Municipal Authority

The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.

 

The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.

  • Five members, serving five-year terms
  • Meetings are on the 2nd Monday of the month at 7:00 P.M.
  • All township meetings are held at the Township Building and open to the public
Authority Members Term Expiration Date
Kevin Cummings, Chairman 2026
John Stipe, Vice Chairman
2029
Dana Pizzarro, Secretary 2026
Sean Ellsworth, Assistant Secretary/Treasurer 2028
Walter Wujcik, Treasurer 2028
Pennoni Associates, Engineer
Patrick M. McKenna, Esq.
Peter Hicks, BoS Liaison
Kevin Miller, Staff Liaison

 

Municipal Authority Genealogy

Audits

Documents

Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.

EAST GOSHEN MUNICIPAL AUTHORITY

August 10, 2015
7:00 PM

  1. CALL TO ORDER/PLEDGE OF ALLEGIANCE/MOMENT OF SILENCE Ask if anyone will be taping the meeting?
  2. CHAIRMAN’S REPORT/OTHER MEMBERS REPORTS
  3. SEWER REPORTS Director of Public Works Report; Pennoni Engineer’s Report; Big Fish Environmental Inc. Report with DMR’s; East Goshen Township Flows
  4. APPROVAL OF MINUTES July 13, 2015
  5. APPROVAL OF INVOICES Pennoni   Invoice #646590   $ 373.75; Pennoni   Invoice #646591   $4,715.25; Maillie   Invoice#1000046840   $8,900.00
  6. LIAISON REPORTS
  7. FINANCIAL REPORTS July 2015 Report
  8. OLD BUSINESS
  9. GOALS Submit an article for each newsletter – Due date for newsletter Need by 1/30/15 – Jack - Completed Need by 5/1/15 – Dana - Completed Need by 8/31/15 - Ed - Completed Need by 10/30/15; Obtain construction permits for the Reservoir Road Pump Station – December 31, 2015 2/6 – Test boring done, meeting with Mike to review preliminary site plan

F:\Data\Shared Data\Agendas\Municipal Authority\2015\8-10-15.doc

and discuss control options. 3/9 concept design completed, met with PA DEP. 5/11 stormwater perc test completed, scheduled to meet with CCCD on 5/21 6/8 Nothing unusual from our meeting with CCCD. Rick and Mark need to met with WG to discuss control process. 6/22 WG is ok with proposed control process

  1. Attend West Goshen Meetings quarterly – more often if needed. 1 st Quarter – Jack - Completed 2 nd Quarter – Jack - Completed 3 rd Quarter - Ed - Completed 4 th Quarter
  2. Respond to capacity requests in 45 days or less.
  3. Continue to implement I & I Plan 5/11 meeting with Mike on 5/13 to review plan
  4. Operate RCSTP in compliance with NPDES Permit February, April, May, June
  1. NEW BUSINESS
  2. CAPACITY REQUESTS
  3. ANY OTHER MATTER
  4. CORRESPONDENCE AND REPORTS OF INTEREST
  5. PUBLIC COMMENT
  6. ADJOURNMENT

F:\Data\Shared Data\Agendas\Municipal Authority\2015\8-10-15.doc

AREA CODE 610
692-7171

EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP

1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

August 3, 2015

To: Municipal Authority
From: Mark Miller
Re: July 2015 Monthly Report

Meters: All meters were read on a daily basis there were no problems to report for the month. The meters have been re-calibrated and returned, Allied will install them August 5th, weather permitting.

C.C. Collection: All pumping stations were visited on a routine basis. We had Aqua come in to clean the grease for routine maintenance.

We are still preparing Cooper Circle and Supplee Valley for road re-surfacing.

A leak was found and repaired at the Reservoir Road permanent meter, flows are back to normal.

R.C. Collection: Was visited on a routine basis. We had to repair a broken pipe at the Hunt Country Pump Station.

R.C. Plant: Was visited on a routine basis with no problems to report.

Re-sale Inspections:

Alarms: We responded to 9 alarms for July.

PA One Calls: We received 39 PA One calls for July.

EGMA 1501

[Logo: Pennoni]

MEMORANDUM

TO: East Goshen Municipal Authority Board
Rick Smith, Township Manager
FROM: Michael Ellis, P.E.
Authority Engineer
DATE: August 6, 2015
SUBJECT: Engineer’s Report

Invoices

  • Invoices with summaries are provided under separate cover.

Ridley Creek Sewage Treatment Plant (RCSTP)

  • No activity since the last report.

Reservoir Road Pump Station

  • We continued with the electrical, controls, site, and stormwater designs. We prepared draft applications for the WQM Part 2 permit, NPDES permit, two PADEP GP-5 “Utility Line Stream Crossings” permits, and one PADEP GP-8 “Temporary Road Crossings (across streams)” permit. We also prepared draft technical specifications.
  • We reviewed and provided comments on the Township’s letter to West Goshen memorializing the pump station operations and flow controls agreement.
  • Tentative schedule: Estimated Date Submit PADEP permit applications mid-September 2015 Rt. 352 soft digs for utilities September 2015 Submit PennDOT Highway Occupancy Permit December 2015 PADEP and PennDOT permit issuance mid-January 2016

Semi-Annual I&I Reports

  • We coordinated with the Public Works Department to determine which manholes portable meters should be installed to pick up flows from large 24/7 commercial uses in the upcoming round of metering.

Page 1 of 1

P:\Projects\EGMA\Memos to Board\2015\Memo to EGMA Board 2015-08-06.docx

Scott was extremely busy this month; Rick will distribute his report upon receipt at the meeting.

2015 JULY 3RD QUARTER- METERS FROM WEST GOSHEN - CC COLLECTION

Precip inchesDATEWESTTOWN WAY READINGWESTTOWN WAY GPDELLIS LANE READINGELLIS LANE GPDPAOLI PIKE READINGPAOLI PIKE GPDWILSON DRIVE READINGWILSON DRIVE GPDSUMMIT GPDNET FLOWSDATE
0.0007/01/152,097,7701,037,0008,966,60699,3005,646,61370,2504,599,014116,13024,000751,32007/01/15
0.0007/02/152,098,7731,003,0008,975,95493,4805,652,64460,3104,609,700106,86024,000742,35007/02/15
0.0007/03/15742,35007/03/15
0.0007/04/15742,35007/04/15
0.0007/05/15742,35007/05/15
0.0007/06/152,102,244867,7509,006,97877,5605,675,48157,0934,646,52992,07324,000641,02507/06/15
0.4807/07/152,103,216972,0009,015,38884,1005,681,38559,0404,656,572100,43024,000728,43007/07/15
0.0507/08/152,104,122906,0009,023,08176,9305,687,25958,7404,666,888103,16024,000667,17007/08/15
0.3407/09/152,105,084962,0009,031,49384,1205,693,15959,0004,674,96180,73024,000738,15007/09/15
1.0007/10/15738,15007/10/15
0.0007/11/15738,15007/11/15
0.0007/12/15738,15007/12/15
0.0007/13/15738,15007/13/15
0.0007/14/15738,15007/14/15
2.5007/15/152,110,857962,1679,088,32294,7155,722,70149,2374,707,86154,83324,000763,38207/15/15
0.0007/16/152,112,0711,214,0009,102,582142,6005,728,86061,5904,715,93780,76024,000929,05007/16/15
0.0007/17/15929,05007/17/15
0.0007/18/15929,05007/18/15
0.0007/19/15929,05007/19/15
0.0007/20/152,115,794930,7509,138,94090,8955,746,64244,4554,742,64866,77824,000728,62307/20/15
0.0007/21/152,116,724930,0009,147,38284,4205,751,07144,2904,751,21985,71024,000715,58007/21/15
0.0007/22/152,117,655931,0009,155,93085,4805,755,47344,0204,760,44792,28024,000709,22007/22/15
0.0007/23/152,118,546891,0009,163,68677,5605,759,77142,9804,767,88874,41024,000696,05007/23/15
0.0007/24/152,119,415869,0009,171,79081,0405,763,90641,3504,775,14972,61024,000674,00007/24/15
0.0007/25/15674,00007/25/15
0.4507/26/15674,00007/26/15
0.0007/27/152,121,909831,3339,196,41182,0705,776,71742,7034,792,80658,85724,000647,70307/27/15
0.0007/28/152,122,822913,0009,204,75983,4805,780,75840,4104,801,73889,32024,000699,79007/28/15
0.0007/29/152,123,711889,0009,212,46577,0605,784,89841,4004,809,47577,37024,000693,17007/29/15
0.1007/30/152,124,582871,0009,219,78573,2005,788,91940,2104,817,25777,82024,000679,77007/30/15
0.0007/31/152,125,466884,0005,792,97440,5504,824,83675,79024,000767,66007/31/15
4.92Day Avg936,88987,53049,86883,66224,000742,755
Day Tot16,864,0001,488,010897,6281,505,920432,00023,025,393
Day Count181718181831

EG TWP

MetricValue
MONTH TO DATE4.92
NORMAL MONTH TO DATE
YEAR TO DATE27.93
NORMAL YEAR TO DATE

f:/data/users/joanna/ 2003 flowmeters | 8/3/2015 2:58 PM

2015 JULY 3RD QUARTER- METERS FROM WEST GOSHEN - CC COLLECTION

HERSHEY'S MILL ASHBRIDGE HICKS METER RESERVOIR BARKWAY
READING GPD READING GPD READING GPD READING GPD READING GPD
39,598,66865,0922,157,81166,00022,357,658302,72075,718,981726,4503,665,4878,770
39,660,50061,8322,158,43762,60022,387,138294,80075,789,995710,1403,666,3798,920
39,889,75657,3142,160,81559,45022,476,986224,62076,028,026595,0783,669,7688,473
39,949,53659,7802,161,43762,20022,505,422284,36076,095,746677,2003,670,7319,630
40,009,57660,0402,162,04961,20022,533,524281,02076,161,347656,0103,671,6008,690
40,069,78060,2042,162,67862,90022,560,640271,16076,226,903655,5603,672,4928,920
40,432,34460,4272,166,52764,15022,685,636208,32776,618,501652,6633,678,51210,033
40,503,61271,2682,167,29676,90022,715,552299,16076,702,040835,3903,679,4329,200
40,759,16063,8872,169,71160,37522,802,111216,39876,954,725631,7133,683,3749,855
40,823,24064,0802,170,30459,30022,827,554254,43077,020,843661,1803,684,3489,740
40,886,57663,3362,170,90460,00022,853,732261,78077,087,793669,5003,685,39210,440
40,947,40460,8282,171,50059,60022,877,024232,92077,149,565617,7203,686,3189,260
41,006,54459,1402,172,06156,10022,899,768227,44077,210,521609,5603,687,1628,440
41,191,34461,6002,173,87660,50022,953,880180,37377,383,011574,9673,689,9829,400
41,253,72462,3802,174,50062,40022,977,834239,54077,446,752637,4103,691,12311,410
41,312,92459,2002,175,10660,60023,001,042232,08077,509,126623,7403,692,0689,450
41,369,81656,8922,175,70559,90023,024,498234,56077,569,966608,4003,693,0439,750
41,431,79861,9822,176,30159,60023,047,932234,34077,631,580616,1403,693,9899,460
61,627 61,876 248,890 653,268 9,436
1,109,282 1,113,775 4,480,028 11,758,820 169,841
18 18 18 18 18

f:/data/users/joanna/
2003 flowmeters

8/3/20159:45 AM

2015 SUMMARY OF METER READINGS

WESTTOWN WAY ELLIS LANE PAOLI PIKE WILSON DRIVE SUMMIT HERSHEY MILL ASHBRIDGE HICKS RESERVOIR BARKWAY
JANUARY1,037,47693,83760,55266,14324,00064,46060,156251,166706,59411,242
FEBRUARY1,023,41190,01559,01764,69524,00069,67364,656265,565683,53111,872
MARCH1,212,666123,31270,91270,48024,00094,74081,101300,634836,72812,978
APRIL1,035,13196,38164,67058,19624,00073,75869,102255,415687,6099,616
MAY950,38383,94562,53256,24224,00064,61364,751238,820640,9549,901
JUNE973,25988,78670,96087,49924,00061,54164,699270,354681,59910,009
JULY936,88987,53049,86883,66224,00061,62761,876248,890653,2689,436
AUGUST
SEPTEMBER
OCTOBER
NOVEMBER
DECEMBER
Total Flows
Monthly Ave1,024,17494,82962,64469,56024,00070,05966,620261,549698,61210,722

To
West Goshen   797,140

2015 flowmeters -all-stations separate month worksheets.xlsxSUMMARY

2015 SUMMARY OF METER READINGS

WESTTOWN WAY ELLIS LANE PAOLI PIKE WILSON DRIVE SUMMIT
JANUARY1,037,47693,83760,55266,14324,000
FEBRUARY1,023,41190,01559,01764,69524,000
MARCH1,212,666123,31270,91270,48024,000
APRIL1,035,13196,38164,67058,19624,000
MAY950,38383,94562,53256,24224,000
JUNE973,25988,78670,96087,49924,000
JULY936,88987,53049,86883,66224,000
AUGUST
SEPTEMBER
OCTOBER
NOVEMBER
DECEMBER
Total Flows
Monthly Ave1,024,17494,82962,64469,56024,000

July Precip. 4.92 - 2015

Bar chart (rotated) of daily precipitation in July 2015, totaling 4.92 inches. Bars appear on days 7 (about 0.48), 8 (about 0.05), 9 (about 0.34), 10 (about 1.0), 15 (about 2.5), 26 (about 0.45) and 31 (about 0.1); other days are zero.

  • Y-axis label: precip (scale: 0, 0.5, 1, 1.5, 2, 2.5)
  • X-axis label: snow/rain (days: 1 through 33)
  • Legend: July

2015 Monthly Precipitation

Bar chart showing monthly precipitation for 2015 from January through July (with August through December at 0). Approximate values shown by bars: January (~4.1), February (~1.6), March (~4.7), April (~4.4), May (~1.3), June (~6.6), July (~4.92).

  • Y-axis scale: 0, 1, 2, 3, 4, 5, 6, 7
  • X-axis categories: January, February, March, April, May, June, July, August, September, October, November, December
  • Legend: Series1

Flowmeters July 2015

Line chart with diamond markers showing daily flowmeter readings in July 2015 (Days 1 to 31), mostly ranging between 640,000 and 760,000, with a peak plateau around 929,050 on days 16 through 19.

  • Y-axis label: Flow's (scale: 0, 100000, 200000, 300000, 400000, 500000, 600000, 700000, 800000, 900000, 1000000)
  • X-axis label: Day of the Month (1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31)
  • Legend: July

Monthly Totals 2015 Jan-Dec

Bar chart showing daily flowmeter totals grouped by month for January through July 2015 (with August through December empty).

  • Y-axis label: Flowmeters (scale: 0, 200000, 400000, 600000, 800000, 1000000, 1200000, 1400000, 1600000)
  • X-axis label: Month (January, February, March, April, May, June, July, August, September, October, November, December)

Draft

EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
MEETING MINUTES
July 13, 2015

The East Goshen Township Municipal Authority held their regular public meeting on Monday, July 13, 2015 at 7:00 pm at the East Goshen Township building. Members in attendance were: Chairman Kevin Cummings, Jack Yahraes, Fran Beck, and Ed McAssey. Also in attendance were: Rick Smith (Township Manager), Mike Ellis (Pennoni), and Jessica Wiesak (Attorney).

COMMON ACRONYMS:

BFES – Big Fish Environmental Services MA- Municipal Authority
BOS – Board of Supervisors NPDES – National Pollutant Discharge Elimination System
CB – Conservancy Board PC – Planning Commission
DEP – Department of Environmental Protection PM – Prevention Maintenance
EPA – Environmental protection Agency PR – Park & Recreation Board
HC – Historical Commission RCSTP – Ridley Creek Sewer Treatment Plant
I&I – Inflow & Infiltration SBR – Sequencing Batch Reactor
LCSTP – Lockwood Chase Sewer Treatment Plant SSO – Sanitary System Overflow
WAS – Waste Activated Sludge

Call to Order & Pledge of Allegiance

Kevin called the meeting to order at 7:00 pm and led those present in the Pledge of Allegiance. There was a moment of silence to remember the troops and all veterans. Kevin asked if anyone would be recording the meeting and there was no response.

Chairman’s Report/Other Members’ Reports

  1. Ed reported that he attended the West Goshen meeting. They hope to submit a report to the DEP in the fall. They are still trying to find solutions to meet the required levels.

Sewer Reports

1. Director of Public Works

No report

2. Pennoni Engineer’s Report

Mike Ellis provided the following report:
Invoices: Invoices with summaries are provided under separate cover.
Ridley Creek Sewage Treatment Plant (RCSTP):
No activity since the last report.
Reservoir Rd Pump Station:
We continued with the stormwater management design, and we will submit a proposal for the Final Design and Permitting scope of work prior to the July 13th Authority meeting.
Hershey’s Mill PS and Marydell PS Diversions
The 2-year maintenance Bonds on the Hershey’s Mill PS and Marydell PS Diversions expire on July and August respectively. We recommend warranty inspections be performed ASAP if they have not already been done.

F:\Data\Shared Data\Minutes\Municipal Authority\2015\MA 7-13-15 draft.doc
1

New Connections
We performed field inspections during construction of the grinder pump and low pressure service piping at 1414 Bramble Lane.

3. Big Fish Environmental Services – Scott reported that the Ridley Creek sewage treatment plant outfall 001 achieved compliance with the NPDES discharge permit during May 2015. Discharge to Applebrook continued in May. Chemical usage utilized for total phosphorus removal, pH and total alkalinity remained consistent with previous months. No mechanical or operational issues were observed during operation of sludge dewatering equipment.

Approval of Minutes

Jack moved to accept the minutes of June 8, 2015. Fran seconded the motion. The motion passed unanimously.

Approval of Invoices

  1. Ed moved to approve payment of the following Pennoni invoices: Pennoni #642371 $ 933.75; Pennoni #642372 $ 333.75; Pennoni #642373 $10,071.50; Pennoni #642374 $ 770.00 Jack seconded the motion. The motion passed unanimously.
  2. Fran moved to approve payment of the following Gawthrop invoices: Gawthrop #133458 $ 380.00; Gawthrop #132427 $ 860.00 (Invoice has been paid)

Financial Reports

Jon Altshul provided the following report:
In June, the Municipal Authority recorded $41,287 in revenues (two Chester Creek Tap-In fees and the DCED Act 537 grant in the amount of $37,162) and $21,024 in expenses (including $9,250 for Reservoir Rd Pump Station engineering and $8,292 for the quarterly administrative chargeback) for a positive variance of $21,024. As of June 30th, the fund balance was $1,539,374, of which $1,499,162 is in the construction account. Note that I applied the grant to the construction account not the general operating account.

Goals

Ed will provide a newsletter article by 8/31/15.
Ed will attend the 3rd quarter West Goshen meeting.

New Business

Mike presented a proposal for professional services for Phase 3 – Final design and permitting. He provided a summary of tasks 1 through 10 and fees. They are ready to initiate Phase 3 which includes Task 11 Final Design; and Task 12 Permitting. He provided a tentative schedule and total cost of $63,200 for these two tasks. Jack moved to approve services 11 and 12 at a cost of $63,200. Fran seconded the motion. The motion passed unanimously.

F:\Data\Shared Data\Minutes\Municipal Authority\2015\MA 7-13-15 draft.doc
2

Adjourment

There being no further business, Jack moved to adjourn the meeting. Ed seconded the motion. The motion passed unanimously. The meeting was adjourned at 7:27 pm. The August meeting will be held on Monday, August 10 at 7:00 pm.

Respectfully submitted,

Ruth Kiefer
Recording Secretary

F:\Data\Shared Data\Minutes\Municipal Authority\2015\MA 7-13-15 draft.doc
3

[Logo: Pennoni / PENNONI ASSOCIATES INC. / CONSULTING ENGINEERS]

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 646590
Invoice Date : 07/29/2015
Project : EGMA1501
Project Name : 2015 General Services

For Services Rendered through: 7/19/2015

Prepared July Engineer's Report, and prepared for and attended July MA meeting.

Phase : **** -- Professional Services

Total Phase : **** -- Professional Services Labor : 373.75
Expense : 0.00
Phase Total : 373.75
Amount Due This Invoice $373.75
Fee : 12,000.00
Prior Billings : 7,926.50
Current Billings : 373.75
Total Billings : 8,300.25

[Handwritten: Approved - RS Charged to- 07424.3110]

Phase : **** -- Professional Services

Labor

Class Hours/Units Rate Amount
Authority Engineer 3.25 115.00 373.75
Labor Total: 3.25 373.75
Total Phase : **** -- Professional Services Labor : $373.75
Expense : $0.00
Total Project : EGMA1501 – 2015 General Services Labor : $373.75
Expense : $0.00

[Handwritten: OK TO PAY 7-15-15]

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority
EGMA1501 Invoice Summary

Invoice Date 07/29/2015

Project: EGMA1501
Pennoni Job No.: 2015 General Services
Invoice No: 646590
Invoice Period: 6/22/2015 to 7/19/2015
Initial Authorization: $ 12,000.00 Date: 7/29/2015
Contract Amount: $ 12,000.00
Previously Invoiced: $ 7,926.50
Current Invoice: $ 373.75
Invoiced to Date ($): $ 8,300.25
Invoiced to Date (%): 69%
Remaining Budget ($): $ 3,699.75
Remaining Budget (%): 31%

Budget by Phase:

Phase Name: 2015 General Services
Phase Budget: $ 12,000.00
Previously Invoiced: $ 7,926.50
Current Invoice: $ 373.75
Invoiced to Date ($): $ 8,300.25
Invoiced to Date (%): 69%
Remaining Budget ($): $ 3,699.75
Remaining Budget (%): 31%

Comments: Prepared July Engineer's Report, and prepared for an attended July MA meeting.

[Logo: Pennoni / PENNONI ASSOCIATES INC. / CONSULTING ENGINEERS]

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 646591
Invoice Date : 07/29/2015
Project : EGMA1504
Project Name : Reservoir Rd PS Design &
Permitting

For Services Rendered through: 7/19/2015

Phase 09 - Completed progress design including electrical, air release valve vendor coordination, updated PNDI search, initial stormwater management calculations, and petroleum pipeline utility coordination and plan revisions at crossings. FINAL INVOICE FOR PHASE 09.

Phase 11 - Initiated final design including electrical, stormwater management calculations and facility design, and stream crossings plans and details, and initiated preparation of specifications.

Phase 12 - Initiated preparation of PADEP Part 2 Water Quality Management permit application and PADEP GP-5 "Utility Line Stream Crossings" and GP-8 "Temporary Road Crossings (across streams)" permit applications.

Phase : 09 -- Progress Design

Total Phase : 09 -- Progress Design Labor : 2,770.00
Expense : 0.00
Phase Total : 2,770.00

[Handwritten: Approved - RS charged to- 07424.3110]

Phase : 11 -- Final Design

Total Phase : 11 -- Final Design Labor : 1,374.00
Expense : 0.00
Phase Total : 1,374.00

Phase : 12 -- Permitting

Total Phase : 12 -- Permitting Labor : 571.25
Expense : 0.00
Phase Total : 571.25
Amount Due This Invoice $4,715.25
Fee : 135,800.00
Prior Billings : 48,272.50
Current Billings : 4,715.25
Total Billings : 52,987.75

[Handwritten: OK TO PAY 7-15-15]

Continued on next page...

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

Project : EGMA1504 -- Reservoir Rd PS Design & Permitting Invoice # : 646591

...Continued from previous page

Phase : 09 -- Progress Design

Labor

Class Hours/Units Rate Amount
Authority Engineer 0.75 115.00 86.25
Senior Engineer 0.50 110.00 55.00
Project Engineer 2.25 97.00 218.25
Associate Engineer 27.00 85.00 2,295.00
Engineering Technician II 1.50 77.00 115.50
Labor Total: 32.00 2,770.00
Total Phase : 09 -- Progress Design Labor : $2,770.00
Expense : $0.00

Phase : 11 -- Final Design

Labor

Class Hours/Units Rate Amount
Authority Engineer 2.50 115.00 287.50
Project Engineer 6.00 97.00 582.00
Associate Engineer 0.50 85.00 42.50
Engineering Technician II 6.00 77.00 462.00
Labor Total: 15.00 1,374.00
Total Phase : 11 -- Final Design Labor : $1,374.00
Expense : $0.00

Phase : 12 -- Permitting

Labor

Class Hours/Units Rate Amount
Authority Engineer 0.75 115.00 86.25
Project Engineer 5.00 97.00 485.00
Labor Total: 5.75 571.25
Total Phase : 12 -- Permitting Labor : $571.25
Expense : $0.00
Total Project : EGMA1504 – Reservoir Rd PS Design & Permitting Labor : $4,715.25
Expense : $0.00

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

Pennoni Associates Inc. Page: 2

East Goshen Municipal Authority
EGMA1504 Invoice Summary

Invoice Date 07/29/2015

Project: EGMA1504
Pennoni Job No.: Reservoir Rd PS Design & Permitting
Invoice No: 646591
Invoice Period: 6/22/2015 to 7/19/2015
Initial Authorization: $ 167,120.00 Date: 7/29/2015
Contract Amount: $ 167,120.00
Previously Invoiced: $ 70,220.25
Current Invoice: $ 4,715.25
Invoiced to Date ($): $ 74,935.50
Invoiced to Date (%): 45%
Remaining Budget ($): $ 92,184.50
Remaining Budget (%): 55%

Budget by Phase:

Phase Name: Progress Design Phase 09
Phase Budget: $ 39,100.00
Previously Invoiced: $ 26,680.00
Current Invoice: $ 2,770.00
Invoiced to Date ($): $ 29,450.00
Invoiced to Date (%): 75%
Remaining Budget ($): $ 9,650.00
Remaining Budget (%): 25%

Comments: Phase 09 - Completed progress design including electrical, air release valve vendor coordination, updated PNDI search, initial stormwater management calculations, and petroleum pipeline utility coordination and plan revisions at crossings. FINAL INVOICE FOR PHASE 09

East Goshen Municipal Authority
EGMA1504 Invoice Summary

Invoice Date 07/29/2015

Project: EGMA1504
Pennoni Job No.: Reservoir Rd PS Design & Permitting
Invoice No: 646591
Invoice Period: 6/22/2015 to 7/19/2015
Initial Authorization: $ 167,120.00 Date: 7/29/2015
Contract Amount: $ 167,120.00
Previously Invoiced: $ 70,220.25
Current Invoice: $ 4,715.25
Invoiced to Date ($): $ 74,935.50
Invoiced to Date (%): 45%
Remaining Budget ($): $ 92,184.50
Remaining Budget (%): 55%

Budget by Phase:

Phase Name: Final Design Phase 11
Phase Budget: $ 47,400.00
Previously Invoiced: $ -
Current Invoice: $ 1,374.00
Invoiced to Date ($): $ 1,374.00
Invoiced to Date (%): 3%
Remaining Budget ($): $ 46,026.00
Remaining Budget (%): 97%

Comments: Phase 11 - Initiated final design including electrical, stormwater management calculations and facility design, and stream crossings plans and details, and initiated preparation of specifications.

East Goshen Municipal Authority - EGMA1504 Invoice Summary

Invoice Date 07/29/2015

ItemValue
Project:EGMA1504
Pennoni Job No.:Reservoir Rd PS Design & Permitting
Invoice No:646591
Invoice Period:6/22/2015 to 7/19/2015
Date:7/29/2015
Initial Authorization:$ 167,120.00
Contract Amount:$ 167,120.00
Previously Invoiced:$ 70,220.25
Current Invoice:$ 4,715.25
Invoiced to Date ($):$ 74,935.50
Invoiced to Date (%):45%
Remaining Budget ($):$ 92,184.50
Remaining Budget (%):55%

Budget by Phase:

Phase ItemValue
Phase Name:Permitting - Phase 12
Phase Budget:$ 15,800.00
Previously Invoiced:$ -
Current Invoice:$ 571.25
Invoiced to Date ($):$ 571.25
Invoiced to Date (%):4%
Remaining Budget ($):$ 15,228.75
Remaining Budget (%):96%

Comments: Phase 12 - Initiated preparation of PADEP Part 2 Water Quality Management permit application and PADEP GP-5 "Utility Line Stream Crossings" and GP-8 "Temporary Road Crossings (across streams)" permit applications.

[Logo: Maillie / Expertise Beyond The Numbers]

PO Box 680 Oaks, PA 19456-0680 Phone: 610-935-1420
E-mail: firm@maillie.com Web: www.maillie.com
East Goshen Municipal Authority
Attn: Mr. Rick Smith
1580 Paoli Pike
West Chester, PA 19380-6107
Client Number: 2500
Invoice: 1000046840

Date: 06/26/2015
Due Date: Upon Receipt
For examination of the financial statements of the Authority for the year ended December 31, 2014, and assistance with preparation of management Discussion and Analysis report. $8,900.00
Billed Time & Expenses $8,900.00
Invoice Total $8,900.00
APPROVED BY: [Handwritten: RS]
DATE PAID:
CHECK #:
CHARGED TO: [Handwritten: 07424.3110]
06/26/2015 05/31/2015 04/30/2015 03/31/2015 02/28/2015+ Total
8,900.00 0.00 0.00 0.00 0.00 $8,900.00

Please return this portion with payment.

ID: 2500
East Goshen Municipal Authority
610-692-7171
Invoice: 1000046840

Date: 06/26/2015
Due Date: Upon Receipt

Amount Due: $8,900.00
Amount Enclosed: $________

[Handwritten: OK TO PAY 7-15-15]

Memo

To: Municipal Authority
From: Jon Altshul
Re: MA July Financial Reports
Date: August 7, 2015

In July, the Municipal Authority recorded $20,130 in revenues (including a $20,000 transfer from the sewer operating fund) and $22,043 in expenses (including $8,900 for the 2014 Audit and $10,842 for Reservoir Road Pump Station engineering), for a negative variance of -$1,912. As of July 31st, the fund balance was $1,537,461, of which $1,488,448 is in the main construction account.

A complete list of all year-to-date expenses and revenues is provided.

EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
July 2015

Account Title Acct # Annual
Budget
Month To Date
Actual
Year To Date
Actual
MUNICIPAL AUTHORITY BEGINNING FUND BALANCE 1,539,373.75
RCSTP BUDGET
REVENUE
INTEREST EARNED - RCSTP EXPANSION 07341 1020 1,600.00 129.80 891.14
GRANT REVENUE 07392 0800 0.00 0.00 0.00
TOTAL REVENUE 1,600.00 129.80 891.14
EXPENSES
R.C.-CAP. PROJ.-ENGINEER 07424 7451 0.00 0.00 0.00
R.C. CAP EXPANSION GEN'L CONTRACTOR 07424 7452 0.00 0.00 0.00
R.C. CAP EXPANSION - ELECTRICAL 07424 7453 0.00 0.00 0.00
R.C. CAP EXP CONTINGENCY CAPITAL 07424 7454 0.00 0.00 0.00
R.C. CAP EXP CONTINGENCY ONGOING 07424 7455 0.00 0.00 0.00
R.C. CAP EXP ADDITIONAL CONTINGENCY 07424 7456 0.00 0.00 0.00
TRANSFER TO SEWER SINKING FUND 07492 0550 0.00 0.00 0.00
TRANSFER TO AUTHORITY CAP FUND 07492 0990 0.00 0.00 0.00
TOTAL EXPENSES 0.00 0.00 0.00
RCSTP NET RESULT 1,600.00 129.80 891.14
U:\bmccool\2015\Municipal Authority\2015 - 07 - Municipal Authority Report.xlsx Page 1 of 3 08/04/2015

EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
July 2015

Account Title Acct # Annual
Budget
Month To Date
Actual
Year To Date
Actual
OPERATING BUDGET
REVENUE
INTEREST EARNINGS 07341 1000 15.00 0.56 6.20
C.C. TAPPING FEES 07364 1100 0.00 0.00 6,000.00
R.C.TAPPING FEES 07364 1110 14,296.00 0.00 14,296.00
CONNECTION FEES - SEWER 07364 1130 0.00 0.00 1,268.64
MISCELLANEOUS REVENUE 07380 1000 0.00 0.00 423.36
TRANSFER FROM SEWER OPERATING 07392 0500 105,105.00 20,000.00 20,000.00
TOTAL REVENUE 119,416.00 20,000.56 41,994.20
EXPENSES
ADMINISTRATIVE WAGES 07424 1400 33,323.00 0.00 16,584.20
MISCELLANEOUS EXPENSE 07424 3000 3,000.00 0.00 1,468.05
MUNIC.AUTH.-AUDITING 07424 3110 10,984.00 8,900.00 8,900.00
ENGINEERING SERVICES 07424 3130 37,300.00 1,921.25 31,138.25
LEGAL SERVICES 07424 3140 9,000.00 380.00 2,380.00
M.C.-DVRFA-DEBT SERVICE 07471 1000 23,240.00 0.00 0.00
M.C.-DVRFA-INTEREST PAYMN 07472 1000 4,169.00 0.00 0.00
M.C.-DVRFA-INTEREST PAYMN 07472 1010 0.00 0.00 0.00
TOTAL EXPENSES 121,016.00 11,201.25 60,470.50
OPERATING NET RESULT (1,600.00) 8,799.31 (18,476.30)
CAPITAL BUDGET
U:\bmccool\2015\Municipal Authority\2015 - 07 - Municipal Authority Report.xlsx Page 2 of 3 08/04/2015

EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
July 2015

Account Title Acct # Annual
Budget
Month To Date
Actual
Year To Date
Actual
REVENUE
DCED GRANT 07354 0400 0.00 0.00 37,162.00
LOAN PROCEEDS-SEWER PROJECT 07393 1001 0.00 0.00 0.00
TRANSFER FROM SEWER CAP RESERVE 07392 0900 0.00 0.00 0.00
TOTAL REVENUE 0.00 0.00 37,162.00
EXPENSES
MARYDELL PUMP STATION - ENGINEER 07425 1000 0.00 0.00 0.00
MARYDELL PUMP STATION -CONSTRUCTION 07425 2000 0.00 0.00 0.00
MANHOLE COVER REPLACEMENTS 07424.7405 0.00 0.00 0.00
C.C. CAPITAL - COLLECTION 07424.7420 0.00 0.00 0.00
LOCHWOOD ABANDONMENT ENGINEER 07424 7475 0.00 0.00 0.00
LOCHWOOD ABANDONMENT CONSTRUCTION 07424 7476 0.00 0.00 0.00
LOCHWOOD ELIMINATION PHASE 2 07424 7477 0.00 0.00 0.00
HERSHEY MILL STATION - ENGINEER 07426 1000 0.00 0.00 0.00
HERSHEY MILL STATION - CONSTRUCTION 07426 2000 0.00 0.00 0.00
RESERVE PUMP STATION - ENGINEER 07427 1000 0.00 0.00 0.00
RESERVE PUMP STATION - CONSTRUCTION 07427 2000 0.00 0.00 0.00
RESERVOIR PUMP STATION - ENGINEER 07428 1000 100,000.00 10,841.50 71,292.00
RESERVOIR PUMP STATION CONSTRUCTION 07428 2000 0.00 0.00 0.00
TOTAL EXPENSES 100,000.00 10,841.50 71,292.00
CAPITAL NET RESULT (100,000.00) (10,841.50) (34,130.00)
MUNICIPAL AUTHORITY ENDING FUND BALANCE 1,537,461.36
U:\bmccool\2015\Municipal Authority\2015 - 07 - Municipal Authority Report.xlsx Page 3 of 3 08/04/2015

East Goshen Township General Ledger - GL Transaction Details

Report Date: 08/07/15 | MGRP18 run by BRIAN | 9 : 21 AM | PAGE 1

Acct #PerSrcTrx #DebitsCreditsBeg/End BalDateCheck/Ref #ID #Name/Description
07341-10000.00INTEREST EARNINGS
1501JE461561.4402/03/15INTERESTINTEREST EARNED JANUARY 2015 07 FUND
15010.001.44-1.44
1502465261.1703/02/15INTERESTINTEREST EARNED FEBRUARY 2015 07 FUND
15020.001.17-2.61
1503469441.0304/02/15INTERESTINTEREST EARNED MARCH 2015 07 FUND
15030.001.03-3.64
1504474070.6105/04/15INTERESTINTEREST EARNED APRIL 2015 07 FUND
15040.000.61-4.25
1505478250.7506/01/15INTERESTINTEREST EARNED MAY 2015 07 FUND
15050.000.75-5.00
1506483340.6407/02/15INTERESTINTEREST EARNED JUNE 2015 07 FUND
15060.000.64-5.64
1507487820.5608/03/15INTERESTINTEREST EARNED JULY 2015 07 FUND
15070.000.56-6.20
07341-1000************0.006.20-6.20
07341-10200.00INTEREST EARNED - RCSTP EXPANSION
150146156131.9702/03/15INTERESTINTEREST EARNED JANUARY 2015 07 FUND

East Goshen Township General Ledger

Report Date 08/07/15 GL Transaction Details PAGE 2
MGRP18 run by BRIAN 9 : 21 AM
Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
1501 0.00 131.97 -131.97
1502 46526 119.08 03/02/15 INTEREST INTEREST EARNED FEBRUARY 2015
07 FUND
1502 0.00 119.08 -251.05
1503 46944 131.27 04/02/15 INTEREST INTEREST EARNED MARCH 2015
07 FUND
1503 0.00 131.27 -382.32
1504 47407 125.90 05/04/15 INTEREST INTEREST EARNED APRIL 2015
07 FUND
1504 0.00 125.90 -508.22
1505 47825 128.37 06/01/15 INTEREST INTEREST EARNED MAY 2015
07 FUND
1505 0.00 128.37 -636.59
1506 48334 124.75 07/02/15 INTEREST INTEREST EARNED JUNE 2015
07 FUND
1506 0.00 124.75 -761.34
1507 48782 129.80 08/03/15 INTEREST INTEREST EARNED JULY 2015
07 FUND
1507 0.00 129.80 -891.14
07341-1020 **** *** ***** 0.00 891.14 -891.14
07354-0400 DCED GRANT 0.00
1506 RE 48107 37,162.00 06/17/15 48107 1 GRANT - RESERVOIR RD PUMP STA
1506 0.00 37,162.00 -37,162.00

East Goshen Township General Ledger

Report Date 08/07/15 GL Transaction Details PAGE 3
MGRP18 run by BRIAN 9 : 21 AM
Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
07354-0400 **** *** ***** 0.00 37,162.00 -37,162.00
07364-1100 C.C. TAPPING FEES 0.00
1505 47736 2,000.00 05/27/15 47736 1 TAP IN FEE - 1334 A PARK AVE
1505 0.00 2,000.00 -2,000.00
1506 47853 2,000.00 06/03/15 47853 1 TAP-IN FEE FOR 1414 BRAMBLE LN
47991 2,000.00 06/10/15 47991 1 TAP IN FEE FOR 14 RESERVOIR RD
1506 0.00 4,000.00 -6,000.00
07364-1100 **** *** ***** 0.00 6,000.00 -6,000.00
07364-1110 R.C.TAPPING FEES 0.00
1504 CR 47236 7,148.00 04/21/15 1123 7875 1 SUNNY RIDGE FARMS LLC
47278 7,148.00 04/23/15 1128 7875 1 SUNNY RIDGE FARMS LLC
1504 0.00 14,296.00 -14,296.00
07364-1110 **** *** ***** 0.00 14,296.00 -14,296.00
07364-1130 CONNECTION FEES - SEWER 0.00
1501 45967 423.00 01/16/15 789 8648 1 GEORGE SMITH & CHRISTINA CONLE
JE 45968 141.12 01/16/15 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
1501 141.12 423.00 -281.88
1502 CR 46296 423.00 02/13/15 248 8650 1 JACOBS, ROBERT & CHERYL
46479 423.00 02/26/15 2381 8649 1 STOFFLET, MICHAEL
JE 46297 141.12 02/13/15 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
46480 141.12 02/26/15 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
1502 282.24 846.00 -845.64
1505 CR 47731 423.00 05/27/15 1124 8651 1 PAPPANO, JOSEPH & PATRICIA
1505 0.00 423.00 -1,268.64

East Goshen Township General Ledger

Report Date 08/07/15 GL Transaction Details PAGE 4
MGRP18 run by BRIAN 9 : 21 AM
Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
07364-1130 **** *** ***** 423.36 1,692.00 -1,268.64
07380-1000 MISCELLANEOUS REVENUE 0.00
1501 JE 45968 141.12 01/16/15 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
1501 0.00 141.12 -141.12
1502 46297 141.12 02/13/15 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
46480 141.12 02/26/15 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
1502 0.00 282.24 -423.36
07380-1000 **** *** ***** 0.00 423.36 -423.36
07392-0500 TRANSFER FROM SEWER OPERATING 0.00
1507 48567 20,000.00 07/16/15 DEPOSIT DEPOSIT $ FROM SEWER ACCT.
1507 0.00 20,000.00 -20,000.00
07392-0500 **** *** ***** 0.00 20,000.00 -20,000.00
07424-1400 ADMINISTRATIVE WAGES 0.00
1503 CD 46874 8,292.10 03/30/15 2267 425 EAST GOSHEN TOWNSHIP - GENERAL
1ST QTR.2015 REIMBURS. FR: MUN.A
1503 8,292.10 0.00 8,292.10
1506 48284 8,292.10 06/30/15 2273 425 EAST GOSHEN TOWNSHIP - GENERAL
2ND QTR.2015 REIMBURSMT FR:MUN.A
1506 8,292.10 0.00 16,584.20
07424-1400 **** *** ***** 16,584.20 0.00 16,584.20
07424-3000 MISCELLANEOUS EXPENSE 0.00
1501 45777 950.00 01/02/15 2260 2132 PENNSYLVANIA MUNICIPAL AUTHORITIES ASSOC
2015 ACTIVE MEMBERSHIP DUES

East Goshen Township General Ledger
GL Transaction Details
PAGE 5
Report Date 08/07/15
MGRP18 run by BRIAN 9 : 21 AM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
07424-3000 1501 CD 46110 500.00 01/29/15 2263 2737 COMMONWEALTH OF PA
ANNUAL FEE - NPDES PERMIT -CHAP.
1501 1,450.00 0.00 1,450.00
1506 JE 48342 18.05 07/02/15 BANK FEE DEPOSIT SLIP ORDER 6/6/15
1506 18.05 0.00 1,468.05
07424-3000 **** *** ***** 1,468.05 0.00 1,468.05
07424-3110 MUNIC.AUTH.-AUDITING 0.00
1507 CD 48553 8,900.00 07/16/15 2275 808 MAILLIE FALCONIERO & CO.
EXAM.FINANCIAL STATEMENTS 12/31/
1507 8,900.00 0.00 8,900.00
07424-3110 **** *** ***** 8,900.00 0.00 8,900.00
07424-3130 ENGINEERING SERVICES 0.00
1501 45953 621.50 01/15/15 2261 1052 PENNONI ASSOCIATES INC.
SERVICES THRU 12/7/14 GENERAL
46013 640.00 01/22/15 2262 1052 PENNONI ASSOCIATES INC.
SERVICE THRU 11/9/14 GEN.SERVICE
1501 1,261.50 0.00 1,261.50
1502 46311 5,571.50 02/13/15 2264 1052 PENNONI ASSOCIATES INC.
SERVICES THRU 1/18/15 2014 CHAP.
1502 5,571.50 0.00 6,833.00
1503 46649 5,685.00 03/12/15 2266 1052 PENNONI ASSOCIATES INC.
SERVICES THRU 2/15/15 2014 CHAP.
1503 5,685.00 0.00 12,518.00
1504 47119 4,718.75 04/15/15 2269 1052 PENNONI ASSOCIATES INC.
SERV. THRU 3/22/15 2015 GEN.SER
1504 4,718.75 0.00 17,236.75

East Goshen Township General Ledger
GL Transaction Details
PAGE 6
Report Date 08/07/15
MGRP18 run by BRIAN 9 : 21 AM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
07424-3130 1505 CD 47583 10,136.50 05/14/15 2270 1052 PENNONI ASSOCIATES INC.
SERV.THRU 4/19/15 2015 GEN.SERV
1505 10,136.50 0.00 27,373.25
1506 47984 1,843.75 06/10/15 2272 1052 PENNONI ASSOCIATES INC.
SERVICE THRU 5/17/15 2015 GEN.SE
1506 1,843.75 0.00 29,217.00
1507 48553 1,921.25 07/16/15 2276 1052 PENNONI ASSOCIATES INC.
SERV.THRU 6/21/15 2015 SEMI-ANN
1507 1,921.25 0.00 31,138.25
07424-3130 **** *** ***** 31,138.25 0.00 31,138.25
07424-3140 LEGAL SERVICES 0.00
1503 46649 300.00 03/12/15 2265 528 GAWTHROP GREENWOOD & HALSTED
LEGAL SERVICE - 1/12/15 GEN.AUT
1503 300.00 0.00 300.00
1504 47119 840.00 04/15/15 2268 528 GAWTHROP GREENWOOD & HALSTED
LEGAL SERVICE 2/6-2/9/15 GEN.AUT
1504 840.00 0.00 1,140.00
1506 47984 860.00 06/10/15 2271 528 GAWTHROP GREENWOOD & HALSTED
LEGAL SERV. 4/7-4/13/15 GEN.AUT
1506 860.00 0.00 2,000.00
1507 48553 380.00 07/16/15 2274 528 GAWTHROP GREENWOOD & HALSTED
LEGAL SERVICE 6/3-6/8/15 GEN.AU
1507 380.00 0.00 2,380.00
07424-3140 **** *** ***** 2,380.00 0.00 2,380.00

East Goshen Township General Ledger
GL Transaction Details
PAGE 7
Report Date 08/07/15
MGRP18 run by BRIAN 9 : 21 AM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
07428-1000 RESERVOIR PUMP STATION - ENGINEER 0.00
1501 45954 137.50 01/15/15 10029 1052 PENNONI ASSOCIATES INC.
SERV.THRU 12/7/14 RESERV.RD ACT
46014 852.50 01/22/15 10030 1052 PENNONI ASSOCIATES INC.
SERVICE THRU 11/9/14 RESERVOIR R
ACT.537
1501 990.00 0.00 990.00
1502 46312 5,382.80 02/13/15 10031 1052 PENNONI ASSOCIATES INC.
SERV.THRU 1/18/15 RESERVOIR RD.P
ACT 537 PLANNING
1502 5,382.80 0.00 6,372.80
1503 46650 10,394.70 03/12/15 10032 1052 PENNONI ASSOCIATES INC.
SERV. THRU 2/15/15 RESERVOIR RD.
1503 10,394.70 0.00 16,767.50
1504 47120 18,607.75 04/15/15 10033 1052 PENNONI ASSOCIATES INC.
SERV. THRU 3/22/15 RESERVOIR RD.
DESIGN & PERMITTING
1504 18,607.75 0.00 35,375.25
1505 47584 15,825.75 05/14/15 10034 1052 PENNONI ASSOCIATES INC.
SERV.THRU 4/19/15 RESERVOIR RD.
DESIGN & PERMITTING
1505 15,825.75 0.00 51,201.00
1506 47990 9,249.50 06/10/15 10035 1052 PENNONI ASSOCIATES INC.
SERV.THRU 5/17/15 RESERVOIR RD
1506 9,249.50 0.00 60,450.50
1507 48554 10,841.50 07/16/15 10036 1052 PENNONI ASSOCIATES INC.
SERV.THRU 6/21/15 - RESERVR.RD P
DESIGN & PERMITTING
1507 10,841.50 0.00 71,292.00

East Goshen Township General Ledger
GL Transaction Details
PAGE 8
Report Date 08/07/15
MGRP18 run by BRIAN 9 : 21 AM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
07428-1000 **** *** ***** 71,292.00 0.00 71,292.00
Grand Total 132,185.86 80,470.70 51,715.16

[Seal: WEST GOSHEN TOWNSHIP 1817]

WEST GOSHEN SEWER AUTHORITY

848 South Concord Road • West Chester, Pennsylvania 19382
610-696-0900 • Fax 610-429-9360

FYI

[Stamp: RC EWSO JUL 20 2015 By [initial]]

July 15, 2015

Mimi Gleason, Township Manager
West Whiteland Township
101 Commerce Drive
Exton, PA 19341

Mr. Rick Smith
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380

Mr. Robert Pingar
Westtown Township
P.O. Box 79
Westtown, PA 19395-0079

Ladies and Gentlemen:

Please find enclosed the West Goshen Sewer Authority’s Annual Financial Statement for the Fiscal Year 2014.

Sincerely,

Tina Charron
Recording Secretary

Enclosure

[Handwritten note: 7-23-15
LET ME KNOW IF YOU WANT A COPY OF THE FULL AUDIT
Rick]

WEST GOSHEN SEWER AUTHORITY

MANAGEMENT'S DISCUSSION AND ANALYSIS - UNAUDITED

This discussion and analysis of the West Goshen Sewer Authority of West Goshen, Pennsylvania, provides an overview of the Authority's performance for the year ended December 31, 2014. Please read it in conjunction with the Authority's financial statements, which begin on page 9.

FINANCIAL HIGHLIGHTS

  • The Authority completed $54,073 of capital improvement projects during 2014.
  • Tapping fees for 2014 were $122,533; a decrease of $552,747 from 2013.
  • Lease rental for 2014 was $407,010; an increase of $13,345 from 2013.
  • Investment income was $36,178; an increase of $320 from 2013.
  • As of December 31, 2014, the Authority reported an ending net position of $22,751,626, a decrease of $343,229 as compared to the prior year.
  • The Authority incurred $154,011 in legal fees to try and prevent the United States Environmental Protection Agency and DEP from adopting unjustified nutrient limits.

USING THIS ANNUAL REPORT

This annual report consists of three parts: management's discussion and analysis, financial statements, and notes. The notes explain in more detail some of the information in the financial statements.

Required Financial Statements

The financial statements report information about the Authority using full accrual accounting methods as utilized by similar business activities in the private sector. These statements offer short and long-term financial information about its activities.

The statement of net position includes all of the Authority's assets and liabilities and provides information about the nature and amounts of investments in resources (assets) and obligations (liabilities). It also provides the basis for evaluating the capital structure of the Authority and assessing the liquidity and financial flexibility of the Authority. All of the current year's revenues and expenses are accounted for in the statement of revenues, expenses, and changes in net position. This statement measures the Authority's profitability and creditworthiness. The statement of cash flows provides information about the Authority's cash receipts and cash payments during the reporting period. The statement reports cash receipts, cash payments, and net changes in cash resulting from operations, investing, and capital and related financing activities and provides answers to such questions as “From where did cash come?,” “For what was cash used?,” and “What was the change in cash balance during the reporting period?”

- 3 -

WEST GOSHEN SEWER AUTHORITY

MANAGEMENT'S DISCUSSION AND ANALYSIS - UNAUDITED (CONT'D)

FINANCIAL ANALYSIS OF THE AUTHORITY

One of the most important questions asked about the Authority's finances is, “Is the Authority better off or worse off as a result of the year's activities?” The statement of net position and the statement of revenues, expenses, and changes in net position tables supply information about the Authority's activities in a way that will help answer this question. These two statements report the net position of the Authority and changes in them. You can think of the Authority's net position (the difference between assets and liabilities) as one way to measure financial health or financial position. Over time, increase or decrease in the Authority's net position is one indicator of whether its financial health is improving or deteriorating. However, you will need to also consider other non-financial factors such as changes in economic conditions, population growth, and new or changed legislation.

The Authority's assets exceeded liabilities by $22,751,626 at the close of 2014. Our analysis focuses on the net position (Table 1) and the changes in net position (Table 2) of the Authority.

Table 1

WEST GOSHEN SEWER AUTHORITY'S NET POSITION
DECEMBER 31, 2014, 2013, AND 2012
2014 2013 2012
Assets:
Current and Other Assets $ 6,688,826 $ 6,752,772 $ 6,298,191
Capital Assets 17,850,154 18,615,860 19,353,881
Total Assets 24,538,980 25,368,632 25,652,072
Current Liabilities 442,354 521,777 489,029
Noncurrent Liabilities 1,345,000 1,752,000 2,140,000
Total Liabilities 1,787,354 2,273,777 2,629,029
Net Position:
Net Investment in Capital Assets 16,098,154 16,475,860 16,843,881
Unrestricted 6,653,472 6,618,995 6,179,162
Total Net Position $ 22,751,626 $ 23,094,855 $ 23,023,043

The largest portion of the Authority's net position reflects its investment in capital assets (land, buildings, equipment, infrastructure, and construction-in-progress) less any related debt used to acquire those assets that is still outstanding. The majority of the outstanding debt of the Authority was incurred for the significant upgrade and expansion to the Wastewater Treatment Plant. Although the Authority's investment in its capital assets is reported net of related debt, it should be noted that the resources needed to repay this debt must be provided from other sources, since the capital assets themselves cannot be used to liquidate these liabilities. The Authority currently has over $6,609,139 in unrestricted cash and investments that can be used for capital improvements and/or repayment of debt.

- 4 -

WEST GOSHEN SEWER AUTHORITY

MANAGEMENT'S DISCUSSION AND ANALYSIS - UNAUDITED (CONT'D)

2014 Revenue Sources

[Pie chart showing 2014 Revenue Sources.]

  • Charges for Services: 18.6%
  • Investment Income: 4.3%
  • Other: 15.3%
  • Lease Rentals, West Goshen Township: 61.8%

2014 Expenses

[Pie chart showing 2014 Expenses.]

  • Engineering Fees: 2.0%
  • Interest on Bonds: 2.0%
  • Legal: 15.0%
  • Administrative Expenses: 2.0%
  • Depreciation Expenses: 79.0%

- 6 -

WEST GOSHEN SEWER AUTHORITY

MANAGEMENT'S DISCUSSION AND ANALYSIS - UNAUDITED (CONT'D)

Summary of Organization and Business

The West Goshen Sewer Authority, at the request of the Township Board of Supervisors, constructed the West Goshen Township Sewerage System. Although the Authority retains ownership of the system, it is leased to the Township through the Board of Supervisors. The Township of West Goshen is responsible for operating the entire system, for maintenance and repair, and for establishing and collecting sewer rentals from users of the system. All sewer revenues of the Township are pledged for the payment of the sewer system operating expenses and lease rentals. Lease rentals in the amount of $407,010 were paid to the Authority for 2014.

The sewerage system, particularly the pumping stations, force mains, interceptors, and treatment plant, was constructed with sufficient capacity to take care of the Township needs many years into the future. When new developments are constructed and/or the service is extended to existing homes, developers and residents are charged a tapping fee to connect to the system. Revenue generated from tapping fees for 2014 amounted to $122,533. Tapping fee revenue can be used to pay down debt or pay for capital projects.

In 2012, the Authority filed Civil Action against the United States Environmental Protection Agency (“EPA”), to challenge action taken by the EPA in its establishment of a TMDL (phosphorus) for Goose Creek. In December 2013, the Sewer Authority entered into an Interim Settlement Agreement with the EPA for the reassessment and reconsideration of Goose Creek. This process should be complete by 2017.

In addition to taking care of the needs of the Township, there is sufficient capacity available in the present system to permit the Authority to provide a limited amount of sewerage service outside of the Township. The Authority currently has written agreements with West Whiteland Township, East Goshen Township, Westtown Township, and Thornbury Township to purchase sewerage capacity in the Treatment Plant.

CAPITAL ASSETS AND DEBT ADMINISTRATION

Capital Assets

The Authority's investment in capital assets as of December 31, 2014 amounted to $17,850,154, net of accumulated depreciation. This investment in capital assets includes land and land improvements, the wastewater treatment plant, the pumping stations, the sewer interceptors and force mains, the machinery and equipment, and any construction-in-progress. The total decrease in the Authority's investment in capital assets for the current fiscal year was $765,706, net of accumulated depreciation. The amount of accumulated depreciation to date is $20,390,591.

- 7 -

WEST GOSHEN SEWER AUTHORITY

MANAGEMENT'S DISCUSSION AND ANALYSIS - UNAUDITED (CONT'D)

Table 3

WEST GOSHEN SEWER AUTHORITY'S CAPITAL ASSETS
DECEMBER 31, 2014, 2013, AND 2012
2014 2013 2012
Buildings and Improvements $ 12,660,768 $ 12,660,768 $ 12,660,768
Equipment 8,506,930 8,437,644 8,329,215
Land Improvements 603,665 603,665 603,665
Land 82,083 82,083 82,083
Infrastructure 16,387,299 16,387,299 16,379,299
Construction-in-progress - 54,073 108,429
Total Capital Assets 38,240,745 38,225,532 38,163,459
Less Accumulated Depreciation (20,390,591) (19,609,672) (18,809,578)
Capital Assets, Net of Depreciation $ 17,850,154 $ 18,615,860 $ 19,353,881

Major capital additions for the current fiscal year included the following:

  • Grinders at Taylor Run Pump Stations

Additional information about the Authority's capital assets is presented in Note 4 to the financial statements.

Long-term Debt

As of December 31, 2014, the Authority had $1,752,000 in notes outstanding versus $2,140,000 in 2013 – a decrease of 18.1 percent. Additional information about the Authority's long-term debt can be found in Note 5 to the financial statements.

NEXT YEAR'S PROJECTS

  • Filtrate Pretreatment and other projects     $250,000
  • New Gas Boiler     $100,000

REQUEST FOR INFORMATION

This financial report was designed to provide a general overview of the West Goshen Sewer Authority's finances for those with an interest in the government's finances. Questions concerning any of the information provided herein or requests for additional financial information should be addressed to: Secretary, West Goshen Sewer Authority, 848 South Concord Road, West Chester, PA 19382.