Municipal Authority
The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.
The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.
- Five members, serving five-year terms
- Meetings are on the 2nd Monday of the month at 7:00 P.M.
- All township meetings are held at the Township Building and open to the public
| Authority Members | Term Expiration Date |
| Kevin Cummings, Chairman | 2026 |
| John Stipe, Vice Chairman |
2029 |
| Dana Pizzarro, Secretary | 2026 |
| Sean Ellsworth, Assistant Secretary/Treasurer | 2028 |
| Walter Wujcik, Treasurer | 2028 |
| Pennoni Associates, Engineer | |
| Patrick M. McKenna, Esq. | |
| Peter Hicks, BoS Liaison | |
| Kevin Miller, Staff Liaison |
Documents
Back to the list | Open the original PDF
Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.
EAST GOSHEN MUNICIPAL AUTHORITY
March 9, 2015
- CALL TO ORDER/PLEDGE OF ALLEGIANCE/MOMENT OF SILENCE Ask if anyone will be taping the meeting?
- CHAIRMAN’S REPORT/OTHER MEMBERS REPORTS
- SEWER REPORTS Director of Public Works Report; Pennoni Engineer’s Report; Big Fish Environmental Inc. Report with DMR’s; East Goshen Township Flows
- APPROVAL OF MINUTES February 9, 2015
- APPROVAL OF INVOICES Item Vendor Invoice Number Amount a. Pennoni Invoice #626537 $1,306.25 b. Pennoni Invoice #626538 $4,378.75 c. Pennoni Invoice #626539 $10,394.70 d. Gawthrop Invoice #128180 $ 300.00
- LIAISON REPORTS
- FINANCIAL REPORTS January 2015 Report
- OLD BUSINESS
- GOALS Submit an article for each newsletter – Due date for newsletter Need by 1/30/15 – Jack - Completed Need by 5/1/15 Need by 8/31/15 Need by 10/30/15; Obtain construction permits for the Reservoir Road Pump Station – December 31, 2015 2/6 – Test boring done, meeting with Mike to review preliminary site plan and discuss control options.
F:\Data\Shared Data\Agendas\Municipal Authority\2015\3-9-15.doc
- Attend West Goshen Meetings quarterly – more often if needed. 1 st Quarter – Jack - Completed 2 nd Quarter 3 rd Quarter 4 th Quarter
- Respond to capacity requests in 45 days or less.
- Continue to implement I & I Plan
- Operate RCSTP in compliance with NPDES Permit
- NEW BUSINESS Review two quotes from Lenni Electric for two surge protectors at Ridley Creek; Reservoir Road Pump Station – review progress prints (Mike will bring to meeting); Consider proposal for Phase 2 (Mike will bring to meeting)
- CAPACITY REQUESTS
- ANY OTHER MATTER
- CORRESPONDENCE AND REPORTS OF INTEREST
- PUBLIC COMMENT
- ADJOURNMENT
F:\Data\Shared Data\Agendas\Municipal Authority\2015\3-9-15.doc
AREA CODE 610
692-7171
EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199
March 4, 2015
To: Municipal Authority
From: Mark Miller
Re: February 2015 Monthly Report
Due to the weather a majority of our time was spent on equipment repairs and road repairs.
Meters: All meters were read on a daily basis.
C.C. Collection: We could not do any televising due to the cold temperatures
R.C. Collection: Pump Stations were visited on a daily basis with no problems to report.
R.C. Plant: No problems to report.
Alarms: We responded to 19 alarms for February.
PA One Calls: We received 51 PA One calls since February.
EGMA 1501
[Logo: Pennoni]
MEMORANDUM
TO: East Goshen Municipal Authority Board
Rick Smith, Township Manager
FROM: Michael Ellis, P.E.
Authority Engineer
DATE: March 5, 2015
SUBJECT: Engineer’s Report
Invoices
- Invoices with summaries are provided under separate cover.
Reservoir Road Pump Station
- The geotechnical report and boring logs were submitted to the Township.
- We prepared a 3 rd draft/revision of the concept design consisting of: a pump station site sketch plan including conceptual diversion details and diversion piping profiles, a written outline of pump station controls and critical features, and a ballpark construction cost estimate. During further concept evaluation and vendor coordination, it was determined that suction-lift pumps on the building floor are not feasible because the maximum suction head of the available pumps is exceeded. Options were discussed with Township staff, and it was decided to proceed with submersible pumps in the wet well. This concept will be presented in more detail at the March 9 th Municipal Authority meeting.
- A Water Quality Management Permit pre-application meeting with PADEP is scheduled for March 13 th at 10:00 am and will be attended by Pennoni Associates and Township staff.
- The existing conditions field survey work began on February 24 th . We completed topography on the Bow Tree pond lot and across the Ridley Creek to the existing sewer interceptor, and we have begun to survey the Bow Tree Drive cartway. We anticipate another 7-8 days to complete the field topography and property boundary work. An exact schedule is not yet known due to snow cover.
Chapter 94 Reports
- We continued work on the 2014 Chapter 94 Reports. We anticipate submitting drafts of the reports to the Township for review around March 16 th .
Page 1 of 2
P:\Projects\EGMA\Memos to Board\2015\Memo to EGMA Board 2015-03-05.docx
EGMA 1501
Lockwood Chase STP Closure NPDES Permit N.O.T.
- Once the snow melts and ground dries out, we will perform a site visit to the former LCSTP site to evaluate the consistency of as-built conditions with the permit plans, so that the NPDES Permit Notice of Termination paperwork can be finalized and submitted to the Chester County Conservation District.
Hershey’s Mill PS and Marydell PS Diversions
- The 2-year Maintenance Bonds on the Hershey’s Mill PS and Marydell PS Diversions expire on July and August respectively. We recommend warranty inspections be performed by May.
Hershey’s Mill PS Muffin Monster
- We notified PADEP that the comminutor has been installed in the pump station for their field evaluation as required by the permit.
Page 2 of 2
P:\Projects\EGMA\Memos to Board\2015\Memo to EGMA Board 2015-03-05.docx
[Logo: Big Fish Environmental Services Inc.]
Monthly Operations Report: February 2015
Executive Summary
The Ridley Creek sewage treatment plant outfall 001 reported a weekly maximum TSS exceedance of 16 mg/L, as compared to the permit limitation of 15 mg/L on January 28, 2015. There was no discharge to Applebrook, which is identified as outfall 002. Chemical usage utilized for total phosphorus removal, pH and total alkalinity remained consistent with previous months. No mechanical or operational issues were observed during operation of the wastewater treatment process and sludge dewatering equipment. Routine preventative maintenance activities were completed.
Treatment Process Operation
During January 2015, there was one (1) exceedance reported for the weekly maximum for TSS of the final effluent discharge limitations for outfall 001. The monthly average TSS was reported as 8 mg/L, with a range of 4 mg/L to 16 mg/L. The TSS concentration of 16 mg/L is believed to be a laboratory error with a 10% range of error. On site analysis of a split sample was measured as 10.2 mg/L. When the laboratory provided initial notice that the TSS concentration exceeded the warning limit of 10 mg/L, the laboratory was instructed to perform a rests of the TSS test. Unfortunately, the laboratory analyzes a liter of sample in order to report the method detection concentration as 2 mg/L rather than 5 mg/L. As a result, insufficient sample volume was available to retest the sample. In addition, notification of the TSS concentration was provide the following week, eliminating the possibility to collect a second sample. Corrective actions included instructing the laboratory to collect two liters of sample for the TSS tests and collecting a second TSS sample when the in-house test result indicate a sample concentration greater than 10 mg/L.
The total phosphorus monthly average concentration was reported as 0.20 mg/L as compared to the permitted limitation of 0.50 mg/L. Final effluent total phosphorus concentration discharged ranged from 0.10 mg/L to 0.27 mg/L. The aluminum sulfate daily average remained consistent during January at 76.6 gpd as compared to the previous month at 74.0 gpd. Table 1 illustrates the final effluent composite sample data reported for the January 2015 eDMR.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 1 of 6
[Logo: Big Fish Environmental Services Inc.]
Table 1
January 2015 - Final Effluent - Out Fall 001
| NPDES Permit Discharge Limitations |
Flow | CBOD5 | TSS | NH4-N | Phosphorus,Total , mg/L | Fecal Coliform | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/ month | mg/L | lbs/ month | mg/L | lbs/ month | mg/L | lbs/ month | Geo Mean | Geo Mean | |
| 200 | 1,000 | ||||||||||
| 0.75 | 20 | 125 | 21 | 131 | 7 | 44 | 0.5 | 3 | |||
| Instantaneous Maximum | 40 | 42 | |||||||||
| Sample Date | |||||||||||
| January 6, 2015 | 0.404 | 3.6 | 12.1 | 5 | 17 | 0.731 | 2.46 | 0.21 | 0.71 | 1 | 0.0000 |
| January 13, 2015 | 0.358 | 2.6 | 7.8 | 4 | 12 | 0.906 | 2.71 | 0.27 | 0.81 | 1 | 0.0000 |
| January 20, 2015 | 0.919 | 2.2 | 16.9 | 6 | 46 | 0.113 | 0.87 | 0.10 | 0.77 | 2 | 0.3010 |
| January 28, 2015 | 0.372 | 2.00 | 6.2 | 16 | 50 | 0.37 | 1.15 | 0.23 | 0.71 | 1 | 0.0000 |
| Average | 0.513 | 2.6 | 10.7 | 8 | 31 | 0.531 | 1.80 | 0.20 | 0.75 | 1 | 0.0753 |
| Minimum | 0.358 | 2.0 | 6.2 | 4 | 12 | 0.113 | 0.87 | 0.10 | 0.71 | 1 | 0.0000 |
| Maximum | 0.919 | 3.6 | 16.9 | 16 | 50 | 0.906 | 2.71 | 0.27 | 0.81 | 2 | 0.3010 |
There was no discharge from Outfall 002 to Applebrook during December 2014.
Table 2 illustrates the influent wastewater pollutant loadings for December 2014. The influent loadings remained within the treatment facility design loadings
Table 2
January 2015 - Influent Wastewater
| Design Basis | Flow | BOD5 | TSS | NH4-N | TKN, mg/L | Phosphorus,Total, mg/L | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | ||
| MGD Average | 335 | 2,098 | 320 | 2,001 | 32 | 200 | 48 | 301 | 9.1 | 57 | |
| Sample Date | |||||||||||
| January 6, 2015 | 0.446 | 162 | 603 | 71 | 264 | 32.6 | 121 | 44.0 | 164 | 4.6 | 17 |
| January 13, 2015 | 0.398 | 188 | 699 | 149 | 554 | 27.1 | 101 | 40.2 | 150 | 4.7 | 17 |
| January 20, 2015 | 0.452 | 153 | 569 | 65 | 242 | 32.8 | 122 | 36.3 | 135 | 4.3 | 16 |
| January 28, 2015 | 0.436 | 111.0 | 413 | 82.0 | 305 | 34.2 | 127 | 42.1 | 157 | 4.7 | 17 |
| Average | 0.433 | 154 | 571 | 92 | 341 | 31.7 | 118 | 40.7 | 151 | 4.6 | 17 |
| Minimum | 0.398 | 111 | 413 | 65 | 242 | 27.1 | 101 | 36.3 | 135 | 4.3 | 16 |
| Maximum | 0.452 | 188 | 699 | 149 | 554 | 34.2 | 127 | 44.0 | 164 | 4.7 | 17 |
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 2 of 6
[Logo: Big Fish Environmental Services Inc.]
Table 3 presents the available Outfall 001 final effluent data for the month of February 2015. There are no anticipated exceedances of the permitted limitations for the month. Split sampling of the composite sample collected by Applied Laboratory Services (ALS) is ongoing for comparative analysis and daily results.
Table 3
February 2015 - Final Effluent - Out Fall 001
| NPDES Permit Discharge Limitations |
Flow | CBOD5 | TSS | NH4-N | Phosphorus,Total , mg/L | Fecal Coliform | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/ month | mg/L | lbs/ month | mg/L | lbs/ month | mg/L | lbs/ month | Geo Mean | Geo Mean | |
| 200 | 1,000 | ||||||||||
| 0.75 | 20 | 125 | 21 | 131 | 7 | 44 | 0.5 | 3 | |||
| Instantaneous Maximum | 40 | 42 | |||||||||
| Sample Date | |||||||||||
| February 3, 2015 | 0.444 | 3.5 | 13.0 | 8 | 30 | 0.866 | 3.21 | 0.15 | 0.56 | 4 | 0.6021 |
| February 10, 2015 | 0.391 | 3.4 | 11.1 | 8 | 26 | 0.372 | 1.21 | 0.21 | 0.68 | 1 | 0.0000 |
| February 17, 2015 | 0.430 | 4.7 | 16.9 | 11 | 39 | 1.790 | 6.42 | 0.31 | 1.11 | 1 | 0.0000 |
| February 25, 2015 | 0.330 | ||||||||||
| Average | 0.399 | 3.9 | 13.6 | 9 | 32 | 1.009 | 3.61 | 0.22 | 0.78 | 2 | 0.2007 |
| Minimum | 0.330 | 3.4 | 11.1 | 8 | 26 | 0.372 | 1.21 | 0.15 | 0.56 | 1 | 0.0000 |
| Maximum | 0.444 | 4.7 | 16.9 | 11 | 39 | 1.790 | 6.42 | 0.31 | 1.11 | 4 | 0.6021 |
During February 2015, there was no discharge of treated effluent to Applebrook. The pump has been placed in the off mode during the winter months.
The influent wastewater pollutant concentrations and loading entering the wastewater treatment facility remained within the design concentrations and loadings. Composite samples are collected at the influent doghouse manhole and influent wet well. The influent flow meter reading is collected from the influent flow meter located prior to the Screening Building, excluding the internal recycle flows.
Table 4 presents the available pollutant data for the influent wastewater collected at the doghouse manhole during February 2015.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 3 of 6
[Logo: Big Fish Environmental Services Inc.]
Table 4
February 2015 - Influent Wastewater
| Design Basis | Flow | BOD5 | TSS | NH4-N | TKN, mg/L | Phosphorus,Total, mg/L | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | ||
| MGD Average | 335 | 2,098 | 320 | 2,001 | 32 | 200 | 48 | 301 | 9.1 | 57 | |
| Sample Date | |||||||||||
| February 3, 2015 | 0.502 | 200 | 837 | 194 | 812 | 29.6 | 124 | 35.4 | 148 | 3.8 | 16 |
| February 10, 2015 | 0.534 | 143 | 598 | 58 | 243 | 31.1 | 130 | 41.9 | 175 | 5.1 | 21 |
| February 17, 2015 | 0.492 | 204 | 854 | 117 | 490 | 34.3 | 144 | 50.5 | 211 | 5.5 | 23 |
| February 25, 2015 | 0.389 | ||||||||||
| Average | 0.479 | 182 | 763 | 123 | 515 | 31.7 | 133 | 42.6 | 178 | 4.8 | 20 |
| Minimum | 0.389 | 143 | 598 | 58 | 243 | 29.6 | 124 | 35.4 | 148 | 3.8 | 16 |
| Maximum | 0.534 | 204 | 854 | 194 | 812 | 34.3 | 144 | 50.5 | 211 | 5.5 | 23 |
Sequencing batch reactors (SBRs) numbered 1, 3 and 4 were in service during February.
Process monitoring of each SBR included ammonia as N, nitrite as N, Nitrate as N, COD, SSV, MLSS and total phosphorus. Foam concentrations remained consistent during February at approximately 80% coverage of the surface area. Sludge wasting rates remain elevated to manage the MLSS concentrations and F:M ratio within the desired goals. As a result, the ammonia as nitrogen concentration has increased, however, is well below the discharge limitation of 7.0 mg/L. Daily monitoring of the influent and final effluent 24-hour composites samples for total phosphorus is ongoing. Daily analysis of the final effluent flow equalization grab sample is total phosphorus is ongoing. Sample collection and analysis of the influent wastewater collected at the influent pump station wet well is ongoing.
Addition of aluminum sulfate solution to the SBRs to assist with phosphorus removal continued. The volume of aluminum sulfate solution to the SBRs
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 4 of 6
[Logo: Big Fish Environmental Services Inc.]
remained fairly consistent at a daily average of 76.6 gpd during February. During January, the soda ash daily addition average remained consistent at 435 lbs. per day. Soda ash assists towards maintaining SBR pH concentrations above 7.0 standard units and assists to replenish alkalinity consumed during the nitrification process and aluminum sulfate solution addition.
SBR No. 2 remains out of service as a treatment unit. Minor repairs will be scheduled as weather conditions permit.
Solids Dewatering and Disposal: February 2015
| Sludge Dewatering Summary | |
|---|---|
| Gallons of sludge dewatered | 193,165 |
| Average Dewatered Total Solids, % | NA |
| Wet Tons | NA |
| Dry Tons | NA |
| Number of dumpsters | 4 |
*Seventeen (17) days of centrifuge operation
Flow data:
| Flow Meter Location | February 2015 | Daily Maximum Flow, gpd | |
|---|---|---|---|
| Total Volume for Month, MG | Average Daily Flow, gpd | ||
| Influent Wastewater to Screening Building* | 12.124 | 433,003 | 591,490 |
| Influent Wastewater to SBRs | 12.388 | 442,445 | 543,168 |
| Internal Recycle | 0.482 | 17,208 | 171,896 |
| Treated Effluent to Disc Filters | 11.784 | 420,848 | 350,144 |
| Final Effluent Discharge | 10.798 | 385,643 | 502,000 |
| Applebrook Golf Course | 0 | 0 | 0 |
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 5 of 6
[Logo: Big Fish Environmental Services Inc.]
Chemical Usage:
| Chemical | February 2015 | |
|---|---|---|
| Daily Average | Total Monthly | |
| Soda Ash | 438 | 12,250 |
| Aluminum Sulfate solution | 76.6 | 2,145 |
| Polymer (centrifuge) | 0.84 | 14.28 |
*Seventeen (17) days of centrifuge operation
During February, sludge wasting to the sludge holding tanks and decanting of the sludge holding tanks was ongoing. Process monitoring included pH, total alkalinity and total solids.
Sludge holding tank No. 1 was in service. The level at the beginning of February was 9.75 feet and the level at the end of the month was 6.15 feet. The initial total solids concentration was 1.14% decreasing to 0.89% at the end of the month. The average pH concentration was 6.95 S.U. Zero gallons of supernatant were decanted during the month. A total of 400 pounds of soda ash were added.
Sludge holding tank No. 2 was in service. The level at the beginning of the month was 9.73 feet and the level at the end was 10.58. The initial total solids concentration was 1.03% total solids increasing to 1.21% at the end of the month. The average pH concentration was 7.13 S.U. and zero pounds of soda ash were added. Zero gallons of supernatant were decanted.
Significant Storm/Hydraulic Loading Events
During February, there were no significant weather events; however, temperatures were measured to be lowered than typical.
Minor Repairs and Preventative Maintenance
No unscheduled repairs preventative maintenance items were performed during February.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 6 of 6
2015 FEBRUARY 1ST QUARTER- METERS FROM WEST GOSHEN - CC COLLECTION
| Precip | DATE | WESTTOWN WAY | ELLIS LANE | PAOLI PIKE | WILSON DRIVE | SUMMIT | NET | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Inches | READING | GPD | READING | GPD | READING | GPD | READING | GPD | GPD | FLOWS | |
| 0.00 | 02/01/15 | ||||||||||
| 0.85 | 02/02/15 | 1,944,391 | 1,009,000 | 7,522,855 | 88,743 | 4,681,710 | 59,153 | 3,649,919 | 50,407 | 24,000 | 810,697 |
| 0.00 | 02/03/15 | 1,945,647 | 1,256,000 | 7,536,361 | 135,060 | 4,688,605 | 68,950 | 3,658,500 | 85,810 | 24,000 | 966,180 |
| 0.00 | 02/04/15 | 1,946,712 | 1,065,000 | 7,545,625 | 92,640 | 4,694,742 | 61,370 | 3,665,929 | 74,290 | 24,000 | 836,700 |
| 0.00 | 02/05/15 | 1,947,771 | 1,059,000 | 7,554,473 | 88,480 | 4,700,918 | 61,760 | 3,672,967 | 70,380 | 24,000 | 838,380 |
| 0.00 | 02/06/15 | 1,948,774 | 1,003,000 | 7,563,455 | 89,820 | 4,706,804 | 58,860 | 3,679,312 | 63,450 | 24,000 | 790,870 |
| 0.00 | 02/07/15 | 790,870 | |||||||||
| 0.00 | 02/08/15 | 790,870 | |||||||||
| 0.07 | 02/09/15 | 1,951,752 | 992,667 | 7,590,026 | 88,570 | 4,724,411 | 58,690 | 3,692,528 | 44,053 | 24,000 | 801,353 |
| 0.00 | 02/10/15 | 1,952,730 | 978,000 | 7,598,241 | 82,150 | 4,730,792 | 63,810 | 3,698,645 | 61,170 | 24,000 | 770,870 |
| 0.00 | 02/11/15 | 1,953,765 | 1,035,000 | 7,607,215 | 89,740 | 4,736,095 | 53,030 | 3,704,966 | 63,210 | 24,000 | 829,020 |
| 0.00 | 02/12/15 | 1,954,755 | 990,000 | 7,615,303 | 80,880 | 4,741,796 | 57,010 | 3,711,703 | 67,370 | 24,000 | 784,740 |
| 0.00 | 02/13/15 | 1,955,743 | 988,000 | 7,623,474 | 81,710 | 4,747,376 | 55,800 | 3,717,855 | 61,520 | 24,000 | 788,970 |
| 0.08 | 02/14/15 | 788,970 | |||||||||
| 0.00 | 02/15/15 | 788,970 | |||||||||
| 0.00 | 02/16/15 | 788,970 | |||||||||
| 0.10 | 02/17/15 | 1,960,675 | 986,400 | 7,668,425 | 89,902 | 4,774,991 | 55,230 | 3,743,833 | 51,956 | 24,000 | 789,312 |
| 0.00 | 02/18/15 | 1,961,676 | 1,001,000 | 7,677,494 | 90,690 | 4,780,853 | 58,620 | 3,750,713 | 68,800 | 24,000 | 782,890 |
| 0.00 | 02/19/15 | 1,962,692 | 1,016,000 | 7,686,801 | 93,070 | 4,786,564 | 57,110 | 3,756,955 | 62,420 | 24,000 | 803,400 |
| 0.00 | 02/20/15 | 803,400 | |||||||||
| 0.50 | 02/21/15 | 803,400 | |||||||||
| 0.00 | 02/22/15 | 803,400 | |||||||||
| 0.00 | 02/23/15 | 1,965,759 | 1,022,333 | 7,714,738 | 93,123 | 4,804,597 | 60,110 | 3,771,909 | 49,847 | 24,000 | 819,253 |
| 0.00 | 02/24/15 | 1,966,763 | 1,004,000 | 7,723,446 | 87,080 | 4,810,406 | 58,090 | 3,779,060 | 71,510 | 24,000 | 787,320 |
| 0.00 | 02/25/15 | 1,967,751 | 988,000 | 7,731,704 | 82,580 | 4,816,007 | 56,010 | 3,786,407 | 73,470 | 24,000 | 775,940 |
| 0.00 | 02/26/15 | 1,968,738 | 987,000 | 7,739,642 | 79,380 | 4,821,830 | 58,230 | 3,793,878 | 74,710 | 24,000 | 774,680 |
| 0.00 | 02/27/15 | 1,969,779 | 1,041,000 | 7,748,308 | 86,660 | 4,827,877 | 60,470 | 3,800,892 | 70,140 | 24,000 | 823,730 |
| 0.00 | 02/28/15 | ||||||||||
| 1.60 | Day Avg | 1,023,411 | 90,015 | 59,017 | 64,695 | 24,000 | 810,697 | ||||
| Day Tot | 18,421,400 | 1,620,279 | 1,062,303 | 1,164,513 | |||||||
| Day Count | 18 | 18 | 18 | 18 | 18 | 26 | |||||
| EG TWP | |
|---|---|
| MONTH TO DATE | 1.60 |
| NORMAL MONTH TO DATE | |
| YEAR TO DATE | 6 |
| NORMAL YEAR TO DATE |
2015 flowmeters -all-stations separate month worksheets.xlsx
3/2/20157:46 AM
2015 1st. Quarter - METERS FROM WEST GOSHEN - CC COLLECTION
| DATE | HERSHEY'S MILL | ASHBRIDGE | HICKS METER | RESERVOIR | BARKWAY | |||||
|---|---|---|---|---|---|---|---|---|---|---|
| READING | GPD | READING | GPD | READING | GPD | READING | GPD | READING | GPD | |
| 02/01/15 | ||||||||||
| 02/02/15 | 28,681,466 | 722,780 | 2,054,602 | 62,333 | 18,565,893 | 228,977 | 65,398,736 | 635,903 | 3,500,838 | 11,633 |
| 02/03/15 | 28,772,444 | 909,780 | 2,055,476 | 87,400 | 18,596,490 | 305,970 | 65,482,813 | 840,770 | 3,502,505 | 16,670 |
| 02/04/15 | 28,842,146 | 697,020 | 2,056,114 | 63,800 | 18,624,636 | 281,460 | 65,555,350 | 725,370 | 3,503,539 | 10,340 |
| 02/05/15 | 28,910,384 | 682,380 | 2,056,728 | 61,400 | 18,654,468 | 298,320 | 65,628,081 | 727,310 | 3,504,594 | 10,550 |
| 02/06/15 | 28,982,785 | 724,010 | 2,057,338 | 61,000 | 18,680,898 | 264,300 | 65,695,848 | 677,670 | 3,505,730 | 11,360 |
| 02/07/15 | ||||||||||
| 02/08/15 | ||||||||||
| 02/09/15 | 29,198,228 | 718,143 | 2,059,201 | 62,100 | 18,748,016 | 223,727 | 65,881,927 | 620,263 | 3,509,070 | 11,133 |
| 02/10/15 | 29,263,082 | 648,540 | 2,059,781 | 58,000 | 18,773,670 | 256,540 | 65,946,641 | 647,140 | 3,510,128 | 10,580 |
| 02/11/15 | 29,331,048 | 679,660 | 2,060,395 | 61,400 | 18,801,744 | 280,740 | 66,015,730 | 690,890 | 3,511,264 | 11,360 |
| 02/12/15 | 29,396,678 | 656,300 | 2,060,973 | 57,800 | 18,829,638 | 278,940 | 66,082,195 | 664,650 | 3,512,303 | 10,390 |
| 02/13/15 | 29,462,710 | 660,320 | 2,061,569 | 59,600 | 18,856,320 | 266,820 | 66,148,275 | 660,800 | 3,513,587 | 12,840 |
| 02/14/15 | ||||||||||
| 02/15/15 | ||||||||||
| 02/16/15 | ||||||||||
| 02/17/15 | ||||||||||
| 02/18/15 | 29,807,910 | 690,400 | 2,064,836 | 65,340 | 18,972,658 | 232,676 | 66,464,704 | 632,858 | 3,519,734 | 12,294 |
| 02/19/15 | 29,874,508 | 665,980 | 2,065,461 | 62,500 | 18,999,872 | 272,140 | 66,532,720 | 680,160 | 3,520,808 | 10,740 |
| 02/20/15 | 29,940,438 | 659,300 | 2,066,141 | 68,000 | 19,026,436 | 265,640 | 66,601,352 | 686,320 | 3,522,484 | 16,760 |
| 02/21/15 | ||||||||||
| 02/22/15 | ||||||||||
| 02/23/15 | 30,162,072 | 738,780 | 2,068,305 | 72,133 | 19,095,400 | 229,880 | 66,799,835 | 661,610 | 3,526,252 | 12,560 |
| 02/24/15 | 30,231,958 | 698,860 | 2,068,957 | 65,200 | 19,122,252 | 268,520 | 66,868,310 | 684,750 | 3,527,438 | 11,860 |
| 02/25/15 | 30,296,108 | 641,500 | 2,069,600 | 64,300 | 19,149,048 | 267,960 | 66,935,776 | 674,660 | 3,528,510 | 10,720 |
| 02/26/15 | 30,361,152 | 650,440 | 2,070,234 | 63,400 | 19,176,936 | 278,880 | 67,003,767 | 679,910 | 3,529,626 | 11,160 |
| 02/27/15 | 30,430,848 | 696,960 | 2,070,915 | 68,100 | 19,204,804 | 278,680 | 67,075,020 | 712,530 | 3,530,701 | 10,750 |
| 02/28/15 | ||||||||||
| 696,731 | 64,656 | 265,565 | 683,531 | 11,872 | ||||||
| 12,541,153 | 1,163,807 | 4,780,169 | 12,303,565 | 213,701 | ||||||
| 18 | 18 | 18 | 18 | 18 | ||||||
2015 flowmeters -all-stations separate month worksheets.xlsx
3/2/20157:46 AM
February Precip. 1.60-2015
[Bar chart printed rotated 90 degrees: daily precipitation for February 2015. Value axis labeled "precip." runs from 0 to 0.9 in steps of 0.1. Category axis labeled "snow/rain" lists 1 through 34. Legend: February.]
Bars (approximate values read from the chart):
- Day 3: about 0.85
- Day 10: about 0.07
- Day 15: about 0.08
- Day 18: about 0.10
- Day 22: about 0.50
2015 Monthly Precipitation
[3-D horizontal bar chart titled 2015 Monthly Precipitation. Scale runs 0 to 4.5 in steps of 0.5; categories January through December. January bar reaches a little over 4; February bar reaches about 1.5 to 2; no bars for March through December.]
Legend: Series1
Flowmeters February 2015
[Line graph showing daily flowmeter readings for February 2015.]
Vertical Axis: Flow's (0 to 1200000 in increments of 200000)
Horizontal Axis: Day of the Month (1 through 28)
Legend: February
Monthly Totals 2015 Jan-Dec
[Bar chart printed rotated sideways, with many thin bars for January and February only (roughly 750000 to 960000); March through December have no bars.]
Value axis: Flowmeters (0 to 1200000 in increments of 200000)
Category axis: Month (January through December)
EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
MEETING MINUTES
February 9, 2015
The East Goshen Township Municipal Authority held their regular public meeting on Monday, February 9, 2015 at 7:00 pm at the East Goshen Township building. Members in attendance were: Chairman Kevin Cummings, Jack Yahraes, and Dana Pizarro. Member Fran Beck participated by phone. Also in attendance were: Rick Smith (Township Manager), Carmen Battavio (Township Supervisor), Scott Towler (Big Fish), Mike Ellis (Pennoni), and Jessica Wiesak (Attorney).
COMMON ACRONYMS:
| BFES – Big Fish Environmental Services | MA- Municipal Authority |
|---|---|
| BOS – Board of Supervisors | NPDES – National Pollutant Discharge Elimination System |
| CB – Conservancy Board | PC – Planning Commission |
| DEP – Department of Environmental Protection | PM – Prevention Maintenance |
| EPA – Environmental protection Agency | PR – Park & Recreation Board |
| HC – Historical Commission | RCSTP – Ridley Creek Sewer Treatment Plant |
| I&I – Inflow & Infiltration | SBR – Sequencing Batch Reactor |
| LCSTP – Lockwood Chase Sewer Treatment Plant | SSO – Sanitary System Overflow |
| WAS – Waste Activated Sludge |
Call to Order & Pledge of Allegiance
Kevin called the meeting to order at 7:00 pm and led those present in the Pledge of Allegiance. There was a moment of silence to remember the troops and all veterans. Kevin asked if anyone would be recording the meeting and there was no response.
Chairman’s Report/Other Members’ Reports
None
Sewer Reports
1. Director of Public Works
The members reviewed Mark Miller’s report for January 2015:
Meters: They were read on a daily basis and West Goshen was agreeable to splitting the cost for remote monitoring of the meters on the Chester Creek Interceptor. Fran noted he was pleased that West Goshen had agreed to split this cost.
C.C. Collection: The pump stations were visited on a daily basis, no problems to report. We were notified of two lateral backups, we responded and cleared both. The new rail system was installed at the Barkway PS.
R.C. Collection: The Hunt Country Pump Station was visited on a daily basis with no problems to report.
R.C. Plant: No problems to report.
Alarms: They responded to 17 alarms for the month of January.
PA One Calls: They received 57 PA One calls in January.
2. Pennoni Engineer’s Report
Mike Ellis gave the following report:
Invoices: Invoices with summaries are provided under separate cover.
F:\Data\Shared Data\Minutes\Municipal Authority\2015\MA 2-9-15 draft.doc
1
Reservoir Rd Pump Station:
1. Mike presented the concept site plan for the pump station. The station complies with applicable zoning and subdivision requirements and we are maintaining the required 50 foot buffer from the Chester Creek. All of the equipment will be located in the building and it will be landscaped.
2. We completed the test boring on January 15, bedrock was encountered at 22’ in both borings and rock would not cause a problem with the pump station.
3. A pre-application meeting will be scheduled with PADEP in March.
Chapter 94 Reports – He has initiated work on the 2014 Chapter 94 Reports.
Lockwood Chase Groundwater Monitoring - He reviewed the 2013 and 2014 groundwater monitoring reports and noted the 3 of the monitoring wells are dry, Nitrate-Nitrogen fluctuates from 5.8 to 13.7 mg/L with mo discernable trend and Fecal Coliform has been at non-detectable levels since the plant was closed.
Lockwood Chase Closure NPDES Permit – He is coordinating the submission of the final closure paperwork with the Township.
Hershey’s Mill PS and Marydell PS Diversion - The maintenance bond for these projects expire in July and August and Mike will schedule final inspection in May
Hershey Mill PS – Mike notified PADEP that the comminutor has been installed.
3. Big Fish Environmental Services – Scott reported that the plant was in compliance for December and January. In December the total Phosphorous is less the permit limit of 0.5 mg/L. They had to replace the variable speed drives on influent pumps 2 and 3. Kevin expressed a concern about the need to replace electrical components so soon, and Scott noted that we regularly see electrical surges at the plant. Scott said he would discuss the possibility of adding surge protectors to selected equipment with Mark.
Approval of Minutes
Jack moved to accept the minutes of January 12, 2015 as corrected. Fran seconded the motion. The motion passed unanimously.
Approval of Invoices
1. Dana moved to approve payment of the following Pennoni invoices:
| Invoice #623589 | $5,300.30 |
|---|---|
| Invoice #623591 | $ 82.50 |
| Invoice #623592 | $ 565.00 |
| Invoice #623593 | $ 464.00 |
| Invoice #623594 | $ 661.25 |
| Invoice #623595 | $2,053.75 |
| Invoice #623596 | $1,827.50 |
Jack seconded the motion. The motion passed unanimously.
Liaison Reports
None.
F:\Data\Shared Data\Minutes\Municipal Authority\2015\MA 2-9-15 draft.doc
2
Financial Reports
In January, the Municipal Authority recorded $556.41 in revenues and $3,702 in expenses, for a variance of -$3,145. As of January 31, the fund balance was $1,586.031, of which $1,520.845 is in the construction account.
Goals
Jack will attend the next West Goshen meeting.
New Business
It was the consensus of the members that the April 13, June 8 and August 10 Municipal Authority meetings would be rescheduled to 6 pm in order to avoid conflicts with the Comp Plan Task Force meetings.
Adjournment
There being no further business, Dana to adjourn the meeting. Jack seconded the motion. The motion passed unanimously. The meeting was adjourned at 7:45 pm.
Respectfully submitted,
Louis F. Smith, Jr.
Township Manager
F:\Data\Shared Data\Minutes\Municipal Authority\2015\MA 2-9-15 draft.doc
3
[Pennoni logo]
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS
INVOICE
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice # : 626537
Invoice Date : 02/20/2015
Project : EGMA1501
Project Name : 2015 General Services
For Services Rendered through: 2/15/2015
Reviewed Lockwood Chase STP annual groundwater monitoring reports for 2013 and 2014, coordinated with Township to obtain prior year's monitoring data, reviewed lab results in 2012 prior to STP closure, and prepared a written summary in the February Engineer's Report; prepared February Engineer's Report; and prepared for and attended the February MA meeting.
Phase : **** -- Professional Services
| Total Phase : **** -- Professional Services | Labor : | 1,306.25 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 1,306.25 | |
| Amount Due This Invoice | $1,306.25 |
| Fee : | 12,000.00 |
|---|---|
| Prior Billings : | 661.25 |
| Current Billings : | 1,306.25 |
| Total Billings : | 1,967.50 |
Phase : **** -- Professional Services
Labor
| Class | Hours/ Units |
Rate | Amount |
|---|---|---|---|
| Authority Engineer | 7.25 | 115.00 | 833.75 |
| Staff Engineer | 5.25 | 90.00 | 472.50 |
| Labor Total: | 12.50 | 1,306.25 |
| Total Phase : **** -- Professional Services | Labor : | $1,306.25 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMA1501 -- 2015 General Services | Labor : | $1,306.25 |
| Expense : | $0.00 |
ok RS 3/5
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMA1501 Invoice Summary
Invoice Date 02/20/2015
| Project: | EGMA1501 | ||
|---|---|---|---|
| Pennoni Job No.: | 2015 General Services | ||
| Invoice No: | 626537 | ||
| Invoice Period: | 1/30/2015 | to | 2/15/2015 |
| Initial Authorization: | $ 12,000.00 | Date: | 2/20/2015 |
| Contract Amount: | $ 12,000.00 | ||
| Previously Invoiced: | $ 661.25 | ||
| Current Invoice: | $ 1,306.25 | ||
| Invoiced to Date ($): | $ 1,967.50 | ||
| Invoiced to Date (%): | 16% | ||
| Remaining Budget ($): | $ 10,032.50 | ||
| Remaining Budget (%): | 84% |
Budget by Phase:
| Phase Name: | 2015 General Services |
|---|---|
| Phase Budget: | $ 12,000.00 |
| Previously Invoiced: | $ 661.25 |
| Current Invoice: | $ 1,306.25 |
| Invoiced to Date ($): | $ 1,967.50 |
| Invoiced to Date (%): | 16% |
| Remaining Budget ($): | $ 10,032.50 |
| Remaining Budget (%): | 84% |
Comments: Reviewed Lockwood Chase STP annual groundwater monitoring reports for 2013 and 2014, coordinated with Township to obtain prior year's monitoring data, reviewed lab results in 2012 prior to STP closure, and prepared a written summary in the February Engineer's Report; prepared February Engineer's Report; and prepared for and attended the February MA meeting.
[Pennoni logo]
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS
INVOICE
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice # : 626538
Invoice Date : 02/20/2015
Project : EGMA1503
Project Name : 2014 Chapter 94 Reports
For Services Rendered through: 2/15/2015
Continued preparation of RCSTP, Chester Creek, and Westtown Chp. 94 Reports including analysis of flow and organic data, coordination with RCSTP operator, and preparation of report narratives, tables, and charts.
Phase : **** -- Professional Services
| Total Phase : **** -- Professional Services | Labor : | 4,378.75 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 4,378.75 | |
| Amount Due This Invoice | $4,378.75 |
| Fee : | 14,800.00 |
|---|---|
| Prior Billings : | 1,827.50 |
| Current Billings : | 4,378.75 |
| Total Billings : | 6,206.25 |
Phase : **** -- Professional Services
Labor
| Class | Hours/ Units |
Rate | Amount |
|---|---|---|---|
| Authority Engineer | 0.75 | 115.00 | 86.25 |
| Associate Engineer | 50.50 | 85.00 | 4,292.50 |
| Labor Total: | 51.25 | 4,378.75 |
| Total Phase : **** -- Professional Services | Labor : | $4,378.75 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMA1503 -- 2014 Chapter 94 Reports | Labor : | $4,378.75 |
| Expense : | $0.00 |
ok RS 3/5
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMA1503 Invoice Summary
Invoice Date 02/20/2015
| Project: | EGMA1503 | ||
|---|---|---|---|
| Pennoni Job No.: | 2015 Chapter 94 Reports | ||
| Invoice No: | 626538 | ||
| Invoice Period: | 1/19/2015 | to | 1/18/2015 |
| Initial Authorization: | $ 14,800.00 | Date: | 2/20/2015 |
| Contract Amount: | $ 10,500.00 | ||
| Previously Invoiced: | $ 1,827.50 | ||
| Current Invoice: | $ 4,378.75 | ||
| Invoiced to Date ($): | $ 6,206.25 | ||
| Invoiced to Date (%): | 59% | ||
| Remaining Budget ($): | $ 4,293.75 | ||
| Remaining Budget (%): | 41% |
Budget by Phase:
| Phase Name: | 2015 Chapter 94 Reports |
|---|---|
| Phase Budget: | $ 10,500.00 |
| Previously Invoiced: | $ 1,827.50 |
| Current Invoice: | $ 4,378.75 |
| Invoiced to Date ($): | $ 6,206.25 |
| Invoiced to Date (%): | 59% |
| Remaining Budget ($): | $ 4,293.75 |
| Remaining Budget (%): | 41% |
Comments: Continued preparation of RCSTP, Chester Creek, and Westtown Chp. 94 Reports including analysis of flow and organic data, coordination with RCSTP operator, and preparation of report narratives, tables, and charts.
[Pennoni logo]
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS
INVOICE
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice # : 626539
Invoice Date : 02/20/2015
Project : EGMA1504
Project Name : Reservoir Rd PS Design & Permitting
For Services Rendered through: 2/15/2015
Phase 01 - We prepared the first draft site concept plans and profiles for alternatives with and without buildings; prepared cost estimates; prepared an outline of pump station design, operations, and controls parameters; attended a site visit to E. Whiteland Twp's Mill Lane PS for scoping; coordinated pump sizing, function, and cost with various vendors; established pump rate and design operating points; met with Township staff to review the first draft concept; initiated revisions to the concept plans to address comments; prepared a draft floor plan of the building; and prepared for the concept plan presentation at the February MA meeting.
Phase 03 - We performed preparatory planning and drafting work in the office for the upcoming field survey.
Phase 07 - We completed and submitted the geotechnical report including borings logs.
| Phase Code / Name | Contract Amount |
Previously Billed |
% Complete |
Complete To Date |
Amount This Invoice |
|---|---|---|---|---|---|
| 01 -- Concept Design est. | $13,700.00 | $2,267.50 | $10,858.25 | $8,590.75 | |
| 02 -- PADEP WQM Permit Pre-Application Mt est. | $1,400.00 | $0.00 | $0.00 | $0.00 | |
| 03 -- Existing Conditions Survey | $23,300.00 | $0.00 | 3.59% | $836.75 | $836.75 |
| 04 -- Sewer Stakeout in Easement Areas est. | $3,600.00 | $0.00 | $0.00 | $0.00 | |
| 05 -- 1636 Bow Tree Dr Bndry Survey & Eas | $4,020.00 | $0.00 | 0.00% | $0.00 | $0.00 |
| 06 -- Add'l Boundary Survey & Easement est. | $9,000.00 | $0.00 | $0.00 | $0.00 | |
| 07 -- Geotechnical Borings | $4,000.00 | $3,032.80 | 100.00% | $4,000.00 | $967.20 |
| 08 -- Install Permanent Survey Benchmarks est. | $4,000.00 | $0.00 | $0.00 | $0.00 | |
| Total : | $63,020.00 | $5,300.30 | $15,695.00 | $10,394.70 |
Amount Due This Invoice $10,394.70
ok RS 3/5
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date 02/20/2015
| Project: | EGMA1504 | ||
|---|---|---|---|
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 626539 | ||
| Invoice Period: | 1/19/2015 | to | 2/15/2015 |
| Initial Authorization: | $ 63,020.00 | Date: | 2/20/2015 |
| Contract Amount: | $ 63,020.00 | ||
| Previously Invoiced: | $ 5,300.30 | ||
| Current Invoice: | $ 10,394.70 | ||
| Invoiced to Date ($): | $ 15,695.00 | ||
| Invoiced to Date (%): | 25% | ||
| Remaining Budget ($): | $ 47,325.00 | ||
| Remaining Budget (%): | 75% |
Budget by Phase:
| Phase Name: | 2015 Semi-Annual I&I Reports |
|---|---|
| Phase Budget: | $ 63,020.00 |
| Previously Invoiced: | $ 5,300.30 |
| Current Invoice: | $ 10,394.70 |
| Invoiced to Date ($): | $ 15,695.00 |
| Invoiced to Date (%): | 25% |
| Remaining Budget ($): | $ 47,325.00 |
| Remaining Budget (%): | 75% |
Comments: Phase 01 - We prepared the first draft site concept plans and profiles for alternatives with and without buildings; prepared cost estimates; prepared an outline of pump station design, operations, and controls parameters; attended a site visit to E. Whiteland Twp's Mill Lane PS for scoping; coordinated pump sizing, function, and cost with various vendors; established pump rate and design operating points; met with Township staff to review the first draft concept; initiated revisions to the concept plans to address comments; prepared a revised draft floor plan of the building; and prepared for the concept plan presentation at the February MA meeting
Phase 03 - We performed preparatory planning and drafting work in the office for the upcoming field survey.
Phase 07 - We completed and submitted the geotechnical report including borings logs
[Gawthrop Greenwood, PC logo]
Gawthrop Greenwood, PC
Attorneys at Law
17 East Gay Street, Suite 100
West Chester, PA 19381-0562
gglaw@gawthrop.com
(p) 610-696-8225
(f) 610-344-0922
www.gawthrop.com
Page: 1
02/04/2015
Client No: 6604-001M
Invoice No. 128180
East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380
General Authority Services
Fees
| Date | Initials | Description | Hours | Amount |
|---|---|---|---|---|
| 01/12/2015 | PMM | Review and analyze packet in preparation for Authority meeting. | 1.50 | |
| For Current Services Rendered | 1.50 | 300.00 | ||
Recapitulation
| Timekeeper | Hours | Hourly Rate | Total |
|---|---|---|---|
| Patrick M. McKenna | 1.50 | $200.00 | $300.00 |
| Total Current Charges | 300.00 |
|---|---|
| Balance Due | $300.00 |
TO MA -
THIS INVOICE HAS BEEN PAID
OK TO PAY
RS 2-10-15
To ensure proper credit, please write client number on your check when returning payment. Thank You.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.
Memo
To: Municipal Authority
From: Jon Altshul
Re: MA February Financial Reports
Date: March 4, 2015
In February, the Municipal Authority recorded $966.25 in revenues and $10,954.30 in expenses (all for engineering), for a variance of -$9,988. As of February 28, the fund balance was $1,576,043, of which $1,515,579 is in the construction account.
A complete list of all year-to-date expenses and revenues is provided.
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
February 2015
| Account Title | Acct # | Annual Budget | Month To Date Actual | Year To Date Actual |
|---|---|---|---|---|
| MUNICIPAL AUTHORITY BEGINNING FUND BALANCE | 1,586,031.43 | |||
| RCSTP BUDGET | ||||
| REVENUE | ||||
| INTEREST EARNED - RCSTP EXPANSION | 07341 1020 | 1,600.00 | 119.08 | 251.05 |
| GRANT REVENUE | 07392 0800 | 0.00 | 0.00 | 0.00 |
| TOTAL REVENUE | 1,600.00 | 119.08 | 251.05 | |
| EXPENSES | ||||
| R.C.-CAP. PROJ.-ENGINEER | 07424 7451 | 0.00 | 0.00 | 0.00 |
| R.C. CAP EXPANSION GEN'L CONTRACTOR | 07424 7452 | 0.00 | 0.00 | 0.00 |
| R.C. CAP EXPANSION - ELECTRICAL | 07424 7453 | 0.00 | 0.00 | 0.00 |
| R.C. CAP EXP CONTINGENCY CAPITAL | 07424 7454 | 0.00 | 0.00 | 0.00 |
| R.C. CAP EXP CONTINGENCY ONGOING | 07424 7455 | 0.00 | 0.00 | 0.00 |
| R.C. CAP EXP ADDITIONAL CONTINGENCY | 07424 7456 | 0.00 | 0.00 | 0.00 |
| TRANSFER TO SEWER SINKING FUND | 07492 0550 | 0.00 | 0.00 | 0.00 |
| TRANSFER TO AUTHORITY CAP FUND | 07492 0990 | 0.00 | 0.00 | 0.00 |
| TOTAL EXPENSES | 0.00 | 0.00 | 0.00 | |
| RCSTP NET RESULT | 1,600.00 | 119.08 | 251.05 | |
U:\bmccool\2015\Municipal Authority\2015 - 02 - Municipal Authority Report.xlsx Page 1 of 3 03/03/2015
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
February 2015
| Account Title | Acct # | Annual Budget | Month To Date Actual | Year To Date Actual |
|---|---|---|---|---|
| OPERATING BUDGET | ||||
| REVENUE | ||||
| INTEREST EARNINGS | 07341 1000 | 15.00 | 1.17 | 2.61 |
| C.C. TAPPING FEES | 07364 1100 | 0.00 | 0.00 | 0.00 |
| R.C.TAPPING FEES | 07364 1110 | 14,296.00 | 0.00 | 0.00 |
| CONNECTION FEES - SEWER | 07364 1130 | 0.00 | 563.76 | 845.64 |
| MISCELLANEOUS REVENUE | 07380 1000 | 0.00 | 282.24 | 423.36 |
| TRANSFER FROM SEWER OPERATING | 07392 0500 | 105,105.00 | 0.00 | 0.00 |
| TOTAL REVENUE | 119,416.00 | 847.17 | 1,271.61 | |
| EXPENSES | ||||
| ADMINISTRATIVE WAGES | 07424 1400 | 33,323.00 | 0.00 | 0.00 |
| MISCELLANEOUS EXPENSE | 07424 3000 | 3,000.00 | 0.00 | 1,450.00 |
| MUNIC.AUTH.-AUDITING | 07424 3110 | 10,984.00 | 0.00 | 0.00 |
| ENGINEERING SERVICES | 07424 3130 | 37,300.00 | 5,571.50 | 6,833.00 |
| LEGAL SERVICES | 07424 3140 | 9,000.00 | 0.00 | 0.00 |
| M.C.-DVRFA-DEBT SERVICE | 07471 1000 | 23,240.00 | 0.00 | 0.00 |
| M.C.-DVRFA-INTEREST PAYMN | 07472 1000 | 4,169.00 | 0.00 | 0.00 |
| M.C.-DVRFA-INTEREST PAYMN | 07472 1010 | 0.00 | 0.00 | 0.00 |
| TOTAL EXPENSES | 121,016.00 | 5,571.50 | 8,283.00 | |
| OPERATING NET RESULT | (1,600.00) | (4,724.33) | (7,011.39) | |
U:\bmccool\2015\Municipal Authority\2015 - 02 - Municipal Authority Report.xlsx Page 2 of 3 03/03/2015
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
February 2015
| Account Title | Acct # | Annual Budget | Month To Date Actual | Year To Date Actual |
|---|---|---|---|---|
| CAPITAL BUDGET | ||||
| REVENUE | ||||
| LOAN PROCEEDS-SEWER PROJECT | 07393 1001 | 0.00 | 0.00 | 0.00 |
| TRANSFER FROM SEWER CAP RESERVE | 07392 0900 | 0.00 | 0.00 | 0.00 |
| TOTAL REVENUE | 0.00 | 0.00 | 0.00 | |
| EXPENSES | ||||
| MARYDELL PUMP STATION - ENGINEER | 07425 1000 | 0.00 | 0.00 | 0.00 |
| MARYDELL PUMP STATION -CONSTRUCTION | 07425 2000 | 0.00 | 0.00 | 0.00 |
| MANHOLE COVER REPLACEMENTS | 07424.7405 | 0.00 | 0.00 | 0.00 |
| C.C. CAPITAL - COLLECTION | 07424.7420 | 0.00 | 0.00 | 0.00 |
| LOCHWOOD ABANDONMENT ENGINEER | 07424 7475 | 0.00 | 0.00 | 0.00 |
| LOCHWOOD ABANDONMENT CONSTRUCTION | 07424 7476 | 0.00 | 0.00 | 0.00 |
| LOCHWOOD ELIMINATION PHASE 2 | 07424 7477 | 0.00 | 0.00 | 0.00 |
| HERSHEY MILL STATION - ENGINEER | 07426 1000 | 0.00 | 0.00 | 0.00 |
| HERSHEY MILL STATION - CONSTRUCTION | 07426 2000 | 0.00 | 0.00 | 0.00 |
| RESERVE PUMP STATION - ENGINEER | 07427 1000 | 0.00 | 0.00 | 0.00 |
| RESERVE PUMP STATION - CONSTRUCTION | 07427 2000 | 0.00 | 0.00 | 0.00 |
| RESERVOIR PUMP STATION - ENGINEER | 07428 1000 | 100,000.00 | 5,382.80 | 6,372.80 |
| RESERVOIR PUMP STATION CONSTRUCTION | 07428 2000 | 0.00 | 0.00 | 0.00 |
| TOTAL EXPENSES | 100,000.00 | 5,382.80 | 6,372.80 | |
| CAPITAL NET RESULT | (100,000.00) | (5,382.80) | (6,372.80) | |
| MUNICIPAL AUTHORITY ENDING FUND BALANCE | 1,576,043.38 | |||
U:\bmccool\2015\Municipal Authority\2015 - 02 - Municipal Authority Report.xlsx Page 3 of 3 03/03/2015
East Goshen Township General Ledger
Report Date 03/03/15 GL Transaction Details PAGE 1
MGRP18 run by BRIAN 4 : 01 PM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07341-1000 INTEREST EARNINGS | 0.00 | |||||||||
| 1501 | JE | 46156 | 1.44 | 02/03/15 | INTEREST | INTEREST EARNED JANUARY 2015 07 FUND |
||||
| 1501 | 0.00 | 1.44 | -1.44 | |||||||
| 1502 | 46526 | 1.17 | 03/02/15 | INTEREST | INTEREST EARNED FEBRUARY 2015 07 FUND |
|||||
| 1502 | 0.00 | 1.17 | -2.61 | |||||||
| 0.00 | 2.61 | -2.61 | ||||||||
| 07341-1020 INTEREST EARNED - RCSTP EXPANSION | 0.00 | |||||||||
| 1501 | 46156 | 131.97 | 02/03/15 | INTEREST | INTEREST EARNED JANUARY 2015 07 FUND |
|||||
| 1501 | 0.00 | 131.97 | -131.97 | |||||||
| 1502 | 46526 | 119.08 | 03/02/15 | INTEREST | INTEREST EARNED FEBRUARY 2015 07 FUND |
|||||
| 1502 | 0.00 | 119.08 | -251.05 | |||||||
| 0.00 | 251.05 | -251.05 | ||||||||
| 07364-1130 CONNECTION FEES - SEWER | 0.00 | |||||||||
| 1501 | CR | 45967 | 423.00 | 01/16/15 | 789 | 8648 | 1 GEORGE SMITH & CHRISTINA CONLE | |||
| JE | 45968 | 141.12 | 01/16/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | |||||
| 141.12 | 423.00 | -281.88 | ||||||||
| 1502 | CR | 46296 | 423.00 | 02/13/15 | 248 | 8650 | 1 JACOBS, ROBERT & CHERYL | |||
| 46479 | 423.00 | 02/26/15 | 2381 | 8649 | 1 STOFFLET, MICHAEL | |||||
| JE | 46297 | 141.12 | 02/13/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | |||||
| 46480 | 141.12 | 02/26/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | ||||||
| 282.24 | 846.00 | -845.64 | ||||||||
| 423.36 | 1,269.00 | -845.64 | ||||||||
| 07380-1000 MISCELLANEOUS REVENUE | 0.00 | |||||||||
| 1501 | 45968 | 141.12 | 01/16/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | |||||
| 0.00 | 141.12 | -141.12 | ||||||||
| 1502 | 46297 | 141.12 | 02/13/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | |||||
| 46480 | 141.12 | 02/26/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | ||||||
| 0.00 | 282.24 | -423.36 | ||||||||
| 0.00 | 423.36 | -423.36 | ||||||||
East Goshen Township General Ledger
Report Date 03/03/15 GL Transaction Details PAGE 2
MGRP18 run by BRIAN 4 : 01 PM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07424-3000 MISCELLANEOUS EXPENSE | 0.00 | |||||||||
| 1501 | CD | 45777 | 950.00 | 01/02/15 | 2260 | 2132 | PENNSYLVANIA MUNICIPAL AUTHORITIES ASSOC 2015 ACTIVE MEMBERSHIP DUES |
|||
| 46110 | 500.00 | 01/29/15 | 2263 | 2737 | COMMONWEALTH OF PA ANNUAL FEE - NPDES PERMIT -CHAP. |
|||||
| 1,450.00 | 0.00 | 1,450.00 | ||||||||
| 1,450.00 | 0.00 | 1,450.00 | ||||||||
| 07424-3130 ENGINEERING SERVICES | 0.00 | |||||||||
| 45953 | 621.50 | 01/15/15 | 2261 | 1052 | PENNONI ASSOCIATES INC. SERVICES THRU 12/7/14 GENERAL |
|||||
| 46013 | 640.00 | 01/22/15 | 2262 | 1052 | PENNONI ASSOCIATES INC. SERVICE THRU 11/9/14 GEN.SERVICE |
|||||
| 1,261.50 | 0.00 | 1,261.50 | ||||||||
| 1502 | 46311 | 5,571.50 | 02/13/15 | 2264 | 1052 | PENNONI ASSOCIATES INC. SERVICES THRU 1/18/15 2014 CHAP. |
||||
| 5,571.50 | 0.00 | 6,833.00 | ||||||||
| 6,833.00 | 0.00 | 6,833.00 | ||||||||
| 07428-1000 RESERVOIR PUMP STATION - ENGINEER | 0.00 | |||||||||
| 1501 | 45954 | 137.50 | 01/15/15 | 10029 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 12/7/14 RESERV.RD ACT |
||||
| 46014 | 852.50 | 01/22/15 | 10030 | 1052 | PENNONI ASSOCIATES INC. SERVICE THRU 11/9/14 RESERVOIR R ACT.537 |
|||||
| 990.00 | 0.00 | 990.00 | ||||||||
| 1502 | 46312 | 5,382.80 | 02/13/15 | 10031 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 1/18/15 RESERVOIR RD.P ACT 537 PLANNING |
||||
| 5,382.80 | 0.00 | 6,372.80 | ||||||||
| 6,372.80 | 0.00 | 6,372.80 | ||||||||
| Beg Bal | 0.00 | 15,079.16 | 1,946.02 | 13,133.14 | ||||||
[Lenni Electric Corporation logo]
New
February 13, 2015
East Goshen Township
1580 Paoli Pike
West Chester, PA. 19380
Attn: Mr. Mark Miller
Re: Ridley Creek WWTP – TVSS for UV System
We offer a T & M budget price of $5,402.80 for the following electrical work at the above referenced location. Our price includes:
- 1 – Install new GE TPR7120S12WMNID TVSS in control room after the transformer install, ahead of the UV system controls install
- LS – Rework pipe and wire
| Materials | $4,092.00 |
|---|---|
| 15% | $613.80 |
| Labor mechanic 5 hrs. @ $75.50 | $377.50 |
| Labor apprentice 5 hrs. @ $58.50 | $292.50 |
| Service Truck | $27.00 |
| $5,402.80 |
If you have any questions, please do not hesitate to contact me directly @ 610-636-6511.
Sincerely,
LENNI ELECTRIC CORPORATION
[Signature: James C. Hallman, Jr.]
James C. Hallman, Jr.
C & I Division
1020 ANDREW DRIVE WEST CHESTER, PA 19380 • 610-436-9922 • FAX 610-436-9926
AN EQUAL OPPORTUNITY EMPLOYER M/F/V