Municipal Authority
The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.
The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.
- Five members, serving five-year terms
- Meetings are on the 2nd Monday of the month at 7:00 P.M.
- All township meetings are held at the Township Building and open to the public
| Authority Members | Term Expiration Date |
| Kevin Cummings, Chairman | 2026 |
| John Stipe, Vice Chairman |
2029 |
| Dana Pizzarro, Secretary | 2026 |
| Sean Ellsworth, Assistant Secretary/Treasurer | 2028 |
| Walter Wujcik, Treasurer | 2028 |
| Pennoni Associates, Engineer | |
| Patrick M. McKenna, Esq. | |
| Peter Hicks, BoS Liaison | |
| Kevin Miller, Staff Liaison |
Documents
Back to the list | Open the original PDF
Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.
EAST GOSHEN MUNICIPAL AUTHORITY
May 10, 2010
Monday, 7:00 PM
- CALL TO ORDER/PLEDGE OF ALLEGIANCE Ask if anyone will be taping the meeting?
- RIDLEY CREEK REPORTS Brickhouse Environmental -; Pennoni –; Costs Summary; Change Orders; Worth & Company, Inc.,; Tank Cleaning Bid
- RIDLEY CREEK INVOICES a. Grainger, #9217937037, 3/31/10 $ 275.50 b. Grainger, #9228782778, 4/14/10 $ 641.98 c. Grainger, #9231297822, 4/16/10 $ 28.58 d. Continental Fire & Safety, #37184, 4/15/10 $ 1,127.48 e. Brickhouse Environmental, #5333, 5/3/10 $ 11,931.25 f. Worth and Co., #P28001, 4/30/10 $170,263.75 g. Wm. H. Clinger Corp., #EGMA0707, 5/2/10 $ 34,539.38 h. Pennoni, #438249, 5/5/10 $ 18,810.50
- CHAIRMAN’S REPORT/OTHER MEMBERS REPORTS
- APPROVAL OF MINUTES April 12, 2010
- ENGINEER’S REPORT Pennoni report
- APPROVAL OF INVOICES a. Gawthrop Greenwood, #78561, 3/31/10 $ 627.00 b. Gawthrop Greenwood, #78562, 3/31/10 $ 304.00 c. Pennoni, #438211, 5/3/10 $ 315.00 d. Pennoni, #438212, 5/3/10 $ 367.50
- LIAISON REPORTS
- FINANCIAL REPORTS
- GOALS
- OLD BUSINESS 2010 Budget; Tank Cleaning Bid
- NEW BUSINESS Budget – request to adopt the 2010 budget; Applebrook Spray Permit
- CAPACITY REQUESTS
- SEWER REPORTS
Monday, May 10, 2010
- 1 -
- Director of Public Works Report – April 2010
- East Goshen Township Flows for February 2010
- Artesian Lockwood Chase Reports
- Artesian Ridley Creek Report
- ANY OTHER MATTER
- CORRESPONDENCE AND REPORTS OF INTEREST E-mail for Residents Bob & Kelley Fish
- PUBLIC COMMENT
- ADJOURNMENT
Reminder – NEWSLETTER ARTICLE SUBMISSION DUE DATES:
| Article Due Date | Delivery date |
|---|---|
| May 12, 2010 | July 1, 2010 |
| August 11, 2010 | October 1, 2010 |
| November 10, 2010 | January 1, 2011 |
Monday, May 10, 2010
- 2 -
2. RIDLEY CREEK REPORTS
a.
2 pgs
[Logo: Brickhouse Environmental]
Brickhouse Environmental
Project Accomplishments
B E Project No. 09-2532-0
East Goshen / Ridley Creek Sewage Treatment Plant Upgrade / Expansion
April 2010
The following Project Management tasks were performed for the Ridley Creek Wastewater Treatment Plant Expansion project:
- 4-1-10 Prepare for and attend the biweekly Progress Meeting.
- 4-1-10 Review contractor’s payment requests for February.
- 4-1-10 Site visit and discussions with construction inspector.
- 4-5-10 Site visit observations of SBR filling, conduit being set along SBR stairs, Treatment building louver perimeters being sealed, screen building tinted sticco coat being applied.
- 4-6-10 Attend Special Meeting with EGTMA representatives to discuss Worth & Company’s request for time extension beyond June 30, 2010.
- 4-7-10 Project review and email exchanges. Preparation and distribution of draft response letters to Worth’s request for time extension and Clinger’s March 15, 2010 letter claiming outstanding issues.
- 4-8-10 Preparation of Project Manager’s report for February 2010.
- 4-9-10 Site visit observations of correction of blower piping to incorporate 45 degree fittings rather than the 90 degree design to avoid louvered interference.
- 4-12-10 Prepare for and attend Authority Meeting, including Executive Session. Site visit to confirm progress and confer with construction inspector.
- 4-14-10 Attend and participate in the wet start up of Siemen’s Jet Tech SBRs using treated effluent of existing plant.
- 4-15-10 Prepare for and attend biweekly Progress Meeting.
- 4-16-10 Site visit to observe progress in wet testing and construction progress.
- 4-19-10 Site visit to observe progress in wet testing and construction progress.
- 4-20-10 Site visit to observe progress in wet testing and construction progress.
2 of 2
[Logo: Brickhouse Environmental]
Brickhouse Environmental
- 4-21-10 Review Clinger’s March 15, 2010 letter and attachments, contract bid design drawings. Began preparing a draft preliminary evaluation of the elements of Clinger’s letter on a point by point basis.
- 4-22-10 Site visit and meeting to discuss wet test status and resolution to overload relay failure for SBR #3.
- 4-22-10 Finish draft preliminary evaluation of the elements of Clinger’s March 15 th letter on a point by point basis.
- 4-23-10 Prepared for and attended a Special Meeting for the EGTMA with the Solicitor and Engineer to discuss the Clinger March 15 th letter. The draft preliminary evaluation of the elements of that letter was distributed and points discussed.
- 4-23-10 Site visit in response to appearance of PADEP’s Water Quality Specialist (Dave Wolfinger) and PADEP’s Permitting (Dave Tally) at the site for a routine inspection.
- 4-26-10 Site visit to monitor programming of new SBR autodailer, SBR #3 overload relay replacement status and wet test progress.
- 4-26-10 Prepare and distribute an email to Clinger’s Bob Dina regarding the status of SBR #3 overload relay.
- 4-27-30 Site visit for simulation of power failures regarding any adverse affects on the SBR equipment and various units. Identified power failure issues with the Aqua Aerobic disc filter control panel and Siemens UV control panel.
- 4-29-10 Prepare for and attend biweekly Progress Meeting held at the site.
- 4-30-10 Site visit observations of effluent collection box weir lowered 6” at the direction of the design Engineer to alleviate effluent flowing over the UV racks rather than confined to the disinfection zone.
Note: As of April 30, 2010 the cumulative project management hours budgeted was 1,234. The actual cumulative hours were 893.
J:\092532.0\April 2010 Bullets.doc
2. BRICKHOUSE
a
7 pgs
Project Manager’s April 2010 Report
Executive Summary
Phase I of the Ridley Creek Sewage Treatment Plant (RCSTP) upgrade and expansion project has largely been completed as of May 5, 2010. There are a few equipment issues from phase I which need to be resolved that will carry over into phase II. These issues were not believed to significant enough discontinue moving forward with the remaining phases.
During the month of April, final preparations were completed to allow the SBRs to be filled with treated effluent from the existing treatment plant to simulate the treatment process. Using several electric pumps, treated effluent was transferred from the effluent overflow box into the dog house manhole where it flowed by gravity through the Screen Building into the influent lift station. The influent lift station pumped the water into one of the four (4) SBRs. The SBRs cycled through all of the treatment cycles in the same manner as if they contained mixed liquor suspended solids with raw wastewater. Representatives from Siemens were on site to provide training and start up services.
During this “wet test” period, the Authority Staff assisted Worth & Company to simulate plant operation during a significant rain event. Additionally, power failures were simulated to evaluate the effect of the treatment plant equipment. Items of concern included replacing a failed overload relay for SBR number 3 mixer pump, Siemens UV lamp bank number 1 and the Aqua Aerobics disc filter control panel. Corrective actions for the Siemens and Aqua Aerobics control panel will carry over into phase II.
Key administrative and contractual items on task for presentation to the Authority Board members for include discussion of Worth & Company’s letter dated February 15, 2010 requesting change in the substantial completion date of June 30, 2010 to September 30, 2010 and Clinger letters dated March 15, 2010 and April 30, 2010.
2 of 7
East Goshen Municipal Authority
Ridley Creek Sewage Treatment Plant Upgrade & Expansion Project
April 2010 Project Manager Report
| To: | East Goshen Municipal Authority Members |
|---|---|
| From: | Scott A. Towler, P.E., Project Manager Dave W. Evans, Project Manager |
| CC: | Evans Andrews, P.E., Authority Engineer |
| Date: | May 6, 2010 |
| Re: | April 2010 – Project Manager Report for the Ridley Creek Capital Expansion Project: |
I. General Construction
- Influent Meter Vault The flow meter communication wiring to the new treatment building was completed. Influent flow measurements are recorded within the new treatment building on a 7-day chart recorder and interfaced with the Siemens SBR control panel; Influent flow measurements are recorded within the new treatment building on a 7-day chart recorder and interfaced with the Siemens SBR control panel; A sump pump and discharge piping were installed (furnished and installed by East Goshen Township Municipal Authority Staff). The plans and specifications did not include a sump pump.; The plans and specifications did not include a sump pump.
- Influent Lift Station Wet well The lift station was placed in service on Thursday, April 15 th to begin pumping treated effluent from the existing treatment plant into the SBRs to evaluate the SBR equipment operation. This is referred to as the “wet test.” All three (3) Flyght pumps are in service and alternate each cycle. Raw sewage was introduced into the lift station on Tuesday, May 5 th .; The lift station was placed in service on Thursday, April 15 th to begin pumping treated effluent from the existing treatment plant into the SBRs to evaluate the SBR equipment operation. This is referred to as the “wet test.”; All three (3) Flyght pumps are in service and alternate each cycle.; Raw sewage was introduced into the lift station on Tuesday, May 5 th .; Valve vault No new activity
- Manhole Number 1 No change in status
- Storm Water Bio Retention Pond Adjacent to Manhole No. 1 No change in status
Page 1 of 6
3 of 7
East Goshen Municipal Authority
Ridley Creek Sewage Treatment Plant Upgrade & Expansion Project
April 2010 Project Manager Report
- Screening Building The lift station was placed in service on Thursday, April 15 th to begin pumping treated effluent from the existing treatment plant through the grinder and screen equipment to simulate typical operations. This is referred to as the “wet test.”; Raw sewage was introduced through the grinder and fine screen on Tuesday, May 5 th .; Screenings were observed to be discharging from the screw auger on Wednesday, May 6 th .; Relocation of the transfer fan approximately 3 vertical feet is planned to prevent the fan from submergence in the event of flooding of the lower section of the screen building.
- Influent Force Main to SBRs No new activity.
- SBR Effluent Discharge Main Trinity excavation was on site to install approximately 15 feet of the effluent discharge pipe parallel to SBR number 1.
- Flocculation Tank Two (2) remaining section of FRP require installation adjacent to the floc mixer.; Adjustment of the FRP decking parallel to the new treatment building remains to be completed.
- Disc Filters and Associated Equipment The disc filters were placed in service on Thursday, April 15th to begin pumping treated effluent from the existing treatment plant into the SBRs to evaluate the SBR equipment operation. This is referred to as the “wet test.”; SBR effluent was introduced into the disc filters on Tuesday, May 5th.; The chemical (“Strike”) to control filter flies within the disc filter basins was introduced on Wednesday, May 6 th . The chemical is non-hazardous and approved for this application.
- SBR Basins The davits to support the hoist to remove the SBR mixer pumps and waste activated sludge (WAS) pumps require installation.; The SBR basins were filled with treated effluent and placed in service on Thursday, April 15 th to allow each SBR to operate through each cycle of treatment to simulate the SBR equipment operation. This is referred to as the “wet test.”; Mixed liquor suspended solids (MLSS) and raw sewage was introduced into SBRs 1, 2 and 3 on Tuesday, May 5 th .
Page 2 of 6
4 of 7
East Goshen Municipal Authority
Ridley Creek Sewage Treatment Plant Upgrade & Expansion Project
April 2010 Project Manager Report
- SBR Equipment The lower knife valves on each SBR effluent pipe into the effluent distribution header were closed approximately in half.
- Treatment Building The silence attenuation cabinets were installed for all five blowers.; The system pressure tanks for the utility water system were installed.
- Treatment Building Roof No new activity
- UV Disinfection System The UV system was placed in service on Thursday, April 15 th to disinfection the effluent from the SBRs to simulate operation of the system under anticipated conditions. This is referred to as the “wet test.”; Treated effluent from the SBRs was initiated on Tuesday, May 5 th .; Continuous monitoring of the effluent water temperature at the discharge side of the UV lamps was initiated.
- Effluent Collection Box The effluent v-notched weir plate was lowered approximately 6-inches.; Treated effluent from the SBRs was initiated on Tuesday, May 5th.
- Effluent Overflow Box No new activity.
- Utility Water Piping The non-potable water system was placed in service.; The Authority Staff furnished and installed wall mounted hose reels, including hose within the Screen and New Treatment Buildings.
- Apple Brook Discharge The electrical disconnect switch was installed.
- Electrical Clinger appeared to maintain a foreman and assistant on site during the past month. On occasion, it was observed to have additional personnel on site.; On May 5, 2010, East Goshen Township Municipal Authority Staff excavated the trench between the existing control building and new treatment building for the conduit claimed as “additional duct banks.”; On May 6, 2010, Clinger was observed to have one electrician installing conduit.
Page 3 of 6
5 of 7
East Goshen Municipal Authority
Ridley Creek Sewage Treatment Plant Upgrade & Expansion Project
April 2010 Project Manager Report
- On April 27, 2010, several power failures were simulated to evaluate the SBR and related equipment during the transition from utility power to generator power and vice versa.
- Rehabilitation of the existing Aeration Blowers Blower number 4 was anticipated to be delivered to the site on Friday, April 30, 2010.
- DAVCO Tank Cleaning The East Goshen Township Municipal Authority Staff opened sealed bids for the removal, disposal and cleaning of the contents of the existing DAVCO treatment plants upon completion of the transfer of MLSS into the SBRs. Aqua Wastewater Management, Inc. was the lowest responsible bidder.; Aqua Wastewater Management, Inc. was the lowest responsible bidder.; In preparation of removing the DAVCO plants from service, McGovern septic service was utilized to remove and disposal of sludge within the sludge holding tanks. Approximately 6 truckloads of liquid sludge were removed on May 5, 2010.; On May 5, 2010, East Goshen Township Municipal Authority Staff assisted Worth and Company Staff with the transfer of MLSS into the SBRs. The East Goshen Township Municipal Authority Staff managed decanted the clear effluent from the clarifiers through the filter and UV system. East Goshen Township Municipal Authority Staff managed the draining of the flow equalization tank and influent lift station wet well.; The East Goshen Township Municipal Authority Staff managed decanted the clear effluent from the clarifiers through the filter and UV system.; East Goshen Township Municipal Authority Staff managed the draining of the flow equalization tank and influent lift station wet well.; On May 6, 2010, Aqua wastewater Management, Inc. began cleaning DAVCO plant number 2.
- Erosion and Sediment Controls East Goshen Township Municipal Authority Worth & Company, Inc. continues to perform inspections of the E&S controls as required after a storm event.
II. Payment Requests
- Worth & Company pencil payment review was conducted on May 3, 2010. Worth & Company was instructed to include information regarding the approved change orders on the request for payment application.
- Clinger pencil payment request review was conducted on May 3, 2010. Clinger was instructed to update the information regarding the approved change orders on the request for payment application.
Page 4 of 6
6 of 7
East Goshen Municipal Authority
Ridley Creek Sewage Treatment Plant Upgrade & Expansion Project
April 2010 Project Manager Report
III. Release of Liens
Release of liens for equipment approved for payment is current.
IV. Meetings
- On April 6, 2010, a special meeting to discuss the response to Clinger’s March 15, 2010 letter was held. Representatives from the Authority, Pennoni Associates, Inc, and Brickhouse Environmental, Inc. were in attendance.
- On April 12, 2010, the monthly East Goshen Township Municipal Authority meeting as attended. Executive session was held during the meeting.
- On April 15, Siemens representative conducted SBR training and while the SBRs contained treated effluent from the existing treatment plant.
- On April 15, 2010, prepared for and attended the bi-weekly progress meeting.
- On April 22, 2010, prepared for and attended the weekly progress meeting.
- On April 23, 2010, prepared for and attended a special meeting to discuss the Authority’s response to Clinger’s March 15, 2010 letter. Representatives from the Authority, Authority’s Solicitor, Pennoni Associates, Inc, and Brickhouse Environmental, Inc. were in attendance.
- On April 23, 2010, participated in an unannounced site visit and inspection of the new SBR treatment plant by Dave Tally and Dave Wolfinger of PADEP. No problems, issues or concerns were observed or noted.
- On April 29, 2010, prepared for and attended the weekly progress meeting.
- On May 6, 2010, participated in an unannounced inspection by Dave Wolfinger of PADEP. No problems, issues or concerns were observed or noted.
V. Correspondence
- April 15, 2010 East Goshen Township Municipal Authority letter to Michael Clinger regarding Outstanding Matters.
- April 15, 2010 East Goshen Township Municipal Authority’s approval of Clinger ‘change order regarding the Applebrook electrical controls and labor.
VI. Potential Extras Identified During the month
- East Goshen Township Municipal Authority approved Clinger’s change order request in the sum of $3,171.00 with respect to the Applebrook pump.
Page 5 of 6
7 of 7
East Goshen Municipal Authority
Ridley Creek Sewage Treatment Plant Upgrade & Expansion Project
April 2010 Project Manager Report
Potential Receipts Identified during the Month
None
VII. Issues for Reconciliation
- Siemens UV bank number 1. UV bank number 1 was observed to trip the breaker within the Siemens UV control panel when electrical power is transferred from utility power to the emergency generator. Worth & Company is coordinating with Siemens to correct the deficiency.
- Aqua Aerobics disc filter control panel was observed to produce a “basin transducer level out of range” alarm. Worth & Company is coordinating with Aqua Aerobics to correct the deficiency.
- Pennoni Associates, Inc. formal letter response to East Goshen Township Municipal Authority regarding Clinger’s March 15, 2010 letter.
- Clinger issued a letter dated April 30, 2010 to the East Goshen Township Municipal Authority explaining that they are proceeding with the installation of the conduit within the duct bank between the existing control building and new treatment plant. They also claim their position that the work is not included as part of the original plans as prepared by Pennoni Associates, Inc.
- Worth & Company issued a letter dated February 15, 2010 requesting for a substantial completion date of September 30, 2010.
- Worth & Company change order number 2. Worth & Company has requested an extension in time as part of the change order.
VIII. Start-up
- May 5, 2010 - SBRs online
- May 6, 2010 - Initiation of cleaning the DAVCO plants
- May 10, 2010 - Demolition begins
Page 6 of 6
3. RIDLEY CREEK INV
a.
1 pg
GRAINGER
8211 BAVARIA ROAD
MACEDONIA, OH 44056-2259
PAGE 1 OF 1
ORIGINAL INVOICE
[Watermark: COPY]
| GRAINGER ACCOUNT NUMBER | 829095066 |
|---|---|
| INVOICE NUMBER | 9217937037 |
| INVOICE DATE | 03/31/2010 |
| DUE DATE | 04/30/2010 |
| AMOUNT DUE | 275.50 |
| PO NUMBER: | SEWER PLANT |
|---|---|
| CALLER: | MARK MILLER |
| CUSTOMER PHONE: | (610) 692-7171 |
| DELIVERY NUMBER: | 6127520270 |
| INCO TERMS: | FOB ORIGIN |
SHIP TO
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA 19380-6107
BILL TO
MDG2005 00008649 1 AT 0357
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA 19380-6107 008649
APPROVED BY: [signature]
DATE PAID:
CHECK #:
CHARGED TO: 07-424-7452
THANK YOU!
FEI NUMBER 36-1150280
FOR ANY QUESTIONS ABOUT THIS INVOICE OR ACCOUNT CALL 1-877-202-2594
| PO LINE # | ITEM # | DESCRIPTION | QUANTITY | BACK ORDERED | UNIT PRICE | TOTAL |
|---|---|---|---|---|---|---|
| 4LU66 | HOSE, WATER, 1 IN, 50 FT MANUFACTURER # CSNCCC01050 |
2 | 95.94 | 191.88 | ||
| 2VCY9 | WATER HOSE, HEAVY DUTY, 3/4 IN X 50 FT MANUFACTURER # CL8334050CEZ |
2 | 41.81 | 83.62 | ||
| INVOICE SUB TOTAL | 275.50 | |||||
NUMBER OF PKGS: 0 WEIGHT: 62.18
DATE SHIPPED: 03/31/2010
CARRIER: UPS GROUND
TRACKING NO: 1Z3018W70348603418 1Z3018W70348606531
These items are sold for domestic consumption in the United States. If exported, purchaser assumes full responsibility for compliance with US export controls.
PAYMENT TERMS NET 30 DAYS. PAY THIS INVOICE NO STATEMENT SENT. PAYABLE IN U.S. DOLLARS.
AMOUNT DUE 275.50
▲ PLEASE DETACH THIS PORTION AND RETURN WITH YOUR PAYMENT. ▲
|
BILL TO: EAST GOSHEN TOWNSHIP 1580 PAOLI PIKE WEST CHESTER, PA 19380-6107 |
REMIT TO: GRAINGER DEPT. 829095066 PALATINE, IL 60038-0001 |
|---|
829095066921793703710000275501000000010000000100000010043032
| ACCOUNT NUMBER | DATE | INVOICE NUMBER | AMOUNT DUE |
|---|---|---|---|
| 829095066 | 03/31/2010 | 9217937037 | 275.50 |
FOR COMMENTS OR CHANGE OF ADDRESS, ENTER INFORMATION ON REVERSE SIDE.
3.
b.
1 pg
GRAINGER
580 E LANCASTER AVE
FRAZER, PA 19355-1808
PAGE 1 OF 1
ORIGINAL INVOICE
[Watermark: COPY]
| GRAINGER ACCOUNT NUMBER | 829095066 |
|---|---|
| INVOICE NUMBER | 9228782778 |
| INVOICE DATE | 04/14/2010 |
| DUE DATE | 05/14/2010 |
| AMOUNT DUE | 641.98 |
| PO NUMBER: | RIDLEY CREEK SEWER P |
|---|---|
| CALLER: | MARK MILLER |
| CUSTOMER PHONE: | (610) 692-7171 |
| ORDER/DELIVERY#: | 1102174021 |
| INCO TERMS: | FOB ORIGIN |
SHIP TO
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA 19380-6107
APPROVED BY: [signature]
DATE PAID:
CHECK #:
CHARGED TO: 07-424-7452
SBR Storage
BILL TO
MDG2010 00016524 1 AB 0360
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA 19380-6107 016524
THANK YOU!
FEI NUMBER 36-1150280
FOR ANY QUESTIONS ABOUT THIS INVOICE OR ACCOUNT CALL 610-727-5251
| PO LINE # | ITEM # | DESCRIPTION | QUANTITY | BACK ORDERED | UNIT PRICE | TOTAL |
|---|---|---|---|---|---|---|
| 1KBF8 | RACK STARTER UNIT, D 36, H 96, L 120 MANUFACTURER # 183609650120DS |
1 | 479.70 | 479.70 | ||
| 1KBD9 | STEP BEAM, W 2 1/2, H 5, L120, LOAD CAP 4412 MANUFACTURER # IBX48120 |
2 | 45.95 | 91.90 | ||
| 2JGK4 | PALLET RACK WIRE DECKING, W 58 IN, D 36 IN MANUFACTURER # 360580Z06004322 |
2 | 35.19 | 70.38 | ||
| INVOICE SUB TOTAL | 641.98 | |||||
NUMBER OF PKGS: 0 WEIGHT: 0.00
These items are sold for domestic consumption in the United States. If exported, purchaser assumes full responsibility for compliance with US export controls.
PAYMENT TERMS NET 30 DAYS. PAY THIS INVOICE NO STATEMENT SENT. PAYABLE IN U.S. DOLLARS.
AMOUNT DUE 641.98
▲ PLEASE DETACH THIS PORTION AND RETURN WITH YOUR PAYMENT. ▲
|
BILL TO: EAST GOSHEN TOWNSHIP 1580 PAOLI PIKE WEST CHESTER, PA 19380-6107 |
REMIT TO: GRAINGER DEPT. 829095066 PALATINE, IL 60038-0001 |
|---|
829095066922878277810000641981000000010000000100000010051445
| ACCOUNT NUMBER | DATE | INVOICE NUMBER | AMOUNT DUE |
|---|---|---|---|
| 829095066 | 04/14/2010 | 9228782778 | 641.98 |
FOR COMMENTS OR CHANGE OF ADDRESS, ENTER INFORMATION ON REVERSE SIDE.
3.
C.
1 pg
GRAINGER
580 E LANCASTER AVE
FRAZER, PA 19355-1808
PAGE 1 OF 1
ORIGINAL INVOICE
[Watermark: COPY]
| GRAINGER ACCOUNT NUMBER | 829095066 |
|---|---|
| INVOICE NUMBER | 9231297822 |
| INVOICE DATE | 04/16/2010 |
| DUE DATE | 05/16/2010 |
| AMOUNT DUE | 28.58 |
| PO NUMBER: | RIDLEY |
|---|---|
| CALLER: | GEORGE THOMPSON |
| CUSTOMER PHONE: | (610) 692-7171 |
| ORDER/DELIVERY#: | 6128994301 |
| INCO TERMS: | FOB ORIGIN |
SHIP TO
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA 19380-6107
BILL TO
MDG2010 00007339 1 AT 0357
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA 19380-6107
APPROVED BY: [signature]
DATE PAID:
CHECK #:
CHARGED TO: 07-424-7452
THANK YOU!
FEI NUMBER 36-1150280
FOR ANY QUESTIONS ABOUT THIS INVOICE OR ACCOUNT CALL 610-727-5251
| PO LINE # | ITEM # | DESCRIPTION | QUANTITY | BACK ORDERED | UNIT PRICE | TOTAL |
|---|---|---|---|---|---|---|
| 3CZG1 | TRIMLINE PHONE, WHITE MANUFACTURER # 205TMW (WHITE) |
1 | 28.58 | 28.58 | ||
| INVOICE SUB TOTAL | 28.58 | |||||
NUMBER OF PKGS: 0 WEIGHT: 1.35
DATE SHIPPED: 04/16/2010
TRACKING NO: G T
These items are sold for domestic consumption in the United States. If exported, purchaser assumes full responsibility for compliance with US export controls.
PAYMENT TERMS NET 30 DAYS. PAY THIS INVOICE NO STATEMENT SENT. PAYABLE IN U.S. DOLLARS.
AMOUNT DUE 28.58
▲ PLEASE DETACH THIS PORTION AND RETURN WITH YOUR PAYMENT. ▲
|
BILL TO: EAST GOSHEN TOWNSHIP 1580 PAOLI PIKE WEST CHESTER, PA 19380-6107 |
REMIT TO: GRAINGER DEPT. 829095066 PALATINE, IL 60038-0001 |
|---|
829095066923129782210000028581000000010000000100000010051609
| ACCOUNT NUMBER | DATE | INVOICE NUMBER | AMOUNT DUE |
|---|---|---|---|
| 829095066 | 04/16/2010 | 9231297822 | 28.58 |
FOR COMMENTS OR CHANGE OF ADDRESS, ENTER INFORMATION ON REVERSE SIDE.
RC EXP 3. RIDLEY CREEK INV
d
2 pgs
Invoice
[Watermark: COPY]
CONTINENTAL FIRE & SAFETY, Inc.
180 VOLUSIA AVE.
TRENTON, NJ 08610-2826
609-588-0096 • fax 609-584-0405
| Date | Invoice # |
|---|---|
| 4/15/2010 | 37184 |
APPROVED BY: [signature]
DATE PAID:
CHECK #:
CHARGED TO: 07424-7452
|
Bill To EAST GOSHEN TOWNSHIP 1580 PAOLI PIKE WEST CHESTER, PA 19380 |
Ship To EAST GOSHEN TOWNSHIP 1580 PAOLI PIKE WEST CHESTER, PA 19380 |
|---|
| P.O. Number | Terms | Rep | Ship | Via | F.O.B. | Project |
|---|---|---|---|---|---|---|
| 1581-10 | NET 30 | AC | 4/15/2010 | DIRECT |
| Quantity | Item Code | Description | Price Each | Amount |
|---|---|---|---|---|
| 1 | MISC | ATI JAFLINE HD HOSE - RED - 3" X 25' WITH 2 1/2" NST COUPLINGS | 169.00 | 169.00 |
| 5 | MISC | ATI JAFLINE HD HOSE - RED - 1 3/4" X 50' WITH 1 1/2" NST COUPLINGS | 119.00 | 595.00 |
| 1 | MISC | CRESTAR GATED WYE - #LWNL - 2 1/2" NST FM INLET X (2) 1 1/2" NST M OUTLETS - NON LOCKING | 199.00 | 199.00 |
| 2 | MISC | 1 1/2" NST POLYCARONATE NOZZLES | 19.00 | 38.00 |
| 2 | MISC | RED HEAD SINGLE HEAD HYDRANT WRENCH #107 | 29.00 | 58.00 |
| 1 | Shipping | SHIPPING AND HANDLING | 64.00 | 64.00T |
| NJ Sales Tax | 7.00% | 4.48 | ||
| Total | $1,127.48 | |||
| WEB SITE | WWW.CONTINENTALFIREANDSAFETY.COM |
|---|
2 of 2
CONTINENTAL FIRE & SAFETY, Inc.
180 VOLUSIA AVE.
TRENTON, NJ 08610-2826
609-588-0096 • fax 609-584-0405
SALES ORDER
| DATE | INVOICE # |
|---|---|
| 4/1/2010 | 37184 |
[Stamp: PENDING (non-posting)]
|
BILL TO EAST GOSHEN TOWNSHIP 1580 PAOLI PIKE WEST CHESTER, PA 19380 |
SHIP TO EAST GOSHEN TOWNSHIP 1580 PAOLI PIKE WEST CHESTER, PA 19380 |
|---|
| P.O. NO. | REP | PROJECT |
|---|---|---|
| 1581-10 | AC |
| ITEM | DESCRIPTION | QTY | RATE | AMOUNT |
|---|---|---|---|---|
| MISC | ATI JAFLINE HD HOSE - RED - 3" X 25' WITH 2 1/2" NST COUPLINGS | 1 | 169.00 | 169.00 |
| MISC | ATI JAFLINE HD HOSE - RED - 1 3/4" X 50' WITH 1 1/2" NST COUPLINGS | 5 | 119.00 | 595.00 |
| MISC | CRESTAR GATED WYE - #LWNL - 2 1/2" NST FM INLET X (2) 1 1/2" NST M OUTLETS - NON LOCKING | 1 | 199.00 | 199.00 |
| MISC | 1 1/2" NST POLYCARONATE NOZZLES | 2 | 19.00 | 38.00 |
| MISC | RED HEAD SINGLE HEAD HYDRANT WRENCH #107 | 2 | 29.00 | 58.00 |
| NJ Sales Tax | 7.00% | 0.00 | ||
| Total | $1,059.00 | |||
[Signature: MSH]
APPROVED BY: _____________________
DATE PAID: _________________________
CHECK #: ___________________________
CHARGED TO: 07-424-7452
[Stamp: PACKING LIST ONLY]
| Web Site | WWW.CONTINENTALFIREANDSAFETY.COM |
|---|
3. RIDLEY CREEK INV
e.
3 pgs
[Logo: Brickhouse Environmental - Consultants and Engineers]
|
East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380 |
Invoice number: 5333 Date: 5/3/2010 Client ID: 548 |
|---|
Contract: 09.2532
E Goshen Twp-Ridley CreekSewer
Scope of Work: Project No. 09-2532-0 E. Goshen/Ridley Creek Sewer Plant/WW Engineering
Attn: Mr. Rick Smith, Township Manager
SEE PROJECT ACCOMPLISHMENTS ATTACHED.
Professional Services Rendered Through the Month of April 2010.
Labor
| Employee Type | Hours | Amount |
|---|---|---|
| Project Manager | 103.75 | 11,931.25 |
| Labor Total | 103.75 | 11,931.25 |
| Amount | |
|---|---|
| Reimbursable | 0.00 |
| Expense Total | 0.00 |
| Invoice Total | 11,931.25 |
ok TCS 5/5/10
Payment Terms: Net Thirty (30) Days; Credit Cards Accepted
When Creativity & Experience Count
515 South Franklin Street
West Chester, PA 19382
Phone 610.692.5770
Fax 610.692.8650
www.brickhouse-environmental.com
2 of 3
Brickhouse Environmental
East Goshen Township: Ridely Creek Sewer Plant Expansion Project Management Schedule
The original budget estimate assumed commencing the first week of May. Week 1 actually commenced 28-April-2009 (week ending 30-April). The schedule reflects this change for monthly comparison based on the agreed $115.00 hourly rate.
| Week Ending | Week | Estimated Project Management | Estimated Cumulative Hours | Estimated Cumulative Fees | Estimated Monthly Fees | Actual Totals Project Management | Actual Totals Cumulative Hours | Actual Totals Cumulative Fees | Actual Totals Monthly Fees |
|---|---|---|---|---|---|---|---|---|---|
| 30-Apr-09 | Week 1 (3 days) | 0 | 0 | $0 | $0 | 18.5 | 18.5 | $2,127.50 | $2,127.50 |
| 3-May-09 | Week 1 (2 days) | 48 | 48 | $5,520 | |||||
| 10-May-09 | Week 2 | 50 | 98 | $11,270 | |||||
| 17-May-09 | Week 3 | 20 | 118 | $13,570 | |||||
| 24-May-09 | Week 4 | 20 | 138 | $15,870 | |||||
| 31-May-09 | Week 5 | 20 | 158 | $18,170 | $18,170 | 73.5 | 92.0 | $10,580.00 | $8,452.50 |
| 7-Jun-09 | Week 6 | 20 | 178 | $20,470 | |||||
| 14-Jun-09 | Week 7 | 20 | 198 | $22,770 | |||||
| 21-Jun-09 | Week 8 | 20 | 218 | $25,070 | |||||
| 28-Jun-09 | Week 9 | 20 | 238 | $27,370 | |||||
| 30-Jun-09 | Week 10 (2 days) | 8 | 246 | $28,290 | $10,120 | 67.8 | 159.8 | $18,371.25 | $7,791.25 |
| 5-Jul-09 | Week 10 (3 days) | 12 | 258 | $29,670 | |||||
| 12-Jul-09 | Week 11 | 20 | 278 | $31,970 | |||||
| 19-Jul-09 | Week 12 | 20 | 298 | $34,270 | |||||
| 26-Jul-09 | Week 13 | 24 | 322 | $37,030 | |||||
| 31-Jul-09 | Week 14 | 24 | 346 | $39,790 | $11,500 | 81.0 | 240.8 | $27,686.25 | $9,315.00 |
| 9-Aug-09 | Week 15 | 24 | 370 | $42,550 | |||||
| 16-Aug-09 | Week 16 | 24 | 394 | $45,310 | |||||
| 23-Aug-09 | Week 17 | 24 | 418 | $48,070 | |||||
| 30-Aug-09 | Week 18 | 24 | 442 | $50,830 | |||||
| 31-Aug-09 | Week 19 (1 day) | 4 | 446 | $51,290 | $11,500 | 67.5 | 308.3 | $35,448.75 | $7,762.50 |
| 6-Sep-09 | Week 19 (4 days) | 20 | 466 | $53,590 | |||||
| 13-Sep-09 | Week 20 | 24 | 490 | $56,350 | |||||
| 20-Sep-09 | Week 21 | 24 | 514 | $59,110 | |||||
| 27-Sep-09 | Week 22 | 24 | 538 | $61,870 | |||||
| 30-Sep-09 | Week 23 (3 days) | 16 | 554 | $63,710 | $12,420 | 64.5 | 372.8 | $42,866.25 | $7,417.50 |
| 4-Oct-09 | Week 23 (2 days) | 8 | 562 | $64,630 | |||||
| 11-Oct-09 | Week 24 | 24 | 586 | $67,390 | |||||
| 18-Oct-09 | Week 25 | 24 | 610 | $70,150 | |||||
| 25-Oct-09 | Week 26 | 24 | 634 | $72,910 | |||||
| 31-Oct-09 | Week 27 | 24 | 658 | $75,670 | $11,960 | 61.5 | 434.3 | $49,938.75 | $7,072.50 |
| 8-Nov-09 | Week 28 | 24 | 682 | $78,430 | |||||
| 15-Nov-09 | Week 29 | 24 | 706 | $81,190 | |||||
| 22-Nov-09 | Week 30 | 20 | 726 | $83,490 | |||||
| 29-Nov-09 | Week 31 | 20 | 746 | $85,790 | |||||
| 30-Nov-09 | Week 32 (1 day) | 4 | 750 | $86,250 | $10,580 | 69.3 | 503.6 | $57,902.50 | $7,963.75 |
| 6-Dec-09 | Week 32 (4 days) | 20 | 770 | $88,550 | |||||
| 13-Dec-09 | Week 33 | 24 | 794 | $91,310 | |||||
| 20-Dec-09 | Week 34 | 20 | 814 | $93,610 | |||||
| 27-Dec-09 | Week 35 | 20 | 834 | $95,910 | |||||
| 31-Dec-09 | Week 36 (4 days) | 16 | 850 | $97,750 | $11,500 | 67.5 | 571.1 | $65,665.00 | $7,762.50 |
| 3-Jan-10 | Week 36 (1 day) | 4 | 854 | $98,210 | |||||
| 10-Jan-10 | Week 37 | 20 | 874 | $100,510 |
092532.50/Schedule.xls | Page 1 of 2
3 of 3
Brickhouse Environmental
East Goshen Township: Ridely Creek Sewer Plant Expansion Project Management Schedule
The original budget estimate assumed commencing the first week of May. Week 1 actually commenced 28-April-2009 (week ending 30-April). The schedule reflects this change for monthly comparison based on the agreed $115.00 hourly rate.
| Week Ending | Week | Estimated Project Management | Estimated Cumulative Hours | Estimated Cumulative Fees | Estimated Monthly Fees | Actual Totals Project Management | Actual Totals Cumulative Hours | Actual Totals Cumulative Fees | Actual Totals Monthly Fees |
|---|---|---|---|---|---|---|---|---|---|
| 17-Jan-10 | Week 38 | 20 | 894 | $102,810 | |||||
| 24-Jan-10 | Week 39 | 24 | 918 | $105,570 | |||||
| 31-Jan-10 | Week 40 | 24 | 942 | $108,330 | $10,580 | 66.3 | 637.4 | $73,283.75 | $7,618.75 |
| 7-Feb-10 | Week 41 | 24 | 966 | $111,090 | |||||
| 14-Feb-10 | Week 42 | 24 | 990 | $113,850 | |||||
| 21-Feb-10 | Week 43 | 24 | 1,014 | $116,610 | |||||
| 28-Feb-10 | Week 44 | 20 | 1,034 | $118,910 | $10,580 | 64.5 | 701.9 | $80,701.25 | $7,417.50 |
| 7-Mar-10 | Week 45 | 20 | 1,054 | $121,210 | |||||
| 14-Mar-10 | Week 46 | 20 | 1,074 | $123,510 | |||||
| 21-Mar-10 | Week 47 | 20 | 1,094 | $125,810 | |||||
| 28-Mar-10 | Week 48 | 20 | 1,114 | $128,110 | |||||
| 31-Mar-10 | Week 49 (3 days) | 16 | 1,130 | $129,950 | $11,040 | 87.0 | 788.9 | $90,706.25 | $10,005.00 |
| 4-Apr-10 | Week 49 (2 days) | 8 | 1,138 | $130,870 | |||||
| 11-Apr-10 | Week 50 | 24 | 1,162 | $133,630 | |||||
| 18-Apr-10 | Week 51 | 24 | 1,186 | $136,390 | |||||
| 25-Apr-10 | Week 52 | 24 | 1,210 | $139,150 | |||||
| 30-Apr-10 | Week 53 | 24 | 1,234 | $141,910 | $11,960 | 103.8 | 892.7 | $102,637.50 | $11,931.25 |
| 9-May-10 | Week 54 | 20 | 1,254 | $144,210 | |||||
| 16-May-10 | Week 55 | 20 | 1,274 | $146,510 | |||||
| 23-May-10 | Week 56 | 20 | 1,294 | $148,810 | |||||
| 30-May-10 | Week 57 | 20 | 1,314 | $151,110 | |||||
| 31-May-10 | Week 58 (1 day) | 4 | 1,318 | $151,570 | $9,660 | ||||
| 6-Jun-10 | Week 58 (4 days) | 16 | 1,334 | $153,410 | |||||
| 13-Jun-10 | Week 59 | 20 | 1,354 | $155,710 | |||||
| 20-Jun-10 | Week 60 | 20 | 1,374 | $158,010 | |||||
| 27-Jun-10 | Week 61 | 20 | 1,394 | $160,310 | |||||
| 30-Jun-10 | Week 62 (3 days) | 12 | 1,406 | $161,690 | $10,120 | ||||
| 4-Jul-10 | Week 62 (2 days) | 8 | 1,414 | $162,610 | |||||
| 11-Jul-10 | Week 63 | 20 | 1,434 | $164,910 | |||||
| 18-Jul-10 | Week 64 | 24 | 1,458 | $167,670 | |||||
| 25-Jul-10 | Week 65 | 24 | 1,482 | $170,430 | |||||
| 31-Jul-10 | Week 66 | 20 | 1,502 | $172,730 | $11,040 | ||||
| 8-Aug-10 | Week 67 | 20 | 1,522 | $175,030 | $2,300 |
092532.50/Schedule.xls | Page 2 of 2
3. RIDLEY CREEK INV f. 1841
Worth & Company, Inc.
Mechanical Contractor
6263 Kellers Church Road
Pipersville, PA 18947
Tel: (267) 362-1100 Fax: (267) 362-1130
www.worthandcompany.com
LETTER OF TRANSMITTAL
Date: May 3, 2010
Job No.: P28001
ATTN: Mark Miller
RE: Ridley Creek WWTP
TO: East Goshen Township
1580 Paoli Pike
West Chester, PA 19380
TEL: 610-692-7171
WE ARE SENDING YOU
- [ ] Shop Drawings
- [ ] Copy of letter
- [X] Other--
- [X] Attached
- [ ] Prints
- [ ] Change Order
- [ ] Under Separate Cover
- [ ] Specifications
- [ ] Submittals
| Copies | Date | Description |
|---|---|---|
| 5 | Application for Payment No. 17 | |
THESE ARE TRANSMITTED as checked below:
- [ ] For Approval
- [ ] For your use
- [X] As requested
- [ ] For review & comment
- [ ] FOR BIDS DUE:
- [ ] Approved as Submitted
- [ ] Approved as Noted
- [ ] Returned for corrections
- [ ] Other - For Signature
- [ ] Resubmit copies for approval
- [ ] Submit copies for distribution
- [ ] Return corrected prints
REMARKS
Hand carried via Jeff Bush
COPY TO: File
SIGNED: Linda D. Nelson
Page 1
Application and Certificate For Payment
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Phone: 267 362-1100 |
Project: Ridley Creek WWTP Contractor Job Number: P28001 Via (Architect): Contract For: |
Application No: 17 Period To: 04/30/10 Architect's Project No: Contract Date: 10/22/08 Date: 04/30/2010 |
|---|
Contractor's Application For Payment
| Change Order Summary | Additions | Deductions |
|---|---|---|
| Change orders approved in previous months by owner | ||
|
Approved this month Number: [blank] Date Approved: [blank] |
||
| Totals | ||
| Net change by change orders | ||
The undersigned Contractor certifies that to the best of the Contractor's knowledge, information, and belief the work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for work for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown herein is now due.
Contractor: Worth and Company, Inc.
By: [signature]
Date: 5/3/10
State of: PA
County of: Bucks
Subscribed and sworn to before me this 3rd day of May 2010 (year).
Notary public: Linda D. Nelson [signature]
My commission expires: Sept 19, 2010
[Seal: COMMONWEALTH OF PENNSYLVANIA Notarial Seal Linda D. Nelson, Notary Public Plumstead Twp., Bucks County My Commission Expires Sept. 19, 2010 Member, Pennsylvania Association of Notaries]
| Original contract sum | 7,865,400.00 |
|---|---|
| Net change by change orders | 0.00 |
| Contract sum to date | 7,865,400.00 |
| Total completed and stored to date | 6,563,865.00 |
| Retainage | |
| 5.0% of completed work | 328,193.25 |
| 0.0% of stored material | 0.00 |
| Total retainage | 328,193.25 |
| Total earned less retainage | 6,235,671.75 |
| Less previous certificates of payment | 6,065,408.00 |
| Current payment due | 170,263.75 |
| Balance to finish, including retainage | 1,629,728.25 |
Architect's Certificate for Payment
In accordance with the Contract Documents, based on on-site observations and the data comprising the above application the Architect certifies to the Owner that to the best of the Architect's knowledge, information and belief the Work has progressed as indicated, the quality of the Work is in accordance with the Contract Documents, and the Contractor is entitled to payment of the Amount Certified.
Amount Certified: $ [blank]
Architect:
By: [blank]
Date: [blank]
This Certification is not negotiable. The Amount Certified is payable only to the Contractor named herein. Issuance, payment, and acceptance of payment are without prejudice to any rights of the Owner or Contractor under this Contract.
Application and Certificate For Payment -- page 2
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Project: Ridley Creek WWTP |
Application No: 17 Contractor's Job Number: P28001 Architect's Project No: |
Date: 04/30/10 Period To: 04/30/10 |
|---|
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G1-000 | Site Work & Yard Piping | |||||||||
| G1-001 | Bonds | 160,000.00 | 160,000.00 | 0.00 | 0.00 | 160,000.00 | 100.00 | 0.00 | 8,000.00 | |
| G1-002 | Insurance | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G1-003 | Mobilization | 100,000.00 | 100,000.00 | 0.00 | 0.00 | 100,000.00 | 100.00 | 0.00 | 5,000.00 | |
| G1-004 | Pre-Planning/Schedule | 20,000.00 | 16,000.00 | 0.00 | 0.00 | 16,000.00 | 80.00 | 4,000.00 | 800.00 | |
| G1-005 | Submittals - Dutchland | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G1-006 | Submittals - Jet Tech | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G1-007 | E & S Controls | 25,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 60.00 | 10,000.00 | 750.00 | |
| G1-008 | Strip Topsoil | 50,000.0050,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | ||
| G1-009 | Temporary Seed | 5,000.003,000.00 | 0.00 | 0.00 | 3,000.00 | 60.00 | 2,000.00 | 150.00 | ||
| G1-010 | Bioretention Basin 1 | 20,000.000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | ||
| G1-011 | Bioretention Basin 2 | 20,000.005,000.00 | 0.00 | 0.00 | 5,000.00 | 25.00 | 15,000.00 | 250.00 | ||
| G1-012 | Temporary Fence | 9,000.006,300.00 | 0.00 | 0.00 | 6,300.00 | 70.00 | 2,700.00 | 315.00 | ||
| G1-013 | Influent Force Main | 85,000.0085,000.00 | 0.00 | 0.00 | 85,000.00 | 100.00 | 0.00 | 4,250.00 | ||
| G1-014 | Filter Feed Force Main85,000.00 | 85,000.00 | 0.00 | 0.00 | 85,000.00 | 100.00 | 0.00 | 4,250.00 | ||
| G1-015 | Filter Effluent | 55,000.00 | 55,000.00 | 0.00 | 0.00 | 55,000.00 | 100.00 | 0.00 | 2,750.00 | |
| G1-016 | System Effluent | 55,000.00 | 55,000.00 | 0.00 | 0.00 | 55,000.00 | 100.00 | 0.00 | 2,750.00 | |
| G1-017 | Filter Feed Pump Suction25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | ||
| G1-018 | Filter Feed Pump Discharge | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G1-019 | Flocculation Tank to Filters | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G1-020 | 4" WAS | 45,000.00 | 0.00 | 4,500.00 | 0.00 | 4,500.00 | 10.00 | 40,500.00 | 225.00 | |
| G1-021 | Yard Drain | 70,000.00 | 52,500.00 | 0.00 | 0.00 | 52,500.00 | 75.00 | 17,500.00 | 2,625.00 | |
| G1-022 | Sludge Pump Suction | 25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | |
| G1-023 | Relocate Air Lines | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| G1-024 | Influent | 45,000.00 | 45,000.00 | 0.00 | 0.00 | 45,000.00 | 100.00 | 0.00 | 2,250.00 | |
| G1-025 | Utility Water | 75,000.00 | 63,750.00 | 0.00 | 0.00 | 63,750.00 | 85.00 | 11,250.00 | 3,187.50 | |
Application and Certificate For Payment -- page 3
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Project: Ridley Creek WWTP |
Application No: 17 Contractor's Job Number: P28001 Architect's Project No: |
Date: 04/30/10 Period To: 04/30/10 |
|---|
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G1-026 | Apple Brook Discharge | 15,000.00 | 14,250.00 | 0.00 | 0.00 | 14,250.00 | 95.00 | 750.00 | 712.50 | |
| G1-027 | PVC Chemical Carrier Pipe | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G1-028 | Potable Water | 45,000.00 | 38,250.00 | 0.00 | 0.00 | 38,250.00 | 85.00 | 6,750.00 | 1,912.50 | |
| G1-029 | 8" Underdrain | 40,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 75.00 | 10,000.00 | 1,500.00 | |
| G1-030 | 1" Compressed Air | 15,000.00 | 3,750.00 | 0.00 | 0.00 | 3,750.00 | 25.00 | 11,250.00 | 187.50 | |
| G1-031 | Sidewalks | 15,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 15,000.00 | 0.00 | |
| G1-032 | VOID | |||||||||
| G1-033 | VOID | |||||||||
| G1-034 | Block | 1,000.00 | 1,000.00 | 0.00 | 0.00 | 1,000.00 | 100.00 | 0.00 | 50.00 | |
| G1-035 | Chain Link Fence | 30,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 30,000.00 | 0.00 | |
| G1-036 | Demo Existing Fence | 10,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 50.00 | 5,000.00 | 250.00 | |
| Subtotal | 1,345,000.00 | 1,068,800.00 | 4,500.00 | 0.00 | 1,073,300.00 | 79.80 | 271,700.00 | 53,665.00 | ||
| G2-000 | Pump Station & Valve Vault | |||||||||
| G2-001 | Excavate Pump Station | 52,000.00 | 52,000.00 | 0.00 | 0.00 | 52,000.00 | 100.00 | 0.00 | 2,600.00 | |
| G2-002 | Install Precast Pump Station | 68,000.00 | 68,000.00 | 0.00 | 0.00 | 68,000.00 | 100.00 | 0.00 | 3,400.00 | |
| G2-003 | Install Anti-Flotation Collar | 3,500.00 | 3,500.00 | 0.00 | 0.00 | 3,500.00 | 100.00 | 0.00 | 175.00 | |
| G2-004 | Backfill Pump Station | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| G2-005 | Excavate Valve Vault | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G2-006 | Install Valve Vault | 28,000.00 | 28,000.00 | 0.00 | 0.00 | 28,000.00 | 100.00 | 0.00 | 1,400.00 | |
| G2-007 | Backfill Valve Vault | 7,500.00 | 5,625.00 | 1,875.00 | 0.00 | 7,500.00 | 100.00 | 0.00 | 375.00 | |
| G2-008 | Painting | 9,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 100.00 | 0.00 | 450.00 | |
| G2-009 | Pipe/Valves/Fittings | 15,000.00 | 14,250.00 | 0.00 | 0.00 | 14,250.00 | 95.00 | 750.00 | 712.50 | |
| G2-010 | Influent Pumps | 65,000.00 | 65,000.00 | 0.00 | 0.00 | 65,000.00 | 100.00 | 0.00 | 3,250.00 | |
| Subtotal | 275,000.00 | 272,375.00 | 1,875.00 | 0.00 | 274,250.00 | 99.73 | 750.00 | 13,712.50 | ||
| G3-000 | Screen Building | |||||||||
| G3-001 | Excavate Screen Bldg; Elev 13' | 38,000.00 | 38,000.00 | 0.00 | 0.00 | 38,000.00 | 100.00 | 0.00 | 1,900.00 | |
5
Application and Certificate For Payment -- page 4
To Owner: East Goshen Municipal Authorit
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17 | Date: 04/30/10 | Period To: 04/30/10
Contractor's Job Number: P28001
Architect's Project No:
| Item Number | Description | Scheduled Value | Work Completed Previous Application | Work Completed This Period | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo |
|---|---|---|---|---|---|---|---|---|---|---|
| G3-002 | Stone Underslab | 5,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 100.00 | 0.00 | 250.00 | |
| G3-003 | Form/Pour 18" Thick Slab | 39,000.00 | 39,000.00 | 0.00 | 0.00 | 39,000.00 | 100.00 | 0.00 | 1,950.00 | |
| G3-004 | Form/Pour Exterior Walls | 65,000.00 | 65,000.00 | 0.00 | 0.00 | 65,000.00 | 100.00 | 0.00 | 3,250.00 | |
| G3-005 | Backfill | 12,000.00 | 10,800.00 | 0.00 | 0.00 | 10,800.00 | 90.00 | 1,200.00 | 540.00 | |
| G3-006 | Excavate Footers; Elev 2'8" | 7,000.00 | 7,000.00 | 0.00 | 0.00 | 7,000.00 | 100.00 | 0.00 | 350.00 | |
| G3-007 | Form/Pour Footers | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| G3-008 | Install Masonry Frost Wall | 9,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 100.00 | 0.00 | 450.00 | |
| G3-009 | Pour Slab | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G3-010 | Form/Pour Channel Walls | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G3-011 | Install Exterior Masonry Walls | 30,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 100.00 | 0.00 | 1,500.00 | |
| G3-012 | Structural Steel | 3,000.00 | 3,000.00 | 0.00 | 0.00 | 3,000.00 | 100.00 | 0.00 | 150.00 | |
| G3-013 | Misc Metals | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G3-014 | Rough Carpentry | 24,000.00 | 24,000.00 | 0.00 | 0.00 | 24,000.00 | 100.00 | 0.00 | 1,200.00 | |
| G3-015 | Dryvit | 18,000.00 | 9,000.00 | 9,000.00 | 0.00 | 18,000.00 | 100.00 | 0.00 | 900.00 | |
| G3-016 | FRP Grating | 4,000.00 | 4,000.00 | 0.00 | 0.00 | 4,000.00 | 100.00 | 0.00 | 200.00 | |
| G3-017 | Hollow Metal & FRP Doors | 1,500.00 | 1,350.00 | 150.00 | 0.00 | 1,500.00 | 100.00 | 0.00 | 75.00 | |
| G3-018 | Overhead Doors | 17,500.00 | 17,500.00 | 0.00 | 0.00 | 17,500.00 | 100.00 | 0.00 | 875.00 | |
| G3-019 | Trolley & Hoist | 2,000.00 | 2,000.00 | 0.00 | 0.00 | 2,000.00 | 100.00 | 0.00 | 100.00 | |
| G3-020 | Plumbing | 5,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 100.00 | 0.00 | 250.00 | |
| G3-021 | HVAC | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G3-022 | Painting | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| Subtotal | 380,000.00 | 369,650.00 | 9,150.00 | 0.00 | 378,800.00 | 99.68 | 1,200.00 | 18,940.00 | ||
| G4-000 | Grinder w/RotatingScreen&Auger | |||||||||
| G4-001 | Screen | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | |
| Subtotal | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | ||
| G5-000 | PrecastPost TensionedSBR Tanks |
Application and Certificate For Payment -- page 5
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Project: Ridley Creek WWTP |
Application No: 17 Contractor's Job Number: P28001 Architect's Project No: |
Date: 04/30/10 Period To: 04/30/10 |
|---|
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G5-001 | Bulk Excavate SBR Structure | 100,000.00 | 100,000.00 | 0.00 | 0.00 | 100,000.00 | 100.00 | 0.00 | 5,000.00 | |
| G5-002 | Stone Underslab-SBR Structure | 30,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 100.00 | 0.00 | 1,500.00 | |
| G5-003 | Concrete Base Slab for SBR | 690,000.00 | 690,000.00 | 0.00 | 0.00 | 690,000.00 | 100.00 | 0.00 | 34,500.00 | |
| G5-004 | Backfill Tank | 20,000.0020,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | ||
| G5-005 | Walls & Walkways | 750,000.00 | 750,000.00 | 0.00 | 0.00 | 750,000.00 | 100.00 | 0.00 | 37,500.00 | |
| G5-006 | Misc Metals | 60,000.00 | 54,000.00 | 3,000.00 | 0.00 | 57,000.00 | 95.00 | 3,000.00 | 2,850.00 | |
| Subtotal | 1,650,000.00 | 1,644,000.00 | 3,000.00 | 0.00 | 1,647,000.00 | 99.82 | 3,000.00 | 82,350.00 | ||
| G6-000 | Treatment Building | |||||||||
| G6-001 | Excavate Footers | 40,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 100.00 | 0.00 | 2,000.00 | |
| G6-002 | Pour Footers | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G6-003 | Pour Pier Footers | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G6-004 | Pour Piers | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G6-005 | Masonry Frost Walls | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G6-006 | Backfill | 8,000.00 | 6,400.00 | 0.00 | 0.00 | 6,400.00 | 80.00 | 1,600.00 | 320.00 | |
| G6-007 | Stone Under Slab | 6,000.00 | 6,000.00 | 0.00 | 0.00 | 6,000.00 | 100.00 | 0.00 | 300.00 | |
| G6-008 | Plumbing Under Slab | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G6-009 | Concrete Slab | 18,000.00 | 17,100.00 | 0.00 | 0.00 | 17,100.00 | 95.00 | 900.00 | 855.00 | |
| G6-010 | Precast Flocculation Tank | 35,000.00 | 35,000.00 | 0.00 | 0.00 | 35,000.00 | 100.00 | 0.00 | 1,750.00 | |
| G6-011 | Precast Effluent Storage Tank | 20,000.00 | 20,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | |
| G6-012 | Poured in Place UV Channel | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G6-013 | Masonry | 72,000.00 | 72,000.00 | 0.00 | 0.00 | 72,000.00 | 100.00 | 0.00 | 3,600.00 | |
| G6-014 | Structural Steel & Deck | 28,000.00 | 28,000.00 | 0.00 | 0.00 | 28,000.00 | 100.00 | 0.00 | 1,400.00 | |
| G6-015 | Misc Metals | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G6-016 | FRP Grating | 10,000.00 | 7,500.00 | 0.00 | 0.00 | 7,500.00 | 75.00 | 2,500.00 | 375.00 | |
| G6-017 | Dryvit | 35,000.00 | 17,500.00 | 17,500.00 | 0.00 | 35,000.00 | 100.00 | 0.00 | 1,750.00 | |
| G6-018 | EPDM Roofing | 40,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 100.00 | 0.00 | 2,000.00 | |
Application and Certificate For Payment -- page 6
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Project: Ridley Creek WWTP |
Application No: 17 Contractor's Job Number: P28001 Architect's Project No: |
Date: 04/30/10 Period To: 04/30/10 |
|---|
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G6-019 | Caulking | 5,000.00 | 1,250.00 | 1,250.00 | 0.00 | 2,500.00 | 50.00 | 2,500.00 | 125.00 | |
| G6-020 | Hollow Metal & FRP Doors | 2,500.00 | 2,250.00 | 0.00 | 0.00 | 2,250.00 | 90.00 | 250.00 | 112.50 | |
| G6-021 | Overhead Doors | 19,500.00 | 19,500.00 | 0.00 | 0.00 | 19,500.00 | 100.00 | 0.00 | 975.00 | |
| G6-022 | Painting | 35,000.00 | 31,500.00 | 0.00 | 0.00 | 31,500.00 | 90.00 | 3,500.00 | 1,575.00 | |
| G6-023 | Top Entry Mixer | 20,000.00 | 20,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | |
| G6-024 | Plumbing | 23,000.00 | 21,850.00 | 1,150.00 | 0.00 | 23,000.00 | 100.00 | 0.00 | 1,150.00 | |
| G6-025 | HVAC | 50,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 80.00 | 10,000.00 | 2,000.00 | |
| Subtotal | 575,000.00 | 533,850.00 | 19,900.00 | 0.00 | 553,750.00 | 96.30 | 21,250.00 | 27,687.50 | ||
| G7-000 | SBR/Chem Feed & Process Piping | |||||||||
| G7-001 | SBR Equipment | 790,000.00 | 766,300.00 | 15,800.00 | 0.00 | 782,100.00 | 99.00 | 7,900.00 | 39,105.00 | |
| G7-002 | Polymer Feed System | 18,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 50.00 | 9,000.00 | 450.00 | |
| G7-003 | Chem Feed Pumps & Piping | 18,000.00 | 16,200.00 | 0.00 | 0.00 | 16,200.00 | 90.00 | 1,800.00 | 810.00 | |
| G7-004 | Inline Static Mixers | 25,500.00 | 25,500.00 | 0.00 | 0.00 | 25,500.00 | 100.00 | 0.00 | 1,275.00 | |
| G7-005 | Inline Grinder | 8,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,500.00 | 0.00 | |
| G7-006 | Utility Water Pumps & Controls | 80,000.00 | 80,000.00 | 0.00 | 0.00 | 80,000.00 | 100.00 | 0.00 | 4,000.00 | |
| G7-007 | Instrumentation & Controls | 127,000.00 | 107,950.00 | 0.00 | 0.00 | 107,950.00 | 85.00 | 19,050.00 | 5,397.50 | |
| G7-008 | FRP Chemical Tank | 25,000.00 | 22,500.00 | 0.00 | 0.00 | 22,500.00 | 90.00 | 2,500.00 | 1,125.00 | |
| G7-009 | Process Piping | 245,000.00 | 232,750.00 | 0.00 | 0.00 | 232,750.00 | 95.00 | 12,250.00 | 11,637.50 | |
| G7-010 | Relocated Apple Brook Pump | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| Subtotal | 1,345,000.00 | 1,268,200.00 | 15,800.00 | 0.00 | 1,284,000.00 | 95.46 | 61,000.00 | 64,200.00 | ||
| G8-000 | Filtration & UV System | |||||||||
| G8-001 | Disk Filters | 470,000.00 | 470,000.00 | 0.00 | 0.00 | 470,000.00 | 100.00 | 0.00 | 23,500.00 | |
| G8-002 | Filter Feed Pumps | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| G8-003 | UV System | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | |
| Subtotal | 660,000.00 | 650,000.00 | 0.00 | 0.00 | 650,000.00 | 98.48 | 10,000.00 | 32,500.00 | ||
| G9-000 | Sludge Digestion & Post EQTank | |||||||||
Application and Certificate For Payment -- page 7
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Project: Ridley Creek WWTP |
Application No: 17 Contractor's Job Number: P28001 Architect's Project No: |
Date: 04/30/10 Period To: 04/30/10 |
|---|
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G9-001 | Demo Interior | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| G9-002 | Sandblasting & Painting | 160,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 160,000.00 | 0.00 | |
| G9-003 | Course Bubble Diffuser | 30,000.00 | 25,550.00 | 0.00 | 0.00 | 25,550.00 | 85.17 | 4,450.00 | 1,277.50 | |
| G9-004 | Centrifugal Blower Recondition | 20,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 40.00 | 12,000.00 | 400.00 | |
| G9-005 | Aeration Tank Rehabilitation | 45,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 45,000.00 | 0.00 | |
| Subtotal | 275,000.00 | 33,550.00 | 0.00 | 0.00 | 33,550.00 | 12.20 | 241,450.00 | 1,677.50 | ||
| GG10-000 | Sludge Dewatering BldgAddition | |||||||||
| GG10-001 | Demo Centrifuge | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-002 | Demo Building | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-003 | Sawcut Floor | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-004 | Excavate Footers | 12,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 12,000.00 | 0.00 | |
| GG10-005 | Form & Pour Footers | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-006 | Masonry Frost Walls | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| GG10-007 | Backfill | 6,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 6,000.00 | 0.00 | |
| GG10-008 | Underslab Plumbing | 5,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 5,000.00 | 0.00 | |
| GG10-009 | Misc Metals | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-010 | Pour Concrete Slab | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-011 | Masonry Walls | 35,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 35,000.00 | 0.00 | |
| GG10-012 | Dryvit | 25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | |
| GG10-013 | Frames & Doors | 1,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 1,500.00 | 0.00 | |
| GG10-014 | Overhead Doors | 6,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 6,000.00 | 0.00 | |
| GG10-015 | Trolley & Hoist | 4,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 4,000.00 | 0.00 | |
| GG10-016 | Carpentry | 39,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 39,000.00 | 0.00 | |
| GG10-017 | Painting | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| GG10-018 | Plumbing | 5,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 5,000.00 | 0.00 | |
| GG10-019 | HVAC | 7,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 7,500.00 | 0.00 | |
Application and Certificate For Payment -- page 8
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Project: Ridley Creek WWTP |
Application No: 17 Contractor's Job Number: P28001 Architect's Project No: |
Date: 04/30/10 Period To: 04/30/10 |
|---|
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| GG11-000 | Sludge DewateringSystem & Pipe | |||||||||
| GG11-001 | Centrifuge | 525,000.00 | 346,215.00 | 0.00 | 0.00 | 346,215.00 | 65.95 | 178,785.00 | 17,310.75 | |
| GG11-002 | Progressive Conveying System | 7,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 7,000.00 | 0.00 | |
| GG11-003 | Sludge Conveying System | 18,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 18,000.00 | 0.00 | |
| GG11-004 | Process Pipe | 200,000.00 | 18,000.00 | 0.00 | 0.00 | 18,000.00 | 9.00 | 182,000.00 | 900.00 | |
| GG12-000 | Site Paving | |||||||||
| GG12-001 | Lump Sum | 50,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 50,000.00 | 0.00 | |
| GG13-000 | Engineered Fill | |||||||||
| GG13-001 | Lump Sum | 4,400.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 4,400.00 | 0.00 | |
| GG14-000 | Flowable Fill | |||||||||
| GG14-001 | Lump Sum | 11,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 11,000.00 | 0.00 | |
| GG18-000 | Alternate G-18 | |||||||||
| GG18-001 | Lump Sum | 125,000.00 | 0.00 | 125,000.00 | 0.00 | 125,000.00 | 100.00 | 0.00 | 6,250.00 | |
| Subtotal | 1,180,400.00 | 364,215.00 | 125,000.00 | 0.00 | 489,215.00 | 41.44 | 691,185.00 | 24,460.75 | ||
| Application Total | 7,865,400.00 | 6,384,640.00 | 179,225.00 | 0.00 | 6,563,865.00 | 83.45 | 1,301,535.00 | 328,193.25 | ||
10.
Page 1
Application and Certificate For Payment
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Phone: 267 362-1100 |
Project: Ridley Creek WWTP Contractor Job Number: P28001 Via (Architect): Contract For: |
Application No: 17 Period To: 04/30/10 Architect's Project No: Contract Date: 10/22/08 Date: 04/30/2010 |
|---|
Contractor's Application For Payment
| Change Order Summary | Additions | Deductions |
|---|---|---|
| Change orders approved in previous months by owner | ||
|
Approved this month Number: [blank] Date Approved: [blank] |
||
| Totals | ||
| Net change by change orders | ||
The undersigned Contractor certifies that to the best of the Contractor's knowledge, information, and belief the work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for work for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown herein is now due.
Contractor: Worth and Company, Inc.
By: [signature]
Date: 5/3/10
State of: PA
County of: Bucks
Subscribed and sworn to before me this 3rd day of May 2010 (year).
Notary public: Linda D. Nelson [signature]
My commission expires: Sept 19, 2010
[Seal: COMMONWEALTH OF PENNSYLVANIA Notarial Seal Linda D. Nelson, Notary Public Plumstead Twp., Bucks County My Commission Expires Sept. 19, 2010 Member, Pennsylvania Association of Notaries]
| Original contract sum | 7,865,400.00 |
|---|---|
| Net change by change orders | 0.00 |
| Contract sum to date | 7,865,400.00 |
| Total completed and stored to date | 6,563,865.00 |
| Retainage | |
| 5.0% of completed work | 328,193.25 |
| 0.0% of stored material | 0.00 |
| Total retainage | 328,193.25 |
| Total earned less retainage | 6,235,671.75 |
| Less previous certificates of payment | 6,065,408.00 |
| Current payment due | 170,263.75 |
| Balance to finish, including retainage | 1,629,728.25 |
Architect's Certificate for Payment
In accordance with the Contract Documents, based on on-site observations and the data comprising the above application the Architect certifies to the Owner that to the best of the Architect's knowledge, information and belief the Work has progressed as indicated, the quality of the Work is in accordance with the Contract Documents, and the Contractor is entitled to payment of the Amount Certified.
Amount Certified: $ [blank]
Architect:
By: [blank]
Date: [blank]
This Certification is not negotiable. The Amount Certified is payable only to the Contractor named herein. Issuance, payment, and acceptance of payment are without prejudice to any rights of the Owner or Contractor under this Contract.
Application and Certificate For Payment -- page 2
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Project: Ridley Creek WWTP |
Application No: 17 Contractor's Job Number: P28001 Architect's Project No: |
Date: 04/30/10 Period To: 04/30/10 |
|---|
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G1-000 | Site Work & Yard Piping | |||||||||
| G1-001 | Bonds | 160,000.00 | 160,000.00 | 0.00 | 0.00 | 160,000.00 | 100.00 | 0.00 | 8,000.00 | |
| G1-002 | Insurance | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G1-003 | Mobilization | 100,000.00 | 100,000.00 | 0.00 | 0.00 | 100,000.00 | 100.00 | 0.00 | 5,000.00 | |
| G1-004 | Pre-Planning/Schedule | 20,000.00 | 16,000.00 | 0.00 | 0.00 | 16,000.00 | 80.00 | 4,000.00 | 800.00 | |
| G1-005 | Submittals - Dutchland | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G1-006 | Submittals - Jet Tech | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G1-007 | E & S Controls | 25,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 60.00 | 10,000.00 | 750.00 | |
| G1-008 | Strip Topsoil | 50,000.0050,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | ||
| G1-009 | Temporary Seed | 5,000.003,000.00 | 0.00 | 0.00 | 3,000.00 | 60.00 | 2,000.00 | 150.00 | ||
| G1-010 | Bioretention Basin 1 | 20,000.000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | ||
| G1-011 | Bioretention Basin 2 | 20,000.005,000.00 | 0.00 | 0.00 | 5,000.00 | 25.00 | 15,000.00 | 250.00 | ||
| G1-012 | Temporary Fence | 9,000.006,300.00 | 0.00 | 0.00 | 6,300.00 | 70.00 | 2,700.00 | 315.00 | ||
| G1-013 | Influent Force Main | 85,000.0085,000.00 | 0.00 | 0.00 | 85,000.00 | 100.00 | 0.00 | 4,250.00 | ||
| G1-014 | Filter Feed Force Main85,000.00 | 85,000.00 | 0.00 | 0.00 | 85,000.00 | 100.00 | 0.00 | 4,250.00 | ||
| G1-015 | Filter Effluent | 55,000.00 | 55,000.00 | 0.00 | 0.00 | 55,000.00 | 100.00 | 0.00 | 2,750.00 | |
| G1-016 | System Effluent | 55,000.00 | 55,000.00 | 0.00 | 0.00 | 55,000.00 | 100.00 | 0.00 | 2,750.00 | |
| G1-017 | Filter Feed Pump Suction25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | ||
| G1-018 | Filter Feed Pump Discharge | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G1-019 | Flocculation Tank to Filters | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G1-020 | 4" WAS | 45,000.00 | 0.00 | 4,500.00 | 0.00 | 4,500.00 | 10.00 | 40,500.00 | 225.00 | |
| G1-021 | Yard Drain | 70,000.00 | 52,500.00 | 0.00 | 0.00 | 52,500.00 | 75.00 | 17,500.00 | 2,625.00 | |
| G1-022 | Sludge Pump Suction | 25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | |
| G1-023 | Relocate Air Lines | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| G1-024 | Influent | 45,000.00 | 45,000.00 | 0.00 | 0.00 | 45,000.00 | 100.00 | 0.00 | 2,250.00 | |
| G1-025 | Utility Water | 75,000.00 | 63,750.00 | 0.00 | 0.00 | 63,750.00 | 85.00 | 11,250.00 | 3,187.50 | |
12
Application and Certificate For Payment -- page 3
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Project: Ridley Creek WWTP |
Application No: 17 Contractor's Job Number: P28001 Architect's Project No: |
Date: 04/30/10 Period To: 04/30/10 |
|---|
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G1-026 | Apple Brook Discharge | 15,000.00 | 14,250.00 | 0.00 | 0.00 | 14,250.00 | 95.00 | 750.00 | 712.50 | |
| G1-027 | PVC Chemical Carrier Pipe | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G1-028 | Potable Water | 45,000.00 | 38,250.00 | 0.00 | 0.00 | 38,250.00 | 85.00 | 6,750.00 | 1,912.50 | |
| G1-029 | 8" Underdrain | 40,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 75.00 | 10,000.00 | 1,500.00 | |
| G1-030 | 1" Compressed Air | 15,000.00 | 3,750.00 | 0.00 | 0.00 | 3,750.00 | 25.00 | 11,250.00 | 187.50 | |
| G1-031 | Sidewalks | 15,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 15,000.00 | 0.00 | |
| G1-032 | VOID | |||||||||
| G1-033 | VOID | |||||||||
| G1-034 | Block | 1,000.00 | 1,000.00 | 0.00 | 0.00 | 1,000.00 | 100.00 | 0.00 | 50.00 | |
| G1-035 | Chain Link Fence | 30,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 30,000.00 | 0.00 | |
| G1-036 | Demo Existing Fence | 10,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 50.00 | 5,000.00 | 250.00 | |
| Subtotal | 1,345,000.00 | 1,068,800.00 | 4,500.00 | 0.00 | 1,073,300.00 | 79.80 | 271,700.00 | 53,665.00 | ||
| G2-000 | Pump Station & Valve Vault | |||||||||
| G2-001 | Excavate Pump Station | 52,000.00 | 52,000.00 | 0.00 | 0.00 | 52,000.00 | 100.00 | 0.00 | 2,600.00 | |
| G2-002 | Install Precast Pump Station | 68,000.00 | 68,000.00 | 0.00 | 0.00 | 68,000.00 | 100.00 | 0.00 | 3,400.00 | |
| G2-003 | Install Anti-Flotation Collar | 3,500.00 | 3,500.00 | 0.00 | 0.00 | 3,500.00 | 100.00 | 0.00 | 175.00 | |
| G2-004 | Backfill Pump Station | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| G2-005 | Excavate Valve Vault | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G2-006 | Install Valve Vault | 28,000.00 | 28,000.00 | 0.00 | 0.00 | 28,000.00 | 100.00 | 0.00 | 1,400.00 | |
| G2-007 | Backfill Valve Vault | 7,500.00 | 5,625.00 | 1,875.00 | 0.00 | 7,500.00 | 100.00 | 0.00 | 375.00 | |
| G2-008 | Painting | 9,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 100.00 | 0.00 | 450.00 | |
| G2-009 | Pipe/Valves/Fittings | 15,000.00 | 14,250.00 | 0.00 | 0.00 | 14,250.00 | 95.00 | 750.00 | 712.50 | |
| G2-010 | Influent Pumps | 65,000.00 | 65,000.00 | 0.00 | 0.00 | 65,000.00 | 100.00 | 0.00 | 3,250.00 | |
| Subtotal | 275,000.00 | 272,375.00 | 1,875.00 | 0.00 | 274,250.00 | 99.73 | 750.00 | 13,712.50 | ||
| G3-000 | Screen Building | |||||||||
| G3-001 | Excavate Screen Bldg; Elev 13' | 38,000.00 | 38,000.00 | 0.00 | 0.00 | 38,000.00 | 100.00 | 0.00 | 1,900.00 | |
13
Application and Certificate For Payment -- page 4
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Project: Ridley Creek WWTP |
Application No: 17 Contractor's Job Number: P28001 Architect's Project No: |
Date: 04/30/10 Period To: 04/30/10 |
|---|
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G3-002 | Stone Underslab | 5,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 100.00 | 0.00 | 250.00 | |
| G3-003 | Form/Pour 18" Thick Slab | 39,000.00 | 39,000.00 | 0.00 | 0.00 | 39,000.00 | 100.00 | 0.00 | 1,950.00 | |
| G3-004 | Form/Pour Exterior Walls | 65,000.00 | 65,000.00 | 0.00 | 0.00 | 65,000.00 | 100.00 | 0.00 | 3,250.00 | |
| G3-005 | Backfill | 12,000.00 | 10,800.00 | 0.00 | 0.00 | 10,800.00 | 90.00 | 1,200.00 | 540.00 | |
| G3-006 | Excavate Footers; Elev 2'8" | 7,000.00 | 7,000.00 | 0.00 | 0.00 | 7,000.00 | 100.00 | 0.00 | 350.00 | |
| G3-007 | Form/Pour Footers | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| G3-008 | Install Masony Frost Wall | 9,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 100.00 | 0.00 | 450.00 | |
| G3-009 | Pour Slab | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G3-010 | Form/Pour Channel Walls | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G3-011 | Install Exterior Masony Walls | 30,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 100.00 | 0.00 | 1,500.00 | |
| G3-012 | Structural Steel | 3,000.00 | 3,000.00 | 0.00 | 0.00 | 3,000.00 | 100.00 | 0.00 | 150.00 | |
| G3-013 | Misc Metals | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G3-014 | Rough Carpentry | 24,000.00 | 24,000.00 | 0.00 | 0.00 | 24,000.00 | 100.00 | 0.00 | 1,200.00 | |
| G3-015 | Dryvit | 18,000.00 | 9,000.00 | 9,000.00 | 0.00 | 18,000.00 | 100.00 | 0.00 | 900.00 | |
| G3-016 | FRP Grating | 4,000.00 | 4,000.00 | 0.00 | 0.00 | 4,000.00 | 100.00 | 0.00 | 200.00 | |
| G3-017 | Hollow Metal & FRP Doors | 1,500.00 | 1,350.00 | 150.000.00 | 1,500.00 | 100.00 | 0.00 | 75.00 | ||
| G3-018 | Overhead Doors | 17,500.00 | 17,500.00 | 0.00 | 0.00 | 17,500.00 | 100.00 | 0.00 | 875.00 | |
| G3-019 | Trolley & Hoist | 2,000.00 | 2,000.00 | 0.00 | 0.00 | 2,000.00 | 100.00 | 0.00 | 100.00 | |
| G3-020 | Plumbing | 5,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 100.00 | 0.00 | 250.00 | |
| G3-021 | HVAC | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G3-022 | Painting | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| Subtotal | 380,000.00 | 369,650.00 | 9,150.00 | 0.00 | 378,800.00 | 99.68 | 1,200.00 | 18,940.00 | ||
| G4-000 | Screen Building | |||||||||
| G4-001 | Grinder w/RotatingScreen&Auger | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | |
| Subtotal | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | ||
| G5-000 | PrecastPost TensionedSBR Tanks | |||||||||
14
Application and Certificate For Payment -- page 5
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Project: Ridley Creek WWTP |
Application No: 17 Contractor's Job Number: P28001 Architect's Project No: |
Date: 04/30/10 Period To: 04/30/10 |
|---|
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G5-001 | Bulk Excavate SBR Structure | 100,000.00 | 100,000.00 | 0.00 | 0.00 | 100,000.00 | 100.00 | 0.00 | 5,000.00 | |
| G5-002 | Stone Underslab-SBR Structure | 30,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 100.00 | 0.00 | 1,500.00 | |
| G5-003 | Concrete Base Slab for SBR | 690,000.00 | 690,000.00 | 0.00 | 0.00 | 690,000.00 | 100.00 | 0.00 | 34,500.00 | |
| G5-004 | Backfill Tank | 20,000.0020,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | ||
| G5-005 | Walls & Walkways | 750,000.00 | 750,000.00 | 0.00 | 0.00 | 750,000.00 | 100.00 | 0.00 | 37,500.00 | |
| G5-006 | Misc Metals | 60,000.00 | 54,000.00 | 3,000.00 | 0.00 | 57,000.00 | 95.00 | 3,000.00 | 2,850.00 | |
| Subtotal | 1,650,000.00 | 1,644,000.00 | 3,000.00 | 0.00 | 1,647,000.00 | 99.82 | 3,000.00 | 82,350.00 | ||
| G6-000 | Treatment Building | |||||||||
| G6-001 | Excavate Footers | 40,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 100.00 | 0.00 | 2,000.00 | |
| G6-002 | Pour Footers | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G6-003 | Pour Pier Footers | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G6-004 | Pour Piers | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G6-005 | Masonry Frost Walls | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G6-006 | Backfill | 8,000.00 | 6,400.00 | 0.00 | 0.00 | 6,400.00 | 80.00 | 1,600.00 | 320.00 | |
| G6-007 | Stone Under Slab | 6,000.00 | 6,000.00 | 0.00 | 0.00 | 6,000.00 | 100.00 | 0.00 | 300.00 | |
| G6-008 | Plumbing Under Slab | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G6-009 | Concrete Slab | 18,000.00 | 17,100.00 | 0.00 | 0.00 | 17,100.00 | 95.00 | 900.00 | 855.00 | |
| G6-010 | Precast Flocculation Tank | 35,000.00 | 35,000.00 | 0.00 | 0.00 | 35,000.00 | 100.00 | 0.00 | 1,750.00 | |
| G6-011 | Precast Effluent Storage Tank | 20,000.00 | 20,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | |
| G6-012 | Poured in Place UV Channel | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G6-013 | Masonry | 72,000.00 | 72,000.00 | 0.00 | 0.00 | 72,000.00 | 100.00 | 0.00 | 3,600.00 | |
| G6-014 | Structural Steel & Deck | 28,000.00 | 28,000.00 | 0.00 | 0.00 | 28,000.00 | 100.00 | 0.00 | 1,400.00 | |
| G6-015 | Misc Metals | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G6-016 | FRP Grating | 10,000.00 | 7,500.00 | 0.00 | 0.00 | 7,500.00 | 75.002,500.00 | 375.00 | ||
| G6-017 | Dryvit | 35,000.00 | 17,500.00 | 17,500.00 | 0.00 | 35,000.00 | 100.00 | 0.00 | 1,750.00 | |
| G6-018 | EPDM Roofing | 40,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 100.00 | 0.00 | 2,000.00 | |
15
Application and Certificate For Payment -- page 6
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Project: Ridley Creek WWTP |
Application No: 17 Contractor's Job Number: P28001 Architect's Project No: |
Date: 04/30/10 Period To: 04/30/10 |
|---|
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G6-019 | Caulking | 5,000.00 | 1,250.00 | 1,250.00 | 0.00 | 2,500.00 | 50.00 | 2,500.00 | 125.00 | |
| G6-020 | Hollow Metal & FRP Doors | 2,500.00 | 2,250.00 | 0.00 | 0.00 | 2,250.00 | 90.00 | 250.00 | 112.50 | |
| G6-021 | Overhead Doors | 19,500.00 | 19,500.00 | 0.00 | 0.00 | 19,500.00 | 100.00 | 0.00 | 975.00 | |
| G6-022 | Painting | 35,000.00 | 31,500.00 | 0.00 | 0.00 | 31,500.00 | 90.00 | 3,500.00 | 1,575.00 | |
| G6-023 | Top Entry Mixer | 20,000.00 | 20,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | |
| G6-024 | Plumbing | 23,000.00 | 21,850.00 | 1,150.00 | 0.00 | 23,000.00 | 100.00 | 0.00 | 1,150.00 | |
| G6-025 | HVAC | 50,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 80.00 | 10,000.00 | 2,000.00 | |
| Subtotal | 575,000.00 | 533,850.00 | 19,900.00 | 0.00 | 553,750.00 | 96.30 | 21,250.00 | 27,687.50 | ||
| G7-000 | SBR/Chem Feed & Process Piping | |||||||||
| G7-001 | SBR Equipment | 790,000.00 | 766,300.00 | 15,800.000.00 | 782,100.00 | 99.00 | 7,900.00 | 39,105.00 | ||
| G7-002 | Polymer Feed System | 18,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 50.00 | 9,000.00 | 450.00 | |
| G7-003 | Chem Feed Pumps & Piping | 18,000.00 | 16,200.00 | 0.00 | 0.00 | 16,200.00 | 90.00 | 1,800.00 | 810.00 | |
| G7-004 | Inline Static Mixers | 25,500.00 | 25,500.00 | 0.00 | 0.00 | 25,500.00 | 100.00 | 0.00 | 1,275.00 | |
| G7-005 | Inline Grinder | 8,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,500.00 | 0.00 | |
| G7-006 | Utility Water Pumps & Controls | 80,000.00 | 80,000.00 | 0.00 | 0.00 | 80,000.00 | 100.00 | 0.00 | 4,000.00 | |
| G7-007 | Instrumentation & Controls | 127,000.00 | 107,950.00 | 0.00 | 0.00 | 107,950.00 | 85.00 | 19,050.00 | 5,397.50 | |
| G7-008 | FRP Chemical Tank | 25,000.00 | 22,500.00 | 0.00 | 0.00 | 22,500.00 | 90.00 | 2,500.00 | 1,125.00 | |
| G7-009 | Process Piping | 245,000.00 | 232,750.00 | 0.00 | 0.00 | 232,750.00 | 95.00 | 12,250.00 | 11,637.50 | |
| G7-010 | Relocated Apple Brook Pump | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| Subtotal | 1,345,000.00 | 1,268,200.00 | 15,800.00 | 0.00 | 1,284,000.00 | 95.46 | 61,000.00 | 64,200.00 | ||
| G8-000 | Filtration & UV System | |||||||||
| G8-001 | Disk Filters | 470,000.00 | 470,000.00 | 0.00 | 0.00 | 470,000.00 | 100.00 | 0.00 | 23,500.00 | |
| G8-002 | Filter Feed Pumps | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| G8-003 | UV System | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | |
| Subtotal | 660,000.00 | 650,000.00 | 0.00 | 0.00 | 650,000.00 | 98.48 | 10,000.00 | 32,500.00 | ||
| G9-000 | Sludge Digestion & Post EQ Tank | |||||||||
16
Application and Certificate For Payment -- page 7
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Project: Ridley Creek WWTP |
Application No: 17 Contractor's Job Number: P28001 Architect's Project No: |
Date: 04/30/10 Period To: 04/30/10 |
|---|
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G9-001 | Demo Interior | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| G9-002 | Sandblasting & Painting | 160,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 160,000.00 | 0.00 | |
| G9-003 | Course Bubble Diffuser | 30,000.00 | 25,550.00 | 0.00 | 0.00 | 25,550.00 | 85.17 | 4,450.00 | 1,277.50 | |
| G9-004 | Centrifugal Blower Recondition | 20,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 40.00 | 12,000.00 | 400.00 | |
| G9-005 | Aeration Tank Rehabilitation | 45,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 45,000.00 | 0.00 | |
| Subtotal | 275,000.00 | 33,550.00 | 0.00 | 0.00 | 33,550.00 | 12.20 | 241,450.00 | 1,677.50 | ||
| GG10-000 | Sludge Dewatering BldgAddition | |||||||||
| GG10-001 | Demo Centrifuge | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-002 | Demo Building | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-003 | Sawcut Floor | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-004 | Excavate Footers | 12,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 12,000.00 | 0.00 | |
| GG10-005 | Form & Pour Footers | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-006 | Masonry Frost Walls | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| GG10-007 | Backfill | 6,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 6,000.00 | 0.00 | |
| GG10-008 | Underslab Plumbing | 5,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 5,000.00 | 0.00 | |
| GG10-009 | Misc Metals | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-010 | Pour Concrete Slab | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-011 | Masonry Walls | 35,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 35,000.00 | 0.00 | |
| GG10-012 | Dryvit | 25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | |
| GG10-013 | Frames & Doors | 1,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 1,500.00 | 0.00 | |
| GG10-014 | Overhead Doors | 6,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 6,000.00 | 0.00 | |
| GG10-015 | Trolley & Hoist | 4,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 4,000.00 | 0.00 | |
| GG10-016 | Carpentry | 39,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 39,000.00 | 0.00 | |
| GG10-017 | Painting | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| GG10-018 | Plumbing | 5,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 5,000.00 | 0.00 | |
| GG10-019 | HVAC | 7,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 7,500.00 | 0.00 | |
17
Application and Certificate For Payment -- page 8
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Project: Ridley Creek WWTP |
Application No: 17 Contractor's Job Number: P28001 Architect's Project No: |
Date: 04/30/10 Period To: 04/30/10 |
|---|
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| GG11-000 | Sludge DewateringSystem & Pipe | |||||||||
| GG11-001 | Centrifuge | 525,000.00 | 346,215.00 | 0.00 | 0.00 | 346,215.00 | 65.95 | 178,785.00 | 17,310.75 | |
| GG11-002 | Progressive Conveying System | 7,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 7,000.00 | 0.00 | |
| GG11-003 | Sludge Conveying System | 18,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 18,000.00 | 0.00 | |
| GG11-004 | Process Pipe | 200,000.00 | 18,000.00 | 0.00 | 0.00 | 18,000.00 | 9.00 | 182,000.00 | 900.00 | |
| GG12-000 | Site Paving | |||||||||
| GG12-001 | Lump Sum | 50,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 50,000.00 | 0.00 | |
| GG13-000 | Engineered Fill | |||||||||
| GG13-001 | Lump Sum | 4,400.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 4,400.00 | 0.00 | |
| GG14-000 | Flowable Fill | |||||||||
| GG14-001 | Lump Sum | 11,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 11,000.00 | 0.00 | |
| GG18-000 | Alternate G-18 | |||||||||
| GG18-001 | Lump Sum | 125,000.00 | 0.00 | 125,000.00 | 0.00 | 125,000.00 | 100.00 | 0.00 | 6,250.00 | |
| Subtotal | 1,180,400.00 | 364,215.00 | 125,000.00 | 0.00 | 489,215.00 | 41.44 | 691,185.00 | 24,460.75 | ||
| Application Total | 7,865,400.00 | 6,384,640.00 | 179,225.00 | 0.00 | 6,563,865.00 | 83.45 | 1,301,535.00 | 328,193.25 | ||
18.
Page 1
Application and Certificate For Payment
|
To Owner: East Goshen Municipal Authorit From (Contractor): Worth and Company, Inc. Phone: 267 362-1100 |
Project: Ridley Creek WWTP Contractor Job Number: P28001 Via (Architect): Contract For: |
Application No: 17 Period To: 04/30/10 Architect's Project No: Contract Date: 10/22/08 Date: 04/30/2010 |
|---|
Contractor's Application For Payment
| Change Order Summary | Additions | Deductions |
|---|---|---|
| Change orders approved in previous months by owner | ||
|
Approved this month Number: [blank] Date Approved: [blank] |
||
| Totals | ||
| Net change by change orders | ||
The undersigned Contractor certifies that to the best of the Contractor's knowledge, information, and belief the work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for work for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown herein is now due.
Contractor: Worth and Company, Inc.
By: [signature]
Date: 5/3/10
State of: PA
County of: Bucks
Subscribed and sworn to before me this 3rd day of May 2010 (year).
Notary public: Linda D. Nelson [signature]
My commission expires: [blank]
[Seal: COMMONWEALTH OF PENNSYLVANIA Notarial Seal Linda D. Nelson, Notary Public Plumstead Twp., Bucks County My Commission Expires Sept. 19, 2010 Member, Pennsylvania Association of Notaries]
| Original contract sum | 7,865,400.00 |
|---|---|
| Net change by change orders | 0.00 |
| Contract sum to date | 7,865,400.00 |
| Total completed and stored to date | 6,563,865.00 |
| Retainage | |
| 5.0% of completed work | 328,193.25 |
| 0.0% of stored material | 0.00 |
| Total retainage | 328,193.25 |
| Total earned less retainage | 6,235,671.75 |
| Less previous certificates of payment | 6,065,408.00 |
| Current payment due | 170,263.75 |
| Balance to finish, including retainage | 1,629,728.25 |
Architect's Certificate for Payment
In accordance with the Contract Documents, based on on-site observations and the data comprising the above application the Architect certifies to the Owner that to the best of the Architect's knowledge, information and belief the Work has progressed as indicated, the quality of the Work is in accordance with the Contract Documents, and the Contractor is entitled to payment of the Amount Certified.
Amount Certified: $ [blank]
Architect:
By: [blank]
Date: [blank]
This Certification is not negotiable. The Amount Certified is payable only to the Contractor named herein. Issuance, payment, and acceptance of payment are without prejudice to any rights of the Owner or Contractor under this Contract.
Application and Certificate For Payment -- page 2
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G1-000 | Site Work & Yard Piping | |||||||||
| G1-001 | Bonds | 160,000.00 | 160,000.00 | 0.00 | 0.00 | 160,000.00 | 100.00 | 0.00 | 8,000.00 | |
| G1-002 | Insurance | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G1-003 | Mobilization | 100,000.00 | 100,000.00 | 0.00 | 0.00 | 100,000.00 | 100.00 | 0.00 | 5,000.00 | |
| G1-004 | Pre-Planning/Schedule | 20,000.00 | 16,000.00 | 0.00 | 0.00 | 16,000.00 | 80.00 | 4,000.00 | 800.00 | |
| G1-005 | Submittals - Dutchland | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G1-006 | Submittals - Jet Tech | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G1-007 | E & S Controls | 25,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 60.00 | 10,000.00 | 750.00 | |
| G1-008 | Strip Topsoil | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G1-009 | Temporary Seed | 5,000.00 | 3,000.00 | 0.00 | 0.00 | 3,000.00 | 60.00 | 2,000.00 | 150.00 | |
| G1-010 | Bioretention Basin 1 | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| G1-011 | Bioretention Basin 2 | 20,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 25.00 | 15,000.00 | 250.00 | |
| G1-012 | Temporary Fence | 9,000.00 | 6,300.00 | 0.00 | 0.00 | 6,300.00 | 70.00 | 2,700.00 | 315.00 | |
| G1-013 | Influent Force Main | 85,000.00 | 85,000.00 | 0.00 | 0.00 | 85,000.00 | 100.00 | 0.00 | 4,250.00 | |
| G1-014 | Filter Feed Force Main | 85,000.00 | 85,000.00 | 0.00 | 0.00 | 85,000.00 | 100.00 | 0.00 | 4,250.00 | |
| G1-015 | Filter Effluent | 55,000.00 | 55,000.00 | 0.00 | 0.00 | 55,000.00 | 100.00 | 0.00 | 2,750.00 | |
| G1-016 | System Effluent | 55,000.00 | 55,000.00 | 0.00 | 0.00 | 55,000.00 | 100.00 | 0.00 | 2,750.00 | |
| G1-017 | Filter Feed Pump Suction | 25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | |
| G1-018 | Filter Feed Pump Discharge | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G1-019 | Flocculation Tank to Filters | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G1-020 | 4" WAS | 45,000.00 | 0.00 | 4,500.00 | 0.00 | 4,500.00 | 10.00 | 40,500.00 | 225.00 | |
| G1-021 | Yard Drain | 70,000.00 | 52,500.00 | 0.00 | 0.00 | 52,500.00 | 75.00 | 17,500.00 | 2,625.00 | |
| G1-022 | Sludge Pump Suction | 25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | |
| G1-023 | Relocate Air Lines | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| G1-024 | Influent | 45,000.00 | 45,000.00 | 0.00 | 0.00 | 45,000.00 | 100.00 | 0.00 | 2,250.00 | |
| G1-025 | Utility Water | 75,000.00 | 63,750.00 | 0.00 | 0.00 | 63,750.00 | 85.00 | 11,250.00 | 3,187.50 | |
Application and Certificate For Payment -- page 3
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G1-026 | Apple Brook Discharge | 15,000.00 | 14,250.00 | 0.00 | 0.00 | 14,250.00 | 95.00 | 750.00 | 712.50 | |
| G1-027 | PVC Chemical Carrier Pipe | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G1-028 | Potable Water | 45,000.00 | 38,250.00 | 0.00 | 0.00 | 38,250.00 | 85.00 | 6,750.00 | 1,912.50 | |
| G1-029 | 8" Underdrain | 40,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 75.00 | 10,000.00 | 1,500.00 | |
| G1-030 | 1" Compressed Air | 15,000.00 | 3,750.00 | 0.00 | 0.00 | 3,750.00 | 25.00 | 11,250.00 | 187.50 | |
| G1-031 | Sidewalks | 15,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 15,000.00 | 0.00 | |
| G1-032 | VOID | |||||||||
| G1-033 | VOID | |||||||||
| G1-034 | Block | 1,000.00 | 1,000.00 | 0.00 | 0.00 | 1,000.00 | 100.00 | 0.00 | 50.00 | |
| G1-035 | Chain Link Fence | 30,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 30,000.00 | 0.00 | |
| G1-036 | Demo Existing Fence | 10,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 50.00 | 5,000.00 | 250.00 | |
| Subtotal | 1,345,000.00 | 1,068,800.00 | 4,500.00 | 0.00 | 1,073,300.00 | 79.80 | 271,700.00 | 53,665.00 | ||
| G2-000 | Pump Station & Valve Vault | |||||||||
| G2-001 | Excavate Pump Station | 52,000.00 | 52,000.00 | 0.00 | 0.00 | 52,000.00 | 100.00 | 0.00 | 2,600.00 | |
| G2-002 | Install Precast Pump Station | 68,000.00 | 68,000.00 | 0.00 | 0.00 | 68,000.00 | 100.00 | 0.00 | 3,400.00 | |
| G2-003 | Install Anti-Flotation Collar | 3,500.00 | 3,500.00 | 0.00 | 0.00 | 3,500.00 | 100.00 | 0.00 | 175.00 | |
| G2-004 | Backfill Pump Station | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| G2-005 | Excavate Valve Vault | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G2-006 | Install Valve Vault | 28,000.00 | 28,000.00 | 0.00 | 0.00 | 28,000.00 | 100.00 | 0.00 | 1,400.00 | |
| G2-007 | Backfill Valve Vault | 7,500.00 | 5,625.00 | 1,875.00 | 0.00 | 7,500.00 | 100.00 | 0.00 | 375.00 | |
| G2-008 | Painting | 9,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 100.00 | 0.00 | 450.00 | |
| G2-009 | Pipe/Valves/Fittings | 15,000.00 | 14,250.00 | 0.00 | 0.00 | 14,250.00 | 95.00 | 750.00 | 712.50 | |
| G2-010 | Influent Pumps | 65,000.00 | 65,000.00 | 0.00 | 0.00 | 65,000.00 | 100.00 | 0.00 | 3,250.00 | |
| Subtotal | 275,000.00 | 272,375.00 | 1,875.00 | 0.00 | 274,250.00 | 99.73 | 750.00 | 13,712.50 | ||
| G3-000 | Screen Building | |||||||||
| G3-001 | Excavate Screen Bldg; Elev 13' | 38,000.00 | 38,000.00 | 0.00 | 0.00 | 38,000.00 | 100.00 | 0.00 | 1,900.00 | |
Application and Certificate For Payment -- page 4
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G3-002 | Stone Underslab | 5,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 100.00 | 0.00 | 250.00 | |
| G3-003 | Form/Pour 18" Thick Slab | 39,000.00 | 39,000.00 | 0.00 | 0.00 | 39,000.00 | 100.00 | 0.00 | 1,950.00 | |
| G3-004 | Form/Pour Exterior Walls | 65,000.00 | 65,000.00 | 0.00 | 0.00 | 65,000.00 | 100.00 | 0.00 | 3,250.00 | |
| G3-005 | Backfill | 12,000.00 | 10,800.00 | 0.00 | 0.00 | 10,800.00 | 90.00 | 1,200.00 | 540.00 | |
| G3-006 | Excavate Footers; Elev 2'8" | 7,000.00 | 7,000.00 | 0.00 | 0.00 | 7,000.00 | 100.00 | 0.00 | 350.00 | |
| G3-007 | Form/Pour Footers | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| G3-008 | Install Masonry Frost Wall | 9,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 100.00 | 0.00 | 450.00 | |
| G3-009 | Pour Slab | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G3-010 | Form/Pour Channel Walls | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G3-011 | Install Exterior Masonry Walls | 30,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 100.00 | 0.00 | 1,500.00 | |
| G3-012 | Structural Steel | 3,000.00 | 3,000.00 | 0.00 | 0.00 | 3,000.00 | 100.00 | 0.00 | 150.00 | |
| G3-013 | Misc Metals | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G3-014 | Rough Carpentry | 24,000.00 | 24,000.00 | 0.00 | 0.00 | 24,000.00 | 100.00 | 0.00 | 1,200.00 | |
| G3-015 | Dryvit | 18,000.00 | 9,000.00 | 9,000.00 | 0.00 | 18,000.00 | 100.00 | 0.00 | 900.00 | |
| G3-016 | FRP Grating | 4,000.00 | 4,000.00 | 0.00 | 0.00 | 4,000.00 | 100.00 | 0.00 | 200.00 | |
| G3-017 | Hollow Metal & FRP Doors | 1,500.00 | 1,350.00 | 150.00 | 0.00 | 1,500.00 | 100.00 | 0.00 | 75.00 | |
| G3-018 | Overhead Doors | 17,500.00 | 17,500.00 | 0.00 | 0.00 | 17,500.00 | 100.00 | 0.00 | 875.00 | |
| G3-019 | Trolley & Hoist | 2,000.00 | 2,000.00 | 0.00 | 0.00 | 2,000.00 | 100.00 | 0.00 | 100.00 | |
| G3-020 | Plumbing | 5,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 100.00 | 0.00 | 250.00 | |
| G3-021 | HVAC | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G3-022 | Painting | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| Subtotal | 380,000.00 | 369,650.00 | 9,150.00 | 0.00 | 378,800.00 | 99.68 | 1,200.00 | 18,940.00 | ||
| G4-000 | Screen | |||||||||
| G4-001 | Grinder w/RotatingScreen&Auger | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | |
| Subtotal | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | ||
| G5-000 | PrecastPost TensionedSBR Tanks | |||||||||
Application and Certificate For Payment -- page 5
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G5-001 | Bulk Excavate SBR Structure | 100,000.00 | 100,000.00 | 0.00 | 0.00 | 100,000.00 | 100.00 | 0.00 | 5,000.00 | |
| G5-002 | Stone Underslab-SBR Structure | 30,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 100.00 | 0.00 | 1,500.00 | |
| G5-003 | Concrete Base Slab for SBR | 690,000.00 | 690,000.00 | 0.00 | 0.00 | 690,000.00 | 100.00 | 0.00 | 34,500.00 | |
| G5-004 | Backfill Tank | 20,000.00 | 20,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | |
| G5-005 | Walls & Walkways | 750,000.00 | 750,000.00 | 0.00 | 0.00 | 750,000.00 | 100.00 | 0.00 | 37,500.00 | |
| G5-006 | Misc Metals | 60,000.00 | 54,000.00 | 3,000.00 | 0.00 | 57,000.00 | 95.00 | 3,000.00 | 2,850.00 | |
| Subtotal | 1,650,000.00 | 1,644,000.00 | 3,000.00 | 0.00 | 1,647,000.00 | 99.82 | 3,000.00 | 82,350.00 | ||
| G6-000 | Treatment Building | |||||||||
| G6-001 | Excavate Footers | 40,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 100.00 | 0.00 | 2,000.00 | |
| G6-002 | Pour Footers | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G6-003 | Pour Pier Footers | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G6-004 | Pour Piers | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G6-005 | Masonry Frost Walls | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G6-006 | Backfill | 8,000.00 | 6,400.00 | 0.00 | 0.00 | 6,400.00 | 80.00 | 1,600.00 | 320.00 | |
| G6-007 | Stone Under Slab | 6,000.00 | 6,000.00 | 0.00 | 0.00 | 6,000.00 | 100.00 | 0.00 | 300.00 | |
| G6-008 | Plumbing Under Slab | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G6-009 | Concrete Slab | 18,000.00 | 17,100.00 | 0.00 | 0.00 | 17,100.00 | 95.00 | 900.00 | 855.00 | |
| G6-010 | Precast Flocculation Tank | 35,000.00 | 35,000.00 | 0.00 | 0.00 | 35,000.00 | 100.00 | 0.00 | 1,750.00 | |
| G6-011 | Precast Effluent Storage Tank | 20,000.00 | 20,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | |
| G6-012 | Poured in Place UV Channel | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G6-013 | Masonry | 72,000.00 | 72,000.00 | 0.00 | 0.00 | 72,000.00 | 100.00 | 0.00 | 3,600.00 | |
| G6-014 | Structural Steel & Deck | 28,000.00 | 28,000.00 | 0.00 | 0.00 | 28,000.00 | 100.00 | 0.00 | 1,400.00 | |
| G6-015 | Misc Metals | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G6-016 | FRP Grating | 10,000.00 | 7,500.00 | 0.00 | 0.00 | 7,500.00 | 75.00 | 2,500.00 | 375.00 | |
| G6-017 | Dryvit | 35,000.00 | 17,500.00 | 17,500.00 | 0.00 | 35,000.00 | 100.00 | 0.00 | 1,750.00 | |
| G6-018 | EPDM Roofing | 40,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 100.00 | 0.00 | 2,000.00 | |
Application and Certificate For Payment -- page 6
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G6-019 | Caulking | 5,000.00 | 1,250.00 | 1,250.00 | 0.00 | 2,500.00 | 50.00 | 2,500.00 | 125.00 | |
| G6-020 | Hollow Metal & FRP Doors | 2,500.00 | 2,250.00 | 0.00 | 0.00 | 2,250.00 | 90.00 | 250.00 | 112.50 | |
| G6-021 | Overhead Doors | 19,500.00 | 19,500.00 | 0.00 | 0.00 | 19,500.00 | 100.00 | 0.00 | 975.00 | |
| G6-022 | Painting | 35,000.00 | 31,500.00 | 0.00 | 0.00 | 31,500.00 | 90.00 | 3,500.00 | 1,575.00 | |
| G6-023 | Top Entry Mixer | 20,000.00 | 20,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | |
| G6-024 | Plumbing | 23,000.00 | 21,850.00 | 1,150.00 | 0.00 | 23,000.00 | 100.00 | 0.00 | 1,150.00 | |
| G6-025 | HVAC | 50,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 80.00 | 10,000.00 | 2,000.00 | |
| Subtotal | 575,000.00 | 533,850.00 | 19,900.00 | 0.00 | 553,750.00 | 96.30 | 21,250.00 | 27,687.50 | ||
| G7-000 | SBR/Chem Feed & Process Piping | |||||||||
| G7-001 | SBR Equipment | 790,000.00 | 766,300.00 | 15,800.00 | 0.00 | 782,100.00 | 99.00 | 7,900.00 | 39,105.00 | |
| G7-002 | Polymer Feed System | 18,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 50.00 | 9,000.00 | 450.00 | |
| G7-003 | Chem Feed Pumps & Piping | 18,000.00 | 16,200.00 | 0.00 | 0.00 | 16,200.00 | 90.00 | 1,800.00 | 810.00 | |
| G7-004 | Inline Static Mixers | 25,500.00 | 25,500.00 | 0.00 | 0.00 | 25,500.00 | 100.00 | 0.00 | 1,275.00 | |
| G7-005 | Inline Grinder | 8,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,500.00 | 0.00 | |
| G7-006 | Utility Water Pumps & Controls | 80,000.00 | 80,000.00 | 0.00 | 0.00 | 80,000.00 | 100.00 | 0.00 | 4,000.00 | |
| G7-007 | Instrumentation & Controls | 127,000.00 | 107,950.00 | 0.00 | 0.00 | 107,950.00 | 85.00 | 19,050.00 | 5,397.50 | |
| G7-008 | FRP Chemical Tank | 25,000.00 | 22,500.00 | 0.00 | 0.00 | 22,500.00 | 90.00 | 2,500.00 | 1,125.00 | |
| G7-009 | Process Piping | 245,000.00 | 232,750.00 | 0.00 | 0.00 | 232,750.00 | 95.00 | 12,250.00 | 11,637.50 | |
| G7-010 | Relocated Apple Brook Pump | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| Subtotal | 1,345,000.00 | 1,268,200.00 | 15,800.00 | 0.00 | 1,284,000.00 | 95.46 | 61,000.00 | 64,200.00 | ||
| G8-000 | Filtration & UV System | |||||||||
| G8-001 | Disk Filters | 470,000.00 | 470,000.00 | 0.00 | 0.00 | 470,000.00 | 100.00 | 0.00 | 23,500.00 | |
| G8-002 | Filter Feed Pumps | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| G8-003 | UV System | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | |
| Subtotal | 660,000.00 | 650,000.00 | 0.00 | 0.00 | 650,000.00 | 98.48 | 10,000.00 | 32,500.00 | ||
| G9-000 | Sludge Digestion & Post EQ Tank | |||||||||
Application and Certificate For Payment -- page 7
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G9-001 | Demo Interior | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| G9-002 | Sandblasting & Painting | 160,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 160,000.00 | 0.00 | |
| G9-003 | Course Bubble Diffuser | 30,000.00 | 25,550.00 | 0.00 | 0.00 | 25,550.00 | 85.17 | 4,450.00 | 1,277.50 | |
| G9-004 | Centrifugal Blower Recondition | 20,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 40.00 | 12,000.00 | 400.00 | |
| G9-005 | Aeration Tank Rehabilitation | 45,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 45,000.00 | 0.00 | |
| Subtotal | 275,000.00 | 33,550.00 | 0.00 | 0.00 | 33,550.00 | 12.20 | 241,450.00 | 1,677.50 | ||
| GG10-000 | Sludge Dewatering BldgAddition | |||||||||
| GG10-001 | Demo Centrifuge | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-002 | Demo Building | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-003 | Sawcut Floor | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-004 | Excavate Footers | 12,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 12,000.00 | 0.00 | |
| GG10-005 | Form & Pour Footers | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-006 | Masonry Frost Walls | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| GG10-007 | Backfill | 6,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 6,000.00 | 0.00 | |
| GG10-008 | Underslab Plumbing | 5,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 5,000.00 | 0.00 | |
| GG10-009 | Misc Metals | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-010 | Pour Concrete Slab | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-011 | Masonry Walls | 35,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 35,000.00 | 0.00 | |
| GG10-012 | Dryvit | 25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | |
| GG10-013 | Frames & Doors | 1,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 1,500.00 | 0.00 | |
| GG10-014 | Overhead Doors | 6,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 6,000.00 | 0.00 | |
| GG10-015 | Trolley & Hoist | 4,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 4,000.00 | 0.00 | |
| GG10-016 | Carpentry | 39,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 39,000.00 | 0.00 | |
| GG10-017 | Painting | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| GG10-018 | Plumbing | 5,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 5,000.00 | 0.00 | |
| GG10-019 | HVAC | 7,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 7,500.00 | 0.00 | |
Application and Certificate For Payment -- page 8
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| GG11-000 | Sludge DewateringSystem & Pipe | |||||||||
| GG11-001 | Centrifuge | 525,000.00 | 346,215.00 | 0.00 | 0.00 | 346,215.00 | 65.95 | 178,785.00 | 17,310.75 | |
| GG11-002 | Progressive Conveying System | 7,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 7,000.00 | 0.00 | |
| GG11-003 | Sludge Conveying System | 18,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 18,000.00 | 0.00 | |
| GG11-004 | Process Pipe | 200,000.00 | 18,000.00 | 0.00 | 0.00 | 18,000.00 | 9.00 | 182,000.00 | 900.00 | |
| GG12-000 | Site Paving | |||||||||
| GG12-001 | Lump Sum | 50,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 50,000.00 | 0.00 | |
| GG13-000 | Engineered Fill | |||||||||
| GG13-001 | Lump Sum | 4,400.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 4,400.00 | 0.00 | |
| GG14-000 | Flowable Fill | |||||||||
| GG14-001 | Lump Sum | 11,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 11,000.00 | 0.00 | |
| GG18-000 | Alternate G-18 | |||||||||
| GG18-001 | Lump Sum | 125,000.00 | 0.00 | 125,000.00 | 0.00 | 125,000.00 | 100.00 | 0.00 | 6,250.00 | |
| Subtotal | 1,180,400.00 | 364,215.00 | 125,000.00 | 0.00 | 489,215.00 | 41.44 | 691,185.00 | 24,460.75 | ||
| Application Total | 7,865,400.00 | 6,384,640.00 | 179,225.00 | 0.00 | 6,563,865.00 | 83.45 | 1,301,535.00 | 328,193.25 | ||
Application and Certificate For Payment
Page 1
To Owner: East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380
Project: Ridley Creek WWTP
1751 Towne Road
Fred Papiernik 267-278-6108
West Chester, PA 19380
Application No: 17
Date: 04/30/2010
Period To: 04/30/10
Architect's Project No:
Contract Date: 10/22/08
From (Contractor): Worth and Company, Inc.
6263 Kellers Church Road
Pipersville, PA 18947
Phone: 267 362-1100
Contractor Job Number: P28001
Via (Architect):
Contract For:
Contractor's Application For Payment
| Change Order Summary | Additions | Deductions | ||
|---|---|---|---|---|
| Change orders approved in previous months by owner | ||||
| Number | Date Approved | |||
| Change orders approved this month | ||||
| Totals | ||||
| Net change by change orders | ||||
| Original contract sum | 7,865,400.00 |
|---|---|
| Net change by change orders | 0.00 |
| Contract sum to date | 7,865,400.00 |
| Total completed and stored to date | 6,563,865.00 |
| Retainage | |
| 5.0% of completed work | 328,193.25 |
| 0.0% of stored material | 0.00 |
| Total retainage | 328,193.25 |
| Total earned less retainage | 6,235,671.75 |
| Less previous certificates of payment | 6,065,408.00 |
| Current payment due | 170,263.75 |
| Balance to finish, including retainage | 1,629,728.25 |
The undersigned Contractor certifies that to the best of the Contractor's knowledge, information and belief the work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for work for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown herein is now due.
Contractor: Worth and Company, Inc.
By: [signature]
Date: 5/3/10
State of: PA
County of: Bucks
Subscribed and sworn to before me this 3rd day of May 2010 (year).
Notary public: Linda D. Neilson [signature]
My commission expires: Sept. 19, 2010
[Seal: Commonwealth of Pennsylvania, Notarial Seal, Linda D. Neilson, Notary Public, Plumstead Twp., Bucks County, My Commission Expires Sept. 19, 2010, Member, Pennsylvania Association of Notaries]
Architect's Certificate for Payment
In accordance with the Contract Documents, based on on-site observations and the data comprising the above application the Architect certifies to the Owner that to the best of the Architect's knowledge, information and belief the Work has progressed as indicated, the quality of the Work is in accordance with the Contract Documents, and the Contractor is entitled to payment of the Amount Certified.
Amount Certified: $__________
Architect:
By: __________ Date: __________
This Certification is not negotiable. The Amount Certified is payable only to the Contractor named herein. Issuance, payment, and acceptance of payment are without prejudice to any rights of the Owner or Contractor under this Contract.
Application and Certificate For Payment -- page 2
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G1-000 | Site Work & Yard Piping | |||||||||
| G1-001 | Bonds | 160,000.00 | 160,000.00 | 0.00 | 0.00 | 160,000.00 | 100.00 | 0.00 | 8,000.00 | |
| G1-002 | Insurance | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G1-003 | Mobilization | 100,000.00 | 100,000.00 | 0.00 | 0.00 | 100,000.00 | 100.00 | 0.00 | 5,000.00 | |
| G1-004 | Pre-Planning/Schedule | 20,000.00 | 16,000.00 | 0.00 | 0.00 | 16,000.00 | 80.00 | 4,000.00 | 800.00 | |
| G1-005 | Submittals - Dutchland | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G1-006 | Submittals - Jet Tech | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G1-007 | E & S Controls | 25,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 60.00 | 10,000.00 | 750.00 | |
| G1-008 | Strip Topsoil | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G1-009 | Temporary Seed | 5,000.00 | 3,000.00 | 0.00 | 0.00 | 3,000.00 | 60.00 | 2,000.00 | 150.00 | |
| G1-010 | Bioretention Basin 1 | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| G1-011 | Bioretention Basin 2 | 20,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 25.00 | 15,000.00 | 250.00 | |
| G1-012 | Temporary Fence | 9,000.00 | 6,300.00 | 0.00 | 0.00 | 6,300.00 | 70.00 | 2,700.00 | 315.00 | |
| G1-013 | Influent Force Main | 85,000.00 | 85,000.00 | 0.00 | 0.00 | 85,000.00 | 100.00 | 0.00 | 4,250.00 | |
| G1-014 | Filter Feed Force Main | 85,000.00 | 85,000.00 | 0.00 | 0.00 | 85,000.00 | 100.00 | 0.00 | 4,250.00 | |
| G1-015 | Filter Effluent | 55,000.00 | 55,000.00 | 0.00 | 0.00 | 55,000.00 | 100.00 | 0.00 | 2,750.00 | |
| G1-016 | System Effluent | 55,000.00 | 55,000.00 | 0.00 | 0.00 | 55,000.00 | 100.00 | 0.00 | 2,750.00 | |
| G1-017 | Filter Feed Pump Suction | 25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | |
| G1-018 | Filter Feed Pump Discharge | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G1-019 | Flocculation Tank to Filters | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G1-020 | 4" WAS | 45,000.00 | 0.00 | 4,500.00 | 0.00 | 4,500.00 | 10.00 | 40,500.00 | 225.00 | |
| G1-021 | Yard Drain | 70,000.00 | 52,500.00 | 0.00 | 0.00 | 52,500.00 | 75.00 | 17,500.00 | 2,625.00 | |
| G1-022 | Sludge Pump Suction | 25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | |
| G1-023 | Relocate Air Lines | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| G1-024 | Influent | 45,000.00 | 45,000.00 | 0.00 | 0.00 | 45,000.00 | 100.00 | 0.00 | 2,250.00 | |
| G1-025 | Utility Water | 75,000.00 | 63,750.00 | 0.00 | 0.00 | 63,750.00 | 85.00 | 11,250.00 | 3,187.50 | |
Application and Certificate For Payment -- page 3
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G1-026 | Apple Brook Discharge | 15,000.00 | 14,250.00 | 0.00 | 0.00 | 14,250.00 | 95.00 | 750.00 | 712.50 | |
| G1-027 | PVC Chemical Carrier Pipe | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G1-028 | Potable Water | 45,000.00 | 38,250.00 | 0.00 | 0.00 | 38,250.00 | 85.00 | 6,750.00 | 1,912.50 | |
| G1-029 | 8" Underdrain | 40,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 75.00 | 10,000.00 | 1,500.00 | |
| G1-030 | 1" Compressed Air | 15,000.00 | 3,750.00 | 0.00 | 0.00 | 3,750.00 | 25.00 | 11,250.00 | 187.50 | |
| G1-031 | Sidewalks | 15,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 15,000.00 | 0.00 | |
| G1-032 | VOID | |||||||||
| G1-033 | VOID | |||||||||
| G1-034 | Block | 1,000.00 | 1,000.00 | 0.00 | 0.00 | 1,000.00 | 100.00 | 0.00 | 50.00 | |
| G1-035 | Chain Link Fence | 30,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 30,000.00 | 0.00 | |
| G1-036 | Demo Existing Fence | 10,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 50.00 | 5,000.00 | 250.00 | |
| Subtotal | 1,345,000.00 | 1,068,800.00 | 4,500.00 | 0.00 | 1,073,300.00 | 79.80 | 271,700.00 | 53,665.00 | ||
| G2-000 | Pump Station & Valve Vault | |||||||||
| G2-001 | Excavate Pump Station | 52,000.00 | 52,000.00 | 0.00 | 0.00 | 52,000.00 | 100.00 | 0.00 | 2,600.00 | |
| G2-002 | Install Precast Pump Station | 68,000.00 | 68,000.00 | 0.00 | 0.00 | 68,000.00 | 100.00 | 0.00 | 3,400.00 | |
| G2-003 | Install Anti-Flotation Collar | 3,500.00 | 3,500.00 | 0.00 | 0.00 | 3,500.00 | 100.00 | 0.00 | 175.00 | |
| G2-004 | Backfill Pump Station | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| G2-005 | Excavate Valve Vault | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G2-006 | Install Valve Vault | 28,000.00 | 28,000.00 | 0.00 | 0.00 | 28,000.00 | 100.00 | 0.00 | 1,400.00 | |
| G2-007 | Backfill Valve Vault | 7,500.00 | 5,625.00 | 1,875.00 | 0.00 | 7,500.00 | 100.00 | 0.00 | 375.00 | |
| G2-008 | Painting | 9,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 100.00 | 0.00 | 450.00 | |
| G2-009 | Pipe/Valves/Fittings | 15,000.00 | 14,250.00 | 0.00 | 0.00 | 14,250.00 | 95.00 | 750.00 | 712.50 | |
| G2-010 | Influent Pumps | 65,000.00 | 65,000.00 | 0.00 | 0.00 | 65,000.00 | 100.00 | 0.00 | 3,250.00 | |
| Subtotal | 275,000.00 | 272,375.00 | 1,875.00 | 0.00 | 274,250.00 | 99.73 | 750.00 | 13,712.50 | ||
| G3-000 | Screen Building | |||||||||
| G3-001 | Excavate Screen Bldg; Elev 13' | 38,000.00 | 38,000.00 | 0.00 | 0.00 | 38,000.00 | 100.00 | 0.00 | 1,900.00 | |
Application and Certificate For Payment -- page 4
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G3-002 | Stone Underslab | 5,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 100.00 | 0.00 | 250.00 | |
| G3-003 | Form/Pour 18" Thick Slab | 39,000.00 | 39,000.00 | 0.00 | 0.00 | 39,000.00 | 100.00 | 0.00 | 1,950.00 | |
| G3-004 | Form/Pour Exterior Walls | 65,000.00 | 65,000.00 | 0.00 | 0.00 | 65,000.00 | 100.00 | 0.00 | 3,250.00 | |
| G3-005 | Backfill | 12,000.00 | 10,800.00 | 0.00 | 0.00 | 10,800.00 | 90.00 | 1,200.00 | 540.00 | |
| G3-006 | Excavate Footers; Elev 2'8" | 7,000.00 | 7,000.00 | 0.00 | 0.00 | 7,000.00 | 100.00 | 0.00 | 350.00 | |
| G3-007 | Form/Pour Footers | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| G3-008 | Install Masonry Frost Wall | 9,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 100.00 | 0.00 | 450.00 | |
| G3-009 | Pour Slab | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G3-010 | Form/Pour Channel Walls | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G3-011 | Install Exterior Masonry Walls | 30,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 100.00 | 0.00 | 1,500.00 | |
| G3-012 | Structural Steel | 3,000.00 | 3,000.00 | 0.00 | 0.00 | 3,000.00 | 100.00 | 0.00 | 150.00 | |
| G3-013 | Misc Metals | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G3-014 | Rough Carpentry | 24,000.00 | 24,000.00 | 0.00 | 0.00 | 24,000.00 | 100.00 | 0.00 | 1,200.00 | |
| G3-015 | Dryvit | 18,000.00 | 9,000.00 | 9,000.00 | 0.00 | 18,000.00 | 100.00 | 0.00 | 900.00 | |
| G3-016 | FRP Grating | 4,000.00 | 4,000.00 | 0.00 | 0.00 | 4,000.00 | 100.00 | 0.00 | 200.00 | |
| G3-017 | Hollow Metal & FRP Doors | 1,500.00 | 1,350.00 | 150.00 | 0.00 | 1,500.00 | 100.00 | 0.00 | 75.00 | |
| G3-018 | Overhead Doors | 17,500.00 | 17,500.00 | 0.00 | 0.00 | 17,500.00 | 100.00 | 0.00 | 875.00 | |
| G3-019 | Trolley & Hoist | 2,000.00 | 2,000.00 | 0.00 | 0.00 | 2,000.00 | 100.00 | 0.00 | 100.00 | |
| G3-020 | Plumbing | 5,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 100.00 | 0.00 | 250.00 | |
| G3-021 | HVAC | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G3-022 | Painting | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| Subtotal | 380,000.00 | 369,650.00 | 9,150.00 | 0.00 | 378,800.00 | 99.68 | 1,200.00 | 18,940.00 | ||
| G4-000 | Screen | |||||||||
| G4-001 | Grinder w/RotatingScreen&Auger | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | |
| Subtotal | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | ||
| G5-000 | PrecastPost TensionedSBR Tanks | |||||||||
Application and Certificate For Payment -- page 5
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G5-001 | Bulk Excavate SBR Structure | 100,000.00 | 100,000.00 | 0.00 | 0.00 | 100,000.00 | 100.00 | 0.00 | 5,000.00 | |
| G5-002 | Stone Underslab-SBR Structure | 30,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 100.00 | 0.00 | 1,500.00 | |
| G5-003 | Concrete Base Slab for SBR | 690,000.00 | 690,000.00 | 0.00 | 0.00 | 690,000.00 | 100.00 | 0.00 | 34,500.00 | |
| G5-004 | Backfill Tank | 20,000.00 | 20,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | |
| G5-005 | Walls & Walkways | 750,000.00 | 750,000.00 | 0.00 | 0.00 | 750,000.00 | 100.00 | 0.00 | 37,500.00 | |
| G5-006 | Misc Metals | 60,000.00 | 54,000.00 | 3,000.00 | 0.00 | 57,000.00 | 95.00 | 3,000.00 | 2,850.00 | |
| Subtotal | 1,650,000.00 | 1,644,000.00 | 3,000.00 | 0.00 | 1,647,000.00 | 99.82 | 3,000.00 | 82,350.00 | ||
| G6-000 | Treatment Building | |||||||||
| G6-001 | Excavate Footers | 40,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 100.00 | 0.00 | 2,000.00 | |
| G6-002 | Pour Footers | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G6-003 | Pour Pier Footers | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G6-004 | Pour Piers | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G6-005 | Masonry Frost Walls | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G6-006 | Backfill | 8,000.00 | 6,400.00 | 0.00 | 0.00 | 6,400.00 | 80.00 | 1,600.00 | 320.00 | |
| G6-007 | Stone Under Slab | 6,000.00 | 6,000.00 | 0.00 | 0.00 | 6,000.00 | 100.00 | 0.00 | 300.00 | |
| G6-008 | Plumbing Under Slab | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G6-009 | Concrete Slab | 18,000.00 | 17,100.00 | 0.00 | 0.00 | 17,100.00 | 95.00 | 900.00 | 855.00 | |
| G6-010 | Precast Flocculation Tank | 35,000.00 | 35,000.00 | 0.00 | 0.00 | 35,000.00 | 100.00 | 0.00 | 1,750.00 | |
| G6-011 | Precast Effluent Storage Tank | 20,000.00 | 20,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | |
| G6-012 | Poured in Place UV Channel | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G6-013 | Masonry | 72,000.00 | 72,000.00 | 0.00 | 0.00 | 72,000.00 | 100.00 | 0.00 | 3,600.00 | |
| G6-014 | Structural Steel & Deck | 28,000.00 | 28,000.00 | 0.00 | 0.00 | 28,000.00 | 100.00 | 0.00 | 1,400.00 | |
| G6-015 | Misc Metals | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G6-016 | FRP Grating | 10,000.00 | 7,500.00 | 0.00 | 0.00 | 7,500.00 | 75.00 | 2,500.00 | 375.00 | |
| G6-017 | Dryvit | 35,000.00 | 17,500.00 | 17,500.00 | 0.00 | 35,000.00 | 100.00 | 0.00 | 1,750.00 | |
| G6-018 | EPDM Roofing | 40,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 100.00 | 0.00 | 2,000.00 | |
Application and Certificate For Payment -- page 6
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G6-019 | Caulking | 5,000.00 | 1,250.00 | 1,250.00 | 0.00 | 2,500.00 | 50.00 | 2,500.00 | 125.00 | |
| G6-020 | Hollow Metal & FRP Doors | 2,500.00 | 2,250.00 | 0.00 | 0.00 | 2,250.00 | 90.00 | 250.00 | 112.50 | |
| G6-021 | Overhead Doors | 19,500.00 | 19,500.00 | 0.00 | 0.00 | 19,500.00 | 100.00 | 0.00 | 975.00 | |
| G6-022 | Painting | 35,000.00 | 31,500.00 | 0.00 | 0.00 | 31,500.00 | 90.00 | 3,500.00 | 1,575.00 | |
| G6-023 | Top Entry Mixer | 20,000.00 | 20,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | |
| G6-024 | Plumbing | 23,000.00 | 21,850.00 | 1,150.00 | 0.00 | 23,000.00 | 100.00 | 0.00 | 1,150.00 | |
| G6-025 | HVAC | 50,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 80.00 | 10,000.00 | 2,000.00 | |
| Subtotal | 575,000.00 | 533,850.00 | 19,900.00 | 0.00 | 553,750.00 | 96.30 | 21,250.00 | 27,687.50 | ||
| G7-000 | SBR/Chem Feed & Process Piping | |||||||||
| G7-001 | SBR Equipment | 790,000.00 | 766,300.00 | 15,800.00 | 0.00 | 782,100.00 | 99.00 | 7,900.00 | 39,105.00 | |
| G7-002 | Polymer Feed System | 18,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 50.00 | 9,000.00 | 450.00 | |
| G7-003 | Chem Feed Pumps & Piping | 18,000.00 | 16,200.00 | 0.00 | 0.00 | 16,200.00 | 90.00 | 1,800.00 | 810.00 | |
| G7-004 | Inline Static Mixers | 25,500.00 | 25,500.00 | 0.00 | 0.00 | 25,500.00 | 100.00 | 0.00 | 1,275.00 | |
| G7-005 | Inline Grinder | 8,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,500.00 | 0.00 | |
| G7-006 | Utility Water Pumps & Controls | 80,000.00 | 80,000.00 | 0.00 | 0.00 | 80,000.00 | 100.00 | 0.00 | 4,000.00 | |
| G7-007 | Instrumentation & Controls | 127,000.00 | 107,950.00 | 0.00 | 0.00 | 107,950.00 | 85.00 | 19,050.00 | 5,397.50 | |
| G7-008 | FRP Chemical Tank | 25,000.00 | 22,500.00 | 0.00 | 0.00 | 22,500.00 | 90.00 | 2,500.00 | 1,125.00 | |
| G7-009 | Process Piping | 245,000.00 | 232,750.00 | 0.00 | 0.00 | 232,750.00 | 95.00 | 12,250.00 | 11,637.50 | |
| G7-010 | Relocated Apple Brook Pump | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| Subtotal | 1,345,000.00 | 1,268,200.00 | 15,800.00 | 0.00 | 1,284,000.00 | 95.46 | 61,000.00 | 64,200.00 | ||
| G8-000 | Filtration & UV System | |||||||||
| G8-001 | Disk Filters | 470,000.00 | 470,000.00 | 0.00 | 0.00 | 470,000.00 | 100.00 | 0.00 | 23,500.00 | |
| G8-002 | Filter Feed Pumps | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| G8-003 | UV System | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | |
| Subtotal | 660,000.00 | 650,000.00 | 0.00 | 0.00 | 650,000.00 | 98.48 | 10,000.00 | 32,500.00 | ||
| G9-000 | Sludge Digestion & Post EQ Tank | |||||||||
Application and Certificate For Payment -- page 7
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G9-001 | Demo Interior | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| G9-002 | Sandblasting & Painting | 160,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 160,000.00 | 0.00 | |
| G9-003 | Course Bubble Diffuser | 30,000.00 | 25,550.00 | 0.00 | 0.00 | 25,550.00 | 85.17 | 4,450.00 | 1,277.50 | |
| G9-004 | Centrifugal Blower Recondition | 20,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 40.00 | 12,000.00 | 400.00 | |
| G9-005 | Aeration Tank Rehabilitation | 45,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 45,000.00 | 0.00 | |
| Subtotal | 275,000.00 | 33,550.00 | 0.00 | 0.00 | 33,550.00 | 12.20 | 241,450.00 | 1,677.50 | ||
| GG10-000 | Sludge Dewatering BldgAddition | |||||||||
| GG10-001 | Demo Centrifuge | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-002 | Demo Building | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-003 | Sawcut Floor | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-004 | Excavate Footers | 12,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 12,000.00 | 0.00 | |
| GG10-005 | Form & Pour Footers | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-006 | Masonry Frost Walls | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| GG10-007 | Backfill | 6,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 6,000.00 | 0.00 | |
| GG10-008 | Underslab Plumbing | 5,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 5,000.00 | 0.00 | |
| GG10-009 | Misc Metals | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-010 | Pour Concrete Slab | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-011 | Masonry Walls | 35,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 35,000.00 | 0.00 | |
| GG10-012 | Dryvit | 25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | |
| GG10-013 | Frames & Doors | 1,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 1,500.00 | 0.00 | |
| GG10-014 | Overhead Doors | 6,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 6,000.00 | 0.00 | |
| GG10-015 | Trolley & Hoist | 4,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 4,000.00 | 0.00 | |
| GG10-016 | Carpentry | 39,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 39,000.00 | 0.00 | |
| GG10-017 | Painting | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| GG10-018 | Plumbing | 5,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 5,000.00 | 0.00 | |
| GG10-019 | HVAC | 7,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 7,500.00 | 0.00 | |
Application and Certificate For Payment -- page 8
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| GG11-000 | Sludge DewateringSystem & Pipe | |||||||||
| GG11-001 | Centrifuge | 525,000.00 | 346,215.00 | 0.00 | 0.00 | 346,215.00 | 65.95 | 178,785.00 | 17,310.75 | |
| GG11-002 | Progressive Conveying System | 7,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 7,000.00 | 0.00 | |
| GG11-003 | Sludge Conveying System | 18,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 18,000.00 | 0.00 | |
| GG11-004 | Process Pipe | 200,000.00 | 18,000.00 | 0.00 | 0.00 | 18,000.00 | 9.00 | 182,000.00 | 900.00 | |
| GG12-000 | Site Paving | |||||||||
| GG12-001 | Lump Sum | 50,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 50,000.00 | 0.00 | |
| GG13-000 | Engineered Fill | |||||||||
| GG13-001 | Lump Sum | 4,400.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 4,400.00 | 0.00 | |
| GG14-000 | Flowable Fill | |||||||||
| GG14-001 | Lump Sum | 11,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 11,000.00 | 0.00 | |
| GG18-000 | Alternate G-18 | |||||||||
| GG18-001 | Lump Sum | 125,000.00 | 0.00 | 125,000.00 | 0.00 | 125,000.00 | 100.00 | 0.00 | 6,250.00 | |
| Subtotal | 1,180,400.00 | 364,215.00 | 125,000.00 | 0.00 | 489,215.00 | 41.44 | 691,185.00 | 24,460.75 | ||
| Application Total | 7,865,400.00 | 6,384,640.00 | 179,225.00 | 0.00 | 6,563,865.00 | 83.45 | 1,301,535.00 | 328,193.25 | ||
Application and Certificate For Payment
Page 1
To Owner: East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380
Project: Ridley Creek WWTP
1751 Towne Road
Fred Papiernik 267-278-6108
West Chester, PA 19380
Application No: 17
Date: 04/30/2010
Period To: 04/30/10
Architect's Project No:
Contract Date: 10/22/08
From (Contractor): Worth and Company, Inc.
6263 Kellers Church Road
Pipersville, PA 18947
Phone: 267 362-1100
Contractor Job Number: P28001
Via (Architect):
Contract For:
Contractor's Application For Payment
| Change Order Summary | Additions | Deductions | ||
|---|---|---|---|---|
| Change orders approved in previous months by owner | ||||
| Number | Date Approved | |||
| Change orders approved this month | ||||
| Totals | ||||
| Net change by change orders | ||||
| Original contract sum | 7,865,400.00 |
|---|---|
| Net change by change orders | 0.00 |
| Contract sum to date | 7,865,400.00 |
| Total completed and stored to date | 6,563,865.00 |
| Retainage | |
| 5.0% of completed work | 328,193.25 |
| 0.0% of stored material | 0.00 |
| Total retainage | 328,193.25 |
| Total earned less retainage | 6,235,671.75 |
| Less previous certificates of payment | 6,065,408.00 |
| Current payment due | 170,263.75 |
| Balance to finish, including retainage | 1,629,728.25 |
The undersigned Contractor certifies that to the best of the Contractor's knowledge, information and belief the work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for work for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown herein is now due.
Contractor: Worth and Company, Inc.
By: [signature]
Date: 5/3/10
State of: PA
County of: Bucks
Subscribed and sworn to before me this 3rd day of May 2010 (year).
Notary public: Linda D. Neilson [signature]
My commission expires: Sept. 19, 2010
[Seal: Commonwealth of Pennsylvania, Notarial Seal, Linda D. Neilson, Notary Public, Plumstead Twp., Bucks County, My Commission Expires Sept. 19, 2010, Member, Pennsylvania Association of Notaries]
Architect's Certificate for Payment
In accordance with the Contract Documents, based on on-site observations and the data comprising the above application the Architect certifies to the Owner that to the best of the Architect's knowledge, information and belief the Work has progressed as indicated, the quality of the Work is in accordance with the Contract Documents, and the Contractor is entitled to payment of the Amount Certified.
Amount Certified: $__________
Architect:
By: __________ Date: __________
This Certification is not negotiable. The Amount Certified is payable only to the Contractor named herein. Issuance, payment, and acceptance of payment are without prejudice to any rights of the Owner or Contractor under this Contract.
35
Application and Certificate For Payment -- page 2
To Owner: East Goshen Municipal Authorit
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17 | Date: 04/30/10 | Period To: 04/30/10
Contractor's Job Number: P28001
Architect's Project No:
| Item Number | Description | Scheduled Value | Work Completed Previous Application | Work Completed This Period | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo |
|---|---|---|---|---|---|---|---|---|---|---|
| G1-000 | Site Work & Yard Piping | |||||||||
| G1-001 | Bonds | 160,000.00 | 160,000.00 | 0.00 | 0.00 | 160,000.00 | 100.00 | 0.00 | 8,000.00 | |
| G1-002 | Insurance | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G1-003 | Mobilization | 100,000.00 | 100,000.00 | 0.00 | 0.00 | 100,000.00 | 100.00 | 0.00 | 5,000.00 | |
| G1-004 | Pre-Planning/Schedule | 20,000.00 | 16,000.00 | 0.00 | 0.00 | 16,000.00 | 80.00 | 4,000.00 | 800.00 | |
| G1-005 | Submittals - Dutchland | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G1-006 | Submittals - Jet Tech | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G1-007 | E & S Controls | 25,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 60.00 | 10,000.00 | 750.00 | |
| G1-008 | Strip Topsoil | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G1-009 | Temporary Seed | 5,000.00 | 3,000.00 | 0.00 | 0.00 | 3,000.00 | 60.00 | 2,000.00 | 150.00 | |
| G1-010 | Bioretention Basin 1 | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| G1-011 | Bioretention Basin 2 | 20,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 25.00 | 15,000.00 | 250.00 | |
| G1-012 | Temporary Fence | 9,000.00 | 6,300.00 | 0.00 | 0.00 | 6,300.00 | 70.00 | 2,700.00 | 315.00 | |
| G1-013 | Influent Force Main | 85,000.00 | 85,000.00 | 0.00 | 0.00 | 85,000.00 | 100.00 | 0.00 | 4,250.00 | |
| G1-014 | Filter Feed Force Main | 85,000.00 | 85,000.00 | 0.00 | 0.00 | 85,000.00 | 100.00 | 0.00 | 4,250.00 | |
| G1-015 | Filter Effluent | 55,000.00 | 55,000.00 | 0.00 | 0.00 | 55,000.00 | 100.00 | 0.00 | 2,750.00 | |
| G1-016 | System Effluent | 55,000.00 | 55,000.00 | 0.00 | 0.00 | 55,000.00 | 100.00 | 0.00 | 2,750.00 | |
| G1-017 | Filter Feed Pump Suction | 25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | |
| G1-018 | Filter Feed Pump Discharge | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G1-019 | Flocculation Tank to Filters | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G1-020 | 4" WAS | 45,000.00 | 0.00 | 4,500.00 | 0.00 | 4,500.00 | 10.00 | 40,500.00 | 225.00 | |
| G1-021 | Yard Drain | 70,000.00 | 52,500.00 | 0.00 | 0.00 | 52,500.00 | 75.00 | 17,500.00 | 2,625.00 | |
| G1-022 | Sludge Pump Suction | 25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | |
| G1-023 | Relocate Air Lines | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| G1-024 | Influent | 45,000.00 | 45,000.00 | 0.00 | 0.00 | 45,000.00 | 100.00 | 0.00 | 2,250.00 | |
| G1-025 | Utility Water | 75,000.00 | 63,750.00 | 0.00 | 0.00 | 63,750.00 | 85.00 | 11,250.00 | 3,187.50 |
Application and Certificate For Payment -- page 3
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G1-026 | Apple Brook Discharge | 15,000.00 | 14,250.00 | 0.00 | 0.00 | 14,250.00 | 95.00 | 750.00 | 712.50 | |
| G1-027 | PVC Chemical Carrier Pipe | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G1-028 | Potable Water | 45,000.00 | 38,250.00 | 0.00 | 0.00 | 38,250.00 | 85.00 | 6,750.00 | 1,912.50 | |
| G1-029 | 8" Underdrain | 40,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 75.00 | 10,000.00 | 1,500.00 | |
| G1-030 | 1" Compressed Air | 15,000.00 | 3,750.00 | 0.00 | 0.00 | 3,750.00 | 25.00 | 11,250.00 | 187.50 | |
| G1-031 | Sidewalks | 15,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 15,000.00 | 0.00 | |
| G1-032 | VOID | |||||||||
| G1-033 | VOID | |||||||||
| G1-034 | Block | 1,000.00 | 1,000.00 | 0.00 | 0.00 | 1,000.00 | 100.00 | 0.00 | 50.00 | |
| G1-035 | Chain Link Fence | 30,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 30,000.00 | 0.00 | |
| G1-036 | Demo Existing Fence | 10,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 50.00 | 5,000.00 | 250.00 | |
| Subtotal | 1,345,000.00 | 1,068,800.00 | 4,500.00 | 0.00 | 1,073,300.00 | 79.80 | 271,700.00 | 53,665.00 | ||
| G2-000 | Pump Station & Valve Vault | |||||||||
| G2-001 | Excavate Pump Station | 52,000.00 | 52,000.00 | 0.00 | 0.00 | 52,000.00 | 100.00 | 0.00 | 2,600.00 | |
| G2-002 | Install Precast Pump Station | 68,000.00 | 68,000.00 | 0.00 | 0.00 | 68,000.00 | 100.00 | 0.00 | 3,400.00 | |
| G2-003 | Install Anti-Flotation Collar | 3,500.00 | 3,500.00 | 0.00 | 0.00 | 3,500.00 | 100.00 | 0.00 | 175.00 | |
| G2-004 | Backfill Pump Station | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| G2-005 | Excavate Valve Vault | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G2-006 | Install Valve Vault | 28,000.00 | 28,000.00 | 0.00 | 0.00 | 28,000.00 | 100.00 | 0.00 | 1,400.00 | |
| G2-007 | Backfill Valve Vault | 7,500.00 | 5,625.00 | 1,875.00 | 0.00 | 7,500.00 | 100.00 | 0.00 | 375.00 | |
| G2-008 | Painting | 9,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 100.00 | 0.00 | 450.00 | |
| G2-009 | Pipe/Valves/Fittings | 15,000.00 | 14,250.00 | 0.00 | 0.00 | 14,250.00 | 95.00 | 750.00 | 712.50 | |
| G2-010 | Influent Pumps | 65,000.00 | 65,000.00 | 0.00 | 0.00 | 65,000.00 | 100.00 | 0.00 | 3,250.00 | |
| Subtotal | 275,000.00 | 272,375.00 | 1,875.00 | 0.00 | 274,250.00 | 99.73 | 750.00 | 13,712.50 | ||
| G3-000 | Screen Building | |||||||||
| G3-001 | Excavate Screen Bldg; Elev 13' | 38,000.00 | 38,000.00 | 0.00 | 0.00 | 38,000.00 | 100.00 | 0.00 | 1,900.00 | |
37
Application and Certificate For Payment -- page 4
To Owner: East Goshen Municipal Authorit
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17 | Date: 04/30/10 | Period To: 04/30/10
Contractor's Job Number: P28001
Architect's Project No:
| Item Number | Description | Scheduled Value | Work Completed Previous Application | Work Completed This Period | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo |
|---|---|---|---|---|---|---|---|---|---|---|
| G3-002 | Stone Underslab | 5,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 100.00 | 0.00 | 250.00 | |
| G3-003 | Form/Pour 18" Thick Slab | 39,000.00 | 39,000.00 | 0.00 | 0.00 | 39,000.00 | 100.00 | 0.00 | 1,950.00 | |
| G3-004 | Form/Pour Exterior Walls | 65,000.00 | 65,000.00 | 0.00 | 0.00 | 65,000.00 | 100.00 | 0.00 | 3,250.00 | |
| G3-005 | Backfill | 12,000.00 | 10,800.00 | 0.00 | 0.00 | 10,800.00 | 90.00 | 1,200.00 | 540.00 | |
| G3-006 | Excavate Footers; Elev 2'8" | 7,000.00 | 7,000.00 | 0.00 | 0.00 | 7,000.00 | 100.00 | 0.00 | 350.00 | |
| G3-007 | Form/Pour Footers | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| G3-008 | Install Masonry Frost Wall | 9,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 100.00 | 0.00 | 450.00 | |
| G3-009 | Pour Slab | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G3-010 | Form/Pour Channel Walls | 50,000.00 | 50,000.00 | 0.00 | 0.00 | 50,000.00 | 100.00 | 0.00 | 2,500.00 | |
| G3-011 | Install Exterior Masonry Walls | 30,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 100.00 | 0.00 | 1,500.00 | |
| G3-012 | Structural Steel | 3,000.00 | 3,000.00 | 0.00 | 0.00 | 3,000.00 | 100.00 | 0.00 | 150.00 | |
| G3-013 | Misc Metals | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G3-014 | Rough Carpentry | 24,000.00 | 24,000.00 | 0.00 | 0.00 | 24,000.00 | 100.00 | 0.00 | 1,200.00 | |
| G3-015 | Dryvit | 18,000.00 | 9,000.00 | 9,000.00 | 0.00 | 18,000.00 | 100.00 | 0.00 | 900.00 | |
| G3-016 | FRP Grating | 4,000.00 | 4,000.00 | 0.00 | 0.00 | 4,000.00 | 100.00 | 0.00 | 200.00 | |
| G3-017 | Hollow Metal & FRP Doors | 1,500.00 | 1,350.00 | 150.00 | 0.00 | 1,500.00 | 100.00 | 0.00 | 75.00 | |
| G3-018 | Overhead Doors | 17,500.00 | 17,500.00 | 0.00 | 0.00 | 17,500.00 | 100.00 | 0.00 | 875.00 | |
| G3-019 | Trolley & Hoist | 2,000.00 | 2,000.00 | 0.00 | 0.00 | 2,000.00 | 100.00 | 0.00 | 100.00 | |
| G3-020 | Plumbing | 5,000.00 | 5,000.00 | 0.00 | 0.00 | 5,000.00 | 100.00 | 0.00 | 250.00 | |
| G3-021 | HVAC | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G3-022 | Painting | 12,000.00 | 12,000.00 | 0.00 | 0.00 | 12,000.00 | 100.00 | 0.00 | 600.00 | |
| Subtotal | 380,000.00 | 369,650.00 | 9,150.00 | 0.00 | 378,800.00 | 99.68 | 1,200.00 | 18,940.00 | ||
| G4-000 | Grinder w/RotatingScreen&Auger | |||||||||
| G4-001 | Screen | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | |
| Subtotal | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | ||
| G5-000 | PrecastPost TensionedSBR Tanks |
Application and Certificate For Payment -- page 5
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G5-001 | Bulk Excavate SBR Structure | 100,000.00 | 100,000.00 | 0.00 | 0.00 | 100,000.00 | 100.00 | 0.00 | 5,000.00 | |
| G5-002 | Stone Underslab-SBR Structure | 30,000.00 | 30,000.00 | 0.00 | 0.00 | 30,000.00 | 100.00 | 0.00 | 1,500.00 | |
| G5-003 | Concrete Base Slab for SBR | 690,000.00 | 690,000.00 | 0.00 | 0.00 | 690,000.00 | 100.00 | 0.00 | 34,500.00 | |
| G5-004 | Backfill Tank | 20,000.00 | 20,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | |
| G5-005 | Walls & Walkways | 750,000.00 | 750,000.00 | 0.00 | 0.00 | 750,000.00 | 100.00 | 0.00 | 37,500.00 | |
| G5-006 | Misc Metals | 60,000.00 | 54,000.00 | 3,000.00 | 0.00 | 57,000.00 | 95.00 | 3,000.00 | 2,850.00 | |
| Subtotal | 1,650,000.00 | 1,644,000.00 | 3,000.00 | 0.00 | 1,647,000.00 | 99.82 | 3,000.00 | 82,350.00 | ||
| G6-000 | Treatment Building | |||||||||
| G6-001 | Excavate Footers | 40,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 100.00 | 0.00 | 2,000.00 | |
| G6-002 | Pour Footers | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G6-003 | Pour Pier Footers | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G6-004 | Pour Piers | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| G6-005 | Masonry Frost Walls | 15,000.00 | 15,000.00 | 0.00 | 0.00 | 15,000.00 | 100.00 | 0.00 | 750.00 | |
| G6-006 | Backfill | 8,000.00 | 6,400.00 | 0.00 | 0.00 | 6,400.00 | 80.00 | 1,600.00 | 320.00 | |
| G6-007 | Stone Under Slab | 6,000.00 | 6,000.00 | 0.00 | 0.00 | 6,000.00 | 100.00 | 0.00 | 300.00 | |
| G6-008 | Plumbing Under Slab | 10,000.00 | 10,000.00 | 0.00 | 0.00 | 10,000.00 | 100.00 | 0.00 | 500.00 | |
| G6-009 | Concrete Slab | 18,000.00 | 17,100.00 | 0.00 | 0.00 | 17,100.00 | 95.00 | 900.00 | 855.00 | |
| G6-010 | Precast Flocculation Tank | 35,000.00 | 35,000.00 | 0.00 | 0.00 | 35,000.00 | 100.00 | 0.00 | 1,750.00 | |
| G6-011 | Precast Effluent Storage Tank | 20,000.00 | 20,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | |
| G6-012 | Poured in Place UV Channel | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G6-013 | Masonry | 72,000.00 | 72,000.00 | 0.00 | 0.00 | 72,000.00 | 100.00 | 0.00 | 3,600.00 | |
| G6-014 | Structural Steel & Deck | 28,000.00 | 28,000.00 | 0.00 | 0.00 | 28,000.00 | 100.00 | 0.00 | 1,400.00 | |
| G6-015 | Misc Metals | 25,000.00 | 25,000.00 | 0.00 | 0.00 | 25,000.00 | 100.00 | 0.00 | 1,250.00 | |
| G6-016 | FRP Grating | 10,000.00 | 7,500.00 | 0.00 | 0.00 | 7,500.00 | 75.00 | 2,500.00 | 375.00 | |
| G6-017 | Dryvit | 35,000.00 | 17,500.00 | 17,500.00 | 0.00 | 35,000.00 | 100.00 | 0.00 | 1,750.00 | |
| G6-018 | EPDM Roofing | 40,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 100.00 | 0.00 | 2,000.00 | |
Application and Certificate For Payment -- page 6
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G6-019 | Caulking | 5,000.00 | 1,250.00 | 1,250.00 | 0.00 | 2,500.00 | 50.00 | 2,500.00 | 125.00 | |
| G6-020 | Hollow Metal & FRP Doors | 2,500.00 | 2,250.00 | 0.00 | 0.00 | 2,250.00 | 90.00 | 250.00 | 112.50 | |
| G6-021 | Overhead Doors | 19,500.00 | 19,500.00 | 0.00 | 0.00 | 19,500.00 | 100.00 | 0.00 | 975.00 | |
| G6-022 | Painting | 35,000.00 | 31,500.00 | 0.00 | 0.00 | 31,500.00 | 90.00 | 3,500.00 | 1,575.00 | |
| G6-023 | Top Entry Mixer | 20,000.00 | 20,000.00 | 0.00 | 0.00 | 20,000.00 | 100.00 | 0.00 | 1,000.00 | |
| G6-024 | Plumbing | 23,000.00 | 21,850.00 | 1,150.00 | 0.00 | 23,000.00 | 100.00 | 0.00 | 1,150.00 | |
| G6-025 | HVAC | 50,000.00 | 40,000.00 | 0.00 | 0.00 | 40,000.00 | 80.00 | 10,000.00 | 2,000.00 | |
| Subtotal | 575,000.00 | 533,850.00 | 19,900.00 | 0.00 | 553,750.00 | 96.30 | 21,250.00 | 27,687.50 | ||
| G7-000 | SBR/Chem Feed & Process Piping | |||||||||
| G7-001 | SBR Equipment | 790,000.00 | 766,300.00 | 15,800.00 | 0.00 | 782,100.00 | 99.00 | 7,900.00 | 39,105.00 | |
| G7-002 | Polymer Feed System | 18,000.00 | 9,000.00 | 0.00 | 0.00 | 9,000.00 | 50.00 | 9,000.00 | 450.00 | |
| G7-003 | Chem Feed Pumps & Piping | 18,000.00 | 16,200.00 | 0.00 | 0.00 | 16,200.00 | 90.00 | 1,800.00 | 810.00 | |
| G7-004 | Inline Static Mixers | 25,500.00 | 25,500.00 | 0.00 | 0.00 | 25,500.00 | 100.00 | 0.00 | 1,275.00 | |
| G7-005 | Inline Grinder | 8,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,500.00 | 0.00 | |
| G7-006 | Utility Water Pumps & Controls | 80,000.00 | 80,000.00 | 0.00 | 0.00 | 80,000.00 | 100.00 | 0.00 | 4,000.00 | |
| G7-007 | Instrumentation & Controls | 127,000.00 | 107,950.00 | 0.00 | 0.00 | 107,950.00 | 85.00 | 19,050.00 | 5,397.50 | |
| G7-008 | FRP Chemical Tank | 25,000.00 | 22,500.00 | 0.00 | 0.00 | 22,500.00 | 90.00 | 2,500.00 | 1,125.00 | |
| G7-009 | Process Piping | 245,000.00 | 232,750.00 | 0.00 | 0.00 | 232,750.00 | 95.00 | 12,250.00 | 11,637.50 | |
| G7-010 | Relocated Apple Brook Pump | 8,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 100.00 | 0.00 | 400.00 | |
| Subtotal | 1,345,000.00 | 1,268,200.00 | 15,800.00 | 0.00 | 1,284,000.00 | 95.46 | 61,000.00 | 64,200.00 | ||
| G8-000 | Filtration & UV System | |||||||||
| G8-001 | Disk Filters | 470,000.00 | 470,000.00 | 0.00 | 0.00 | 470,000.00 | 100.00 | 0.00 | 23,500.00 | |
| G8-002 | Filter Feed Pumps | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| G8-003 | UV System | 180,000.00 | 180,000.00 | 0.00 | 0.00 | 180,000.00 | 100.00 | 0.00 | 9,000.00 | |
| Subtotal | 660,000.00 | 650,000.00 | 0.00 | 0.00 | 650,000.00 | 98.48 | 10,000.00 | 32,500.00 | ||
| G9-000 | Sludge Digestion & Post EQ Tank | |||||||||
Application and Certificate For Payment -- page 7
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| G9-001 | Demo Interior | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| G9-002 | Sandblasting & Painting | 160,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 160,000.00 | 0.00 | |
| G9-003 | Course Bubble Diffuser | 30,000.00 | 25,550.00 | 0.00 | 0.00 | 25,550.00 | 85.17 | 4,450.00 | 1,277.50 | |
| G9-004 | Centrifugal Blower Recondition | 20,000.00 | 8,000.00 | 0.00 | 0.00 | 8,000.00 | 40.00 | 12,000.00 | 400.00 | |
| G9-005 | Aeration Tank Rehabilitation | 45,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 45,000.00 | 0.00 | |
| Subtotal | 275,000.00 | 33,550.00 | 0.00 | 0.00 | 33,550.00 | 12.20 | 241,450.00 | 1,677.50 | ||
| GG10-000 | Sludge Dewatering Bldg Addition | |||||||||
| GG10-001 | Demo Centrifuge | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-002 | Demo Building | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-003 | Sawcut Floor | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-004 | Excavate Footers | 12,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 12,000.00 | 0.00 | |
| GG10-005 | Form & Pour Footers | 8,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 8,000.00 | 0.00 | |
| GG10-006 | Masonry Frost Walls | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| GG10-007 | Backfill | 6,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 6,000.00 | 0.00 | |
| GG10-008 | Underslab Plumbing | 5,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 5,000.00 | 0.00 | |
| GG10-009 | Misc Metals | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-010 | Pour Concrete Slab | 10,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 10,000.00 | 0.00 | |
| GG10-011 | Masonry Walls | 35,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 35,000.00 | 0.00 | |
| GG10-012 | Dryvit | 25,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 25,000.00 | 0.00 | |
| GG10-013 | Frames & Doors | 1,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 1,500.00 | 0.00 | |
| GG10-014 | Overhead Doors | 6,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 6,000.00 | 0.00 | |
| GG10-015 | Trolley & Hoist | 4,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 4,000.00 | 0.00 | |
| GG10-016 | Carpentry | 39,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 39,000.00 | 0.00 | |
| GG10-017 | Painting | 20,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 20,000.00 | 0.00 | |
| GG10-018 | Plumbing | 5,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 5,000.00 | 0.00 | |
| GG10-019 | HVAC | 7,500.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 7,500.00 | 0.00 | |
Application and Certificate For Payment -- page 8
To Owner: East Goshen Municipal Authority
From (Contractor): Worth and Company, Inc.
Project: Ridley Creek WWTP
Application No: 17
Contractor's Job Number: P28001
Architect's Project No:
Date: 04/30/10
Period To: 04/30/10
| Item Number | Description | Scheduled Value | Work Completed | Materials Presently Stored | Completed and Stored to Date | % | Balance to Finish | Retention | Memo | |
|---|---|---|---|---|---|---|---|---|---|---|
| Previous Application | This Period | |||||||||
| GG11-000 | Sludge DewateringSystem & Pipe | |||||||||
| GG11-001 | Centrifuge | 525,000.00 | 346,215.00 | 0.00 | 0.00 | 346,215.00 | 65.95 | 178,785.00 | 17,310.75 | |
| GG11-002 | Progressive Conveying System | 7,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 7,000.00 | 0.00 | |
| GG11-003 | Sludge Conveying System | 18,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 18,000.00 | 0.00 | |
| GG11-004 | Process Pipe | 200,000.00 | 18,000.00 | 0.00 | 0.00 | 18,000.00 | 9.00 | 182,000.00 | 900.00 | |
| GG12-000 | Site Paving | |||||||||
| GG12-001 | Lump Sum | 50,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 50,000.00 | 0.00 | |
| GG13-000 | Engineered Fill | |||||||||
| GG13-001 | Lump Sum | 4,400.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 4,400.00 | 0.00 | |
| GG14-000 | Flowable Fill | |||||||||
| GG14-001 | Lump Sum | 11,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 11,000.00 | 0.00 | |
| GG18-000 | Alternate G-18 | |||||||||
| GG18-001 | Lump Sum | 125,000.00 | 0.00 | 125,000.00 | 0.00 | 125,000.00 | 100.00 | 0.00 | 6,250.00 | |
| Subtotal | 1,180,400.00 | 364,215.00 | 125,000.00 | 0.00 | 489,215.00 | 41.44 | 691,185.00 | 24,460.75 | ||
| Application Total | 7,865,400.00 | 6,384,640.00 | 179,225.00 | 0.00 | 6,563,865.00 | 83.45 | 1,301,535.00 | 328,193.25 | ||
3 RIDLEY CREEK INV
g.
19 pgs
APPLICATION AND CERTIFICATION FOR PAYMENT
AIA DOCUMENT G702 | PAGE 1 OF 2 PAGES
TO OWNER: East Goshen Municipal Auth.
1580 Paoli Pike
West Chester, PA 19331
FROM CONTRACTOR: Wm. H. Clinger Corp.
736 Baltimore Pike, P.O. Box 158
Concordville, PA 19331
CONTRACT FOR: Electrical Contractor
PROJECT: Ridley Creek Sewage Treatment Plant Upgrade & Expansion Project
VIA ARCHITECT: Pennoni Associates
One Drexel Plaza, 3001 Market St.
Philadelphia, PA 19104-2897
APPLICATION NO: 14
PERIOD TO: 5/2/2010
PROJECT NOS: EGMA0707
CONTRACT DATE: 11/5/2008
Distribution to:
[ ] OWNER
[X] ARCHITECT
[ ] CONSTRUCTION MANAGER
[ ]
[ ]
Our Job# CEG800
CONTRACTOR'S APPLICATION FOR PAYMENT
Application is made for payment, as shown below, in connection with the Contract. Continuation Sheet, AIA Document G703, is attached.
| 1. ORIGINAL CONTRACT SUM | $ 974,000.00 |
|---|---|
| 2. Net change by Change Orders | $ $33,313.24 |
| 3. CONTRACT SUM TO DATE (Line 1 ± 2) | $ 1,007,313.24 |
| 4. TOTAL COMPLETED & STORED TO DATE (Column G on G703) | $ 883,015.89 |
| 5. RETAINAGE: a. 5 % of Completed Work (Column D + E on G703) $ 45,816.45 b. % of Stored Material (Column F on G703) $ Total Retainage (Lines 5a + 5b or Total in Column I of G703) |
$ 45,816.45 |
| 6. TOTAL EARNED LESS RETAINAGE (Line 4 Less Line 5 Total) | $ 837,199.44 |
| 7. LESS PREVIOUS CERTIFICATES FOR PAYMENT (Line 6 from prior Certificate) | $ 802,660.06 |
| 8. CURRENT PAYMENT DUE | $ 34,539.38 |
| 9. BALANCE TO FINISH, INCLUDING RETAINAGE (Line 3 less Line 6) | 170,113.80 |
| CHANGE ORDER SUMMARY | ADDITIONS | DEDUCTIONS |
|---|---|---|
| Total changes approved in previous months by Owner | ||
| Total approved this Month | $33,313.24 | |
| TOTALS | $33,313.24 | |
| NET CHANGES by Change Order | $33,313.24 | |
The undersigned Contractor certifies that to the best of the Contractor's knowledge, information and belief the Work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for Work for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown herein is now due.
CONTRACTOR: Wm. H. Clinger Corp.
By: Michael V. Clinger (Michael V. Clinger, President) | Date: 5/4/2010
State of: Pennsylvania | County of: Dela
Subscribed and sworn to before me this 4th day of May, 2010.
Notary Public: [signature]
My Commission expires: 2/28/2014
COMMONWEALTH OF PENNSYLVANIA
NOTARIAL SEAL
Joseph P. Natale, Notary Public
Concord Township, Delaware County
My commission expires February 28, 2014
ARCH
In accorda... the data comprisin... that to the... essed as indicated,... ts, and the Contra...
AMOUNT ...
(Attach ex... tial all figures on this Applicatio... amount certified.) ARCHITI...
By: ... e:
This Certi... to the Contracto... thout prejudice...
Evan Has to Approve
MARK
AIA DOCUMENT G702 · APPLICATION AND CERTIFICATION FOR PAYMENT · 1992 EDITION · AIA · ©1992 · THE AMERIC... 3-5292
CONTINUATION SHEET
AIA DOCUMENT G703 PAGE 2 OF 2 PAGES
AIA Document G702, APPLICATION AND CERTIFICATION FOR PAYMENT, containing Contractor's signed certification is attached.
In tabulations below, amounts are stated to the nearest dollar.
Use Column I on Contracts where variable retainage for line items may apply.
APPLICATION NO: 14
APPLICATION DATE: 5/4/2010
PERIOD TO: 5/2/2010
ARCHITECT'S PROJECT NO: EGMA0707
Wm. H. Clinger Corp.
| A ITEM NO. |
B DESCRIPTION OF WORK |
C SCHEDULED VALUE |
D WORK COMPLETED FROM PREVIOUS APPLICATION (D + E) |
E WORK COMPLETED THIS PERIOD |
F MATERIALS PRESENTLY STORED (NOT IN D OR E) |
G TOTAL COMPLETED AND STORED TO DATE (D+E+F) |
% (G ÷ C) |
H BALANCE TO FINISH (C - G) |
I RETAINAGE |
|---|---|---|---|---|---|---|---|---|---|
| *** | SEE ATTACHED | 0 | |||||||
| Total: GRAND TOTALS | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ||
AIA DOCUMENT G703 · CONTINUATION SHEET FOR G702 · 1992 EDITION · AIA · ©1992 THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVENUE, N.W., WASHINGTON, D.C. 20006-5292 G703-1992
7
3 of 19
CUST: EAST GOSHEN MUNICIPAL AUTH.
1580 PAOLI PIKE
WEST CHESTER PA 19331
JOB: Rid.Creek Sewage Trtmnt. Plnt.
APPLICATION NO: 14
PERIOD ENDING : 05/30/10
INVOICE NO : 4363
Page: 1
FROM: William H. Clinger Corp.
PO Box 158, 736 Baltimore Pike
Concordville, PA 19331
ARCHITECT: PENNONI ASSOCIATES
One Drexel Plaza
3001 Market Street
Philadelphia PA 19104-2897
CONTRACT NO:
CONTRACT DATE: 11/13/08
JOB DESCRIPTION: Rid.Creek Sewage Trtmnt. Plnt.
OUR JOB # : CEG800
| CHANGE ORDERS | |||
|---|---|---|---|
| ADDITIONS | DEDUCTIONS | ||
| PREVIOUS TOTAL | .00 | .00 | |
| -----CURRENT----- | |||
| Number | Date | ||
| 001 | 03/31/10 | 5,106.00 | |
| 002 | 04/01/10 | 1,451.24 | |
| 003 | 04/12/10 | 3,171.00 | |
| 001A | 04/01/10 | 23,585.00 | |
| TOTALS TO DATE | 33,313.24 | .00 | |
| NET AMOUNT | 33,313.24 | ||
| ORIGINAL CONTRACT AMOUNT | $ | 974,000.00 |
|---|---|---|
| TOTAL CHANGE ORDER AMOUNT | $ | 33,313.24 |
| TOTAL CONTRACT INCLUDING CHANGE ORDERS | $ | 1,007,313.24 |
| AMOUNT COMPLETED TO DATE | $ | 883,015.89 |
| RETAINAGE - % OF WORK COMPLETED | $ | 45,816.45 |
| % OF STORED MATERIAL | ||
| COMPLETED TO DATE LESS RETAINAGE | $ | 837,199.44 |
| PREVIOUS AMOUNT BILLED | $ | 802,660.06 |
| SALES TAX | $ | .00 |
| CURRENT AMOUNT DUE | $ | 34,539.38 |
| AMOUNT REMAINING | $ | 170,113.80 |
4 of 19
Job Number: CEG800 Rid.Creek Sewage Trtmnt. Plnt.
Application No.: 14 Period From: 03/31/10 Page Number 2
Project # :
Invoice Number : 4363 Thru: 05/30/10
| ITEM NUMBER | DESCRIPTION OF WORK | SCHEDULED VALUE | ----WORK COMPLETED---- | STORED MATERIALS | COMPLETED AND STORED | BALANCE TO FINISH | RETAINAGE | ||
|---|---|---|---|---|---|---|---|---|---|
| PREVIOUS APPLICATION | THIS PERIOD | TO DATE | % | ||||||
| 1 | DIRECT COST | ||||||||
| 1 | Labor-Field | .00 | .00 | .00 | .00 | .00 | 0 | .00 | .00 |
| 3 | Materials | .00 | .00 | .00 | .00 | .00 | 0 | .00 | .00 |
| 4 | Subcontractor | .00 | .00 | .00 | .00 | .00 | 0 | .00 | .00 |
| 5 | Equipment Rental | .00 | .00 | .00 | .00 | .00 | 0 | .00 | .00 |
| 6 | Small Tools | .00 | .00 | .00 | .00 | .00 | 0 | .00 | .00 |
| 7 | Other Charges | .00 | .00 | .00 | .00 | .00 | 0 | .00 | .00 |
| PM | Labor-Proj. Mgr. | .00 | .00 | .00 | .00 | .00 | 0 | .00 | .00 |
| Total DIRECT COST | .00 | .00 | .00 | .00 | .00 | 0 | .00 | .00 | |
| CO | Change Orders | ||||||||
| 001 | Change Order #001 | 5,106.00 | .00 | 5,106.00 | .00 | 5,106.00 | 100 | .00 | 510.60 |
| 002 | Change Order #002 | 1,451.24 | .00 | 1,451.24 | .00 | 1,451.24 | 100 | .00 | 145.12 |
| 003 | Change Order #003 | 3,171.00 | .00 | 3,171.00 | .00 | 3,171.00 | 100 | .00 | 317.10 |
| 001A | Change Order #001 (A) | 23,585.00 | .00 | 23,585.00 | .00 | 23,585.00 | 100 | .00 | 2,358.50 |
| Total Change Orders | 33,313.24 | .00 | 33,313.24 | .00 | 33,313.24 | 100 | .00 | 3,331.32 | |
| MOB | Mobilization | ||||||||
| 1 | Mobilization-Labor | 2,772.00 | 2,772.00 | .00 | .00 | 2,772.00 | 100 | .00 | 138.60 |
| 3 | Mobilization-Material | 5,611.00 | 5,611.00 | .00 | .00 | 5,611.00 | 100 | .00 | 280.55 |
| 5 | Equipment Rental | .00 | .00 | .00 | .00 | .00 | 0 | .00 | .00 |
| Total Mobilization | 8,383.00 | 8,383.00 | .00 | .00 | 8,383.00 | 100 | .00 | 419.15 | |
| DEMO | Demo | ||||||||
| 1 | Demo-Labor | 18,775.00 | .00 | .00 | .00 | .00 | 0 | 18,775.00 | .00 |
| Total Demo | 18,775.00 | .00 | .00 | .00 | .00 | 0 | 18,775.00 | .00 | |
| TEMP | Temporay Power | ||||||||
| 1 | Temporay Power-labor | 10,820.00 | 10,820.00 | .00 | .00 | 10,820.00 | 100 | .00 | 541.00 |
| 3 | Temporay Power-Material | 12,000.00 | 12,000.00 | .00 | .00 | 12,000.00 | 100 | .00 | 600.00 |
| Total Temporay Power | 22,820.00 | 22,820.00 | .00 | .00 | 22,820.00 | 100 | .00 | 1,141.00 | |
| 11000 | Aerial Work | ||||||||
| 1 | Aerial Work-Labor | 486.00 | 486.00 | .00 | .00 | 486.00 | 100 | .00 | 24.30 |
| 3 | Aerial Work-Material | .00 | .00 | .00 | .00 | .00 | 0 | .00 | .00 |
| 4 | Aerial Work-Subcontractor | 6,172.00 | 6,172.00 | .00 | .00 | 6,172.00 | 100 | .00 | 308.60 |
5 of 19
Job Number: CEG800 Rid.Creek Sewage Trtmnt. Plnt.
Application No.: 14 Period From: 03/31/10 Page Number 3
Project # :
Invoice Number : 4363 Thru: 05/30/10
| ITEM NUMBER | DESCRIPTION OF WORK | SCHEDULED VALUE | ----WORK COMPLETED---- | STORED MATERIALS | COMPLETED AND STORED | BALANCE TO FINISH | RETAINAGE | ||
|---|---|---|---|---|---|---|---|---|---|
| PREVIOUS APPLICATION | THIS PERIOD | TO DATE | % | ||||||
| Total Aerial Work | 6,658.00 | 6,658.00 | .00 | .00 | 6,658.00 | 100 | .00 | 332.90 | |
| 11100 | Site Work | ||||||||
| 1 | Site Work-Labor | 7,160.00 | 6,086.00 | .00 | .00 | 6,086.00 | 85 | 1,074.00 | 304.30 |
| 3 | Site Work-Material | 5,985.00 | 5,985.00 | .00 | .00 | 5,985.00 | 100 | .00 | 299.25 |
| 4 | Site Work-Subcontractor | 24,449.00 | 20,781.65 | .00 | .00 | 20,781.65 | 85 | 3,667.35 | 1,039.08 |
| Total Site Work | 37,594.00 | 32,852.65 | .00 | .00 | 32,852.65 | 87 | 4,741.35 | 1,642.63 | |
| 11200 | Underground Conduit | ||||||||
| 1 | Underground Conduit-Labor | 25,984.00 | 25,984.00 | .00 | .00 | 25,984.00 | 100 | .00 | 1,299.20 |
| 3 | Underground Conduit-Mater | 7,530.00 | 7,530.00 | .00 | .00 | 7,530.00 | 100 | .00 | 376.50 |
| Total Underground Conduit | 33,514.00 | 33,514.00 | .00 | .00 | 33,514.00 | 100 | .00 | 1,675.70 | |
| 11210 | Underground Cable | ||||||||
| 1 | Underground Cable-Labor | 28,179.00 | 28,179.00 | .00 | .00 | 28,179.00 | 100 | .00 | 1,408.95 |
| 3 | Underground Cable-Materia | 62,338.00 | 62,338.00 | .00 | .00 | 62,338.00 | 100 | .00 | 3,116.90 |
| Total Underground Cable | 90,517.00 | 90,517.00 | .00 | .00 | 90,517.00 | 100 | .00 | 4,525.85 | |
| 11220 | Underground Terms | ||||||||
| 1 | Underground Terms-Labor | 12,762.00 | 12,762.00 | .00 | .00 | 12,762.00 | 100 | .00 | 638.10 |
| 3 | Underground Terms-Materia | 2,272.00 | 2,272.00 | .00 | .00 | 2,272.00 | 100 | .00 | 113.60 |
| Total Underground Terms | 15,034.00 | 15,034.00 | .00 | .00 | 15,034.00 | 100 | .00 | 751.70 | |
| 11230 | Underground Equip | ||||||||
| 1 | Underground Equip-Labor | 7,276.00 | 7,276.00 | .00 | .00 | 7,276.00 | 100 | .00 | 363.80 |
| 3 | Underground Equip-Materia | 1,234.00 | 1,234.00 | .00 | .00 | 1,234.00 | 100 | .00 | 61.70 |
| Total Underground Equip | 8,510.00 | 8,510.00 | .00 | .00 | 8,510.00 | 100 | .00 | 425.50 | |
| 11300 | Trt.Bldg.Pwr Cond | ||||||||
| 1 | Trt.Bldg.Pwr Cond-Labor | 49,464.00 | 49,464.00 | .00 | .00 | 49,464.00 | 100 | .00 | 2,473.20 |
| 3 | Trt.Bldg.Pwr Cond-Materia | 40,442.00 | 40,442.00 | .00 | .00 | 40,442.00 | 100 | .00 | 2,022.10 |
| Total Trt.Bldg.Pwr Cond | 89,906.00 | 89,906.00 | .00 | .00 | 89,906.00 | 100 | .00 | 4,495.30 | |
| 11310 | Trt.Bldg.Pwr Cables | ||||||||
| 1 | Trt.Bldg.Pwr Cables-Labor | 20,672.00 | 20,672.00 | .00 | .00 | 20,672.00 | 100 | .00 | 1,033.60 |
| 3 | Trt.Bldg.Pwr Cables-Mater | 5,874.00 | 5,874.00 | .00 | .00 | 5,874.00 | 100 | .00 | 293.70 |
| Total Trt.Bldg.Pwr Cables | 26,546.00 | 26,546.00 | .00 | .00 | 26,546.00 | 100 | .00 | 1,327.30 | |
| 11320 | Trt.Bldg.Pwr Terms | ||||||||
| 1 | Trt.Bldg.Pwr Terms-Labor | 6,352.00 | 6,352.00 | .00 | .00 | 6,352.00 | 100 | .00 | 317.60 |
6 of 19
Job Number: CEG800 Rid.Creek Sewage Trtmnt. Plnt.
Application No.: 14 Period From: 03/31/10 Page Number 4
Project # :
Invoice Number : 4363 Thru: 05/30/10
| ITEM NUMBER | DESCRIPTION OF WORK | SCHEDULED VALUE | ----WORK COMPLETED---- | STORED MATERIALS | COMPLETED AND STORED | BALANCE TO FINISH | RETAINAGE | ||
|---|---|---|---|---|---|---|---|---|---|
| PREVIOUS APPLICATION | THIS PERIOD | TO DATE | % | ||||||
| 3 | Trt.Bldg.Pwr Terms-Materi | 1,029.00 | 1,029.00 | .00 | .00 | 1,029.00 | 100 | .00 | 51.45 |
| Total Trt.Bldg.Pwr Terms | 7,381.00 | 7,381.00 | .00 | .00 | 7,381.00 | 100 | .00 | 369.05 | |
| 11330 | Trt.Bldg. Equip | ||||||||
| 1 | Trt.Bldg. Equip-Labor | 25,754.00 | 25,754.00 | .00 | .00 | 25,754.00 | 100 | .00 | 1,287.70 |
| 3 | Trt.Bldg. Equip-Material | 90,861.00 | 90,861.00 | .00 | .00 | 90,861.00 | 100 | .00 | 4,543.05 |
| Total Trt.Bldg. Equip | 116,615.00 | 116,615.00 | .00 | .00 | 116,615.00 | 100 | .00 | 5,830.75 | |
| 11340 | Trt.Bldg.Branch Cond | ||||||||
| 1 | Trt.Bldg.Branch Cond-Labo | 18,940.00 | 18,940.00 | .00 | .00 | 18,940.00 | 100 | .00 | 947.00 |
| 3 | Trt.Bldg.Branch Cond-Mate | 11,570.00 | 11,570.00 | .00 | .00 | 11,570.00 | 100 | .00 | 578.50 |
| Total Trt.Bldg.Branch Cond | 30,510.00 | 30,510.00 | .00 | .00 | 30,510.00 | 100 | .00 | 1,525.50 | |
| 11350 | Trt.Bldg.Branch Wire | ||||||||
| 1 | Trt.Bldg.Branch Wire-Labo | 2,772.00 | 2,716.56 | 55.44 | .00 | 2,772.00 | 100 | .00 | 138.60 |
| 3 | Trt.Bldg.Branch Wire-Mate | 997.00 | 977.06 | 19.94 | .00 | 997.00 | 100 | .00 | 49.85 |
| Total Trt.Bldg.Branch Wire | 3,769.00 | 3,693.62 | 75.38 | .00 | 3,769.00 | 100 | .00 | 188.45 | |
| 11360 | Trt.Bldg.Branch Dev | ||||||||
| 1 | Trt.Bldg.Branch Dev-Labor | 4,157.00 | 4,073.86 | 83.14 | .00 | 4,157.00 | 100 | .00 | 207.85 |
| 3 | Trt.Bldg.Branch Dev-Mater | 1,459.00 | 1,429.82 | 29.18 | .00 | 1,459.00 | 100 | .00 | 72.95 |
| Total Trt.Bldg.Branch Dev | 5,616.00 | 5,503.68 | 112.32 | .00 | 5,616.00 | 100 | .00 | 280.80 | |
| 11370 | Trt.Bldg.Ltg.Cond | ||||||||
| 1 | Trt.Bldg.Ltg.Cond-Labor | 22,289.00 | 20,060.10 | 2,228.90 | .00 | 22,289.00 | 100 | .00 | 1,114.45 |
| 3 | Trt.Bldg.Ltg.Cond-Materia | 12,545.00 | 11,290.50 | 1,254.50 | .00 | 12,545.00 | 100 | .00 | 627.25 |
| Total Trt.Bldg.Ltg.Cond | 34,834.00 | 31,350.60 | 3,483.40 | .00 | 34,834.00 | 100 | .00 | 1,741.70 | |
| 11380 | Trt.Bldg.Ltg.Wire | ||||||||
| 1 | Trt.Bldg.Ltg.Wire-Labor | 1,790.00 | 1,611.00 | 179.00 | .00 | 1,790.00 | 100 | .00 | 89.50 |
| 3 | Trt.Bldg.Ltg.Wire-Materia | 669.00 | 602.10 | 66.90 | .00 | 669.00 | 100 | .00 | 33.45 |
| Total Trt.Bldg.Ltg.Wire | 2,459.00 | 2,213.10 | 245.90 | .00 | 2,459.00 | 100 | .00 | 122.95 | |
| 11390 | Trt.Bldg.Lt.fixt | ||||||||
| 1 | Trt.Bldg.Lt.fixt-Labor | 7,391.00 | 6,651.90 | 739.10 | .00 | 7,391.00 | 100 | .00 | 369.55 |
| 3 | Trt.Bldg.Lt.fixt-Material | 204,093.00 | 204,093.00 | .00 | .00 | 204,093.00 | 100 | .00 | 10,204.65 |
| Total Trt.Bldg.Lt.fixt | 211,484.00 | 210,744.90 | 739.10 | .00 | 211,484.00 | 100 | .00 | 10,574.20 | |
| 21300 | Inflt. Pmp.St Pwr Cond | ||||||||
| 1 | Inflt. Pmp.St Pwr Cond-La | 6,698.00 | 6,698.00 | .00 | .00 | 6,698.00 | 100 | .00 | 334.90 |
7 of 19
Job Number: CEG800 Rid.Creek Sewage Trtmnt. Plnt.
Application No.: 14 Period From: 03/31/10 Page Number 5
Project # :
Invoice Number : 4363 Thru: 05/30/10
| ITEM NUMBER | DESCRIPTION OF WORK | SCHEDULED VALUE | ----WORK COMPLETED---- | STORED MATERIALS | COMPLETED AND STORED | BALANCE TO FINISH | RETAINAGE | ||
|---|---|---|---|---|---|---|---|---|---|
| PREVIOUS APPLICATION | THIS PERIOD | TO DATE | % | ||||||
| 3 | Inflt. Pmp.St Pwr Cond-Ma | 3,460.00 | 3,460.00 | .00 | .00 | 3,460.00 | 100 | .00 | 173.00 |
| Total Inflt. Pmp.St Pwr Cond | 10,158.00 | 10,158.00 | .00 | .00 | 10,158.00 | 100 | .00 | 507.90 | |
| 21310 | Inflt. Pmp.St Pwr Cab | ||||||||
| 1 | Inflt. Pmp.St Pwr Cab-Lab | 7,565.00 | 7,565.00 | .00 | .00 | 7,565.00 | 100 | .00 | 378.25 |
| 3 | Inflt. Pmp.St Pwr Cab-Mat | 2,249.00 | 2,249.00 | .00 | .00 | 2,249.00 | 100 | .00 | 112.45 |
| Total Inflt. Pmp.St Pwr Cab | 9,814.00 | 9,814.00 | .00 | .00 | 9,814.00 | 100 | .00 | 490.70 | |
| 21320 | Inflt. Pmp.St Pwr Term | ||||||||
| 1 | Inflt. Pmp.St Pwr Term-La | 1,763.00 | 1,763.00 | .00 | .00 | 1,763.00 | 100 | .00 | 88.15 |
| 3 | Inflt. Pmp.St Pwr Term-Ma | 313.00 | 313.00 | .00 | .00 | 313.00 | 100 | .00 | 15.65 |
| Total Inflt. Pmp.St Pwr Term | 2,076.00 | 2,076.00 | .00 | .00 | 2,076.00 | 100 | .00 | 103.80 | |
| 21330 | Inflt. Pmp.St Equip. | ||||||||
| 1 | Inflt. Pmp.St Equip.-Labo | 973.00 | 973.00 | .00 | .00 | 973.00 | 100 | .00 | 48.65 |
| 3 | Inflt. Pmp.St Equip.-Mate | 355.00 | 355.00 | .00 | .00 | 355.00 | 100 | .00 | 17.75 |
| Total Inflt. Pmp.St Equip. | 1,328.00 | 1,328.00 | .00 | .00 | 1,328.00 | 100 | .00 | 66.40 | |
| 21340 | Inflt. Pmp.St Ltg.Cond | ||||||||
| 1 | Inflt. Pmp.St Ltg.Cond-La | 3,951.00 | 3,951.00 | .00 | .00 | 3,951.00 | 100 | .00 | 197.55 |
| 3 | Inflt. Pmp.St Ltg.Cond-Ma | 4,846.00 | 4,846.00 | .00 | .00 | 4,846.00 | 100 | .00 | 242.30 |
| Total Inflt. Pmp.St Ltg.Cond | 8,797.00 | 8,797.00 | .00 | .00 | 8,797.00 | 100 | .00 | 439.85 | |
| 21350 | Inflt. Pmp.St Ltg.Wire | ||||||||
| 1 | Inflt. Pmp.St Ltg.Wire-La | 2,431.00 | 2,431.00 | .00 | .00 | 2,431.00 | 100 | .00 | 121.55 |
| 3 | Inflt. Pmp.St Ltg.Wire-Ma | 1,979.00 | 1,979.00 | .00 | .00 | 1,979.00 | 100 | .00 | 98.95 |
| Total Inflt. Pmp.St Ltg.Wire | 4,410.00 | 4,410.00 | .00 | .00 | 4,410.00 | 100 | .00 | 220.50 | |
| 21360 | Inflt. Pmp.St Ltg.Fixt | ||||||||
| 1 | Inflt. Pmp.St Ltg.Fixt-La | 2,006.00 | 2,006.00 | .00 | .00 | 2,006.00 | 100 | .00 | 100.30 |
| 3 | Inflt. Pmp.St Ltg.Fixt-Ma | 11,578.00 | 11,578.00 | .00 | .00 | 11,578.00 | 100 | .00 | 578.90 |
| Total Inflt. Pmp.St Ltg.Fixt | 13,584.00 | 13,584.00 | .00 | .00 | 13,584.00 | 100 | .00 | 679.20 | |
| 31300 | Screen Bldg Pwr Cond | ||||||||
| 1 | Screen Bldg Pwr Cond-Labo | 13,397.00 | 13,397.00 | .00 | .00 | 13,397.00 | 100 | .00 | 669.85 |
| 3 | Screen Bldg Pwr Cond-Mate | 9,566.00 | 9,566.00 | .00 | .00 | 9,566.00 | 100 | .00 | 478.30 |
| Total Screen Bldg Pwr Cond | 22,963.00 | 22,963.00 | .00 | .00 | 22,963.00 | 100 | .00 | 1,148.15 | |
| 31310 | Screen Bldg Pwr Cab | ||||||||
| 1 | Screen Bldg Pwr Cab-Labor | 2,067.00 | 1,963.65 | 103.35 | .00 | 2,067.00 | 100 | .00 | 103.35 |
8 of 19
Job Number: CEG800 Rid.Creek Sewage Trtmnt. Plnt.
Application No.: 14 Period From: 03/31/10 Page Number 6
Project # :
Invoice Number : 4363 Thru: 05/30/10
| ITEM NUMBER | DESCRIPTION OF WORK | SCHEDULED VALUE | ----WORK COMPLETED---- | STORED MATERIALS | COMPLETED AND STORED | BALANCE TO FINISH | RETAINAGE | ||
|---|---|---|---|---|---|---|---|---|---|
| PREVIOUS APPLICATION | THIS PERIOD | TO DATE | % | ||||||
| 3 | Screen Bldg Pwr Cab-Mater | 645.00 | 612.75 | 32.25 | .00 | 645.00 | 100 | .00 | 32.25 |
| Total Screen Bldg Pwr Cab | 2,712.00 | 2,576.40 | 135.60 | .00 | 2,712.00 | 100 | .00 | 135.60 | |
| 31320 | Screen Bldg Pwr Term | ||||||||
| 1 | Screen Bldg Pwr Term-Labo | 486.00 | 481.14 | 4.86 | .00 | 486.00 | 100 | .00 | 24.30 |
| 3 | Screen Bldg Pwr Term-Mate | 75.00 | 74.25 | .75 | .00 | 75.00 | 100 | .00 | 3.75 |
| Total Screen Bldg Pwr Term | 561.00 | 555.39 | 5.61 | .00 | 561.00 | 100 | .00 | 28.05 | |
| 31330 | Screen Bldg. Eq | ||||||||
| 1 | Screen Bldg. Eq-Labor | 2,310.00 | 2,310.00 | .00 | .00 | 2,310.00 | 100 | .00 | 115.50 |
| 3 | Screen Bldg. Eq-Material | 879.00 | 879.00 | .00 | .00 | 879.00 | 100 | .00 | 43.95 |
| Total Screen Bldg. Eq | 3,189.00 | 3,189.00 | .00 | .00 | 3,189.00 | 100 | .00 | 159.45 | |
| 41300 | Sldg Dewat Bld Pwr Cond | ||||||||
| 1 | Sldg Dewat Bld Pwr Cond-L | 17,554.00 | .00 | .00 | .00 | .00 | 0 | 17,554.00 | .00 |
| 3 | Sldg Dewat Bld Pwr Cond-M | 9,283.00 | .00 | .00 | .00 | .00 | 0 | 9,283.00 | .00 |
| Total Sldg Dewat Bld Pwr Cond | 26,837.00 | .00 | .00 | .00 | .00 | 0 | 26,837.00 | .00 | |
| 41310 | Sldg Dewat Bld Pwr Cab | ||||||||
| 1 | Sldg Dewat Bld Pwr Cab-La | 6,813.00 | .00 | .00 | .00 | .00 | 0 | 6,813.00 | .00 |
| 3 | Sldg Dewat Bld Pwr Cab-Ma | 2,673.00 | .00 | .00 | .00 | .00 | 0 | 2,673.00 | .00 |
| Total Sldg Dewat Bld Pwr Cab | 9,486.00 | .00 | .00 | .00 | .00 | 0 | 9,486.00 | .00 | |
| 41320 | Sldg Dewat Bld Pwr Term | ||||||||
| 1 | Sldg Dewat Bld Pwr Term-L | 8,661.00 | .00 | .00 | .00 | .00 | 0 | 8,661.00 | .00 |
| 3 | Sldg Dewat Bld Pwr Term-M | 1,403.00 | .00 | .00 | .00 | .00 | 0 | 1,403.00 | .00 |
| Total Sldg Dewat Bld Pwr Term | 10,064.00 | .00 | .00 | .00 | .00 | 0 | 10,064.00 | .00 | |
| 41330 | Sldg Dewat Bld Equip | ||||||||
| 1 | Sldg Dewat Bld Equip-Labo | 13,397.00 | .00 | .00 | .00 | .00 | 0 | 13,397.00 | .00 |
| 3 | Sldg Dewat Bld Equip-Mate | 1,150.00 | 1,150.00 | .00 | .00 | 1,150.00 | 100 | .00 | 57.50 |
| Total Sldg Dewat Bld Equip | 14,547.00 | 1,150.00 | .00 | .00 | 1,150.00 | 8 | 13,397.00 | 57.50 | |
| 41400 | Control Rm Bra Cond | ||||||||
| 1 | Control Rm Bra Cond-Labor | 13,859.00 | 6,929.50 | .00 | .00 | 6,929.50 | 50 | 6,929.50 | 346.48 |
| 3 | Control Rm Bra Cond-Mater | 6,526.00 | 3,263.00 | .00 | .00 | 3,263.00 | 50 | 3,263.00 | 163.15 |
| Total Control Rm Bra Cond | 20,385.00 | 10,192.50 | .00 | .00 | 10,192.50 | 50 | 10,192.50 | 509.63 | |
| 41410 | Control Rm Bra Wire | ||||||||
| 1 | Control Rm Bra Wire-Labor | 2,431.00 | .00 | .00 | .00 | .00 | 0 | 2,431.00 | .00 |
9 of 19
Job Number: CEG800 Rid.Creek Sewage Trtmnt. Plnt.
Application No.: 14 Period From: 03/31/10 Page Number 7
Project # :
Invoice Number : 4363 Thru: 05/30/10
| ITEM NUMBER | DESCRIPTION OF WORK | SCHEDULED VALUE | ----WORK COMPLETED---- | STORED MATERIALS | COMPLETED AND STORED | BALANCE TO FINISH | RETAINAGE | ||
|---|---|---|---|---|---|---|---|---|---|
| PREVIOUS APPLICATION | THIS PERIOD | TO DATE | % | ||||||
| 3 | Control Rm Bra Wire-Mater | 781.00 | .00 | .00 | .00 | .00 | 0 | 781.00 | .00 |
| Total Control Rm Bra Wire | 3,212.00 | .00 | .00 | .00 | .00 | 0 | 3,212.00 | .00 | |
| 41420 | Control Rm Equip | ||||||||
| 1 | Control Rm Equip-Labor | 2,067.00 | 1,550.25 | .00 | .00 | 1,550.25 | 75 | 516.75 | 77.51 |
| 3 | Control Rm Equip-Material | 631.00 | 473.25 | .00 | .00 | 473.25 | 75 | 157.75 | 23.66 |
| Total Control Rm Equip | 2,698.00 | 2,023.50 | .00 | .00 | 2,023.50 | 75 | 674.50 | 101.17 | |
| 41430 | Control Rm Ltg Cond | ||||||||
| 1 | Control Rm Ltg Cond-Labor | 14,262.00 | .00 | .00 | .00 | .00 | 0 | 14,262.00 | .00 |
| 3 | Control Rm Ltg Cond-Mater | 6,526.00 | .00 | .00 | .00 | .00 | 0 | 6,526.00 | .00 |
| Total Control Rm Ltg Cond | 20,788.00 | .00 | .00 | .00 | .00 | 0 | 20,788.00 | .00 | |
| 41440 | Control Rm Ltg Wire | ||||||||
| 1 | Control Rm Ltg Wire-Labor | 2,431.00 | .00 | .00 | .00 | .00 | 0 | 2,431.00 | .00 |
| 3 | Control Rm Ltg Wire-Mater | 781.00 | .00 | .00 | .00 | .00 | 0 | 781.00 | .00 |
| Total Control Rm Ltg Wire | 3,212.00 | .00 | .00 | .00 | .00 | 0 | 3,212.00 | .00 | |
| 41450 | Control Rm Ltg Fixt | ||||||||
| 1 | Control Rm Ltg Fixt-Labor | 2,918.00 | .00 | .00 | .00 | .00 | 0 | 2,918.00 | .00 |
| 3 | Control Rm Ltg Fixt-Mater | 9,336.00 | 9,336.00 | .00 | .00 | 9,336.00 | 100 | .00 | 466.80 |
| Total Control Rm Ltg Fixt | 12,254.00 | 9,336.00 | .00 | .00 | 9,336.00 | 76 | 2,918.00 | 466.80 | |
| Job Totals | 1007313.24 | 844,905.34 | 38,110.55 | .00 | 883,015.89 | 88 | 124,297.35 | 45,816.45 | |
10 of 19
William H. Clinger Corp.
PO Box 158, 736 Baltimore Pike
Concordville, PA 19331
JOB: CEG800 Rid.Creek Sewage Trtmnt. Plnt.
Contract No:
Certified Payroll Report
Page: 1
For Week Starting: 03/29/2010 Ending: 04/04/2010
Employee 1:
Job Classification: Apprentice 4
Name & Address: JOHN P MC GINLEY, 40 RUTH ROAD, BROOKHAVEN PA 19015
Exmp,Soc.Sec.#,Minority: M-1, XXX-XX-2359, White Male
| Mon. 29 | Tue. 30 | Wed. 31 | Thu. 01 | Fri. 02 | Sat. 03 | Sun. 04 | Total Hours | Hourly Rate | Gross Pay | Deductions | Tax.Gross | Non-Txble | Tot Ded's | Net Pay | Check No. | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| P | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | Fed. W/T | 43.75 | COPE | .72 | 695.16 | .00 | 206.75 | 488.41 | 015091 |
| O | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | FICA | 53.18 | DUES | 37.54 | |||||
| S | 8.00 | 8.00 | 8.00 | 8.00 | 4.00 | .00 | .00 | 36.00 | 19.31 | 695.16 | State W/T | 21.34 | CREDIT UNI | 41.71 | |||||
| EMPLOYER PAID BENEFITS ......... 367.16 | Local W/T | 6.95 | |||||||||||||||||
| HRS & GROSS THIS JOB 36.00 ..... 695.16 | SDI/SUI | .56 | |||||||||||||||||
| EXPENSE & PER DIEM THIS JOB ..... .00 | Direct Dep | 1.00 | |||||||||||||||||
| TOTAL ..... 1062.32 | |||||||||||||||||||
Employee 2:
Job Classification: Journeyman
Name & Address: MATTHEW J BURKE, 846 DOWNINGTOWN PIKE, WEST CHESTER PA 19380
Exmp,Soc.Sec.#,Minority: S-0, XXX-XX-4590, White Male
| P | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | Fed. W/T | 267.89 | COPE | .72 | 1425.60 | .00 | 600.36 | 825.24 | 015099 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| O | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | FICA | 109.06 | DUES | 76.98 | |||||
| S | 8.00 | 8.00 | 8.00 | 8.00 | 4.00 | .00 | .00 | 36.00 | 39.60 | 1425.60 | State W/T | 43.77 | CREDIT UNI | 85.54 | |||||
| EMPLOYER PAID BENEFITS ......... 714.04 | Local W/T | 14.26 | |||||||||||||||||
| HRS & GROSS THIS JOB 36.00 ..... 1425.60 | SDI/SUI | 1.14 | |||||||||||||||||
| EXPENSE & PER DIEM THIS JOB ..... .00 | Direct Dep | 1.00 | |||||||||||||||||
| TOTAL ..... 2139.64 | |||||||||||||||||||
Employee 3:
Job Classification: [blank]
Name & Address: ROBERT F DINA, SR., 1 BOHEMIA RD, BEAR DE 19701
Exmp,Soc.Sec.#,Minority: M-3, XXX-XX-8600, White Male
| P | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | Fed. W/T | 364.70 | 2520.00 | .00 | 772.86 | 1747.14 | 015112 | ||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| O | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | FICA | 192.78 | |||||||
| S | .00 | 8.00 | .00 | .00 | .00 | .00 | .00 | 8.00 | 63.00 | 504.00 | State W/T | 112.36 | |||||||
| EMPLOYER PAID BENEFITS ......... .00 | |||||||||||||||||||
| HRS & GROSS THIS JOB 8.00 ..... 504.00 | SDI/SUI | 2.02 | |||||||||||||||||
| EXPENSE & PER DIEM THIS JOB ..... .00 | Direct Dep | 101.00 | |||||||||||||||||
| TOTAL ..... 504.00 | |||||||||||||||||||
11 of 19
William H. Clinger Corp.
PO Box 158, 736 Baltimore Pike
Concordville, PA 19331
JOB: CEG800 Rid.Creek Sewage Trtmnt. Plnt.
Contract No:
Certified Payroll Report
Page: 2
For Week Starting: 03/29/2010 Ending: 04/04/2010
Job Totals:
| Total Hours | Regular | Overtime | Premium | Total |
|---|---|---|---|---|
| Mon | 16.00 | .00 | .00 | 16.00 |
| Tue | 24.00 | .00 | .00 | 24.00 |
| Wed | 16.00 | .00 | .00 | 16.00 |
| Thu | 16.00 | .00 | .00 | 16.00 |
| Fri | 8.00 | .00 | .00 | 8.00 |
| Sat | .00 | .00 | .00 | .00 |
| Sun | .00 | .00 | .00 | .00 |
| TOTAL HOURS FOR WEEK | 80.00 | .00 | .00 | 80.00 |
| TOTAL EMPLOYER PAID BENEFITS FOR WEEK | 1081.20 |
|---|---|
| TOTAL GROSS FOR WEEK | 2624.76 |
| TOTAL EXPENSE & PER DIEM | .00 |
| TOTAL FOR WEEK | 3705.96 |
Wages And Deductions
| Total Pay | 4640.76 |
|---|---|
| FICA | 355.02 |
| Federal Tax | 676.34 |
| State & Local Taxes | 202.40 |
| Misc. Deductions | 103.00 |
| Union Dues | 243.21 |
| Total Deductions | 1579.97 |
| Net Pay | 3060.79 |
12 of 19
William H. Clinger Corp.
PO Box 158, 736 Baltimore Pike
Concordville, PA 19331
JOB: CEG800 Rid.Creek Sewage Trtmnt. Plnt.
Contract No:
Certified Payroll Report
Page: 1
For Week Starting: 04/05/2010 Ending: 04/11/2010
Employee 1:
Job Classification: Apprentice 4
Name & Address: JOHN P MC GINLEY, 40 RUTH ROAD, BROOKHAVEN PA 19015
Exmp,Soc.Sec.#,Minority: M-1, XXX-XX-2359, White Male
| Mon. 05 | Tue. 06 | Wed. 07 | Thu. 08 | Fri. 09 | Sat. 10 | Sun. 11 | Total Hours | Hourly Rate | Gross Pay | Deductions | Tax.Gross | Non-Txble | Tot Ded's | Net Pay | Check No. | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| P | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | Fed. W/T | 55.33 | COPE | .80 | 772.40 | .00 | 236.32 | 536.08 | 015132 |
| O | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | FICA | 59.09 | DUES | 41.71 | |||||
| S | 8.00 | 8.00 | 8.00 | 8.00 | 8.00 | .00 | .00 | 40.00 | 19.31 | 772.40 | State W/T | 23.71 | CREDIT UNI | 46.34 | |||||
| EMPLOYER PAID BENEFITS ......... 407.95 | Local W/T | 7.72 | |||||||||||||||||
| HRS & GROSS THIS JOB 40.00 ..... 772.40 | SDI/SUI | .62 | |||||||||||||||||
| EXPENSE & PER DIEM THIS JOB ..... .00 | Direct Dep | 1.00 | |||||||||||||||||
| TOTAL ..... 1180.35 | |||||||||||||||||||
Employee 2:
Job Classification: Journeyman
Name & Address: MATTHEW J BURKE, 846 DOWNINGTOWN PIKE, WEST CHESTER PA 19380
Exmp,Soc.Sec.#,Minority: S-0, XXX-XX-4590, White Male
| P | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | Fed. W/T | 310.66 | COPE | .80 | 1584.00 | .00 | 679.96 | 904.04 | 015140 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| O | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | FICA | 121.18 | DUES | 85.54 | |||||
| S | 8.00 | 8.00 | 8.00 | 8.00 | 8.00 | .00 | .00 | 40.00 | 39.60 | 1584.00 | State W/T | 48.63 | CREDIT UNI | 95.04 | |||||
| EMPLOYER PAID BENEFITS ......... 793.38 | Local W/T | 15.84 | |||||||||||||||||
| HRS & GROSS THIS JOB 40.00 ..... 1584.00 | SDI/SUI | 1.27 | |||||||||||||||||
| EXPENSE & PER DIEM THIS JOB ..... .00 | Direct Dep | 1.00 | |||||||||||||||||
| TOTAL ..... 2377.38 | |||||||||||||||||||
Employee 3:
Job Classification: [blank]
Name & Address: ROBERT F DINA, SR., 1 BOHEMIA RD, BEAR DE 19701
Exmp,Soc.Sec.#,Minority: M-3, XXX-XX-8600, White Male
| P | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | Fed. W/T | 364.70 | 2520.00 | .00 | 772.86 | 1747.14 | 015153 | ||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| O | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | FICA | 192.78 | |||||||
| S | .00 | 16.00 | .00 | .00 | .00 | .00 | .00 | 16.00 | 63.00 | 1008.00 | State W/T | 112.36 | |||||||
| EMPLOYER PAID BENEFITS ......... .00 | |||||||||||||||||||
| HRS & GROSS THIS JOB 16.00 ..... 1008.00 | SDI/SUI | 2.02 | |||||||||||||||||
| EXPENSE & PER DIEM THIS JOB ..... .00 | Direct Dep | 101.00 | |||||||||||||||||
| TOTAL ..... 1008.00 | |||||||||||||||||||
13 of 19
William H. Clinger Corp.
PO Box 158, 736 Baltimore Pike
Concordville, PA 19331
JOB: CEG800 Rid.Creek Sewage Trtmnt. Plnt.
Contract No:
Certified Payroll Report
Page: 2
For Week Starting: 04/05/2010 Ending: 04/11/2010
Job Totals:
| Total Hours | Regular | Overtime | Premium | Total |
|---|---|---|---|---|
| Mon | 16.00 | .00 | .00 | 16.00 |
| Tue | 32.00 | .00 | .00 | 32.00 |
| Wed | 16.00 | .00 | .00 | 16.00 |
| Thu | 16.00 | .00 | .00 | 16.00 |
| Fri | 16.00 | .00 | .00 | 16.00 |
| Sat | .00 | .00 | .00 | .00 |
| Sun | .00 | .00 | .00 | .00 |
| TOTAL HOURS FOR WEEK | 96.00 | .00 | .00 | 96.00 |
| TOTAL EMPLOYER PAID BENEFITS FOR WEEK | 1201.33 |
|---|---|
| TOTAL GROSS FOR WEEK | 3364.40 |
| TOTAL EXPENSE & PER DIEM | .00 |
| TOTAL FOR WEEK | 4565.73 |
Wages And Deductions
| Total Pay | 4876.40 |
|---|---|
| FICA | 373.05 |
| Federal Tax | 730.69 |
| State & Local Taxes | 212.17 |
| Misc. Deductions | 103.00 |
| Union Dues | 270.23 |
| Total Deductions | 1689.14 |
| Net Pay | 3187.26 |
14 of 19
William H. Clinger Corp.
PO Box 158, 736 Baltimore Pike
Concordville, PA 19331
JOB: CEG800 Rid.Creek Sewage Trtmnt. Plnt.
Contract No:
Certified Payroll Report
Page: 1
For Week Starting: 04/12/2010 Ending: 04/18/2010
Employee 1:
Job Classification: Apprentice 4
Name & Address: JOHN P MC GINLEY, 40 RUTH ROAD, BROOKHAVEN PA 19015
Exmp,Soc.Sec.#,Minority: M-1, XXX-XX-2359, White Male
| Mon. 12 | Tue. 13 | Wed. 14 | Thu. 15 | Fri. 16 | Sat. 17 | Sun. 18 | Total Hours | Hourly Rate | Gross Pay | Deductions | Tax.Gross | Non-Txble | Tot Ded's | Net Pay | Check No. | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| P | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | Fed. W/T | 55.33 | COPE | .80 | 772.40 | .00 | 236.32 | 536.08 | 015174 |
| O | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | FICA | 59.09 | DUES | 41.71 | |||||
| S | 8.00 | 8.00 | 8.00 | 8.00 | 8.00 | .00 | .00 | 40.00 | 19.31 | 772.40 | State W/T | 23.71 | CREDIT UNI | 46.34 | |||||
| EMPLOYER PAID BENEFITS ......... 407.95 | Local W/T | 7.72 | |||||||||||||||||
| HRS & GROSS THIS JOB 40.00 ..... 772.40 | SDI/SUI | .62 | |||||||||||||||||
| EXPENSE & PER DIEM THIS JOB ..... .00 | Direct Dep | 1.00 | |||||||||||||||||
| TOTAL ..... 1180.35 | |||||||||||||||||||
Employee 2:
Job Classification: Journeyman
Name & Address: MATTHEW J BURKE, 846 DOWNINGTOWN PIKE, WEST CHESTER PA 19380
Exmp,Soc.Sec.#,Minority: S-0, XXX-XX-4590, White Male
| P | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | Fed. W/T | 310.66 | DUES | 85.54 | 1584.00 | .00 | 664.12 | 919.88 | 015182 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| O | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | FICA | 121.18 | CREDIT UNI | 95.04 | |||||
| S | 8.00 | 8.00 | 8.00 | 8.00 | 8.00 | .00 | .00 | 40.00 | 39.60 | 1584.00 | State W/T | 48.63 | |||||||
| EMPLOYER PAID BENEFITS ......... 793.38 | |||||||||||||||||||
| HRS & GROSS THIS JOB 40.00 ..... 1584.00 | SDI/SUI | 1.27 | |||||||||||||||||
| EXPENSE & PER DIEM THIS JOB ..... .00 | Direct Dep | 1.00 | |||||||||||||||||
| TOTAL ..... 2377.38 | COPE | .80 | |||||||||||||||||
15 of 19
William H. Clinger Corp.
PO Box 158, 736 Baltimore Pike
Concordville, PA 19331
JOB: CEG800 Rid.Creek Sewage Trtmnt. Plnt.
Contract No:
Certified Payroll Report
Page: 2
For Week Starting: 04/12/2010 Ending: 04/18/2010
Job Totals:
| Total Hours | Regular | Overtime | Premium | Total |
|---|---|---|---|---|
| Mon | 16.00 | .00 | .00 | 16.00 |
| Tue | 16.00 | .00 | .00 | 16.00 |
| Wed | 16.00 | .00 | .00 | 16.00 |
| Thu | 16.00 | .00 | .00 | 16.00 |
| Fri | 16.00 | .00 | .00 | 16.00 |
| Sat | .00 | .00 | .00 | .00 |
| Sun | .00 | .00 | .00 | .00 |
| TOTAL HOURS FOR WEEK | 80.00 | .00 | .00 | 80.00 |
| TOTAL EMPLOYER PAID BENEFITS FOR WEEK | 1201.33 |
|---|---|
| TOTAL GROSS FOR WEEK | 2356.40 |
| TOTAL EXPENSE & PER DIEM | .00 |
| TOTAL FOR WEEK | 3557.73 |
Wages And Deductions
| Total Pay | 2356.40 |
|---|---|
| FICA | 180.27 |
| Federal Tax | 365.99 |
| State & Local Taxes | 81.95 |
| Misc. Deductions | 2.00 |
| Union Dues | 270.23 |
| Total Deductions | 900.44 |
| Net Pay | 1455.96 |
16 of 19
William H. Clinger Corp.
PO Box 158, 736 Baltimore Pike
Concordville, PA 19331
JOB: CEG800 Rid.Creek Sewage Trtmnt. Plnt.
Contract No:
Certified Payroll Report
Page: 1
For Week Starting: 04/19/2010 Ending: 04/25/2010
Employee 1:
Job Classification: Apprentice 4
Name & Address: JOHN P MC GINLEY, 40 RUTH ROAD, BROOKHAVEN PA 19015
Exmp,Soc.Sec.#,Minority: M-1, XXX-XX-2359, White Male
| Mon. 19 | Tue. 20 | Wed. 21 | Thu. 22 | Fri. 23 | Sat. 24 | Sun. 25 | Total Hours | Hourly Rate | Gross Pay | Deductions | Tax.Gross | Non-Txble | Tot Ded's | Net Pay | Check No. | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| P | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | Fed. W/T | 55.33 | COPE | .80 | 772.40 | .00 | 236.32 | 536.08 | 015215 |
| O | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | FICA | 59.09 | DUES | 41.71 | |||||
| S | 8.00 | 8.00 | 8.00 | 8.00 | 8.00 | .00 | .00 | 40.00 | 19.31 | 772.40 | State W/T | 23.71 | CREDIT UNI | 46.34 | |||||
| EMPLOYER PAID BENEFITS ......... 407.95 | Local W/T | 7.72 | |||||||||||||||||
| HRS & GROSS THIS JOB 40.00 ..... 772.40 | SDI/SUI | .62 | |||||||||||||||||
| EXPENSE & PER DIEM THIS JOB ..... .00 | Direct Dep | 1.00 | |||||||||||||||||
| TOTAL ..... 1180.35 | |||||||||||||||||||
Employee 2:
Job Classification: Journeyman
Name & Address: MATTHEW J BURKE, 846 DOWNINGTOWN PIKE, WEST CHESTER PA 19380
Exmp,Soc.Sec.#,Minority: S-0, XXX-XX-4590, White Male
| P | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | Fed. W/T | 310.66 | COPE | .80 | 1584.00 | .00 | 679.96 | 904.04 | 015223 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| O | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | .00 | FICA | 121.18 | DUES | 85.54 | |||||
| S | 8.00 | 8.00 | 8.00 | 8.00 | 8.00 | .00 | .00 | 40.00 | 39.60 | 1584.00 | State W/T | 48.63 | CREDIT UNI | 95.04 | |||||
| EMPLOYER PAID BENEFITS ......... 793.38 | Local W/T | 15.84 | |||||||||||||||||
| HRS & GROSS THIS JOB 40.00 ..... 1584.00 | SDI/SUI | 1.27 | |||||||||||||||||
| EXPENSE & PER DIEM THIS JOB ..... .00 | Direct Dep | 1.00 | |||||||||||||||||
| TOTAL ..... 2377.38 | |||||||||||||||||||
17 of 19
William H. Clinger Corp.
PO Box 158, 736 Baltimore Pike
Concordville, PA 19331
JOB: CEG800 Rid.Creek Sewage Trtmnt. Plnt.
Contract No:
Certified Payroll Report
Page: 2
For Week Starting: 04/19/2010 Ending: 04/25/2010
Job Totals:
| Total Hours | Regular | Overtime | Premium | Total |
|---|---|---|---|---|
| Mon | 16.00 | .00 | .00 | 16.00 |
| Tue | 16.00 | .00 | .00 | 16.00 |
| Wed | 16.00 | .00 | .00 | 16.00 |
| Thu | 16.00 | .00 | .00 | 16.00 |
| Fri | 16.00 | .00 | .00 | 16.00 |
| Sat | .00 | .00 | .00 | .00 |
| Sun | .00 | .00 | .00 | .00 |
| TOTAL HOURS FOR WEEK | 80.00 | .00 | .00 | 80.00 |
| TOTAL EMPLOYER PAID BENEFITS FOR WEEK | 1201.33 |
|---|---|
| TOTAL GROSS FOR WEEK | 2356.40 |
| TOTAL EXPENSE & PER DIEM | .00 |
| TOTAL FOR WEEK | 3557.73 |
Wages And Deductions
| Total Pay | 2356.40 |
|---|---|
| FICA | 180.27 |
| Federal Tax | 365.99 |
| State & Local Taxes | 97.79 |
| Misc. Deductions | 2.00 |
| Union Dues | 270.23 |
| Total Deductions | 916.28 |
| Net Pay | 1440.12 |
18 of 19
CLINGER
Nearly a half-century of excellence
736 Baltimore Pike
P.O. Box 158
Concordville, PA 19331
Phone: (610) 459-1234
Fax: (610) 459-8823
Attn: Matt McAloon
3001 Mareket Street
Philadelphia, PA 19104
Re: Ridley Creek Sewage Treatment Plant Upgrade and Expansion Project
May 4, 2010
To Whom It May Concern:
Upon receipt of payment for our application # 14, Wm. H. Clinger Corp. will be paying the following vendors: A Cutting Edge Corp. @ $4,050; Eastern HighReach Co @ $2,767; Rumsey Electric Supply Co. @ $38,216 and Acton Mobile Industries @ $54.
Sincerely,
Joseph P. Natale
Chief Financial Officer
William H. Clinger Corp.
ELECTRICAL CONSTRUCTION ■ COMMUNICATIONS CABLING ■ COMPUTER NETWORKS
19 of 19
COMMONWEALTH OF PENNSYLVANIA
STD-28 REV. 07/07
MONTHLY CONTRACT COMPLIANCE REPORT FOR CONSTRUCTION CONTRACTORS
| 1. CONTRACT NO. C000045819 |
2. FEDERAL INCOME TAX NO. 23-1538466 |
3. CURRENT REPORT PERIOD BEGINNING DATE: 3-29-10 ENDING DATE: 5-2-10 |
4. NAME AND ADDRESS OF FIRM WM. H. CLINGER CORPORATION 736 BALTIMORE PIKE, PO BOX 158 CONCORDVILLE, PA 19331 |
5. [X] CONTRACTOR [ ] SUBCONTRACTOR |
|---|---|---|---|---|
| 6. HAVE SUBCONTRACTS BEEN SIGNED? ___ YES ___ NO/NOT ALL |
7. COUNTY WHERE PROJECT IS LOCATED CHESTER |
8. JOB SITE RIDLEY CREEK SEWAGE TREATMENT PLANT PROJECT NO. EGMA0707 |
9. DO SUBCONTRACTS CONTAIN NONDISCRIMINATION CLAUSE AS REQUIRED BY THE STATE CONTRACT? [X] YES ___ NOT YET/NOT ALL |
|
| 10. PERCENT OF PROJECT COMPLETE 88 % |
11. NOTICE TO PROCEED DATE 11/14/2008 |
12. DOLLAR AMOUNT OF CONTRACT $ 974,000.00 |
13. ESTIMATED PROJECT PEAK EMPLOYMENT A. MONTH & YEAR: JAN-2010 | B. NO. OF EMPLOYEES: 9 |
|
| JOB CLASSIFICATION | 14. HOURS WORKED ON PROJECT FOR REPORT PERIOD - TOTAL HOURS OF ALL EMPLOYEES BY TRADE (M) | TOTAL HOURS (F) | BLACK (NOT OF HISPANIC ORIGIN) (M) | BLACK (F) | HISPANIC (M) | HISPANIC (F) | AMERICAN INDIAN OR ALASKAN NATIVE (M) | AMERICAN INDIAN (F) | ASIAN OR PACIFIC ISLANDER (M) | ASIAN OR PACIFIC ISLANDER (F) | 15. EMPLOYEES ON PROJECT - NUMBER OF EMPLOYEES (M) | NUMBER OF EMPLOYEES (F) | NUMBER OF MINORITY EMPLOYEES (M) | NUMBER OF MINORITY EMPLOYEES (F) |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| OFFICIALS & MANAGERS | 24 | 1 | ||||||||||||
| SUPERVISORS | ||||||||||||||
| FOREMEN/WOMEN | 160 | 1 | ||||||||||||
| OFFICE & CLERICAL | ||||||||||||||
| EQUIPMENT OPERATORS | ||||||||||||||
| MECHANICS | ||||||||||||||
| TRUCK DRIVERS | ||||||||||||||
| METAL WORKERS (iron, sheet...) | ||||||||||||||
| CARPENTERS | ||||||||||||||
| MASONS (brick, stone, cement...) | ||||||||||||||
| ELECTRICIANS | ||||||||||||||
| PIPEFITTERS, PLUMBERS | ||||||||||||||
| PAINTERS | ||||||||||||||
| LABORERS, SEMI-SKILLED | ||||||||||||||
| LABORERS, UNSKILLED | ||||||||||||||
| APPRENTICES | 152 | 1 | ||||||||||||
| OTHER | ||||||||||||||
| TOTALS | 336 | 3 |
16. LIST SUBCONTRACTORS THAT WORKED ON THE PROJECT DURING THE PERIOD AND ATTACH THE STD-28s of those with subcontracts of $100,000 or more
N/A
17. PREPARED BY: (SIGNATURE, NAME & TITLE OF CONTRACTOR/REPRESENTATIVE)
[Signature], JOSEPH P. NATALE - CEO
18. TELEPHONE NO. (INCLUDE AREA CODE)
(610) 459-1234
19. DATE
5-4-10
[Handwritten: 3. RIDLEY CREEK INV
h.
3 pg]
Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS
INVOICE
Philadelphia, PA
215-222-3000 Fax: 215-222-3588
Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice # : 438249
Invoice Date : 05/05/2010
Project : EGMA0707
Project Name : RCSTP Expansion
For Services Rendered through: 04/18/2010
Construction meetings with contractors and Township; construction management; shop drawing and schedule review; site observation of construction and consultation with Township regarding same. Additional effort this invoice period has included special project meetings for Phase 2 start-up; review of the mixed liquor transfer from existing system to new SBR tanks with operator; troubleshooting control problems with influent pumps; responses to Contractor RFIs; schedule reviews; tracking pressure test failure; and review/negotiations of change orders with Township and contractors.
| Phase Code / Name | Contract Amount | Previously Billed | % Complete | Complete To Date | Amount This Invoice |
|---|---|---|---|---|---|
| 01 -- Permit Design | est. $111,400.00 | $111,385.00 | $111,385.00 | $0.00 | |
| 02 -- Permitting | est. $14,200.00 | $14,184.00 | $14,184.00 | $0.00 | |
| 03 -- Final Design | est. $226,700.00 | $226,655.50 | $226,655.50 | $0.00 | |
| 04 -- Bidding | est. $14,500.00 | $14,446.50 | $14,446.50 | $0.00 | |
| 05 -- Construction | est. $136,200.00 | $136,197.62 | $136,197.62 | $0.00 | |
| 06 -- Additional Submittals | est. $20,000.00 | $19,997.18 | $19,997.18 | $0.00 | |
| 10 -- Continued Construction Services | est. $99,700.00 | $73,007.48 | $91,817.98 | $18,810.50 | |
| Total : | $622,700.00 | $595,873.28 | $614,683.78 | $18,810.50 |
Amount Due This Invoice: $18,810.50
[Handwritten: ok TS 5/6]
[Handwritten circled: NEED TO DISCUSS PAGE 3]
[Handwritten circled: 1]
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
2 of 3
East Goshen Municipal Authority
EGMA0707 Invoice Summary
Invoice Date 05-05-2010
| Project: | RCSTP Expansion and Upgrade | ||
|---|---|---|---|
| Pennoni Job No.: | EGMA0707 | ||
| Invoice No: | 438249 | ||
| Invoice Period: | 3/22/2010 | to | 4/18/2010 |
| Initial Authorization: | $ 465,000.00 | Date: | 8/14/2007 |
| Changes: | $ - | Date: | 2/5/2009 |
| Changes: | $ 58,000.00 | Date: | 5/11/2009 |
| Changes: | $ 99,700.00 | Date: | 1/11/2010 |
| Contract Amount: | $ 622,700.00 | ||
| Previously Invoiced: | $ 595,873.28 | ||
| Current Invoice: | $ 18,810.50 | ||
| Invoiced to Date ($): | $ 614,683.78 | ||
| Invoiced to Date (%): | 99% | ||
| Remaining Budget ($): | $ 8,016.22 | ||
| Remaining Budget (%): | 1% | ||
Budget by Phase:
| Phase No. | 05 | 06 | 10 |
|---|---|---|---|
| Phase Name: | Construction | Additional Engineering | Continued Eng Svcs |
| Phase Budget: | $ 88,200.00 | $ 10,000.00 | $ 99,700.00 |
| Change of 5/11/09: | $ 48,000.00 | $ 10,000.00 | |
| Contract Amount: | $ 136,200.00 | $ 20,000.00 | $ 99,700.00 |
| Previously Invoiced: | $ 136,197.62 | $ 16,469.18 | $ 73,007.48 |
| Current Invoice: | $ - | $ 3,528.00 | $ 18,810.50 |
| Invoiced to Date ($): | $ 136,197.62 | $ 19,997.18 | $ 91,817.98 |
| Invoiced to Date (%): | 100% | 100% | 92% |
| Remaining Budget ($): | $ 2.38 | $ 2.82 | $ 7,882.02 |
| Remaining Budget (%): | 0% | 0% | 8% |
Comments: Phase 10 - Continued Engineering Services
Construction meetings with contractors and Township; construction management; shop drawing and schedule review; and site observation of construction. Consultation with Township regarding same.
Additional effort this invoice period has included special project meetings for Phase 2 start-up; review of the mixed liquor transfer from existing system to new SBR tanks with operator; troubleshooting control problems with influent pumps; responses to Contractor RFIs; schedule reviews; tracking pressure test failure; and review/negotiations of change orders with Township and contractors.
Invoiced effort does not include effort related to responding to the Electrical Contractor's letter of 3/15/2010 and review meeting with Township, Brickhouse and the Solicitor.
[Handwritten circled: 2]
3 of 3
East Goshen Municipal Authority
EGMA0707 Invoice Summary
Invoice Date 05-05-2010
Effort by Labor Category under Phase 10:
| Category | Previous Hrs. | Current | Total Hrs. |
|---|---|---|---|
| Authority Engineer | 62.8 | 10.0 | 72.8 |
| Senior Engineer | 215.0 | 44.5 | 259.5 |
| Senior Designer | 57.0 | 41.0 | 98.0 |
| Project Engineer | 38.5 | 10.5 | 49.0 |
| Associate Engineer | 7.0 | 0.0 | 7.0 |
| Graduate Engineer | 43.0 | 0.0 | 43.0 |
| Project Representative/Inspector | 2.5 | 0.0 | 2.5 |
| Technical Specialist (McAloon) | 434.0 | 107.0 | 541.0 |
| Engineering Technician I | 2.5 | 11.0 | 13.5 |
| Administrative Assistant I | 0.5 | 0.0 | 0.5 |
| Totals | 862.8 | 224.0 | 1086.8 |
Budget/Schedule Status (November to June):
Schedule % = 75%
Budget % = 92%
Budgeted effort will exceed the current authorization with the next invoice (effort through May 21, 2010). The current rate of effort is approximately $18,400 per month over the past 5 months. Given the projected construction end date of September 30, 2010 (5 months from now), and approximately 1 month of project close-out (punchlist, contractor final application for payment, as-built plans, etc.) the authorization for continued engineering services should be increased by $110,000 (rounded).
We will make every effort to minimize our effort as we continue with the project, however given the history of the construction to date, we can not provide a final estimate of engineering services required to complete this project.
[Handwritten circled: 3]
[Handwritten: 7. INVOICES a 1pg]
Gawthrop Greenwood, PC
Attorneys at Law
17 East Gay Street, Suite 100
West Chester, PA 19381-0562
gglaw@gawthrop.com
(p) 610-696-8225
(f) 610-344-0922
www.gawthrop.com
COPY
East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380
Page: 1
03/31/2010
Client No: 6604-01M
Statement No. 78561
General Authority Services
Fees
| Date / By | Description | Hours | Amount |
|---|---|---|---|
| 03/08/2010 RFA |
Review packet for Authority meeting of 3/8/10. | 0.50 | |
| 03/31/2010 RFA |
Review letter from Evan Andrews. | 0.30 | |
| For Current Services Rendered | 0.80 | 152.00 | |
Recapitulation
| Timekeeper | Hours | Hourly Rate | Total |
|---|---|---|---|
| Robert F. Adams | 0.80 | $190.00 | $152.00 |
| Previous Balance | $1,102.00 |
|---|---|
| Total Current Charges | 152.00 |
| 03/15/2010 Fee Payment | -627.00 |
| Balance Due | $627.00 |
To ensure proper credit, please write client number on your check when returning payment. Thank You.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.
[Handwritten: 7. INVOICES b. 1pg]
Gawthrop Greenwood, PC
Attorneys at Law
17 East Gay Street, Suite 100
West Chester, PA 19381-0562
gglaw@gawthrop.com
(p) 610-696-8225
(f) 610-344-0922
www.gawthrop.com
COPY
East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380
Page: 1
03/31/2010
Client No: 6604-06M
Statement No. 78562
Ridley Creek Treatment Plant Upgrades/ Expansion
Fees
| Date / By | Description | Hours | Amount |
|---|---|---|---|
| 03/18/2010 RFA |
Review message from Rick Smith and forwarded letter from Clinger. | 0.70 | |
| 03/22/2010 RFA |
Review message from Jack Yahraes regarding delegation of change order authority to Rick Smith; Message to Jack Yahraes regarding procedure for change order approval authorization. | 0.60 | |
| For Current Services Rendered | 1.30 | 247.00 | |
Recapitulation
| Timekeeper | Hours | Hourly Rate | Total |
|---|---|---|---|
| Robert F. Adams | 1.30 | $190.00 | $247.00 |
| Previous Balance | $57.00 |
|---|---|
| Total Current Charges | 247.00 |
| Balance Due | $304.00 |
To ensure proper credit, please write client number on your check when returning payment. Thank You.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.
[Handwritten: 7. INVOICES C. 2 pg]
Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS
INVOICE
Philadelphia, PA
215-222-3000 Fax: 215-222-3588
Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice # : 438211
Invoice Date : 05/03/2010
Project : EGMA0903
Project Name : RCSTP Sewer Modeling
For Services Rendered through: 04/18/2010
Finalize and submit semi-annual report to DEP as required by the CO&A. Consultation with Township.
Phase : **** -- Professional Services
| Labor : | 315.00 |
|---|---|
| Expense : | 0.00 |
| Phase Total : | 315.00 |
Amount Due This Invoice: $315.00
| Fee : | 28,300.00 |
|---|---|
| Prior Billings : | 27,956.50 |
| Current Billings : | 315.00 |
| Total Billings : | 28,271.50 |
Phase : **** -- Professional Services
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 3.00 | 105.00 | 315.00 |
| Labor Total: | 3.00 | 315.00 |
| Total Phase : **** -- Professional Services | Labor : | $315.00 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMA0903 -- RCSTP Sewer Modeling | Labor : | $315.00 |
| Expense : | $0.00 |
[Handwritten: ok TS 5/6]
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
2 of 2
East Goshen Municipal Authority
EGMA0903 Invoice Summary
Invoice Date 05-03-2010
| Project: | RCSTP Sewer Modeling | ||
|---|---|---|---|
| Pennoni Job No.: | EGMA 0903 | ||
| Invoice No: | 438211 | ||
| Invoice Period: | 3/22/2010 | to | 4/18/2010 |
| Initial Authorization: | $ 28,300.00 | Date: | 9/17/2009 |
| Changes: | $ - | Date: | |
| Contract Amount: | $ 28,300.00 | ||
| Previously Invoiced: | $ 27,956.50 | ||
| Current Invoice: | $ 315.00 | ||
| Invoiced to Date ($): | $ 28,271.50 | ||
| Invoiced to Date (%): | 100% | ||
| Remaining Budget ($): | $ 28.50 | ||
| Remaining Budget (%): | 0% | ||
Budget by Phase:
| Phase No. | |
|---|---|
| Phase Name: | RCSTP Sewer Modeling |
| Phase Budget: | $ 28,300.00 |
| Previously Invoiced: | $ 27,956.50 |
| Current Invoice: | $ 315.00 |
| Invoiced to Date ($): | $ 28,271.50 |
| Invoiced to Date (%): | 100% |
| Remaining Budget ($): | $ 28.50 |
| Remaining Budget (%): | 0% |
Comments: Finalize and submit semi-annual report to DEP as required by the CO&A. Consultation with Township. This is the final invoice for the Project.
[Handwritten: 7. INVOICES d. 2 pg]
Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS
INVOICE
Philadelphia, PA
215-222-3000 Fax: 215-222-3588
Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice # : 438212
Invoice Date : 05/03/2010
Project : EGMA1000
Project Name : 2010 Annual Services
For Services Rendered through: 04/18/2010
Preparation and participation in monthly board meeting; and consultation with Township.
Phase : **** -- Professional Services
| Labor : | 367.50 |
|---|---|
| Expense : | 0.00 |
| Phase Total : | 367.50 |
Amount Due This Invoice: $367.50
| Fee : | 10,000.00 |
|---|---|
| Prior Billings : | 7,162.00 |
| Current Billings : | 367.50 |
| Total Billings : | 7,529.50 |
Phase : **** -- Professional Services
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 3.50 | 105.00 | 367.50 |
| Labor Total: | 3.50 | 367.50 |
| Total Phase : **** -- Professional Services | Labor : | $367.50 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMA1000 -- 2010 Annual Services | Labor : | $367.50 |
| Expense : | $0.00 |
[Handwritten: ok TS 5/6]
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
2 of 2
East Goshen Municipal Authority
EGMA1000 Invoice Summary
Invoice Date 05-03-2010
| Project: | 2010 Annual Services | ||
|---|---|---|---|
| Pennoni Job No.: | EGMA 1000 | ||
| Invoice No: | 438212 | ||
| Invoice Period: | 3/22/2010 | to | 4/18/2010 |
| Initial Authorization: | $ 10,000.00 | Date: | 1/11/2010 |
| Changes: | $ - | Date: | |
| Contract Amount: | $ 10,000.00 | ||
| Previously Invoiced: | $ 7,162.00 | ||
| Current Invoice: | $ 367.50 | ||
| Invoiced to Date ($): | $ 7,529.50 | ||
| Invoiced to Date (%): | 75% | ||
| Remaining Budget ($): | $ 2,470.50 | ||
| Remaining Budget (%): | 25% | ||
Budget by Phase:
| Phase No. | **** |
|---|---|
| Phase Name: | 2010 Annual Services |
| Phase Budget: | $ 10,000.00 |
| Previously Invoiced: | $ 7,162.00 |
| Current Invoice: | $ 367.50 |
| Invoiced to Date ($): | $ 7,529.50 |
| Invoiced to Date (%): | 75% |
| Remaining Budget ($): | $ 2,470.50 |
| Remaining Budget (%): | 25% |
Comments: Preparation and participation in monthly board meeting and consultation with Township.
[Handwritten: 10. GOALS 2 page]
2010
EAST GOSHEN MUNICIPAL AUTHORITY GOALS
MAY REPORT
ON-GOING
- Submit an article for each newsletter. Need by 2/10/10 Fran - Completed; Need by 5/12/10 Jack; Need by 8/11/10 Joe; Need by 11/10/10 Dana
- Attend West Goshen Meetings quarterly – more often if needed. 1 st Quarter (March) Fran - Completed; 2 nd Quarter (June) Dana; 3 rd Quarter (September) Joe; 4 th Quarter (December) Jack
- Respond to capacity requests in 45 days or less. Michael Mirarchi (143 Line Road) request of 1/21/10 granted on 4/12/10).
- Implement I & I Plan. - Ongoing – March Report filed
- Conduct a sewer facilities tour after RCSTP construction is complete
RIDLEY CREEK PROJECT
- Monitor construction.
- Invite Board of Supervisors and all other ABC members to tour the plant during the start up period when the SBR unit is running on treated effluent. SBR Tour conducted on 3/15/10
- Invite Board of Supervisors and all other ABC members to a primer educational session on SBR’s. SBR Class conducted on 3/15/10
- Have Siemens conduct a training session for Artesian and Township Employees on the new SBR unit. (This would be in lieu of us going to the Siemens’ facility in the mid-west.)
ACT 537 PLANNING
- Obtain Act 537 Plan approval for the Lockwood STP Abandonment Project.
- Obtain Act 537 Plan approval for the Greenhill PS Redirection and the Reserve PS Abandonment Project.
- Obtain Act 537 Plan approval for the Marydell PS Abandonment project.
F:\Data\Shared Data\ABC'S\Municipal Authority\Goals\2010\051010.doc
2 of 2
- Obtain construction permits, solicit bids and start construction of the Marydell PS Abandonment project.
- Obtain Act 537 Plan approval for the Reservoir Road PS Diversion Project.
FUNDING
- H20 Grant – Obtain funding and use monies ($464,195) to pay for construction at RCSTP. Transfer $464,195 from RCSTP construction account to the Authority’s general account.
F:\Data\Shared Data\ABC'S\Municipal Authority\Goals\2010\051010.doc
[Handwritten: 11. OLD BUSINESS a. 4 pgs]
Memo
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380
Voice (610) 692-7171
Fax (610) 425-8950
E-mail rsmith@eastgoshen.org
| Date: | May 3, 2010 |
|---|---|
| To: | Municipal Authority |
| From: | Rick Smith, Township Manager |
| Re: | 2010 Budget |
Attached is the 2010 Budget with the 2011 to 2014 projections broken down as requested.
The Operating Budget only covers the normal operating expense of the Authority, which is around $120,000 per year. As you know, the Board of Supervisors has agreed to transfer funding from Sewer Operating to cover these costs on a monthly basis.
The RCSTP Budget covers the costs associated with RCSTP Project. The Project was funded via a bond. We have been awarded a grant for $464,195 for this project. I intend to use the grant money for the project and take $464,195 of the bond money and apply it to the Capital Budget.
The Capital Budget covers the cost associated with the abandonment of Lockwood, the removal of the Reserve Pump Station, the redirection of Hershey Mill Pump Station and the construction of the Reservoir Road Pump Station. I am showing the $464,195 from the RCSTP Project as a receipt. We will need to borrow additional monies for fund all of these projects.
F:\Data\Shared Data\Finance Dept\Budget\2010\Memo to MA 050310.doc
2 of 4
EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
ACTUAL 2009 AND BUDGET 2010 to 2014
CAPITAL BUDGET
| Account | Description | ACTUAL 2009 | BUDGET 2010 | BUDGET 2011 | BUDGET 2012 | BUDGET 2013 | BUDGET 2014 | COMMENTS |
|---|---|---|---|---|---|---|---|---|
| BEGINNING FUND BALANCE | 0 | 134,195 | 1,987,500 | 1,765,000 | 1,090,000 | |||
| REVENUE | ||||||||
| 07341.1000 | INTEREST EARNINGS | |||||||
| 07341.1010 | CAPITAL RESERVE - INTEREST | |||||||
| 07341.1020 | INTEREST EARNINGS - RCSTP EXPANSION | |||||||
| 07364.1100 | TAPPING FEES-CHESTER CREEK | |||||||
| 07364.1110 | TAPPING FEES-RIDLEY CREEK | |||||||
| 07364.1130 | SEWER CONNECTIN FEES - PINE ROCK | |||||||
| 07380.1000 | MISCELLANEOUS REVENUE | |||||||
| 07392.0100 | TRANSFER FROM GENL ACCT | |||||||
| 07392.0804 | LOAN PROCEEDS-RCSTP PROJECT | 2,129,305 | Borrowing required to finish all projects | |||||
| 07392.0800 | GRANTS | |||||||
| 07392.0900 | TRANSFER FROM SEWER CAP RESERVE | |||||||
| TRANSFER FROM RCSTP BUDGET | 464,195 | Transfer from RCSTP Fund | ||||||
| TOTAL REVENUE | 0 | 464,195 | 2,129,305 | 0 | 0 | 0 | ||
| EXPENDITURES: | ||||||||
| 07424.1400 | ADMINISTRATIVE WAGES | |||||||
| 07471.1000 | M.C.-DVRFA-PRINCIPAL | |||||||
| 07472.1000 | M.C.-DVRFA-INTEREST | |||||||
| 07471.1010 | LOAN - PRINCIPAL | |||||||
| 07472.1010 | LOAN - INTEREST | |||||||
| 07424.3110 | AUDITING EXPENSE | |||||||
| 07424.3000 | MISCELLANEOUS EXPENSE | |||||||
| 07424.3130 | ENGINEERING SERVICES | |||||||
| 07424.3140 | LEGAL SERVICES | |||||||
| 07424.7400 | W.G. C.C.STP-UPGRADE | |||||||
| 07424.7410 | C.C. CAPITAL -METERS | |||||||
| 07424.7420 | C.C. CAPITAL-COLLECTION | |||||||
| 07424.7430 | C.C. CAPITAL-INTERCEPTOR | 92,881 | ||||||
| 07424.7431 | C.C. CAPITAL PROJ. ENGINEER. | |||||||
| 07424.7440 | R.C.-STP CAPITAL EXPANSN | 1,243 | ||||||
| 07424.7450 | R.C.-CAPITAL-COLLECTION | |||||||
| 07424.7451 | R.C.-CAPITAL PROJ. ENG. | |||||||
| 07424.7452 | R.C. CAPITAL EXPANSION - GENERAL CONTRACTOR | |||||||
| 07424.7453 | R.C. CAPITAL EXPANSION - ELECTRICAL CONTRACTOR | |||||||
| 07424.7454 | R.C. CAPITAL EXPANSION - CONTINGENCY CAPITAL | |||||||
| 07424.7455 | R.C. CAPITAL EXPANSION - CONTINGENCY ONGOING | |||||||
| 07424.7470 | LOCHWOOD-COLLECT.-CAP. | |||||||
| 07424.7475 | LOCKWOOD ABANDONMENT - PROJECT ENGINEER | 1,012 | 40,000 | 15,000 | Start in 2010 finish in 2011 | |||
| 07424.7476 | LOCKWOOD ABANDONMENT- CONSTRUCTION | 165,000 | 175,000 | |||||
| 07424.7490 | CAPITAL REPLACEMENT-RIDLEY CREEK STP | |||||||
| 07424.7491 | CAPITAL REPLACEMENT-ASHBRIDGE PUMP STATION | |||||||
| 07424.7495 | CAPITAL REPLACEMENT-LOCHWOOD CHASE | |||||||
| 07425.1000 | MARYDELL PUMP STATION - PROJECT ENGINEER | 45,000 | 11,000 | Start in 2010 finish in 2011 | ||||
| 07425.2000 | MARYDELL PUMP STATION - CONSTRUCTION | 80,000 | 75,000 | |||||
| 07426.1000 | HERSHEY MILL PUMP STATION - PROJECT ENGINEER | 15,500 | Start and finish in 2012 | |||||
| 07426.2000 | HERSHEY MILL PUMP STATION - CONSTRUCTION | 45,000 | ||||||
| 07427.1000 | RESERVE PUMP STATION - PROJECT ENGINEER | 32,000 | Start and finish in 2012 | |||||
| 07427.2000 | RESERVE PUMP STATION - CONSTRUCTION | 130,000 | ||||||
| 07428.1000 | RESERVOIR PUMP STATION - PROJECT ENGINEER | 175,000 | 90,000 | Start in 2013 finish in 2014 | ||||
| 07428.2000 | RESERVOIR ROAD PUMP STATION - CONSTRUCTION | 500,000 | 1,000,000 | |||||
| 07492.0100 | TRANSFER TO GENERAL FUND | |||||||
| 07492.0500 | TRANSFER TO SEWER OPERATING FUND | 45,000 | ||||||
| 07492.0550 | TRANSFER TO SEWER CAP RESERVE | |||||||
| TOTAL EXPENDITURES | 140,136 | 330,000 | 276,000 | 222,500 | 675,000 | 1,090,000 | ||
| NET SURPLUS/-DEFICIT | 134,195 | 1,853,305 | (222,500) | (675,000) | (1,090,000) | |||
| ENDING FUND BALANCE | 134,195 | 1,987,500 | 1,765,000 | 1,090,000 | 0 |
F:\Data\Shared Data\Finance Dept\Budget\2010\2010 MUNICIPAL AUTHORITY BUDGET 050310.xlsCAPITAL | 5/3/2010 | 11
3 of 4
EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
ACTUAL 2009 AND BUDGET 2010 to 2014
RCSTP BUDGET
| Account | Description | ACTUAL 2009 | BUDGET 2010 | BUDGET 2011 | BUDGET 2012 | BUDGET 2013 | BUDGET 2014 | COMMENTS |
|---|---|---|---|---|---|---|---|---|
| BEGINNING FUND BALANCE | 3,487,222 | - | - | - | - | |||
| REVENUE | ||||||||
| 07341.1000 | INTEREST EARNINGS | |||||||
| 07341.1010 | CAPITAL RESERVE - INTEREST | |||||||
| 07341.1020 | INTEREST EARNINGS_RCSTP EXPANSION | 86,511 | 15,000 | 0 | 0 | 0 | 0 | |
| 07364.1100 | TAPPING FEES-CHESTER CREEK | |||||||
| 07364.1110 | TAPPING FEES-RIDLEY CREEK | |||||||
| 07364.1130 | SEWER CONNECTIN FEES - PINE ROCK | |||||||
| 07380.1000 | MISCELLANEOUS REVENUE | |||||||
| 07392.0100 | TRANSFER FROM GENL ACCT | |||||||
| 07392.0804 | LOAN PROCEEDS-RCSTP PROJECT | 0 | 0 | 0 | 0 | 0 | ||
| 07392.0800 | GRANTS | 0 | 464,195 | 0 | 0 | 0 | 0 | |
| 07392.0900 | TRANSFER FROM SEWER CAP RESERVE | 0 | 0 | 0 | 0 | 0 | ||
| TOTAL REVENUE | 86,511 | 479,195 | 0 | 0 | 0 | 0 | ||
| EXPENDITURES: | ||||||||
| 07424.1400 | ADMINISTRATIVE WAGES | |||||||
| 07471.1000 | M.C.-DVRFA-PRINCIPAL | |||||||
| 07472.1000 | M.C.-DVRFA-INTEREST | |||||||
| 07471.1010 | LOAN - PRINCIPAL | |||||||
| 07472.1010 | LOAN - INTEREST | |||||||
| 07424.3110 | AUDITING EXPENSE | |||||||
| 07424.3000 | MISCELLANEOUS EXPENSE | |||||||
| 07424.3130 | ENGINEERING SERVICES | |||||||
| 07424.3140 | LEGAL SERVICES | |||||||
| 07424.7400 | W.G. C.C.STP-UPGRADE | |||||||
| 07424.7410 | C.C. CAPITAL -METERS | |||||||
| 07424.7420 | C.C. CAPITAL-COLLECTION | |||||||
| 07424.7430 | C.C. CAPITAL-INTERCEPTOR | |||||||
| 07424.7431 | C.C. CAPITAL PROJ. ENGINEER. | |||||||
| 07424.7440 | R.C.-STP. CAPITAL EXPANSN | 0 | 0 | |||||
| 07424.7450 | R.C.-CAPITAL-COLLECTION | 0 | 0 | |||||
| 07424.7451 | R.C.-CAPITAL PROJ. ENG. | 208,556 | 172,000 | Pennoni $100k Brickhouse $48k extra $25k | ||||
| 07424.7452 | R.C. CAPITAL EXPANSION - GENERAL CONTRACTOR | 5,338,597 | 2,526,803 | |||||
| 07424.7453 | R.C. CAPITAL EXPANSION - ELECTRICAL CONTRACTOR | 455,219 | 518,781 | |||||
| 07424.7454 | R.C. CAPITAL EXPANSION - CONTINGENCY CAPITAL | 11,696 | 274,638 | $80 in identified expenses +$100 k unknown | ||||
| 07424.7455 | R.C. CAPITAL EXPANSION - CONTINGENCY ONGOING | 9,426 | 10,000 | $1k per month | ||||
| 07424.7470 | LOCHWOOD-COLLECT.-CAP. | |||||||
| 07424.7475 | LOCKWOOD ABANDONMENT - PROJECT ENGINEER | |||||||
| 07424.7476 | LOCKWOOD ABANDONMENT - CONSTRUCTION | |||||||
| 07424.7490 | CAPITAL REPLACEMENT-RIDLEY CREEK STP | |||||||
| 07424.7491 | CAPITAL REPLACEMENT-ASHBRIDGE PUMP STATION | |||||||
| 07424.7495 | CAPITAL REPLACEMENT-LOCHWOOD CHASE | |||||||
| 07425.1000 | MARYDELL PUMP STATION - PROJECT ENGINEER | |||||||
| 07425.2000 | MARYDELL PUMP STATION - CONSTRUCTION | |||||||
| 07426.1000 | HERSHEY MILL PUMP STATION - PROJECT ENGINEER | |||||||
| 07426.2000 | HERSHEY MILL PUMP STATION - CONSTRUCTION | |||||||
| 07427.1000 | RESERVE PUMP STATION - PROJECT ENGINEER | |||||||
| 07427.2000 | RESERVE PUMP STATION - CONSTRUCTION | |||||||
| 07428.1000 | RESERVOIR PUMP STATION = PROJECT ENGINEER | |||||||
| 07428.2000 | RESERVOIR ROAD PUMP STATION - CONSTRUCTION | |||||||
| 07472.0100 | TRANSFER TO GENERAL FUND | |||||||
| 07492.0500 | TRANSFER TO SEWER OPERATING FUND | |||||||
| 07492.0550 | TRANSFER TO SEWER CAP RESERVE | |||||||
| TRANSFER TO AUTHORITY CAPITAL FUND | 464,195 | |||||||
| TOTAL EXPENDITURES | 6,023,494 | 3,966,417 | 0 | 0 | 0 | 0 | ||
| NET SURPLUS/-DEFICIT | (3,487,222) | 0 | 0 | 0 | 0 | |||
| ENDING FUND BALANCE | 3,487,222 | 0 | 0 | 0 | 0 | 0 |
5/3/2010
F:\Data\Shared Data\Finance Dept\Budget2010\2010 MUNICIPAL AUTHORITY BUDGET 050310.xlsRCSTP
1
4 of 4
EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
ACTUAL 2009 AND BUDGET 2010 to 2014
OPERATING BUDGET
| Account | Description | ACTUAL 2009 | BUDGET 2010 | BUDGET 2011 | BUDGET 2012 | BUDGET 2013 | BUDGET 2014 | COMMENTS |
|---|---|---|---|---|---|---|---|---|
| BEGINNING FUND BALANCE | 49,913 | 4,486 | (102,795) | (211,967) | (323,069) | |||
| REVENUE | ||||||||
| 07341.1000 | INTEREST EARNINGS | 1,479 | 0 | 0 | 0 | 0 | 0 | |
| 07341.1010 | CAPITAL RESERVE - INTEREST | 0 | 0 | 0 | 0 | 0 | 0 | |
| 07341.1020 | INTEREST EARNINGS_RCSTP EXPANSION | 0 | 0 | 0 | 0 | 0 | 0 | |
| 07364.1100 | TAPPING FEES-CHESTER CREEK | 0 | 6,000 | 6,000 | 6,000 | 6,000 | 6,000 | 3 houses per year |
| 07364.1110 | TAPPING FEES-RIDLEY CREEK | 2,715 | 6,000 | 6,000 | 6,000 | 6,000 | 6,000 | 3 houses per year |
| 07364.1130 | SEWER CONNECTIN FEES - PINE ROCK | 6,294 | ||||||
| 07380.1000 | MISCELLANEOUS REVENUE | 706 | 1,000 | 1,000 | 1,000 | 1,000 | 1,000 | |
| 07392.0100 | TRANSFER FROM GENL ACCT | 60,000 | Per BoS 4/6/10 | |||||
| 07392.0804 | LOAN PROCEEDS-RCSTP PROJECT | 0 | 0 | 0 | 0 | 0 | 0 | |
| 07392.0800 | GRANTS | 0 | 0 | 0 | 0 | 0 | 0 | |
| 07392.0900 | TRANSFER FROM SEWER CAP RESERVE | 50,416 | 0 | 0 | 0 | 0 | 0 | |
| TOTAL REVENUE | 61,610 | 73,000 | 13,000 | 13,000 | 13,000 | 13,000 | ||
| EXPENDITURES: | ||||||||
| 07424.1400 | ADMINISTRATIVE WAGES | 34,672 | 36,206 | 36,930 | 37,669 | 38,422 | 39,191 | |
| 07471.1000 | M.C.-DVRFA-PRINCIPAL | 16,520 | 16,520 | 16,520 | 16,520 | 16,520 | 16,520 | |
| 07472.1000 | M.C.-DVRFA-INTEREST | 9,201 | 9,201 | 9,201 | 9,201 | 9,201 | 9,201 | |
| 07471.1010 | LOAN - PRINCIPAL | 0 | 0 | 0 | 0 | 0 | 0 | |
| 07472.1010 | LOAN - INTEREST | 0 | 0 | 0 | 0 | 0 | ||
| 07424.3110 | AUDITING EXPENSE | 8,500 | 8,500 | 8,670 | 8,843 | 9,020 | 9,201 | |
| 07424.3000 | MISCELLANEOUS EXPENSE | 29,812 | 4,000 | 4,080 | 4,162 | 4,245 | 4,330 | |
| 07424.3130 | ENGINEERING SERVICES | 35,019 | 32,000 | 32,640 | 33,293 | 33,959 | 34,638 | |
| 07424.3140 | LEGAL SERVICES | 9,173 | 12,000 | 12,240 | 12,485 | 12,734 | 12,989 | |
| 07424.7400 | W.G. C.C.STP-UPGRADE | |||||||
| 07424.7410 | C.C. CAPITAL -METERS | |||||||
| 07424.7420 | C.C. CAPITAL-COLLECTION | |||||||
| 07424.7430 | C.C. CAPITAL-INTERCEPTOR | |||||||
| 07424.7431 | C.C. CAPITAL PROJ. ENGINEER. | |||||||
| 07424.7440 | R.C.-STP. CAPITAL EXPANSN | |||||||
| 07424.7450 | R.C.-CAPITAL-COLLECTION | |||||||
| 07424.7451 | R.C.-CAPITAL PROJ. ENG. | |||||||
| 07424.7452 | R.C. CAPITAL EXPANSION - GENERAL CONTRACTOR | |||||||
| 07424.7453 | R.C. CAPITAL EXPANSION - ELECTRICAL CONTRACTOR | |||||||
| 07424.7454 | R.C. CAPITAL EXPANSION - CONTINGENCY CAPITAL | |||||||
| 07424.7455 | R.C. CAPITAL EXPANSION - CONTINGENCY ONGOING | |||||||
| 07424.7470 | LOCHWOOD-COLLECT.-CAP. | |||||||
| 07424.7475 | LOCKWOOD ABANDONMENT - PROJECT ENGINEER | |||||||
| 07424.7476 | LOCKWOOD ABANDONMENT - CONSTRUCTION | |||||||
| 07424.7490 | CAPITAL REPLACEMENT-RIDLEY CREEK STP | |||||||
| 07424.7491 | CAPITAL REPLACEMENT-ASHBRIDGE PUMP STATION | |||||||
| 07424.7495 | CAPITAL REPLACEMENT-LOCHWOOD CHASE | |||||||
| 07425.1000 | MARYDELL PUMP STATION - PROJECT ENGINEER | |||||||
| 07425.2000 | MARYDELL PUMP STATION - CONSTRUCTION | |||||||
| 07426.1000 | HERSHEY MILL PUMP STATION - PROJECT ENGINEER | |||||||
| 07426.2000 | HERSHEY MILL PUMP STATION - CONSTRUCTION | |||||||
| 07427.1000 | RESERVE PUMP STATION - PROJECT ENGINEER | |||||||
| 07427.2000 | RESERVE PUMP STATION - CONSTRUCTION | |||||||
| 07428.1000 | RESERVOIR PUMP STATION = PROJECT ENGINEER | |||||||
| 07428.2000 | RESERVOIR ROAD PUMP STATION - CONSTRUCTION | |||||||
| 07472.0100 | TRANSFER TO GENERAL FUND | |||||||
| 07492.0500 | TRANSFER TO SEWER OPERATING FUND | |||||||
| 07492.0550 | TRANSFER TO SEWER CAP RESERVE | |||||||
| TOTAL EXPENDITURES | 142,897 | 118,427 | 120,281 | 122,172 | 124,101 | 126,069 | ||
| NET SURPLUS/-DEFICIT | (45,427) | (107,281) | (109,172) | (111,101) | (113,069) | |||
| ENDING FUND BALANCE | 4,486 | (102,795) | (211,967) | (323,069) | (436,138) |
5/3/2010
F:\Data\Shared Data\Finance Dept\Budget2010\2010 MUNICIPAL AUTHORITY BUDGET 050310.xlsOPERATING
1
[Handwritten: 11. OLD BUSINESS b. 2 pgs]
AREA CODE 610
692-7171
EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199
April 20, 2010
Mr. Steve MarchakAqua Wastewater Management, Inc.
762 West Lancaster Avenue
Bryn Mawr PA 19010
Re: Tank Cleaning Bid
April 19, 2010
Dear Mr. Marchak:
At their meeting on Monday April 12, 2010, the Municipal Authority authorized Mark Miller, the Township Director of Public Works to open bids for the tank cleaning and to award the bid to the lowest responsible bidder who met the specifications.
Mark has reviewed the bids and determined that the Aqua Wastewater Management bid for $24,234.00 is the lowest responsible bid and based on the Authority’s action on April 12, 2010, Mark has awarded Aqua the contract for tank cleaning.
Please provide me with the performance bond, payment bond and certificate of insurance within five (5) days of the date this letter. I have also enclosed a copy of the agreement. Please execute two copies and return them to me.
As we discussed I expect that the tank cleaning can commence the week of May 3, 2010. We should have a better handle on the start date this Friday. It may also be beneficial for us to meet at the Ridley Creek Sewer Plant the end of this week or the beginning of next week. This would allow you to coordinate the vacuum truck part of the cleaning project with our general contractor.
Please give me a call at 610-692-7171 or e-mail me at rsmith@eastgoshen.org if you have any questions or need additional information.
Sincerely,
[Signature: Rick Smith]
Louis F. Smith, Jr.
Township Manager
Enclosure
Cc: All Bidders.
F:\Data\Shared Data\Public Works Dept\Bids\Tank Cleaning 2010\Award Letter 042010.doc
2 of 2
East Goshen Township
Bid opening for Tank Cleaning
Opened April 19th at 10:00 am.
| Aqua: | $24,234.00 |
|---|---|
| US Environmental | $25,014.00 |
| Franc Environmental | $34,016.00 |
| Russell Reed Co. | $34,586.00 |
| McGovern Environmental | $46,534.00 |
[Handwritten: 12. NEW BUSINESS a. 1pg]
610-692-7171
www.eastgoshen.org
BOARD OF SUPERVISORS
EAST GOSHEN TOWNSHIP
CHESTER COUNTY
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199
May 3, 2010
Mr. Jack Yahraes, ChairmanEast Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380
Re: Budget
Dear Jack:
At the annual Financial Planning Session on April 19, the Board of Supervisors requested that I write to the Municipal Authority asking that you adopt your 2010 budget soon and that you provide the Board with a copy of it and your five-year budget at your earliest convenience.
Please give me a call at 610-692-7171 or e-mail me at rsmith@eastgoshen.org if you have any questions or need additional information.
Sincerely,
[Signature: Rick]
Louis F. Smith, Jr.
Township Manager
Cc: Board of Supervisors
F:\Data\Shared Data\Finance Dept\Budget\2010\Letter to Ma 050310.doc
12. NEW BUSINESS
6.
4 pgs
Memo
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380
Date: May 4, 2010
To: Municipal Authority
From: Rick Smith, Township Manager
Re: Applebrook Spray Permit
When Applebrook Golf Course was approved, we amended our permit for Ridley Creek Sewer Plant (RCSTP) to provide for a secondary discharge into a storage pond on the Golf Course Property. This pond is considered “Waters of the Commonwealth”. We also entered into an agreement with Applebrook to fund the installation of a pump and force main to convey treated effluent from RCSTP to the pond. When Applebrook needs water for irrigation, the pump is turned on, the water is pumped to the pond, and Applebrook draws out the water for irrigation.
If you recall during 2001 we were in a drought condition. As such “non-essential” uses of water was prohibited by PA DEP. You had to ask for water in restaurants, you could not irrigate your lawn, etc. A golf course was not considered an “essential” business and the irrigation of them was prohibited. While there was an exception for watering newly seeded areas, which applied to Applebrook at that time, they were concerned that they would not be able to irrigate during a future drought.
The solution was to obtain a spray irrigation permit for the Golf Course, which was issued in 2002. They would then be able to spray/irrigate the Golf Course during a drought. Since the irrigation system was not initially set up as a “spray irrigation” system there was no direct connection between the force main and the irrigation system. In order to “spray” under the new permit Applebrook would have to physically connect the force main to their irrigation system.
A few years later, the powers to be at DEP concluded that golf courses were an “essential business” and therefore able to irrigate during a drought. Accordingly, the need for the permit became moot and it expired in 2005.
In 2008, we received a letter from DEP about the need to prepare a Comprehensive Groundwater Evaluation. I advised DEP that the spray irrigation permit had expired. I spoke to Mike Gogg at DEP in late April and he advised that they still considered the spray permit active. He noted that we could “renew” it if we wanted to or he requested a letter canceling the permit.
I do not believe that there is no longer any need for the spray permit, and Evan estimates that it would cost $5,500 to prepare the Comprehensive Groundwater Evaluation.
I told Mike Gogg I would run this by the Authority and get back to him.
F:\Data\Shared Data\Public Works Dept\Sewer\Ridley Creek\Applebrook Irrigation\Ground Water Monitoring\Memo to MA 050410.doc
2 of 4
FILE COPY
610-692-7171
www.eastgoshen.org
BOARD OF SUPERVISORS
EAST GOSHEN TOWNSHIP
CHESTER COUNTY
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199
April 12, 2010
Michael L. Grogg
Department of Environmental Protection
2 East Main Street
Norristown, PA 19401
Re: Applebrook Golf Course
East Goshen Township
Chester County
Dear Mr. Grogg:
I was reviewing our file on Applebrook and I came across your letter of November 20, 2008 (enclosed).
It is my understanding that the “Spray Irrigation Permit” for the Applebrook Golf Course expired in 2005 (enclosed). I am not sure if this information was ever conveyed to you.
Please give me a call at 610-692-7171 or e-mail me at rsmith@eastgoshen.org if you have any questions or need additional information.
Sincerely,
Rick Smith
Louis F. Smith, Jr.
Township Manager
Enclosures
F:\Data\Shared Data\Public Works Dept\Sewer\Ridley Creek\Applebrook Irrigation\Ground Water Monitoring\Letter to PADEP 041210.doc
3 of 4
Pennsylvania Department of Environmental Protection
2 East Main Street
Norristown, PA 19401
November 20, 2008
Southeast Regional Office
Phone: 484-250-5970
Fax: 484-250-5971
COPY
RECEIVED
BY:
DEC - 8 2008
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380
Re: Applebrook Golf Course
East Goshen Township
Chester County
Dear Permittee:
This letter is to notify you of changes to how groundwater monitoring data will be reported to the Department of Environmental Protection (Department). Enclosed, you will find a copy of the new permit language for reporting groundwater data and an example report. The Department is implementing this change in an effort to streamline the reporting requirements for each permittee. This revised language will be included in your next permit renewal. However, we request that you comply with this revised reporting format at this time. The enclosed example report represents the minimum information needed by the Department; additional information can be included in your actual report if you determine it is necessary to accurately reflect the conditions at your site.
The major changes are that groundwater data will now be submitted to the Department once per year in the form of an annual groundwater report, instead of quarterly submissions on the Background Monitoring Form. Your groundwater sampling frequency and parameters will remain as prescribed in your current permit. Each successive annual report builds upon the prior reports, and all pertinent information contained in the prior reports must also appear in the most recent report. For this reason, it is highly recommended that reports be developed in a format which allows easy update.
Please also note that a Comprehensive Groundwater Evaluation (CGE) will need to be completed once every five years as part of the permit renewal application. The CGE’s purpose is to identify any trends in groundwater data which suggest that corrective measures need to be taken to prevent a threat to public health or the environment. Please note that, while the yearly reports can be completed by a nonlicensed representative of the permittee, a professional geologist must complete the CGE.
Your first annual groundwater report is to be submitted within 28 days of the end of your annual permit cycle. For example, if your permit was issued on March 4, 2008, then your first annual groundwater report is due by April 28, 2009. Your first CGE is to be submitted along with your next permit renewal application. Please do not submit your quarterly data to the Department from this point on. All data must be submitted in your annual report. Please note, you may submit your annual reports on a CD-ROM if you choose. The CD-ROM must include a signed transmittal letter from the permittee.
An Equal Opportunity Employer
www.dep.state.pa.us
Printed on Recycled Paper
4 of 4
East Goshen Municipal Authority - 2 - November 20, 2008
If you have any questions regarding these changes, please call the above phone number and ask to speak to a hydrogeologist in the Planning Section.
Sincerely,
Michael L. Grogg
Michael L. Grogg
Geologic Specialist
Water Management
Enclosures
cc: Mr. Evans
Mr. Dudley
Ms. Fields
East Goshen Township
(joh08)325-5
15. SEWER RPT
a.
8 pgs
AREA CODE 610
692-7171
EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199
May 5, 2010
To: Municipal Authority
From: Mark Miller
Re: April 2010 Monthly Report
Meter: Meters were read on a daily basis. The portable meters are being read on a weekly basis.
C.C. Collection: We have been busy making repairs to the system. To date, we have repaired 8 major breaks. We have several more to replace.
R.C. Collection: We have made several repairs to the system. We will be replacing manhole covers in the Bowtree Development due to large pick holes.
Plants: The plants are running well, no problems to report.
Ridley Creek Plant: As I reported earlier, the plant went live on May 4, 2010.
PA One Calls: 112 PA One Call’s for the month of April.
Alarms: 14 alarms for the month of April.
f:\data\shared data\public works dept\monthly reports\2010 municipal\2010 municipal authority april report doc..doc
2 of 8
2008 FLOWMETERS
2010 APRIL 2ND QUARTER
| Precip Inches | DATE | WESTTOWN WAY READING | WESTTOWN WAY GPD | ELLIS LANE READING | ELLIS LANE GPD | PAOLI PIKE READING | PAOLI PIKE GPD | WILSON DRIVE READING | WILSON DRIVE GPD | SUMMIT GPD | NET FLOWS |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 0.00 | 04/01/10 | 1,589,042 | 1,976,000 | 13,102,438 | 238,080 | 7,316,522 | 94,610 | 8,627,391 | 75,360 | 20,400 | 1,567,950 |
| 0.00 | 04/02/10 | 0 | 0 | 0 | 0 | 20,400 | 0 | ||||
| 0.00 | 04/03/10 | 0 | 0 | 0 | 0 | 20,400 | 0 | ||||
| 0.00 | 04/04/10 | 0 | 0 | 0 | 0 | 20,400 | 0 | ||||
| 0.00 | 04/05/10 | 1,596,027 | 1,746,250 | 13,180,453 | 195,038 | 7,353,606 | 92,710 | 8,651,895 | 61,260 | 20,400 | 1,397,243 |
| 0.30 | 04/06/10 | 1,597,745 | 1,718,000 | 13,198,921 | 184,680 | 7,363,537 | 99,310 | 8,659,649 | 77,540 | 20,400 | 1,356,470 |
| 0.00 | 04/07/10 | 1,599,489 | 1,744,000 | 13,216,846 | 179,250 | 7,373,438 | 99,010 | 8,668,373 | 87,240 | 20,400 | 1,378,500 |
| 0.70 | 04/08/10 | 1,601,045 | 1,556,000 | 13,234,488 | 176,420 | 7,383,187 | 97,490 | 8,678,452 | 100,790 | 20,400 | 1,181,300 |
| 0.00 | 04/09/10 | 0 | 0 | 0 | 0 | 20,400 | 0 | ||||
| 0.00 | 04/10/10 | 0 | 0 | 0 | 0 | 20,400 | 0 | ||||
| 0.20 | 04/11/10 | 0 | 0 | 0 | 0 | 20,400 | 0 | ||||
| 0.00 | 04/12/10 | 1,607,431 | 1,596,500 | 13,307,509 | 182,553 | 7,422,304 | 97,793 | 8,704,968 | 66,290 | 20,400 | 1,249,865 |
| 0.15 | 04/13/10 | 1,608,999 | 1,568,000 | 13,324,284 | 167,750 | 7,431,795 | 94,910 | 8,713,303 | 83,350 | 20,400 | 1,221,990 |
| 0.00 | 04/14/10 | 1,610,496 | 1,497,000 | 13,341,129 | 168,450 | 7,439,582 | 77,870 | 8,720,726 | 74,230 | 20,400 | 1,176,450 |
| 0.50 | 04/15/10 | 1,611,972 | 1,476,000 | 13,357,459 | 163,300 | 7,448,648 | 90,660 | 8,728,597 | 78,710 | 20,400 | 1,143,330 |
| 0.28 | 04/16/10 | 1,613,490 | 1,518,000 | 13,374,196 | 167,370 | 7,457,903 | 92,550 | 8,736,085 | 74,880 | 20,400 | 1,183,200 |
| 0.00 | 04/17/10 | 0 | 0 | 0 | 0 | 20,400 | 0 | ||||
| 0.00 | 04/18/10 | 0 | 0 | 0 | 0 | 20,400 | 0 | ||||
| 0.00 | 04/19/10 | 1,617,821 | 1,443,667 | 13,423,608 | 164,707 | 7,485,459 | 91,853 | 8,749,399 | 44,380 | 20,400 | 1,142,727 |
| 0.00 | 04/20/10 | 1,619,262 | 1,441,000 | 13,439,660 | 160,520 | 7,494,538 | 90,790 | 8,754,851 | 54,520 | 20,400 | 1,135,170 |
| 0.15 | 04/21/10 | 1,620,656 | 1,394,000 | 13,454,689 | 150,290 | 7,503,522 | 89,840 | 8,760,395 | 55,440 | 20,400 | 1,098,430 |
| 0.20 | 04/22/10 | 1,622,047 | 1,391,000 | 13,469,971 | 152,820 | 7,512,624 | 91,020 | 8,766,692 | 62,970 | 20,400 | 1,084,190 |
| 0.00 | 04/23/10 | 1,623,426 | 1,379,000 | 13,485,207 | 152,360 | 7,521,222 | 85,980 | 8,772,499 | 58,070 | 20,400 | 1,082,590 |
| 0.25 | 04/24/10 | 20,400 | 0 | ||||||||
| 0.60 | 04/25/10 | 20,400 | 0 | ||||||||
| 0.55 | 04/26/10 | 1,627,571 | 1,381,667 | 13,533,406 | 160,663 | 7,547,858 | 88,787 | 8,784,360 | 39,537 | 20,400 | 1,092,680 |
| 0.50 | 04/27/10 | 1,629,228 | 1,657,000 | 13,554,459 | 210,530 | 7,555,688 | 78,300 | 8,790,172 | 58,120 | 20,400 | 1,310,050 |
| 0.00 | 04/28/10 | 1,630,705 | 1,477,000 | 13,571,858 | 173,990 | 7,562,767 | 70,790 | 8,796,249 | 60,770 | 20,400 | 1,171,450 |
| 0.00 | 04/29/10 | 1,632,116 | 1,411,000 | 13,588,111 | 162,530 | 7,569,521 | 67,540 | 8,802,485 | 62,360 | 20,400 | 1,118,570 |
| 0.00 | 04/30/10 | 20,400 | 0 | ||||||||
| 4.38 | 1,545,846 | 174,279 | 89,043 | 67,148 | 1,278,991 |
| Metric | E.GOSHEN |
|---|---|
| MONTH TO DATE | 4.38 |
| NORMAL MONTH TO DATE | |
| YEAR TO DATE | 22.91 |
| NORMAL YEAR TO DATE |
2010 flowmeters -all-stations separate month worksheets.xlsAPR
5/5/20109:58 AM
3 of 8
2008 FLOWMETERS
2010 APRIL 2ND QUARTER
| DATE | HERSHEY'S MILL READING | HERSHEY'S MILL GPD | ASHBRIDGE READING | ASHBRIDGE GPD | HICKS METER READING | HICKS METER GPD | RESERVOIR READING | RESERVOIR GPD | SHERMAN READING | SHERMAN GPD | BARKWAY READING | BARKWAY GPD |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 04/01/10 | 18,559,372 | 119,630 | 785,291 | 195,300 | 7,481,030 | 474,190 | 91,585,710 | 1,256,060 | 329,299 | 4,550 | 1,468,886 | 24,060 |
| 04/02/10 | 0 | 0 | 0 | 0 | 0 | 0 | ||||||
| 04/03/10 | 0 | 0 | 0 | 0 | 0 | 0 | ||||||
| 04/04/10 | 0 | 0 | 0 | 0 | 0 | 0 | ||||||
| 04/05/10 | 18,606,240 | 117,170 | 792,096 | 170,125 | 7,638,404 | 393,435 | 92,020,367 | 1,086,643 | 331,021 | 4,305 | 1,477,664 | 21,945 |
| 04/06/10 | 18,616,986 | 107,460 | 793,603 | 150,700 | 7,682,189 | 437,850 | 92,136,707 | 1,163,400 | 331,478 | 4,570 | 1,479,505 | 18,410 |
| 04/07/10 | 18,627,194 | 102,080 | 795,054 | 145,100 | 7,724,744 | 425,550 | 92,244,550 | 1,078,430 | 331,961 | 4,830 | 1,481,144 | 16,390 |
| 04/08/10 | 18,636,766 | 95,720 | 796,421 | 136,700 | 7,769,126 | 443,820 | 92,351,415 | 1,068,650 | 332,390 | 4,290 | 1,482,784 | 16,400 |
| 04/09/10 | ||||||||||||
| 04/10/10 | 0 | 0 | 0 | 0 | 0 | 0 | ||||||
| 04/11/10 | 0 | 0 | 0 | 0 | 0 | 0 | ||||||
| 04/12/10 | 18,674,867 | 95,253 | 801,850 | 135,725 | 7,918,392 | 373,165 | 92,753,761 | 1,005,865 | 334,595 | 5,513 | 1,488,383 | 13,998 |
| 04/13/10 | 18,683,521 | 86,540 | 803,108 | 125,800 | 7,959,406 | 410,140 | 92,854,578 | 1,008,170 | 335,149 | 5,540 | 1,489,613 | 12,300 |
| 04/14/10 | 18,691,990 | 84,690 | 804,309 | 120,100 | 7,997,903 | 384,970 | 92,952,032 | 974,540 | 335,741 | 5,920 | 1,490,845 | 12,320 |
| 04/15/10 | 18,700,109 | 81,190 | 805,511 | 120,200 | 8,036,345 | 384,420 | 93,047,281 | 952,490 | 336,223 | 4,820 | 1,491,986 | 11,410 |
| 04/16/10 | 18,708,324 | 82,150 | 806,697 | 118,600 | 8,076,281 | 399,360 | 93,145,550 | 982,690 | 336,767 | 5,440 | 1,493,187 | 12,010 |
| 04/17/10 | ||||||||||||
| 04/18/10 | 0 | 0 | 0 | 0 | 0 | 0 | ||||||
| 04/19/10 | 18,732,568 | 80,813 | 810,173 | 115,867 | 8,171,196 | 316,383 | 93,413,881 | 894,437 | 338,383 | 5,387 | 1,497,136 | 13,163 |
| 04/20/10 | 18,740,195 | 76,270 | 811,272 | 109,900 | 8,207,970 | 367,740 | 93,506,850 | 929,690 | 339,043 | 6,600 | 1,498,362 | 12,260 |
| 04/21/10 | 18,747,512 | 73,170 | 812,331 | 105,900 | 8,243,362 | 353,920 | 93,596,879 | 900,290 | 339,599 | 5,560 | 1,499,462 | 11,000 |
| 04/22/10 | 18,754,736 | 72,240 | 813,372 | 104,100 | 8,279,393 | 360,310 | 93,686,531 | 896,520 | 340,179 | 5,800 | 1,500,526 | 10,640 |
| 04/23/10 | 18,761,775 | 70,390 | 814,370 | 99,800 | 8,315,190 | 357,970 | 93,775,823 | 892,920 | 340,769 | 5,900 | 1,501,715 | 11,890 |
| 04/24/10 | ||||||||||||
| 04/25/10 | ||||||||||||
| 04/26/10 | 18,783,319 | 71,813 | 817,596 | 107,533 | 8,408,356 | 310,553 | 94,034,187 | 861,213 | 342,455 | 5,620 | 1,505,478 | 12,543 |
| 04/27/10 | 18,790,468 | 71,490 | 818,887 | 129,100 | 8,447,592 | 392,360 | 94,137,299 | 1,031,120 | 343,012 | 5,570 | 1,506,651 | 11,730 |
| 04/28/10 | 18,797,298 | 68,300 | 820,026 | 113,900 | 8,485,106 | 375,140 | 94,230,600 | 933,010 | 343,555 | 5,430 | 1,507,747 | 10,960 |
| 04/29/10 | 18,804,025 | 67,270 | 821,055 | 102,900 | 8,523,641 | 385,350 | 94,322,384 | 917,840 | 344,067 | 5,120 | 1,508,921 | 11,740 |
| 04/30/10 | ||||||||||||
| 85,455 | 126,703 | 386,665 | 991,262 | 5,303 | 13,956 |
2010 flowmeters -all-stations separate month worksheets.xlsAPR
5/5/20109:58 AM
4 of 8
2010 SUMMARY OF METER READINGS
| WESTTOWN WAY |
ELLIS LANE |
PAOLI PIKE |
WILSON DRIVE |
SUMMIT | HERSHEY MILL |
ASHBRIDGE | HICKS | RESERVOIR | SHERMAN | BARKWAY | |
|---|---|---|---|---|---|---|---|---|---|---|---|
| JANUARY | 1,425,517 | 123,265 | 81,325 | 63,991 | 20,400 | 83,711 | 103,900 | 363,921 | 882,367 | 5,627 | 13,543 |
| FEBRUARY | 1,462,759 | 132,866 | 74,793 | 70,879 | 20,400 | 77,500 | 103,327 | 332,371 | 906,362 | 5,456 | 13,156 |
| MARCH | 1,603,009 | 170,328 | 75,607 | 63,240 | 20,400 | 102,840 | 146,865 | 404,526 | 1,071,132 | 5,071 | 19,213 |
| APRIL | 1,545,846 | 174,279 | 89,043 | 67,148 | 20,400 | 85,455 | 126,703 | 386,665 | 991,262 | 5,303 | 13,956 |
| MAY | |||||||||||
| JUNE | |||||||||||
| JULY | |||||||||||
| AUGUST | |||||||||||
| SEPTEMBER | |||||||||||
| OCTOBER | |||||||||||
| NOVEMBER | |||||||||||
| DECEMBER | |||||||||||
| Total Flows | |||||||||||
| Monthly Ave | 1,509,283 | 150,185 | 80,192 | 66,315 | 20,400 | 87,377 | 120,199 | 371,871 | 962,781 | 5,364 | 14,967 |
To West Goshen: 1,212,592
2010 flowmeters -all-stations separate month worksheets.xlsSUMMARY
April Precip. 4.38 - 2010
April
Precip.
4.5 4 3.5 3 2.5 2 1.5 1 0.5 0
Snow/rain
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Monthly Totals 2010 (Jan-Dec)
Monthly Totals
Precip.
9 8 7 6 5 4 3 2 1 0
1 2 3 4 5 6 7 8 9 10 11 12
Month
Flowmeters April 2010
April
Flow#s
1800000 1600000 1400000 1200000 1000000 800000 600000 400000 200000 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Day of the Month
Monthly Totals 2010 Jan-Dec
Flowmeters
2500000 2000000 1500000 1000000 500000 0
January February March April May June July August September October November December
Month
17. CORRESPONDENCE
a.
1 pg
MA
Tarsi, Joyce
From: Mark Miller [mmiller@eastgoshen.org]
Sent: Wednesday, May 05, 2010 3:50 AM
To: 'Joyce Tarsi'
Subject: FW: Ridely Creek Treatment Plant
Joyce
Can you send this out with MA and BOS.
Thanks
Mark
-----Original Message-----
From: Kelley Fish [mailto:pafishfam@verizon.net]
Sent: Tuesday, May 04, 2010 1:59 PM
To: mmiller@eastgoshen.org
Cc: dmconathy@eastgoshen.org
Subject: Ridely Creek Treatment Plant
Mark,
We would like to thank you for an outstanding job regarding the expansion of the Ridley Creek Treatment Plant. We live right across the street from the driveway to the plant so we were exposed to much of the traffic. We expected it to be a long 18 months. Not so, the expansion from our perspective was very well organized. You provided us with timely, accurate notifications of happenings that would affect us. The trucks were not intrusive and the drivers were very courteous. Thank you for being so "on top" of everything and letting us know you were available if we had any questions/concerns.
Thanks once again!
Bob & Kelley Fish
1
FYI
AREA CODE 610
692-7171
EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199
May 3, 2010
Michael Mirarchi, President
M.J. Mirarchi, Inc.
250 West Lancaster Avenue, Suite 108
Wayne, PA 19087
Re: 143 Line Road
Dear Mike:
At their meeting on April 12, the Municipal Authority approved your request to connect your five lot subdivision at 143 Line Road in Willistown Township to the East Goshen Township public sewer system subject to the following conditions.
- The Authority will require conformation from Willistown Township that they are in agreement with your request.
- The method of connection needs to be approved by the Authority Engineer.
- You would be responsible for obtaining all permits required to connect to the public sewer.
- You would be responsible for all construction, and inspection costs associated with connecting to the public sewer.
- Payment of the tapping fee of $2,000 per lot to East Goshen Municipal Authority.
- Payment of the previously agreed upon contribution of $20,000 to the East Goshen Municipal Authority.
By way of this letter, I am advising Hugh Murray, Willistown Township Manager, of your request and the Authority’s decision. With respect to condition #1 I would encourage you to contact him directly to see what would be required from his end.
Please give me a call at 610-692-7171 if you have any questions or need additional information.
Sincerely,
Rick Smith
Louis F. Smith, Jr.
Township Manager
cc: Hugh Murray, Township Manager
F:\Data\Shared Data\Willistown\Sewer\143 Line Road\Letter re capacity 143 Line Road.doc
FYI
610-692-7171
www.eastgoshen.org
BOARD OF SUPERVISORS
EAST GOSHEN TOWNSHIP
CHESTER COUNTY
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199
April 21, 2010
Mr. John Thaeder, Vice President
Artesian Resources Corporation
P.O. Box 15004
Wilmington DE 19850
Re: Lochwood Chase Sewer Treatment Plant
Dear John:
Following up on our meeting on April 21st the Township will only impose liquidated damages in the amount of $200 since only two test where missed.
We will deduct this from your next invoice.
Please give me a call at 610-692-7171 or e-mail me at rsmith@eastgoshen.org if you have any questions or need additional information.
Sincerely,
Rick
Louis F. Smith, Jr.
Township Manager