Municipal Authority
The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.
The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.
- Five members, serving five-year terms
- Meetings are on the 2nd Monday of the month at 7:00 P.M.
- All township meetings are held at the Township Building and open to the public
| Authority Members | Term Expiration Date |
| Kevin Cummings, Chairman | 2026 |
| John Stipe, Vice Chairman |
2029 |
| Dana Pizzarro, Secretary | 2026 |
| Sean Ellsworth, Assistant Secretary/Treasurer | 2028 |
| Walter Wujcik, Treasurer | 2028 |
| Pennoni Associates, Engineer | |
| Patrick M. McKenna, Esq. | |
| Peter Hicks, BoS Liaison | |
| Kevin Miller, Staff Liaison |
Documents
Back to the list | Open the original PDF
Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.
EAST GOSHEN MUNICIPAL AUTHORITY
December 14, 2015
7:00 PM
1. CALL TO ORDER/PLEDGE OF ALLEGIANCE/MOMENT OF SILENCE
a. Ask if anyone will be taping the meeting?
2. CHAIRMAN’S REPORT/OTHER MEMBERS REPORTS
3. SEWER REPORTS
4.
a. Director of Public Works Report
b. Pennoni Engineer’s Report
c. Big Fish Environmental Inc. Report with DMR’s
3. APPROVAL OF MINUTES
a. November 9, 2015
4. APPROVAL OF INVOICES
| a. Pennoni | Invoice #665054 | $ 172.50 |
|---|---|---|
| b. Pennoni | Invoice #665055 | $ 86.25 |
| c. Pennoni | Invoice #665360 | $6,690.75 |
| d. Gawthrop | Invoice #137649 | $ 380.00 |
| e. Gawthrop | Invoice #139094 | $ 780.00 |
| f. Shainline Excavating | #39818 | $1,900.00 |
5. LIAISON REPORTS
6 . FINANCIAL REPORTS
a. November 2015 Report
7. OLD BUSINESS
8. GOALS
a. Submit an article for each newsletter – Due date for newsletter
Need by 1/30/15 – Jack - Completed
Need by 5/1/15 – Dana - Completed
Need by 8/31/15 - Ed - Completed
Need by 10/30/15 – Dana - Completed
b. Obtain construction permits for the Reservoir Road Pump Station – December 31, 2015 2/6 – Test boring done, meeting with Mike to review preliminary site plan
F:\Data\Shared Data\Agendas\Municipal Authority\2015\12-14-15.doc
and discuss control options. 3/9 concept design completed, met with PA DEP. 5/11 stormwater perc test completed, scheduled to meet with CCCD on 5/21 6/8 Nothing unusual from our meeting with CCCD. Rick and Mark need to meet with WG to discuss control process. 6/22 WG is ok with proposed control process
c. Attend West Goshen Meetings quarterly – more often if needed.
1st Quarter – Jack - Completed
2nd Quarter – Jack - Completed
3rd Quarter - Ed - Completed
4th Quarter
d. Respond to capacity requests in 45 days or less. 930 North Chester Road, 3 & 5 School Lane
e. Continue to implement I & I Plan 5/11 meeting with Mike on 5/13 to review plan
f. Operate RCSTP in compliance with NPDES Permit February, April, May, June, July, August, September, October
9. NEW BUSINESS
a. Consider 2016 ABC Goals
b. Appointment of Solicitor
c. Reservoir Road Reallocation of Budget
d. Consider proposal for preparation of O&M Manual
e. Big Fish Price Increase
f. Pennoni 2016 Fee schedule
10. CAPACITY REQUESTS
a. 942 Cornwallis Drive Sewer Capacity
11. ANY OTHER MATTER
12. CORRESPONDENCE AND REPORTS OF INTEREST
a. East Goshen Township Comprehensive Plan 2015
13. PUBLIC COMMENT
14. ADJOURNMENT
F:\Data\Shared Data\Agendas\Municipal Authority\2015\12-14-15.doc
AREA CODE 610
692-7171
EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199
December 11, 2015
To: Municipal Authority
From: Mark Miller
Re: November 2015 Monthly Report
Meters: We checked all meters once a week, no problems to report.
Average Flow – 820,362
November Precipitation – 1.97
C.C. Collection: We checked all pumping stations on a daily basis with no problems to report. We will be pulling pumps this month as part of our routine maintenance.
We replaced the manhole castings on Amstel Way; they were the old style lids. We will be replacing several others in the neighborhood.
R.C. Collection: All pump stations were visited on a routine basis with no problems to report. Building maintenance was performed in house.
I was asked to take a tour of the West Goshen plant last week. I asked Jack if he wanted to take a field trip; we toured the plant with David Woodward and their new Engineer. We can talk at our meeting.
R.C. Plant: Was visited on a routine basis with no problems to report.
Re-sale Inspections:
Alarms: We responded to 2 alarms for November.
PA One Calls: We received 31 PA One calls for November.
EGMA 1501
Pennoni
MEMORANDUM
| TO: | East Goshen Municipal Authority Board Rick Smith, Township Manager |
|---|---|
| FROM: | Michael Ellis, P.E. Authority Engineer |
| DATE: | December 10, 2015 |
| SUBJECT: | Engineer’s Report |
Invoices
- Invoices with summaries are provided under separate cover.
Ridley Creek Sewage Treatment Plant (RCSTP)
- We met with the PW Department to determine the desired content for a new Standard Operating Procedures / O&M Manual for the RCSTP and the Township’s pump stations. A proposal to prepare the Manual was submitted.
Reservoir Road Pump Station
- Soft dig test pits at the proposed petroleum products pipeline crossings were performed on November 13, 2015. We observed and documented the pipeline locations and depths. Design plans were updated and resubmitted to the three utility companies for approval of the proposed crossings. Williams-Transco has approved the plans, and we are awaiting responses from Sunoco and PPL-IEC.
- Aqua Water provided a “will serve” letter for a water service to the pump station.
- Design plans are 99% complete subject to addressing limited comments from Public Works. We are awaiting comments from the Township Codes Department also.
- Application packages were submitted on November 19, 2015 to PADEP for the Ridley Creek GP-5 “Utility Line Stream Crossings” and GP-8 “Temporary Road Crossings (across streams)” permits and for the Chester Creek Small Projects Joint Permit for the pump station site and Chester Creek utility crossing.
- The application package for an Individual NPDES Permit for Stormwater Discharges Associated with Construction Activities was submitted to the Chester County Conservation District on December 7, 2015.
- We anticipate submitting the PennDOT Highway Occupancy Permit application for force main construction along and across E. Strasburg Road and Rt. 352, including detour route plans for road closures, by December 15, 2015.
Page 1 of 2
P:\Projects\EGMA\Memos to Board\2015\Memo to EGMA Board 2015-12-10.docx
EGMA 1501
- The tentative schedule follows: Estimated Date Submit PADEP GP and JP Permit applications November 19, 2015 Submit NPDES Permit application December 7, 2015 Submit PennDOT HOP application for force main December 15, 2015 Submit PADEP WQM Part II Permit application December 21, 2015 PennDOT Permit issuance January 2016 PADEP and CCCD Permit issuances March-April 2016
Semi-Annual I&I Reports
- The PW Department plans to download portable meter data and forward to us by December 14, 2015. We intend to analyze data and prepare a semi-annual I&I Report by the end of December.
New Connections
- We reviewed a couple iterations of a grinder pump plan submission for a proposed new house on a subdivided parcel at 930 N. Chester Road.
Page 2 of 2
P:\Projects\EGMA\Memos to Board\2015\Memo to EGMA Board 2015-12-10.docx
Big Fish Environmental Services Inc.
Monthly Operations Report: November 2015
Executive Summary
The Ridley Creek sewage treatment plant outfall 001 achieved compliance with the NPDES discharge permit during October 2015. Discharge to Applebrook continued during October. Chemical usage utilized for total phosphorus removal, pH and total alkalinity remained consistent with previous months. No mechanical or operational issues were observed during operation of sludge dewatering equipment.
Treatment Process Operation
During October 2015, there were no exceedances of the final effluent discharge limitations for outfall 001. Additional TSS samples were collected twice per week to allow for a means to calculate a weekly average. The total phosphorus monthly average concentration of 0.34 mg/L as compared to the permitted limitation of 0.50 mg/L. Table 1 illustrates the final effluent composite sample data reported for the August 2015 eDMR. During the month, the final effluent total phosphorus concentration discharged ranged from 0.27 mg/L to 0.39 mg/L. The aluminum sulfate daily average slightly decreased to 83.2 gpd as compared to October’s average of 89.9 gpd.
Table 1
October 2015 - Final Effluent - Out Fall 001
| NPDES Permit Discharge Limitations | Flow | CBOD5 | TSS | NH4-N | Phosphorus, Total, mg/L | Fecal Coliform | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | Geo Mean | Geo Mean | |
| 0.75 | 20 | 125 | 10 | 131 | 7 | 44 | 0.5 | 3 | 200 | 1,000 | |
| Instantaneous Maximum | 40 | 42 | |||||||||
| Sample Date | |||||||||||
| October 6, 2015 | 0.188 | 2.0 | 3.1 | 4 | 6 | 0.971 | 1.52 | 0.33 | 0.52 | 1 | 0.0000 |
| October 8, 2015 | 0.177 | 4 | 6 | ||||||||
| October 13, 2015 | 0.178 | 2.3 | 3.4 | 4 | 6 | 1.650 | 2.45 | 0.39 | 0.58 | 1 | 0.0000 |
| October 15, 2015 | 0.194 | 6 | 10 | ||||||||
| October 20, 2015 | 0.206 | 2.0 | 3.4 | 5 | 9 | 4.57 | 7.85 | 0.27 | 0.46 | 1 | 0.0000 |
| October 22, 2015 | 0.182 | 3 | 5 | ||||||||
| October 27, 2015 | 0.191 | 2.3 | 3.7 | 6 | 10 | 0.200 | 0.32 | 0.35 | 0.56 | 1 | 0.0000 |
| October 30, 2015 | 0.292 | 3 | 7 | ||||||||
| Average | 0.201 | 2.2 | 3.4 | 4 | 7 | 1.848 | 3.04 | 0.34 | 0.53 | 1 | 0.0000 |
| Minimum | 0.177 | 2.0 | 3.1 | 3 | 5 | 0.200 | 0.32 | 0.27 | 0.46 | 1 | 0.0000 |
| Maximum | 0.292 | 2.3 | 3.7 | 6 | 10 | 4.570 | 7.85 | 0.39 | 0.58 | 1 | 0.0000 |
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 1 of 7
Big Fish Environmental Services Inc.
Discharge to Applebrook, Outfall 002, continued during October 2015. Table 1 illustrates the final effluent composite sample data reported for the October 2015 eDMR. There were exceedances of the permitted discharge limitations for Outfall 002.
Table 2
October 2015 - Applebrook - Out Fall 002
| NPDES Permit Discharge Limitations | Flow | CBOD5 | TSS | NH4-N | Phosphorus, Total, mg/L | Fecal Coliform | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | Geo Mean | Geo Mean | |
| 0.75 | 20 | 125 | 21 | 131 | 7 | 44 | 0.5 | 3 | 200 | 1,000 | |
| Instantaneous Maximum | 40 | 42 | |||||||||
| Sample Date | |||||||||||
| October 6, 2015 | 0.134 | 2.0 | 2.2 | 4.0 | 4.5 | 1.0 | 1.1 | 0.3 | 0.4 | 1.0 | 0.0 |
| October 8, 2015 | 0.128 | 4.0 | 4.3 | ||||||||
| October 13, 2015 | 0.133 | 2.3 | 2.5 | 4.0 | 4.4 | 1.7 | 1.8 | 0.4 | 0.4 | 1.0 | 0.0 |
| October 15, 2015 | 0.128 | 6.0 | 6.4 | ||||||||
| October 20, 2015 | 0.114 | 2.0 | 1.9 | 5.0 | 4.7 | 4.6 | 4.3 | 0.3 | 0.3 | 1.0 | 0.0 |
| October 22, 2015 | 0.118 | 3.0 | 2.9 | ||||||||
| October 27, 2015 | 0.126 | 2.3 | 2.4 | 6.0 | 6.3 | 0.2 | 0.2 | 0.4 | 0.4 | 1.0 | 0.0 |
| October 30, 2015 | 0.108 | 3.0 | 2.7 | ||||||||
| Average | 0.1235 | 2.2 | 2.3 | 4 | 4.5 | 1.85 | 1.86 | 0.34 | 0.36 | 1 | 0.0000 |
| Minimum | 0.1080 | 2.0 | 1.9 | 3 | 2.7 | 0.20 | 0.211 | 0.27 | 0.26 | 1 | 0.0000 |
| Maximum | 0.1336 | 2.3 | 2.5 | 6 | 6.4 | 4.57 | 4.34 | 0.39 | 0.43 | 1 | 0.0000 |
Table 3 illustrates the influent wastewater pollutant loadings for October 20115. The influent loadings remained within the treatment facility design loadings.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 2 of 7
Big Fish Environmental Services Inc.
Table 3
October 2015 - Influent Wastewater
| Design Basis | Flow | BOD5 | TSS | NH4-N | TKN, mg/L | Phosphorus, Total, mg/L | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | |
| 335 | 2,098 | 320 | 2,001 | 32 | 200 | 48 | 301 | 9.1 | 57 | ||
| Sample Date | |||||||||||
| October 6, 2015 | 0.344 | 118 | 339 | 146 | 419 | 35.4 | 102 | 43.9 | 126 | 5.5 | 16 |
| October 13, 2015 | 0.374 | 134 | 384 | 103 | 296 | 36.3 | 104 | 46.3 | 145 | 4.9 | 14 |
| October 20, 2015 | 0.376 | 95.9 | 275 | 102 | 293 | 39.0 | 112 | 51.9 | 163 | 4.7 | 13 |
| October 27, 2015 | 0.350 | 198 | 568 | 299 | 858 | 38.1 | 109 | 50.0 | 146 | 6.3 | 18 |
| Average | 0.361 | 136 | 392 | 163 | 466 | 37.2 | 107 | 48.0 | 145 | 5.4 | 15 |
| Minimum | 0.344 | 96 | 275 | 102 | 293 | 35.4 | 102 | 43.9 | 126 | 4.7 | 13 |
| Maximum | 0.376 | 198 | 568 | 299 | 858 | 39.0 | 112 | 51.9 | 163 | 6.3 | 18 |
Table 4 presents the available Outfall 001 final effluent data for the month of November 2015. During November, the presence of foam conditions on the surface of the SBRs increased slightly ranging from 60% to 80% of the surface area. This is attributed to decreasing water temperatures. Increasing the F:M ratio and decreasing MLSS concentrations is employed to assist in managing the increase in filamentous growth.
During November, there were no exceedances of the permitted limitations for Outfall 001. There was no discharge from outfall 002. Split sampling of the composite sample collected by Applied Laboratory Services (ALS) is ongoing for comparative analysis and daily results.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 3 of 7
Big Fish Environmental Services Inc.
Table 4
November 2015 - Final Effluent - Out Fall 001
| NPDES Permit Discharge Limitations | Flow | CBOD5 | TSS | NH4-N | Phosphorus, Total, mg/L | Fecal Coliform | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | Geo Mean | Geo Mean | |
| 0.75 | 20 | 125 | 10 | 131 | 7 | 44 | 0.5 | 3 | 200 | 1,000 | |
| Instantaneous Maximum | 40 | 42 | |||||||||
| Sample Date | |||||||||||
| November 3, 2015 | 0.285 | 2.5 | 5.9 | 7 | 17 | 0.545 | 1.30 | 0.25 | 0.59 | 3 | 0.4771 |
| November 5, 2015 | 0.282 | 6 | 14 | ||||||||
| November 10, 2015 | 0.296 | 2.8 | 6.9 | 10 | 25 | 0.340 | 0.84 | 0.44 | 1.09 | 2 | 0.3010 |
| November 12, 2015 | 0.324 | 6 | |||||||||
| November 17, 2015 | 0.299 | 2.0 | 6 | 15 | 0.410 | 0.34 | 1 | ||||
| November 19, 2015 | 0.315 | 5 | 13 | ||||||||
| November 24, 2015 | 0.336 | 2.3 | 6.4 | 1 | 3 | 0.26 | 0.71 | 0.10 | 0.28 | 1 | 0.0000 |
| November 26, 2015 | 0.352 | 5 | 15 | ||||||||
| November 30, 2015 | 0.325 | 5 | 14 | ||||||||
| Average | 0.313 | 2.4 | 6.4 | 6 | 14 | 0.388 | 0.95 | 0.28 | 0.65 | 2 | 0.2594 |
| Minimum | 0.282 | 2.0 | 5.9 | 1 | 3 | 0.255 | 0.71 | 0.10 | 0.28 | 1 | 0.0000 |
| Maximum | 0.352 | 2.8 | 6.9 | 10 | 25 | 0.545 | 1.30 | 0.44 | 1.09 | 3 | 0.4771 |
During November 2015, there was no discharge of treated effluent to Applebrook.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 4 of 7
Big Fish Environmental Services Inc.
The influent wastewater pollutant concentrations and loading entering the wastewater treatment facility remained within the design concentrations and loadings. Composite samples are collected at the influent doghouse manhole and influent wet well. The influent flow meter reading is collected from the influent flow meter located prior to the Screening Building, excluding the internal recycle flows.
Table 5 presents the available pollutant data for the influent wastewater collected at the doghouse manhole during November 2015.
Table 5
November 2015 - Influent Wastewater
| Design Basis | Flow | BOD5 | TSS | NH4-N | TKN, mg/L | Phosphorus, Total, mg/L | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | |
| 335 | 2,098 | 320 | 2,001 | 32 | 200 | 48 | 301 | 9.1 | 57 | ||
| Sample Date | |||||||||||
| November 3, 2015 | 0.373 | 270 | 840 | 251 | 781 | 35.0 | 109 | 49.2 | 153 | 6.6 | 21 |
| November 10, 2015 | 0.372 | 122 | 380 | 192 | 597 | 44.0 | 137 | 49.6 | 154 | 6.0 | 19 |
| November 17, 2015 | 0.360 | 210 | 653 | 288 | 896 | 54.9 | 171 | 74.7 | 224 | 8.3 | 26 |
| November 24, 2015 | 0.391 | 97.6 | 304 | 140.0 | 436 | 49.4 | 154 | 54.8 | 179 | 5.5 | 17 |
| Average | 0.374 | 175 | 544 | 218 | 678 | 45.8 | 143 | 57.1 | 177 | 6.6 | 21 |
| Minimum | 0.360 | 98 | 304 | 140 | 436 | 35.0 | 109 | 49.2 | 153 | 5.5 | 17 |
| Maximum | 0.391 | 270 | 840 | 288 | 896 | 54.9 | 171 | 74.7 | 224 | 8.3 | 26 |
Sequencing batch reactors (SBRs) numbered 1, 3 and 4 were in service during October. Process monitoring of each SBR included ammonia as N, nitrite as N, Nitrate as N, COD, SSV, MLSS and total phosphorus. Daily analysis of the final effluent flow equalization grab sample is total phosphorus is ongoing. Sample collection and analysis of the influent wastewater collected at the influent pump station wet well is ongoing.
Addition of aluminum sulfate solution to the SBRs to assist with phosphorus removal continued. The volume of aluminum sulfate solution to the SBRs decreased to from 89.9 gpd to 83.2 gpd. Soda ash daily addition decreased from 439 lbs. /day to 410 lbs. /day. Soda ash assists towards maintaining SBR pH concentrations above 7.0
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 5 of 7
Big Fish Environmental Services Inc.
standard units and assists to replenish alkalinity consumed during the nitrification process and aluminum sulfate solution addition.
SBR No. 2 remains out of service as a treatment unit. Minor repairs will be scheduled as weather conditions permit.
Solids Dewatering and Disposal: November 2015
| Sludge Dewatering Summary | |
|---|---|
| Gallons of sludge dewatered | 285,003 |
| Number of dumpsters | 4 |
*seventeen (17) days of centrifuge operation
Flow data:
| Flow Meter Location | November 2015 | ||
|---|---|---|---|
| Total Volume for Month, MG | Average Daily Flow, gpd | Daily Maximum Flow, gpd | |
| Influent Wastewater to Screening Building* | 11.580 | 385,989 | 474,480 |
| Influent Wastewater to SBRs | 12.039 | 401,291 | 468,160 |
| Internal Recycle | 0.649 | 21,625 | 83,380 |
| Treated Effluent to Disc Filters | 12.128 | 311,600 | 403,000 |
| Final Effluent Discharge | 9.348 | 404,252 | 470,080 |
| Applebrook Golf Course | No Discharge | No Discharge | No Discharge |
Chemical Usage:
| Chemical | November 2015 | |
|---|---|---|
| Daily Average | Total Monthly | |
| Soda Ash | 410 | 4,450 |
| Aluminum Sulfate solution | 83.2 | 2,497 |
| Polymer (centrifuge) | 0.84 | 14.30 |
*seventeen (17) days of centrifuge operation
During November, sludge wasting to the sludge holding tanks and decanting of the sludge holding tanks was ongoing. Process monitoring included pH, total alkalinity and total solids.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 6 of 7
Big Fish Environmental Services Inc.
Sludge holding tank No. 1 was in service. The level at the beginning of November was 12.06 feet and the level at the end of the month was 8.96 feet. The average pH concentration was 6.66 S.U. and average total alkalinity concentration was 133 mg/L. Zero gallons of supernatant were decanted during the month. Zero pounds of soda ash were added.
Sludge holding tank No. 2 was in service. The level at the beginning of the month was 8.40 feet and the level at the end was 8.04. The average pH concentration was 6.21 S.U. and average total alkalinity concentration was 128 mg/L. 400 pounds of soda ash were added. Zero gallons of supernatant were decanted.
Significant Storm/Hydraulic Loading Events
During November, there was one (1) storm event resulting in a daily precipitation amount equal to or greater than 0.5 inches measured during a 24 hour period. This event occurred on November 19th resulting in 1.06 inches of rainfall. Plant operations were adjusted to manage the precipitation to prevent exceedances of the permitted discharge limitations for Outfalls 001 and 002.
Minor Repairs and Preventative Maintenance
No unscheduled minor repairs or equipment failures were experienced during November. Scheduled repairs during the month included the following activities:
| November 19th: | Replaced failed UV lamps and installed a new polymer tote. |
|---|---|
| November 23rd: | Flushed the aluminum sulfate chemical lines. |
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 7 of 7
Draft
EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
MEETING MINUTES
November 9, 2015
The East Goshen Township Municipal Authority held their regular public meeting on Monday, November 9, 2015 at 7:00 pm at the East Goshen Township building. Members in attendance were: Chairman Kevin Cummings, Jack Yahraes, Fran Beck, Dana Pizarro and Ed McAssey. Also in attendance were: Mark Miller (Director of Public Works), Mike Ellis (Pennoni), Pat McKenna (Attorney) and Walter Wujcik (Conservancy Board).
COMMON ACRONYMS:
| BFES – Big Fish Environmental Services BOS – Board of Supervisors CB – Conservancy Board DEP – Department of Environmental Protection EPA – Environmental protection Agency HC – Historical Commission I&I – Inflow & Infiltration LCSTP – Lockwood Chase Sewer Treatment Plant |
MA- Municipal Authority NPDES – National Pollutant Discharge Elimination System PC – Planning Commission PM – Prevention Maintenance PR – Park & Recreation Board RCSTP – Ridley Creek Sewer Treatment Plant SBR – Sequencing Batch Reactor SSO – Sanitary System Overflow WAS – Waste Activated Sludge |
|---|
Call to Order & Pledge of Allegiance
Kevin called the meeting to order at 7:00 pm and led those present in the Pledge of Allegiance. There was a moment of silence to remember the troops and all veterans. Kevin asked if anyone would be recording the meeting and there was no response.
Sewer Reports
1. Director of Public Works
Meters: All meters were read on a daily basis. The new recording system is working.
C.C. Collection: We were notified of three sewer clogs. Two were caused by the cleanouts getting pushed up by the frost. The third one was caused by debris in the clean out. We replaced three manhole castings and lids.
R.C. Collection: Was visited on a routine basis with no problems to report.
R.C.Plant: Was visited on a routine basis with no problems to report.
Alarms: We responded to 3 alarms for October.
PA One Calls: We received 28 PA One calls for October.
2. Pennoni Engineer’s Report
Mike Ellis provided the following report:
Invoices: Invoices with summaries are provided under separate cover.
Ridley Creek Sewage Treatment Plant (RCSTP):
No activity since the last report.
Reservoir Rd Pump Station:
We submitted the Small Projects Joint Permit Application for the pump station site and Chester Creek Utility Crossing to DEP, including the Chapter 106 Floodplain Management Site Restoration Permit Application. We also submitted the GP-5 “Utility Line Stream Crossing” and
F:\Data\Shared Data\Minutes\Municipal Authority\2015\MA 11-09-15 draft.doc
1
GP-8 “Temporary Road Crossings (across streams)” permit applications for the Ridley Creek Utility Crossing to DEP.
The Individual NPDES Permit application for Stormwater Discharges Associated with Construction Activities is nearly complete. We anticipate submitting to DEP by November 11.
Upon receipt of comments from the Township Codes Department on the approx. 90% progress design plan submission, we will finalize and submit the Water Quality Management (WQM) Part II Permit Application to DEP.
The Township Engineer’s staff performed a peer review of the stormwater design, and issued a letter that the design is in compliance with the EGT Stormwater Ordinance.
12 rock borings were performed in the open space area between Bow Tree Drive and the Ridley Creek (around the pond) in the proposed force main alignment at approx. 100 intervals. Borings were to a depth of 14 feet, and bedrock was not encountered. Weathered rock was encountered at 13 feet in two of the borings.
Soft dig test pits at proposed petroleum and gas pipeline crossings in/along N. Chester Road and Strasburg Road are scheduled the week of November 9-13.
The tentative schedule follows:
| Submit NPDES permit application | November 11, 2015 |
|---|---|
| Soft digs for utilities | week of November 9, 2015 |
| Submit WQM Part II permit application | November 20, 2015 |
| Submit PennDOT Highway Occupancy Permit Application for proposed force main | January 2016 |
| PADEP & PennDOT permit issuance | February-March 2016 |
Semi-Annual I&I Reports
We provided comments on the first three weeks of portable meter data for the relocated and recalibrated meters to the Township PW Dept, and we coordinated with them to evaluate apparent calibration issues on some of the meters. We have requested additional meter data be provided by the end of November so that we can analyze and prepare a semi-annual I&I report by the end of December.
Kevin mentioned that when Sunoco is working on the pipeline along Rt. 352 at the Bow Tree/Pin Oaks crossover, we should put a sleeve in since the road will be closed.
Mike commented that the applicant in this process should be the Municipal Authority.
3. Big Fish Environmental Services
Scott’s report showed that the Ridley Creek sewage treatment plant outfall 001 achieved compliance with the NPDES discharge permit during September 2015. Discharge to Applebrook continued during October. Chemical usage utilized for total phosphorus removal, pH and total alkalinity remained consistent with previous months. No mechanical or operational issues were observed during operation of sludge dewatering equipment.
During October there were 4 Storm events resulting in daily precipitation amounts equal to or greater than 0.5 inches measured during a 24 hour period. These events occurred on October 1st with 0.48 inches, October 2nd 1.66 inches, October 9th with 0.72 inches and October 28th with 2.38 inches. A total of 5.35 inches of rainfall was measured at the facility during October. Plant operations were adjusted to manage the precipitation to prevent exceedances of the permitted discharge limitations for outfalls 001 and 002.
F:\Data\Shared Data\Minutes\Municipal Authority\2015\MA 11-09-15 draft.doc
2
Approval of Minutes
Jack moved to accept the minutes of October 12, 2015. Fran seconded the motion. The motion passed unanimously.
Approval of Invoices
1. Ed moved to approve payment of the following Pennoni invoices:
- Pennoni #660830 $ 431.25
- Pennoni #660831 $ 221.25
- Pennoni #660832 $ 7,240.75
Jack seconded the motion. The motion passed unanimously. Mike reviewed the status of the budgets for these payments.
Liaison Reports
Conservancy Board – Walter reported that the final total of trees the Board will receive from Mullray is 10, so they removed the other flags. They will review the results of the Comprehensive Plan in order to plan their goals for 2016. They will be setting the date for “Keep East Goshen Beautiful Day”.
Financial Reports
Jon Altshul provided the following report:
In October, the Municipal Authority recorded $128 in revenues (all from interest) and $37,667 in expenses (including $36,766 for Reservoir Road Pump Station engineering), for a negative variance of -$37,539. As of October 31st, the fund balance was $1,498,552 of which $1,435,629 is in the main construction account.
Old Business
- Microbeads – Discussion tabled. This may be a topic for a newsletter article.
- Chester Creek Interceptor Sample Data – Mike reviewed the results of the grab sample that was done in November 2014. Kevin feels a 24 hour composite is needed.
Goals
Kevin reviewed the goals. All articles for the newsletter in 2015 are done. Ed will attend the 4th quarter West Goshen meeting.
Goals for 2016 were discussed with the following result:
- Newsletter articles – It was decided that the MA will submit articles on an as needed basis since they don’t hold any events.
- C, D, E, & F will be included. B (Reservoir Rd Pump Station) should be done so it won’t be included. It was decided to add another goal – Enhance operating procedures.
New Business
- Appointment of Solicitor – Gawthrop Greenwood, PC presented a letter to maintain their current rate of $200/hour for legal services to the Municipal Authority. Jack moved to retain Gawthrop Greenwood, PC as Solicitor to the Municipal Authority for 2016. Fran seconded the motion. The motion passed unanimously.
F:\Data\Shared Data\Minutes\Municipal Authority\2015\MA 11-09-15 draft.doc
3
Capacity Requests
- 3 &5 School Lane - The request for sanitary sewer service, including grinder pumps, for 3 & 5 School Lane was approved.
- 930 N. Chester Road – The subdivision plan proposes to split the 4 acre parcel into 2 lots and develop a new single family home on the new lot. The new lot proposes to connect to the public sewer system and use a grinder pump. If there is a lateral there, the Authority members feel it should be a requirement that both lots have to connect. Jack moved to approve the request for capacity. Ed seconded the motion. The motion passed unanimously.
Any Other Matter
- Operation Procedures – Mark pointed out that the last time the Operating Procedures for the plant and pump stations was reviewed was in 1980 by Yerkes. Mike will have a review meeting to put together a scope of work and make a proposal. Pat suggested that this should be done every 5 years.
- Kevin acknowledged receipt of the report from Kroll Bond Rating Agency (KBRA) which affirmed the long-term rating of AAA with a stable outlook on East Goshen Municipal Authority.
Adjournment
There being no further business, Dana moved to adjourn the meeting. Fran seconded the motion. The motion passed unanimously. The meeting was adjourned at 7:45 pm. The next meeting will be held on Monday, December 14 at 7:00 pm.
Respectfully submitted,
Ruth Kiefer
Recording Secretary
F:\Data\Shared Data\Minutes\Municipal Authority\2015\MA 11-09-15 draft.doc
4
Pennoni
INVOICE
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328
| East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380-6199 Attention: Louis F. Smith, Twp Mgr. |
Invoice #: 665054 Invoice Date: 11/23/2015 Project: EGMA1501 Project Name: 2015 General Services |
|---|
For Services Rendered through: 11/8/2015
November Engineer's Report and preparation for November MA meeting.
Phase: **** -- Professional Services
Total Phase: **** -- Professional Services
| Labor: | 172.50 |
|---|---|
| Expense: | 0.00 |
| Phase Total: | 172.50 |
Amount Due This Invoice: $172.50
| Fee: | 12,000.00 |
|---|---|
| Prior Billings: | 9,277.75 |
| Current Billings: | 172.50 |
| Total Billings: | 9,450.25 |
Phase: **** -- Professional Services
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 1.50 | 115.00 | 172.50 |
| Labor Total: | 1.50 | 172.50 |
| Total Phase: **** -- Professional Services | Labor: $172.50 Expense: $0.00 |
|---|---|
| Total Project: EGMA1501 -- 2015 General Services | Labor: $172.50 Expense: $0.00 |
[Handwritten in red: ok RS 12-8-15]
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMA1501 Invoice Summary
Invoice Date 11/08/2015
| Project: | EGMA1501 | ||
|---|---|---|---|
| Pennoni Job No.: | 2015 General Services | ||
| Invoice No: | 665054 | ||
| Invoice Period: | 10/19/2015 | to | 11/8/2015 |
| Initial Authorization: | $ 12,000.00 | Date: | 11/23/2015 |
| Contract Amount: | $ 12,000.00 | ||
| Previously Invoiced: | $ 9,277.75 | ||
| Current Invoice: | $ 172.50 | ||
| Invoiced to Date ($): | $ 9,450.25 | ||
| Invoiced to Date (%): | 79% | ||
| Remaining Budget ($): | $ 2,549.75 | ||
| Remaining Budget (%): | 21% |
Budget by Phase:
| Phase Name: | 2015 General Services |
|---|---|
| Phase Budget: | $ 12,000.00 |
| Previously Invoiced: | $ 9,277.75 |
| Current Invoice: | $ 172.50 |
| Invoiced to Date ($): | $ 9,450.25 |
| Invoiced to Date (%): | 79% |
| Remaining Budget ($): | $ 2,549.75 |
| Remaining Budget (%): | 21% |
Comments: November Engineer's Report and preparation for November MA meeting.
Pennoni
INVOICE
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328
| East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380-6199 Attention: Louis F. Smith, Twp Mgr. |
Invoice #: 665055 Invoice Date: 11/23/2015 Project: EGMA1502 Project Name: 2015 Semi-Annual I&I Reports |
|---|
For Services Rendered through: 11/8/2015
Coordinated with PW Dept on portable meter calibrations and flow & level readings based on analysis of first month of data.
Phase: **** -- Professional Services
Total Phase: **** -- Professional Services
| Labor: | 86.25 |
|---|---|
| Expense: | 0.00 |
| Phase Total: | 86.25 |
Amount Due This Invoice: $86.25
| Fee: | 10,500.00 |
|---|---|
| Prior Billings: | 7,598.75 |
| Current Billings: | 86.25 |
| Total Billings: | 7,685.00 |
Phase: **** -- Professional Services
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 0.75 | 115.00 | 86.25 |
| Labor Total: | 0.75 | 86.25 |
| Total Phase: **** -- Professional Services | Labor: $86.25 Expense: $0.00 |
|---|---|
| Total Project: EGMA1502 -- 2015 Semi-Annual I&I Reports | Labor: $86.25 Expense: $0.00 |
[Handwritten in red: ok RS 12-8-15]
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMA1502 Invoice Summary
Invoice Date 11/08/2015
| Project: | EGMA1502 | ||
|---|---|---|---|
| Pennoni Job No.: | 2015 Semi-Annual I&I Reports | ||
| Invoice No: | 665055 | ||
| Invoice Period: | 10/19/2015 | to | 11/8/2015 |
| Initial Authorization: | $ 10,500.00 | Date: | 11/23/2015 |
| Contract Amount: | $ 10,500.00 | ||
| Previously Invoiced: | $ 7,598.75 | ||
| Current Invoice: | $ 86.25 | ||
| Invoiced to Date ($): | $ 7,685.00 | ||
| Invoiced to Date (%): | 73% | ||
| Remaining Budget ($): | $ 2,815.00 | ||
| Remaining Budget (%): | 27% |
Budget by Phase:
| Phase Name: | 2015 Semi-Annual I&I Reports |
|---|---|
| Phase Budget: | $ 10,500.00 |
| Previously Invoiced: | $ 7,598.75 |
| Current Invoice: | $ 86.25 |
| Invoiced to Date ($): | $ 7,685.00 |
| Invoiced to Date (%): | 73% |
| Remaining Budget ($): | $ 2,815.00 |
| Remaining Budget (%): | 27% |
Comments: Coordinated with PW Dept on portable meter calibrations and flow & level readings based on analysis of first month of data.
Pennoni
INVOICE
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328
| East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380-6199 Attention: Louis F. Smith, Twp Mgr. |
Invoice #: 665360 Invoice Date: 11/24/2015 Project: EGMA1504 Project Name: Reservoir Rd PS Design & Permitting |
|---|
For Services Rendered through: 11/8/2015
Phase 11 - Continued coordination for soft dig utility test pits scope and schedule with PPL-IES, Sunoco, Williams-Transco, and Township; continued preparation of specifications and advanced to approx. 99% complete electrical design.
Phase 12 Contract Effort - Continued with preparation of PADEP WQM Part II permit application, NPDES permit application and PCSM plan, Chapter 105 GP-5 "Utility Line Stream Crossings" and GP-8 "Temporary Road Crossings (across streams)" permit application for Ridley Creek; Chapter 105 GP-5 "Utility Line Stream Crossings" and Small Projects Joint Permit application for Chester Creek and pump station site.
Phase 12 Supplemental Effort for continued preparation of Chapter 105 and 106 General Permit & Joint Permit application for Chester Creek utility crossing and floodplain analysis. Supplemental effort in this invoice = $1,515.00. Prior supplemental effort invoiced $2,063.25: Total supplemental effort projected to be $6,000.00.
Phase : 11 -- Final Design
Total Phase : 11 -- Final Design
| Labor: | 145.50 |
|---|---|
| Expense: | 2,022.75 |
| Phase Total: | 2,168.25 |
Phase : 12 -- Permitting
Total Phase : 12 -- Permitting
| Labor: | 4,522.50 |
|---|---|
| Expense: | 0.00 |
| Phase Total: | 4,522.50 |
Amount Due This Invoice: $6,690.75
| Fee: | 141,800.00 |
|---|---|
| Prior Billings: | 106,453.25 |
| Current Billings: | 6,690.75 |
| Total Billings: | 113,144.00 |
[Handwritten in red: ok RS 12-8]
Continued on next page...
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
Project : EGMA1504 -- Reservoir Rd PS Design & Permitting
Invoice # : 665360
...Continued from previous page
Phase : 11 -- Final Design
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Project Engineer | 1.50 | 97.00 | 145.50 |
| Labor Total: | 1.50 | 145.50 |
Expenses
| Description | Units | Rate | Amount |
|---|---|---|---|
| Engineering Servs-direct 10/29/2015 | Carew Associates, Inc. | 2,022.75 | |
| Subconsultant Total | 2,022.75 | ||
| Expense Total: | $2,022.75 | ||
| Total Phase : 11 -- Final Design | Labor : $145.50 Expense : $2,022.75 |
|---|
Phase : 12 -- Permitting
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 3.00 | 115.00 | 345.00 |
| Project Engineer | 2.50 | 97.00 | 242.50 |
| Senior Enviromental Scientist | 13.00 | 90.00 | 1,170.00 |
| Associate Engineer | 28.00 | 85.00 | 2,380.00 |
| Engineering Technician II | 5.00 | 77.00 | 385.00 |
| Labor Total: | 51.50 | 4,522.50 |
| Total Phase : 12 -- Permitting | Labor : $4,522.50 Expense : $0.00 |
|---|---|
| Total Project : EGMA1504 -- Reservoir Rd PS Design & Permitting | Labor : $4,668.00 Expense : $2,022.75 |
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
Pennoni Associates Inc.
Page: 2
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date 11/08/2015
| Project: | EGMA1504 | ||
|---|---|---|---|
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 665360 | ||
| Invoice Period: | 10/19/2015 | to | 11/8/2015 |
| Initial Authorization: | $ 167,120.00 | Date: | 11/24/2015 |
| Contract Amount: | $ 167,120.00 | ||
| Previously Invoiced: | $ 121,160.25 | ||
| Current Invoice: | $ 7,240.75 | ||
| Invoiced to Date ($): | $ 128,401.00 | ||
| Invoiced to Date (%): | 77% | ||
| Remaining Budget ($): | $ 38,719.00 | ||
| Remaining Budget (%): | 23% |
Budget by Phase:
| Phase Name: | Final Design | Phase 11 |
|---|---|---|
| Phase Budget: | $ 47,400.00 | |
| Previously Invoiced: | $ 43,781.75 | |
| Current Invoice: | $ 2,168.25 | |
| Invoiced to Date ($): | $ 45,950.00 | |
| Invoiced to Date (%): | 97% | |
| Remaining Budget ($): | $ 1,450.00 | |
| Remaining Budget (%): | 3% | |
Comments: Phase 11 - Continued coordination for soft dig utility test pits scope and schedule with PPL-IES, Sunoco, Williams-Transco, and Township; continued preparation of specifications and advanced to approx. 99% complete electrical design.
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date 11/08/2015
| Project: | EGMA1504 | |||
|---|---|---|---|---|
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | |||
| Invoice No: | 665360 | |||
| Invoice Period: | 10/19/2015 | to | 11/8/2015 | |
| Initial Authorization: | $ | 167,120.00 | Date: | 11/24/2015 |
| Contract Amount: | $ | 173,120.00 | ||
| Previously Invoiced: | $ | 128,401.00 | ||
| Current Invoice: | $ | 6,690.75 | ||
| Invoiced to Date ($): | $ | 135,091.75 | ||
| Invoiced to Date (%): | 78% | |||
| Remaining Budget ($): | $ | 38,028.25 | ||
| Remaining Budget (%): | 22% | |||
Budget by Phase:
| Phase Name: | Permitting | Phase 12 |
|---|---|---|
| Phase Budget: | $ | 21,800.00 |
| Previously Invoiced: | $ | 11,629.00 |
| Current Invoice: | $ | 4,522.50 |
| Invoiced to Date ($): | $ | 16,151.50 |
| Invoiced to Date (%): | 74% | |
| Remaining Budget ($): | $ | 5,648.50 |
| Remaining Budget (%): | 26% | |
Comments:
Phase 12 Contract Effort - Continued with preparation of PADEP WQM Part II permit application, NPDES permit application and PCSM plan, Chapter 105 GP-5 "Utility Line Stream Crossings" and GP-8 "Temporary Road Crossings (across streams)" permit application for Ridley Creek; Chapter 105 GP-5 "Utility Line Stream Crossings" and Small Projects Joint Permit application for Chester Creek and pump station site.
Phase 12 Supplemental Effort for continued preparation of Chapter 105 and 106 General Permit & Joint Permit application for Chester Creek utility crossing and floodplain analysis. Supplemental effort in this invoice = $1,515.00. Prior supplemental effort invoiced $2,063.25: Total supplemental effort projected to be $6,000.00.
Gawthrop Greenwood, PC
Attorneys at Law
17 East Gay Street, Suite 100
West Chester, PA 19381-0562
gglaw@gawthrop.com
(p) 610-696-8225
(f) 610-344-0922
www.gawthrop.com
East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380
Page: 1
11/06/2015
Client No: 6604-001R
Invoice No. 137649
General Authority Services
Fees
| Hours | ||||
|---|---|---|---|---|
| 10/12/2015 | PMM | Review and analyze agenda and meeting packet in preparation for Authority meeting; Attend Authority meeting. | 1.90 | |
| For Current Services Rendered | 1.90 | 380.00 |
Recapitulation
| Timekeeper | Hours | Hourly Rate | Total |
|---|---|---|---|
| Patrick M. McKenna | 1.90 | $200.00 | $380.00 |
| Previous Balance | $260.00 | |
|---|---|---|
| Total Current Charges | 380.00 | |
| 10/15/2015 | Payment | -260.00 |
| Balance Due | $380.00 |
OK TO PAY
Rick 11/12/15
PAID IN November
To ensure proper credit, please write client number on your check when returning payment. Thank You.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.
Gawthrop Greenwood, PC
Attorneys at Law
17 East Gay Street, Suite 100
West Chester, PA 19381-0562
gglaw@gawthrop.com
(p) 610-696-8225
(f) 610-344-0922
www.gawthrop.com
East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380
Page: 1
12/09/2015
Client No: 6604-001R
Invoice No. 139094
General Authority Services
Fees
| Date | Timekeeper | Description | Hours | Amount |
|---|---|---|---|---|
| 11/09/2015 | PMM | Review and analyze meeting packet in preparation for Authority meeting; Attend Authority meeting. | 2.00 | |
| 11/10/2015 | PMM | Review and analyze Township Code regarding under what circumstances a property owner is required to connect to the sanitary sewer system; Numerous emails to/from M Miller, K Cummings and R Smith regarding same. | 1.30 | |
| 11/20/2015 | PMM | Email from R Smith with memo regarding capital improvements and maintenance for West Goshen Sewer Treatment Plant; Reply; Email from E McAssey regarding same. | 0.60 | |
| For Current Services Rendered | 3.90 | 780.00 |
Recapitulation
| Timekeeper | Hours | Hourly Rate | Total |
|---|---|---|---|
| Patrick M. McKenna | 3.90 | $200.00 | $780.00 |
| Date | Description | Amount |
|---|---|---|
| Previous Balance | $380.00 | |
| Total Current Charges | 780.00 | |
| 11/20/2015 | Payment | -380.00 |
| Balance Due | $780.00 |
OK RS 12-11-15
Shainline Excavating, Inc.
800 Township Line Road800 Township Line Road
Phoenixville, Pa 19460-3052
Phone # (610)935-8300
Invoice
| Date | 11/20/2015 |
|---|---|
| Invoice # | 39818 |
1580 PAOLI PIKE
WEST CHESTER, PA 19380
| P.O. No. | JOB NO. | CUSTOMER'S JOB # | Due Date | Terms |
|---|---|---|---|---|
| SH0811 | sh0811 | 12/20/2015 | NET 30 DAYS |
| REFERENCE LINE 1 | REFERENCE LINE 2 | REFERENCE LINE 3 |
|---|---|---|
| Attn: Rick Smith | Equipment rental |
| Qty | EXP | EQUIP | Description | Rate | Amount |
|---|---|---|---|---|---|
| 1 | EQUIP RENTAL | each | EQUIPMENT RENTAL CONTRACT | 1,900.00 | 1,900.00 |
[Handwritten: OK RS 11/24/15 Reservoir RD PS Project]
A finance charge of 1.5% per month will be charged oin all amounts NOT PAID within 30 days (18% APR)
Total: $1,900.00
Memo
| To: | Municipal Authority |
|---|---|
| From: | Jon Altshul |
| Re: | MA November Financial Reports |
| Date: | December, 2015 |
In November, the Municipal Authority recorded $113 in revenues (all from interest) and $9,986 in expenses, for a negative variance of $9,873. As of November 30th, the fund balance was $1,488,679, of which $1,426,785 is in the main construction account.
A complete list of all year-to-date expenses and revenues is provided.
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKEWEST CHESTER, PA
Municipal Authority
November 2015
| Account Title | Acct # | Annual Budget | Month To Date Actual | Year To Date Actual |
|---|---|---|---|---|
| MUNICIPAL AUTHORITY BEGINNING FUND BALANCE | 1,498,552.02 | |||
| RCSTP BUDGET | ||||
| REVENUE | ||||
| INTEREST EARNED - RCSTP EXPANSION | 07341 1020 | 1,600.00 | 112.03 | 1,382.86 |
| GRANT REVENUE | 07392 0800 | 0.00 | 0.00 | 0.00 |
| TOTAL REVENUE | 1,600.00 | 112.03 | 1,382.86 | |
| EXPENSES | ||||
| R.C.-CAP. PROJ.-ENGINEER | 07424 7451 | 0.00 | 0.00 | |
| R.C. CAP EXPANSION GEN'L CONTRACTOR | 07424 7452 | 0.00 | 0.00 | |
| R.C. CAP EXPANSION - ELECTRICAL | 07424 7453 | 0.00 | 0.00 | |
| R.C. CAP EXP CONTINGENCY CAPITAL | 07424 7454 | 0.00 | 0.00 | |
| R.C. CAP EXP CONTINGENCY ONGOING | 07424 7455 | 0.00 | 0.00 | |
| R.C. CAP EXP ADDITIONAL CONTINGENCY | 07424 7456 | 0.00 | 0.00 | |
| TRANSFER TO SEWER SINKING FUND | 07492 0550 | 0.00 | 0.00 | |
| TRANSFER TO AUTHORITY CAP FUND | 07492 0990 | 0.00 | 0.00 | |
| TOTAL EXPENSES | 0.00 | 0.00 | 0.00 | |
| RCSTP NET RESULT | 1,600.00 | 112.03 | 1,382.86 | |
| OPERATING BUDGET | ||||
U:\bmccool\2015\Municipal Authority\2015 - 11 - Municipal Authority Report.xlsx
Page 1 of 3
12/04/2015
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKEWEST CHESTER, PA
Municipal Authority
November 2015
| Account Title | Acct # | Annual Budget | Month To Date Actual | Year To Date Actual |
|---|---|---|---|---|
| REVENUE | ||||
| INTEREST EARNINGS | 07341 1000 | 15.00 | 1.11 | 10.08 |
| C.C. TAPPING FEES | 07364 1100 | 0.00 | 0.00 | 27,600.00 |
| R.C.TAPPING FEES | 07364 1110 | 14,296.00 | 0.00 | 16,296.00 |
| CONNECTION FEES - SEWER | 07364 1130 | 0.00 | 0.00 | 1,268.64 |
| MISCELLANEOUS REVENUE | 07380 1000 | 0.00 | 0.00 | 423.36 |
| TRANSFER FROM SEWER OPERATING | 07392 0500 | 105,105.00 | 0.00 | 20,000.00 |
| TOTAL REVENUE | 119,416.00 | 1.11 | 65,598.08 | |
| EXPENSES | ||||
| ADMINISTRATIVE WAGES | 07424 1400 | 33,323.00 | 0.00 | 24,251.00 |
| MISCELLANEOUS EXPENSE | 07424 3000 | 3,000.00 | 0.00 | 1,468.05 |
| MUNIC.AUTH.-AUDITING | 07424 3110 | 10,984.00 | 0.00 | 8,900.00 |
| ENGINEERING SERVICES | 07424 3130 | 37,300.00 | 652.50 | 33,265.75 |
| LEGAL SERVICES | 07424 3140 | 9,000.00 | 380.00 | 3,320.00 |
| M.C.-DVRFA-DEBT SERVICE | 07471 1000 | 23,240.00 | 0.00 | 0.00 |
| M.C.-DVRFA-INTEREST PAYMN | 07472 1000 | 4,169.00 | 0.00 | 0.00 |
| M.C.-DVRFA-INTEREST PAYMN | 07472 1010 | 0.00 | 0.00 | 0.00 |
| TOTAL EXPENSES | 121,016.00 | 1,032.50 | 71,204.80 | |
| OPERATING NET RESULT | (1,600.00) | (1,031.39) | (5,606.72) | |
| CAPITAL BUDGET | ||||
U:\bmccool\2015\Municipal Authority\2015 - 11 - Municipal Authority Report.xlsx
Page 2 of 3
12/04/2015
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKEWEST CHESTER, PA
Municipal Authority
November 2015
| Account Title | Acct # | Annual Budget | Month To Date Actual | Year To Date Actual |
|---|---|---|---|---|
| REVENUE | ||||
| DCED GRANT | 07354 0400 | 0.00 | 0.00 | 37,162.00 |
| LOAN PROCEEDS-SEWER PROJECT | 07393 1001 | 0.00 | 0.00 | 0.00 |
| TRANSFER FROM SEWER CAP RESERVE | 07392 0900 | 0.00 | 0.00 | 0.00 |
| TOTAL REVENUE | 0.00 | 0.00 | 37,162.00 | |
| EXPENSES | ||||
| MARYDELL PUMP STATION - ENGINEER | 07425 1000 | 0.00 | 0.00 | 0.00 |
| MARYDELL PUMP STATION -CONSTRUCTION | 07425 2000 | 0.00 | 0.00 | 0.00 |
| MANHOLE COVER REPLACEMENTS | 07424.7405 | 0.00 | 0.00 | 0.00 |
| C.C. CAPITAL - COLLECTION | 07424.7420 | 0.00 | 0.00 | 0.00 |
| LOCHWOOD ABANDONMENT ENGINEER | 07424 7475 | 0.00 | 0.00 | 0.00 |
| LOCHWOOD ABANDONMENT CONSTRUCTION | 07424 7476 | 0.00 | 0.00 | 0.00 |
| LOCHWOOD ELIMINATION PHASE 2 | 07424 7477 | 0.00 | 0.00 | 0.00 |
| HERSHEY MILL STATION - ENGINEER | 07426 1000 | 0.00 | 0.00 | 0.00 |
| HERSHEY MILL STATION - CONSTRUCTION | 07426 2000 | 0.00 | 0.00 | 0.00 |
| RESERVE PUMP STATION - ENGINEER | 07427 1000 | 0.00 | 0.00 | 0.00 |
| RESERVE PUMP STATION - CONSTRUCTION | 07427 2000 | 0.00 | 0.00 | 0.00 |
| RESERVOIR PUMP STATION - ENGINEER | 07428 1000 | 100,000.00 | 8,953.75 | 133,435.75 |
| RESERVOIR PUMP STATION CONSTRUCTION | 07428 2000 | 0.00 | 0.00 | 0.00 |
| TOTAL EXPENSES | 100,000.00 | 8,953.75 | 133,435.75 | |
| CAPITAL NET RESULT | (100,000.00) | (8,953.75) | (96,273.75) | |
| MUNICIPAL AUTHORITY ENDING FUND BALANCE | 1,488,678.91 | |||
U:\bmccool\2015\Municipal Authority\2015 - 11 - Municipal Authority Report.xlsx
Page 3 of 3
12/04/2015
East Goshen Township General Ledger
Report Date 12/04/15
GL Transaction Details
PAGE 1
MGRP18 run by BRIAN 10 : 56 AM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07341-1000 | INTEREST EARNINGS | 0.00 | ||||||||
| 1501 | JE | 46156 | 1.44 | 02/03/15 | INTEREST | INTEREST EARNED JANUARY 2015 07 FUND | ||||
| 1501 | 0.00 | 1.44 | -1.44 | |||||||
| 1502 | 46526 | 1.17 | 03/02/15 | INTEREST | INTEREST EARNED FEBRUARY 2015 07 FUND | |||||
| 1502 | 0.00 | 1.17 | -2.61 | |||||||
| 1503 | 46944 | 1.03 | 04/02/15 | INTEREST | INTEREST EARNED MARCH 2015 07 FUND | |||||
| 1503 | 0.00 | 1.03 | -3.64 | |||||||
| 1504 | 47407 | 0.61 | 05/04/15 | INTEREST | INTEREST EARNED APRIL 2015 07 FUND | |||||
| 1504 | 0.00 | 0.61 | -4.25 | |||||||
| 1505 | 47825 | 0.75 | 06/01/15 | INTEREST | INTEREST EARNED MAY 2015 07 FUND | |||||
| 1505 | 0.00 | 0.75 | -5.00 | |||||||
| 1506 | 48334 | 0.64 | 07/02/15 | INTEREST | INTEREST EARNED JUNE 2015 07 FUND | |||||
| 1506 | 0.00 | 0.64 | -5.64 | |||||||
| 1507 | 48782 | 0.56 | 08/03/15 | INTEREST | INTEREST EARNED JULY 2015 07 FUND | |||||
| 1507 | 0.00 | 0.56 | -6.20 | |||||||
| 1508 | 49202 | 0.64 | 09/01/15 | INTEREST | INTEREST EARNED AUGUST 2015 07 FUND | |||||
| 1508 | 0.00 | 0.64 | -6.84 | |||||||
| 1509 | 49635 | 0.85 | 10/02/15 | INTEREST | INTEREST EARNED SEPT.2015 07 FUND | |||||
East Goshen Township General Ledger
Report Date 12/04/15
GL Transaction Details
PAGE 2
MGRP18 run by BRIAN 10 : 56 AM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 1509 | 0.00 | 0.85 | -7.69 | |||||||
| 1510 | 50108 | 1.28 | 11/03/15 | INTEREST | INTEREST EARNED OCTOBER 2015 07 FUND | |||||
| 1510 | 0.00 | 1.28 | -8.97 | |||||||
| 1511 | 50447 | 1.11 | 12/03/15 | INTEREST | INTEREST EARNED NOVEMBER 2015 07 FUND | |||||
| 1511 | 0.00 | 1.11 | -10.08 | |||||||
| 07341-1000 | **** | *** | ***** | 0.00 | 10.08 | -10.08 | ||||
| 07341-1020 | INTEREST EARNED - RCSTP EXPANSION | 0.00 | ||||||||
| 1501 | 46156 | 131.97 | 02/03/15 | INTEREST | INTEREST EARNED JANUARY 2015 07 FUND | |||||
| 1501 | 0.00 | 131.97 | -131.97 | |||||||
| 1502 | 46526 | 119.08 | 03/02/15 | INTEREST | INTEREST EARNED FEBRUARY 2015 07 FUND | |||||
| 1502 | 0.00 | 119.08 | -251.05 | |||||||
| 1503 | 46944 | 131.27 | 04/02/15 | INTEREST | INTEREST EARNED MARCH 2015 07 FUND | |||||
| 1503 | 0.00 | 131.27 | -382.32 | |||||||
| 1504 | 47407 | 125.90 | 05/04/15 | INTEREST | INTEREST EARNED APRIL 2015 07 FUND | |||||
| 1504 | 0.00 | 125.90 | -508.22 | |||||||
| 1505 | 47825 | 128.37 | 06/01/15 | INTEREST | INTEREST EARNED MAY 2015 07 FUND | |||||
| 1505 | 0.00 | 128.37 | -636.59 | |||||||
East Goshen Township General Ledger
Report Date 12/04/15
GL Transaction Details
PAGE 3
MGRP18 run by BRIAN 10 : 56 AM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07341-1020 | 1506 | JE | 48334 | 124.75 | 07/02/15 | INTEREST | INTEREST EARNED JUNE 2015 07 FUND | |||
| 1506 | 0.00 | 124.75 | -761.34 | |||||||
| 1507 | 48782 | 129.80 | 08/03/15 | INTEREST | INTEREST EARNED JULY 2015 07 FUND | |||||
| 1507 | 0.00 | 129.80 | -891.14 | |||||||
| 1508 | 49202 | 128.91 | 09/01/15 | INTEREST | INTEREST EARNED AUGUST 2015 07 FUND | |||||
| 1508 | 0.00 | 128.91 | -1,020.05 | |||||||
| 1509 | 49635 | 124.25 | 10/02/15 | INTEREST | INTEREST EARNED SEPT.2015 07 FUND | |||||
| 1509 | 0.00 | 124.25 | -1,144.30 | |||||||
| 1510 | 50108 | 126.53 | 11/03/15 | INTEREST | INTEREST EARNED OCTOBER 2015 07 FUND | |||||
| 1510 | 0.00 | 126.53 | -1,270.83 | |||||||
| 1511 | 50447 | 112.03 | 12/03/15 | INTEREST | INTEREST EARNED NOVEMBER 2015 07 FUND | |||||
| 1511 | 0.00 | 112.03 | -1,382.86 | |||||||
| 07341-1020 | **** | *** | ***** | 0.00 | 1,382.86 | -1,382.86 | ||||
| 07354-0400 | DCED GRANT | 0.00 | ||||||||
| 1506 | RE | 48107 | 37,162.00 | 06/17/15 | 48107 | 1 | GRANT - RESERVOIR RD PUMP STA | |||
| 1506 | 0.00 | 37,162.00 | -37,162.00 | |||||||
| 07354-0400 | **** | *** | ***** | 0.00 | 37,162.00 | -37,162.00 | ||||
East Goshen Township General Ledger
Report Date 12/04/15
GL Transaction Details
PAGE 4
MGRP18 run by BRIAN 10 : 56 AM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07364-1100 | C.C. TAPPING FEES | 0.00 | ||||||||
| 1505 | 47736 | 2,000.00 | 05/27/15 | 47736 | 1 | TAP IN FEE - 1334 A PARK AVE | ||||
| 1505 | 0.00 | 2,000.00 | -2,000.00 | |||||||
| 1506 | 47853 | 2,000.00 | 06/03/15 | 47853 | 1 | TAP-IN FEE FOR 1414 BRAMBLE LN | ||||
| 47991 | 2,000.00 | 06/10/15 | 47991 | 1 | TAP IN FEE FOR 14 RESERVOIR RD | |||||
| 1506 | 0.00 | 4,000.00 | -6,000.00 | |||||||
| 1509 | CR | 49458 | 21,600.00 | 09/21/15 | 249 | 8069 | 1 GOSHEN MEADOWS INVESTORS L.P. | |||
| 1509 | 0.00 | 21,600.00 | -27,600.00 | |||||||
| 07364-1100 | **** | *** | ***** | 0.00 | 27,600.00 | -27,600.00 | ||||
| 07364-1110 | R.C.TAPPING FEES | 0.00 | ||||||||
| 1504 | 47236 | 7,148.00 | 04/21/15 | 1123 | 7875 | 1 SUNNY RIDGE FARMS LLC | ||||
| 47278 | 7,148.00 | 04/23/15 | 1128 | 7875 | 1 SUNNY RIDGE FARMS LLC | |||||
| 1504 | 0.00 | 14,296.00 | -14,296.00 | |||||||
| 1509 | RE | 49423 | 2,000.00 | 09/18/15 | 49423 | 1 | TAP IN FEE FOR 1606 ATLEE DR | |||
| 1509 | 0.00 | 2,000.00 | -16,296.00 | |||||||
| 07364-1110 | **** | *** | ***** | 0.00 | 16,296.00 | -16,296.00 | ||||
| 07364-1130 | CONNECTION FEES - SEWER | 0.00 | ||||||||
| 1501 | CR | 45967 | 423.00 | 01/16/15 | 789 | 8648 | 1 GEORGE SMITH & CHRISTINA CONLE | |||
| JE | 45968 | 141.12 | 01/16/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | |||||
| 1501 | 141.12 | 423.00 | -281.88 | |||||||
| 1502 | CR | 46296 | 423.00 | 02/13/15 | 248 | 8650 | 1 JACOBS, ROBERT & CHERYL | |||
| 46479 | 423.00 | 02/26/15 | 2381 | 8649 | 1 STOFFLET, MICHAEL | |||||
| JE | 46297 | 141.12 | 02/13/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | |||||
| 46480 | 141.12 | 02/26/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | ||||||
| 1502 | 282.24 | 846.00 | -845.64 | |||||||
East Goshen Township General Ledger
Report Date 12/04/15
GL Transaction Details
PAGE 5
MGRP18 run by BRIAN 10 : 56 AM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07364-1130 | 1505 | CR | 47731 | 423.00 | 05/27/15 | 1124 | 8651 | 1 PAPPANO, JOSEPH & PATRICIA | ||
| 1505 | 0.00 | 423.00 | -1,268.64 | |||||||
| 07364-1130 | **** | *** | ***** | 423.36 | 1,692.00 | -1,268.64 | ||||
| 07380-1000 | MISCELLANEOUS REVENUE | 0.00 | ||||||||
| 1501 | JE | 45968 | 141.12 | 01/16/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | ||||
| 1501 | 0.00 | 141.12 | -141.12 | |||||||
| 1502 | 46297 | 141.12 | 02/13/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | |||||
| 46480 | 141.12 | 02/26/15 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | ||||||
| 1502 | 0.00 | 282.24 | -423.36 | |||||||
| 07380-1000 | **** | *** | ***** | 0.00 | 423.36 | -423.36 | ||||
| 07392-0500 | TRANSFER FROM SEWER OPERATING | 0.00 | ||||||||
| 1507 | 48567 | 20,000.00 | 07/16/15 | DEPOSIT | DEPOSIT $ FROM SEWER ACCT. | |||||
| 1507 | 0.00 | 20,000.00 | -20,000.00 | |||||||
| 07392-0500 | **** | *** | ***** | 0.00 | 20,000.00 | -20,000.00 | ||||
| 07424-1400 | ADMINISTRATIVE WAGES | 0.00 | ||||||||
| 1503 | CD | 46874 | 8,292.10 | 03/30/15 | 2267 | 425 | EAST GOSHEN TOWNSHIP - GENERAL 1ST QTR.2015 REIMBURS. FR: MUN.A |
|||
| 1503 | 8,292.10 | 0.00 | 8,292.10 | |||||||
| 1506 | 48284 | 8,292.10 | 06/30/15 | 2273 | 425 | EAST GOSHEN TOWNSHIP - GENERAL 2ND QTR.2015 REIMBURSMT FR:MUN.A |
||||
| 1506 | 8,292.10 | 0.00 | 16,584.20 | |||||||
| 1509 | 49529 | 8,292.10 | 09/25/15 | 2280 | 425 | EAST GOSHEN TOWNSHIP - GENERAL 3RD QTR 2015 REIMBURSEMENT FR: MA |
||||
East Goshen Township General Ledger
Report Date 12/04/15 GL Transaction Details PAGE 6
MGRP18 run by BRIAN 10 : 56 AM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07424-1400 | 1509 | CD | 49551 | -8,292.10 | 09/25/15 | 2280 | 425 | EAST GOSHEN TOWNSHIP - GENERAL VOID CK.2280 |
||
| 49552 | 7,666.80 | 09/25/15 | 2281 | 425 | EAST GOSHEN TOWNSHIP - GENERAL 3RD QTR.2015 REIMBURSEMNT FR: MA |
|||||
| 1509 | 7,666.80 | 0.00 | 24,251.00 | |||||||
| 07424-1400 | **** | *** | ***** | 24,251.00 | 0.00 | 24,251.00 | ||||
| 07424-3000 | MISCELLANEOUS EXPENSE | 0.00 | ||||||||
| 1501 | 45777 | 950.00 | 01/02/15 | 2260 | 2132 | PENNSYLVANIA MUNICIPAL AUTHORITIES ASSOC 2015 ACTIVE MEMBERSHIP DUES |
||||
| 46110 | 500.00 | 01/29/15 | 2263 | 2737 | COMMONWEALTH OF PA ANNUAL FEE - NPDES PERMIT -CHAP. |
|||||
| 1501 | 1,450.00 | 0.00 | 1,450.00 | |||||||
| 1506 | JE | 48342 | 18.05 | 07/02/15 | BANK FEE | DEPOSIT SLIP ORDER 6/6/15 | ||||
| 1506 | 18.05 | 0.00 | 1,468.05 | |||||||
| 07424-3000 | **** | *** | ***** | 1,468.05 | 0.00 | 1,468.05 | ||||
| 07424-3110 | MUNIC.AUTH.-AUDITING | 0.00 | ||||||||
| 1507 | CD | 48553 | 8,900.00 | 07/16/15 | 2275 | 808 | MAILLIE FALCONIERO & CO. EXAM.FINANCIAL STATEMENTS 12/31/ |
|||
| 1507 | 8,900.00 | 0.00 | 8,900.00 | |||||||
| 07424-3110 | **** | *** | ***** | 8,900.00 | 0.00 | 8,900.00 | ||||
| 07424-3130 | ENGINEERING SERVICES | 0.00 | ||||||||
| 1501 | 45953 | 621.50 | 01/15/15 | 2261 | 1052 | PENNONI ASSOCIATES INC. SERVICES THRU 12/7/14 GENERAL |
||||
| 46013 | 640.00 | 01/22/15 | 2262 | 1052 | PENNONI ASSOCIATES INC. SERVICE THRU 11/9/14 GEN.SERVICE |
|||||
| 1501 | 1,261.50 | 0.00 | 1,261.50 |
East Goshen Township General Ledger
Report Date 12/04/15
GL Transaction Details
PAGE 7
MGRP18 run by BRIAN 10 : 56 AM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07424-3130 | 1502 | CD | 46311 | 5,571.50 | 02/13/15 | 2264 | 1052 | PENNONI ASSOCIATES INC. SERVICES THRU 1/18/15 2014 CHAP. |
||
| 1502 | 5,571.50 | 0.00 | 6,833.00 | |||||||
| 1503 | 46649 | 5,685.00 | 03/12/15 | 2266 | 1052 | PENNONI ASSOCIATES INC. SERVICES THRU 2/15/15 2014 CHAP. |
||||
| 1503 | 5,685.00 | 0.00 | 12,518.00 | |||||||
| 1504 | 47119 | 4,718.75 | 04/15/15 | 2269 | 1052 | PENNONI ASSOCIATES INC. SERV. THRU 3/22/15 2015 GEN.SER |
||||
| 1504 | 4,718.75 | 0.00 | 17,236.75 | |||||||
| 1505 | 47583 | 10,136.50 | 05/14/15 | 2270 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 4/19/15 2015 GEN.SERV |
||||
| 1505 | 10,136.50 | 0.00 | 27,373.25 | |||||||
| 1506 | 47984 | 1,843.75 | 06/10/15 | 2272 | 1052 | PENNONI ASSOCIATES INC. SERVICE THRU 5/17/15 2015 GEN.SE |
||||
| 1506 | 1,843.75 | 0.00 | 29,217.00 | |||||||
| 1507 | 48553 | 1,921.25 | 07/16/15 | 2276 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 6/21/15 2015 SEMI-ANN |
||||
| 1507 | 1,921.25 | 0.00 | 31,138.25 | |||||||
| 1508 | 48772 | 373.75 | 08/03/15 | 2277 | 1052 | PENNONI ASSOCIATES INC. SERVICES THRU 7/19/15 2015 GEN.S |
||||
| 1508 | 373.75 | 0.00 | 31,512.00 | |||||||
| 1509 | 49338 | 460.00 | 09/11/15 | 2279 | 1052 | PENNONI ASSOCIATES INC. SERVICE THRU 8/16/15 2015 GEN.SE |
||||
| 1509 | 460.00 | 0.00 | 31,972.00 | |||||||
| 1510 | 49748 | 641.25 | 10/13/15 | 2283 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 9/20/15 2015 SEMI-ANN |
||||
East Goshen Township General Ledger
Report Date 12/04/15
GL Transaction Details
PAGE 8
MGRP18 run by BRIAN 10 : 56 AM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 1510 | 641.25 | 0.00 | 32,613.25 | |||||||
| 1511 | 50314 | 652.50 | 11/19/15 | 2285 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 10/18/15 2015 GEN.SERV |
||||
| 1511 | 652.50 | 0.00 | 33,265.75 | |||||||
| 07424-3130 | **** | *** | ***** | 33,265.75 | 0.00 | 33,265.75 | ||||
| 07424-3140 | LEGAL SERVICES | 0.00 | ||||||||
| 1503 | 46649 | 300.00 | 03/12/15 | 2265 | 528 | GAWTHROP GREENWOOD & HALSTED LEGAL SERVICE - 1/12/15 GEN.AUT |
||||
| 1503 | 300.00 | 0.00 | 300.00 | |||||||
| 1504 | 47119 | 840.00 | 04/15/15 | 2268 | 528 | GAWTHROP GREENWOOD & HALSTED LEGAL SERVICE 2/6-2/9/15 GEN.AUT |
||||
| 1504 | 840.00 | 0.00 | 1,140.00 | |||||||
| 1506 | 47984 | 860.00 | 06/10/15 | 2271 | 528 | GAWTHROP GREENWOOD & HALSTED LEGAL SERV. 4/7-4/13/15 GEN.AUT |
||||
| 1506 | 860.00 | 0.00 | 2,000.00 | |||||||
| 1507 | 48553 | 380.00 | 07/16/15 | 2274 | 528 | GAWTHROP GREENWOOD & HALSTED LEGAL SERVICE 6/3-6/8/15 GEN.AU |
||||
| 1507 | 380.00 | 0.00 | 2,380.00 | |||||||
| 1508 | 48918 | 300.00 | 08/12/15 | 2278 | 528 | GAWTHROP GREENWOOD & HALSTED LEGAL SERVICES 7/13/15 GEN.AUTH |
||||
| 1508 | 300.00 | 0.00 | 2,680.00 | |||||||
| 1510 | 49748 | 260.00 | 10/13/15 | 2282 | 528 | GAWTHROP GREENWOOD & HALSTED LEGAL SERVICES 8/10/15 GEN.AUTH. |
||||
| 1510 | 260.00 | 0.00 | 2,940.00 | |||||||
East Goshen Township General Ledger
Report Date 12/04/15
GL Transaction Details
PAGE 9
MGRP18 run by BRIAN 10 : 56 AM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07424-3140 | 1511 | CD | 50314 | 380.00 | 11/19/15 | 2284 | 528 | GAWTHROP GREENWOOD & HALSTED LEGAL SERV. 10/12/15 GEN.AUTH. |
||
| 1511 | 380.00 | 0.00 | 3,320.00 | |||||||
| 07424-3140 | **** | *** | ***** | 3,320.00 | 0.00 | 3,320.00 | ||||
| 07428-1000 | RESERVOIR PUMP STATION - ENGINEER | 0.00 | ||||||||
| 1501 | 45954 | 137.50 | 01/15/15 | 10029 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 12/7/14 RESERV.RD ACT |
||||
| 46014 | 852.50 | 01/22/15 | 10030 | 1052 | PENNONI ASSOCIATES INC. SERVICE THRU 11/9/14 RESERVOIR R ACT.537 |
|||||
| 1501 | 990.00 | 0.00 | 990.00 | |||||||
| 1502 | 46312 | 5,382.80 | 02/13/15 | 10031 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 1/18/15 RESERVOIR RD.P ACT 537 PLANNING |
||||
| 1502 | 5,382.80 | 0.00 | 6,372.80 | |||||||
| 1503 | 46650 | 10,394.70 | 03/12/15 | 10032 | 1052 | PENNONI ASSOCIATES INC. SERV. THRU 2/15/15 RESERVOIR RD. |
||||
| 1503 | 10,394.70 | 0.00 | 16,767.50 | |||||||
| 1504 | 47120 | 18,607.75 | 04/15/15 | 10033 | 1052 | PENNONI ASSOCIATES INC. SERV. THRU 3/22/15 RESERVOIR RD. DESIGN & PERMITTING |
||||
| 1504 | 18,607.75 | 0.00 | 35,375.25 | |||||||
| 1505 | 47584 | 15,825.75 | 05/14/15 | 10034 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 4/19/15 RESERVOIR RD. DESIGN & PERMITTING |
||||
| 1505 | 15,825.75 | 0.00 | 51,201.00 | |||||||
| 1506 | 47990 | 9,249.50 | 06/10/15 | 10035 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 5/17/15 RESERVOIR RD |
||||
| 1506 | 9,249.50 | 0.00 | 60,450.50 | |||||||
East Goshen Township General Ledger
Report Date 12/04/15
GL Transaction Details
PAGE 10
MGRP18 run by BRIAN 10 : 57 AM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07428-1000 | 1507 | CD | 48554 | 10,841.50 | 07/16/15 | 10036 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 6/21/15 - RESERVR.RD P DESIGN & PERMITTING |
||
| 1507 | 10,841.50 | 0.00 | 71,292.00 | |||||||
| 1508 | 48773 | 4,715.25 | 08/03/15 | 10037 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 7/19/15 RESERVOIR RD |
||||
| 1508 | 4,715.25 | 0.00 | 76,007.25 | |||||||
| 1509 | 49341 | 11,709.00 | 09/11/15 | 10038 | 1052 | PENNONI ASSOCIATES INC. SERVICES THRU 8/16/15 RESERV.RD |
||||
| 1509 | 11,709.00 | 0.00 | 87,716.25 | |||||||
| 1510 | 49749 | 34,515.75 | 10/13/15 | 10039 | 1052 | PENNONI ASSOCIATES INC. SERV. THRU 9/20/815 RESERVR RD |
||||
| JE | 50127 | 2,250.00 | 11/04/15 | RECLASS | RECLASS EARTHCORE INV.6865 PYMT. 10/22 CK.10040 | |||||
| 1510 | 36,765.75 | 0.00 | 124,482.00 | |||||||
| 1511 | CD | 50190 | 1,500.00 | 11/09/15 | 10041 | 263 | CHESTER COUNTY CONSERVATION DISTRICT RESERVOIR RD. PERMIT FEE |
|||
| 213.00 | 11/09/15 | 10042 | 2299 | CLEAN WATER FUND -PA DEP - BUREAU WATER DISTURBED ACREAGE FEE-RESERV.RD |
||||||
| *** | 1,713.00 | 0.00 *** | ||||||||
| 50313 | 7,240.75 | 11/19/15 | 10043 | 1052 | PENNONI ASSOCIATES INC. SERVICES THRU 10/8/15 RESERVR.RD |
|||||
| 1511 | 8,953.75 | 0.00 | 133,435.75 | |||||||
| 07428-1000 | **** | *** | ***** | 133,435.75 | 0.00 | 133,435.75 | ||||
| 07428-2000 | RESERVOIR PUMP STATION CONSTRUCTION | 0.00 | ||||||||
| 1510 | 49947 | 2,250.00 | 10/22/15 | 10040 | 2911 | EARTHCORE SERVICES LLC TRUCK RIG MOBILIZATION, SKIDSTEE TRACK RIG, AUGER PROBES |
||||
| JE | 50127 | 2,250.00 | 11/04/15 | RECLASS | RECLASS EARTHCORE INV.6865 PYMT. 10/22 CK.10040 | |||||
| 1510 | 2,250.00 | 2,250.00 | 0.00 | |||||||
East Goshen Township General Ledger
Report Date 12/04/15
GL Transaction Details
PAGE 11
MGRP18 run by BRIAN 10 : 57 AM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07428-2000 | **** | *** | ***** | 2,250.00 | 2,250.00 | 0.00 | ||||
| Grand Total | 207,313.91 | 106,816.30 | 100,497.61 | |||||||
DRAFT 12/11/2015
Municipal Authority Goals for 2016
Using the comprehensive plan that was adopted on October 20, 2015 as a guide, I propose the following goals for the Municipal Authority (MA) for 2016. Our goals for 2016 and the sections of the comprehensive plan that impact the MA are listed below.
- Operate RCSTP in compliance with NPDES Permit requirements.
- Continue to implement formal I & I plan.
- Respond to capacity requests within 45 days.
- Update the operations manual for RCSTP and pump stations.
- Submit topical articles of interest for the East Goshen newsletter.
- Attend West Goshen Municipal Authority meetings to keep informed of planned capital expenditures and operation compliance.
Municipal Authority Goals for 2015
- GOALS Submit an article for each newsletter – Due date for newsletter Need by 1/30/15 – Jack - Completed Need by 5/1/15 – Dana - Completed Need by 8/31/15 - Ed - Completed Need by 10/30/15 – Dana - Completed; Need by 1/30/15 – Jack - Completed; Need by 5/1/15 – Dana - Completed; Need by 8/31/15 - Ed - Completed; Need by 10/30/15 – Dana - Completed; Obtain construction permits for the Reservoir Road Pump Station – December 31, 2015 2/6 – Test boring done, meeting with Mike to review preliminary site plan and discuss control options. 3/9 concept design completed, met with PA DEP. 5/11 stormwater perc test completed, scheduled to meet with CCCD on 5/21 6/8 Nothing unusual from our meeting with CCCD. Rick and Mark need to meet with WG to discuss control process. 6/22 WG is ok with proposed control process; Attend West Goshen Meetings quarterly – more often if needed. 1 st Quarter – Jack - Completed 2 nd Quarter – Jack - Completed 3 rd Quarter - Ed - Completed 4 th Quarter; 1 st Quarter – Jack - Completed; 2 nd Quarter – Jack - Completed; 3 rd Quarter - Ed - Completed; 4 th Quarter; Respond to capacity requests in 45 days or less.
e. Continue to implement I & I Plan 5/11 meeting with Mike on 5/13 to review plan
f. Operate RCSTP in compliance with NPDES Permit February, April, May, June, July, August, September, October
9. Community Facilities and Services Plan
| 9.6. | Continuing the provisions of effective administrative, public works, and related services. | * | on-going | BOS | MA | Maintenance | GF |
|---|---|---|---|---|---|---|---|
| 9.7. | Continuing to support important and viable Community Facilities. | * | on-going | BOS | PR | Maintenance | GF |
10. Utilities Plan
| 10.1. | Continuing to provide effective sewage disposal and wastewater treatment with oversight of the Municipal Authority. | * | on-going | BOS | MA | Development | PS |
|---|---|---|---|---|---|---|---|
| 10.2. | Continuing to provide effective solid waste disposal, and recycling services. | * | on-going | BOS | MA | Maintenance | GF |
| 10.3. | Maintaining the role of the East Goshen Township Municipal Authority for evaluating sewered and unsewered areas. | * | on-going | BOS | MA | Special Study, Plan Review | PS |
F:\Data\Shared Data\ABC'S\Municipal Authority\Goals\2016\Municipal Authority Goals for 2016.doc
17 East Gay Street, Suite 100, P.O. Box 562 p. 610.696.8225
West Chester, PA 19381-0562 www.gawthrop.com
Gawthrop Greenwood, PC
Attorneys at Law
Patrick M. McKenna
610.696.8225 x 155
610.344.0922 fax
pmckenna@gawthrop.com
October 27, 2015
OCT 28 2015
Louis F. Smith, Jr., Manager
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380-6199
Re: 2016 Fees For Legal Services
Dear Rick:
Please be advised that for 2016, Gawthrop Greenwood has no plans to change the rates or the terms of engagement under which we currently service East Goshen Municipal Authority.
The firm is pleased to have the continuing opportunity to provide legal services to the Municipal Authority in 2016 at our current rate of $200 per hour. I highly value our long-standing relationship with East Goshen Township and its officials and staff. I would expect that for purposes of budgeting you would be safe in assuming that our experience in 2016 will be similar to the amount of work we did in 2015.
Very truly yours,
Patrick M. McKenna
PMM/ams
Reservoir Road Pump Station
12/10/2015
| Task No. | Activity | Approved Fee | Effort To-Date (thru 12/6/15) | Completed? | |
|---|---|---|---|---|---|
| 1 | Concept Design | $13,700.00 | $13,655.75 | T&M | Yes |
| 2 | DEP WQM Pre-App. Meeting | $1,400.00 | $1,300.00 | T&M | Yes |
| 3 | Existing Conditions Survey | $23,300.00 | $22,783.75 | LS | No |
| 4 | Sewer Stakeout in Easements | $3,600.00 | $0.00 | T&M | No |
| 5 | 1636 Bow Tree Dr. Boundary Survey & Easement | $4,020.00 | $0.00 | LS | No |
| 6 | Additional Boundary Surveys & Easements | $9,000.00 | $0.00 | T&M | No |
| 7 | Geotechnical Borings | $4,000.00 | $4,000.00 | LS | Yes |
| 8 | Install Permanent Survey Benchmarks | $4,000.00 | $0.00 | T&M | No |
| 9 | Progress Design | $39,100.00 | $29,450.00 | T&M | Yes |
| 10 | Infiltration Testing | $1,800.00 | $1,800.00 | T&M | Yes |
| 11 | Final Design | $47,400.00 | ±$56,333.50 | T&M | No |
| 12 | Permitting | $15,800.00* | ±$20,759.25* | T&M | No |
| TOTAL | $167,120.00 | ±$150,082.25 |
*Permitting originally approved for $15,800 without fee for floodplain H&H analysis or Joint Permit (JP) application. Fee for this extra effort was proposed at $11,500. Analysis and JP applications have been completed and submitted to PADEP for an additional $6,426, a portion of which was approved for payment at the November MA meeting. The remainder of the $6,426 still needs to be formally approved in the December and January monthly invoices.
Supplemental Fee
Projected effort to complete Phases 11 and 12 design, bid documents, and remaining permit applications will exceed the approved T&M fee estimate by approx. $18,000 + $6,426 for the H&H and JP application for a grand total approx. $24,426. This does not include responses or revisions to address any regulatory agency comments.
Reallocation of Budget
Phases 1, 2, 3, and 9 were completed for a combined $10,315 under budget.
We discussed that Phases 4, 6, and 8 work is not necessary at this time. These phases are a total of $16,600.
The total remaining from under budget phases and non-required phases is $26,915. A transfer of these funds into Phases 11 and 12 will cover the projected effort to complete the project as well as approx 20 hours of coordination with regulatory agencies and revisions/responses to any agency comments on the various permit applications.
Supplemental Work
- Floodplain H&H analysis and Joint Permit floodplain filling/creek crossing permit application
- Stormwater management design and NPDES permit application more effort than anticipated due to multiple stormwater BMPs being needed and significant plan detailing for Ridley Creek HQ watershed.
- DEP updated the NPDES Notice of Intent Application package in October after we had already filled nearly all of it out. They require most current forms so we had to re-do on new and additional forms.
- Prepared PennDOT HOP applications for soft dig test pits (approved Phase 12 Permitting scope included HOP applications for force main construction but not for test pits).
- More coordination with utility companies in preparation for soft dig test pits.
- PECO required an 8'x8' transformer pad/vault after the SWM design was completed. Since the pad was much larger than typical, we had to revise the entire SWM design to manage the extra impervious area.
Remaining Work
- QC review and submit PADEP Part 2 WQM permit application for the pump station
- Finalize PennDOT HOP application and detour routes for force main construction
- QC review bid document
- Update cost estimate for changes made during final design
- Water service application
- Field measure depths of several utility structures that were inaccessible to survey crew
- Confirm building architectural finish with EGT
- Address any comments from EGT Codes Dept
- Address PW comments to add utility sink in building
Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS
December 10, 2015
Rick Smith, Township Manager
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380
Re: Proposal for Professional Services
RCSTP and Pump Stations' O&M Manual
Dear Mr. Smith:
Pennoni Associates Inc. is pleased to submit the following proposal to prepare a new Operations and Maintenance (O&M) Manual for the Ridley Creek Sewage Treatment Plant (RCSTP) and for the pump stations in the conveyance systems.
BACKGROUND
The current Standard Operating Procedures manual for the Township-wide wastewater system was prepared in the 1970s and is no longer relevant with the current and expanded RCSTP and pump stations (PS), today's operating procedures and technology, OSHA safety standards, contacts, etc.
SCOPE OF WORK
Pennoni will prepare a brand new O&M Manual encompassing the RCSTP, Hershey's Mill Pump Station, Hunt Country Pump Station, Ashbridge Pump Station, Barkway Pump Station, and for critical components of the collection and conveyance system such as meters. The O&M Manual will include, but not necessarily be limited to, the following:
- Brief description of facilities Age, location, average flow rates, hydraulic and organic capacities, etc.; General treatment process of RCSTP with single-line process diagram
- Current permits
- Contact lists for Township & Authority personnel and contractors/consultants
- Information on key equipment such as pump, meter, generator make and models
- Equipment and chemical product literature and MSDS
- Standard operating procedures, particularly frequency of visits to pump stations and operational procedures during visits
- Regular maintenance procedures such as frequency of wet well cleaning, generator maintenance, meter calibration, etc.
- Control mechanisms for systems such as transducers in pump station wet wells
- Conditions that constitute emergencies
- Emergency response procedures
- Safety procedures, such as confined space entry procedures and related safety equipment information and lock-out tag-out
- Training requirements and certifications
- Township-wide sewer system map
Christiana Executive Campus • 121 Continental Drive • Suite 207 • Newark, DE 19713 • Ph: 302-655-4451 • Fx: 302-654-2895
www.pennoni.com
Rick Smith
December 10, 2015
Page 2
RCSTP and PS O&M Manual
The PW Department will provide listings of each pump station's equipment and pump station product literature and data sheets that are on file. Pennoni has the equipment records and literature for the expanded RCSTP.
Pennoni will assemble the O&M Manual documentation into a bound document with copies to keep at the RCSTP, each pump station, and at the Township building.
SCHEDULE
We anticipate the O&M Manual can be completed within 90 days of Notice to Proceed.
FEE
Our estimated fee, to be billed on a time and material basis, is $12,500.00. Work will be completed on an hourly basis, billed at the Authority's approved rates for Pennoni for the year in which work is performed.
Extraordinary expenses, authorized in advance and identifiable to the specific project will be billed in addition to the above stated fees. These expenses include, but are not limited to: application fees, UPS and delivery charges, and the reproduction of plans and specifications by outside services. We do not bill for such items as relatively small amounts of in-house printing, mailing expenses, reasonable telephone calls, and travel expenses.
BILLING AND PAYMENT
Fees will be billed monthly, based on actual services completed. Payment is due upon receipt of invoice. Billing and Payment shall be in accordance with Item three (3) of the below-referenced General Terms and Conditions.
The client acknowledges that the method of Billing and Payment has been discussed in detail; that the terms agreed upon can only be changed by a written addendum agreed to by both parties; and work may be stopped until payment is made in accordance with the agreement.
TERMS AND CONDITIONS
General
Pennoni Associates Inc. General Terms and Conditions (Form No. LE01, Rev. 11/2014) are considered as part of this proposal.
Rick Smith
December 10, 2015
Page 3
RCSTP and PS O&M Manual
We appreciate this opportunity to submit our proposal. Should you have any questions or need additional information, please do not hesitate to call. Please sign and return one (1) copy of this proposal as our Notice to Proceed.
Sincerely,
PENNONI ASSOCIATES INC.
Michael J. Ellis, PE
Authority Engineer
ACCEPTED BY: ________________________________________________
(Print Name and Title) ________________________________________________
DATE: ________________________________________________
W:\PROJECTS\EGMA\Proposals\2015-12-10 RCSTP and PS O&M Manual\O&M Manual proposal 12-10-2015.docx
BIG FISH
Rick Smith
From: scott_towler <scott_towler@comcast.net>
Sent: Friday, December 11, 2015 7:50 AM
To: Rick Smith
Cc: 'Phillips, Barb'
Subject: RE: RCSTP October Invoice
Rick,
Thank you.
Thanks again for the opportunity to operate RCSTP on behalf of the Township.
Enjoy a great day.
Sent from my Verizon Wireless 4G LTE smartphone
-------- Original message --------
From: Rick Smith <rsmith@eastgoshen.org>
Date: 12/11/2015 7:29 AM (GMT-05:00)
To: 'Scott' <scott_towler@comcast.net>
Cc: '"Phillips, Barb"' <bphillips@eastgoshen.org>
Subject: RE: RCSTP October Invoice
Scott
I am ok with the 2% increase
Rick
From: Scott [mailto:scott_towler@comcast.net]
Sent: Wednesday, December 09, 2015 11:01 PM
To: Rick Smith
Cc: Phillips, Barb
Subject: RCSTP October Invoice
Rick,
1
I apologize for being a nuisance. Can you provide an update on the status of the October O&M invoice for RCSTP? If there are any questions, don't hesitate to contact me.
I would like to request the Authority considering renewing our service to operate RCSTP and the sludge dewatering system. The CPI index for all services not including housing and rent for the area is 1.7%. I would like to Board and Township to consider a 2.0% increase of the base fee and hourly rate. If you're in agreement, I'll prepare a letter to accompany the O&M report for Monday's meeting.
Please advise.
Thanks again for the opportunity to operate RCSTP and serve both the Township and Municipal Authority.
Sincerely,
Scott A. Towler
2
Pennoni
PENNONI ASSOCIATES INC.
CONSULTING ENGINEERS
December 4, 2015
EGMA1600
Rick Smith, Township Manager
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380
Re: Fee Schedule for Year 2016 and Annual Services
East Goshen Municipal Authority
Dear Rick:
Pennoni is proud to serve East Goshen Municipal Authority, and we look forward to working with you again in 2016. We have enjoyed the challenging projects this year, and we cherish the relationships we have formed with the Authority, the Township, and the community. We respectfully request reappointment as Authority Engineer for 2016.
The proposed rates shown below for 2016 apply to our work as Municipal Authority Engineer. We are proposing an increase of approximately 3% per classification, with a range from 2.6% to 3.5% per classification.
- Authority Engineer....................................................................$119/hr
- Senior Engineer.........................................................................$113/hr
- Project Engineer........................................................................$100/hr
- Staff Engineer...........................................................................$93/hr
- Associate Engineer....................................................................$88/hr
- Senior Engineering Technician................................................$88/hr
- Graduate Engineer...................................................................$79/hr
- Engineering Technician II........................................................$79/hr
- Engineering Technician I.........................................................$69/hr
While our company has many employee classifications, these are the classifications most frequently utilized in performing tasks for our municipal clients. We assign the most appropriate level staff competent to perform the work effort requested.
As part of our responsibilities to the Authority as the appointed Engineer, we will provide the following professional services:
- Participation in monthly meetings of the Authority Board.
- Preparation of semi-annual sewer reports in March and September.
- Continuing support in I&I reduction with periodic sewer meter data analysis upon request.
- Preparation of the annual Chapter 94 Municipal Wasteload Management Reports.
- Consultation on issues on behalf of the Authority.
Christiana Executive Campus • 121 Continental Drive • Suite 207 • Newark, DE 19713 • Ph: 302-655-4451 • Fx: 302-654-2895
www.pennoni.com
EGMA1600
December 4, 2015
Page 2
Year 2016 Annual Services
Rick Smith
The estimated total fee for annual services is $38,500, to be billed on an hourly basis at the above rates. We have allocated the budget as follows:
- Monthly meetings and general consultation: $12,300
- I&I support and semi-annual reports: $11,200
- Chapter 94 reports: $15,000
The estimated fees are based upon the actual level of effort for each activity over the past four years. The total fee for these activities is a 3% increase over our 2015 fee, consistent with the 2016 budget approved by the Municipal Authority.
Similar to previous years, we will establish separate accounts for each project listed above, and each project will be invoiced separately. Other projects outside of general services, as requested, will be proposed separately and at the approved rates schedule.
If you have any questions, please do not hesitate to contact me.
Sincerely,
PENNONI ASSOCIATES INC.
Michael J. Ellis, PE
Authority Engineer
P:\Projects\EGMA\EGMA General Services for 2016\2016 EGMA Annual Services Proposal.docx
Memorandum
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380
Voice: 610-692-7171
Fax: 610-692-8950
E-mail: mgordon@eastgoshen.org
Date: 11/25/2015
To: Municipal Authority
From: Mark Gordon, Township Zoning Officer
Re: 53-4-37.1 / 942 Cornwallis Drive /Sewer Capacity
Dear Authority Members,
Enclosed is a subdivision application for a 2 lot subdivision at 942 Cornwallis Drive. The plan proposes to split the 3.5 ac parcel into two lots. The existing home is connected to public sewer. The applicant proposes to demolish the existing home and redevelop the lot with two new Single Family homes. The development will result in one new single family home connected to the public sewer system.
The applicant is requesting capacity for one new EDU and to reuse the existing EDU.
Draft Motion:
I move that we approve the sewer capacity request and authorize staff to forward the sewer planning module exemption request to DEP.
F:\Data\Shared Data\Property Management\53-4\53-4-37.1 (942 Cornwallis Drive)\SD Application 2015\Memo to MA 11262015.doc
Request for Sewage Planning Exemption
942 Cornwallis Drive
1. Introduction
Robert L. Gionfriddo is the owner/developer of the subject property, located at 942 Cornwallis Drive, West Chester, PA 19382. The property is located southwest of Cornwallis Drive in East Goshen Township and contains 3.59 acres of land (illustrated on Map 1).
Map 1 shows the project location on an aerial photograph map, and Map 2 shows the project location on a USGS Map– the development area is highlighted.
Map 1: Aerial Photograph:
Project Location: 942 Cornwallis Dr
Map labels: Devon Ln, Monte Vista Dr, Linda Vista Dr, East Goshen Farmers Market, East Goshen Park, Chandler Dr, N Chester Rd, Cornwallis Dr, King George Ct, Meadowbrook Ln, Del Vacchio Landscape & Garden Center, Vista Dr, Paoli Pike, Chester County Chamber of Business & Industry, Colonial Ln, Ridley Creek, East Goshen Cemetery, Pepper Mill, 352, Wawa, Bellingham, East Goshen Elementary School, Talmadge Dr, Oak Ln, E Boot Rd, Cherry Ln, Linden Ln, Generals Way, Saratoga Dr, Von Steuben Dr, East Goshen Township Park, Bridge Ct.
3800-CD-WSFR0359 Rev. 5/2010
Map 2: USGS Map:
PROJECT LOCATION
Map labels: ROAD, Mill, 500, GOSHEN, 450, TAYLOR AVE, ROAD, 462, Ridley, 438, 352, 400, 469, Goshenville, BM 388, BM 389, 413.
| Engineer | Project Information |
|---|---|
| JMR ENGINEERING, LLC 444 CREAMERY WAY, SUITE 300 EXTON, PA 19341 PHONE: (484) 880-7342 EMAIL: jack@JMRengineering.com Plotted: 11/25/15 | File: USGS Map.dwg |
USGS MAP: WEST CHESTER QUAD FOR 942 CORNWALLIS DRIVE EAST GOSHEN TOWNSHIP | CHESTER COUNTY, PA PROJECT #1090 | SCALE: 1"=1000' | DATE: 11/25/15 | BY: SRH |
3800-CD-WSFR0359 Rev. 5/2010
2. Project Description
ROBERT L. GIONFRIDDO is proposing to subdivide a 3.59-acre property located at 942 Cornwallis Drive, East Goshen Township, Chester County, Pennsylvania. The development shall subdivide the existing Tax Parcel Number 53-4-37.1 into two (2) separate parcels. Access for the two (2) new lots is provided by a proposed shared paved driveway intersecting with Cornwallis Drive. The lot falls within the R-2 Low Density Residential Zoning District and is proposed to contain two (2) detached single family dwellings and a shared driveway. The existing dwelling is currently served by public sewer. The proposed lot shall also be served by public sewer. Sewer treatment and disposal will be provided via Ridley Creek Sewer Treatment Plant.
Table 1 shows the breakdown of projected sewage flows for the proposed development.
Table 1:
| 942 Cornwallis Drive | |||
|---|---|---|---|
| Proposed Development | Unit Count | Flow (gpd) | Projected Flow (gpd) |
| Single Family Dwelling | 1 | 275 | 275 |
Total flow for the project is anticipated to be 275 gpd.
SUMMARY
The developer is requesting approval to allocate 1 EDU's of treatment and disposal to the proposed facility.
3800-CD-WSFR0359 Rev. 5/2010
- Development Information Name of Development: 942 Cornwallis Drive Developer Name: Robert Gionfriddo Address: 942 Cornwallis Drive, West Chester, PA 19380 Telephone #: (610) 476-0818 Email: argcomfort@gmail.com
- Location of Development a. County: Chester b. Municipality: East Goshen Township c. Address or Coordinates Lat: 39° 59' 49.8" N Long: -75° 33' 4.1" W d. Tax Parcel # 53-4-37.1 e. USGS Quad Name: West Chester Quad inches up 3.28 over 3.15 from bottom left corner of map. f. Located in a High Quality/Exceptional Value watershed? [×] Yes [ ] No
- Type of Development Proposed (check appropriate box) [×] Residential [ ] Multi-Residential Describe: 2 Single Family Dwellings/2 Lots [ ] Commercial [ ] Institutional Describe: ________________________________________ [ ] Brownfield Site Redevelopment [ ] Other (specify): ________________________________________
- Size a. # of lots: 2 # of EDUs: 1 b. # of lots since 5/15/72: N/A c. Development Acreage: 0.73 d. Remaining Acreage: 2.86
- Sewage Flows: 275 gpd
- Proposed Sewage Disposal Method (check applicable boxes) a. [×] Sewerage System [×] Existing (connection only) [ ] New (extension) [×] Public [ ] Private [ ] Pump Station(s)/Force Main [×] Gravity Name of existing system being extended: ________________________________________ Interceptor Name: ________________________________________ Treatment Facility Name: Ridley Creek Sewer Treatment Plant NPDES Permit: ________________________________________ b. [ ] Construction of Treatment Facility [ ] With Stream Discharge [ ] With Land Application (not including IRSIS) [ ] Other [ ] Repair? Name of waterbody where point of discharge is proposed (if stream discharge): ________________________________________ c. [ ] Onlot Sewage Disposal Systems (check appropriate box) [ ] Individual onlot system(s) (including IRSIS) [ ] Community onlot system [ ] Large-Volume onlot system d. [ ] Retaining tanks Number of Holding Tanks: ________________ Number of Privies: ________________
- [ ] Request Sewage Facilities Planning Module forms in electronic format
- Request for Planning Exemption a. Protection of rare, endangered or threatened species Check one: [ ] The "PNDI Project Environmental Review Receipt" is attached. or [×] A completed "PNDI Project Planning & Environmental Review Form," (PNDI Form) is attached. I request DEP staff to complete the required PNDI search for my project. I realize that my planning exemption will be considered incomplete and that the DEP processing of my planning exemption request will be delayed, until a "PNDI Project Environmental Review Receipt" and all supporting documentation from jurisdictional agencies (when necessary) is/are received by DEP. Applicant or Consultant Initials: ______ b. [×] Plot Plan Attached [ ] Site Reports Attached c. Onlot Disposal Systems (1) I certify that the Official Plan shows this area as an onlot service area. ________________________________________ / ______________ (Signature of Municipal Official) Date ________________________________________ / ______________ Name (Print) Title Municipality (must be same as in 2.b.): ________________________________________ Telephone #: ________________________ (2) I certify that each lot in this subdivision has been tested and is suitable for both a primary and replacement sewage disposal system. ________________________________________ / ______________ Signature of SEO Date ________________________________________ / ______________ Name (Print) Certification # Telephone #: ________________________ (3) I certify that each lot in this subdivision is at least 1 acre in size ________________________________________ / ______________ (Signature of Project Applicant/Agent) Date d. Public Sewerage Service (i.e., ownership by municipality or authority) Based upon written documentation, I certify that the facilities proposed for use have capacity and that no overload exists or is projected within 5 years. (Attach documents.) ________________________________________ / ______________ (Signature of Municipal Official) Date ________________________________________ / ______________ Name (Print) Title Municipality (must be same as in 2.b.): ________________________________________ Telephone #: ________________________
- 4 -
Return Correspondence/Forms to:
DEPARTMENT OF ENVIRONMENTAL PROTECTION
DEP USE
Components Sent
- Onlot Disposal
- Collection and Treatment
- Planning Agency Review
- Exempt from Planning
Code
Date
"Fold Here"
PNDI Project Environmental Review Receipt
Project Search ID: 20151125540582
1. PROJECT INFORMATION
Project Name: Gionfriddo
Date of review: 11/25/2015 11:22:45 AM
Project Category: Development,Residential,subdivision which will contain 1-2 lots with 1-2 single family living units
Project Area: 3.7 acres
County: Chester Township/Municipality: East Goshen
Quadrangle Name: WEST CHESTER ~ ZIP Code: 19380
Decimal Degrees: 39.997154 N, -75.551131 W
Degrees Minutes Seconds: 39° 59' 49.8" N, -75° 33' 4.1" W
Map showing the project location parcel outlined in red.
Labels: King George Ct; Cornwallis Dr; Google; Map data ©2015 Google.
2. SEARCH RESULTS
| Agency | Results | Response |
|---|---|---|
| PA Game Commission | No Known Impact | No Further Review Required |
| PA Department of Conservation and Natural Resources | Potential Impact | FURTHER REVIEW IS REQUIRED, See Agency Response |
| PA Fish and Boat Commission | No Known Impact | No Further Review Required |
| U.S. Fish and Wildlife Service | No Known Impact | No Further Review Required |
As summarized above, Pennsylvania Natural Diversity Inventory (PNDI) records indicate there may be potential impacts to threatened and endangered and/or special concern species and resources within the project area. If the response above indicates "No Further Review Required" no additional communication with the respective agency is required. If the response is "Further Review Required" or "See Agency Response," refer to the appropriate agency comments below. Please see the DEP Information Section of this receipt if a PA Department of Environmental Protection Permit is required.
Page 1 of 5
PNDI Project Environmental Review Receipt
Project Search ID: 20151125540582
Note that regardless of PNDI search results, projects requiring a Chapter 105 DEP individual permit or GP 5, 6, 7, 8, 9 or 11 in certain counties (Adams, Berks, Bucks, Carbon, Chester, Cumberland, Delaware, Lancaster, Lebanon, Lehigh, Monroe, Montgomery, Northampton, Schuylkill and York) must comply with the bog turtle habitat screening requirements of the PASPGP.
RESPONSE TO QUESTION(S) ASKED
Q1: "Will the entire project area (including any discharge), plus a 300 feet buffer around the project area, all occur in or on an existing building, parking lot, driveway, road, road shoulder, street, runway, paved area, railroad bed, maintained (periodically mown) lawn, crop agriculture field or maintained orchard?"
Your answer is: 3. Unknown
3. AGENCY COMMENTS
Regardless of whether a DEP permit is necessary for this proposed project, any potential impacts to threatened and endangered species and/or special concern species and resources must be resolved with the appropriate jurisdictional agency. In some cases, a permit or authorization from the jurisdictional agency may be needed if adverse impacts to these species and habitats cannot be avoided.
These agency determinations and responses are valid for two years (from the date of the review), and are based on the project information that was provided, including the exact project location; the project type, description, and features; and any responses to questions that were generated during this search. If any of the following change: 1) project location, 2) project size or configuration, 3) project type, or 4) responses to the questions that were asked during the online review, the results of this review are not valid, and the review must be searched again via the PNDI Environmental Review Tool and resubmitted to the jurisdictional agencies. The PNDI tool is a primary screening tool, and a desktop review may reveal more or fewer impacts than what is listed on this PNDI receipt. The jurisdictional agencies strongly advise against conducting surveys for the species listed on the receipt prior to consultation with the agencies.
PA Game Commission
RESPONSE: No Impact is anticipated to threatened and endangered species and/or special concern species and resources.
PA Department of Conservation and Natural Resources
RESPONSE: Further review of this project is necessary to resolve the potential impacts(s). Please send project information to this agency for review (see WHAT TO SEND).
DCNR Species: (Note: The PNDI tool is a primary screening tool, and a desktop review may reveal more or fewer species than what is listed below. After desktop review, if a botanical survey is required by DCNR, we recommend the DCNR Botanical Survey Protocols, available here: http://www.gis.dcnr.state.pa.us/hgis-er/PNDI_DCNR.aspx)
Scientific Name: Fimbristylis annua
Common Name: Annual Fimbry
Current Status: Threatened
Proposed Status: Threatened
Scientific Name: Sensitive Species**
Page 2 of 5
PNDI Project Environmental Review Receipt
Project Search ID: 20151125540582
Common Name:
Current Status: Threatened
Proposed Status: Threatened
Scientific Name: Symphyotrichum depauperatum
Common Name: Serpentine Aster
Current Status: Threatened
Proposed Status: Threatened
PA Fish and Boat Commission
RESPONSE: No Impact is anticipated to threatened and endangered species and/or special concern species and resources.
U.S. Fish and Wildlife Service
RESPONSE: No impacts to federally listed or proposed species are anticipated. Therefore, no further consultation/coordination under the Endangered Species Act (87 Stat. 884, as amended; 16 U.S.C. 1531 et seq. is required. Because no take of federally listed species is anticipated, none is authorized. This response does not reflect potential Fish and Wildlife Service concerns under the Fish and Wildlife Coordination Act or other authorities.
* Special Concern Species or Resource - Plant or animal species classified as rare, tentatively undetermined or candidate as well as other taxa of conservation concern, significant natural communities, special concern populations (plants or animals) and unique geologic features.
** Sensitive Species - Species identified by the jurisdictional agency as collectible, having economic value, or being susceptible to decline as a result of visitation.
WHAT TO SEND TO JURISDICTIONAL AGENCIES
If project information was requested by one or more of the agencies above, send the following information to the agency(s) seeking this information (see AGENCY CONTACT INFORMATION).
Check-list of Minimum Materials to be submitted:
- x SIGNED copy of this Project Environmental Review Receipt
- x Project narrative with a description of the overall project, the work to be performed, current physical characteristics of the site and acreage to be impacted.
- x Project location information (name of USGS Quadrangle, Township/Municipality, and County)
- x USGS 7.5-minute Quadrangle with project boundary clearly indicated, and quad name on the map
The inclusion of the following information may expedite the review process.
- x A basic site plan(particularly showing the relationship of the project to the physical features such as wetlands, streams, ponds, rock outcrops, etc.)
- ____ Color photos keyed to the basic site plan (i.e. showing on the site plan where and in what direction each photo was taken and the date of the photos)
- x Information about the presence and location of wetlands in the project area, and how this was determined
Page 3 of 5
PNDI Project Environmental Review Receipt Project Search ID: 20151125540582
(e.g., by a qualified wetlands biologist), if wetlands are present in the project area, provide project plans showing the location of all project features, as well as wetlands and streams
4. DEP INFORMATION
The Pa Department of Environmental Protection (DEP) requires that a signed copy of this receipt, along with any required documentation from jurisdictional agencies concerning resolution of potential impacts, be submitted with applications for permits requiring PNDI review. For cases where a "Potential Impact" to threatened and endangered species has been identified before the application has been submitted to DEP, the application should not be submitted until the impact has been resolved. For cases where "Potential Impact" to special concern species and resources has been identified before the application has been submitted, the application should be submitted to DEP along with the PNDI receipt. The PNDI Receipt should also be submitted to the appropriate agency according to directions on the PNDI Receipt. DEP and the jurisdictional agency will work together to resolve the potential impact(s). See the DEP PNDI policy at http://www.naturalheritage.state.pa.us.
Page 4 of 5
PNDI Project Environmental Review Receipt Project Search ID: 20151125540582
5. ADDITIONAL INFORMATION
The PNDI environmental review website is a preliminary screening tool. There are often delays in updating species status classifications. Because the proposed status represents the best available information regarding the conservation status of the species, state jurisdictional agency staff give the proposed statuses at least the same consideration as the current legal status. If surveys or further information reveal that a threatened and endangered species and/or special concern species and resources exist in your project area, contact the appropriate jurisdictional agency/agencies immediately to identify and resolve any impacts.
For a list of species known to occur in the county where your project is located, please see the species lists by county found on the PA Natural Heritage Program (PNHP) home page (www.naturalheritage.state.pa.us). Also note that the PNDI Environmental Review Tool only contains information about species occurrences that have actually been reported to the PNHP.
6. AGENCY CONTACT INFORMATION
|
PA Department of Conservation and Natural Resources |
U.S. Fish and Wildlife Service |
|---|---|
|
PA Fish and Boat Commission |
PA Game Commission |
7. PROJECT CONTACT INFORMATION
Name: John M. Robinson, PE
Company/Business Name: JMR Engineering, LLC.
Address: 444 Creamery Way, Suite 300
City, State, Zip: Exton, PA 19341
Phone:(484) 880-7342 Fax:( )
Email: jack@jmrengineering.com
8. CERTIFICATION
I certify that ALL of the project information contained in this receipt (including project location, project size/configuration, project type, answers to questions) is true, accurate and complete. In addition, if the project type, location, size or configuration changes, or if the answers to any questions that were asked during this online review change, I agree to re-do the online environmental review.
John M. Robinson (Agent)
applicant/project proponent signature
11/25/2015
date
Page 5 of 5