Municipal Authority

The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.

 

The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.

  • Five members, serving five-year terms
  • Meetings are on the 2nd Monday of the month at 7:00 P.M.
  • All township meetings are held at the Township Building and open to the public
Authority Members Term Expiration Date
Kevin Cummings, Chairman 2026
John Stipe, Vice Chairman
2029
Dana Pizzarro, Secretary 2026
Sean Ellsworth, Assistant Secretary/Treasurer 2028
Walter Wujcik, Treasurer 2028
Pennoni Associates, Engineer
Patrick M. McKenna, Esq.
Peter Hicks, BoS Liaison
Kevin Miller, Staff Liaison

 

Municipal Authority Genealogy

Audits

Documents

Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.

EAST GOSHEN MUNICIPAL AUTHORITY

November 9, 2009
Monday, 7:00 PM

  1. CALL TO ORDER/PLEDGE OF ALLEGIANCE Announce that the Recording Secretary will be taping the meeting for her use and that the tape will be erased when the minutes for that meeting have been approved.; Ask if anyone will be taping the meeting?
  2. RIDLEY CREEK REPORTS Brickhouse Environmental -; Pennoni -; Artesian-; Worth & Company Change Orders -; Recommendation concerning SPR tank and contract time; Paving at Ridley Creek; Summary; DEP - review
  3. RIDLEY CREEK INVOICES Pennoni, #422066, 10/30/09      $ 6,577.00;
  4. CHAIRMAN’S REPORT/OTHER MEMBERS REPORTS
  5. APPROVAL OF MINUTES October 12, 2009
  6. ENGINEER’S REPORT Pennoni report
  7. APPROVAL OF INVOICES Pennoni, #422065, 10/30/09      $ 1,384.00; Pennoni, #422064, 10/30/09      $ 303.75; Pennoni, #422063, 10/30/09      $ 1,860.00; Pennoni, #422062, 10/30/09      $ 956.50; Pennoni, #422061, 10/30/09      $ 767.75; Gawthrop Greenwood, #73972, 9/30/09      $ 643.02;
  8. LIAISON REPORTS
  9. FINANCIAL REPORTS
  10. GOALS
  11. OLD BUSINESS
  12. NEW BUSINESS Carry Over at the Ridley Creek Plant and Hershey Mill Pump Station; Maillie, Falconiero & Co – Audit; Projected 2009 and Budget 2010 to 2012
  13. CAPACITY REQUESTS
  14. SEWER REPORTS Lochwood Chase Operations Report – August 2009

Monday, November 9, 2009

- 1 -

  1. Director of Public Works Report – October 2009;
  2. ANY OTHER MATTER
  3. CORRESPONDENCE AND REPORTS OF INTEREST
  4. PUBLIC COMMENT
  5. ADJOURNMENT

Reminder – NEWSLETTER ARTICLE SUBMISSION DUE DATES:

Article Due Date Delivery date
11/10/09 1/1/10

Monday, November 9, 2009

- 2 -

2 RIDLEY CREEK REPORTS
b.
2 pgs

Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

November 4, 2009

EGMA0707/05

Rick Smith, Township Manager
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380

Re: RCSTP Upgrade and Expansion
Continued Construction Services

Dear Mr. Smith:

As discussed, Pennoni “capped” our billings for the construction phase of this project as agreed with the Authority on May 11, 2009 until the original contracted completion date of November 13, 2009. In the event that the construction continued past November 13, 2009, Pennoni was permitted to resume invoicing effort incurred after November 13 until the project is completed (substantial completion currently scheduled for June 30, 2010). It is assumed that final completion will be reached approximately 30 days later.

SCOPE OF WORK

Construction Observation: We will continue to provide Matt McAloon for construction observation during active construction to confirm that the Contractors’ work conforms to the plans and specifications. We anticipate that the average weekly inspection time will be approximately 20 hours per week (down from 25 during the previous year) and continue for approximately 32 weeks (to June 30, 2010). During the period between substantial completion to final completion, we anticipate an additional 60 hours of construction observation effort. The total estimated construction observation effort is therefore 700 hours.

Project Administration: We will continue to respond to contractor requests for information, review submittals and pay requests, and conduct bi-weekly progress meetings. We anticipate that the average monthly effort for project administration will be approximately 40 hours per month for approximately 9 months (to July 30, 2010 – final completion).

System Start-Up: Witness the start-up and testing of installed equipment (wastewater screen, influent pump station, SBRs (at intermediate phase and final completion), cloth filters, and centrifuge. Start-up and testing will be performed by the Contractors and equipment suppliers (96 hours).

Contractor Changes: We will respond to contract changes (either as a result of conditions uncovered in the field or proposed improvement to the project or schedule) as authorized by the Authority. We propose an allowance of $7,500.00 to cover this effort if so authorized.

One Drexel Plaza • 3001 Market Street • Philadelphia, PA 19104-2897 • Tel: 215-222-3000 • Fax: 215-222-3588
www.pennoni.com

2 of 2

EGMA0707/05      November 4, 2009      Page 2
Rick Smith      Continued Construction Services

ESTIMATED FEE

Our estimated fee for the above scope of work and project duration, to be billed on a time and material basis, is $99,700.00. The work will be done on an hourly basis at our standard rates established in our Engineering Services Agreement.

Should you have any questions or need additional information, please do not hesitate to call.

Very truly yours,

PENNONI ASSOCIATES INC.

Evan R. Andrews
Evan R. Andrews, P.E.
Authority Engineer

RCSTP Continued Construction Services (11-04-2009)

2. RIDLEY CREEK
c.
2 pgs

ARTESIAN RESOURCES
100 YEARS OF SUPERIOR SERVICE
Artesian Water Company ▲ Artesian Wastewater Management ▲ Artesian Utility Development ▲ Artesian Water Maryland

October 27, 2009

Mr. Mark Miller, Director of Public Works
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380

RE: Ridley Creek Wastewater Treatment Facility
August 2009 Operations Report

Dear Mr. Miller:

The following is the August 2009 monthly operations report for East Goshen Township’s Ridley Creek Wastewater Treatment Facility.

Treatment plant operations were normal during the month of August 2009. Routine inspections and equipment preventative maintenance were completed as required. The total amount of wastewater treated and discharged during the month was 8,239,600 gallons, which represents an average daily flow of 274,653 gallons per day.

The operations staff continued to visually inspect the manholes outside the fence for signs of overflows. No evidence was found to indicate any overflows occurred during the month of August 2009.

The influent area operated normally during the month. The muffin monster, both raw lift pumps and associated controls experienced no operational problems. As a result of the Artesian safety audit conducted during the month, the operator is no longer permitted to enter the wet well area for routine cleaning and maintenance due to it being classified as a “Confined Space”. This classification will limit the operators’ ability to regularly hose the walls and cat walk as well as inspect and clean the level transducer.

The flow equalization system operated normally during the month. The Rotomat unit was in service continuously and debris generated by the unit was disposed of via the dumpster. The plant operator continued to remove sand and debris buildups from the bottom of the Rotomat box on a regular basis. The forward flow pumps and associated controls were in service continuously. Soda ash continued to be added daily through the feed system to help control pH values.

The package sewage treatment plant operated normally during the month. The aeration tanks were medium brown colored with very light tan colored surface foam buildups. The clarifiers operated normally as well. Sludge wasting continued to be accomplished to control the biomass. Mixed Liquor Suspended Solids (MLSS) analyses continue to be completed on a weekly basis to monitor the solids concentrations in both aeration tanks.

664 Churchmans Road, Newark, Delaware 19702, P.O. Box 15004 Wilmington, Delaware 19850 Phone: (302) 453-6900 Fax: (302) 453-6957
P.O. Box 177 Harbeson, Delaware 19951 Phone: (302) 684-2527 Fax: (302) 684-5164
28322 Lewes-Georgetown Hwy., Unit 4, Milton, DE 19968
e-mail: artesian@artesianwater.com Website: artesianwater.com

2 of 2

The sand filters were operational throughout the month with hose water being utilized to assist the lifting of sand. The chlorine contact tank and ultraviolet light disinfection system were in service continuously during the month of August.

The belt filter press was operated for two hundred forty (240) hours during the month of August to dewater approximately two hundred seventy-five thousand (275,000) gallons of waste activated sludge to produce three (3) dumpster loads of dried sludge for disposal.

During the month of August, the Artesian Safety Team conducted a safety audit of the facility. The findings of the audit indicated the facility needs some minor improvements to address safety concerns. These items include signage, safety chains, fire extinguishers, housekeeping, etc.

On August 28, 2009, the Pennsylvania Department of Environmental Protection conducted an inspection of the facility as part of the Chapter 94 compliance needs. The inspection went well and the township was informed the moratorium on new connections has been lifted.

The treatment plant expansion / modification project continued during the month of August. Work involving the operations staff included meetings and over site on the tank repairs and installation of new equipment.

The Applebrooke subdivision transfer pump was in service continuously during the month of August 2009. The flow meter associated with the pump remains out of service and the flows are continuing to be estimated.

Results of influent and final effluent samples collected during the month indicate compliance with current permit limitations.

Should you have any questions, please do not hesitate to contact me.

Sincerely,

Artesian Utility Development, Inc.

Thomas M. Horrex / bmr
Thomas M. Horrex, L.O., S. E.O.
Pennsylvania Operations Supervisor

TMH/bmr

cc: Mr. Evan Andrews - Pennoni Associates
    File

11-4-09
2. RIDLEY CREEK
g.
8 pgs

EAST GOSHEN MUNICIPAL AUTHORITY
RIDLEY CREEK EXPANSION PROJECT
SUMMARY

November 3, 2009

Name Budget or Contract amt. This Month To Date Balance % of work completed
EXPENSES
Borrowing costs $52,250.00 $0.00 $52,250.00 $0.00 100.00%
Worth $7,865,400.00 $727,172.53 $4,234,369.45 $3,631,030.55 53.84%
  change orders $8,753.00 $0.00 $0.00 $8,753.00 0.00%
Clinger $974,000.00 $111,255.75 $250,520.03 $723,479.97 25.72%
  change orders $5,106.00 $0.00 $0.00 $5,106.00 0.00%
Pennoni (Inspection) $136,200.00 $3,528.00 $132,316.40 $3,883.60 97.15%
Pennoni (Rechargeable) $20,000.00 $0.00 $12,961.75 $7,038.25 64.81%
Brickhouse $175,000.00 $7,417.50 $42,866.25 $132,133.75 24.50%
Extras
Capital $247,595.00 $0.00 $39,198.38 $208,396.62 15.83%
Capital (Identified but not paid) $23,696.00 $0.00 $0.00 $23,696.00 0.00%
Trailer, Phone, Porta Pot & Internet $12,000.00 $537.52 $6,565.19 $5,434.81 54.71%
EXPENSES TOTAL $9,520,000.00 $849,911.30 $4,771,047.45 $4,748,952.55 50.12%
RECEIPTS
Liquidated Damages $0.00 $0.00 $0.00 $0.00 0.00%
Pennoni (Rechargeable) -$20,000.00 $0.00 $0.00 -$20,000.00
NET COST $9,500,000.00 $4,728,952.55

Retainage (10% until 50% of the project is done then it drops back to 5%)

Worth $222,861.55 5%
Clinger $27,835.57 10%
Total $250,697.12

We have identified $467,000 in potential extras which includes $110,000 for Township Labor

F:\Data\Shared Data\Public Works Dept\Bids\RCSTP 2007\payments\RCSTP EXPANSION EXPENSES 110309.xls
SUMMARY V2

2 of 8

EAST GOSHEN MUNICIPAL AUTHORITY
RIDLEY CREEK CAPITAL EXPANSION PROJECT
DETAIL

November 3, 2009

Date Amount Subtotals Name Description
Worth
2/9/2009 $561,150.00 Worth & Company Application #1
3/9/2009 $480,825.00 Worth & Company Application #2
4/9/2009 $768,780.00 Worth & Company Application #3
5/8/2009 $125,352.90 Worth & Company Application #4
5/31/2009 $485,103.12 Worth & Company Application #5
6/30/2009 $267,975.00 Worth & Company Application #6
7/31/2009 $138,217.50 Worth & Company Application #7
8/31/2009 $679,793.40 Worth & Company Application #8
9/30/2009 $504,310.98 Worth & Company Application #9
9/30/2009 $222,861.55 Worth & Company Application #10 (5% retainage)
$4,234,369.45 $4,234,369.45
Clinger
4/9/2009 $22,152.64 Clinger Application #1
5/8/2009 $15,714.77 Clinger Application #2
5/31/2009 $77,973.43 Clinger Application #3
6/30/2009 $12,567.46 Clinger Application #4
8/30/2009 $10,855.98 Clinger Application #5
9/30/2009 $111,255.75 Clinger Application #6
$250,520.03 $250,520.03
Pennoni
? $712.50 PENNONI ASSOCIATES INC. RCSTP EXP.PROJ. SERV. THRU ?
10/30/2008 $943.50 PENNONI ASSOCIATES INC. RCSTP EXP.PROJ. SERV. THRU 10/19/08
12/5/2008 $18,115.98 PENNONI ASSOCIATES INC. RCSTP EXP.PROJ. SERV. THRU 11/30/08
1/15/2009 $12,929.00 PENNONI ASSOCIATES INC. RCSTP EXP.PROJ. SERV. THRU 12/28/08
2/5/2009 $13,352.50 PENNONI ASSOCIATES INC. RCSTP EXP.PROJ. SERV. THRU 1/25/09
3/19/2009 $31,288.00 PENNONI ASSOCIATES INC. RCSTP EXP.PROJ. SERV. THRU 3/1/09
4/8/2009 $29,010.46 PENNONI ASSOCIATES INC. RCSTP EXP.PROJ. SERV. THRU 3/29/09
5/6/2009 $22,436.46 PENNONI ASSOCIATES INC. RCSTP EXP.PROJ. SERV. THRU 4/26/09
7/29/2009 $3,528.00 PENNONI ASSOCIATES INC. RCSTP EXP PROJ SERV THRU 7/19/09
$132,316.40 $132,316.40

F:\Data\Shared Data\Public Works Dept\Bids\RCSTP 2007\payments\RCSTP EXPANSION EXPENSES 110309.xls
DETAIL

3 of 8

Date Amount Subtotals Name Description
Pennoni (rechargeable)
2/5/2009 $2,840.50 PENNONI ASSOCIATES INC. RCSTP EXP.PROJ. SERV. THRU 1/25/09
3/19/2009 $4,934.75 PENNONI ASSOCIATES INC. RCSTP EXP.PROJ. SERV. THRU 3/1/09
4/8/2009 $3,777.00 PENNONI ASSOCIATES INC. RCSTP EXP.PROJ. SERV. THRU 3/29/09
5/6/2009 $1,409.50 PENNONI ASSOCIATES INC. RCSTP EXP.PROJ. SERV. THRU 4/26/09
$12,961.75 $12,961.75
Brickhouse
5/12/2009 $2,127.50 BRICKHOUSE Apr-09
6/1/2009 $8,452.50 BRICKHOUSE May-09
7/1/2009 $7,791.25 BRICKHOUSE Jun-09
8/3/2009 $9,315.00 BRICKHOUSE Jul-09
9/1/2009 $7,762.50 BRICKHOUSE Aug-09
10/1/2009 $7,417.50 BRICKHOUSE Sep-09
$42,866.25 $42,866.25
Extras - Capital - Paid
12/22/2008 $44.98 EAST GOSHEN TOWNSHIP REIMBURSE GEN.FUND FOR OFFICE DEPOT
12/31/2008 $88.00 FASTSIGNS RED ON WHITE ALUM. SIGNS
1/12/2009 $177.00 FASTSIGNS SIGNS - PLEASE AVOID TOWNE DR...
12/1/2008 $36.00 GREAT VALLEY LOCKSHOP KEYS FOR CONTRACTOR
12/8/2008 $160.80 GREAT VALLEY LOCKSHOP PADLOCKS, REKEY CYLINDERS & KEYS
12/29/2008 $474.82 HANSON AGGREGATES INC 36.95 TONS SUBBASE AGGREGATE
12/31/2008 $908.00 HANSON AGGREGATES INC 70.66 TONS SUBGRADE 2 AGGREGATE
12/15/2008 $2,089.39 LENNI ELECTRIC CORPORAT TEMP SERV. FOR TRAILER - RIDLEY CRK
12/31/2008 $120.00 LENNI ELECTRIC CORPORAT SEWER PLANT - GUY WIRE RELOCATE
12/29/2008 $7,865.00 MACANGA INC. TRUCK & TRACKHOE RENTAL 12/5-12/18
12/1/2008 $2,466.00 PATTERSON, MICHAEL J. MATERIALS & LABOR - SPLIT RAIL FENCE
12/15/2008 $4,907.72 PIPE XPRESS INC. COPPER TUBING, BRASS COMP, COUPLING
12/29/2008 $813.74 PIPE XPRESS INC. BURIAL HYDRANT, BRASS CURB STOP, &
12/1/2008 $129.00 RAM-T CORPORATION 2 FT. SILT FENCE
12/8/2008 $1,183.00 RANSOME RENTAL COMPAN CATERPILLAR - TRUCK LOADER RENTAL
12/29/2008 $3,960.00 RANSOME RENTAL COMPAN CATERPILLAR RENTAL 11/13-11/25/08
12/29/2008 $908.00 RANSOME RENTAL COMPAN CATERPILLAR RENTAL 12/15 - 12/18/08
12/31/2008 $1,044.85 RANSOME RENTAL COMPAN CATERPILLAR RENTAL 12/15-12/16/08
12/8/2008 $119.95 SAFETY SOLUTIONS INC. MEDICAL SUPPLIES
12/1/2008 $635.60 US MUNICIPAL SUPPLY INC. CUSTOM SIGNS - RIDLEY CREEK TREATMT
12/31/2008 $157.50 GAWTHROP GREENWOOD LEGAL
1/31/2009 $936.50 GAWTHROP GREENWOOD LEGAL
3/19/2009 $1,246.64 HAMMOND & MCCMLOSY WATER SERVICE
3/31/2009 $1,254.00 GAWTHROP GREENWOOD LEGAL
4/2/2009 $274.21 PIPE XPRESS INC. YARD HYDRANT #2
4/2/2009 $1,910.28 HAMMOND & MCCMLOSY WATER PIPING
5/11/2009 $158.69 US MUNICIPAL SUPPLY INC. 3 SIGNS
4/30/2009 $264.86 LENNI ELECTRIC CORPORAT WIRED HOT WATER HEATER
5/31/2009 $133.00 GAWTHROP GREENWOOD LEGAL

F:\Data\Shared Data\Public Works Dept\Bids\RCSTP 2007\payments\RCSTP EXPANSION EXPENSES 110309.xls
DETAIL

4 of 8

Date Amount Subtotals Name Description
6/30/2009 $304.00 GAWTHROP GREENWOOD LEGAL
7/17/2009 $1,481.00 EAST GOSHEN TOWNSHIP BLOWER MOTOR (REPAIRED AND KEPT AS A SPARE)
9/10/2009 $254.85 AGWAY TREE STAKES AND PEAT MOSS
8/25/2009 $1,855.00 HARMONY HILL NURSERIES 16 TREES
8/31/2009 $836.00 GAWTHROP GREENWOOD 2 MONTH LEGAL
$39,198.38 $39,198.38
Extras - Capital - Identified extras that have not been paid
$20,396.00 Driveway Restoration
$3,300.00 Restoration of parking area
$23,696.00 $23,696.00
Trailer, Phone, Porta Potty & Internet
12/15/2008 $1,039.10 ACTON MOBILE INDUSTRIES RENTAL MOBILE OFFICE
12/22/2008 $239.10 ACTON MOBILE INDUSTRIES MOBILE OFFICE RENTAL - THRU 1/19/09
1/21/2009 $239.10 ACTON MOBILE INDUSTRIES MOBILE OFFICE RENTAL - 1/20-2/20/09
2/10/2009 $239.10 ACTON MOBILE INDUSTRIES MOBILE OFFICE RENTAL - 2/20-3/20/09
3/10/2009 $239.10 ACTON MOBILE INDUSTRIES MOBILE OFFICE RENTAL - 3/20 - 4/19
4/10/2009 $239.10 ACTON MOBILE INDUSTRIES MOBILE OFFICIE RENTAL - 4/20 - 5/19
5/10/2009 $239.10 ACTON MOBILE INDUSTRIES MOBILE OFFICIE RENTAL 5-20 - 6/19
6/10/2009 $239.10 ACTON MOBILE INDUSTRIES MOBILE OFFICIE RENTAL 6/20 - 7/19
7/10/2009 $239.10 ACTON MOBILE INDUSTRIES 7/20 to 8/19
8/10/2009 $239.10 ACTON MOBILE INDUSTRIES 8/20 to
9/10/2009 $239.10 ACTON MOBILE INDUSTRIES
10/10/2009 $239.10 ACTON MOBILE INDUSTRIES thru 11/19
$3,669.20 $3,669.20
12/15/2008 $140.00 POTTY QUEEN RENTAL PORTABLE TOILET - RIDLEY CRK
12/22/2008 $64.47 POTTY QUEEN RENTAL TOILET 12/23-1/10/08
2/8/2009 $95.00 POTTY QUEEN RENTAL TOILET 2/8-3/7
3/8/2009 $95.00 POTTY QUEEN RENTAL TOILET 3/8-4/4
4/5/2009 $95.00 POTTY QUEEN RENTAL TOILET 4/5-5/2
5/5/2009 $95.00 POTTY QUEEN RENTAL TOILET ????
7/26/2009 $95.00 POTTY QUEEN RENTAL 7/26 TO 8/22
8/23/2009 $95.00 POTTY QUEEN Rental 8/23 to 9/19
9/20/2009 $95.00 POTTY QUEEN RENTAL 9/20 to 10/17
10/18/2009 $95.00 POTTY QUEEN 10/18/09 to 11/14/09
$964.47 $964.47

F:\Data\Shared Data\Public Works Dept\Bids\RCSTP 2007\payments\RCSTP EXPANSION EXPENSES 110309.xls
DETAIL

5 of 8

Date Amount Subtotals Name Description
12/22/2008 $174.65 VERIZON -7041 NOVEMBER 25 - DECEMBER 6, 2008
1/7/2009 $137.87 VERIZON -7041 BILLING DATE 1/07/09
2/7/2009 $130.34 VERIZON -7041 BILLING DATE 2/07/09
3/7/2009 $133.97 VERIZON -7041 BILLING DATE 3/7/09
4/7/2009 $136.00 VERIZON -7041 BILLING DATE 4/7/09
5/7/2009 $137.66 VERIZON -7041 BILLING DATE 5/7/09
6/7/2009 $178.47 VERIZON -7041 BILLINGDATE 6/7/2009
7/7/2009 $145.21 VERIZON -7041 Billing Date 7/7/09
8/7/2009 $134.44 VERIZON -7041 Billing Date 8/7/09
9/7/2009 $132.93 VERIZON -7041 billing date 9/7/09
9/7/2009 $133.43 VERIZON -7041 Billing date 10/7/09
$1,574.97 $1,574.97
8/31/2009 $286.56 VERIZON INTERNET (FIRST BILL)
9/28/2009 $69.99 VERIZON INTERNET (FIRST BILL)
$356.55 $356.55
$6,565.19

F:\Data\Shared Data\Public Works Dept\Bids\RCSTP 2007\payments\RCSTP EXPANSION EXPENSES 110309.xls
DETAIL

6 of 8

EAST GOSHEN MUNICIPAL AUTHORITY
RIDLEY CREEK CAPITAL EXPANSION PROJECT
POTENTIAL EXTRAS

November 3, 2009

Potential capital extras

Pennoni (additional 6 months) $50,000
Excavation $0
Blower Repairs (2) $12,000
Pipe conduit Conflicts $30,000
Shoring at EQ tank (we will get a credit) $0
Controls $10,000
Sludge room retrofit $10,000
Motor Control Retrofit Clinger CO3
HVAC Thermostats $5,000
Cathode Protection $10,000
Treatment Tanks $200,000
Township Labor $110,000
Total potential extras $437,000

Potential Receipts

Worth Engineering recharges (6 months) $0
Worth liquidated damages (6 months @ $100 day) $0
Worth - Reduced excavation as a result of SBR tank shift $0
Worth - Savings as a result of shifting screen building $0
Total Potential Receipts $0

F:\Data\Shared Data\Public Works Dept\Bids\RCSTP 2007\payments\RCSTP EXPANSION EXPENSES 110309.xls
POTENTIAL EXTRAS

7 of 8

EAST GOSHEN MUNICIPAL AUTHORITY
RIDLEY CREEK CAPITAL EXPANSION PROJECT
CHANGE ORDERS

November 3, 2009

NO. AMOUNT APPROVED WORK STATUS PAID
WORTH
1 $3,210.00 2/24/09 BLOWER #1 REPAIR APPROVED NO
2 $5,543.00 5/11/09 BLOWER #2 REPAIR APPROVED NO
3 BLOWER #3 REPAIR APPROVED
Total $8,753.00
CLINGER
1 $7,034.00 Denied EXTEND 34 KV LINES DENIED
3 $5,106.00 7/1/09 CORNER UNIT FOR MOTOR CONTROL CENTER APPROVED NO
Total $5,106.00

F:\Data\Shared Data\Public Works Dept\Bids\RCSTP 2007\payments\RCSTP EXPANSION EXPENSES 110309.xls
CHANGE ORDERS

8 of 8

EAST GOSHEN MUNICIPAL AUTHORITY
RIDLEY CREEK CAPITAL EXPANSION PROJECT
POTENTIAL EXTRAS

November 3, 2009

Potential capital extras

Pennoni (additional 6 months) $50,000
Excavation $0
Blower Repairs (2) $12,000
Pipe conduit Conflicts $30,000
Shoring at EQ tank (we will get a credit) $0
Controls $10,000
Sludge room retrofit $10,000
Motor Control Retrofit Clinger CO3
HVAC Thermostats $5,000
Cathode Protection $10,000
Treatment Tanks $200,000
Township Labor $110,000
Total potential extras $437,000

Potential Receipts

Worth Engineering recharges (6 months) $0
Worth liquidated damages (6 months @ $100 day) $0
Worth - Reduced excavation as a result of SBR tank shift $0
Worth - Savings as a result of shifting screen building $0
Total Potential Receipts $0

F:\Data\Shared Data\Public Works Dept\Bids\RCSTP 2007\payments\RCSTP EXPANSION EXPENSES 110309.xls
POTENTIAL EXTRAS

2. RIDLEY CREEK REPORTS
h.
1 pg

Pennsylvania Department of Environmental Protection
2 East Main Street
Norristown, PA 19401
October 9, 2009

Southeast Regional Office      Phone: 484-250-5970
                                            Fax: 484-250-5971

Mr. Francis X. Beck
Authority Chairman
East Goshen Municipal Authority
East Goshen Township Building
1580 Paoli Pike
West Chester, PA 19380

Ms. Dorothy E. McClintock
Willistown Township
688 Sugartown Road
Malvern, PA 19355

Re: Sewage
Chapter 94 Annual Report
Ridley Creek Sewage Treatment Plant
East Goshen Township
Chester County

Dear Mr. Beck and Ms. McClintock:

The Pennsylvania Department of Environmental Protection (“Department”) has completed its review of East Goshen Township’s 2008 Municipal Wasteload Management Annual Report (“Chapter 94 Report”) for the Ridley Creek Sewage Treatment Plant. The revised information received by the Department on October 5, 2009, adequately addresses the deficiencies enumerated in the Department’s letter dated September 2, 2009 (copy enclosed). Please note that until the treatment plant expansion has been completed and is fully operational, the Department can only grant sewage planning approvals and sewage planning exemptions based on currently permitted capacities.

In next year’s report, please respond to all items listed in the checklist and update the Department on any progress towards installing flow meters.

If you have any questions or concerns, please call me at 484-250-5133.

Sincerely,

Courtney Vanous
Courtney Vanous
Sewage Planning Specialist 1
Water Management

Enclosure: 94 Review Letter

cc: Mr. Smith - East Goshen Township (via e-mail)
Mr. Andrews - Pennoni Associates, Inc. (via e-mail)
Planning Section
Re 30 (GJE09WQ)281-19

An Equal Opportunity Employer      www.dep.state.pa.us      Printed on Recycled Paper

3. RIDLEY CREEK INVOICES
a
2 pgs

Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

INVOICE

Philadelphia, PA
215-222-3000 Fax: 215-222-3588

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 422066
Invoice Date : 10/30/2009
Project : EGMA0903
Project Name : RCSTP Sewer Modeling

For Services Rendered through: 10/18/2009

Collection and cataloging of sewer plans; assembling flow data; and communication with Client regarding same.

Phase : **** -- Professional Services

Total Phase : **** -- Professional Services Labor : 6,577.00
Expense : 0.00
Phase Total : 6,577.00
Amount Due This Invoice $6,577.00
Fee : 28,300.00
Prior Billings : 7,493.00
Current Billings : 6,577.00
Total Billings : 14,070.00

Phase : **** -- Professional Services
Labor

Class Hours/Units Rate Amount
Authority Engineer 10.50 105.00 1,102.50
Project Engineer 7.75 90.00 697.50
Associate Engineer 47.00 77.00 3,619.00
Graduate Engineer 7.50 67.00 502.50
Engineering Technician I 11.50 57.00 655.50
Labor Total: 84.25 6,577.00
Total Phase : **** -- Professional Services Labor : $6,577.00
Expense : $0.00
Total Project : EGMA0903 -- RCSTP Sewer Modeling Labor : $6,577.00
Expense : $0.00

ok RS 10/30

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

2 of 2

East Goshen Municipal Authority
EGMA0903 Invoice Summary
Invoice Date 10-30-2009

Project: RCSTP Sewer Modeling
Pennoni Job No.: EGMA 0903
Invoice No: 422066
Invoice Period: 9/21/2009 to 10/18/2009
    Initial Authorization: $ 28,300.00 Date: 9/17/2009
    Changes: $ - Date:
    Contract Amount: $ 28,300.00
    Previously Invoiced: $ 7,493.00
    Current Invoice: $ 6,577.00
    Invoiced to Date ($): $ 14,070.00
    Invoiced to Date (%): 50%
    Remaining Budget ($): $ 14,230.00
    Remaining Budget (%): 50%

Budget by Phase:
Phase No.

Phase Name: RCSTP Sewer Modeling
Phase Budget: $ 28,300.00
Previously Invoiced: $ 7,493.00
Current Invoice: $ 6,577.00
Invoiced to Date ($): $ 14,070.00
Invoiced to Date (%): 50%
Remaining Budget ($): $ 14,230.00
Remaining Budget (%): 50%

Comments: Collection and cataloging of sewer plans; assembling flow data; and communication with Client regarding same.

5. Minutes
4 pgs

EAST GOSHEN TOWNSHIP
MUNICIPAL AUTHORITY MEETING MINUTES
October 12, 2009

The East Goshen Township Municipal Authority held their regularly scheduled meeting on Monday, October 12, 2009 at 7:00 PM at the East Goshen Township building. Members in attendance were: Chairman Fran Beck, Jack Yahraes, Dana Pizarro, Mike Steinberger, and Joe McCawley. Also in attendance were: Township Manager Rick Smith, Township Solicitor Bob Adams. Public Works Manager Mark Mill, Scott Towler and Dave Evans from Brickhouse Environmental, Steve Cantrell and Jeff Bush from Worth, and Authority Engineer Evan Andrews, Ellen Carmody from the Historical Commission, and Meghan Hedgcock from the Planning Commission.

COMMON ACRONYMS:

MA – Municipal Authority I&I – Inflow & Infiltration
HC – Historical Commission RCSTP – Ridley Creek Sewer Treatment Plant
PC – Planning Commission LCSTP – Lockwood Chase Sewer Treatment Plant
CB – Conservancy Board DEP – Department of Environmental Protection
PR – Park & Recreation Board EPA – Environmental Protection Agency
BOS – Board of Supervisors PHMC – Pennsylvania Historical Museum Commission
NPDES – National Pollutant Discharge Elimination System
  1. CALL TO ORDER The meeting was called to order at 7:00pm and Fran led those present in the Pledge of Allegiance.
  2. RECORDING MEETINGS -Fran announced that the recording secretary would be digitally recording this meeting and that the recording will be erased upon approval of the final minutes. Fran also asked if anyone in attendance was planning to record this meeting.
  3. RCSTP REPORT No new activity was reported for the Influent Meter Vault. The aluminum gate valves were set in place, as was the aluminum stairway from the upper level to access the influent flow channels. The fine screen unit was also installed and the floor pad for the screen discharge was poured as well. The piping and gate valve from the SBR effluent decant pipe adjacent to the floc tank was installed. The concrete cast in walls for containment tank foundation was installed as well. Equipment for the third SBR was delivered to the construction site, as was a fiberglass aluminum storage tank. On September 14 th , piping and equipment was placed within the SBR basin. Biweekly progress meetings continue. On October 6 th , a meeting was held with Pennoni, Worth and Company, Dutchland, and the Municipal Authority to discuss resolving the schedule delay and liquidated damages. Scott added that a meeting was held with Mary Ann Stolfus and Jeff Bush to wrap up any loose ends, change order requests were completed and a new date of June 30, 2010 for completion were all discussed. It is recommended that the MA accept the 10 year warranty

MA Minutes 10/12/2009      Page 1 of 4

204

on the SBR tanks. Joe noted that the completion has been moved back 7 months, but the township and Authority would save $42,000.00

Steve Cantrell from Worth and Company spoke stating that the true motive is to give a quality plant. He added that they have made efforts to get the project back on track. Joe questioned if it is realistic for the project to be completed by June of 2010. Steve noted that he is confident that all will be completed to quality at that time. Evan and Mark Miller were in agreement with this comment.

A motion was made by Joe to accept the settlement with Worth and Company. Jack seconded the motion and no further discussion or public comment was heard. The motion passed unanimously.

4. RCSTP INVOICES

A. West Chester Agway, Inv. #054681, 9/10/09 - $254.85.
Jack moved to approve payment to West Chester Agway in the amount of $254.85 for RCSTP project landscape materials. Joe seconded the motion. No further discussion or public comment was heard. The motion passed unanimously.

B. Brickhouse Enviromental, 10/1/2009- $ 7,417.50.
Joe moved to approve payment to Brickhouse Enviromental for the RCSTP expansion in the amount of $ 7,417.50. Dana seconded the motion. No further discussion or public comment was heard. The motion passed unanimously.

C. Worth and Company, Invoice # P28001, 9/30/09- $ 504,310.98.
Joe moved to approve payment to Worth and Company for the RCSTP in the amount of $504,310.98. Mike seconded the motion. No further discussion or public comment was heard. The motion passed unanimously.

D. Wm. H. Clinger Corp, Inv#. EGMA0707 - $111,255.75.
Joe moved to approve payment to Wm. H. Clinger Corp.for RCSTP in the amount of $111,255.75. Dana seconded the motion. No further discussion or public comment was heard. The motion passed unanimously.

E. A missing invoice from Worth and Company in the amount of $222,861.55, Inv# 10.
Jack moved to approve payment to Worth and Company in the amount of $222,861.55. Joe seconded the motion. No further discussion or public comment was heard. The motion passed unanimously.

5. APPROVAL OF MINUTES

The minutes of August 10, 2009 were reviewed. Jack moved that the minutes of August 10, 2009 be approved as corrected. Joe seconded the motion. No further discussion or public comment was heard. The motion passed unanimously. The minutes of September 17, 2009 were reviewed. Mike motioned to approve as presented. Jack seconded the motion. No further discussion or public comment was heard. The motion passed unanimously.

6. ENGINEERING REPORT

Evan reported that construction phase services continue with progress meetings with contractors and the township every other Thursday. Observation services continue and include communication and coordination with Brickhouse and the Township. A special project meeting was held on 9/25/09 to resolve warranty for SBR tanks with Worth, Dutchland, and the Township. The current project schedule anticipates substantial completion in June of 2010.

MA Minutes 10/12/2009

Page 2 of 4

3 of 4

Ridley Creek hydraulic model development has begun with a scheduled completion date of December 1, 2009. The semi-annual report to DEP per the CO&A was sent on September 18, 2009 ahead of the September 30th deadline. The next deadline is December 1, 2009.

A response to the DEP's letter of September 2, 2009 regarding the Annual Chapter 94 Report was provided on October 2nd. The DEP comments were focused on projected hydraulic and organize loads to the RCSTP. DEP also requested metering data on the Ridley Creek Collection System. Metering information from the I/I Metering Project was provided.

A second letter dated 9/30/2009 was received from the DEP regarding the Annual Chapter 94 Report for the Lochwood Chase STP. DEP comments were focused on plant flow measurements and loading on the treatment plant. A response is currently being prepared for submittal to the DEP by November 6, 2009.

The DEP is requiring additional metering in all sanitary sewage collection systems including East Goshen. The recommendation is to identify location within the township-wide collection system that can be cost-effectively metered in order to comply with the requirements of Chapter 24.

7. APPROVAL OF INVOICES

A. Pennoni – Inv. #418854, 9/30/09 - $7,493.00.
Mike moved to approve payment to Pennoni in the amount of $7,493.00 for RSCTP expansion project. Joe seconded the motion. No further discussion or public comment was heard. The motion passed unanimously.

B. Pennoni – Inv. #418851, 9/30/09 - $645.00.
Jack moved to approve payment to Pennoni in the amount of $645.00 for RSCTP expansion project. Joe seconded the motion. No further discussion or public comment was heard. The motion passed unanimously.

C. Pennoni – Inv. #418852, 9/30/09 - $268.00.
Joe moved to approve payment to Pennoni in the amount of $268.00 for RSCTP expansion project. Dana seconded the motion. No further discussion or public comment was heard. The motion passed unanimously.

D. Pennoni – Inv. #418853, 9/30/09 - $1,673.00.
Joe moved to approve payment to Pennoni in the amount of $1,673.00 for the RSCTP expansion project. Jack seconded the motion No further discussion or public comment was heard. The motion passed unanimously.

E. Verizon – 8/29/09 - $286.56.
Jack moved to approve payment to Verizon in the amount of $286.56 for the RSCTP expansion project internet services. Dana seconded the motion No further discussion or public comment was heard. The motion passed unanimously. The decision was made to pre-approve moving forward, Joe made the motion and Dana seconded the motion. No further discussion or public comment was heard. The motion passed unanimously.

8. LIAISON REPORTS

Ellen Carmody, HC –reported that Living History Day was a huge success and attendance was at its highest. Meghan noted that the PC approved Sullivan's Grove and a C/U application for 1422 Paoli Pike.

MA Minutes 10/12/2009

Page 3 of 4

4 of 4

9. FINANCIAL REPORT

Mike reviewed the financial report and noted that there was nothing new to report.

10. NEW BUSINESS

A memo from Mark Miller in reference to lab equipment that will be needed once the SBR comes on line. The equipment that will be required totals $12,000.00. Jack motioned to approve the purchase of needed lab equipment and Mike seconded the motion. No further discussion or public comment was heard. The motion passed unanimously.

11. SEWER REPORTS

Routine maintenance continues. See reports for further information.

12. PUBLIC COMMENT – none

13. ADJOURNMENT

Mike moved that the meeting adjourn. Joe seconded the motion. No further discussion or public comment was made. The motion carried unanimously. The meeting adjourned at 8:36 PM.

Respectfully submitted by: __________________________________________________
Linda Jones, Recording Secretary

MA Minutes 10/12/2009

Page 4 of 4

6. ENGINEER'S RPT
2pp

Pennoni

MEMORANDUM

TO:East Goshen Municipal Authority Board
Rick Smith, Township Manager
FROM:Evan R. Andrews, P.E.
Authority Engineer
DATE:November 4, 2009
SUBJECT:Engineer's Report

RCSTP Upgrade and Expansion

  • Construction phase services continue including: progress meetings with the Contractors and Township every other Thursday; observation services continue including coordination and communication with Brickhouse and the Township; receipt, review, and return of Contractor submittals; negotiation, review, and approval of Payment Requests.
  • Meeting held on 11/3/09 with Worth to review outstanding change orders.
  • Current Project Schedule anticipates substantial completion in June 2010.

I/I Metering Project

  • Metering at the intersection of Saratoga Drive and Paoli Pike and Tallmadge Drive and Paoli Pike. The sewers upstream of these two locations run parallel to Ridley Creek. The goal of this metering is to locate the part(s) of the collection system upstream that might be the source of continuous flow observed at the Chester Road meter.
  • Adjust the Towne Drive meter location to the Ridley Creek Interceptor immediately upstream of the 8-inch sewer from Achom Drive. This location will be a substitute for the 2009 Paoli Pike East metering since the 8-inch diameter Paoli Pike East line does not appear to have any significant I/I problems.

RCSTP System Hydraulic Characterization

  • Ridley Creek hydraulic model development has begun with a draft report to be provided to the Township in 10 days. The final report is due to DEP by December 1, 2009 per the CO&A.

Ridley Creek Consent Order

  • Flow meters to be set by the Township at the locations noted above under “I/I Metering Project”.
  • The next deadline is the Ridley Creek hydraulic model due December 1, 2009.

LM03 05/2002

2 of 2

Chapter 94 Reporting

  • A second letter dated September 30, 2009 was received from DEP regarding the Annual Chapter 94 Report for the Lochwood Chase STP. DEP comments are focused on plant flow measurements and loading on the treatment plant. A response was submitted to DEP on October 26, 2009.
  • DEP is requiring additional metering in all sanitary sewage collection systems including East Goshen. Our recommendation is to identify locations in the township-wide collection system that can be cost-effectively metered in order to comply with the requirements of Chapter 94.
  • Chapter 94 also requires that all STPs receiving 100,000 gpd or more have influent meters by January 1, 2010. A meter is included in the RCSTP upgrade and expansion but will likely not be on-line by this date. It will therefore be necessary to place a temporary meter at the RCSTP until the permanent meter is operational, possibly in March.

West Goshen Diversion Project

  • A memo summarizing the identification and evaluation of diversion locations from the Chester Creek collection system to the Ridley Creek collection system has been prepared. The conclusion is that a “slip-stream” diversion is the most cost-effective alternative.
  • We recommend that a meeting with West Goshen to discuss the evaluation and their reaction to the diversion of approximately 300,000 gpd from their Chester Creek STP. The discussion would also include the Hershey Mill, Reserve and Marydell pump station diversions.

LM03 05/2002

7. INVOICES

Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

INVOICE

Philadelphia, PA
215-222-3000 Fax: 215-222-3588

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice #: 422065
Invoice Date: 10/30/2009
Project: EGMA0900
Project Name: 2009 Annual Services

For Services Rendered through: 10/18/2009

Participation in monthly Board meeting; prepare responses to DEP comments on Annual Chapter 94 Report; consultation with Authority.

Phase : **** -- Professional Services

Total Phase : **** -- Professional ServicesLabor :1,384.00
Expense :0.00
Phase Total :1,384.00
Fee :8,000.00Amount Due This Invoice$1,384.00
Prior Billings :6,586.50
Current Billings :1,384.00
Total Billings :7,970.50

Phase : **** -- Professional Services

Labor

Class Hours/Units Rate Amount
Authority Engineer2.00105.00210.00
Staff Engineer11.5083.00954.50
Graduate Engineer2.0067.00134.00
Engineering Technician I1.5057.0085.50
Labor Total:17.001,384.00
Total Phase : **** -- Professional ServicesLabor :$1,384.00
Expense :$0.00
Total Project : EGMA0900 -- 2009 Annual ServicesLabor :$1,384.00
Expense :$0.00

ok RS 10/30

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority
EGMA0900 Invoice Summary
Invoice Date 10-30-2009

Project:2009 Annual Services
Pennoni Job No.:EGMA0900
Invoice No:422065
Invoice Period:9/21/2009to10/18/2009
Initial Authorization:$ 5,000.00Date:12/9/2008
Changes:$ 3,000.00Date:9/17/2009
Contract Amount:$ 8,000.00
Previously Invoiced:$ 6,586.50
Current Invoice:$ 1,384.00
Invoiced to Date ($):$ 7,970.50
Invoiced to Date (%):100%
Remaining Budget ($):$ 29.50
Remaining Budget (%):0%

Budget by Phase:
Phase No. 01

Phase Name:Project
Phase Budget:$ 8,000.00
Previously Invoiced:$ 6,586.50
Current Invoice:$ 1,384.00
Invoiced to Date ($):$ 7,970.50
Invoiced to Date (%):100%
Remaining Budget ($):$ 29.50
Remaining Budget (%):0%

Comments: Participation in monthly Board meeting; consultation with Authority.
Prepare responses to DEP comments on Annual Chapter 94 Report.

Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

INVOICE

Philadelphia, PA
215-222-3000 Fax: 215-222-3588

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice #: 422064
Invoice Date: 10/30/2009
Project: EGMA0809
Project Name: Marydell Diversion Planning

For Services Rendered through: 10/18/2009

Layout of plot plan drawings and sewer layout. Consultation with Client regarding same.

Phase : 03 -- Final Update Revision

Total Phase : 03 -- Final Update RevisionLabor :303.75
Expense :0.00
Phase Total :303.75
Fee :11,500.00Amount Due This Invoice$303.75
Prior Billings :6,290.75
Current Billings :303.75
Total Billings :6,594.50

Phase : 03 -- Final Update Revision

Labor

Class Hours/Units Rate Amount
Authority Engineer0.50105.0052.50
Graduate Engineer3.7567.00251.25
Labor Total:4.25303.75
Total Phase : 03 -- Final Update RevisionLabor :$303.75
Expense :$0.00
Total Project : EGMA0809 -- Marydell Diversion PlanningLabor :$303.75
Expense :$0.00

ok RS 10/30

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municpal Authority
EGMA0809 Invoice Summary
Invoice Date 10-30-2009

Project:Marydell Pump Station Diversion Project Planning
Pennoni Job No.:EGMA 0809
Invoice No:422064
Invoice Period:9/21/2009to10/18/2009
Initial Authorization:$ 11,500.00Date:12/8/2008
Changes:$ -Date:
Contract Amount:$ 11,500.00
Previously Invoiced:$ 6,290.75
Current Invoice:$ 303.75
Invoiced to Date ($):$ 6,594.50
Invoiced to Date (%):57%
Remaining Budget ($):$ 4,905.50
Remaining Budget (%):43%

Budget by Phase:

Phase No. 01 02 03 04 05
Phase Name: DEP Coordination Draft Update Revision Final Update Revision DEP Approval & Cost Recovery Add'l Meeting Allowance
Phase Budget: $ 1,100.00 $ 5,300.00 $ 3,300.00 $ 1,300.00 $ 500.00
Previously Invoiced: $ 650.00 $ 5,372.75 $ - $ - $ -
Current Invoice: $ 268.00 $ 303.75 $ - $ -
Invoiced to Date ($): $ 650.00 $ 5,640.75 $ 303.75 $ - $ -
Invoiced to Date (%): 59% 106% 9% 0% 0%
Remaining Budget ($): $ 450.00 $ (340.75) $ 2,996.25 $ 1,300.00 $ 500.00
Remaining Budget (%): 41% -6% 91% 100% 100%

Comments: Layout of plot plan drawings and sewer layout.
Consultation with Client regarding same.

Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

INVOICE

Philadelphia, PA
215-222-3000 Fax: 215-222-3588

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice #: 422063
Invoice Date: 10/30/2009
Project: EGMA0808
Project Name: WG Diversion Project Planning

For Services Rendered through: 10/18/2009

Review of sewer area flows and identification/evaluation of diversion locations. Consultation with Township regarding same.

Phase : 02 -- Diversion Conceptual Design

Total Phase : 02 -- Diversion Conceptual DesignLabor :1,860.00
Expense :0.00
Phase Total :1,860.00
Fee :25,200.00Amount Due This Invoice$1,860.00
Prior Billings :3,491.00
Current Billings :1,860.00
Total Billings :5,351.00

Phase : 02 -- Diversion Conceptual Design

Labor

Class Hours/Units Rate Amount
Authority Engineer4.00105.00420.00
Project Engineer16.0090.001,440.00
Labor Total:20.001,860.00
Total Phase : 02 -- Diversion Conceptual DesignLabor :$1,860.00
Expense :$0.00
Total Project : EGMA0808 -- WG Diversion Project PlanningLabor :$1,860.00
Expense :$0.00

ok RS 10/30

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority
EGMA0808 Invoice Summary
Invoice Date 10-30-2009

FieldValueExtra
Project:West Goshen Diversion Planning
Pennoni Job No.:EGMA 0808
Invoice No:422063
Invoice Period:9/21/2009to 10/18/2009
Initial Authorization:$ 25,200.00Date: 12/8/2008
Changes:$ -Date:
Contract Amount:$ 25,200.00
Previously Invoiced:$ 3,491.00
Current Invoice:$ 1,860.00
Invoiced to Date ($):$ 5,351.00
Invoiced to Date (%):21%
Remaining Budget ($):$ 19,849.00
Remaining Budget (%):79%

Budget by Phase:

Phase No.010203040506
Phase Name:DEP CoordinationDiversion Concept DesignDraft Update RevisionFinal Update RevisionDEP Approval & Cost RecoveryAdd'l Meeting Allowance
Phase Budget:$ 1,100.00$ 7,500.00$ 9,400.00$ 3,900.00$ 1,800.00$ 1,500.00
Previously Invoiced:$ 956.00$ 2,535.00$ -$ -$ -$ -
Current Invoice:$ -$ 1,860.00$ -$ -$ -$ -
Invoiced to Date ($):$ 956.00$ 4,395.00$ -$ -$ -$ -
Invoiced to Date (%):87%59%0%0%0%0%
Remaining Budget ($):$ 144.00$ 3,105.00$ 9,400.00$ 3,900.00$ 1,800.00$ 1,500.00
Remaining Budget (%):13%41%100%100%100%100%

Comments: Review of sewer area flows and identification/evaluation of diversion locations. Consultation with Township regarding same.

Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

INVOICE

Philadelphia, PA
215-222-3000 Fax: 215-222-3588

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice #: 422062
Invoice Date: 10/30/2009
Project: EGMA0704
Project Name: Pump Station Special Study

For Services Rendered through: 10/18/2009

Layout of plot plan drawings and sewer layout.

Phase : 01 -- Planning Study

Total Phase : 01 -- Planning StudyLabor :956.50
Expense :0.00
Phase Total :956.50
Fee :14,000.00Amount Due This Invoice$956.50
Prior Billings :9,542.25
Current Billings :956.50
Total Billings :10,498.75

Phase : 01 -- Planning Study

Labor

Class Hours/Units Rate Amount
Authority Engineer2.25105.00236.25
Graduate Engineer10.7567.00720.25
Labor Total:13.00956.50
Total Phase : 01 -- Planning StudyLabor :$956.50
Expense :$0.00
Total Project : EGMA0704 -- Pump Station Special StudyLabor :$956.50
Expense :$0.00

ok RS 10/30

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority
EGMA0704 Invoice Summary
Invoice Date 10-30-2009

Project:Hershey Mill and Reserve Pump Station Diversion Special Planning Study
Pennoni Job No.:EGMA0704
Invoice No:422062
Invoice Period:8/17/2009to10/18/2009
Initial Authorization:$ 14,000.00Date:7/9/2007
Changes:$ -Date:
Contract Amount:$ 14,000.00
Previously Invoiced:$ 9,542.25
Current Invoice:$ 956.50
Invoiced to Date ($):$ 10,498.75
Invoiced to Date (%):75%
Remaining Budget ($):$ 3,501.25
Remaining Budget (%):25%

Budget by Phase:

Phase No. 01 02
Phase Name: Act 537 Special Study Meetings Allowance
Phase Budget: $ 12,500.00 $ 1,500.00
Previously Invoiced: $ 9,542.25 $ -
Current Invoice: $ 956.50 $ -
Invoiced to Date ($): $ 10,498.75 $ -
Invoiced to Date (%): 84% 0%
Remaining Budget ($): $ 2,001.25 $ 1,500.00
Remaining Budget (%): 16% 100%

Comments: Layout of plot plan drawings and sewer layout.
Consultation with Township regarding same.

Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

INVOICE

Philadelphia, PA
215-222-3000 Fax: 215-222-3588

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice #: 422061
Invoice Date: 10/30/2009
Project: EGMA0703
Project Name: LCSTP Decommissioning Planning

For Services Rendered through: 10/18/2009

Layout of plot plan drawings and sewer layout.

Phase : 02 -- Act 537 Plan Update

Total Phase : 02 -- Act 537 Plan UpdateLabor :767.75
Expense :0.00
Phase Total :767.75
Fee :23,700.00Amount Due This Invoice$767.75
Prior Billings :17,658.00
Current Billings :767.75
Total Billings :18,425.75

Phase : 02 -- Act 537 Plan Update

Labor

Class Hours/Units Rate Amount
Authority Engineer1.25105.00131.25
Graduate Engineer9.5067.00636.50
Labor Total:10.75767.75
Total Phase : 02 -- Act 537 Plan UpdateLabor :$767.75
Expense :$0.00
Total Project : EGMA0703 -- LCSTP Decommissioning PlanningLabor :$767.75
Expense :$0.00

ok RS 10/30

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority
EGMA0703 Invoice Summary
Invoice Date 10-30-2009

Project:LCSTP Decommissioning Planning
Pennoni Job No.:EGMA0703
Invoice No:422061
Invoice Period:8/17/2009to10/18/2009
Initial Authorization:$ 23,700.00Date:5/14/2007
Changes:$ -Date:
Contract Amount:$ 23,700.00
Previously Invoiced:$ 17,658.00
Current Invoice:$ 767.75
Invoiced to Date ($):$ 18,425.75
Invoiced to Date (%):78%
Remaining Budget ($):$ 5,274.25
Remaining Budget (%):22%

Budget by Phase:

Phase No. 01 02
Phase Name: DEP Coordination Act 537 Plan Update
Phase Budget: $ 3,700.00 $ 20,000.00
Previously Invoiced: $ 2,583.75 $ 15,074.25
Current Invoice: $ - $ 767.75
Invoiced to Date ($): $ 2,583.75 $ 15,842.00
Invoiced to Date (%): 70% 79%
Remaining Budget ($): $ 1,116.25 $ 4,158.00
Remaining Budget (%): 30% 21%

Comments: Layout of plot plan drawings and sewer layout.

COPY

Gawthrop Greenwood, PC
Attorneys at Law

17 East Gay Street Suite 100
P.O. Box 562
West Chester, PA 19381-0562
gglaw@gawthrop.com
(p) 610-696-8225
(f) 610-344-0922
www.gawthrop.com

East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380
Page: 1
09/30/2009
Client No: 6604-01M
Statement No: 73972

General Authority Services

Fees

Date / Timekeeper Description Hours Amount
09/15/2009
RFA
Review message from Evan Andrews regarding report to DEP regarding consent order and agreement status. 0.30
09/17/2009
RFA
Review proposed status report from Pennoni on compliance with consent order and agreement; Message to Evan Andrews regarding status report. 0.80
RFA Review packet for 9/21 Authority meeting. 0.50
09/18/2009
RFA
Review message from Evan Andrews regarding semi-annual corrective action report under CO&A. 0.30
09/21/2009
RFA
Review letter from Evan Andrews regarding consent order. 0.30
09/24/2009
RFA
Review message from Evan Andrews regarding consent order and agreement affidavit of mailing; review executive summary of infiltration and inflow abatement program. 0.90
For Current Services Rendered 3.10 589.00

Recapitulation

Timekeeper Hours Hourly Rate Total
Robert F. Adams 3.10 $190.00 $589.00

Expenses

Westlaw research charges 54.02
Total Expenses Thru 09/30/2009 54.02

ok RS 10/16

East Goshen Municipal Authority
General Authority Services
Page: 2
09/30/2009
Client No: 6604-01M
Statement No: 73972
Previous Balance $2,033.00
Total Current Charges 643.02
09/28/2009 Fee Payment -2,033.00
Balance Due $643.02

To ensure proper credit, please write client number on your check when returning payment. Thank You.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.

10. GOALS
2pp

2009
EAST GOSHEN MUNICIPAL AUTHORITY GOALS
OCTOBER REPORT

ON-GOING

  1. Submit an article for each newsletter. Need by 2/11/08 Mike Completed; Need by 5/13/09 Fran Completed; Need by 8/12/09 Joe Not Completed; Need by 11/9/08 Dana
  2. Attend West Goshen Meetings quarterly – more often if needed. 1 st Quarter (3/4/09) Mike Completed; 2 nd Quarter (6/309) Jack Completed; 3 rd Quarter (9/2/09) Dana Completed; 4 th Quarter (12/2/09) Fran
  3. Respond to capacity requests in 45 days or less. Angelini, 957 Cornwallis Drive 1 EDU - 14 days
  4. Implement I& I Plan – Currently on Schedule
  5. Conduct an annual facilities tour in June. Put on hold until after construction is complete

RIDLEY CREEK PROJECT

Monitor Construction – Excavation and steel complete for SBR slab. SBR panels are currently being poured by Dutchland. Slab poured, commenced excavation for lift station. Lift station installed, Valve Vault installed. SBR panels installed. Poles moved, SBR tank almost completed. Project Manager on board on 4/28. Screen Building under construction. Repairs being done on SBR Walls. Treatment Building under construction. SBR Wall Tank testing in progress. SBR and screen installed.

ACT 537 PLANNING

  1. Obtain Act 537 Plan approval for the Lockwood STP Abandonment Project – Board of Supervisors scheduled to adopt resolution on 2/17. BoS approved resolution on 3/3/09. Submitted to DEP on 3/5/09. Received 3/26/09 comment letter.
  2. Obtain Act 537 Plan approval for the Greenhill PS Redirection and the Reserve PS Abandonment Project Board of Supervisors scheduled to adopt resolution on 2/17. BoS approved resolution on 3/3/09. Submitted to DEP on 3/5/09. Received 3/27/09 comment letter
  3. Obtain Act 537 Plan approval for the Marydell PS Abandonment project. Met with DEP to review project on 2/5. Submitted Task Activity Report to DEP on 2/9/09. Task Activity report approved by DEP on 2/27/09
  4. Obtain Act 537 Plan approval for the Reservoir Road PS Diversion Project. Submitted 2007 Sewer Study to DEP on 2/9/09. Received 3/3/09 comment letter from DEP.

F:\Data\Shared Data\ABC'S\Municipal Authority\Goals\2009\111609.doc

2 of 2

FUNDING
Apply for funding for above projects once Act 537 approval has been obtained. Started preparation of a PA H2O grant for RCSTP. Applied for H2O Grant on 2/11/09. Awarded a grant for $464,195 on 7/14/09.

F:\Data\Shared Data\ABC'S\Municipal Authority\Goals\2009\111609.doc

12. NEW BUSINESS
3 pgs

AREA CODE 610
692-7171

EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

To:Municipal Authority
From:Mark Miller
RE:Carry Over at the Ridley Creek Plant and Hershey Mill Pump Station

As you know we have an agreement with the DEP that in the event of a carryover we must pay $1000.00 per occurrence.

The carryover happened on October 24, 2009, as we received over 2 ½ inches of rain in a very short period of time.

We had a carryover at the Ridley Creek Plant and also at the Hershey Mill Pump Station. Unfortunately I did not report the carryover until Monday morning. Since I did not call Saturday the DEP will be sending a notice of violation.

Enclosed are the DEP reports.

F:\Data\Shared Data\Public Works Dept\DEP Letters\Ltr. to Municipal Authority about carryover at two plants To.doc

Sanitary Sewer Overflow (SSO) Report to PADEP

2 of 3

1. Date, Name, Phone # of person completing this report Date: 10/26/2009
Name: Mark Miller
Phone #: 610-692-7171
2. Organization name and address? East Goshen Township 1580 Paoli Pike
West Chester, PA 19380
3. Date found and specific location of SSO? 10-24-2009
Hershey Mill Pump Station
Greenhill Road
4. How was SSO discovered? By who? Heavy Rain 2 plus inches in 45 minutes
Mark Miller, Public Works Department
5. Start and end time of SSO (actual or estimate?) 7:00 - 8:00 pm
6. Date, time and name of person who notified PADEP of SSO? Date: 10-26-2009
Time: 7:45 am
Name: Sue Smith
7. Description and actual or estimated volume of SSO Undetermined
8. Where, precisely, did SSO go? (land, roadway, basement, swale, storm sewer, creek, etc) Roadway / storm sewer
9. What caused SSO? How was it stopped? Deluge of rain
Pumps catching up.
10. Describe extent of contamination and how it was cleaned up It was washed away
11. What actions will be taken to prevent a re-occurrence? When? Look for INI, Starting today 10/26/2009 televising scheduled for November 3, 4, 5, 2009.
12. Other comments?

FAX 1-484-250-5971
3 of 3

Sanitary Sewer Overflow (SSO) Report to PADEP

1. Date, Name, Phone # of person completing this report Date: 26 October 2009
Name: Thomas M. Horrex
Phone #: 610-587-2826
2. Organization name and address? East Goshen Township
1580 Paoli Pike
West Chester, PA 19380
Ridley Creek WWTF
3. Date found and specific location of SSO? 26 October 2009
Overflow from 1st manhole back from WWTF wetwell
4. How was SSO discovered? By who? Overflow was found by visually inspecting manholes by Thomas M. Horrex (plant operator)
5. Start and end time of SSO (actual or estimate?) ESTIMATED it occured sometime late Saturday night or early Sunday morning after RAINFALL
6. Date, time and name of person who notified PADEP of SSO? Date: 26 October 2009
Time: 2:30 pm
Name: Thomas M. Horrex
7. Description and actual or estimated volume of SSO Raw sewage overflow of undetermined amount caused by the excessive RAINFALL (2.5") from the first manhole behind the treatment plant wetwell.
8. Where, precisely, did SSO go? (land, roadway, basement, swale, storm sewer, creek, etc) The sewage flowed into the field around the manhole.
9. What caused SSO? How was it stopped? Excessive RAINFALL (2.5") in a hour period that the collection system/wetwell could not handle.
10. Describe extent of contamination and how it was cleaned up There is very little evidence of overflow except for some solids/debris around the manhole. The township will clean up the effected Area and spread lime to help Neutralize the ground on 27 October 2009.
11. What actions will be taken to prevent a re-occurrence? When? Investigation of I & I and corrective actions (repairs) where necessary. Township has currently scheduled televising to begin in the near future.
12. Other comments? NA

12 NEW BUSINESS
5 pgs

MAILLIE, FALCONIERO & COMPANY, LLP

Certified Public Accountants and Business Counselors

www.maillie.com
PO Box 3068
West Chester, PA 19380-3068
610-696-4353
Fax: 610-430-8811

D. Scott Detar
George J. Falconero
John J. Crenny, Jr.
Frank L. Pellegrini
James M. Powers
Glenn B. Bachman
Raymond T. Mock
Robert L. Caruso
Edward J. Furman
Robert L. Boland
Robert M. Manero
Donald J. Pierce

October 23, 2009

Louis F. Smith, Township Manager
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380

We are pleased to confirm our understanding of the services we are to provide the East Goshen Municipal Authority for the year ended December 31, 2009. We will audit the financial statements of the East Goshen Municipal Authority as of and for the year ended December 31, 2009. Accounting standards generally accepted in the United States provide for certain required supplementary information (RSI), such as management's discussion and analysis (MD&A), to accompany the East Goshen Municipal Authority's basic financial statements. As part of our engagement, we will apply certain limited procedures to the East Goshen Municipal Authority's RSI. These limited procedures will consist principally of inquiries of management regarding the methods of measurement and presentation, which management is responsible for affirming to us in its representation letter. Unless we encounter problems with the presentation of the RSI or with procedures relating to it, we will disclaim an opinion on it. The following RSI is required by generally accepted accounting principles and will be subjected to certain limited procedures, but will not be audited:

  1. Management's Discussion and Analysis.

Audit Objective

The objective of our audit is the expression of an opinion as to whether your basic financial statements are fairly presented, in all material respects, in conformity with generally accepted accounting principles and to report on the fairness of the additional information referred to in the first paragraph when considered in relation to the basic financial statements taken as a whole. Our audit will be conducted in accordance with auditing standards generally accepted in the United States of America and will include tests of the accounting records and other procedures we consider necessary to enable us to express such an opinion. If our opinion on the financial statements is other than unqualified, we will fully discuss the reasons with you in advance. If, for any reason, we are unable to complete the audit or are unable to form or have not formed an opinion, we may decline to express an opinion or to issue a report as a result of this engagement.

Counselors to the Closely Held Business Since 1946

2 of 5

MAILLIE, FALCONIERO & COMPANY, LLP

Certified Public Accountants and Business Counselors

Louis F. Smith, Township Manager
East Goshen Municipal Authority
- 2 -
October 23, 2009

Management Responsibilities

Management is responsible for the basic financial statements and all accompanying information as well as all representations contained therein. You are also responsible for making all management decisions and performing all management functions; for designating an individual with suitable skill, knowledge, or experience to oversee our assistance with the preparation of your financial statements and related notes and any other nonattest services we provide; and for evaluating the adequacy and results of those services and accepting responsibility for them.

Management is responsible for establishing and maintaining effective internal controls, including monitoring ongoing activities; for the selection and application of accounting principles; and for the fair presentation in the financial statements of the financial position of the East Goshen Municipal Authority and the changes in net assets and cash flows, in conformity with U.S. generally accepted accounting principles.

Management is also responsible for making all financial records and related information available to us and for the accuracy and completeness of that information. Your responsibilities include adjusting the financial statements to correct material misstatements and confirming to us in the representation letter that the effects of any uncorrected misstatements aggregated by us during the current engagement and pertaining to the latest period presented are immaterial, both individually and in the aggregate, to the financial statements taken as a whole.

You are responsible for the design and implementation of programs and controls to prevent and detect fraud, and for informing us about all known or suspected fraud or illegal acts affecting the government involving (1) management, (2) employees who have significant roles in internal control and (3) others where the fraud or illegal acts could have a material effect on the financial statements. Your responsibilities include informing us of your knowledge of any allegations of fraud or suspected fraud affecting the government received in communications from employees, former employees, regulators, or others. In addition, you are responsible for identifying and ensuring that the entity complies with applicable laws and regulations.

With regard to the electronic dissemination of audited financial statements, including financial statements published electronically on your website, you understand that electronic sites are a means to distribute information, and, therefore, we are not required to read the information contained in these sites or to consider the consistency of other information in the electronic site with the original document.

3 of 5

MAILLIE, FALCONIERO & COMPANY, LLP

Certified Public Accountants and Business Counselors

Louis F. Smith, Township Manager
East Goshen Municipal Authority
- 3 -
October 23, 2009

Audit Procedures - General

An audit includes examining, on a test basis, evidence supporting the amounts and disclosures in the financial statements; therefore, our audit will involve judgment about the number of transactions to be examined and the areas to be tested. We will plan and perform the audit to obtain reasonable rather than absolute assurance about whether the financial statements are free of material misstatement, whether from (1) errors, (2) fraudulent financial reporting, (3) misappropriation of assets, or (4) violations of laws or governmental regulations that are attributable to the entity or to acts by management or employees acting on behalf of the entity.

Because an audit is designed to provide reasonable, but not absolute, assurance and because we will not perform a detailed examination of all transactions, there is a risk that material misstatements may exist and not be detected by us. In addition, an audit is not designed to detect immaterial misstatements or violations of laws or governmental regulations that do not have a direct and material effect on the financial statements. Our responsibility as auditors is limited to the period covered by our audit and does not extend to any later periods for which we are not engaged as auditors.

Our procedures will include tests of documentary evidence supporting the transactions recorded in the accounts, and may include tests of the physical existence of inventories, and direct confirmation of receivables and certain other assets and liabilities by correspondence with selected individuals, funding sources, creditors and financial institutions. We will request written representations from your attorneys as part of the engagement, and they may bill you for responding to this inquiry. At the conclusion of our audit, we will require certain written representations from you about the financial statements and related matters.

Audit Procedures - Internal Control

Our audit will include obtaining an understanding of the entity and its environment, including internal control, sufficient to assess the risks of material misstatement of the financial statements and to design the nature, timing and extent of further audit procedures. An audit is not designed to provide assurance on internal control or to identify deficiencies in internal control. However, during the audit, we will communicate to management and those charged with governance internal control related matters that are required to be communicated under AICPA professional standards.

4 of 5

MAILLIE, FALCONIERO & COMPANY, LLP

Certified Public Accountants and Business Counselors

Louis F. Smith, Township Manager
East Goshen Municipal Authority
- 4 -
October 23, 2009

Audit Procedures - Compliance

As part of obtaining reasonable assurance about whether the financial statements are free of material misstatement, we will perform tests of the East Goshen Municipal Authority's compliance with applicable laws and regulations and the provisions of contracts and agreements. However, the objective of our audit will not be to provide an opinion on overall compliance, and we will not express such an opinion.

Engagement Administration, Fees and Other

We understand that your employees will prepare all cash or other confirmations we request and will locate any documents selected by us for testing.

James E. Yiaski, CPA, is the engagement partner and is responsible for supervising the engagement and signing the report or authorizing another individual to sign it.

Our fee for these services will be at our standard hourly rates plus out-of-pocket costs (such as report reproduction, word processing, postage, travel, copies, telephone, etc.) Based on our experience with the 2008 audit and discussions concerning the Authority's 2009 activities, we estimate our fee will be approximately $6,900. The fee estimate is based on anticipated cooperation from your personnel and the assumption that unexpected circumstances will not be encountered during the audit. If significant additional time is necessary, we will discuss it with you and arrive at a new fee estimate before we incur the additional costs. Our standard hourly rates vary according to the degree of responsibility involved and the experience level of the personnel assigned to your audit. Our invoices for these fees will be rendered as work progresses and are payable on presentation. In accordance with our firm policies, work may be suspended if your account becomes 30 days or more overdue and may not be resumed until your account is paid in full. If we elect to terminate our services for nonpayment, our engagement will be deemed to have been completed upon written notification of termination, even if we have not completed our report. You will be obligated to compensate us for all time expended and to reimburse us for all out-of-pocket costs through the date of termination.

5 of 5

MAILLIE, FALCONIERO & COMPANY, LLP

Certified Public Accountants and Business Counselors

Louis F. Smith, Township Manager
East Goshen Municipal Authority
- 5 -
October 23, 2009

We appreciate the opportunity to be of service to the East Goshen Municipal Authority and believe this letter accurately summarizes the significant terms of our engagement. If you have any questions, please let us know. If you agree with the terms of our engagement as described in this letter, please sign the enclosed copy and return it to us.

Very truly yours,

MAILLIE, FALCONIERO & COMPANY, LLP

James E. Yiaski, CPA

RESPONSE:

This letter correctly sets forth the understanding of the East Goshen Municipal Authority.

By: ____________________________________

Title: ___________________________________

Date: ___________________________________

11/4/2009

12 NEW BUSINESS
2 pgs

EAST GOSHEN TOWNSHIP
MUNICIPAL AUTHORITY
PROJECTED 2009 AND BUDGET 2010 to 2012

BUDGET
2009
PROJ'T
2009
BUDGET
2010
BUDGET
2011
BUDGET
2012
BUDGET
2013
BUDGET
2014
COMMENTS
BEGINNING FUND BALANCE 10,729,427 10,729,427 3,170,052 (766,080) (2,236,361) (2,346,533) (2,456,635)
REVENUE
07341.1000 INTEREST EARNINGS 25,000 1,600 1,000 1,000 1,000 1,000 1,000 best guess
07341.1010 CAPITAL RESERVE - INTEREST 45,000 0 0 0 0 0 0
07341.1020 INTEREST EARNINGS_RCSTP EXPANSION 0 83,600 15,000 0 0 0 0 assume 1% for 6 months on 3.1 million
07364.1100 TAPPING FEES-CHESTER CREEK 10,000 0 6,000 6,000 6,000 6,000 6,000 3 houses per year
07364.1110 TAPPING FEES-RIDLEY CREEK 10,000 2,000 6,000 6,000 6,000 6,000 6,000 3 houses per year
07364.1130 SEWER CONNECTIN FEES - PINE ROCK 0 1,409 0
07380.1000 MISCELLANEOUS REVENUE 0 706 1,000 1,000 1,000 1,000 1,000
07392.0804 LOAN PROCEEDS 0 0 0 0 0 0
07392.0100 TRANSFER FROM GEN'L ACCT 0
07392.???? GRANTS 0 0 464,195 0 Assumes we receive in 2010
07392.0900 TRANSFER FROM SEWER CAP RESERVE 0 50,416
TOTAL REVENUE 10,819,427 10,869,158 3,663,247 (752,080) (2,224,361) (2,332,533) (2,442,635)
EXPENDITURES:
07424.1400 ADMINISTRATIVE WAGES 36,206 36,206 36,206 36,930 37,669 38,422 39,191
07471.1000 M.C.-DVRFA-PRINCIPAL 16,520 16,520 16,520 16,520 16,520 16,520 16,520 Assume +2%
07472.1000 M.C.-DVRFA-INTEREST 9,201 9,201 9,201 9,201 9,201 9,201 9,201
07471.1010 LOAN - PRINCIPAL 0 0 0 0 0 0
07472.1010 LOAN - INTEREST 0 0 0 0 0 0
07424.3110 AUDITING EXPENSE 8,500 8,500 8,500 8,670 8,843 9,020 9,201 Assume +2%
07424.3000 MISCELLANEOUS EXPENSE 4,000 25,897 4,000 4,080 4,162 4,245 4,330 Assume +2%
07424.3130 ENGINEERING SERVICES 32,000 20,000 32,000 32,640 33,293 33,959 34,638 Assume +2%
07424.3140 LEGAL SERVICES 25,000 12,000 12,000 12,240 12,485 12,734 12,989 Assume +2%
07424.7400 W.G. C.C.STP-UPGRADE 26,000 26,000 0 0 0 0 0
07242.7410 C.C. CAPITAL -METERS 0 0
07424.7420 C.C. CAPITAL-COLLECTION 130,000 91,023 0 0 0 0 0
07424.7430 C.C. CAPITAL-INTERCEPTOR 2,000 2,000 0 0 0 0 0
07424.7431 C.C. CAPITAL PROJ. ENGINEER. 0 1,243 0 0 0 0 0
07424.7440 R.C.-STP. CAPITAL EXPANS'N 9,300,000 0 0 0 0 0 0
07424.7450 R.C.-CAPITAL-COLLECTION 0 0 0 0 0 0 0
07424.7451 R.C.-CAPITAL PROJ. ENG. 100,000 200,000 0 0 0 0 0
07424.7452 R.C. CAPITAL EXPANSION - GENERAL CONTRACTOR 5,250,000 2,615,400
07424.7453 R.C. CAPITAL EXPANSION - ELECTRICAL CONTRACTOR 500,000 474,000
07424.7454 R.C. CAPITAL EXPANSION - CONTINGENCY CAPITAL 107,000
07424.7455 R.C. CAPITAL EXPANSION - CONTINGENCY ONGOING 8,000
07424.7470 LOCHWOOD-COLLECT.-CAP. 0 0 0 0 0 0
MARYDELL PUMP STATION - PROJECT ENGINEER 11,500 40,000 11,000
MARYDELL PUMP STATION - CONSTRUCTION 80,000 75,000
HERSHEY MILL PUMP STATION - PROJECT ENGINEER 10,350 14,500
HERSHEY MILL PUMP STATION - CONSTRUCTION 45,000

F:\Data\Shared Data\Finance Dept\Budget\2010\2010 MUNICIPAL AUTHORITY BUDGET 110309.xls 1]

11/4/2009

2 of 2

EAST GOSHEN TOWNSHIP
MUNICIPAL AUTHORITY
PROJECTED 2009 AND BUDGET 2010 to 2012

BUDGET
2009
PROJ'T
2009
BUDGET
2010
BUDGET
2011
BUDGET
2012
BUDGET
2013
BUDGET
2014
COMMENTS
RESERVE PUP STATION - PROJECT ENGINEER 15,350 32,000
RESERVE PUP STATION - CONSTRUCTION 130,000
07424.7475 LOCKWOOD ABANDONMENT - PROJECT ENGINEER 27,700 40,000 15,000
LOCKWOOD ABANDONMENT - CONSTRUCTION 165,000 175,000
RESERVOIR PUMP STATION = PROJECT ENGINEER 25,200 175,000 90,000
RESERVOIR ROAD PUMP STATION - CONSTRUCTION 500,000 1,000,000
07492.1000 TRANSFER TO GENERAL FUND 0 45,000
07492.1000 TRANSFER TO SEWER CAP RESERVE 1,200,000 1,250,416
07492.0550
07492.0500
07424.7495
TOTAL EXPENDITURES 10,889,427 7,699,106 4,429,327 1,486,281 122,172 124,101 126,069
NET SURPLUS/-DEFICIT (70,000) 3,170,052 (766,080) (2,238,361) (2,346,533) (2,456,635) (2,568,704)
ENDING FUND BALANCE (70,000) 3,170,052 (766,080) (2,238,361) (2,346,533) (2,456,635) (2,568,704)

F:\Data\Shared Data\Finance Dept\Budget\2010\2010 MUNICIPAL AUTHORITY BUDGET 110309.xls 2]

14. SEWER REPORT
a.
2 pgs

ARTESIAN RESOURCES

Artesian Water Company | Artesian Wastewater Management | Artesian Utility Development | Artesian Water Maryland
100 YEARS OF SUPERIOR SERVICE

October 27, 2009

Mr. Mark Miller, Director of Public Works
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380

RE: Lochwood Chase Wastewater Treatment Facility
August 2009 Operations Report

Dear Mr. Miller:

The following is the August 2009 monthly operations report for East Goshen Township's Lochwood Chase Wastewater Treatment Facility.

Treatment plant operations were normal during the month of August 2009. Routine inspections and equipment preventative maintenance were completed as required. The total amount of wastewater treated and discharged during the month was 412,800 gallons, which represents an average daily flow of 13,760 gallons per day.

The influent area operated normally during the month. The comminutor unit was in service continuously and no problems were experienced with the unit's controls. The plant operator continued to remove rags and debris from the housing, clear the bypass bar screen and shovel grit from the bottom of the pit on a regular basis. Debris and grit accumulations were disposed of via the trash can.

The aeration pond operated normally during the month. The pond's color remained brownish with some light surface scum and duckweed buildups. Both floating aerators continued to be operated in the automatic mode with two (2) OFF cycles per day to minimize noise complaints and over-aeration problems.

The polishing pond operated normally as well. The pond's color remained greenish due to algae growth with moderate amounts of surface duckweed buildups. The level continued to fluctuate with discharge spraying.

The chlorine contact tank and chlorine feed systems were operational throughout the month of August to meet disinfection requirements. Liquid chlorine continued to be added manually to the chlorine tank prior to each spray cycle to improve disinfection and minimize odor issues.

664 Churchmans Road, Newark, Delaware 19702, P.O. Box 15004 Wilmington, Delaware 19850 Phone: (302) 453-6900 Fax: (302) 453-6957
P.O. Box 177 Harbeson, Delaware 19951 Phone: (302) 684-2527 Fax: (302) 684-5164
28322 Lewes-Georgetown Hwy., Unit 4, Milton, DE 19968
e-mail: artesian@artesianwater.com Website: artesianwater.com

2 of 2

The discharge spray system was operational during the month of August. The #2 discharge pump was utilized in the hand position with spray fields No. 1 through No. 5 being opened manually to prevent backpressure on the pump. The plant operator inspected the sprayfields in use to ensure the sprayheads were in proper working order.

Results of influent and final effluent samples collected during the month indicate compliance with current permit limitations.

Should you have any questions, please do not hesitate to contact me.

Sincerely,
Artesian Utility Development, Inc.

Thomas M. Horrex / bmr
Thomas M. Horrex, L.O., S.E.O.
Pennsylvania Operations Supervisor

TMH/bmr

cc: Mr. Evan Andrews - Pennoni Associates
File

14. SEWER REPORTS
2. 5 pgs

RECEIVED
BY: ___________
OCT 28 2009

Pennoni

PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS

October 26, 2009

EGMA 0900

CERTIFIED MAIL/RETURN RECEIPT REQUESTED

Courtney Vanous
Sewage Planning Specialist I
Southeast Regional Office
2 East Main Street
Norristown, PA 19401
(484) 250-5900

RE: Response to DEP Comments on Chapter 94 Annual Report
Lochwood Chase Sewage Treatment Plant
East Goshen Township, Chester County

Dear Ms. Vanous:

East Goshen Township has received your letter of September 30, 2009 regarding the Township's Chapter 94 Annual Report. The following is a response to the comments contained in the letter.

Lochwood Chase Sewage Treatment Plant (LCSTP) Loading and Metering

The LCSTP is undergoing planning to be eliminated. Currently, the LCSTP conveyance system is serving 107 single family residences with no future connections anticipated. The loading from these residences is well below 100,000 gpd and therefore influent flow measuring, indicating, or recording devices are not required at the treatment plant.

Chapter 94 Report Checklist

Paragraph 94.12

Section (a)(1) The treatment plant has been serving the same 107 single family residences since approximately 1981 and there are no new connections contemplated for this service area. The LCSTP has a permitted hydraulic capacity of 0.0252 MGD. The flow into the LCSTP is not metered therefore a line graph depicting monthly average flows is not available. A temporary flow meter was installed for the period from April 15, 2007 to August 21 2007 and the average daily flow over this period was 0.0196 MGD. An average daily flow of 0.020 MGD (approximately 187 gpd per EDU) has been used for use in estimating loadings (both historic and projected).

One Drexel Plaza | 3001 Market Street | Philadelphia, PA 19104-2897 | Tel: 215-222-3000 | Fax: 215-222-3588
www.pennoni.com

2 of 5

EGMA0900
Courtney Vanous
October 26, 2009
Page 2
Chapter 94 Annual Report Comments

Section (a)(2) A line graph depicting monthly average organic loading (expressed in pounds per day of BOD5) for each month for the past 5 Years and projected for the next 5 years is attached. The loadings have been calculated using the recorded influent BOD5 at the LCSTP (one sample per month) and an average daily flow of 0.020 MGD as described in the previous response (Section (a)(1)).

The influent organic load design basis is not included in the DEP permits and is not known to the Township. The LCSTP is a spray irrigation facility and has not had difficulty achieving its treatment limits. The average monthly influent organic loading is approximately 49.7 ppd with a maximum observed load of approximately 162.8 ppd in May 2005 (believed to be due to an erroneous BOD5 sample result of 976 mg/L).

Section (a)(3) The LCSTP has been serving the same 107 single family residences since approximately 1981 and there are no new connections contemplated for this service area. An average daily flow of 0.020 MGD (approximately 187 gpd per EDU) has been used for use in estimating loadings (both historic and projected).

Section (a)(5) The Lochwood Chase STP is a spray irrigation facility and was permitted without an influent flow meter therefore calibration records are not available.

Section (a)(6) There are no flow meters on the Lochwood Chase sewer system. The Township will evaluate possible meter location(s) within the collection system as part of a Township-wide evaluation.

The Township has not experienced problems with the sewers in the Lochwood Chase development and rehabilitation or cleaning is currently not needed to maintain the integrity of the system and prevent or eliminate bypassing, sanitary sewer overflow, excessive infiltration, and other system problems.

Section (a)(7) There are no pump stations on the Lochwood Chase sewer system.

Paragraph 94.13

Section (b) There are no flow meters in the Lochwood Chase sewer system or at the head of the STP. Calibration Records are therefore not available.

We expect that the responses provided herein adequately address the PADEP comments contained in your September 30, 2009 letter.

G:\PROJECTS\EGMA\EGMA General Services 2009\Chapter 94 Report for 2009\EGMA0900 DEP Chapt 94 Response LCSTP.doc

3 of 5

EGMA0900
Courtney Vanous
October 26, 2009
Page 3
Chapter 94 Annual Report Comments

Should you have any questions please feel free to contact me at (215) 222-3000, extension 3345.

Very truly yours,

PENNONI ASSOCIATES INC.

Evan R. Andrews, P.E.
Authority Engineer

Attachments

cc: Rick Smith (East Goshen Township)

G:\PROJECTS\EGMA\EGMA General Services 2009\Chapter 94 Report for 2009\EGMA0900 DEP Chapt 94 Response LCSTP.doc

4 of 5

East Goshen Municipal Authority
Lochwood Chase STP

Influent Organic Concentration (mg/L)

Month 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
January 203 193 No Data 336 288 255 255 255 255 255
February 367 214 193 193 193 232 232 232 232 232
March 163 284 164 371 204 237 237 237 237 237
April 174 371 572 225 353 339 339 339 339 339
May 272 976 245 357 331 436 436 436 436 436
June 700 99 181 288 315 317 317 317 317 317
July 172 172 402 356 525 325 325 325 325 325
August 252 276 152 189 152 204 204 204 204 204
September 386 144 200 201 255 237 237 237 237 237
October 260 94 414 No Data 376 286 286 286 286 286
November 182 329 260 885 225 376 376 376 376 376
December 503 383 330 159 239 323 323 323 323 323
Average Annual (mg/l) 303 295 283 324 288 297 297 297 297 297

Influent Organic Load (pounds per day)

Month 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
January 33.9 32.2 No Data 56.0 48.0 42.5 42.5 42.5 42.5 42.5
February 61.2 35.7 32.2 32.2 32.2 38.7 38.7 38.7 38.7 38.7
March 27.2 47.4 27.4 61.9 34.0 39.6 39.6 39.6 39.6 39.6
April 29.0 61.9 95.4 37.5 58.9 56.5 56.5 56.5 56.5 56.5
May 45.4 162.8 40.9 59.5 55.2 72.8 72.8 72.8 72.8 72.8
June 116.8 16.5 30.2 48.0 52.5 52.8 52.8 52.8 52.8 52.8
July 28.7 28.7 67.1 59.4 87.6 54.3 54.3 54.3 54.3 54.3
August 42.0 46.0 25.4 31.5 25.4 34.1 34.1 34.1 34.1 34.1
September 64.4 24.0 33.4 33.5 42.5 39.6 39.6 39.6 39.6 39.6
October 43.4 15.7 69.1 No Data 62.7 47.7 47.7 47.7 47.7 47.7
November 30.4 54.9 43.4 147.6 37.5 62.8 62.8 62.8 62.8 62.8
December 83.9 63.9 55.0 26.5 39.9 53.8 53.8 53.8 53.8 53.8
Average Annual (ppd) 50.5 49.1 47.2 54.0 48.0 49.6 49.6 49.6 49.6 49.6

! Use annual average daily flow = 0.020 MGD
LCSTP 94 Report for 2008 (Updated)

5 of 5

Lochwood Chase STP Organic Load

Y-Axis (Pounds per Day): 0.0, 20.0, 40.0, 60.0, 80.0, 100.0, 120.0, 140.0, 160.0, 180.0

X-Axis: Jan-04, May-04, Sep-04, Jan-05, May-05, Sep-05, Jan-06, May-06, Sep-06, Jan-07, May-07, Sep-07, Jan-08, May-08, Sep-08, Jan-09, May-09, Sep-09, Jan-10, May-10, Sep-10, Jan-11, May-11, Sep-11, Jan-12, May-12, Sep-12, Jan-13, May-13, Sep-13

LCSTP 94 Report for 2008 (Updated)
Organic Chart

14. SEWER REPORTS
b.
8 pgs

AREA CODE 610 692-7171

EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP

1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

November 4, 2009

To: Municipal Authority
From: Mark Miller
Re: October 2009 Monthly Report

Meter: Meters have been read on a daily basis. We have installed the portable flow meters per Evans request.

C.C. Collection: We have been televising the collection lines in Mill Valley; we also have been televising the collection lines in the Reserve development.

During the heavy rainfall on October 24 we had numerous problems as each pump stations suffered excessive In Flow. The Hershey Mill Pump Station overflowed. The overflow was reported to the DEP on Monday morning.

We experienced problems at three other Stations; however they did not carry over.

R.C. Collection: We did not have any problems with the Hunt Country Pump Station.

Lochwood Plant: No problems to report.

Ridley Creek Plant: Routine maintenance was performed. We will be replacing the belts on the belt filter press.

Alarms: 27 alarms for the month of October.

PA One Calls: 120 PA One Call's for the month of October.

f:\data\shared data\public works dept\monthly reports\2009 municipal\2009 municipal authority oct. report doc.doc

2 of 8

2008 FLOWMETERS

2009 OCTOBER 4TH QUARTER

PrecipDATEWESTTOWN WAY READINGWESTTOWN WAY GPDELLIS LANE READINGELLIS LANE GPDPAOLI PIKE READINGPAOLI PIKE GPDWILSON DRIVE READINGWILSON DRIVE GPDSUMMIT GPDNET FLOWSDATE
0.0010/01/091,327,9731,212,00010,693,07192,6205,939,86132,2407,354,023105,06020,400982,08010/01/09
0.0010/02/091,329,0641,091,00010,701,65485,8305,942,82229,6107,362,74087,17020,400888,39010/02/09
0.2010/03/0920,400010/03/09
0.0010/04/0920,400010/04/09
0.0010/05/091,332,3451,093,66710,729,85494,0005,952,29631,5807,380,94360,67720,400907,41010/05/09
0.0410/06/091,333,5351,190,00010,739,998101,4405,956,55142,5507,391,020100,77020,400945,24010/06/09
0.0010/07/091,334,6231,088,00010,748,01980,2105,961,08645,3507,398,39073,70020,400888,74010/07/09
0.0010/08/091,335,7231,100,00010,756,86288,4305,966,52154,3507,407,34289,52020,400867,70010/08/09
0.0010/09/091,336,8201,097,00010,765,64887,8605,972,13356,1207,416,80694,64020,400858,38010/09/09
0.2010/10/0920,400010/10/09
0.0010/11/0920,400010/11/09
0.0010/12/091,340,0291,069,66710,792,94590,9905,991,48964,5207,440,99380,62320,400833,53310/12/09
0.0010/13/091,341,1601,131,00010,801,43984,9405,997,65561,6607,451,490104,97020,400879,43010/13/09
0.0010/14/091,342,2561,096,00010,809,75683,1706,005,33076,7507,461,922104,32020,400831,76010/14/09
0.8510/15/091,343,3601,104,00010,818,02582,6906,013,19178,6107,472,451105,29020,400837,41010/15/09
1.0010/16/091,344,6311,271,00010,829,127111,0206,022,19990,0807,483,149106,98020,400962,92010/16/09
0.7510/17/0920,400010/17/09
0.5010/18/0920,400010/18/09
0.0010/19/091,349,0131,460,66710,872,557144,7676,048,49187,6407,508,33083,93720,4001,144,32310/19/09
0.0010/20/091,350,2731,260,00010,883,231106,7406,056,23677,4507,518,709103,79020,400972,02010/20/09
0.0010/21/091,351,5071,234,00010,893,16699,3506,064,14379,0707,528,63499,25020,400956,33010/21/09
0.0010/22/091,352,6401,133,00010,902,56994,0306,072,50683,6307,537,82191,87020,400863,47010/22/09
0.2010/23/091,353,8091,169,00010,911,89793,2806,079,81373,0707,547,45096,29020,400906,36010/23/09
2.5010/24/0920,400010/24/09
0.0010/25/0920,400010/25/09
0.1310/26/091,358,1161,435,66710,952,913136,7206,101,18271,2307,569,40973,19720,4001,154,52010/26/09
1.5410/27/091,359,3941,278,00010,963,854109,4106,107,08459,0207,578,25088,41020,4001,021,16010/27/09
0.2210/28/091,361,2101,816,00010,982,922190,6806,114,93078,4607,589,466112,16020,4001,434,70010/28/09
0.0010/29/091,363,0691,859,00011,001,461185,3906,122,84779,1707,599,616101,50020,4001,492,94010/29/09
0.6010/30/091,364,4881,419,00011,014,599131,3806,131,35585,0807,609,02494,08020,4001,108,46010/30/09
0.1210/31/0920,400010/31/09
9.211,254,894107,95265,32993,555988,058
DAILY LOCINQUIREREG TWP
MONTH TO DATE9.21
NORMAL MONTH TO DATE
YEAR TO DATE58
NORMAL YEAR TO DATE

2007 flowmeters -all-stations separate month worksheets.xls

3 of 8

2008 FLOWMETERS

2009 OCTOBER 4TH QUARTER

HERSHEY'S MILL READINGHERSHEY'S MILL GPDASHBRIDGE READINGASHBRIDGE GPDHICKS METER READINGHICKS METER GPDRESERVOIR READINGRESERVOIR GPDSHERMAN READINGSHERMAN GPDBARKWAY READINGBARKWAY GPD
17,052,88857,170589,04172,5001,044,472342,00075,438,012727,530225,3605,4001,208,90912,030
17,058,23953,510589,67263,1001,074,868303,96075,505,705676,930225,9215,6101,210,00410,950
17,077,54864,363591,71768,1671,153,288261,40075,702,709656,680227,4885,2231,213,82912,750
17,082,73051,820001,192,825395,37075,781,419787,100228,1546,6601,215,35515,260
17,086,64139,110001,219,887270,62075,847,164657,450228,5203,6601,216,1758,200
17,092,10654,650593,65264,5001,252,679327,92075,919,171720,070228,9844,6401,217,18410,090
17,097,78356,770594,26661,4001,284,885322,06075,989,951707,800229,5936,0901,218,37211,880
17,115,54459,203596,20764,7001,363,329261,48076,187,741659,300231,4676,2471,221,99312,070
17,121,29757,530596,83062,3001,396,664333,35076,259,830720,890231,9945,2701,223,19612,030
17,126,89555,980597,45062,0001,428,746320,82076,329,310694,800232,5895,9501,224,29911,030
17,132,37854,830598,06261,2001,462,091333,45076,399,863705,530233,1855,9601,225,45611,570
17,138,37559,970598,79273,0001,497,601355,10076,479,395795,320233,9407,5501,226,60211,460
17,158,79468,063601,868102,5331,597,013331,37376,740,523870,427235,7065,8871,230,61713,383
17,164,89260,980602,70183,3001,632,839358,26076,820,164796,410236,2855,7901,231,73911,220
17,170,91960,270603,50380,2001,666,620337,81076,898,226780,620236,8035,1801,232,83510,960
17,176,50955,900604,20470,1001,700,169335,49076,970,925726,990237,2994,9601,234,01611,810
17,182,36058,510604,89969,5001,734,482343,13077,046,370754,450237,8145,1501,235,12311,070
17,206,18879,427607,989103,0001,836,234339,17377,304,316859,820239,5265,7071,239,77515,507
17,212,66364,750608,82183,2001,871,692354,58077,384,849805,330239,9874,6101,240,86310,880
17,220,72380,600610,292147,1001,915,745440,53077,496,0411,111,920240,6286,4101,242,30714,440
17,228,69979,760611,720142,8001,960,204444,59077,607,6181,115,770241,0854,5701,243,66913,620
17,236,38576,860612,807108,7001,996,160359,56077,695,730881,120241,6095,2401,244,80411,350
61,36574,695339,638782,3755,53511,980

2007 flowmeters -all-stations separate month worksheets.xls

4 of 8

2009 SUMMARY OF METER READINGS

Month WESTTOWN WAY ELLIS LANE PAOLI PIKE WILSON DRIVE SUMMIT HERSHEY MILL ASHBRIDGE HICKS RESERVOIR SHERMAN BARKWAY
JANUARY 1,277,483 95,426 42,394 63,547 20,400 65,016 67,836 307,570 763,687 6,386 12,279
FEBRUARY 1,211,464 87,515 41,270 60,703 20,400 63,382 62,862 292,756 721,327 5,850 11,963
MARCH 1,152,893 82,510 38,294 56,906 20,400 55,330 61,242 300,092 672,897 5,534 11,410
APRIL 1,273,653 106,236 39,685 58,079 20,400 59,615 77,712 314,679 744,604 6,096 11,541
MAY 1,304,080 106,881 64,480 65,970 20,400 65,744 83,088 343,439 792,633 5,869 11,521
JUNE 1,320,702 112,744 60,869 78,465 20,400 63,152 87,581 341,020 807,211 6,010 11,736
JULY 1,145,310 92,563 64,786 70,508 20,400 57,932 64,481 314,779 706,552 5,990 10,873
AUGUST 1,205,548 104,700 47,158 99,749 20,400 64,338 76,794 722,167 722,167 5,474 10,664
SEPTEMBER 1,145,397 97,724 37,981 79,651 20,400 58,006 72,494 315,816 717,067 5,708 11,321
OCTOBER 1,254,894 107,952 65,329 93,555 204,000 61,365 74,695 339,638 782,375 5,535 11,980
NOVEMBER
DECEMBER
Total Flows
Monthly Ave 1,229,142 99,425 50,225 72,713 38,760 61,388 72,879 359,196 743,052 5,845 11,529

To
West Goshen: 1,006,779

2009 flowmeters -all-stations separate month worksheets.xlsSUMMARY

5 of 8

Flowmeters October 2009

Legend: October

Y-Axis (Flow#s): 0, 200000, 400000, 600000, 800000, 1000000, 1200000, 1400000, 1600000

X-Axis (Day): 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31

6 of 8

Monthly Totals 2009 Jan-Dec

Y-Axis (Flowmeters): 0, 200000, 400000, 600000, 800000, 1000000, 1200000, 1400000, 1600000, 1800000

X-Axis (Month): January, February, March, April, May, June, July, August, September, October, November, December

October Precip. 9.21 - 2009

[Bar chart showing precipitation for October 2009. Y-axis: 0 to 10 with increments of 1. X-axis: 1 to 34. Legend: October.]

60

8 of 8

Monthly Totals 2009 (Jan-Dec)

Legend: Monthly Totals

Y-Axis (Precip.): 0, 1, 2, 3, 4, 5, 6, 7, 8, 9, 10

X-Axis (Month): 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12

CHAR

CAPITOL HILL AUTHORITY REPORT

GOVERNMENT RELATIONS NEWSLETTER

PMAA - Pennsylvania Municipal Authorities Association [FYI stamp]

1000 North Front Street, Suite 401 • Wormleysburg, PA 17043 • 717-737-7655 / 737-8431 (Fax) • www.municipalauthorities.org

Vol. 50 No. 3 | October 21, 2009

[Received Oct 23 2009]

Skinny Budget 101 Days Late

On Friday, October 9, 2009 Governor Rendell signed the state budget presented to him by the legislature, a record 101 days late. The “summer of pain” for many organizations and people ended with a $27.8 billion spending plan. This figure is $524 million less than last year’s budget, a reduction of 1.8%. However, this reduction does not reflect much bigger reductions that certain agencies are seeing.

DEP took a 27% cut in their annual budget which was reduced by $58 million. They lost $3.5 million under general government operations and $13.5 million in environmental protection operations. These cuts will affect both programs and personnel and it is expected that DEP will be forced to furlough several hundred people. Many of those jobs will be cut in the regional offices potentially depleting the number of permit writers and inspectors. Act 537 planning grants lost $843,000 (a 45% reduction) and enforcement grants lost $1.9 million (40% reduction). The Safe Water Fund, sewer and water grants through legislative initiatives, was zeroed out, a loss of $11 million. The $2 million Storm Water Management fund was also zeroed out.

Other agencies taking big hits were: DCNR, a 19% reduction that included $9.3 million in cuts to state parks and a 50% cut to spraying for black flies and gypsy moths, and DCED, a 53% reduction which severely slashed many of their grant and loan programs.

Revenue sources included the Rainy Day Fund ($755 million-now exhausted), transfers from the Tobacco Fund, Health Care Provider Retention Fund, and Medical Care Fund, increased taxes on cigarettes and business assets, and the allowance (and taxing) of table games at casinos. There was no tax established on withdrawal of natural gas from Marcellus Shale drilling although more state owned lands were authorized for gas drilling leases.

The new Fiscal Code bill (HB 1614), includes amendatory language that allows the state to float bonds tied to last year’s infrastructure funding bills, Act 63 and Act 64. These bills provided the $800 million to the Commonwealth Financing Authority (CFA) and the $400 million to PENNVEST. The fiscal bill also contains a section prohibiting lobbying firms from receiving payments that are contingent on securing future H2O-PA grants for their clients through CFA funding.

DEP Proposed Regulation on Total Dissolved Solids

DEP has proposed a new regulation that deals with Total Dissolved Solids (TDS) in wastewater effluent. You may be aware this issue has arisen in the last year mostly due to high TDS in Pennsylvania waterways that was suspected of coming from “treated” Marcellus Shale frac (brine) water and/or abandoned mine drainage discharges.

In an effort to deal with this, DEP developed a proposed regulation that could impose discharge limits on TDS in many wastewater treatment plants, whether or not they treat frac water from drilling opertions. This has cast a wide net over many sewage treatment plants who do not take the frac wastewater but may have elevated TDS levels due to the residential, commercial and industrial waste they currently treat. Their TDS levels were never a discharge issue until the recent proposal from DEP. Sewage plants may be impacted by these new standards because DEP has focused on all dischargers instead of those who are treating frac water (solely, or as part of the flow incorporated at a sewage treatment plant).

New or increased municipal discharges with high TDS levels under the proposed regulation (2,000 mg/l TDS or over 100,000 lbs/day) may need to do pretreatment or other costly advanced treatment. PMAA is participating in a Stakeholder Group convened by the Water Resources Advisory Committee and DEP to address concerns over this issue. DEP plans to hold five public hearings across the state on this proposal during the week of 12/7/09. Please contact Pete Slack of PMAA (slack@municipalauthorities.org) with any issues or other information. The link to the proposed regulation from DEP is on PMAA’s website at www.municipalauthorities.org, select Government Relations across the top, select Regulations in the drop-down box, then select “regulation” in the first paragraph.

DEP Publishes Final Technical Guidance Documents for Public Notification

Amendments to DEP’s drinking water regulations (25 PA Code, Ch 109) relating to public notification (PN) were published in final-form in the May 9, 2009 PA Bulletin. The changes were made to strengthen the public notice requirements for imminent threat violations and situations (also known as Tier 1).

To accompany these changes, DEP recently published two final technical guidance documents dealing with PN. A short summary follows:

Policy for Determining When Loss of Positive Pressure DEP ID: 383-2129-004.

Description: The Pennsylvania Safe Drinking Water Regulations (Chapter 109) require public water suppliers to report to the Department within 1 hour when they experience a situation that causes a loss of positive water pressure in any portion of the distribution system where there is evidence of contamination or a water supplier suspects a high risk of contamination. Additionally, this situation may require water suppliers to issue a Tier 1 public notification. The guidance document provides uniform instructions and protocol for responding to loss of positive pressure situations in the distribution system to ensure the protection of public health. The effective date is October 3, 2009.

A 30-day comment period was provided which concluded on March 23, 2009. Comments on the draft guidance document were received from 8 commentators. Based on the comments received, the Department revised the guidance to expand the examples of evidence of contamination and include wavier criteria to avoid bacteriological sampling. For questions contact Lisa Daniels at (717) 772-4046 or ldaniels@state.pa.us.

Policy for Issuing and Removing Water Supply Warnings DEP ID: 383-2129-005.

Description: The Pennsylvania Safe Drinking Water Regulations (Chapter 109) require public water suppliers to issue public notifications that include water supply warnings during imminent threat situations (also known as Tier 1 violations or situations). The guidance document provides instructions for issuing and removing water supply warnings and includes the following topics: Tier 1 violations and situations, a drinking water standards and health advisory table, drinking water treatment chemicals and associated health effects, and types of water supply warnings. The effective date is October 3, 2009.

A 30-day comment period was provided which concluded on March 23, 2009. Based on comments, changes were made including: deletion of the text regarding examples of loss of positive pressure situations, provided additional explanation for what water suppliers are required to do when a contaminant exceeds a health advisory level, and provided more information under the “Do Not Drink” and “Do Not Use” notice section. For questions contact Deborah Rotz at (717) 772-2190 or drotz@state.pa.us.

Both guidance documents can be found at www.depweb.state.pa.us, select Water Topics, then Drinking Water.

610-692-7171 | FYI | www.eastgoshen.org

BOARD OF SUPERVISORS
EAST GOSHEN TOWNSHIP
CHESTER COUNTY
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

November 2, 2009

Re: Vehicle operation within Township openspace areas

Dear property owner,

It has been brought to the Township's attention that All Terrain Vehicles (ATV's) are being operated within the Bowtree / Clocktower openspace areas. The operation of vehicles within township parks and openspace areas is prohibited pursuant to §163 of the East Goshen Township Code.

§163-3 Rules and Regulations
Vehicular restrictions. Parking or driving on park property is prohibited except in authorized areas. Unregistered vehicles of any kind are not allowed within park grounds without special permission from the Park and Recreation Commission or for township maintenance, police, fire or other necessary activity.

All properties which abut the openspace are being notified of this violation. If anyone should observe this activity I urge you to call the Westtown East Goshen Police Department immediately.

Sincerely,

Mark A. Gordon
Township Zoning Officer

CC: Chief John Dumond, Westtown East Goshen Police

F:\Data\Shared Data\Code Dept\ATV Riding in Openspace\102909.doc

610-692-7171 | FYI | www.eastgoshen.org

BOARD OF SUPERVISORS
EAST GOSHEN TOWNSHIP
CHESTER COUNTY
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

November 2, 2009

Re: Vehicle operation within Township openspace areas

Dear property owner,

It has been brought to the Township's attention that All Terrain Vehicles (ATV's) are being operated within the Supplee Valley openspace areas. The operation of vehicles within township parks and openspace areas is prohibited pursuant to §163 of the East Goshen Township Code.

§163-3 Rules and Regulations
I. Vehicular restrictions. Parking or driving on park property is prohibited except in authorized areas. Unregistered vehicles of any kind are not allowed within park grounds without special permission from the Park Board except those vehicles used in the course of park maintenance or other necessary activity.

All properties which abut the openspace are being notified of this violation. If anyone should observe this activity I urge you to call the Westtown East Goshen Police Department immediately.

Sincerely,

[Signature: Mark A. Gordon]

Mark A. Gordon
Township Zoning Officer

CC: Chief John Dumond, Westtown East Goshen Police

F:\Data\Shared Data\Code Dept\ATV Riding in Openspace_Supplee 110209.doc

610-692-7171 | www.eastgoshen.org

BOARD OF SUPERVISORS
EAST GOSHEN TOWNSHIP
CHESTER COUNTY
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

October 27, 2009

Dear Property Owner:

The purpose of this letter is to inform you that mark and Helen McGinley, 77 Dilworthtown Rd., Thornton, PA 19373, have submitted an application for a variance to the Township. The applicant would like to construct a single-family detached dwelling unit on his property at 19 School Lane.

The applicant is requesting a variance from the 20-foot minimum side yard requirement for the dwelling. The existing lot is only 50 feet wide so the variance, if granted would result in only a fifteen foot side yards.

The Zoning Hearing Board will hold a public hearing to consider the variance application and decide whether or not to grant the requested variance.

The Planning Commission will review the application and make a recommendation to the Zoning Hearing Board. The Board of Supervisors may, if they choose, take a position on this application. The public meetings for the project's review and potential approval are as follows:

November 4, 2009 Planning Commission meeting (7:30 pm - workshop at 7:00 pm)
November 17, 2009 Board of Supervisors (8:00 pm - workshop at 7:00 pm)
November 18, 2009 Zoning Hearing Board Public Hearing (7:30 pm)

All public hearings, meetings, and workshops are open to the public and they are held at the Township Building, 1580 Paoli Pike. The application is available for review at the Township Building during normal business hours. Any person who wishes to attend the hearing and has a disability and/or requires an auxiliary aid, service or other accommodation to observe or participate in the hearing, he or she should contact Joyce A. Tarsi at (610) 692-7171 to discuss how those needs may be accommodated.

Should you have any questions or need additional information, please call me at (610) 692-7171, or email me at mgordon@eastgoshen.org.

Sincerely,

[Signature: Mark Gordon]

Mark Gordon
Township Zoning Officer

Cc: Mark and Helen McGinley
Authority, Boards and Commissions

F:\Data\Shared Data\Property Management\53-6g\53-6g-23 19 School Lane\Variance 2009\1000 foot letter 102709.doc