Municipal Authority
The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.
The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.
- Five members, serving five-year terms
- Meetings are on the 2nd Monday of the month at 7:00 P.M.
- All township meetings are held at the Township Building and open to the public
| Authority Members | Term Expiration Date |
| Kevin Cummings, Chairman | 2026 |
| John Stipe, Vice Chairman |
2029 |
| Dana Pizzarro, Secretary | 2026 |
| Sean Ellsworth, Assistant Secretary/Treasurer | 2028 |
| Walter Wujcik, Treasurer | 2028 |
| Pennoni Associates, Engineer | |
| Patrick M. McKenna, Esq. | |
| Peter Hicks, BoS Liaison | |
| Kevin Miller, Staff Liaison |
Documents
Back to the list | Open the original PDF
Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.
EAST GOSHEN MUNICIPAL AUTHORITY
April 13, 2015
The meeting will start at 6 pm
- CALL TO ORDER/PLEDGE OF ALLEGIANCE/MOMENT OF SILENCE a. Ask if anyone will be taping the meeting?
- CHAIRMAN'S REPORT/OTHER MEMBERS REPORTS
- SEWER REPORTS a. Director of Public Works Report b. Pennoni Engineer's Report c. Big Fish Environmental Inc. Report with DMR's d. East Goshen Township Flows
- APPROVAL OF MINUTES a. March 9, 2015
- APPROVAL OF INVOICES a. Pennoni Invoice #630705 $1,756.25 b. Pennoni Invoice #630706 $ 368.75 c. Pennoni Invoice #630707 $2,593.75 d. Pennoni Invoice #630893 $6,619.50 e. Pennini Invoice #630894 $11,988.25 f. Gawthrop Invoice #129252 $ 660.00
- LIAISON REPORTS
- FINANCIAL REPORTS a. March 2015 Report
- OLD BUSINESS
- GOALS a. Submit an article for each newsletter – Due date for newsletter Need by 1/30/15 – Jack - Completed Need by 5/1/15 Need by 8/31/15 Need by 10/30/15
F:\Data\Shared Data\Agendas\Municipal Authority\2015\4-13-15.doc
b. Obtain construction permits for the Reservoir Road Pump Station – December 31, 2015 2/6 – Test boring done, meeting with Mike to review preliminary site plan and discuss control options. 3/9 concept design completed, met with PA DEP.
c. Attend West Goshen Meetings quarterly – more often if needed.
1st Quarter – Jack - Completed
2nd Quarter
3rd Quarter
4th Quarter
d. Respond to capacity requests in 45 days or less.
e. Continue to implement I & I Plan
f. Operate RCSTP in compliance with NPDES Permit February
- NEW BUSINESS a. Review two quotes from Lenni Electric for two surge protectors at Ridley Creek b. Reservoir Road Pump Station – review progress prints (Mike will bring to meeting) c. Consider proposal to update 2007 Sewer Needs Analysis
- CAPACITY REQUESTS
- ANY OTHER MATTER
- CORRESPONDENCE AND REPORTS OF INTEREST
- PUBLIC COMMENT
- ADJOURNMENT
F:\Data\Shared Data\Agendas\Municipal Authority\2015\4-13-15.doc
AREA CODE 610
692-7171
EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199
April 10, 2015
To: Municipal Authority
From: Mark Miller
Re: March 2015 Monthly Report
Meters: All meters were read on a daily basis.
C.C. Collection: We responded to 4 lateral clogs, two were in Grand Oak, one in Hershey Mills and one in White Chimney. All clogs were cleared.
R.C. Collection: Pump Stations were visited on a daily basis with no problems to report.
R.C. Plant: No problems to report.
Re-sale Inspections: We had four re-sale lateral inspections in the Twp. I inspected them and found no problems.
Alarms: We responded to 14 alarms for March.
PA One Calls: We received 46 PA One calls since March.
EGMA 1501
Pennoni
MEMORANDUM
TO: East Goshen Municipal Authority Board
Rick Smith, Township Manager
FROM: Michael Ellis, P.E.
Authority Engineer
DATE: April 9, 2015
SUBJECT: Engineer's Report
Invoices
- Invoices with summaries are provided under separate cover.
Ridley Creek Sewage Treatment Plant (RCSTP)
- We provided consultation and correspondence to the Township on the proposed surge protection addition and replacement and the premature UV ballast failures. We agree with the proposed approach to add a new TVSS immediately prior to the ballasts and that the ballast failures are likely due to surges. The Township should consider contacting the new ballast vendor and manufacturer to determine their troubleshooting and customer support capabilities now in the event there continue to be issues following the new TVSS installation.
- We attended a tour of the plant and a field visit to the Ashbridge Pump Station with Mark Miller and Pat McKenna on April 2 nd .
Reservoir Road Pump Station
- We attended the PADEP Water Quality Management (WQM) Permit pre-application with Rick Smith at PADEP's Norristown office on March 13 th . PADEP had some minor comments, but they were agreeable to the design and permitting approach for the project. The project will require an individual WQM permit instead of a general permit due to the proposed daily pump volume.
- We initiated the progress design including site layout, diversion details and diversion piping profiles, pump design, wet well and valve vault, building architectural and HVAC, power, and controls. A current draft of plans will be presented at the April 13 th Municipal Authority meeting.
- The existing conditions field survey work continued and has been substantially completed. An existing conditions plan is nearly complete. Once complete, force main plans and profiles will be prepared.
Page 1 of 3
P:\Projects\EGMA\Memos to Board\2015\Memo to EGMA Board 2015-04-09.docx
EGMA 1501
- We are coordinating with the PW Department to perform two infiltration tests at the proposed pump station site within the next 2 weeks. The tests are needed for future stormwater management design. Once the tests are performed, we will schedule a NPDES Stormwater pre-application meeting with PADEP and the Chester County Conservation District.
Chapter 94 Reports
- We completed the 2014 Chapter 94 Reports for the RCSTP, West Goshen Service Area (WGSA), and Westtown Service Area, and we submitted them to PADEP on March 31 st . The RCSTP, pump stations, and sewers all have adequate capacity. A summary of the RCSTP and WGSA reports follows:
RCSTP
The 2014 annual average influent flow (not including recycle flows) was 0.409 MGD, and the 3-month maximum average flow was 0.479 MGD. The plant's permitted average capacity is 0.750 MGD. The 5-year projected annual average and maximum month flows are 0.396 MGD and 0.458 MGD respectively.
The 2014 annual average organic loading (not including recycle flows) was 701 lbs/day BOD5, and the maximum month loading was 930 lbs/day BOD5. The permitted capacity is 2,098 lbs/day. The 5-year projected annual average and maximum month loadings are 706 lbs/day and 1,085 lbs/day respectively.
The interceptor is considered to have had adequate capacity to convey the maximum daily flow in 2014. The Hershey's Mill and Hunt Country Pump Stations are projected to have adequate capacity for the projected 2-year peak day flows.
WGSA
The 2014 annual average flow was 0.771 MGD, the 3-month maximum average flow was 0.930 MGD, and the maximum daily flow was 2.142 MGD. The 5-year projected annual average and maximum month flows are 0.827 MGD and 0.982 MGD respectively.
The interceptor had more-than-adequate capacity to convey the maximum daily flow in 2014. The Ashbridge and Barkway Pump Stations are projected to have adequate capacity for the projected 2-year peak day flows.
Semi-Annual I&I Report
- We analyzed portable and permanent meter flows for the past 6-month period, and we prepared the semi-annual I&I report. We expect to issue the report on April 10 th .
Lockwood Chase STP Closure NPDES Permit N.O.T.
- We plan to perform a site visit to the former LCSTP site to evaluate the consistency of as-built conditions with the permit plans within the next month, so that the NPDES Permit Notice of Termination paperwork can be finalized and submitted to the Chester County Conservation District.
Page 2 of 3
P:\Projects\EGMA\Memos to Board\2015\Memo to EGMA Board 2015-04-09.docx
EGMA 1501
Hershey's Mill PS and Marydell PS Diversions
- The 2-year Maintenance Bonds on the Hershey's Mill PS and Marydell PS Diversions expire on July and August respectively. We recommend warranty inspections be performed by May.
Hershey's Mill PS Muffin Monster
- We notified PADEP in early March that the comminutor has been installed in the pump station for their field evaluation as required by the permit, but we have not received a response.
Page 3 of 3
P:\Projects\EGMA\Memos to Board\2015\Memo to EGMA Board 2015-04-09.docx
Big Fish Environmental Services Inc.
Monthly Operations Report: March 2015
Executive Summary
The Ridley Creek sewage treatment plant outfall 001 achieved compliance with the NPDES discharge permit during February 2015. There was no discharge to Applebrook, which is identified as outfall 002. Chemical usage utilized for total phosphorus removal, pH and total alkalinity remained consistent with previous months. No mechanical or operational issues were observed during operation of the SBR and sludge dewatering equipment.
Treatment Process Operation
During February 2015, there were no exceedances of the final effluent discharge limitations for outfall 001. The total phosphorus monthly average concentration of 0.26 mg/L as compared to the permitted limitation of 0.50 mg/L. Table 1 illustrates the final effluent composite sample data reported for the February 2015 eDMR. During the month, the final effluent total phosphorus concentration discharged ranged from 0.15 mg/L to 0.36 mg/L. The aluminum sulfate daily average increased during February to 87.0 gpd.
Table 1: February 2015 - Final Effluent - Out Fall 001
| NPDES Permit Discharge Limitations / Sample Date | Flow MGD Average | CBOD5 mg/L | CBOD5 lbs/month | TSS mg/L | TSS lbs/month | NH4-N mg/L | NH4-N lbs/month | Phosphorus, Total, mg/L mg/L | Phosphorus, Total, mg/L lbs/month | Fecal Coliform Geo Mean | Fecal Coliform Geo Mean |
|---|---|---|---|---|---|---|---|---|---|---|---|
| NPDES Permit Discharge Limitations | 0.75 | 20 | 125 | 21 | 131 | 7 | 44 | 0.5 | 3 | 200 | 1,000 |
| Instantaneous Maximum | 40 | 42 | |||||||||
| February 3, 2015 | 0.444 | 3.5 | 13.0 | 8 | 30 | 0.866 | 3.21 | 0.15 | 0.56 | 4 | 0.6021 |
| February 9, 2015 | 0.502 | 9 | 38 | ||||||||
| February 10, 2015 | 0.391 | 3.4 | 11.1 | 8 | 26 | 0.372 | 1.2 | 0.21 | 0.68 | 1 | 0.0000 |
| February 17, 2015 | 0.430 | 4.7 | 16.9 | 12 | 43 | 1.790 | 6.4 | 0.31 | 1.11 | 1 | 0.0000 |
| February 25, 2015 | 0.330 | 2.5 | 6.9 | 7 | 19 | 1.96 | 5.4 | 0.50 | 1.38 | 2 | 0.3010 |
| Average | 0.419 | 3.5 | 11.9 | 9 | 31 | 1.247 | 4.06 | 0.29 | 0.93 | 2 | 0.2258 |
| Minimum | 0.330 | 2.5 | 6.9 | 7 | 19 | 0.372 | 1.21 | 0.15 | 0.56 | 1 | 0.0000 |
| Maximum | 0.502 | 4.7 | 16.9 | 12 | 43 | 1.960 | 6.42 | 0.50 | 1.38 | 4 | 0.6021 |
There was no discharge from Outfall 002 to Applebrook during February 2015.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 1 of 6
Big Fish Environmental Services Inc.
Table 2 illustrates the influent wastewater pollutant loadings for February 20115. The influent loadings remained within the treatment facility design loadings.
Table 2: February 2015 - Influent Wastewater
| Design Basis / Sample Date | Flow MGD Average | BOD5 mg/L | BOD5 lbs/day | TSS mg/L | TSS lbs/day | NH4-N mg/L | NH4-N lbs/day | TKN, mg/L mg/L | TKN, mg/L lbs/day | Phosphorus, Total, mg/L mg/L | Phosphorus, Total, mg/L lbs/day |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Design Basis | 335 | 2,098 | 320 | 2,001 | 32 | 200 | 48 | 301 | 9.1 | 57 | |
| February 3, 2015 | 0.502 | 200 | 837 | 194 | 812 | 29.6 | 124 | 35.4 | 3.8 | 3.8 | 16 |
| February 10, 2015 | 0.534 | 143 | 599 | 58 | 243 | 31.1 | 130 | 41.9 | 2.0 | 5.1 | 21 |
| February 17, 2015 | 0.492 | 204 | 854 | 117 | 490 | 34.3 | 144 | 50.5 | 4.6 | 5.5 | 23 |
| February 25, 2015 | 0.431 | 168 | 703 | 281 | 1,176 | 31.5 | 132 | 41.5 | 4.2 | 5.3 | 22 |
| Average | 0.490 | 179 | 748 | 163 | 680 | 31.6 | 132 | 42.3 | 4 | 4.9 | 21 |
| Minimum | 0.431 | 143 | 599 | 58 | 243 | 29.6 | 124 | 35.4 | 2 | 3.8 | 16 |
| Maximum | 0.534 | 204 | 854 | 281 | 1176 | 34.3 | 144 | 50.5 | 5 | 5.5 | 23 |
Table 3 presents the available Outfall 001 final effluent data for the month of March 2015. During March, excessive foam conditions on the surface of the SBRs resulting from filamentous growth, primarily Microthrix parvicella. This bacterium becomes excessively predominate at low organic loadings and water temperatures less than 15°C. Historically during the past three (3) years, it has been observed this filamentous growth becomes excessive during January, February and March of each year. As a result, solids carryover from the SBRs tend to become elevated, which can contribute to exceeding the permitted total suspended solids (TSS) discharge concentrations. The final effluent TSS discharge concentrations were observed to periodically elevated, however, additional sample collection of the final effluent quality resulted in a monthly TSS concentration within the permitted discharge limitations.
Process control measures to minimize the adverse effects of the Microthrix parvicella bacterium included increased lowering the MLSS concentrations. One impact of lowering the MLSS concentrations during this time of year as temperatures and hydraulic conditions vary, result in inhibiting the effectiveness of nitrification. During March, the final effluent ammonia as nitrogen concentrations became elevated.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 2 of 6
Big Fish Environmental Services Inc.
At the present time, there are no anticipated exceedances of the permitted limitations for the month. Split sampling of the composite sample collected by Applied Laboratory Services (ALS) is ongoing for comparative analysis and daily results.
Table 3: March 2015 - Final Effluent - Out Fall 001
| NPDES Permit Discharge Limitations / Sample Date | Flow MGD Average | CBOD5 mg/L | CBOD5 lbs/month | TSS mg/L | TSS lbs/month | NH4-N mg/L | NH4-N lbs/month | Phosphorus, Total, mg/L mg/L | Phosphorus, Total, mg/L lbs/month | Fecal Coliform Geo Mean | Fecal Coliform Geo Mean |
|---|---|---|---|---|---|---|---|---|---|---|---|
| NPDES Permit Discharge Limitations | 0.75 | 20 | 125 | 21 | 131 | 7 | 44 | 0.5 | 3 | 200 | 1,000 |
| Instantaneous Maximum | 40 | 42 | |||||||||
| March 3, 2015 | 0.371 | 3.5 | 10.8 | 15 | 46 | 2.000 | 6.19 | 0.00 | 89 | 1.9494 | |
| March 9, 2015 | 0.460 | 9 | 35 | ||||||||
| March 10, 2015 | 0.528 | 4.4 | 19.4 | 4 | 18 | 4.440 | 19.6 | 0.20 | 0.88 | 1 | 0.0000 |
| March 12, 2015 | 0.410 | 7 | 24 | ||||||||
| March 17, 2015 | 0.411 | 4.7 | 16.1 | 6 | 21 | 10.300 | 35.3 | 0.30 | 1.03 | 14 | 1.1461 |
| March 18, 2015 | 0.426 | 6 | 21 | ||||||||
| March 19, 2015 | 0.360 | 15 | 45 | ||||||||
| March 24, 2015 | 0.454 | 5.40 | 20.4 | 15 | 57 | 11.10 | 42.0 | 0.26 | 0.98 | 2 | 0.3010 |
| March 25, 2015 | 0.354 | 15 | 44 | ||||||||
| March 27, 2015 | 0.506 | 7 | 30 | ||||||||
| March 31, 2015 | 0.381 | 2.40 | 7.63 | 10 | 32 | 0.15 | 0.48 | 2 | 0.3010 | ||
| Average | 0.424 | 4.1 | 14.9 | 10 | 34 | 6.960 | 25.77 | 0.23 | 0.67 | 7 | 0.8491 |
| Minimum | 0.354 | 2.4 | 7.6 | 4 | 18 | 2.000 | 6.19 | 0.15 | 0.00 | 1 | 0.0000 |
| Maximum | 0.528 | 5.4 | 20.4 | 15 | 57 | 11.100 | 42.03 | 0.30 | 1.03 | 89 | 1.9494 |
During March 2015, there was no discharge of treated effluent to Applebrook. The pump has been placed in the off mode during the winter months.
The influent wastewater pollutant concentrations and loading entering the wastewater treatment facility remained within the design concentrations and loadings. Composite samples are collected at the influent doghouse manhole and influent wet well. The influent flow meter reading is collected from the influent flow meter located prior to the Screening Building, excluding the internal recycle flows.
Table 4 presents the available pollutant data for the influent wastewater collected at the doghouse manhole during March 2015.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 3 of 6
Big Fish Environmental Services Inc.
Table 4: March 2015 - Influent Wastewater
| Design Basis / Sample Date | Flow MGD Average | BOD5 mg/L | BOD5 lbs/day | TSS mg/L | TSS lbs/day | NH4-N mg/L | NH4-N lbs/day | TKN, mg/L mg/L | TKN, mg/L lbs/day | Phosphorus, Total, mg/L mg/L | Phosphorus, Total, mg/L lbs/day |
|---|---|---|---|---|---|---|---|---|---|---|---|
| Design Basis | 335 | 2,098 | 320 | 2,001 | 32 | 200 | 48 | 301 | 9.1 | 57 | |
| March 3, 2015 | 0.485 | 171 | 692 | 104 | 421 | 31.0 | 125 | 39.1 | 3.8 | 4.2 | 17 |
| March 10, 2015 | 0.836 | 199 | 805 | 64 | 259 | 33.7 | 136 | 31.9 | 2.0 | 3.8 | 15 |
| March 17, 2015 | 0.551 | 42.8 | 173 | 69 | 279 | 16.8 | 68 | 17.8 | 4.6 | 2.0 | 8 |
| March 24, 2015 | 0.444 | 186 | 752 | 210 | 849 | 27.5 | 111 | 40.4 | 4.2 | 4.6 | 19 |
| March 31, 2015 | 0.460 | 189 | 764 | 199 | 28.8 | 116 | 4.2 | 17 | |||
| Average | 0.555 | 158 | 637 | 129 | 452 | 27.6 | 111 | 32.3 | 4 | 3.8 | 15 |
| Minimum | 0.444 | 43 | 173 | 64 | 259 | 16.8 | 68 | 17.8 | 2 | 2.0 | 8 |
| Maximum | 0.836 | 199 | 805 | 210 | 849 | 33.7 | 136 | 40.4 | 5 | 4.6 | 19 |
Sequencing batch reactors (SBRs) numbered 1, 3 and 4 were in service during February and March.
Process monitoring of each SBR included ammonia as N, nitrite as N, Nitrate as N, COD, SSV, MLSS and total phosphorus. Foam concentrations increased slightly during November and December. The average coverage of the surface area was estimated at 90%. Increased sludge wasting rates were maintained to manage the MLSS concentrations and F:M ratio within the desired goals. Daily monitoring of the influent and final effluent 24-hour composites samples for total phosphorus is ongoing. Daily analysis of the final effluent flow equalization grab sample is total phosphorus is ongoing. Sample collection and analysis of the influent wastewater collected at the influent pump station wet well is ongoing.
Addition of aluminum sulfate solution to the SBRs to assist with phosphorus removal continued. The volume of aluminum sulfate solution to the SBRs increased to a daily average of 87.0 gpd during March. During March, soda ash daily addition decreased to 389 lbs. per day. Soda ash assists towards maintaining SBR pH concentrations above 7.0 standard units and assists to replenish alkalinity consumed during the nitrification process and aluminum sulfate solution addition.
SBR No. 2 remains out of service as a treatment unit. Minor repairs will be scheduled as weather conditions permit.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 4 of 6
Big Fish Environmental Services Inc.
Solids Dewatering and Disposal: March 2015
| Sludge Dewatering Summary | |
|---|---|
| Gallons of sludge dewatered | 315,382 |
| Average Dewatered Total Solids, % | NA |
| Wet Tons | NA |
| Dry Tons | NA |
| Number of dumpsters | 6 |
*Twenty two (22) days of centrifuge operation
Flow data:
| March 2015 | |||
|---|---|---|---|
| Flow Meter Location | Total Volume for Month, MG | Average Daily Flow, gpd | Daily Maximum Flow, gpd |
| Influent Wastewater to Screening Building* | 16.685 | 538,237 | 902,200 |
| Influent Wastewater to SBRs | 16.307 | 526,041 | 769,984 |
| Internal Recycle | 0.417 | 13,445 | 139,042 |
| Treated Effluent to Disc Filters | 15.671 | 505,505 | 739,392 |
| Final Effluent Discharge | 13.381 | 431,645 | 617,000 |
| Applebrook Golf Course | 0 | 0 | 0 |
*The final effluent daily maximum flow of 919,000 is attributed to the result of an erroneous level meter reading. The transducer and v-notch weir were cleaned and the subsequent flow measurements recorded were within the anticipated range.
Chemical Usage:
| March 2015 | ||
|---|---|---|
| Chemical | Daily Average | Total Monthly |
| Soda Ash | 389 | 11,650 |
| Aluminum Sulfate solution | 87.0 | 2,696 |
| Polymer (centrifuge) | 0.84 | 18.44 |
*twenty two (22) days of centrifuge operation
During March, sludge wasting to the sludge holding tanks and decanting of the sludge holding tanks was ongoing. Process monitoring included pH, total alkalinity and total solids.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 5 of 6
Big Fish Environmental Services Inc.
Sludge holding tank No. 1 was in service. The level at the beginning of March was 6.20 feet and the level at the end of the month was 9.08 feet. The initial total solids concentration was 0.76% decreasing to 0.66% at the end of the month. The average pH concentration was 6.90 S.U. Zero gallons of supernatant were decanted during the month. A total of 1,400 pounds of soda ash were added.
Sludge holding tank No. 2 was in service. The level at the beginning of the month was 11.40 feet and the level at the end was 8.73. The initial total solids concentration was 1.29% total solids decreasing to 0.85% at the end of the month. The average pH concentration was 6.75 S.U. and 850 pounds of soda ash was added. Zero gallons of supernatant were decanted.
Significant Storm/Hydraulic Loading Events
During March, there were four storm events resulting in daily precipitation amounts greater than 0.5 inches measured during a 24 hour period. A total of 4.4 inches of rainfall and 10.0 inches of snow were measured at the facility during March. Influent flows nearly doubled from a monthly average of 538,237 gpd to 841,790 gpd on March 4th, 836,410 gpd on March 16th and 902,200 gpd on March 14th.
Minor Repairs and Preventative Maintenance
No unscheduled repairs preventative maintenance items were performed during March.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 6 of 6
2015 MARCH 1ST QUARTER- METERS FROM WEST GOSHEN - CC COLLECTION
| Precip Inches | DATE | WESTTOWN WAY READING | WESTTOWN WAY GPD | ELLIS LANE READING | ELLIS LANE GPD | PAOLI PIKE READING | PAOLI PIKE GPD | WILSON DRIVE READING | WILSON DRIVE GPD | SUMMIT GPD | NET FLOWS |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 0.50 | 03/01/15 | ||||||||||
| 0 | 03/02/15 | ||||||||||
| 0.00 | 03/03/15 | 1,973,822 | 1,010,750 | 7,786,361 | 95,133 | 4,852,311 | 61,085 | 3,823,396 | 56,260 | 24,000 | 798,273 |
| 0.35 | 03/04/15 | 1,974,997 | 1,175,000 | 7,797,673 | 113,120 | 4,859,489 | 71,780 | 3,830,919 | 75,230 | 24,000 | 914,870 |
| 0.47 | 03/05/15 | 914,870 | |||||||||
| 0.00 | 03/06/15 | 914,870 | |||||||||
| 0.00 | 03/07/15 | 914,870 | |||||||||
| 0.00 | 03/08/15 | 914,870 | |||||||||
| 0.00 | 03/09/15 | 1,980,949 | 1,190,400 | 7,861,067 | 126,788 | 4,893,678 | 68,378 | 3,862,474 | 63,110 | 24,000 | 932,124 |
| 0.75 | 03/10/15 | 1,982,303 | 1,354,000 | 7,876,067 | 150,000 | 4,901,687 | 80,090 | 3,871,715 | 92,410 | 24,000 | 1,031,500 |
| 0.00 | 03/11/15 | 1,984,050 | 1,747,000 | 7,896,068 | 200,010 | 4,912,561 | 108,740 | 3,881,484 | 97,690 | 24,000 | 1,340,560 |
| 0.00 | 03/12/15 | 1,985,542 | 1,492,000 | 7,912,623 | 165,550 | 4,921,193 | 86,320 | 3,890,890 | 94,060 | 24,000 | 1,146,070 |
| 0.00 | 03/13/15 | 1,986,750 | 1,208,000 | 7,924,446 | 118,230 | 4,928,097 | 69,040 | 3,899,921 | 90,310 | 24,000 | 930,420 |
| 1.10 | 03/14/15 | 930,420 | |||||||||
| 0.00 | 03/15/15 | 930,420 | |||||||||
| 0.00 | 03/16/15 | 1,990,929 | 1,393,000 | 7,972,050 | 158,680 | 4,950,780 | 75,610 | 3,915,882 | 53,203 | 24,000 | 1,105,507 |
| 0.00 | 03/17/15 | 1,992,120 | 1,191,000 | 7,983,461 | 114,110 | 4,957,660 | 68,800 | 3,930,999 | 151,170 | 24,000 | 856,920 |
| 0.00 | 03/18/15 | 1,993,256 | 1,136,000 | 7,994,008 | 105,470 | 4,964,145 | 64,850 | 3,931,973 | 9,740 | 24,000 | 955,940 |
| 0.00 | 03/19/15 | 955,940 | |||||||||
| 0.50 | 03/20/15 | 1,995,461 | 1,102,500 | 8,013,938 | 99,650 | 4,976,737 | 62,960 | 3,945,052 | 65,395 | 24,000 | 874,495 |
| 0.00 | 03/21/15 | 874,495 | |||||||||
| 0.00 | 03/22/15 | 874,495 | |||||||||
| 0.00 | 03/23/15 | 1,998,840 | 1,126,333 | 8,050,152 | 120,713 | 4,996,566 | 66,097 | 3,958,232 | 43,933 | 24,000 | 895,590 |
| 0.00 | 03/24/15 | 1,999,931 | 1,091,000 | 8,060,529 | 103,770 | 5,002,939 | 63,730 | 3,964,475 | 62,430 | 24,000 | 861,070 |
| 0.11 | 03/25/15 | 2,001,023 | 1,092,000 | 8,070,028 | 94,990 | 5,008,864 | 59,250 | 3,970,362 | 58,870 | 24,000 | 878,890 |
| 0.60 | 03/26/15 | 2,002,039 | 1,016,000 | 8,078,881 | 88,530 | 5,014,890 | 60,260 | 3,975,704 | 53,420 | 24,000 | 813,790 |
| 0.00 | 03/27/15 | 2,003,301 | 1,262,000 | 8,092,684 | 138,030 | 5,022,481 | 75,910 | 3,983,845 | 81,410 | 24,000 | 966,650 |
| 0.00 | 03/28/15 | 966,650 | |||||||||
| 0.00 | 03/29/15 | 966,650 | |||||||||
| 0.00 | 03/30/15 | 2,006,763 | 1,154,000 | 8,129,608 | 123,080 | 5,043,442 | 69,870 | 3,997,815 | 46,567 | 24,000 | 914,483 |
| 0.35 | 03/31/15 | 2,007,850 | 1,087,000 | 8,139,984 | 103,760 | 5,049,807 | 63,650 | 4,005,158 | 73,430 | 24,000 | 846,160 |
| 4.73 | Day Avg | 1,212,666 | 123,312 | 70,912 | 70,480 | 24,000 | 938,685 | ||||
| Day Tot | 21,827,983 | 2,219,614 | 1,276,420 | 1,268,638 | 432,000 | 27,221,862 | |||||
| Day Count | 18 | 18 | 18 | 18 | 18 | 29 | |||||
| EG TWP | |||||||||||
| MONTH TO DATE | 4.73 | ||||||||||
| NORMAL MONTH TO DATE | |||||||||||
| YEAR TO DATE | 10.73 | ||||||||||
| NORMAL YEAR TO DATE |
2015 flowmeters -all-stations separate month worksheets.xlsxMAR
4/1/201510:36 AM
2015 MARCH 1ST QUARTER- METERS FROM WEST GOSHEN - CC COLLECTION
| DATE | HERSHEY'S MILL READING | HERSHEY'S MILL GPD | ASHBRIDGE READING | ASHBRIDGE GPD | HICKS METER READING | HICKS METER GPD | RESERVOIR READING | RESERVOIR GPD | BARKWAY READING | BARKWAY GPD |
|---|---|---|---|---|---|---|---|---|---|---|
| 3/1/2015 | ||||||||||
| 3/2/2015 | ||||||||||
| 3/3/2015 | 30,710,870 | 700,055 | 2,073,608 | 67,325 | 19,299,364 | 236,400 | 67,342,706 | 669,215 | 3,535,731 | 12,575 |
| 3/4/2015 | 30,784,536 | 736,660 | 2,074,376 | 76,800 | 19,330,306 | 309,420 | 67,424,177 | 814,710 | 3,537,073 | 13,420 |
| 3/5/2015 | ||||||||||
| 3/6/2015 | ||||||||||
| 3/7/2015 | ||||||||||
| 3/8/2015 | ||||||||||
| 3/9/2015 | 31,195,174 | 821,276 | 2,078,572 | 83,920 | 19,463,450 | 266,288 | 67,823,495 | 798,636 | 3,545,336 | 16,526 |
| 3/10/2015 | 31,287,652 | 924,780 | 2,079,461 | 88,900 | 19,499,044 | 355,940 | 67,918,505 | 950,100 | 3,546,966 | 16,300 |
| 3/11/2015 | 31,395,520 | 1,078,680 | 2,080,760 | 129,900 | 19,542,274 | 432,300 | 68,039,199 | 1,206,940 | 3,549,219 | 22,530 |
| 3/12/2015 | 31,500,706 | 1,051,860 | 2,081,820 | 106,000 | 19,580,522 | 382,480 | 68,144,836 | 1,056,370 | 3,550,980 | 17,610 |
| 3/13/2015 | 31,600,210 | 995,040 | 2,082,559 | 73,900 | 19,612,912 | 323,900 | 68,230,480 | 856,440 | 3,552,125 | 11,450 |
| 3/14/2015 | ||||||||||
| 3/15/2015 | ||||||||||
| 3/16/2015 | 31,962,500 | 1,207,633 | 2,085,494 | 97,833 | 19,699,942 | 290,100 | 68,509,640 | 930,533 | 3,556,665 | 15,133 |
| 3/17/2015 | 32,074,604 | 1,121,040 | 2,086,225 | 73,100 | 19,731,672 | 317,300 | 68,594,667 | 850,270 | 3,557,654 | 9,890 |
| 3/18/2015 | 32,178,276 | 1,036,720 | 2,086,947 | 72,200 | 19,762,264 | 305,920 | 68,675,270 | 806,030 | 3,558,777 | 11,230 |
| 3/19/2015 | ||||||||||
| 3/20/2015 | 32,371,950 | 968,370 | 2,088,355 | 70,400 | 19,819,040 | 283,880 | 68,827,658 | 761,940 | 3,560,946 | 10,845 |
| 3/21/2015 | ||||||||||
| 3/22/2015 | ||||||||||
| 3/23/2015 | 32,665,172 | 977,407 | 2,090,688 | 77,767 | 19,891,742 | 242,340 | 69,051,797 | 747,130 | 3,564,599 | 12,177 |
| 3/24/2015 | 32,753,270 | 880,980 | 2,091,371 | 68,300 | 19,920,498 | 287,560 | 69,127,623 | 758,260 | 3,565,767 | 11,680 |
| 3/25/2015 | 32,842,490 | 892,200 | 2,092,101 | 73,000 | 19,948,144 | 276,460 | 69,202,924 | 753,010 | 3,566,788 | 10,210 |
| 3/26/2015 | 32,925,852 | 833,620 | 2,092,751 | 65,000 | 19,975,372 | 272,280 | 69,272,764 | 698,400 | 3,567,758 | 9,700 |
| 3/27/2015 | 33,017,272 | 914,200 | 2,093,612 | 86,100 | 20,007,678 | 323,060 | 69,362,061 | 892,970 | 3,568,834 | 10,760 |
| 3/28/2015 | ||||||||||
| 3/29/2015 | ||||||||||
| 3/30/2015 | 33,312,854 | 985,273 | 2,095,987 | 79,167 | 20,079,378 | 239,000 | 69,590,009 | 759,827 | 3,572,388 | 11,847 |
| 3/31/2015 | 33,405,592 | 927,380 | 2,096,689 | 70,200 | 20,106,056 | 266,780 | 69,665,041 | 750,320 | 3,573,361 | 9,730 |
| 947,399 | 81,101 | 300,634 | 836,728 | 12,978 | ||||||
| 17,053,174 | 1,459,812 | 5,411,408 | 15,061,101 | 233,613 | ||||||
| 18 | 18 | 18 | 18 | 18 |
2015 flowmeters -all-stations separate month worksheets.xlsxMAR
4/1/201510:36 AM
Bar chart titled "March Precip. 4.73 - 2015" showing daily snow/rain precipitation (0 to 1.2 inches) across days 1 to 32 of March 2015.
Bar chart titled "2015 Monthly Precipitation" showing monthly precipitation totals (0 to 5 inches) from January through December 2015, with bars plotted for January, February, and March.
Line chart titled "Flowmeters March 2015" showing daily flowmeter readings (0 to 1,600,000) across days 1 to 31 of the month of March 2015.
Bar chart titled "Monthly Totals 2015 Jan-Dec" showing flowmeter readings (0 to 1,600,000) by month from January through December 2015, with daily bars plotted for January, February, and March.
EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
MEETING MINUTES
March 9, 2015
The East Goshen Township Municipal Authority held their regular public meeting on Monday, March 9, 2015 at 6:00 pm at the East Goshen Township building. Members in attendance were: Vice Chairman Dana Pizarro, Jack Yahraes, Fran Beck, and Ed McAssey. Also in attendance were: Rick Smith (Township Manager), Carmen Battavio (Township Supervisor), Mike Ellis (Pennoni), Patrick McKenna (Attorney) and Walter Wujcik (Conservancy Board).
COMMON ACRONYMS:
| BFES – Big Fish Environmental Services | MA- Municipal Authority |
|---|---|
| BOS – Board of Supervisors | NPDES – National Pollutant Discharge Elimination System |
| CB – Conservancy Board | PC – Planning Commission |
| DEP – Department of Environmental Protection | PM – Prevention Maintenance |
| EPA – Environmental protection Agency | PR – Park & Recreation Board |
| HC – Historical Commission | RCSTP – Ridley Creek Sewer Treatment Plant |
| I&I – Inflow & Infiltration | SBR – Sequencing Batch Reactor |
| LCSTP – Lockwood Chase Sewer Treatment Plant | SSO – Sanitary System Overflow |
| WAS – Waste Activated Sludge |
Call to Order & Pledge of Allegiance
Dana called the meeting to order at 7:00 pm and led those present in the Pledge of Allegiance. There was a moment of silence to remember the troops and all veterans. Dana asked if anyone would be recording the meeting and there was no response.
Chairman's Report/Other Members' Reports
- Jack reported that he attended the West Goshen meeting which was very short. No report.
Sewer Reports
1. Director of Public Works
Mark Miller reported for February 2015: Due to the weather a majority of our time was spent on equipment repairs and road repairs.
Meters: All meters were read on a daily basis.
C.C. Collection: We could not do any televising due to the cold temperatures.
R.C.Collection: Pump Stations were visited on a daily basis with no problems to report.
R.C. Plant: No problems to report.
Alarms: We responded to 19 alarms for the month of February.
PA One Calls: We received 51 PA One calls in February.
2. Pennoni Engineer's Report
Mike Ellis gave the following report:
Invoices: Invoices with summaries are provided under separate cover.
Reservoir Rd Pump Station:
- The geotechnical report and boring logs were submitted to the Township.
- We prepared a 3 rd draft/revision of the concept design consisting of: a pump station site sketch plan including conceptual diversion details and diversion piping profiles, a
F:\Data\Shared Data\Minutes\Municipal Authority\2015\MA 3-9-15 draft.doc | 1
- written outline of pump station controls and critical features, and a ballpark construction cost estimate. During further concept evaluation and vendor coordination, it was determined that suction-lift pumps on the building floor are not feasible because the maximum suction head of the available pumps is exceeded. Options were discussed with township staff, and it was decided to proceed with submersible pumps in the wet well. This concept will be presented in more detail at the March 9 th Municipal Authority meeting.
- A Water Quality Management Permit pre-application meeting with PADEP is scheduled for March 13 th at 10:00 am and will be attended by Pennoni Associates and Township staff.
- The existing conditions field survey work began on February 24 th . We completed topography on the Bow tree pond lot and across the Ridley Creek to the existing sewer interceptor, and we have begun to survey the Bow Tree Drive cartway. We anticipate another 7-8 days to complete the field topography and property boundary work. An exact schedule is not yet known due to snow cover.
Chapter 94 reports - We continue work on the 2014 Chapter 94 reports. We anticipate submitting drafts of the reports to the Township for review around March 16th.
Lockwood Chase STP Closure NPDES Permit N.O.T.- Once the snow melts and ground dries out, we will perform a site visit to the former LCSTP site to evaluate the consistency of as-built conditions with the permit plans, so that the NPDES Permit Notice of Termination paperwork can be finalized and submitted to the Chester County Conservation District.
Hershey's Mill PS and Marydell PS Diversions – The 2-year Maintenance Bonds on the Hershey's Mill PS and Marydell PS Diversions expire in July and August respectively. We recommend warranty inspections be performed by May.
Hershey's Mill PS Muffin Monster – we notified PADEP that the comminutor has been installed in the pump station for their field evaluation as required by the permit.
3. Big Fish Environmental Services
Scott reported that the Ridley Creek sewage treatment plant outfall 001 reported a weekly maximum TSS exceedance of 16 mg/L, as compared to the permit limitation of 15 mg/L on January 28, 2015. There was no discharge to Applebrook, which is identified as outfall 002. Chemical usage utilized for total phosphorus removal, pH and total alkalinity remained consistent with previous months. No mechanical or operational issues were observed during operation of the wastewater treatment process and sludge dewatering equipment. Routine preventative maintenance activities were completed.
Approval of Minutes
Jack moved to accept the minutes of February 9, 2015 as corrected. Fran seconded the motion. The motion passed unanimously.
Approval of Invoices
- Ed moved to approve payment of the following Pennoni invoices:
- a. Pennoni #626537 $ 1,306.25
- b. Pennoni #626538 $ 4.378.75
- c. Pennoni #626539 $10,394.70
Jack seconded the motion. The motion passed unanimously.
F:\Data\Shared Data\Minutes\Municipal Authority\2015\MA 3-9-15 draft.doc | 2
2. Fran moved to approve payment of the Gawthrop Invoice #128180 for $300.00. Ed seconded the motion. The motion passed unanimously.
Liaison Reports
Conservancy Board – Walter reminded everyone that Keep East Goshen Beautiful Day is on Saturday, April 11 at 8:30 am. Also the Board will have a planting in late April or early May.
Board of Supervisors – Carmen mentioned that tomorrow March 10 at 7:00 pm the BOS will have a combined meeting with the Planning Commission to review Swiss Farms and Dunkin Donuts requests.
Financial Reports
Jon Altshul provided the following report:
In February, the Municipal Authority recorded $966.25 in revenues, and $10,954.30 in expenses (all for engineering) for a variance of -$9,988. As of February 28, the fund balance was $1,576,043 of which $1,515,579 is in the construction account.
Goals
Dana will do an article for the next Township newsletter.
New Business
- The quote from Lenni Electric for a new surge protector to be added before the TVSS was reviewed. They are trying to avoid replacing the valves on the UV. The Authority members thought the main was protected. Mike will check into this.
- Phase 2 Proposal – Mike reviewed the Proposal for Professional Services for Phase 2: Progress Design and Infiltration Testing Reservoir Road Pump Station Design & Permitting. The Phase 2 Scope of Work is divided into 2 tasks – 1 Progress Design, and 2 Infiltration Testing.
The proposed schedule is:
| Notice to proceed | March 9 |
|---|---|
| 1st Progress design Submission | April 10 |
| 1st Township Review Meeting | April 17 |
| Infiltration Testing | TBD |
| NPDES Permit Pre-Application Meeting | by April 24 |
| 2nd Progress Design Submission | May 1 |
| 2nd Township Review Meeting | May 7 |
Estimated Fee is:
| Task 1 – Progress Design | $39,100.00 |
|---|---|
| Task 2 – Infiltration Testing | $ 1,800.00 |
| TOTAL | $40,900.00 |
Mike estimates the total cost for the Reservoir Road Pump Station to be $1.7 million plus 20% contingency.
Jack moved to accept the proposal as presented. Ed seconded the motion. The motion passed unanimously.
F:\Data\Shared Data\Minutes\Municipal Authority\2015\MA 3-9-15 draft.doc
3
Adjourment
There being no further business, Jack moved to adjourn the meeting. Fran seconded the motion. The motion passed unanimously. The meeting was adjourned at 8:00 pm.
Respectfully submitted,
Ruth Kiefer
Recording Secretary
F:\Data\Shared Data\Minutes\Municipal Authority\2015\MA 3-9-15 draft.doc
4
INVOICE
Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice # : 630705
Invoice Date : 04/01/2015
Project : EGMA1501
Project Name : 2015 General Services
For Services Rendered through: 3/22/2015
Reviewed Lockwood Chase STP's 2014 groundwater monitoring report approval letter from PADEP; reviewed status of PADEP permit construction completion certifications for diversion projects and began to fill out certification forms; prepared March Engineer's Report; prepared for and attended March MA meeting including Reservoir Road PS project status presentation; coordinated with Township regarding electrical surge protection of UV ballasts at RCSTP and other possible ballast failure mechanisms; and prepared Township-wide sewer drainage basins exhibit for use in Comprehensive Plan Update.
Phase : **** -- Professional Services
| Total Phase : **** -- Professional Services | Labor : | 1,756.25 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 1,756.25 | |
| Amount Due This Invoice | $1,756.25 |
| Fee : | 12,000.00 |
|---|---|
| Prior Billings : | 1,967.50 |
| Current Billings : | 1,756.25 |
| Total Billings : | 3,723.75 |
Phase : **** -- Professional Services
| Labor Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 10.75 | 115.00 | 1,236.25 |
| Staff Engineer | 2.00 | 90.00 | 180.00 |
| Associate Engineer | 4.00 | 85.00 | 340.00 |
| Labor Total: | 16.75 | 1,756.25 |
| Total Phase : **** -- Professional Services | Labor : | $1,756.25 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMA1501 – 2015 General Services | Labor : | $1,756.25 |
| Expense : | $0.00 |
[Signature] RS 4/10
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMA1501 Invoice Summary
Invoice Date 04/01/2015
| Project: | EGMA1501 | ||
|---|---|---|---|
| Pennoni Job No.: | 2015 General Services | ||
| Invoice No: | 630705 | ||
| Invoice Period: | 2/16/2015 | to | 3/22/2015 |
| Initial Authorization: | $ 12,000.00 | Date: | 4/1/2015 |
| Contract Amount: | $ 12,000.00 | ||
| Previously Invoiced: | $ 1,967.50 | ||
| Current Invoice: | $ 1,756.25 | ||
| Invoiced to Date ($): | $ 3,723.75 | ||
| Invoiced to Date (%): | 31% | ||
| Remaining Budget ($): | $ 8,276.25 | ||
| Remaining Budget (%): | 69% |
Budget by Phase:
| Phase Name: | 2015 General Services |
|---|---|
| Phase Budget: | $ 12,000.00 |
| Previously Invoiced: | $ 1,967.50 |
| Current Invoice: | $ 1,756.25 |
| Invoiced to Date ($): | $ 3,723.75 |
| Invoiced to Date (%): | 31% |
| Remaining Budget ($): | $ 8,276.25 |
| Remaining Budget (%): | 69% |
Comments: Reviewed Lockwood Chase STP's 2014 groundwater monitoring report approval letter from PADEP; reviewed status of PADEP permit construction completion certifications for diversion projects and began to fill out certification forms; prepared March Engineer's Report; prepared for and attended March MA meeting including Reservoir Road PS project status presentation; coordinated with Township regarding electrical surge protection of UV ballasts at RCSTP and other possible ballast failure mechanisms; and prepared Township-wide sewer drainage basins exhibit for use in Comprehensive Plan Update.
INVOICE
Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice # : 630706
Invoice Date : 04/01/2015
Project : EGMA1502
Project Name : 2015 Semi-Annual I&I Reports
For Services Rendered through: 3/22/2015
Performed a cursory analysis of February 2015 portable meter data.
Phase : **** -- Professional Services
| Total Phase : **** -- Professional Services | Labor : | 368.75 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 368.75 | |
| Amount Due This Invoice | $368.75 |
| Fee : | 10,500.00 |
|---|---|
| Prior Billings : | 2,053.75 |
| Current Billings : | 368.75 |
| Total Billings : | 2,422.50 |
Phase : **** -- Professional Services
| Labor Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 0.25 | 115.00 | 28.75 |
| Associate Engineer | 4.00 | 85.00 | 340.00 |
| Labor Total: | 4.25 | 368.75 |
| Total Phase : **** -- Professional Services | Labor : | $368.75 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMA1502 – 2015 Semi-Annual I&I Reports | Labor : | $368.75 |
| Expense : | $0.00 |
[Signature] RS 4/10
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMA1502 Invoice Summary
Invoice Date 04/01/2015
| Project: | EGMA1502 | ||
|---|---|---|---|
| Pennoni Job No.: | 2015 Semi-Annual I&I Reports | ||
| Invoice No: | 630706 | ||
| Invoice Period: | 1/19/2015 | to | 3/22/2015 |
| Initial Authorization: | $ 10,500.00 | Date: | 4/1/2015 |
| Contract Amount: | $ 10,500.00 | ||
| Previously Invoiced: | $ 2,053.75 | ||
| Current Invoice: | $ 368.75 | ||
| Invoiced to Date ($): | $ 2,422.50 | ||
| Invoiced to Date (%): | 23% | ||
| Remaining Budget ($): | $ 8,077.50 | ||
| Remaining Budget (%): | 77% |
Budget by Phase:
| Phase Name: | 2015 Semi-Annual I&I Reports |
|---|---|
| Phase Budget: | $ 10,500.00 |
| Previously Invoiced: | $ 2,053.75 |
| Current Invoice: | $ 368.75 |
| Invoiced to Date ($): | $ 2,422.50 |
| Invoiced to Date (%): | 23% |
| Remaining Budget ($): | $ 8,077.50 |
| Remaining Budget (%): | 77% |
Comments: Performed a cursory analysis of February 2015 portable meter data.
INVOICE
Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice # : 630707
Invoice Date : 04/01/2015
Project : EGMA1503
Project Name : 2014 Chapter 94 Reports
For Services Rendered through: 3/22/2015
Continued preparation of RCSTP, West Goshen (Chester Creek), and Westtown Chp. 94 Reports including analysis of flow and organic data and preparation of report narratives, tables, and charts.
Phase : **** -- Professional Services
| Total Phase : **** -- Professional Services | Labor : | 2,593.75 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 2,593.75 | |
| Amount Due This Invoice | $2,593.75 |
| Fee : | 14,800.00 |
|---|---|
| Prior Billings : | 6,206.25 |
| Current Billings : | 2,593.75 |
| Total Billings : | 8,800.00 |
Phase : **** -- Professional Services
| Labor Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 0.75 | 115.00 | 86.25 |
| Associate Engineer | 29.50 | 85.00 | 2,507.50 |
| Labor Total: | 30.25 | 2,593.75 |
| Total Phase : **** -- Professional Services | Labor : | $2,593.75 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMA1503 – 2014 Chapter 94 Reports | Labor : | $2,593.75 |
| Expense : | $0.00 |
[Signature] RS 4/10
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMA1503 Invoice Summary
Invoice Date 04/01/2015
| Project: | EGMA1503 | ||
|---|---|---|---|
| Pennoni Job No.: | 2015 Chapter 94 Reports | ||
| Invoice No: | 630707 | ||
| Invoice Period: | 2/16/2015 | to | 3/22/2015 |
| Initial Authorization: | $ 14,800.00 | Date: | 4/1/2015 |
| Contract Amount: | $ 10,500.00 | ||
| Previously Invoiced: | $ 6,206.25 | ||
| Current Invoice: | $ 2,593.75 | ||
| Invoiced to Date ($): | $ 8,800.00 | ||
| Invoiced to Date (%): | 84% | ||
| Remaining Budget ($): | $ 1,700.00 | ||
| Remaining Budget (%): | 16% |
Budget by Phase:
| Phase Name: | 2015 Chapter 94 Reports |
|---|---|
| Phase Budget: | $ 10,500.00 |
| Previously Invoiced: | $ 6,206.25 |
| Current Invoice: | $ 2,593.75 |
| Invoiced to Date ($): | $ 8,800.00 |
| Invoiced to Date (%): | 84% |
| Remaining Budget ($): | $ 1,700.00 |
| Remaining Budget (%): | 16% |
Comments: Continued preparation of RCSTP, West Goshen (Chester Creek), and Westtown Chp. 94 Reports including analysis of flow and organic data, and preparation of report narratives, tables, and charts.
INVOICE
Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice # : 630893
Invoice Date : 04/01/2015
Project : EGMA1504
Project Name : Reservoir Rd PS Design & Permitting
For Services Rendered through: 3/22/2015
Phase 01 - We prepared the 2nd and 3rd (final) iterative drafts of the concept site plan, profiles, diversion approach, and building layout; updated cost estimates accordingly; updated the outline of pump station design, operations, and controls parameters accordingly; continued coordination with vendors and Township staff to determine suction lift pumps are infeasible and to design for submersibles in a wet well; and prepared for the final concept plan presentation at the March MA meeting. Phase 01 is completed. FINAL INVOICE FOR PHASE 01.
Phase 02 - We prepared for and attended the permit pre-application meeting at PADEP's office. Preparation included evaluation of permitting forms and typical requirements, revisions to concept plans to address comments from March MA meeting, and coordination with Township Manager. We also prepared meeting minutes. Phase 02 is completed. FINAL INVOICE FOR PHASE 02.
Phase 09 - We initiated the progress design effort including site layout, wet well sizing and sections, pump and operating range design, and cursory evaluation of availability of 3-phase electric.
Phase : 01 -- Concept Design
| Total Phase : 01 -- Concept Design | Labor : | 2,797.50 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 2,797.50 |
Phase : 02 -- PADEP WQM Permit Pre-Application Mt
| Total Phase : 02 -- PADEP WQM Permit Pre-Application Mt | Labor : | 1,300.00 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 1,300.00 |
Phase : 09 -- Progress Design
| Total Phase : 09 -- Progress Design | Labor : | 2,522.00 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 2,522.00 | |
| Amount Due This Invoice | $6,619.50 |
| Fee : | 68,600.00 |
|---|---|
| Prior Billings : | 15,695.00 |
| Current Billings : | 6,619.50 |
| Total Billings : | 22,314.50 |
[Signature] ok RS 4/10
Continued on next page...
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date04/01/2015
| Project: | EGMA1504 | ||
|---|---|---|---|
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 630893 & 630894 | ||
| Invoice Period: | 2/16/2015 | to | 3/22/2015 |
| Initial Authorization: | $ 103,920.00 | Date: | 4/1/2015 |
| Contract Amount: | $ 103,920.00 | ||
| Previously Invoiced: | $ 15,695.00 | ||
| Current Invoice: | $ 18,607.75 | ||
| Invoiced to Date ($): | $ 34,302.75 | ||
| Invoiced to Date (%): | 33% | ||
| Remaining Budget ($): | $ 69,617.25 | ||
| Remaining Budget (%): | 67% |
Budget by Phase:
| Phase Name: | Concept Plans | Phase 01 |
|---|---|---|
| Phase Budget: | $ 13,700.00 | |
| Previously Invoiced: | $ 10,858.25 | |
| Current Invoice: | $ 2,797.50 | |
| Invoiced to Date ($): | $ 13,655.75 | |
| Invoiced to Date (%): | 99.7% | |
| Remaining Budget ($): | $ 44.25 | |
| Remaining Budget (%): | 0.3% |
Comments: Phase 01 - We prepared the 2nd and 3rd (final) iterative drafts of the concept site plan, profiles, diversion approach, and building layout; updated cost estimates accordingly; updated the outline of pump station design, operations, and controls parameters accordingly; continued coordination with vendors and Township staff to determine suction lift pumps are infeasible and to design for submersibles in a wet well; and prepared for the final concept plan presentation at the March MA meeting. Phase 01 is completed. FINAL INVOICE FOR PHASE 01.
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date04/01/2015
| Project: | EGMA1504 | ||
|---|---|---|---|
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 630893 & 630894 | ||
| Invoice Period: | 2/16/2015 | to | 3/22/2015 |
| Initial Authorization: | $ 103,920.00 | Date: | 4/1/2015 |
| Contract Amount: | $ 103,920.00 | ||
| Previously Invoiced: | $ 15,695.00 | ||
| Current Invoice: | $ 18,607.75 | ||
| Invoiced to Date ($): | $ 34,302.75 | ||
| Invoiced to Date (%): | 33% | ||
| Remaining Budget ($): | $ 69,617.25 | ||
| Remaining Budget (%): | 67% |
Budget by Phase:
| Phase Name: | PADEP WQM Permit Pre-Appllication Mt | Phase 02 |
|---|---|---|
| Phase Budget: | $ 1,400.00 | |
| Previously Invoiced: | $ - | |
| Current Invoice: | $ 1,300.00 | |
| Invoiced to Date ($): | $ 1,300.00 | |
| Invoiced to Date (%): | 93% | |
| Remaining Budget ($): | $ 100.00 | |
| Remaining Budget (%): | 7% |
Comments: Phase 02 - We prepared for and attended the permit pre-application meeting at PADEP's office. Preparation included evaluation of permitting forms and typical requirements, revisions to concept plans to address comments from March MA meeting, and coordination with Township Manager. We also prepared meeting minutes. Phase 02 is completed. FINAL INVOICE FOR PHASE 02
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date04/01/2015
| Project: | EGMA1504 | ||
|---|---|---|---|
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 630893 & 630894 | ||
| Invoice Period: | 2/16/2015 | to | 3/22/2015 |
| Initial Authorization: | $ 103,920.00 | Date: | 4/1/2015 |
| Contract Amount: | $ 103,920.00 | ||
| Previously Invoiced: | $ 15,695.00 | ||
| Current Invoice: | $ 18,607.75 | ||
| Invoiced to Date ($): | $ 34,302.75 | ||
| Invoiced to Date (%): | 33% | ||
| Remaining Budget ($): | $ 69,617.25 | ||
| Remaining Budget (%): | 67% |
Budget by Phase:
| Phase Name: | Existing Conditions Survey | Phase 03 |
|---|---|---|
| Phase Budget: | $ 23,300.00 | |
| Previously Invoiced: | $ 836.75 | |
| Current Invoice: | $ 11,988.25 | |
| Invoiced to Date ($): | $ 12,825.00 | |
| Invoiced to Date (%): | 55% | |
| Remaining Budget ($): | $ 10,475.00 | |
| Remaining Budget (%): | 45% |
Comments: Phase 03 - We performed field survey at the proposed point of connection to the Ridley Creek interceptor sewer, around the Bow Tree pond, and along a portion of Bow Tree Drive; and we created an existing conditions and topography plan from the surveyed data.
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date04/01/2015
| Project: | EGMA1504 | ||
|---|---|---|---|
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 630893 & 630894 | ||
| Invoice Period: | 2/16/2015 | to | 3/22/2015 |
| Initial Authorization: | $ 103,920.00 | Date: | 4/1/2015 |
| Contract Amount: | $ 103,920.00 | ||
| Previously Invoiced: | $ 15,695.00 | ||
| Current Invoice: | $ 18,607.75 | ||
| Invoiced to Date ($): | $ 34,302.75 | ||
| Invoiced to Date (%): | 33% | ||
| Remaining Budget ($): | $ 69,617.25 | ||
| Remaining Budget (%): | 67% |
Budget by Phase:
| Phase Name: | Stakeout In Easement Areas | Phase 04 |
|---|---|---|
| Phase Budget: | $ 3,600.00 | |
| Previously Invoiced: | $ - | |
| Current Invoice: | $ - | |
| Invoiced to Date ($): | $ - | |
| Invoiced to Date (%): | 0% | |
| Remaining Budget ($): | $ 3,600.00 | |
| Remaining Budget (%): | 100% |
Comments: ta.
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date04/01/2015
| Project: | EGMA1504 | ||
|---|---|---|---|
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 630893 & 630894 | ||
| Invoice Period: | 2/16/2015 | to | 3/22/2015 |
| Initial Authorization: | $ 103,920.00 | Date: | 4/1/2015 |
| Contract Amount: | $ 103,920.00 | ||
| Previously Invoiced: | $ 15,695.00 | ||
| Current Invoice: | $ 18,607.75 | ||
| Invoiced to Date ($): | $ 34,302.75 | ||
| Invoiced to Date (%): | 33% | ||
| Remaining Budget ($): | $ 69,617.25 | ||
| Remaining Budget (%): | 67% |
Budget by Phase:
| Phase Name: | 1636 Bow Tree Dr Bndry Survey & Easement | Phase 05 |
|---|---|---|
| Phase Budget: | $ 4,020.00 | |
| Previously Invoiced: | $ - | |
| Current Invoice: | $ - | |
| Invoiced to Date ($): | $ - | |
| Invoiced to Date (%): | 0% | |
| Remaining Budget ($): | $ 4,020.00 | |
| Remaining Budget (%): | 100% |
Comments:
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date04/01/2015
| Project: | EGMA1504 | ||
|---|---|---|---|
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 630893 & 630894 | ||
| Invoice Period: | 2/16/2015 | to | 3/22/2015 |
| Initial Authorization: | $ 103,920.00 | Date: | 4/1/2015 |
| Contract Amount: | $ 103,920.00 | ||
| Previously Invoiced: | $ 15,695.00 | ||
| Current Invoice: | $ 18,607.75 | ||
| Invoiced to Date ($): | $ 34,302.75 | ||
| Invoiced to Date (%): | 33% | ||
| Remaining Budget ($): | $ 69,617.25 | ||
| Remaining Budget (%): | 67% |
Budget by Phase:
| Phase Name: | Add'l Bndry Survey & Easement | Phase 06 |
|---|---|---|
| Phase Budget: | $ 9,000.00 | |
| Previously Invoiced: | $ - | |
| Current Invoice: | $ - | |
| Invoiced to Date ($): | $ - | |
| Invoiced to Date (%): | 0% | |
| Remaining Budget ($): | $ 9,000.00 | |
| Remaining Budget (%): | 100% |
Comments:
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date04/01/2015
| Project: | EGMA1504 | ||
|---|---|---|---|
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 630893 & 630894 | ||
| Invoice Period: | 2/16/2015 | to | 3/22/2015 |
| Initial Authorization: | $ 103,920.00 | Date: | 4/1/2015 |
| Contract Amount: | $ 103,920.00 | ||
| Previously Invoiced: | $ 15,695.00 | ||
| Current Invoice: | $ 18,607.75 | ||
| Invoiced to Date ($): | $ 34,302.75 | ||
| Invoiced to Date (%): | 33% | ||
| Remaining Budget ($): | $ 69,617.25 | ||
| Remaining Budget (%): | 67% |
Budget by Phase:
| Phase Name: | Geotechnical Boring | Phase 07 |
|---|---|---|
| Phase Budget: | $ 4,000.00 | |
| Previously Invoiced: | $ 4,000.00 | |
| Current Invoice: | $ - | |
| Invoiced to Date ($): | $ 4,000.00 | |
| Invoiced to Date (%): | 100% | |
| Remaining Budget ($): | $ - | |
| Remaining Budget (%): | 0% |
Comments:
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date04/01/2015
| Field | Value | Extra | Extra Value |
|---|---|---|---|
| Project: | EGMA1504 | ||
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 630893 & 630894 | ||
| Invoice Period: | 2/16/2015 | to | 3/22/2015 |
| Initial Authorization: | $ 103,920.00 | Date: | 4/1/2015 |
| Contract Amount: | $ 103,920.00 | ||
| Previously Invoiced: | $ 15,695.00 | ||
| Current Invoice: | $ 18,607.75 | ||
| Invoiced to Date ($): | $ 34,302.75 | ||
| Invoiced to Date (%): | 33% | ||
| Remaining Budget ($): | $ 69,617.25 | ||
| Remaining Budget (%): | 67% |
Budget by Phase:
| Field | Value | Phase |
|---|---|---|
| Phase Name: | Permanent Survey Benchmarks | Phase 08 |
| Phase Budget: | $ 4,000.00 | |
| Previously Invoiced: | $ - | |
| Current Invoice: | $ - | |
| Invoiced to Date ($): | $ - | |
| Invoiced to Date (%): | 0% | |
| Remaining Budget ($): | $ 4,000.00 | |
| Remaining Budget (%): | 100% |
Comments:
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date04/01/2015
| Field | Value | Extra | Extra Value |
|---|---|---|---|
| Project: | EGMA1504 | ||
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 630893 & 630894 | ||
| Invoice Period: | 2/16/2015 | to | 3/22/2015 |
| Initial Authorization: | $ 103,920.00 | Date: | 4/1/2015 |
| Contract Amount: | $ 103,920.00 | ||
| Previously Invoiced: | $ 15,695.00 | ||
| Current Invoice: | $ 18,607.75 | ||
| Invoiced to Date ($): | $ 34,302.75 | ||
| Invoiced to Date (%): | 33% | ||
| Remaining Budget ($): | $ 69,617.25 | ||
| Remaining Budget (%): | 67% |
Budget by Phase:
| Field | Value | Phase |
|---|---|---|
| Phase Name: | Progress Design | Phase 09 |
| Phase Budget: | $ 39,100.00 | |
| Previously Invoiced: | $ - | |
| Current Invoice: | $ 2,522.00 | |
| Invoiced to Date ($): | $ 2,522.00 | |
| Invoiced to Date (%): | 6% | |
| Remaining Budget ($): | $ 36,578.00 | |
| Remaining Budget (%): | 94% |
Comments: Phase 09 - We initiated the progress design effort including site layout, wet well sizing and sections, pump and operating range design, and cursory evaluation of availability of 3-phase electric.
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date04/01/2015
| Field | Value | Extra | Extra Value |
|---|---|---|---|
| Project: | EGMA1504 | ||
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 630893 & 630894 | ||
| Invoice Period: | 2/16/2015 | to | 3/22/2015 |
| Initial Authorization: | $ 103,920.00 | Date: | 4/1/2015 |
| Contract Amount: | $ 103,920.00 | ||
| Previously Invoiced: | $ 15,695.00 | ||
| Current Invoice: | $ 18,607.75 | ||
| Invoiced to Date ($): | $ 34,302.75 | ||
| Invoiced to Date (%): | 33% | ||
| Remaining Budget ($): | $ 69,617.25 | ||
| Remaining Budget (%): | 67% |
Budget by Phase:
| Field | Value | Phase |
|---|---|---|
| Phase Name: | Infiltration Testing | Phase 10 |
| Phase Budget: | $ 1,800.00 | |
| Previously Invoiced: | $ - | |
| Current Invoice: | $ - | |
| Invoiced to Date ($): | $ - | |
| Invoiced to Date (%): | 0% | |
| Remaining Budget ($): | $ 1,800.00 | |
| Remaining Budget (%): | 100% |
Comments:
Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS
INVOICE
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice # : 630894
Invoice Date : 04/01/2015
Project : EGMA1504
Project Name : Reservoir Rd PS Design & Permitting
For Services Rendered through: 3/22/2015
Phase 03 - We performed field survey at the proposed point of connection to the Ridley Creek interceptor sewer, around the Bow Tree pond, and along a portion of Bow Tree Drive; and we created an existing conditions and topography plan from the surveyed data.
Phase : 03 -- Existing Conditions Survey
| Description | Detail | Sub-Amount | Total |
|---|---|---|---|
| Contract Amount | $23,300.00 | ||
| Percent Complete | 55.04% | ||
| Contract Amount Completed | $12,825.00 | ||
| Less Previous Billed | $(836.75) | ||
| Phase Subtotal | $11,988.25 | ||
| Amount Due This Invoice | $11,988.25 |
ok RS 4-10
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
Project : EGMA1504 -- Reservoir Rd PS Design & Permitting Invoice # : 630893
...Continued from previous page
Phase : 01 -- Concept Design
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 7.75 | 115.00 | 891.25 |
| Senior Engineer | 3.00 | 110.00 | 330.00 |
| Project Engineer | 16.25 | 97.00 | 1,576.25 |
| Labor Total: | 27.00 | 2,797.50 |
Total Phase : 01 -- Concept Design Labor : $2,797.50 Expense : $0.00
Phase : 02 -- PADEP WQM Permit Pre-Application Mt
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 10.25 | 115.00 | 1,178.75 |
| Project Engineer | 1.25 | 97.00 | 121.25 |
| Labor Total: | 11.50 | 1,300.00 |
Total Phase : 02 -- PADEP WQM Permit Pre-Application Mt Labor : $1,300.00 Expense : $0.00
Phase : 09 -- Progress Design
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 3.50 | 115.00 | 402.50 |
| Project Engineer | 11.00 | 97.00 | 1,067.00 |
| Staff Engineer | 1.00 | 90.00 | 90.00 |
| Engineering Technician II | 12.50 | 77.00 | 962.50 |
| Labor Total: | 28.00 | 2,522.00 |
Total Phase : 09 -- Progress Design Labor : $2,522.00 Expense : $0.00
Total Project : EGMA1504 -- Reservoir Rd PS Design & Permitting Labor : $6,619.50 Expense : $0.00
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
Pennoni Associates Inc. Page: 2
Gawthrop Greenwood, PC
Attorneys at Law
17 East Gay Street, Suite 100
West Chester, PA 19381-0562
gglaw@gawthrop.com
(p) 610-696-8225
(f) 610-344-0922
www.gawthrop.com
East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380
Page: 1
03/09/2015
Client No: 6604-001M
Invoice No. 129252
General Authority Services
Fees
| Date | Timekeeper | Description | Hours | Amount |
|---|---|---|---|---|
| 02/06/2015 | JKW | Review meeting packet in preparation for Municipal Authority meeting. | 0.50 | |
| 02/09/2015 | JKW | Attend Municipal Authority meeting. | 1.30 | |
| For Current Services Rendered | 1.80 | 360.00 |
Recapitulation
| Timekeeper | Hours | Hourly Rate | Total |
|---|---|---|---|
| Jessica K. Wiesak | 1.80 | $200.00 | $360.00 |
| Item | Amount |
|---|---|
| Previous Balance | $300.00 |
| Total Current Charges | 360.00 |
| Balance Due | $660.00 |
[Signature] RS
4/10
To ensure proper credit, please write client number on your check when returning payment. Thank You.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.
Memo
To: Municipal Authority
From: Jon Altshul
Re: MA March Financial Reports
Date: April 8, 2015
In March, the Municipal Authority recorded $132 in revenues and $24,672 in expenses (including $8,292 for the quarterly overhead chargeback, $10,395 for Reservoir Rd Pump Station engineering and $5,685 for general engineering), for a variance of -$24,540. As of March 31, the fund balance was $1,551,504, of which $1,505,313 is in the construction account.
A complete list of all year-to-date expenses and revenues is provided.
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
March 2015
| Account Title | Acct # | Annual Budget | Month To Date Actual | Year To Date Actual |
|---|---|---|---|---|
| MUNICIPAL AUTHORITY BEGINNING FUND BALANCE | 1,576,043.38 | |||
| RCSTP BUDGET | ||||
| REVENUE | ||||
| INTEREST EARNED - RCSTP EXPANSION | 07341 1020 | 1,600.00 | 131.27 | 382.32 |
| GRANT REVENUE | 07392 0800 | 0.00 | 0.00 | 0.00 |
| TOTAL REVENUE | 1,600.00 | 131.27 | 382.32 | |
| EXPENSES | ||||
| R.C.-CAP. PROJ.-ENGINEER | 07424 7451 | 0.00 | 0.00 | 0.00 |
| R.C. CAP EXPANSION GEN'L CONTRACTOR | 07424 7452 | 0.00 | 0.00 | 0.00 |
| R.C. CAP EXPANSION - ELECTRICAL | 07424 7453 | 0.00 | 0.00 | 0.00 |
| R.C. CAP EXP CONTINGENCY CAPITAL | 07424 7454 | 0.00 | 0.00 | 0.00 |
| R.C. CAP EXP CONTINGENCY ONGOING | 07424 7455 | 0.00 | 0.00 | 0.00 |
| R.C. CAP EXP ADDITIONAL CONTINGENCY | 07424 7456 | 0.00 | 0.00 | 0.00 |
| TRANSFER TO SEWER SINKING FUND | 07492 0550 | 0.00 | 0.00 | 0.00 |
| TRANSFER TO AUTHORITY CAP FUND | 07492 0990 | 0.00 | 0.00 | 0.00 |
| TOTAL EXPENSES | 0.00 | 0.00 | 0.00 | |
| RCSTP NET RESULT | 1,600.00 | 131.27 | 382.32 |
U:\bmccool\2015\Municipal Authority\2015 - 03 - Municipal Authority Report.xlsx Page 1 of 3 04/08/2015
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
March 2015
| Account Title | Acct # | Annual Budget | Month To Date Actual | Year To Date Actual |
|---|---|---|---|---|
| OPERATING BUDGET | ||||
| REVENUE | ||||
| INTEREST EARNINGS | 07341 1000 | 15.00 | 1.03 | 3.64 |
| C.C. TAPPING FEES | 07364 1100 | 0.00 | 0.00 | 0.00 |
| R.C.TAPPING FEES | 07364 1110 | 14,296.00 | 0.00 | 0.00 |
| CONNECTION FEES - SEWER | 07364 1130 | 0.00 | 0.00 | 845.64 |
| MISCELLANEOUS REVENUE | 07380 1000 | 0.00 | 0.00 | 423.36 |
| TRANSFER FROM SEWER OPERATING | 07392 0500 | 105,105.00 | 0.00 | 0.00 |
| TOTAL REVENUE | 119,416.00 | 1.03 | 1,272.64 | |
| EXPENSES | ||||
| ADMINISTRATIVE WAGES | 07424 1400 | 33,323.00 | 8,292.10 | 8,292.10 |
| MISCELLANEOUS EXPENSE | 07424 3000 | 3,000.00 | 0.00 | 1,450.00 |
| MUNIC.AUTH.-AUDITING | 07424 3110 | 10,984.00 | 0.00 | 0.00 |
| ENGINEERING SERVICES | 07424 3130 | 37,300.00 | 5,685.00 | 12,518.00 |
| LEGAL SERVICES | 07424 3140 | 9,000.00 | 300.00 | 300.00 |
| M.C.-DVRFA-DEBT SERVICE | 07471 1000 | 23,240.00 | 0.00 | 0.00 |
| M.C.-DVRFA-INTEREST PAYMN | 07472 1000 | 4,169.00 | 0.00 | 0.00 |
| M.C.-DVRFA-INTEREST PAYMN | 07472 1010 | 0.00 | 0.00 | 0.00 |
| TOTAL EXPENSES | 121,016.00 | 14,277.10 | 22,560.10 | |
| OPERATING NET RESULT | (1,600.00) | (14,276.07) | (21,287.46) |
U:\bmccool\2015\Municipal Authority\2015 - 03 - Municipal Authority Report.xlsx Page 2 of 3 04/08/2015
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
March 2015
| Account Title | Acct # | Annual Budget | Month To Date Actual | Year To Date Actual |
|---|---|---|---|---|
| CAPITAL BUDGET | ||||
| REVENUE | ||||
| LOAN PROCEEDS-SEWER PROJECT | 07393 1001 | 0.00 | 0.00 | 0.00 |
| TRANSFER FROM SEWER CAP RESERVE | 07392 0900 | 0.00 | 0.00 | 0.00 |
| TOTAL REVENUE | 0.00 | 0.00 | 0.00 | |
| EXPENSES | ||||
| MARYDELL PUMP STATION - ENGINEER | 07425 1000 | 0.00 | 0.00 | 0.00 |
| MARYDELL PUMP STATION -CONSTRUCTION | 07425 2000 | 0.00 | 0.00 | 0.00 |
| MANHOLE COVER REPLACEMENTS | 07424.7405 | 0.00 | 0.00 | 0.00 |
| C.C. CAPITAL - COLLECTION | 07424.7420 | 0.00 | 0.00 | 0.00 |
| LOCHWOOD ABANDONMENT ENGINEER | 07424 7475 | 0.00 | 0.00 | 0.00 |
| LOCHWOOD ABANDONMENT CONSTRUCTION | 07424 7476 | 0.00 | 0.00 | 0.00 |
| LOCHWOOD ELIMINATION PHASE 2 | 07424 7477 | 0.00 | 0.00 | 0.00 |
| HERSHEY MILL STATION - ENGINEER | 07426 1000 | 0.00 | 0.00 | 0.00 |
| HERSHEY MILL STATION - CONSTRUCTION | 07426 2000 | 0.00 | 0.00 | 0.00 |
| RESERVE PUMP STATION - ENGINEER | 07427 1000 | 0.00 | 0.00 | 0.00 |
| RESERVE PUMP STATION - CONSTRUCTION | 07427 2000 | 0.00 | 0.00 | 0.00 |
| RESERVOIR PUMP STATION - ENGINEER | 07428 1000 | 100,000.00 | 10,394.70 | 16,767.50 |
| RESERVOIR PUMP STATION CONSTRUCTION | 07428 2000 | 0.00 | 0.00 | 0.00 |
| TOTAL EXPENSES | 100,000.00 | 10,394.70 | 16,767.50 | |
| CAPITAL NET RESULT | (100,000.00) | (10,394.70) | (16,767.50) | |
| MUNICIPAL AUTHORITY ENDING FUND BALANCE | 1,551,503.88 |
U:\bmccool\2015\Municipal Authority\2015 - 03 - Municipal Authority Report.xlsx Page 3 of 3 04/08/2015
East Goshen Township General Ledger
Report Date 04/08/15 - GL Transaction Details - PAGE 1
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07341-1000 | INTEREST EARNINGS | 0.00 | ||||||||
| 1501 | JE | 46156 | 1.44 | 02/03/15 | INTEREST | INTEREST EARNED JANUARY 2015 07 FUND | ||||
| 0.00 | 1.44 | -1.44 | ||||||||
| 1502 | 46526 | 1.17 | 03/02/15 | INTEREST | INTEREST EARNED FEBRUARY 2015 07 FUND | |||||
| 0.00 | 1.17 | -2.61 | ||||||||
| 1503 | 46944 | 1.03 | 04/02/15 | INTEREST | INTEREST EARNED MARCH 2015 07 FUND | |||||
| 0.00 | 1.03 | -3.64 | ||||||||
| 0.00 | 3.64 | -3.64 | ||||||||
| 07341-1020 | INTEREST EARNED - RCSTP EXPANSION | 0.00 | ||||||||
| 1501 | 46156 | 131.97 | 02/03/15 | INTEREST | INTEREST EARNED JANUARY 2015 07 FUND | |||||
| 0.00 | 131.97 | -131.97 | ||||||||
| 1502 | 46526 | 119.08 | 03/02/15 | INTEREST | INTEREST EARNED FEBRUARY 2015 07 FUND | |||||
| 0.00 | 119.08 | -251.05 | ||||||||
| 1503 | 46944 | 131.27 | 04/02/15 | INTEREST | INTEREST EARNED MARCH 2015 07 FUND | |||||
| 0.00 | 131.27 | -382.32 | ||||||||
| 0.00 | 382.32 | -382.32 | ||||||||
| 07364-1130 | CONNECTION FEES - SEWER | 0.00 | ||||||||
| 1501 | CR | 45967 | 423.00 | 01/16/15 | 789 | 8648 | 1 GEORGE SMITH & CHRISTINA CONLE | |||
| JE | 45968 | 141.12 | 01/16/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | |||||
| 141.12 | 423.00 | -281.88 | ||||||||
| 1502 | CR | 46296 | 423.00 | 02/13/15 | 248 | 8650 | 1 JACOBS, ROBERT & CHERYL | |||
| 46479 | 423.00 | 02/26/15 | 2381 | 8649 | 1 STOFFLET, MICHAEL | |||||
| JE | 46297 | 141.12 | 02/13/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | |||||
| 46480 | 141.12 | 02/26/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | ||||||
| 282.24 | 846.00 | -845.64 | ||||||||
| 423.36 | 1,269.00 | -845.64 | ||||||||
| 07380-1000 | MISCELLANEOUS REVENUE | 0.00 |
East Goshen Township General Ledger
Report Date 04/08/15 GL Transaction Details PAGE 2
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 1501 | JE | 45968 | 141.12 | 01/16/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | ||||
| 0.00 | 141.12 | -141.12 | ||||||||
| 1502 | 46297 | 141.12 | 02/13/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | |||||
| 46480 | 141.12 | 02/26/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | ||||||
| 0.00 | 282.24 | -423.36 | ||||||||
| 0.00 | 423.36 | -423.36 | ||||||||
| 07424-1400 | ADMINISTRATIVE WAGES | 0.00 | ||||||||
| 1503 | CD | 46874 | 8,292.10 | 03/30/15 | 2267 | 425 | EAST GOSHEN TOWNSHIP - GENERAL 1ST QTR.2015 REIMBURS. FR: MUN.A | |||
| 8,292.10 | 0.00 | 8,292.10 | ||||||||
| 8,292.10 | 0.00 | 8,292.10 | ||||||||
| 07424-3000 | MISCELLANEOUS EXPENSE | 0.00 | ||||||||
| 1501 | 45777 | 950.00 | 01/02/15 | 2260 | 2132 | PENNSYLVANIA MUNICIPAL AUTHORITIES ASSOC 2015 ACTIVE MEMBERSHIP DUES | ||||
| 46110 | 500.00 | 01/29/15 | 2263 | 2737 | COMMONWEALTH OF PA ANNUAL FEE - NPDES PERMIT -CHAP. | |||||
| 1,450.00 | 0.00 | 1,450.00 | ||||||||
| 1,450.00 | 0.00 | 1,450.00 | ||||||||
| 07424-3130 | ENGINEERING SERVICES | 0.00 | ||||||||
| 45953 | 621.50 | 01/15/15 | 2261 | 1052 | PENNONI ASSOCIATES INC. SERVICES THRU 12/7/14 GENERAL | |||||
| 46013 | 640.00 | 01/22/15 | 2262 | 1052 | PENNONI ASSOCIATES INC. SERVICE THRU 11/9/14 GEN.SERVICE | |||||
| 1,261.50 | 0.00 | 1,261.50 | ||||||||
| 1502 | 46311 | 5,571.50 | 02/13/15 | 2264 | 1052 | PENNONI ASSOCIATES INC. SERVICES THRU 1/18/15 2014 CHAP. | ||||
| 5,571.50 | 0.00 | 6,833.00 | ||||||||
| 1503 | 46649 | 5,685.00 | 03/12/15 | 2266 | 1052 | PENNONI ASSOCIATES INC. SERVICES THRU 2/15/15 2014 CHAP. | ||||
| 5,685.00 | 0.00 | 12,518.00 | ||||||||
| 12,518.00 | 0.00 | 12,518.00 |
East Goshen Township General Ledger
Report Date 04/08/15 GL Transaction Details PAGE 3
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07424-3140 | LEGAL SERVICES | 0.00 | ||||||||
| 300.00 | 03/12/15 | 2265 | 528 | GAWTHROP GREENWOOD & HALSTED LEGAL SERVICE - 1/12/15 GEN.AUT | ||||||
| 300.00 | 0.00 | 300.00 | ||||||||
| 300.00 | 0.00 | 300.00 | ||||||||
| 07428-1000 | RESERVOIR PUMP STATION - ENGINEER | 0.00 | ||||||||
| 1501 | 45954 | 137.50 | 01/15/15 | 10029 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 12/7/14 RESERV.RD ACT | ||||
| 46014 | 852.50 | 01/22/15 | 10030 | 1052 | PENNONI ASSOCIATES INC. SERVICE THRU 11/9/14 RESERVOIR R ACT.537 | |||||
| 990.00 | 0.00 | 990.00 | ||||||||
| 1502 | 46312 | 5,382.80 | 02/13/15 | 10031 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 1/18/15 RESERVOIR RD.P ACT 537 PLANNING | ||||
| 5,382.80 | 0.00 | 6,372.80 | ||||||||
| 1503 | 46650 | 10,394.70 | 03/12/15 | 10032 | 1052 | PENNONI ASSOCIATES INC. SERV. THRU 2/15/15 RESERVOIR RD. | ||||
| 10,394.70 | 0.00 | 16,767.50 | ||||||||
| 16,767.50 | 0.00 | 16,767.50 | ||||||||
| Beg Bal | 0.00 | 39,750.96 | 2,078.32 | 37,672.64 |
LENNI
ELECTRIC
CORPORATION
February 13, 2015
East Goshen Township
1580 Paoli Pike
West Chester, PA. 19380
Attn: Mr. Mark Miller
Re: Ridley Creek WWTP – TVSS Replacement
We offer a T & M budget price of $4,168.85 for the following electrical work at the above referenced location. Our price includes:
- 1 – Replace existing GE TPHE2774OME TVSS in MDP-B
| Item | Amount |
|---|---|
| Materials | $3,339.00 |
| 15% | $500.85 |
| Labor mechanic 4 hrs. @ $75.50 | $307.00 |
| Service Truck | $27.00 |
| Total | $4,168.85 |
If you have any questions, please do not hesitate to contact me directly @ 610-636-6511.
Sincerely,
LENNI ELECTRIC CORPORATION
[Signature] James C. Hallman, Jr.
James C. Hallman, Jr.
C & I Division
1020 ANDREW DRIVE WEST CHESTER, PA 19380 • 610-436-9922 • FAX 610-436-9926
AN EQUAL OPPORTUNITY EMPLOYER M/F/V
LENNI
ELECTRIC
CORPORATION
February 13, 2015
East Goshen Township
1580 Paoli Pike
West Chester, PA. 19380
Attn: Mr. Mark Miller
Re: Ridley Creek WWTP – TVSS for UV System
We offer a T & M budget price of $5,402.80 for the following electrical work at the above referenced location. Our price includes:
- 1 – Install new GE TPR7120S12WMNiD TVSS in control room after the transformer install, ahead of the UV system controls install
- LS – Rework pipe and wire
| Item | Amount |
|---|---|
| Materials | $4,092.00 |
| 15% | $613.80 |
| Labor mechanic 5 hrs. @ $75.50 | $377.50 |
| Labor apprentice 5 hrs. @ $58.50 | $292.50 |
| Service Truck | $27.00 |
| Total | $5,402.80 |
If you have any questions, please do not hesitate to contact me directly @ 610-636-6511.
Sincerely,
LENNI ELECTRIC CORPORATION
[Signature] James C. Hallman, Jr.
James C. Hallman, Jr.
C & I Division
1020 ANDREW DRIVE WEST CHESTER, PA 19380 • 610-436-9922 • FAX 610-436-9926
AN EQUAL OPPORTUNITY EMPLOYER M/F/V
Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS
April 10, 2015
Rick Smith, Township Manager
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380
Re: Proposal for Professional Services
Township Wastewater Capacity Needs Evaluation Update
Dear Mr. Smith:
Pennoni Associates Inc. is pleased to submit the following proposal to update the East Goshen Township Wastewater Capacity Needs Evaluation.
BACKGROUND
Pennoni evaluated and projected the potential maximum future wastewater flows throughout East Goshen Township in the attached “Township Wastewater Capacity Needs Evaluation” letter, dated February 9, 2007. The maximum Township-wide future public wastewater flow was projected to be 1.736 MGD. This evaluation was the basis for the recent expansion of the Ridley Creek Sewage Treatment Plant (RCSTP), several constructed pump station and gravity sewer diversions, and the planned Reservoir Road Pump Station diversion.
This evaluation is over eight years old, and actual flows, existing connections, and projected connections vary from that which was predicted in 2007. There is also interest from adjacent municipalities to connect new development(s) and an existing development with failing on-lot systems to East Goshen’s sewer system. The Needs Evaluation needs to be revisited and updated to determine East Goshen’s current wastewater needs as well as the feasibility of additional connections from other municipalities.
SCOPE OF WORK
Pennoni will update the Needs Evaluation based on existing flows, currently committed and approved flows, and potential flows from within the Township. Potential flows will be focused on large undeveloped tracts but may also include existing developments with problematic on-lot systems. The total future projected flow in the Township will be compared to the capacity of the RCSTP and the allowable capacity of the intermunicipal agreement with West Goshen Township to determine available capacity for connections from other municipalities. We will prepare a letter report to summarize the analysis in a similar format to the attached 2007 letter.
SCHEDULE
We anticipate the evaluation can be completed within 30 days of Notice to Proceed.
FEE
Our estimated fee, to be billed on a time and material basis, is $2,050.00. Work will be completed on an hourly basis, billed at the Authority’s approved rates for Pennoni for the year in which work is performed.
Christiana Executive Campus • 121 Continental Drive, Suite 207 • Newark, DE 19713 • Tel: 302-655-4451 • Fax: 302-654-2895
www.pennoni.com
Rick Smith
April 10, 2015
Page 2
Wastewater Capacity Needs Evaluation Update
Extraordinary expenses, authorized in advance and identifiable to the specific project will be billed in addition to the above stated fees. These expenses include, but are not limited to: application fees, UPS and delivery charges, and the reproduction of plans and specifications by outside services. We do not bill for such items as relatively small amounts of in-house printing, mailing expenses, reasonable telephone calls, and travel expenses.
BILLING AND PAYMENT
Fees will be billed monthly, based on actual services completed. Payment is due upon receipt of invoice. Billing and Payment shall be in accordance with Item three (3) of the below-referenced General Terms and Conditions.
The client acknowledges that the method of Billing and Payment has been discussed in detail; that the terms agreed upon can only be changed by a written addendum agreed to by both parties; and work may be stopped until payment is made in accordance with the agreement.
TERMS AND CONDITIONS
General
Pennoni Associates Inc. General Terms and Conditions (Form No. LE01, Rev. 09/2002) are considered as part of this proposal.
We appreciate this opportunity to submit our proposal. Should you have any questions or need additional information, please do not hesitate to call. Please sign and return one (1) copy of this proposal as our Notice to Proceed.
Sincerely,
PENNONI ASSOCIATES INC.
[Signature]
Michael J. Ellis, P.E.
Authority Engineer
ACCEPTED BY: ___________________________
___________________________
(Print Name and Title)
DATE: ___________________________
W:\PROJECTS\EGMA\Proposals\EGT Wastewater Needs Evaluation Update 4-10-15.docx