided a sample of the lining. Ed moved to approve purchase of the StrayWall® product for $2,500. Dana seconded the motion. The motion passed unanimously.

Adjournment

There being no further business, Fran moved to adjourn the meeting. Kevin seconded the motion. The motion passed unanimously. The meeting was adjourned at 8:15 pm.

Respectfully submitted,

Ruth Kiefer
Recording Secretary

F:\Data\Shared Data\Minutes\Municipal Authority\2014\MA 4-21-14 draft.doc

7

Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 587993
Invoice Date : 04/23/2014
Project : EGMA1306
Project Name : Reserve PS Diversion Construction P

For Services Rendered through: 4/13/2014

Coordinated with contractor to obtain required contract closeout documents and reviewed remaining certified payrolls and geotechnical consultant's report of detention basin berm compaction acceptability.

Phase : **** -- Professional Services
Total Phase : **** -- Professional Services

Labor : 197.25
Expense : 0.00
Phase Total : 197.25

Amount Due This Invoice: $197.25

Fee : 20,000.00
Prior Billings : 14,240.50
Current Billings : 197.25
Total Billings : 14,437.75

Phase : **** -- Professional Services
Labor

Class Hours/
Units
Rate Amount
Senior Engineer 0.75 113.00 84.75
Graduate Engineer 1.50 75.00 112.50
Labor Total: 2.25 197.25
Total Phase : **** -- Professional Services Labor : $197.25
Expense : $0.00
Total Project : EGMA1306 -- Reserve PS Diversion Construction P Labor : $197.25
Expense : $0.00

ok RS 5/8/14

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority

EGMA1307 Invoice Summary

Invoice Date 04/23/2014

Description Amount Reference Date/Range
Project: EGMA1306
Pennoni Job No.: Reserve PS Diversion Construction P
Invoice No: 587993
Invoice Period: 1/13/2014 to 4/13/2014
Initial Authorization: $ 20,000.00 Date: 4/23/2014
Contract Amount: $ 20,000.00
Previously Invoiced: $ 14,240.50
Current Invoice: $ 197.25
Invoiced to Date ($): $ 14,437.75
Invoiced to Date (%): 72%
Remaining Budget ($): $ 5,562.25
Remaining Budget (%): 28%

Budget by Phase:

Phase Summary Amount
Phase Name: Reserve PS Diversion
Construction Phase
Phase Budget: $ 20,000.00
Previously Invoiced: $ 14,240.50
Current Invoice: $ 197.25
Invoiced to Date ($): $ 14,437.75
Invoiced to Date (%): 72%
Remaining Budget ($): $ 5,562.25
Remaining Budget (%): 28%

Comments: Coordinated with contractor to obtain required contract closeout documents and reviewed remaining certified payrolls and geotechnical consultant's report of detention basin berm compaction acceptability.

Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 587994
Invoice Date : 04/23/2014
Project : EGMA1307
Project Name : Reservoir Rd PS Act 537 Planning

For Services Rendered through: 4/13/2014

Coordinated revised fee with Conestoga-Rovers & Associates (CRA), the bog turtle consultant per Municipal Authority's recommendation; assisted and guided CRA on-site during in-field Phase 1 bog turtle habitat assessment; revised proposed force main routing and construction access to run to north side of Bow Tree pond and through cleared access path per bog turtle assessment including preparation of additional existing and proposed conditions plans from County and State GIS data, aerial images, subdivision plans, and observed (not surveyed) conditions; and continued preparation of Act 537 Plan narrative report.

Phase : 03 -- Act 537 Plan Update
Total Phase : 03 -- Act 537 Plan Update

Labor : 4,724.50
Expense : 0.00
Phase Total : 4,724.50

Amount Due This Invoice $4,724.50

Phase : 03 -- Act 537 Plan Update
Labor

Class Hours/
Units
Rate Amount
Authority Engineer 15.25 110.00 1,677.50
Project Engineer 1.00 95.00 95.00
Engineering Technician II 41.00 72.00 2,952.00
Labor Total: 57.25 4,724.50
Total Phase : 03 -- Act 537 Plan Update Labor : $4,724.50
Expense : $0.00
Total Project : EGMA1307 -- Reservoir Rd PS Act 537 Planning Labor : $4,724.50
Expense : $0.00

ok RS 5/8/14

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority

EGMA1307 Invoice Summary

Invoice Date 04/23/2014

Description Amount Reference Date/Range
Project: EGMA1307
Pennoni Job No.: Reservoir Rd PS Act 537 Planning
Invoice No: 587994
Invoice Period: 3/17/2014 to 4/13/2014
Initial Authorization: $ 77,400.00 Date: 4/23/2014
Contract Amount: $ 84,900.00
Previously Invoiced: $ 59,369.75
Current Invoice: $ 4,724.50
Invoiced to Date ($): $ 64,094.25
Invoiced to Date (%): 75%
Remaining Budget ($): $ 20,805.75
Remaining Budget (%): 25%

Budget by Phase:

Phase Summary Amount
Phase Name: Reservoir Rd PS Act
537 Planning
Phase Budget: $ 84,900.00
Previously Invoiced: $ 59,369.75
Current Invoice: $ 4,724.50
Invoiced to Date ($): $ 64,094.25
Invoiced to Date (%): 75%
Remaining Budget ($): $ 20,805.75
Remaining Budget (%): 25%

Comments: Coordinated revised fee with Conestoga-Rovers & Associates (CRA), the bog turtle consultant per Municipal Authority's recommendation; assisted and guided CRA on-site during in-field Phase 1 bog turtle habitat assessment; revised proposed force main routing and construction access to run to north side of Bow Tree pond and through cleared access path per bog turtle assessment including preparation of additional existing and proposed conditions plans from County and State GIS data, aerial images, subdivision plans, and observed (not surveyed) conditions; and continued preparation of Act 537 Plan narrative report.

Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 587995
Invoice Date : 04/23/2014
Project : EGMA1401
Project Name : 2014 General Services

For Services Rendered through: 4/13/2014

Researched alternatives for RCSTP flexible tank covers and discussed specifics of tank cover study deliverable memo with Twp Manager; coordinated with Abel Recon to obtain discounted pricing for SprayWall manhole lining demonstration for Fairway Village manhole; consultated with PW Director during Ashbridge force main leak detection and repair including field visit by M. McAloon; responded to inquiry from a consultant about industrial waste discharge requirements; coordinated with Township and consultant regarding process for Goshen Meadows manhole connection PADOT HOP application; and initiated update of Pennoni's Township-wide sewer mapping to use new GPS-located manhole locations.

Phase : **** -- Professional Services
Total Phase : **** -- Professional Services

Labor : 992.00
Expense : 0.00
Phase Total : 992.00

Amount Due This Invoice: $992.00

Fee : 10,300.00
Prior Billings : 2,821.25
Current Billings : 992.00
Total Billings : 3,813.25

Phase : **** -- Professional Services
Labor

Class Hours/
Units
Rate Amount
Authority Engineer 3.50 113.00 395.50
Project Engineer 0.50 95.00 47.50
Senior Engineering Technician 3.00 83.00 249.00
Engineering Technician II 4.00 75.00 300.00
Labor Total: 11.00 992.00
Total Phase : **** -- Professional Services Labor : $992.00
Expense : $0.00
Total Project : EGMA1401 -- 2014 General Services Labor : $992.00
Expense : $0.00

ok RS 5/8/14

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority

EGMA1401 Invoice Summary

Invoice Date 04/23/2014

Project: EGMA1401
Pennoni Job No.: 2014 General Services
Invoice No: 587995
Invoice Period: 3/17/2014 to 4/13/2014
Initial Authorization: $ 10,300.00 Date: 4/23/2014
Contract Amount: $ 10,300.00
Previously Invoiced: $ 2,821.25
Current Invoice: $ 992.00
Invoiced to Date ($): $ 3,813.25
Invoiced to Date (%): 37%
Remaining Budget ($): $ 6,486.75
Remaining Budget (%): 63%

Budget by Phase:

Phase Name: 2014 General Services
Phase Budget: $ 10,300.00
Previously Invoiced: $ 2,821.25
Current Invoice: $ 992.00
Invoiced to Date ($): $ 3,813.25
Invoiced to Date (%): 37%
Remaining Budget ($): $ 6,486.75
Remaining Budget (%): 63%

Comments: Researched alternatives for RCSTP flexible tank covers and discussed specifics of tank cover study deliverable memo with Twp Manager; coordinated with Abel Recon to obtain discounted pricing for SprayWall manhole lining demonstration for Fairway Village manhole; consultated with PW Director during Ashbridge force main leak detection and repair including field visit by M. McAloon; responded to inquiry from a consultant about industrial waste discharge requirements; coordinated with Township and consultant regarding process for Goshen Meadows manhole connection PADOT HOP application; and initiated update of Pennoni's Township-wide sewer mapping to use new GPS-located manhole locations.

[Logo: Pennoni]
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 587996
Invoice Date : 04/23/2014
Project : EGMA1402
Project Name : 2014 Semi-Annual I&I Reports

For Services Rendered through: 4/13/2014

Analyzed temporary and permanent meter data, prepared draft Semi-Annual I/I Report #11, and met with Twp Manager and PW Director to discuss findings and recommendations.

Phase : **** -- Professional Services

Total Phase : **** -- Professional Services Labor : 4,562.25
Expense : 0.00
Phase Total : 4,562.25
Amount Due This Invoice $4,562.25
Fee : 10,300.00
Prior Billings : 0.00
Current Billings : 4,562.25
Total Billings : 4,562.25

Phase : **** -- Professional Services
Labor

Class Hours/
Units
Rate Amount
Authority Engineer 12.00 113.00 1,356.00
Graduate Engineer 42.75 75.00 3,206.25
Labor Total: 54.75 4,562.25
Total Phase : **** -- Professional Services Labor : $4,562.25
Expense : $0.00
Total Project : EGMA1402 -- 2014 Semi-Annual I&I Reports Labor : $4,562.25
Expense : $0.00

[Handwritten: ok RS 5/8/14]

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority

EGMA1401 Invoice Summary

Invoice Date 04/23/2014

Project: EGMA1402
Pennoni Job No.: 2014 Semi-Annual I&I Reports
Invoice No: 587996
Invoice Period: 3/3/2014 to 4/13/2014
Initial Authorization: $ 10,300.00 Date: 4/23/2014
Contract Amount: $ 10,300.00
Previously Invoiced: $ -
Current Invoice: $ 4,562.25
Invoiced to Date ($): $ 4,562.25
Invoiced to Date (%): 44%
Remaining Budget ($): $ 5,737.75
Remaining Budget (%): 56%

Budget by Phase:

Phase Name: 2014 Semi-Annual I&I Reports
Phase Budget: $ 10,300.00
Previously Invoiced: $ -
Current Invoice: $ 4,562.25
Invoiced to Date ($): $ 4,562.25
Invoiced to Date (%): 44%
Remaining Budget ($): $ 5,737.75
Remaining Budget (%): 56%

Comments: Analyzed temporary and permanent meter data, prepared draft Semi-Annual I/I Report #11, and met with Twp Manager and PW Director to discuss findings and recommendations.

[Logo: Pennoni]
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 587997
Invoice Date : 04/23/2014
Project : EGMA1403
Project Name : 2013 Chapter 94 Reports

For Services Rendered through: 4/13/2014

FINAL INVOICE

Finalized and submitted Chapter 94 Reports to PADEP for Ridley Creek STP, West Goshen Service Area, and Westtown Service Area.

Phase : **** -- Professional Services

Total Phase : **** -- Professional Services Labor : 671.50
Expense : 0.00
Phase Total : 671.50
Amount Due This Invoice $644.25
Fee : 14,400.00
Prior Billings : 13,755.75
Current Billings : 644.25
Total Billings : 14,400.00

(Note: Contract Amt. is NTE)

Phase : **** -- Professional Services
Labor

Class Hours/
Units
Rate Amount
Authority Engineer 2.00 113.00 226.00
Senior Engineer 1.00 108.00 108.00
Graduate Engineer 4.50 75.00 337.50
Labor Total: 7.50 671.50
Total Phase : **** -- Professional Services Total Amount Billable This Invoice: $644.25

[Handwritten: ok RS 5/8/14]

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority

EGMA1403 Invoice Summary

Invoice Date 04/23/2014

Project: EGMA1403
Pennoni Job No.: 2013 Chapter 94 Reports
Invoice No: 587997
Invoice Period: 3/17/2014 to 4/13/2014
Initial Authorization: $ 14,400.00 Date: 4/23/2014
Contract Amount: $ 14,400.00
Previously Invoiced: $ 13,755.75
Current Invoice: $ 644.25
Invoiced to Date ($): $ 14,400.00
Invoiced to Date (%): 100%
Remaining Budget ($): $ -
Remaining Budget (%): 0%

Budget by Phase:

Phase Name: 2013 Chapter 94 Reports
Phase Budget: $ 14,400.00
Previously Invoiced: $ 13,755.75
Current Invoice: $ 644.25
Invoiced to Date ($): $ 14,400.00
Invoiced to Date (%): 100%
Remaining Budget ($): $ -
Remaining Budget (%): 0%

Comments: FINAL INVOICE

Finalized and submitted Chapter 94 Reports to PADEP for Ridley Creek STP, West Goshen Service Area, and Westtown Service Area.

Memo

To: Municipal Authority
From: Jon Altshul
Re: MA April Financial Reports
Date: May 5, 2014

The Municipal Authority recorded $133 in revenues and $15,677 in expenses in March, a difference of -$15,545. The expenses were from payments to Pennoni and Gawthrop Greenwood. The fund balance is now $1,598,005.

A complete list of all monthly expenses is provided.

EAST GOSHEN TOWNSHIP

1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
April 2014

Account Title Acct # Annual
Budget
Month To Date
Actual
Year To Date
Actual
MUNICIPAL AUTHORITY BEGINNING FUND BALANCE 1,613,549.48
RCSTP BUDGET
REVENUE
INTEREST EARNED - RCSTP EXPANSION 07341 1020 2,000.00 131.45 528.41
GRANT REVENUE 07392 0800 0.00 0.00 0.00
TOTAL REVENUE 2,000.00 131.45 528.41
EXPENSES
R.C.-CAP. PROJ.-ENGINEER 07424 7451 0.00 0.00 0.00
R.C. CAP EXPANSION GEN'L CONTRACTOR 07424 7452 0.00 0.00 0.00
R.C. CAP EXPANSION - ELECTRICAL 07424 7453 0.00 0.00 0.00
R.C. CAP EXP CONTINGENCY CAPITAL 07424 7454 0.00 0.00 0.00
R.C. CAP EXP CONTINGENCY ONGOING 07424 7455 0.00 0.00 0.00
R.C. CAP EXP ADDITIONAL CONTINGENCY 07424 7456 0.00 0.00 0.00
TRANSFER TO SEWER SINKING FUND 07492 0550 0.00 0.00 0.00
TRANSFER TO AUTHORITY CAP FUND 07492 0990 0.00 0.00 0.00
TOTAL EXPENSES 0.00 0.00 0.00
RCSTP NET RESULT 2,000.00 131.45 528.41

U:\bmccool\2014\Municipal Authority\2014 - 04 - Municipal Authority Report.xlsx      Page 1 of 3      05/05/14

EAST GOSHEN TOWNSHIP

1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
April 2014

Account Title Acct # Annual
Budget
Month To Date
Actual
Year To Date
Actual
OPERATING BUDGET
REVENUE
INTEREST EARNINGS 07341 1000 27.00 1.21 4.83
C.C. TAPPING FEES 07364 1100 124,000.00 0.00 20,000.00
R.C.TAPPING FEES 07364 1110 21,444.00 0.00 6,000.00
CONNECTION FEES - SEWER 07364 1130 0.00 0.00 845.64
MISCELLANEOUS REVENUE 07380 1000 0.00 0.00 423.36
TRANSFER FROM SEWER OPERATING 07392 0500 0.00 0.00 21,000.00
TOTAL REVENUE 145,471.00 1.21 48,273.83
EXPENSES
ADMINISTRATIVE WAGES 07424 1400 32,768.00 0.00 8,043.02
MISCELLANEOUS EXPENSE 07424 3000 4,000.00 0.00 1,450.00
MUNIC.AUTH.-AUDITING 07424 3110 10,800.00 0.00 0.00
ENGINEERING SERVICES 07424 3130 35,525.00 8,808.25 16,087.00
LEGAL SERVICES 07424 3140 7,000.00 960.00 2,460.00
M.C.-DVRFA-DEBT SERVICE 07471 1000 22,120.00 0.00 0.00
M.C.-DVRFA-INTEREST PAYMN 07472 1000 5,115.00 0.00 0.00
M.C.-DVRFA-INTEREST PAYMN 07472 1010 0.00 0.00 0.00
TOTAL EXPENSES 117,328.00 9,768.25 28,040.02
OPERATING NET RESULT 28,143.00 (9,767.04) 20,233.81

U:\bmccool\2014\Municipal Authority\2014 - 04 - Municipal Authority Report.xlsx      Page 2 of 3      05/05/14

EAST GOSHEN TOWNSHIP

1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
April 2014

Account Title Acct # Annual
Budget
Month To Date
Actual
Year To Date
Actual
CAPITAL BUDGET
REVENUE
LOAN PROCEEDS-SEWER PROJECT 07393 1001 0.00 0.00 0.00
TRANSFER FROM SEWER CAP RESERVE 07392 0900 0.00 0.00 0.00
TOTAL REVENUE 0.00 0.00 0.00
EXPENSES
MARYDELL PUMP STATION - ENGINEER 07425 1000 0.00 0.00 0.00
MARYDELL PUMP STATION -CONSTRUCTION 07425 2000 0.00 0.00 0.00
MANHOLE COVER REPLACEMENTS 07424.7405 0.00 0.00 0.00
C.C. CAPITAL - COLLECTION 07424.7420 0.00 0.00 0.00
LOCHWOOD ABANDONMENT ENGINEER 07424 7475 0.00 0.00 0.00
LOCHWOOD ABANDONMENT CONSTRUCTION 07424 7476 0.00 0.00 0.00
LOCHWOOD ELIMINATION PHASE 2 07424 7477 0.00 0.00 0.00
HERSHEY MILL STATION - ENGINEER 07426 1000 0.00 0.00 0.00
HERSHEY MILL STATION - CONSTRUCTION 07426 2000 0.00 0.00 0.00
RESERVE PUMP STATION - ENGINEER 07427 1000 0.00 0.00 0.00
RESERVE PUMP STATION - CONSTRUCTION 07427 2000 0.00 0.00 0.00
RESERVOIR PUMP STATION - ENGINEER 07428 1000 75,000.00 5,909.00 21,027.75
RESERVOIR PUMP STATION CONSTRUCTION 07428 2000 0.00 0.00 0.00
TOTAL EXPENSES 75,000.00 5,909.00 21,027.75
CAPITAL NET RESULT (75,000.00) (5,909.00) (21,027.75)
MUNICIPAL AUTHORITY ENDING FUND BALANCE 1,598,004.89

U:\bmccool\2014\Municipal Authority\2014 - 04 - Municipal Authority Report.xlsx      Page 3 of 3      05/05/14

East Goshen Township General Ledger
Report Date 05/05/14 GL Transaction Details PAGE 1
MGRP18 run by BRIAN 12 : 52 PM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
07341-1000 INTEREST EARNINGS 0.00
1401 JE 41027 0.58 02/04/14 INTEREST INTEREST EARNED JANUARY 2014
07 FUND
0.00 0.58 -0.58
1402 41391 1.33 03/04/14 INTEREST INTEREST EARNED FEBRUARY 2014
07100.1000
0.00 1.33 -1.91
1403 41840 1.71 04/01/14 INTEREST INTEREST EARNED MARCH 2014
07 FUND
0.00 1.71 -3.62
1404 42321 1.21 05/02/14 INTEREST INTEREST EARNED APRIL 2014
07100.1000
0.00 1.21 -4.83
0.00 4.83 -4.83
07341-1020 INTEREST EARNED - RCSTP EXPANSION 0.00
1401 41028 137.33 02/04/14 INTEREST INTEREST EARNED JANUARY 2014
07 CONSTRUCTION FUND
0.00 137.33 -137.33
1402 41392 123.56 03/04/14 INTEREST INTEREST EARNED FEBRUARY 2014
07 CONSTRUCTION FUND
0.00 123.56 -260.89
1403 41841 136.07 04/01/14 INTEREST INTEREST EARNED MARCH 2014
07 CONSTRUCTION FUND
0.00 136.07 -396.96
1404 42322 131.45 05/02/14 INTEREST INTEREST EARNED APRIL 2014
CONSTRUCT.FUNDS
0.00 131.45 -528.41
0.00 528.41 -528.41
07364-1100 C.C. TAPPING FEES 0.00
1401 CR 40976 12,600.00 01/31/14 3034 8069 1 GOSHEN MEADOWS INVESTORS L.P.
0.00 12,600.00 -12,600.00
1402 41258 5,400.00 02/24/14 3553 8069 1 GOSHEN MEADOWS INVESTORS L.P.
RE 41263 2,000.00 02/24/14 41263 1 TAP IN FEE - 211 ELLIS LANE
0.00 7,400.00 -20,000.00
0.00 20,000.00 -20,000.00

East Goshen Township General Ledger

Report Date 05/05/14 | GL Transaction Details | PAGE 2
MGRP18 run by BRIAN | 12 : 52 PM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
07364-11100.00R.C.TAPPING FEES
412802,000.0002/25/1441280 1TAP IN FEE-903 SORELL HILL LT2
0.002,000.00-2,000.00
1403415532,000.0003/13/1441553 1TAP IN FEE FOR 909 SORRELL LT4
416082,000.0003/17/1441608 1TAP IN FEE-905 SORRELL LOT 3
0.004,000.00-6,000.00
0.006,000.00-6,000.00
07364-11300.00CONNECTION FEES - SEWER
1402CR41044423.0002/04/143508035 1JACOBS, ROBERT & CHERYL
41124423.0002/14/147748033 1GEORGE SMITH & CHRISTINA CONLE
JE41045141.1202/04/14PINE ROCKANNUAL PINE ROCK INSTALLMENT
41125141.1202/14/14PINE ROCKANNUAL PINE ROCK INSTALLMENT
282.24846.00-563.76
1403CR41402423.0003/04/1423078034 1STOFFLET, MICHAEL
JE41407141.1203/04/14PINE ROCKANNUAL PINE ROCK INSTALLMENT
141.12423.00-845.64
423.361,269.00-845.64
07380-10000.00MISCELLANEOUS REVENUE
140241045141.1202/04/14PINE ROCKANNUAL PINE ROCK INSTALLMENT
41125141.1202/14/14PINE ROCKANNUAL PINE ROCK INSTALLMENT
0.00282.24-282.24
140341407141.1203/04/14PINE ROCKANNUAL PINE ROCK INSTALLMENT
0.00141.12-423.36
0.00423.36-423.36
07392-05000.00TRANSFER FROM SEWER OPERATING
1401406741,000.0001/08/14DEPOSITDEPOSIT $ INTO MA GENERAL FROM 05 FUND
4074720,000.0001/14/14XFERXFER $ FROM SEWER TO MA TO COVER EXPENSES
0.0021,000.00-21,000.00
0.0021,000.00-21,000.00
07424-14000.00ADMINISTRATIVE WAGES
1403CD418158,043.0203/31/142237425EAST GOSHEN TOWNSHIP - GENERAL 1ST QTR.2014 MUN.AUTH. REIMBURSM
8,043.020.008,043.02

East Goshen Township General Ledger
Report Date 05/05/14 GL Transaction Details PAGE 3
MGRP18 run by BRIAN 12 : 52 PM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
8,043.02 0.00 8,043.02
07424-3000 MISCELLANEOUS EXPENSE 0.00
1401 40597 500.00 01/06/14 2228 2737 DEP - COMMONWEALTH OF PA
NPDES PERMITS - CHAPTER 92A 2014
950.00 01/06/14 2229 2132 PENNSYLVANIA MUNICIPAL AUTHORITIES ASSOC
2014 ACTIVE MEMBERSHIP DUES
*** 1,450.00 0.00 ***
1,450.00 0.00 1,450.00
1,450.00 0.00 1,450.00
07424-3130 ENGINEERING SERVICES 0.00
40653 -663.75 01/06/14 2224 1052 PENNONI ASSOCIATES INC.
VOID CK. DUE TO PRINTER PROBLEM
40743 663.75 01/14/14 2230 1052 PENNONI ASSOCIATES INC.
SERVICES THRU 12/8/13 GENERAL S
JE 40746 1,845.00 01/14/14 REFUND PENNONI REFUND DUE TO
DUPLICATE PAYMENT
0.00 1,845.00 -1,845.00
1402 CD 41103 2,236.50 02/11/14 2233 1052 PENNONI ASSOCIATES INC.
SERVICES THROUGH 1/12/14 GEN.SER
2,236.50 0.00 391.50
1403 41540 6,887.25 03/12/14 2236 1052 PENNONI ASSOCIATES INC.
SERVICES THRU 2/9/14 2013 CHAP.
6,887.25 0.00 7,278.75
1404 42153 8,808.25 04/23/14 2239 1052 PENNONI ASSOCIATES INC.
SERVICES THRU 3/16/14 CHAP.94 RE
8,808.25 0.00 16,087.00
17,932.00 1,845.00 16,087.00
07424-3140 LEGAL SERVICES 0.00
1402 41310 800.00 02/27/14 2234 528 GAWTHROP GREENWOOD & HALSTED
LEGAL SERVICES - NOV.2013 GEN.AU
800.00 0.00 800.00
1403 41540 700.00 03/12/14 2235 528 GAWTHROP GREENWOOD & HALSTED
LEGAL SERVICE - FEB.2014 GEN.AUT
700.00 0.00 1,500.00
1404 42074 960.00 04/16/14 2238 528 GAWTHROP GREENWOOD & HALSTED
LEGAL SERVICE - MARCH 2014 GEN.A
960.00 0.00 2,460.00

East Goshen Township General Ledger
Report Date 05/05/14 GL Transaction Details PAGE 4
MGRP18 run by BRIAN 12 : 52 PM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
2,460.00 0.00 2,460.00
07424-7460 LOCHWOOD - CAPITAL -STP 0.00
1401 40739 1,290.00 01/14/14 10012 2695 BRICKHOUSE ENVIRONMENTAL
LOCHWOOD CHASE PROJECT - DEC.201
40744 -1,290.00 01/14/14 10012 2695 BRICKHOUSE ENVIRONMENTAL
VOID CK. - INCORRECT CASH ACCT.U
40745 1,290.00 01/14/14 2231 2695 BRICKHOUSE ENVIRONMENTAL
LOCHWOOD CHASE PROJECT - DEC. 20
JE 40820 1,290.00 01/22/14 DEPOSIT DEPOSIT TO REIMBURSE 07 MA
FOR 05 EXPENSE
1,290.00 1,290.00 0.00
1,290.00 1,290.00 0.00
07428-1000 RESERVOIR PUMP STATION - ENGINEER 0.00
1402 CD 41107 10,687.50 02/11/14 10013 1052 PENNONI ASSOCIATES INC.
SERV.THROUGH 1/12/14 RESERVE PS
10,687.50 0.00 10,687.50
1403 41541 4,431.25 03/12/14 10014 1052 PENNONI ASSOCIATES INC.
SERV.THRU 2/9/14 RESERV.RD. PS
4,431.25 0.00 15,118.75
1404 42154 5,909.00 04/23/14 10015 1052 PENNONI ASSOCIATES INC.
SERVICES THRU 3/16/14 RESERV.RD
5,909.00 0.00 21,027.75
21,027.75 0.00 21,027.75
Beg Bal 0.00 52,626.13 52,360.60 265.529999971

[Handwritten: 8A]

MUNICIPAL AUTHORITY MISSION STATEMENT:

DRAFT 5/8/14

The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or lease, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.

F:\Data\Shared Data\ABC'S\Municipal Authority\By-Laws & Mission\Mission Statement Draft 050814.doc

[Handwritten: 8d.]

[Logo: Pennoni]
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

MEMORANDUM

TO: Rick Smith
Mark Miller
East Goshen Municipal Authority
FROM: Michael J. Ellis, P.E.
DATE: May 9, 2014
SUBJECT: ODOR CONTROL ALTERNATIVES – COVERS AND MISTERS
UPDATE #1
RIDLEY CREEK SEWAGE TREATMENT PLANT

An evaluation of odor control alternatives and tank covers was briefly discussed at the January 13th Municipal Authority meeting. It is our understanding that there have been no odor complaints, but the Authority is interested in proactively evaluating the feasibility and cost of odor control alternatives for planning purposes.

We researched multiple alternatives and prepared a rough cost analysis for a few common odor control solutions.

The two most common methods of odor control are tank covers and chemical misters.

1. Covers – There are several different types of covers:

  • Solid, fixed cover Fiberglass reinforced plastic (FRP) covers were included as an alternative bid item in the RCSTP Upgrade and Expansion in 2008. Covers were included for the SBR tanks, post equalization tanks, and sludge digestion tanks. The bids ranged from $750,000 to $810,000 for the covers.; The expected cost for a new bid project would likely be over $1,000,000 due to price increases and bidding expenses, since it would be a stand-alone project (no cost savings as would be expected by including it in the overall plant expansion contract).; Additional considerations that would need to be evaluated during the design of tank covers that could add cost include: New structural support members on the walkways Addition of carbon columns and fans to the interior to control a resultant musty odor.; New structural support members on the walkways; Addition of carbon columns and fans to the interior to control a resultant musty odor.
  • Flexible cover, such as fabric, geo-membrane, or tarps – The cover would need to be able to handle/shed a rain and snow load so some additional supports are needed. Carbon columns and fans may be needed. Flexible covers generally are inflatable, arch/frame supported, or floating (see below). Flexible covers are expected to be less expensive than solid, fixed covers. Specific alternatives include but are not limited to:

EGMA1307      May 9, 2014      Page 2 of 2
East Goshen Municipal Authority      RCSTP Odor Control Alternatives

  • SBR tank covers by Geomembrane Technologies Inc. (GTI) GTI's structurally supported cover system consists of a retractable fabric cover tensioned over a series of low profile aluminum arches. The covers are typically used at wastewater treatment plants to capture odorous off gas for removal and treatment. Water treatment plants use the covers for blocking sunlight to control algae growth and chlorine usage/disinfection byproduct formation. The cover fabric is strong and durable, and can be quickly disconnected and easily retracted to access tank internals for maintenance or inspection. Rainwater can drain off the cover. Estimated costs for acquisition and installation would be about $350,000 to cover the SBR tanks only. GTI's cover system cannot be used on the circular post equalization and sludge digestion tanks due the arch design. A separate cover would therefore need to be used on those tanks if the GTI cover was used on the SBR tanks.
  • Environetics, Inc. offers the custom manufactured Defender Tank Cover. The cover is composed of heavy duty reinforced geomembrane materials combined with clear span structural aluminum frames, and stainless steel hardware that provide a durable, maintenance free service life. Its opaque, light blocking, characteristics virtually eliminate UV light from the tanks for effective algae control. Access hatch and atmospheric vent options are available. It is our understanding that the covers can be provided on all tanks at the plant since they are custom-made. We are awaiting confirmation and pricing from the vendor.
  • Other alternatives to be added.
  • Floating cover – Cover can be solid, flexible, or balls. Although floating covers are the least expensive alternative, they are not recommended because they can potentially cause a conflict with the decanter and backwash valves, may require additional baffles be added to prevent conflicts with existing equipment, and restrict visibility of the water surface. The Armor Ball cover could be acquired and installed in a quantity to cover all the tanks for approximately $30,000. The balls float on the water surface covering approximately 91% of the surface area.; Environetics, Inc. also offers a floating style cover comprised of buoyant modules filled with thermal insulation to cover the entire tank surface. We are awaiting further information and pricing from the vendor.

2. Misters – There are two general types of misters: odor neutralizing (removes odor) and odor masking (masks odor like a scented air freshener).

  • Specific locations, typically around the site perimeter, would need to be determined.
  • The lower initial capital cost compared to covers is offset by the continuous chemical supply costs required for normal operation.
  • Misters may not be as effective at odor control as covers.

END OF MEMO

W:\PROJECTS\EGMA\EGMA1401-2014 General Services\RCSTP Tank Covers\Tank Covers MEMO Rev 5-9-14 DRAFT.docx      LM03 10/2005

[Logo: Pennoni]
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

May 8, 2014

EGMA1307

Jack Yahraes, Chairman
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380

Re: Minor Act 537 Plan Update Revision
Reservoir Road Pump Station
East Goshen Township, Chester County, PA

Dear Mr. Yahraes:

On behalf of the East Goshen Municipal Authority, we have prepared the attached Update Revision to East Goshen Township's Act 537 Sewage Facilities Management Plan for the Reservoir Road Pump Station. The Municipal Authority is required to sign Section K of the Update Revision to certify that the proposed diversion will not cause any system overloads. We have attached the two (2) respective pages from the Update Revision for your signature. Please sign and return the pages to me by July 9, 2014.

Executive Summary

The Act 537 Plan Update Revision proposes the construction of the Reservoir Road Pump Station to divert approximately 300,000 gallons per day (gpd) of existing residential and commercial wastewater flow from East Goshen's existing Chester Creek Collection System (CCCS) to East Goshen's existing Ridley Creek Sewage Treatment Plant (RCSTP). Wastewater in the CCCS is currently conveyed to the West Goshen Sewage Treatment Plant (WGSTP). The current intermunicipal agreement between East Goshen and West Goshen limits East Goshen's capacity to 1,000,000 gpd. East Goshen's 2007 Township Wastewater Needs Evaluation projected that potential future development would increase the flow through the CCCS to almost 1,300,000 gpd. The projected flow increase exceeds both the intermunicipal agreement flow limitation and the available treatment capacity of the WGSTP. The Township Wastewater Needs Evaluation considered several alternatives to meet East Goshen's future wastewater needs, and the recommended alternative was to expand and upgrade the RCSTP from 400,000 gpd to 750,000 gpd and maintain 1,000,000 gpd capacity at West Goshen by constructing several sewer diversions. As of fall 2013, the RCSTP had been expanded and four of five sewer diversions had been constructed. The proposed Reservoir Road Pump Station is the only remaining diversion and is the final component in the implementation of the selected alternative from the Township Wastewater Needs Evaluation.

This proposed increase in flow to the RCSTP was included in the design of the plant's recent capacity upgrade. The project is anticipated to increase the operating efficiency and improve the function of the RCSTP due to the increased hydraulic and organic loadings, decrease the cost for conveyance and treatment of flows sent to West Goshen Township, decrease East Goshen's

Christiana Executive Campus • 121 Continental Drive, Suite 207 • Newark, DE 19713 • Tel: 302-655-4451 • Fax: 302-654-2895
www.pennoni.com

3800-FM-BPNPSM0353m 1/2013
Form

9. ADDITIONAL REQUIREMENTS FOR PENNVEST PROJECTS:

[ ] A copy of the additional information is attached. If PENNVEST funding is to be sought for the project, address these additional items in terms of any project impacts and measures to avoid or mitigate same.

  • Cost Effectiveness
  • Air quality
  • Floodplains
  • Wild and scenic rivers
  • Coastal zone management
  • Socio-economic impacts
  • Water supplies
  • Other environmentally sensitive areas

J. ALTERNATIVE SEWAGE FACILITIES ANALYSIS (See Section J of instructions)

[X] An alternative sewage facilities analysis has been prepared as described in Section J of the instructions and is attached.

The applicant may choose to include additional information beyond that required by Section J of the instructions.

K. CHAPTER 94 CONSISTENCY DETERMINATION (See Section K of instructions)

[X] Projects that propose the use of existing municipal collection, conveyance or wastewater treatment facilities, or the construction of collection and conveyance facilities to be served by existing municipal wastewater treatment facilities must be consistent with the requirements of Chapter 94 of DEP's rules and regulations (relating to Municipal Wasteload Management). If more than one municipality or authority will be affected by the project, please obtain the information required in this section for each. Additional sheets may be attached for this purpose.

1. Project Flows 300,000 gpd

2. Total Sewage Flows to Facilities

  1. Enter average and peak sewage flows for each proposed or existing facility as designed or permitted.
  2. Enter the present average and peak sewage flows for the critical sections of existing facilities.
  3. Enter the average and peak sewage flows projected for 5 years through the critical sections of existing facilities which includes existing, proposed, or future projects.

To complete the table, refer to Section K of instructions.

a. Design and/or Permitted
Capacity (gpd)
b. Present Flows (gpd) c. Projected Flows in
5 years (gpd)
Average Peak Average Peak Average Peak
Collection 717,902 717,902 30,525 101,954 30,525 101,954
Conveyance 1,903,769 1,903,769 363,835 1,215,209 667,660 1,795,034
Treatment 750,000 3,000,000 384,000 1,280,850 687,825 1,860,675

3. Collection and Conveyance Facilities

The questions below are to be answered by the sewer authority, municipality, or agency responsible for completing the Chapter 94 report for the collection and conveyance facilities. These questions should be answered in coordination with the latest Chapter 94 annual report and the above table.

This project proposes sewer extensions or tap-ins. Will these actions create a hydraulic overload within five years on any existing collection or conveyance facilities that are part of the system?      [ ] Yes    [X] No

a. If yes, this sewage facilities planning module will not be accepted for review by the municipality, delegated local agency and/or DEP until all inconsistencies with Chapter 94 are resolved or unless there is an approved plan and schedule granting an allocation for this project. A letter granting allocations to this project under the plan and schedule must be attached to the module package.

- 6 -

3800-FM-BPNPSM0353m 1/2013
Form

b. If no, the sewer authority, municipality, or agency responsible for completing the Chapter 94 report for the collection and conveyance facilities must sign below to indicate that the collection and conveyance facilities have adequate capacity and are able to provide service to the proposed development in accordance with Chapter 94 requirements and that this proposal will not affect this status.

c. Collection System
Name of Agency, Authority, Municipality: East Goshen Municipal Authority
Name of Responsible Agent: Jack E. Yahraes, Chairman
Agent Signature: ________________________________________
Date: ________________________________________

d. Conveyance System
Name of Agency, Authority, Municipality: East Goshen Municipal Authority
Name of Responsible Agent: Jack E. Yahraes, Chairman
Agent Signature: ________________________________________
Date: ________________________________________

K. CHAPTER 94 CONSISTENCY DETERMINATION (continued)

4. Treatment Facility

The questions below are to be answered by the facility permittee in coordination with the information in the table and the latest Chapter 94 report.

This project proposes the use of an existing wastewater treatment plant for the disposal of sewage. Will this action create a hydraulic or organic overload within 5 years at that facility?      [ ] Yes    [X] No

a. If yes, this planning module for sewage facilities will not be reviewed by the municipality, delegated local agency and/or DEP until this inconsistency with Chapter 94 is resolved or unless there is an approved plan and schedule granting an allocation for this project. A letter granting allocations to this project under the plan and schedule must be attached to the planning module.

b. If no, the treatment facility permittee must sign below to indicate that this facility has adequate treatment capacity and is able to provide wastewater treatment services for the proposed development in accordance with Chapter 94 requirements and that this proposal will not impact this status

c. Name of Agency, Authority, Municipality: East Goshen Municipal Authority
Name of Responsible Agent: Jack E. Yahraes, Chairman
Agent Signature: ________________________________________
Date: ________________________________________

L. INSTITUTIONAL EVALUATION (See Section L of instructions)

[X] An institutional evaluation is attached. Identify the entity which will design, obtain necessary permits, construct, own and operate the proposed facilities. If a low pressure vacuum or effluent sewer are proposed, discuss purchase, installation, operation and maintenance responsibilities for the individual pumping, valves, tanks, etc.

- 7 -

[Handwritten note in red ink: ANY OTHER MATTER]

[Logo: Pennoni]
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

MEMORANDUM

TO: Rick Smith
East Goshen Municipal Authority
CC: Mark Miller
Ronald Smith Inc.
FROM: Michael J. Ellis, P.E. [Signature: MJE] [Handwritten: ok RS 5-9-14]
DATE: May 9, 2014
SUBJECT: RECOMMENDATION FOR PAYMENT #3 (FINAL)
RESERVE PUMP STATION SANITARY SEWER DIVERSION

We recommend the Municipal Authority conditionally approve Payment #3 (Final) to Ronald Smith Inc. for the subject project in the amount of $7,316.82 at their May 12th meeting. The recommended condition is that payment not be physically made until the contractor addresses the following items to the satisfaction of the Authority Engineer, Township Manager, and Township PW Director:

Outstanding Items

  1. Remove the filter sock along the creek.
  2. Restore the constructed lawn area at the former location of the pump station building and driveway. Grass is not growing in well, and the soil is rocky. Additional topsoil and seed is expected to be needed.
  3. Submit a corrected Application and Certification form for Payment #3 (Final). We've marked up the submitted application with required revisions and have attached it for your reference.
  4. As-built plans have been submitted by the contractor directly to the Township. Pennoni needs to review the plans to confirm they are acceptable. I intend to perform the review prior to the May 12 th Municipal Authority meeting.

We have reviewed the following attached contract closeout documents and have found them acceptable:

  • Daily Field Report from Earth Engineering Inc. certifying the backfill compaction within the detention basin berm
  • Contractor's Release
  • Consent of Surety to Final Payment
  • Contract Bond (including the Maintenance Bond)
  • Payroll Certifications #1-7 for Ronald Smith Inc.

The Maintenance Bond was provided with the original contract bond at the beginning of the project. As stated in the Maintenance Bond, the 2-year guarantee period shall begin on the date of acceptance of the work. The date of acceptance shall be considered November 6, 2013, which is the date that Pennoni certified Payment Application #2, at which point the project was substantially complete.

END OF MEMO

P:\Projects\EGMA\EGMA1306-Reserve PS Diversion Construction\DOCUMENTS\Payments\Payment #3 (Final) Memo 5-9-14.docx      LM03 10/2005