Municipal Authority

The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.

 

The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.

  • Five members, serving five-year terms
  • Meetings are on the 2nd Monday of the month at 7:00 P.M.
  • All township meetings are held at the Township Building and open to the public
Authority Members Term Expiration Date
Kevin Cummings, Chairman 2026
John Stipe, Vice Chairman
2029
Dana Pizzarro, Secretary 2026
Sean Ellsworth, Assistant Secretary/Treasurer 2028
Walter Wujcik, Treasurer 2028
Pennoni Associates, Engineer
Patrick M. McKenna, Esq.
Peter Hicks, BoS Liaison
Kevin Miller, Staff Liaison

 

Municipal Authority Genealogy

Audits

Documents

Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.

EAST GOSHEN MUNICIPAL AUTHORITY

March 14, 2016
7:00 PM

  1. CALL TO ORDER/PLEDGE OF ALLEGIANCE/MOMENT OF SILENCE Ask if anyone will be taping the meeting?
  2. CHAIRMAN’S REPORT/OTHER MEMBERS REPORTS
  3. SEWER REPORTS Director of Public Works Report; Pennoni Engineer’s Report; Big Fish Environmental Inc. Report with DMR’s
  4. APPROVAL OF MINUTES February 8, 2016
  5. APPROVAL OF INVOICES a. Pennoni Invoice #678096 $311.25 b. Pennoni Invoice #678097 $1,623.50 c. Pennoni Invoice #678098 $1,868.25 d. Pennoni Invoice #678099 $1,155.25 e. Pennoni Invoice #678100 $2,209.50 f. Pennoni Invoice #678101 $3,248.75 g. Pennoni Invoice #678618 $1,392.75 h. Gawthrop Invoice #141172 $480.00
  6. LIAISON REPORTS
  7. FINANCIAL REPORTS February 2016 Report
  8. OLD BUSINESS
  9. GOALS Operate the Ridley Creek Sewer Treatment Plant in compliance with NPDES Permit requirements.; Continue to implement the formal Inflow (surface water) & Infiltration (ground water), (collectively “I&I”) Plan to reduce the amount of I&I into the sewer system.

F:\Data\Shared Data\Agendas\Municipal Authority\2016\3-14-16 - .doc

  1. Respond to capacity requests within 45 days. Develop an operation manual for Ridley Creek Sewer Treatment Plant and pump stations.
  2. Submit topical articles of interest for the East Goshen newsletter.
  3. Attend West Goshen Municipal Authority meetings to keep informed of planned capital expenditures and operation compliance.
  1. NEW BUSINESS 943 Cornwallis Drive Sewage Facilities Planning Module Exemption
  2. CAPACITY REQUESTS
  3. ANY OTHER MATTER
  4. CORRESPONDENCE AND REPORTS OF INTEREST
  5. PUBLIC COMMENT
  6. ADJOURNMENT

F:\Data\Shared Data\Agendas\Municipal Authority\2016\3-14-16 - .doc

AREA CODE 610
692-7171

EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

March 5, 2016

To: Municipal Authority
From: Mark Miller
Re: February 2016 Monthly Report

Monthly Flows: The average daily flow to West Goshen was 850,000 to 900,000. It was over One Million for 10 days. They dropped down once everything settled down. We also installed the portable meters at the new locations.

Meters: The meters were calibrated on the first of the month. I’m currently working with Allied Control and Lenni Electric on the logistics for the Ridley Creek flow meters.

C.C. Collection: We were notified of a problem on Heather Lane; the resident thought his lateral was backing up. We inspected the pipe and the clean-out pipe had pulled out of the tee. We pushed the pipe back into the tee. This is the second time we have replaced the tee.

R.C. Collection: The leaks that we located on Cornwallis Drive have been repaired. Our next area will be the Ridley Creek Interceptor line from Paoli Pike and Line Road to the plan we will also inspect the Applebrook carriage homes and the Applebrook Reserve.

We placed an order for 2’ and 4’ risers as well as casting and lids. As we need to raise several casting in low areas.

R.C. Plant: We had to pull the utility water pump for repairs. While pulling the pump we found the piping to be in bad shape plus all the gaskets were blown out. We pulled the piping and replaced it as well as the gaskets and hardware. The pump went to Deckmen’s for repairs. The estimate to

repair the pump was $3,890.00. The cost to replace the pump is $8,300.00. I gave the ok to repair the pump.

We also pulled the number 1 lift station pump for routine maintenance; the bearings on the top end need to be replaced in order to get to the bearings the pump has to be completely pulled down. The cost for the repairs are $5,000.00 . I gave them the ok for repairs. If we were to send the pump back to FLYGHT for repairs the cost could be $7,800.00. Once the pump returns we install it and pull pump 2 for maintenance.

Lenni Electric was called into replace the UPS boxes on the filters. Lenni has also been on site going thru all the electrical components.

While we were working on the Utility water piping the Dave Wolfinger showed for a surprise inspection he said he found the plant to be in good working condition and was impressed with the preventive maintenance being done.

When we did the work at the plant we needed to rent a 6 inch trailer pump to bypass the flow. I would recommend we purchase a trailer mounted pump in the 2017 budget. As you know most of our problems with sewer flows are weather related; if we had a full blown pump failure at the plant we would not be able to pump the effluent. The nearest pump is 2.5 hours away in New Jersey and then there is no guarantee they will have what we need. We could also use the pump to bypass pump the interceptor lines and pump stations if need be. When we were working at the plant the DEP showed up for an inspection, the inspector was very surprised that we did not own a large pump and hinted that we should consider purchasing one.

Action Items: MUFFIN MONSTER REPAIR
DISCUSS UPGRADES AT HUNT COUNTRY PUMP STATION

Sewer Lateral: Five sewer laterals repaired for the month by plumbers.

Alarms: We responded to 37 alarms for February.

PA One Calls: We received 50 Pa One calls February.

To: Municipal Authority
From: Mark Miller
Re: Muffin Monster Repair (ACTION ITEM)

The Muffin Monster has been in operation since 2009 and needs to be rebuilt. I contacted Charlie Deckman about rebuilding the unit. However, after he priced out the job it is cheaper for us to do a swap out with JWC who is the manufacture. This is the same thing we did with the Ash Bridge Pump Station. The cost would be $21,151.00 with shipping. My recommendation would be to pull the unit and do the swap out with JWC, it comes with a full manufacture warranty.

Mark S. Miller
Director of Public Works

JWC Environmental
Customer Service Center
2600 S. Garnsey Street
Santa Ana, CA 92707 USA
Phone: 949 833-3888
Toll Free: 800 331-2277
Fax: 714 549-4007

Customer: 6005886
Mark Miller
East Goshen Township
1580 Paoli Pike
West Chester , PA 19380
US
610-692-7171

Quote Number: 31733
Quote Date: 02/29/2016
Terms: NET 30 DAYS
Pricing: Valid 60 Days
FOB: Origin
Lead Time: 3-4 Weeks ARO Shipping and Handling is included both ways in this price
Grinder Serial #: 105661-2-1

Project: Ridley Creek WWTP

All orders will be billed the applicable sales tax, based on the "ship to address", unless a valid tax exemption certificate is provided prior to shipment.

Part Number Description Qty Unit Price Extended Price
EVAL_CA CDD3210-XDS2.0 Exchange Return
Expected Return
Grinder SN: 105661-2-1
1 $0.00 $0.00
CDD3210-XDS2.0 CDD3210-XDS2.0 Exchange
11T Cam Cutters
1:1 Stack Alloy STL
Buna N Elastomers
Motor Type Electric
Less 5HP Motor
Less Spool
Less 29:1 Reducer
Grinder SN: TBD
Paint: Epoxy Green
Drums 1/2" Perforated Drums
1 $21,151.00 $21,151.00
CORERT Core Return
CORE RETURN
Please return your unit within 30 days
to activate the Warranty on your
Santa Ana, CA 92707Recondition Cutter Cartridge and to
qualify you for the future Exchanges.
Return equipment to:
********************************************
JWC Environmental
2600 South Garnsey Street
Santa Ana, CA 92707
1 $0.00 $0.00
Shipping Shipping & Handling 1 $0.00 $0.00
Please verify serial number is correct. Sub Total $21,151.00

Sue Smith

From: Mark Miller <mmiller@eastgoshen.org>
Sent: Wednesday, March 09, 2016 5:45 AM
To: ssmith@eastgoshen.org
Cc: mmiller@eastgoshen.org
Subject: Hunt Country pump station rehab

To Municipal Authority
From Mark Miller
Ref. Hunt Country Pumping Station Rehab

I have reached out to J.T Seeley Inc. to get pricing to rehabilitate the Hunt Country Pumping Station. Attached is the quote from J.T.Seeley & Company Keep in mind that our thoughts would be to install the components from the reserve pumping station. I sent the control panel to John Laidley to update some of the electronics and get it ready to go since the one that is in place now has been in service for 35 years. Attached is the quote from J.T. Seeley in the amount of 13,626.00 the cost to upgrade the existing pumps by Deckmen will be $2,500.00 per pump.
I met with MGK to get a price to gut and install the new rail system and pumps.

Mark S. Miller
Director of Public Works
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380
O: (610) 692-7171 x3402
F: (610) 692-8950
mmiller@eastgoshen.org
www.eastgoshen.org

1

TO
EAST GOSHEN

MH R473A

Gusher
MANHOLE
4 FT

Manhole leaking on Cornwallis Dr

Repair: Drill and pump grout in.

73-R473A_2252016-1146_U_16750.mp4

Navigate Favorites Help

MH R473
2/25/2016

TO
EAST GOSHEN

MH R473A

0 FT

Cornwallis Dr.

Repair: Drill and pump grout in.

Sump Pump
Cornwallis Dr.

Enforcement Letter will be sent

TO
EAST GOSHEN

MH R462

Big Fish Environmental Services Inc.

Monthly Operations Report: February 2016

Executive Summary

The Ridley Creek sewage treatment plant outfall 001 achieved compliance with the NPDES discharge permit during January 2016. Discharge to Applebrook was discontinued during January. Chemical usage utilized for total phosphorus removal, pH and total alkalinity remained consistent with previous months. No mechanical or operational issues were observed during operation of sludge dewatering equipment.

Treatment Process Operation

During January 2016, there were no exceedances of the final effluent discharge limitations for outfall 001. Additional TSS samples were collected twice per week to allow for a means to calculate a weekly average. The total phosphorus monthly average concentration of 0.12 mg/L as compared to the permitted limitation of 0.50 mg/L. Table 1 illustrates the final effluent composite sample data reported for the January 2016 eDMR. During the month, the final effluent total phosphorus concentration discharged ranged from 0.10 mg/L to 0.16 mg/L.

Table 1
January 2016 - Final Effluent - Out Fall 001
NPDES Permit Discharge Limitations Flow CBOD5 TSS NH4-N Phosphorus,Total , mg/L Fecal Coliform
MGD Average mg/L lbs/month mg/L lbs/month mg/L lbs/month mg/L lbs/month Geo Mean Geo Mean
0.75 20 125 10 131 7 44 0.5 3 200 1,000
Instantaneous Maximum 40 42
Sample Date
January 5, 2016 0.377 2.6 8.2 1 3 0.333 1.05 0.10 0.31 1 0.0000
January 7, 2016 0.338 2 6
January 12, 2016 0.385 2.0 6.4 3 10 0.244 0.78 0.11 0.35 1 0.0000
January 14, 2016 0.358 2 6
January 19, 2016 0.443 5.1 18.8 6 22 1.46 5.39 0.12 0.44 3 0.4771
January 21, 2016 0.365 4 12
January 26, 2016 0.362 5.2 15.7 5 15 8.30 25.1 0.16 0.48 90 1.9542
January 28, 2016 0.376 5 16
Average 0.376 3.7 12.3 4 11 2.584 8.07 0.12 0.40 4 0.6078
Minimum 0.338 2.0 6.4 1 3 0.244 0.78 0.10 0.31 1 0.0000
Maximum 0.443 5.2 18.8 6 22 8.300 25.06 0.16 0.48 90 1.9542

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382

Page 1 of 8

Big Fish Environmental Services Inc.

Discharge to Applebrook, Outfall 002, continued to remain off line during January 2016. Table 2 illustrates the influent composite sample data reported for the January 2016.

Table 2
January 2016 - Influent Wastewater
Design Basis Flow BOD5 TSS NH4-N TKN, mg/L Phosphorus,Total, mg/L
mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day
MGD Average 335 2,098 320 2,001 32 200 48 301 9.1 57
Sample Date
January 5, 2016 0.481 199 798 188 754 36.7 147 46.0 184 3.9 16
January 12, 2016 0.471 188 754 200 802 30.8 123 34.1 134 3.8 15
January 19, 2016 0.468 156 625 68 273 33.6 135 37.2 145 3.9 16
January 29, 2016 0.530 225 902 197 790 36.8 148 41.1 182 4.1 16
Average 0.487 192 770 163 654 34.5 138 39.6 161 3.9 16
Minimum 0.468 156 625 68 273 30.8 123 34.1 134 3.8 15
Maximum 0.530 225 902 200 802 36.8 148 46.0 184 4.1 16

Table 3 presents the available Outfall 001 final effluent data for the month of February 2016. During February, the presence of foam conditions on the surface of the SBRs remained consistent with the previous month with foam concentrations ranging from 10% to 60% of the area. This is attributed to decreasing water temperatures supporting conditions for growth of filamentous bacteria. Increasing the F:M ratio and decreasing MLSS concentrations is employed to assist in managing the increase in filamentous growth.

During February, there are no anticipated exceedances of the permitted limitations for Outfall 001. There was no discharge from outfall 002. Split sampling of the composite sample collected by Applied Laboratory Services (ALS) is ongoing for comparative analysis and daily results.

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382

Page 2 of 8

Big Fish Environmental Services Inc.

Table 3
February 2016 - Final Effluent - Out Fall 001
NPDES Permit Discharge Limitations Flow CBOD5 TSS NH4-N Phosphorus,Total , mg/L Fecal Coliform
MGD Average mg/L lbs/month mg/L lbs/month mg/L lbs/month mg/L lbs/month Geo Mean Geo Mean
0.75 20 125 10 131 7 44 0.5 3 200 1,000
Instantaneous Maximum 40 42
Sample Date
February 2, 2016 0.409 2.9 9.9 4 14 7.09 24.18 0.21 0.72 1 0.0000
February 5, 2016 0.559 1 5
February 9, 2016 0.390 2.0 6.5 1 3 3.40 11.06 0.18 0.59 2 0.3010
February 12, 2016 0.491 1 4
February 16, 2016 0.699 2.0 11.7 2 12 3.38 19.70 0.16 0.93 1 0.0000
February 18, 2016 0.413 3 10
February 23, 2016 0.432 2.4 8.6 5 18 3.044 10.97 0.10 0.36 1 0.0000
February 25, 2016
Average 0.485 2.3 9.2 2 9 4.229 16.48 0.16 0.65 1 0.0753
Minimum 0.390 2.0 6.5 1 3 3.044 10.97 0.10 0.36 1 0.0000
Maximum 0.699 2.9 11.7 5 18 7.090 24.18 0.21 0.93 2 0.3010

The influent wastewater pollutant concentrations and loading entering the wastewater treatment facility remained within the design concentrations. Composite samples are collected at the influent doghouse manhole and influent wet well. The influent flow meter reading is collected from the influent flow meter located prior to the Screening Building, excluding the internal recycle flows.

Table 4 presents the available pollutant data for the influent wastewater collected at the doghouse manhole during February 2016.

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382

Page 3 of 8

Big Fish Environmental Services Inc.

Table 4
February 2016 - Influent Wastewater
Design Basis Flow BOD5 TSS NH4-N TKN, mg/L Phosphorus,Total, mg/L
mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day
MGD Average 335 2,098 320 2,001 32 200 48 301 9.1 57
Sample Date
February 2, 2016 0.495 272 1,124 196 810 30.1 124 42.2 174 5.7 24
February 9, 2016 0.488 193 797 122 504 23.7 98 36.7 149 3.9 16
February 16, 2016 0.961 179 739 186 768 31.6 131 38.6 309 4.0 17
February 23, 2016 0.543 164 677 346 1,429 25.9 107 31.2 141 3.9 16
Average 0.622 202 834 213 878 27.8 115 37.2 194 4.4 18
Minimum 0.488 164 677 122 504 23.7 98 31.2 141 3.9 16
Maximum 0.961 272 1124 346 1429 31.6 131 42.2 309 5.7 24

Sequencing batch reactors (SBRs) numbered 1, 3 and 4 were in service during January and February. Process monitoring of each SBR included ammonia as N, nitrite as N, Nitrate as N, COD, SSV, MLSS and total phosphorus. Daily analysis of the final effluent flow equalization grab sample is total phosphorus is ongoing. Sample collection and analysis of the influent wastewater collected at the influent pump station wet well is ongoing.

Addition of aluminum sulfate solution to the SBRs to assist with phosphorus removal continued. The volume of aluminum sulfate solution to the SBRs decreased to from 72.1 gpd to 70.3 gpd. Soda ash daily addition increased from 406 lbs. per day to 417 lbs. per day. Soda ash assists towards maintaining SBR pH concentrations above 7.0 standard units and assists to replenish alkalinity consumed during the nitrification process and aluminum sulfate solution addition.

SBR No. 2 remains out of service as a treatment unit. Minor repairs will be scheduled as weather conditions permit.

Solids Dewatering and Disposal: February 2016

Sludge Dewatering Summary
Gallons of sludge dewatered 245,576
Number of dumpsters 4

*Eighteen (18) days of centrifuge operation

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382

Page 4 of 8

Big Fish Environmental Services Inc.

Flow data:

Flow Meter Location February 2016 Daily Maximum Flow, gpd
Total Volume for Month, MG Average Daily Flow, gpd
Influent Wastewater to Screening Building* 17.465 602,254 1,098,740
Influent Wastewater to SBRs 16.748 577,514 885,824
Internal Recycle 0.612 21,092 292,596
Treated Effluent to Disc Filters 16.536 570,214 803,968
Final Effluent Discharge 14.056 484,690 699,000
Applebrook Golf Course No Discharge No Discharge No Discharge

Chemical Usage:

Chemical February 2016
Daily Average Total Monthly
Soda Ash 417 12,500
Aluminum Sulfate solution 70.3 2,039
Polymer (centrifuge) 0.84 15.12

*twenty two (22) days of centrifuge operation

During February, sludge wasting to the sludge holding tanks and decanting of the sludge holding tanks was ongoing. Process monitoring included pH, total alkalinity and total solids.

Sludge holding tank No. 1 was in service. The level at the beginning of February was 11.19 feet. The level transducer failed on February 23rd. The average total solids concentration was 0.93%. The average pH was 5.89 S.U. with an average total alkalinity of 85 mg/L. Zero gallons of supernatant were decanted during the month. 350 pounds of soda ash were added.

Sludge holding tank No. 2 was in service. The level at the beginning of the month was 7.07 feet and the level at the end was 11.81. The average total solids concentration was 0.70%. The average pH was 6.56 S.U. with an average total alkalinity of 123 mg/L. Zero pounds of soda ash were added. Zero gallons of supernatant were decanted.

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382

Page 5 of 8

Big Fish Environmental Services Inc.

PA DEP

February 17, 2016: Dave Wolfinger from PA DEP arrived on site unannounced to perform an annual from 9:30 AM through 11:30 AM.

Significant Storm/Hydraulic Loading Events

During February, there were five (5) storm events resulting in a daily precipitation amount equal to or greater than 0.4 inches measured during a 24 hour period. A total of 4.68 inches of rainfall were measured during the month. These events occurred on the following dates:

  • February 2 nd : 0.78 inches
  • February 15 th : 0.43 inches
  • February 16 th : 1.04 inches
  • February 23 rd : 0.54 inches
  • February 24 th : 1.42 inches

Plant operations were adjusted to manage the precipitation to prevent exceedances of the permitted discharge limitations for Outfall 001.

On February 4th, the SBR set points were adjusted as follows to manage the elevated hydraulic loadings as a result of rain and snow melt. At an influent flow at approximately 564.25 gpm, which is equivalent to 812,520 gpd, the following SBR adjustments were incorporated.

  • Sludge wasting still off to all 3 SBRs
  • Minimum aeration time 120 minutes per cycle
  • Maximum aeration time 180 minutes per cycle
  • Minimum react time was set at 60 minutes per cycle. The previous setting was 75 minutes per cycle, however, the setting was adjusted during the evening of February 3 rd as part of the response for maximum SBR decant alarms

On February 8th, the React settings were returned to the initial settings from 60 to 75 minutes per cycle.

On February 9th, the settle settings were returned to the initial settings from 45 to 60 minutes per cycle.

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382

Page 6 of 8

Big Fish Environmental Services Inc.

Minor Repairs and Preventative Maintenance

February 3, 2016: The alum line to the disc filters blew apart at injector site. All liquid was contained in alum containment area. Removed the LMI pump from service and isolated piping. Jim scheduled for troubleshooting the malfunction for February 4th.

February 4, 2016: The pump suction strainer on hard piping between alum tank and pumps had solidified. Cleaned and replaced. This task has been added to the preventative maintenance schedule.

February 14, 2016: Removed and cleaned the pump discharge chemical feed injector (located within effluent piping to the disc filters). This task has been added to the preventative maintenance schedule.

Replaced effluent sampler suction drive tubing.

February 16, 2016: Power failures reported prior to arriving on site. Both generators operated approximately for one hour.

Responded to Siemens Panel (Max decant) Alarm last evening after heavy rain came through.

SBR adjustments:
Decreased minimum React from to 90 to 60 minutes per cycle.
Decreased settle time from 60 to 30 minutes per cycle.

February 17, 2016: Mark Miller’s Township crew performed the following tasks:

  • Removed influent pump number 1 for overhaul and rebuild.
  • Removed utility water pump number 1 for overhaul and rebuild.
  • Replaced a leaking gasket for Utility pump number 2.
  • Lenni Electric electricians removed the UPS from disc filter number 1 control pan for replacement.
  • Electrician (Joe) installed new UPS units in both Disc Filter control panels.

February 18, 2016: Completed the disassembly of the sludge pump and piping to remove blockages as a result of “rag” build up. The shear plat on the sludge grinder is recommended for replacement.

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382

Page 7 of 8

Big Fish Environmental Services Inc.

February 23, 2016: Sludge tank number 1 level transducer failed. A replacement transducer is planned.

BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382

Page 8 of 8

Draft

EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
MEETING MINUTES
February 8, 2016

The East Goshen Township Municipal Authority held their regular public meeting on Monday, February 8, 2016 at 7:00 pm at the East Goshen Township building. Members in attendance were: Chairman Dana Pizarro, Kevin Cummings, Jack Yahraes, and Ed McAssey. Also in attendance were: Rick Smith (Township Manager), Mike Ellis (Pennoni), Carmen Battavio (Township Supervisor) and Patrick McKenna (Attorney).

COMMON ACRONYMS:

BFES – Big Fish Environmental Services MA- Municipal Authority
BOS – Board of Supervisors NPDES – National Pollutant Discharge Elimination System
CB – Conservancy Board PC – Planning Commission
DEP – Department of Environmental Protection PM – Prevention Maintenance
EPA – Environmental protection Agency PR – Park & Recreation Board
HC – Historical Commission RCSTP – Ridley Creek Sewer Treatment Plant
I&I – Inflow & Infiltration SBR – Sequencing Batch Reactor
LCSTP – Lockwood Chase Sewer Treatment Plant SSO – Sanitary System Overflow
WAS – Waste Activated Sludge

Call to Order & Pledge of Allegiance

Dana called the meeting to order at 7:00 pm and led those present in the Pledge of Allegiance.
There was a moment of silence to remember the troops and all veterans.
Dana asked if anyone would be recording the meeting. There was no response.

CHAIRMAN’S/MEMBERS REPORTS

1. Ed reported that he attended the West Goshen Sewer Authority meeting. He provided copies of reports on Capital Improvements from their Township Engineer and a consulting engineer.

Sewer Reports

1. Director of Public Works, Mark Miller’s written report:

Monthly Flows: The average daily flow to West Goshen was 821,000 gallons per day.
Meters: All meters were read on a daily basis.
C.C. Collection: The pumping stations were visited on a daily basis. We experienced a pump failure at the Hershey Mill Pump station. Pump #2 was pulled while we were there. We decided to pull pump #1 as well, as they were due to be pulled for routine maintenance and were taken to Deckmens. We also had a problem in the control panel at the pump station. The electronic rotating switch was not operating. We replaced the switch and put the station back in operation. The main seal on pump #2 failed which caused the pump to become inoperative. Both needed new cutters and top and bottom seals. Lenni Electric was in to perform routine maintenance at the pumping stations.
While performing routine cleaning of the sewer lines in White Chimneys, we found over a dozen manholes that were deteriorating due to the hydrogen sulfide from the Ashbridge pumping station. Mike Ellis and Matt inspected the manholes with Steve Biondi and me. Mike was going to check and see if Abel Recon was on the COSTARS Program. If that

F:\Data\Shared Data\Minutes\Municipal Authority\2016\MA 2-8-16 draft.doc

1

is the case, we will get a cost from them to do the work. Abel Recon is the company that did the manhole demonstration last year in Fairway Village. We repaired several lateral stand pipes this month.
R.C. Collection – Pump stations were visited on a daily basis. We have had an ongoing problem with excessive grease. We tried chemically treating it, however that has not worked. We started this week vacuuming the grease and will continue on a set schedule. I hope to have the prices from Sealy Associates to upgrade the pump and rail system at the Hunt Country Pump Station for your meeting. John Laidley is currently going over the control panel that was saved from the Reserve Pump station.
R.C. Plant: Scott requested 2 UPS boxes from the filter feed control panels. Lenni Electric is replacing the Wall Pack lighting with LED fixtures. We are also upgrading the fluorescent lighting with LED lighting. The heater in the screen was removed and repaired. The emergency generators were serviced this month. We had to replace the batteries on the Detroit Generator.

Action Items: Need your approval to have Mike Ellis prepare specifications to repair the manholes in White Chimneys.
Lochwood Plant Closure:
Alarms: We responded to 27 alarms for January.
PA One Calls: We received 57 PA One calls for January.

2. Pennoni Engineer’s Report

Mike Ellis provided the following report:
Invoices: Invoices with summaries are provided under separate cover.
Ridley Creek Sewage Treatment Plant (RCSTP):
No activity since the last report.
Reservoir Rd Pump Station:
PADEP issued the permits for the Ridley Creek GP-5 “Utility Line Stream Crossings” and GP-8 “Temporary Road Crossings (across streams)” and for the pump station site floodplain filling work.
We are awaiting PADEP response for the Chester Creek Small Projects Joint Permit for the pump station site and the Chester Creek Utility crossing.
Williams-Transco and Sunoco have approved the petroleum pipeline crossings. We are still awaiting a response from PPL-IEC.
We revised and resubmitted the PennDOT Highway Occupancy Permit application for force main construction along and across E. Strasburg Road and Rt. 352 including detour route plans for road closures, to address PennDOT’s initial comments. Penn DOT has requested a field meeting at the site before performing the remainder of their review, and we are in the process of scheduling it.
We met with the Chester County Conservation District (CCCD) on December 22, 2015 to discuss their initial comments on the NPDES Permit application. We are editing the plans and permit application documents to address the comments, and we expect to submit the revised documents to CCCD by February 12, 2016.
The Water Quality Management Park II Permit application will be submitted to PADEP after the plans are revised to address CCCD’s comments.
We prepared a sanitary sewer easement exhibit and legal descriptions for 1636 Bow Tree Drive.

F:\Data\Shared Data\Minutes\Municipal Authority\2016\MA 2-8-16 draft.doc

2

The tentative schedule follows:

Submitted PADEP GP and JP Permit application November 19, 2015
Submit revised NPDES Permit Application February 12, 2016
Submit PADEP WQM Part II Permit application February 15, 2016
PennDOT Permit issuance February-March 2016
PADEP & CCD Permit issuances April-May 2016

Semi-Annual I&I Reports
We met with the Township Manager and Public Works Director and reviewed Semi-Annual Sewer System Status Report #14 on January 21, 2016. The report was revised thereafter and re-issued on February 4, 2016..
RCSTP and Pump Stations’ O&M Plan
We met with the Township Manager and Public Works Director and reviewed an outline of proposed content for the O&M Plan on January 21, 2016. We have proceeded with preparation of the Plan.
White Chimneys Manhole Rehabilitation
We performed field observation of numerous manholes in the White Chimneys neighborhood that are downstream of the Ashbridge Pump station force main discharge that are deteriorated from hydrogen sulfide. We evaluated manhole lining construction and contracting approaches and prepared a construction cost estimate. Recommendations, including a map, were forwarded to the Township.
Chapter 94 Reports
We have begun to prepare the reports.

3. Big Fish Environmental Services

– Scott’s report showed that the Ridley Creek sewage treatment plant outfall 001 achieved compliance with the NPDES discharge permit during December 2015. Discharge to Applebrook discontinued during December. Chemical usage utilized for total phosphorus removal, pH and total alkalinity remained consistent with previous months. No mechanical or operational issues were observed during operation of sludge dewatering equipment.
During January there were 3 storm events resulting in a daily precipitation amount equal to or greater than 0.5 inches measured during a 24 hour period. These events occurred on January 9th resulting in 1.22 inches of rainfall and January 22nd and 23rd resulting in 12 inches of snowfall measured on both days for a total of 24 inches. Plant operations were adjusted to manage the precipitation to prevent exceedances of the permitted discharge limitation for Outfall 001.
Minor repairs and preventative maintenance were:
January 23rd: Disc filter #2 Allen Bradley display blank. The back wash valve and pump control lights on and function in hand mode. The filter controls were found not functioning in automatic mode. Filter is accepting and filtering flow. Checked inside control panel, looks like there is power to only half of the panel. Checked fuses and breakers all looked normal.
January 26th: Both filters were rewired to bypass the failed uninterrupted power supplies (UPS’s). These power supply breakers were determined to be located in the SBR control room and are labeled backwards. Both filters were drained and cleaned filter #2 before returning to service since it hadn’t been operating correctly.

F:\Data\Shared Data\Minutes\Municipal Authority\2016\MA 2-8-16 draft.doc

3

The sampler at the influent building was returned to service. The extension cord going to the sampler is under a large pile of snow and found to be damaged.
January 28th: A UV ballast failed which resulted in an alarm. Both UV light banks were temporarily operated on-line in “Hand” mode until the ballast can safely be replaced, some UV lamps.
January 31st: Cleaned auger sprayer nozzles.
Replaced UV Ballast and lamps.

Approval of Minutes

Jack moved to accept the minutes of January 11, 2016 as amended. Kevin seconded the motion. The motion passed unanimously.

Approval of Invoices

1. Kevin moved to approve payment of the following Pennoni invoices:

  1. Pennoni #673182 $ 1,039.75
  2. Pennoni #673187 $ 2,778.75
  3. Pennoni #673183 $ 2,565.50
  4. Pennoni #673184 $ 725.75
  5. Pennoni #673185 $ 488.75
  6. Pennoni #673186 $ 872.25

Ed seconded the motion. The motion passed unanimously.
2. Jack moved to approve payment of Gawthrop Greenwood invoice #139997 for $400.00. Ed seconded the motion. The motion passed unanimously.

Liaison Reports

Board of Supervisors – Carmen reported that the Board will be reviewing the Park Master Plan and encouraged everyone to look at it.

Financial Reports

Jon Altshul provided the following written report:
In January, the Municipal Authority recorded $5,115 in revenues (primarily from tap-in fees for Colonial Lane) and $2,042 in expenses, for a positive variance of $3,073. As of January 31st, the fund balance was $1,464,350, of which $1,415,986 is in the main construction account.

New Business

1. Mike did a Power Pint presentation of the Sewer System Metering and I&I Overview. He showed the areas currently covered by portable meters and mentioned they are proposing a portable meter to pick up Hersheys Mill Estates. The manholes are old and they plan to replace lids and frames. They also plan to do smoke testing along Ridley Creek.
Carmen mentioned that a few years ago there was a problem with grease at the Applebrook Golf Club which clogged the systems of the townhouses. Rick said they replaced the trap system at the club.
Mike showed where permanent meters are already installed and where they propose to put new ones. I&I overflows in Chester Creek – they metered flows from QVC & UPS area and found nothing.

F:\Data\Shared Data\Minutes\Municipal Authority\2016\MA 2-8-16 draft.doc

4

White Chimneys – They checked the manholes in White Chimneys and found that some need replacement. They propose using a spray lining which dries very quickly and would cost $400/vertical foot which is still less than replacing the entire manhole.
MH C-226 has an unusual configuration and is corroded so that it needs a new manhole. They are reviewing several options for placement of this manhole. Dana thanked Mike for the presentation.
2. Auditor’s letter - Jack moved to ask Maillie to keep their fee at the same rate as last year. Ed seconded the motion. The motion passed. Rick will get the cost for last year.
3. Proposed West Goshen Township Sewer Improvements – The schedule for equipment replacement for the next 5 years was reviewed. Rick explained that East Goshen’s fee is for operation/maintenance based on flow. Ed pointed out that some of the current equipment they are using is very old. He clarified that the items in the “2016” column are not for correction of the phosphorus problem. Rick will get the necessary information and get it to Patrick.
Public Comment: Margie Swart, 1519 Links Drive, commented that she is a West Goshen resident. She asked what is included in the sewer fee that East Goshen residents pay. Rick answered cost for Ridley Creek Sewer Plant and West Goshen cost.

Any Other Matter

1. Jack referred to the Pennoni Semi-Annual Sewer System Status Report #14, on page 9, #6 – re-occupancy inspections add “from building down spouts and sump pumps.”

Adjournment

There being no further business, Jack moved to adjourn the meeting. Kevin seconded the motion. The motion passed unanimously. The meeting was adjourned at 8:30 pm. The next meeting will be held on Monday, March 14, 2016 at 7:00 pm.

Respectfully submitted,

Ruth Kiefer
Recording Secretary

F:\Data\Shared Data\Minutes\Municipal Authority\2016\MA 2-8-16 draft.doc

5

Pennoni

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 678096
Invoice Date : 02/23/2016
Project : EGMA1504
Project Name : Reservoir Rd PS Design & Permitting

For Services Rendered through: 2/14/2016

Phase 12 - Resubmission of PennDOT HOP application and coordination with PennDOT to address Business Partner ID and other non-technical comments; set-up pre-review field meeting with PennDOT.

Phase : 12 -- Permitting

Total Phase : 12 -- Permitting Labor : 311.25
Expense : 0.00
Phase Total : 311.25
Fee : 136,316.25 Amount Due This Invoice $311.25
Prior Billings : 132,457.25
Current Billings : 311.25
Total Billings : 132,768.50

Phase : 12 -- Permitting

Labor

Class Hours/
Units
Rate Amount
Authority Engineer 0.75 115.00 86.25
Staff Engineer 2.50 90.00 225.00
Labor Total: 3.25 311.25
Total Phase : 12 -- Permitting Labor : $311.25
Expense : $0.00
Total Project : EGMA1504 – Reservoir Rd PS Design & Permitting Labor : $311.25
Expense : $0.00

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date 2/23/2016

Project: EGMA1504
Pennoni Job No.: Reservoir Rd PS Design & Permitting
Invoice No: 678096
Invoice Period: 1/18/2016 to 2/14/2016
Initial Authorization: $ 167,120.00 Date: 2/23/2016
Contract Amount: $ 167,120.00
Previously Invoiced: $ 154,405.00
Current Invoice: $ 1,934.75
Invoiced to Date ($): $ 156,339.75
Invoiced to Date (%): 94%
Remaining Budget ($): $ 10,780.25
Remaining Budget (%): 6%

Budget by Phase:

Phase Name: Permitting Phase 12
Phase Budget: $ 28,610.50
Previously Invoiced: $ 24,666.25
Current Invoice: $ 311.25
Invoiced to Date ($): $ 24,977.50
Invoiced to Date (%): 87%
Remaining Budget ($): $ 3,633.00
Remaining Budget (%): 13%

Comments: Phase 12 - Resubmission of PennDOT HOP application and coordination with PennDOT to address Business Partner ID and other non-technical comments; set-up pre-review field meeting with PennDOT.

Pennoni

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 678097
Invoice Date : 02/23/2016
Project : EGMA1504
Project Name : Reservoir Rd PS Design & Permitting

For Services Rendered through: 2/14/2016

Phase 05 - Initial preparation of permanent and temporary easement exhibit and legal description for 1636 Bow Tree Drive.

Phase : 05 -- 1636 Bow Tree Dr Bndry Survey & Eas

Contract Amount $4,020.00
Percent Complete 40.39%
Contract Amount Completed $1,623.50
Less Previous Billed $0.00
Phase Subtotal $1,623.50
Amount Due This Invoice $1,623.50

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date 2/23/2016

Project: EGMA1504
Pennoni Job No.: Reservoir Rd PS Design & Permitting
Invoice No: 678097
Invoice Period: 1/18/2016 to 2/14/2016
Initial Authorization: $ 167,120.00 Date: 2/23/2016
Contract Amount: $ 167,120.00
Previously Invoiced: $ 154,405.00
Current Invoice: $ 1,934.75
Invoiced to Date ($): $ 156,339.75
Invoiced to Date (%): 94%
Remaining Budget ($): $ 10,780.25
Remaining Budget (%): 6%

Budget by Phase:

Phase Name: 1636 Bow Tree Dr Boundary & Esmnts Phase 05
Phase Budget: $ 4,020.00
Previously Invoiced: $ -
Current Invoice: $ 1,623.50
Invoiced to Date ($): $ 1,623.50
Invoiced to Date (%): 40%
Remaining Budget ($): $ 2,396.50
Remaining Budget (%): 60%

Comments: Phase 05 - Initial preparation of permanent and temporary easement exhibit and legal description for 1636 Bow Tree Drive.

Reservoir Road Pump Station Design & Permitting

INVOICE SUMMARY

For Services Rendered through: 2/14/2016

Task No. Activity Contract Amount* Invoiced Effort thru 2/14/2016 Remaining Budget ($) Remaining Budget (%) Completed?
1 Concept Design $13,655.75 $13,655.75 - - Yes
2 DEP WQM Pre-App. Meeting $1,300.00 $1,300.00 - - Yes
3 Existing Conditions Survey $22,783.75 $22,783.75 - - Yes
4 Sewer Stakeout in Easements $0.00 $0.00 - - Scope eliminated
5 1636 Bow Tree Dr. Boundary Survey & Easement $4,020.00 $1,623.50 $2,396.50 60% No
6 Additional Boundary Surveys & Easements $0.00 $0.00 - - Scope eliminated
7 Geotechnical Borings $4,000.00 $4,000.00 - - Yes
8 Install Permanent Survey Benchmarks $0.00 $0.00 - - Scope eliminated
9 Progress Design $29,450.00 $29,450.00 - - Yes
10 Infiltration Testing $1,800.00 $1,800.00 - - Yes
11 Final Design $61,500.00 $56,748.50 $4,751.50 8% No
12 Permitting $28,610.50 $24,977.50 $3,633.00 13% No
TOTAL $167,120.00 $156,339.00 $10,781.00 6%

*After 12/14/2015 approved re-allocation of task budgets.

Pennoni

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 678098
Invoice Date : 02/23/2016
Project : EGMA1505
Project Name : RCSTP and Pump Station O&M Manual

For Services Rendered through: 2/14/2016

Submitted O&M Manual outline to Township, attended review meeting with Township Manager and PW Director, and continued preparation of O&M Manual including but not limited to procedures, safety section, references, permit docs, and coordination with Township to obtain additional equipment and other information.

Phase : **** -- Professional Services

Total Phase : **** -- Professional Services Labor : 1,868.25
Expense : 0.00
Phase Total : 1,868.25
Fee : 12,500.00 Amount Due This Invoice $1,868.25
Prior Billings : 725.75
Current Billings : 1,868.25
Total Billings : 2,594.00

Phase : **** -- Professional Services

Labor

Class Hours/
Units
Rate Amount
Authority Engineer 2.75 115.00 316.25
Project Engineer 16.00 97.00 1,552.00
Labor Total: 18.75 1,868.25
Total Phase : **** -- Professional Services Labor : $1,868.25
Expense : $0.00
Total Project : EGMA1505 – RCSTP and Pump Station O&M Manual Labor : $1,868.25
Expense : $0.00

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority
EGMA1505 Invoice Summary
Invoice Date 02/23/2016

Project: EGMA1505
Pennoni Job No.: RCSTP & Pump Station O&M Manual
Invoice No: 678098
Invoice Period: 1/18/2016 to 2/14/2016
Initial Authorization: $ 12,500.00 Date: 2/23/2016
Contract Amount: $ 12,500.00
Previously Invoiced: $ 725.75
Current Invoice: $ 1,868.25
Invoiced to Date ($): $ 2,594.00
Invoiced to Date (%): 21%
Remaining Budget ($): $ 9,906.00
Remaining Budget (%): 79%

Budget by Phase:

Phase Name: RCSTP & Pump Station O&M Manual
Phase Budget: $ 12,500.00
Previously Invoiced: $ 725.75
Current Invoice: $ 1,868.25
Invoiced to Date ($): $ 2,594.00
Invoiced to Date (%): 21%
Remaining Budget ($): $ 9,906.00
Remaining Budget (%): 79%

Comments: Submitted O&M Manual outline to Township, attended review meeting with Township Manager and PW Director, and continued preparation of O&M Manual including but not limited to procedures, safety section, references, permit docs, and coordination with Township to obtain additional equipment and other information.

Pennoni

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 678099
Invoice Date : 02/23/2016
Project : EGMA1601
Project Name : 2016 General Services

For Services Rendered through: 2/14/2016

Prepared February's Engineer's Report and prepared for and attended February MA meeting. Alternatives analysis for manhole rehab vs. replacement of Ashbridge PS Force Main Terminal Manhole C226 including preparation of draft alternative letter and powerpoint presentation slides of terminal manhole replacement recommendations for February MA meeting.

Phase : **** -- Professional Services

Total Phase : **** -- Professional Services Labor : 1,155.25
Expense : 0.00
Phase Total : 1,155.25

Amount Due This Invoice: $1,155.25

Fee : 12,300.00
Prior Billings : 488.75
Current Billings : 1,155.25
Total Billings : 1,644.00

Phase : **** -- Professional Services

Labor

Class Hours/Units Rate Amount
Authority Engineer 6.25 115.00 718.75
Project Engineer 4.50 97.00 436.50
Labor Total: 10.75 1,155.25
Total Phase : **** -- Professional Services Labor : $1,155.25
Expense : $0.00
Total Project : EGMA1601 -- 2016 General Services Labor : $1,155.25
Expense : $0.00

[Handwritten: ok RS 3-3-16]

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority

EGMA1601 Invoice Summary

Invoice Date 02/23/2016

Project: EGMA1601
Pennoni Job No.: 2016 General Services
Invoice No: 678099
Invoice Period: 1/18/2016 to 2/14/2016
Initial Authorization: $ 12,300.00 Date: 2/23/2016
Contract Amount: $ 12,300.00
Previously Invoiced: $ 488.75
Current Invoice: $ 1,155.75
Invoiced to Date ($): $ 1,644.50
Invoiced to Date (%): 13%
Remaining Budget ($): $ 10,655.50
Remaining Budget (%): 87%

Budget by Phase:

Phase Name: 2016 General Services
Phase Budget: $ 12,300.00
Previously Invoiced: $ 488.75
Current Invoice: $ 1,155.75
Invoiced to Date ($): $ 1,644.50
Invoiced to Date (%): 13%
Remaining Budget ($): $ 10,655.50
Remaining Budget (%): 87%

Comments: Prepared February's Engineer's Report and prepared for and attended February MA meeting. Alternatives analysis for manhole rehab vs. replacement of Ashbridge PS Force Main Terminal Manhole C226 including preparation of draft alternatives letter and powerpoint presentation slides of terminal manhole replacement recommendations for February MA meeting.

Pennoni

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 678100
Invoice Date : 02/23/2016
Project : EGMA1602
Project Name : 2016 Semi-Annual I&I Reports

For Services Rendered through: 2/14/2016

Attended semi-annual I&I report review meeting with Township Manager and PW Dept; revised report and issued Updated Semi-Annual Sewer System Status Report #14; and prepared mapping and Powerpoint presentation on metering, I&I, and sewer system investigations for February MA meeting.

Phase : **** -- Professional Services

Total Phase : **** -- Professional Services Labor : 2,209.50
Expense : 0.00
Phase Total : 2,209.50

Amount Due This Invoice: $2,209.50

Fee : 11,200.00
Prior Billings : 0.00
Current Billings : 2,209.50
Total Billings : 2,209.50

Phase : **** -- Professional Services

Labor

Class Hours/Units Rate Amount
Authority Engineer 8.50 115.00 977.50
Engineering Technician II 16.00 77.00 1,232.00
Labor Total: 24.50 2,209.50
Total Phase : **** -- Professional Services Labor : $2,209.50
Expense : $0.00
Total Project : EGMA1602 -- 2016 Semi-Annual I&I Reports Labor : $2,209.50
Expense : $0.00

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority

EGMA1603 Invoice Summary

Invoice Date2/23/2016

Project: EGMA1602
Pennoni Job No.: 2016 Semi-Annual I&I Reports
Invoice No: 678100
Invoice Period: NTP to 2/14/2016
Initial Authorization: $ 11,200.00 Date: 2/23/2016
Contract Amount: $ 11,200.00
Previously Invoiced: $ -
Current Invoice: $ 2,029.50
Invoiced to Date ($): $ 2,029.50
Invoiced to Date (%): 18%
Remaining Budget ($): $ 9,170.50
Remaining Budget (%): 82%

Budget by Phase:

Phase Name: 2016 Semi-Annual I&I Reports
Phase Budget: $ 11,200.00
Previously Invoiced: $ -
Current Invoice: $ 2,029.50
Invoiced to Date ($): $ 2,029.50
Invoiced to Date (%): 18%
Remaining Budget ($): $ 9,170.50
Remaining Budget (%): 82%

Comments: Attended semi-annual I&I report review meeting with Township Manager and PW Dept; revised report and issued Updated Semi-Annual Sewer System Status Report #14; and prepared mapping and Powerpoint presentation on metering, I&I, and sewer system investigations for February MA meeting.

Pennoni

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 678101
Invoice Date : 02/23/2016
Project : EGMA1603
Project Name : 2015 Chapter 94 Reports

For Services Rendered through: 2/14/2016

Continued preparation of Chapter 94 Reports.

Phase : **** -- Professional Services

Total Phase : **** -- Professional Services Labor : 3,248.75
Expense : 0.00
Phase Total : 3,248.75

Amount Due This Invoice: $3,248.75

Fee : 15,000.00
Prior Billings : 872.25
Current Billings : 3,248.75
Total Billings : 4,121.00

Phase : **** -- Professional Services

Labor

Class Hours/Units Rate Amount
Authority Engineer 1.25 115.00 143.75
Township Engineer 0.25 115.00 28.75
Project Engineer 14.25 97.00 1,382.25
Graduate Engineer 22.00 77.00 1,694.00
Labor Total: 37.75 3,248.75
Total Phase : **** -- Professional Services Labor : $3,248.75
Expense : $0.00
Total Project : EGMA1603 -- 2015 Chapter 94 Reports Labor : $3,248.75
Expense : $0.00

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority

EGMA1603 Invoice Summary

Invoice Date 02/23/2016

Project: EGMA1603
Pennoni Job No.: 2015 Chapter 94 Reports
Invoice No: 678101
Invoice Period: 1/18/2016 to 2/14/2016
Initial Authorization: $ 15,000.00 Date: 2/23/2016
Contract Amount: $ 15,000.00
Previously Invoiced: $ 872.75
Current Invoice: $ 3,248.75
Invoiced to Date ($): $ 4,121.50
Invoiced to Date (%): 27%
Remaining Budget ($): $ 10,878.50
Remaining Budget (%): 73%

Budget by Phase:

Phase Name: 2015 Chapter 94 Reports
Phase Budget: $ 15,000.00
Previously Invoiced: $ 872.75
Current Invoice: $ 3,248.75
Invoiced to Date ($): $ 4,121.50
Invoiced to Date (%): 27%
Remaining Budget ($): $ 10,878.50
Remaining Budget (%): 73%

Comments: Continued preparation of Chapter 94 Reports.

Pennoni

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 678618
Invoice Date : 02/23/2016
Project : EGMA1604
Project Name : White Chimneys MH Lining Bid Doc

For Services Rendered through: 2/14/2016

Field visits to White Chimneys manholes by Authority Engineer and Sr. Engineering Technician. Evaluated/researched interior manhole lining construction contracting alternatives including Costars, prepared construction cost estimate, prepared exhibit of manholes to be lined, and assembled info for Township and MA. Prepared powerpoint presentation slides of proposed manhole lining project for February MA meeting

Phase : **** -- Professional Services

Total Phase : **** -- Professional Services Labor : 1,392.75
Expense : 0.00
Phase Total : 1,392.75

Amount Due This Invoice: $1,392.75

Fee : 4,400.00
Prior Billings : 0.00
Current Billings : 1,392.75
Total Billings : 1,392.75

Phase : **** -- Professional Services

Labor

Class Hours/Units Rate Amount
Authority Engineer 7.25 115.00 833.75
Senior Engineering Technician 2.50 85.00 212.50
Engineering Technician II 4.50 77.00 346.50
Labor Total: 14.25 1,392.75
Total Phase : **** -- Professional Services Labor : $1,392.75
Expense : $0.00
Total Project : EGMA1604 -- White Chimneys MH Lining Bid Doc Labor : $1,392.75
Expense : $0.00

[Handwritten: ok RS - 3-3-16]

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority

EGMA1601 Invoice Summary

Invoice Date 02/23/2016

Project: EGMA1604
Pennoni Job No.: White Chimneys MH Lining Bid Doc
Invoice No: 678618
Invoice Period: NTP to 2/14/2016
Initial Authorization: $ 4,400.00 Date: 2/23/2016
Contract Amount: $ 4,400.00
Previously Invoiced: $ -
Current Invoice: $ 1,392.75
Invoiced to Date ($): $ 1,392.75
Invoiced to Date (%): 32%
Remaining Budget ($): $ 3,007.25
Remaining Budget (%): 68%

Budget by Phase:

Phase Name: White Chimneys MH Lining Bid Doc
Phase Budget: $ 4,400.00
Previously Invoiced: $ -
Current Invoice: $ 1,392.75
Invoiced to Date ($): $ 1,392.75
Invoiced to Date (%): 32%
Remaining Budget ($): $ 3,007.25
Remaining Budget (%): 68%

Comments: Field visits to White Chimneys manholes by Authority Engineer and Sr. Engineering Technician. Evaluated/researched interior manhole lining construction contracting alternatives including Costars, prepared construction cost estimate, prepared exhibit of manholes to be lined, and assembled info for Township and MA. Prepared powerpoint presentation slides of proposed manhole lining project for February MA meeting

Gawthrop Greenwood, PC
Attorneys at Law
17 East Gay Street, Suite 100
West Chester, PA 19381-0562
gglaw@gawthrop.com
(p) 610-696-8225
(f) 610-344-0922
www.gawthrop.com

Page: 1
02/09/2016
Client No: 6604-001R
Invoice No. 141172

East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380

General Authority Services

Fees

Date / Timekeeper Description Hours Amount
01/11/2016
JKW
Review agenda in preparation for meeting; Attend meeting. 2.00
01/29/2016
PMM
Emails from/to R Smith regarding preparing easement for Pusey. 0.40
For Current Services Rendered 2.40 480.00

Recapitulation

Timekeeper Hours Hourly Rate Total
Jessica K. Wiesak 2.00 $200.00 $400.00
Patrick M. McKenna 0.40 200.00 80.00

Total Current Charges: 480.00

Balance Due: $480.00

[Handwritten: 2-18-16 OK TO PAY RS]
[Handwritten in red: THIS WAS PAID IN FEBRUARY]

To ensure proper credit, please write client number on your check when returning payment. Thank You.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.

Memo

To: Municipal Authority
From: Jon Altshul
Re: MA February Financial Reports
Date: March 4, 2016

In February, the Municipal Authority recorded $8,521 in revenues (primarily from a tap-in fee for 957 Cornwallis Drive) and $26,762 in expenses (including $19,313 for Reservoir Road Pump Station engineering) and $6,969 for non-capital engineering, for a negative variance of $18,241. As of February 29th, the fund balance was $1,446,108, of which $1,396,773 is in the main construction account.

A complete list of all year-to-date expenses and revenues is provided.

EAST GOSHEN TOWNSHIP

1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
February 2016

Account Title Acct # Annual Budget Month To Date Actual Year To Date Actual
MUNICIPAL AUTHORITY BEGINNING FUND BALANCE 1,464,349.58
RCSTP BUDGET
REVENUE
INTEREST EARNED - RCSTP EXPANSION 07341 1020 1,500.00 103.56 214.15
GRANT REVENUE 07392 0800 0.00 0.00 0.00
TOTAL REVENUE 1,500.00 103.56 214.15
EXPENSES
R.C.-CAP. PROJ.-ENGINEER 07424 7451 0.00 0.00 0.00
R.C. CAP EXPANSION GEN'L CONTRACTOR 07424 7452 0.00 0.00 0.00
R.C. CAP EXPANSION - ELECTRICAL 07424 7453 0.00 0.00 0.00
R.C. CAP EXP CONTINGENCY CAPITAL 07424 7454 0.00 0.00 0.00
R.C. CAP EXP CONTINGENCY ONGOING 07424 7455 0.00 0.00 0.00
R.C. CAP EXP ADDITIONAL CONTINGENCY 07424 7456 0.00 0.00 0.00
TRANSFER TO SEWER SINKING FUND 07492 0550 0.00 0.00 0.00
TRANSFER TO AUTHORITY CAP FUND 07492 0990 0.00 0.00 0.00
TOTAL EXPENSES 0.00 0.00 0.00
RCSTP NET RESULT 1,500.00 103.56 214.15
OPERATING BUDGET

U:\bmccool\2016\Municipal Authority\2016 - 02 - Municipal Authority Report.xlsx
Page 1 of 3
03/03/2016

EAST GOSHEN TOWNSHIP

1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
February 2016

Account Title Acct # Annual Budget Month To Date Actual Year To Date Actual
REVENUE
INTEREST EARNINGS 07341 1000 10.00 0.51 0.94
C.C. TAPPING FEES 07364 1100 4,000.00 0.00 0.00
R.C.TAPPING FEES 07364 1110 4,000.00 7,148.00 12,152.00
CONNECTION FEES - SEWER 07364 1130 0.00 845.64 845.64
MISCELLANEOUS REVENUE 07380 1000 0.00 423.36 423.36
TRANSFER FROM SEWER OPERATING 07392 0500 93,832.00 0.00 0.00
TOTAL REVENUE 101,842.00 8,417.51 13,421.94
EXPENSES
ADMINISTRATIVE WAGES 07424 1400 0.00 0.00 0.00
MISCELLANEOUS EXPENSE 07424 3000 3,000.00 0.00 1,641.62
MUNIC.AUTH.-AUDITING 07424 3110 9,500.00 0.00 0.00
ENGINEERING SERVICES 07424 3130 38,500.00 6,969.00 6,969.00
LEGAL SERVICES 07424 3140 9,000.00 480.00 880.00
M.C.-DVRFA-DEBT SERVICE 07471 1000 24,920.00 0.00 0.00
M.C.-DVRFA-INTEREST PAYMN 07472 1000 3,172.00 0.00 0.00
M.C.-DVRFA-INTEREST PAYMN 07472 1010 0.00 0.00 0.00
TOTAL EXPENSES 88,092.00 7,449.00 9,490.62
OPERATING NET RESULT 13,750.00 968.51 3,931.32

U:\bmccool\2016\Municipal Authority\2016 - 02 - Municipal Authority Report.xlsx
Page 2 of 3
03/03/2016

EAST GOSHEN TOWNSHIP

1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
February 2016

19,313.25
Account Title Acct # Annual Budget Month To Date Actual Year To Date Actual
CAPITAL BUDGET
REVENUE
LOAN PROCEEDS-SEWER PROJECT 07393 1001 0.00 0.00 0.00
TRANSFER FROM SEWER CAP RESERVE 07392 0900 0.00 0.00 0.00
TOTAL REVENUE 0.00 0.00 0.00
EXPENSES
MARYDELL PUMP STATION - ENGINEER 07425 1000 0.00 0.00 0.00
MARYDELL PUMP STATION -CONSTRUCTION 07425 2000 0.00 0.00 0.00
MANHOLE COVER REPLACEMENTS 07424.7405 0.00 0.00 0.00
C.C. CAPITAL - COLLECTION 07424.7420 0.00 0.00 0.00
LOCHWOOD ABANDONMENT ENGINEER 07424 7475 0.00 0.00 0.00
LOCHWOOD ABANDONMENT CONSTRUCTION 07424 7476 0.00 0.00 0.00
LOCHWOOD ELIMINATION PHASE 2 07424 7477 0.00 0.00 0.00
HERSHEY MILL STATION - ENGINEER 07426 1000 0.00 0.00 0.00
HERSHEY MILL STATION - CONSTRUCTION 07426 2000 0.00 0.00 0.00
RESERVE PUMP STATION - ENGINEER 07427 1000 0.00 0.00 0.00
RESERVE PUMP STATION - CONSTRUCTION 07427 2000 0.00 0.00 0.00
RESERVOIR PUMP STATION - ENGINEER 07428 1000 0.00 19,313.25
RESERVOIR PUMP STATION CONSTRUCTION 07428 2000 0.00 0.00 0.00
ASBSTOS CONCRETE ENGINEERING 07429 3130 25,000.00 0.00 0.00
DIVERSION PROJ.- LEGAL 07429 3166 0.00 0.00 0.00
TOTAL EXPENSES 25,000.00 19,313.25 19,313.25
CAPITAL NET RESULT (25,000.00) (19,313.25) (19,313.25)
MUNICIPAL AUTHORITY ENDING FUND BALANCE 1,446,108.40

U:\bmccool\2016\Municipal Authority\2016 - 02 - Municipal Authority Report.xlsx
Page 3 of 3
03/03/2016

East Goshen Township General Ledger

Report Date 03/03/16
GL Transaction Details
PAGE 1
MGRP18 run by BRIAN 10 : 01 AM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
07341-1000 INTEREST EARNINGS 0.00
1601 JE 51240 0.43 02/01/16 INTEREST INTEREST EARNED JANUARY 2016 07 FUND
1601 0.00 0.43 -0.43
1602 51651 0.51 03/01/16 INTEREST INTEREST EARNED FEBRUARY 2016 07 FUND
1602 0.00 0.51 -0.94
07341-1000 **** *** ***** 0.00 0.94 -0.94
07341-1020 INTEREST EARNED - RCSTP EXPANSION 0.00
1601 51240 110.59 02/01/16 INTEREST INTEREST EARNED JANUARY 2016 07 FUND
1601 0.00 110.59 -110.59
1602 51651 103.56 03/01/16 INTEREST INTEREST EARNED FEBRUARY 2016 07 FUND
1602 0.00 103.56 -214.15
07341-1020 **** *** ***** 0.00 214.15 -214.15
07364-1110 R.C.TAPPING FEES 0.00
1601 CR 51204 5,004.00 01/28/16 1247 7875 1 SUNNY RIDGE FARMS LLC
1601 0.00 5,004.00 -5,004.00
1602 RE 51557 7,148.00 02/23/16 51557 1 TAP IN FEE-957 CORNWALLIS DR
1602 0.00 7,148.00 -12,152.00
07364-1110 **** *** ***** 0.00 12,152.00 -12,152.00
07364-1130 CONNECTION FEES - SEWER 0.00

East Goshen Township General Ledger

Report Date 03/03/16
GL Transaction Details
PAGE 2
MGRP18 run by BRIAN 10 : 01 AM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
1602 CR 51318 423.00 02/05/16 804 9354 1 GEORGE SMITH & CHRISTINA CONLE
51322 423.00 02/05/16 344 9356 1 JACOBS, ROBERT & CHERYL
51357 423.00 02/08/16 2435 9355 1 STOFFLET, MICHAEL
JE 51319 141.12 02/05/16 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
51323 141.12 02/05/16 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
51358 141.12 02/08/16 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
1602 423.36 1,269.00 -845.64
07364-1130 **** *** ***** 423.36 1,269.00 -845.64
07380-1000 MISCELLANEOUS REVENUE 0.00
51319 141.12 02/05/16 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
51323 141.12 02/05/16 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
51358 141.12 02/08/16 PINE ROCK ANNUAL PINE ROCK INSTALLMENT
1602 0.00 423.36 -423.36
07380-1000 **** *** ***** 0.00 423.36 -423.36
07424-3000 MISCELLANEOUS EXPENSE 0.00
1601 CD 50894 978.00 01/04/16 3004 2132 PENNSYLVANIA MUNICIPAL AUTHORITIES ASSOC
2016 ACTIVE MEMBERSHIP DUES
51002 163.62 01/18/16 3005 2967 SAFEGUARD
CHECK ORDER FEE
51028 500.00 01/14/16 3006 2737 COMMONWEALTH OF PA
NPDES PERMITS -CHAP.92A 2016 PERMIT# PA0050504
1601 1,641.62 0.00 1,641.62
07424-3000 **** *** ***** 1,641.62 0.00 1,641.62
07424-3130 ENGINEERING SERVICES 0.00
1602 51394 5,905.25 02/10/16 3008 1052 PENNONI ASSOCIATES INC.
SERVICES THRU 1/17/16 RCSTP & PU STATION O&M MANUAL
51527 1,063.75 02/23/16 3010 1052 PENNONI ASSOCIATES INC.
SERV.THRU 12/13/16 2015 GEN.SER
1602 6,969.00 0.00 6,969.00

East Goshen Township General Ledger

Report Date 03/03/16
GL Transaction Details
PAGE 3
MGRP18 run by BRIAN 10 : 01 AM

Acct # Per Src Trx # Debits Credits Beg/End Bal Date Check/Ref # ID # Name/Description
07424-3130 **** *** ***** 6,969.00 0.00 6,969.00
07424-3140 LEGAL SERVICES 0.00
1601 51149 400.00 12/17/15 3007 528 GAWTHROP GREENWOOD & HALSTED
LEGAL SERVICES 12/14/15 - GEN.AU
1601 400.00 0.00 400.00
1602 51503 480.00 02/19/16 3009 528 GAWTHROP GREENWOOD & HALSTED
LEGAL SERVICE 1/11-1/29/16 GEN.A
1602 480.00 0.00 880.00
07424-3140 **** *** ***** 880.00 0.00 880.00
07428-1000 RESERVOIR PUMP STATION - ENGINEER 0.00
51395 2,565.50 02/10/16 103 1052 PENNONI ASSOCIATES INC.
SERVICE THRU 1/17/16 RESERV.RD.P
51528 16,747.75 02/23/16 104 1052 PENNONI ASSOCIATES INC.
SERVICE THRU 12/13/15 RESERV.RD
1602 19,313.25 0.00 19,313.25
07428-1000 **** *** ***** 19,313.25 0.00 19,313.25
Grand Total 29,227.23 14,059.45 15,167.78

EAST GOSHEN MUNICIPAL AUTHORITY

CONCISE STATEMENTS

Concise Statement of Net Position
December 31, 2015

ASSETS
Current assets $ 1,461,277
Net investment in lease 9,260,809
TOTAL ASSETS $ 10,722,086
LIABILITIES AND NET POSITION
LIABILITIES
Notes payable, principal due annually through 2032, variable interest rate $ 10,177,000
Accounts payable 164
Accrued interest payable 6,378
TOTAL LIABILITIES 10,183,542
NET POSITION
Unrestricted 538,544
TOTAL LIABILITIES AND NET POSITION $ 10,722,086

Concise Statement of Revenues, Expenses and Changes in Net Position
Year Ended December 31, 2015

OPERATING REVENUES $ 878,890
OPERATING EXPENSES 106,605
OPERATING INCOME 772,285
NONOPERATING REVENUES (EXPENSES)
Grant 37,162
Investment income 1,505
Tapping fees 45,588
Transfers (to) from East Goshen Township, net (445,000)
TOTAL NONOPERATING REVENUES (EXPENSES) (360,745)
CHANGE IN NET POSITION 411,540
NET POSITION AT BEGINNING OF YEAR 127,004
NET POSITION AT END OF YEAR $ 538,544

A complete copy of the audited financial statements prepared by independent certified public accountants is available for public inspection in the Authority's office, Monday through Friday, between the hours of 8:00 a.m. and 4:00 p.m. The Authority's office is located at 1580 Paoli Pike, West Chester, Pennsylvania.

A complete copy of the audited financial statements prepared by independent certified public accountants is available for public inspection in the Authority's office, Monday through Friday, between the hours of 8:00 a.m. and 4:00 p.m. The Authority's office is located at 1580 Paoli Pike, West Chester, Pennsylvania.

EDWARD B. WALSH & ASSOCIATES, INC.
Complete Civil Engineering Design / Consultation Services
Lionville Professional Center
125 Dowlin Forge Road
Exton, PA 19341

February 19, 2016

Rick Smith, Township Manager
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380-6199

RE: 943 Cornwallis Drive
Sewage Facilities Planning Module Exemption

RECEIVED
FEB 24 2016
BY ____________

Dear Mr. Smith:

Enclosed please find five (5) copies of the Sewage Facilities Planning Module exemption request for the above referenced project. Please have the appropriate individual(s) review and sign section 8.d. If you could please return one of the original packages to our office once it has been approved and signed it would be appreciated.

If you have any questions of need additional information please let me know.

Sincerely,
EDWARD B. WALSH & ASSOC., INC.

[Signature: Scott J. Andress]
Scott J. Andress
Enclosure(s)

REGISTERED PROFESSIONAL ENGINEERS & LAND SURVEYORS
Pennsylvania, New Jersey, Delaware & Maryland
610-903-0060 FAX 610-903-0080
www.ebwalshinc.com
Established 1985

3800-CD-BPNPSM0359 2/2015

1. Development Information

Name of Development: 943 Cornwallis Drive
Developer Name: T. Richard Moser Land Developers, LP
Address: 1171 Lancaster Avenue, Suite 201
Berwyn, PA 19312
Telephone #: 610-725-0812
Email: NA

2. Location of Development

a. County: Chester
b. Municipality: East Goshen
c. Address or Coordinates: 943 Cornwallis Drive, West Chester, PA 19380
d. Tax Parcel #: 53-4-57
e. USGS Quad Name: West Chester
inches up: 23 over: 7 from bottom right corner of map.
f. Located in a High Quality/Exceptional Value watershed?
[X] Yes    [ ] No

3. Type of Development Proposed (check appropriate box)

[X] Residential    [ ] Multi-Residential
Describe: 2 lot residential subdivision of approx. 2.6 acres.

[ ] Commercial    [ ] Institutional
Describe: ____________________

[ ] Brownfield Site Redevelopment
[ ] Other (specify): ____________________

4. Size

a. # of lots: 2    # of EDUs: 1
b. # of lots since 5/15/72: 0
c. Development Acreage: 2.6
d. Remaining Acreage: 0

5. Sewage Flows

275 gpd

6. Proposed Sewage Disposal Method (check applicable boxes)

a. [X] Sewerage System
[X] Existing (connection only)    [ ] New (extension)
[X] Public    [ ] Private
[ ] Pump Station(s)/Force Main    [ ] Gravity
Name of existing system being extended: East Goshen Municipal Authority
Interceptor Name: Route 352
Treatment Facility Name: East Goshen Township
NPDES Permit # PA0050504

b. [ ] Construction of Treatment Facility
[ ] With Stream Discharge
[ ] With Land Application (not including IRSIS)
[ ] Other
[ ] Repair?
Name of waterbody where point of discharge is proposed (if stream discharge): ____________________

c. [ ] Onlot Sewage Disposal Systems (check appropriate box)
[ ] Individual onlot system(s) (including IRSIS)
[ ] Community onlot system
[ ] Large-Volume onlot system

d. [ ] Retaining tanks
Number of Holding Tanks: ____________________
Number of Privies: ____________________

7. [ ] Request Sewage Facilities Planning Module forms in electronic format

8. Request for Planning Exemption

a. Protection of rare, endangered or threatened species
Check one:
[X] The "PNDI Project Environmental Review Receipt" is attached.
or
[ ] A completed "PNDI Project Planning & Environmental Review Form," (PNDI Form) is attached. I request DEP staff to complete the required PNDI search for my project. I realize that my planning exemption will be considered incomplete and that the DEP processing of my planning exemption request will be delayed, until a "PNDI Project Environmental Review Receipt" and all supporting documentation from jurisdictional agencies (when necessary) is/are received by DEP.

Applicant or Consultant Initials: ____________________

b. [X] Plot Plan Attached    [ ] Site Reports Attached

c. Onlot Disposal Systems
(1) I certify that the Official Plan shows this area as an onlot service area.
____________________ / ________
(Signature of Municipal Official)    Date
____________________ / ________
Name (Print)    Title
________________________________________
Municipality (must be same as in 2.b.)
Telephone # ____________________

(2) I certify that each lot in this subdivision has been tested and is suitable for both a primary and replacement sewage disposal system.
____________________ / ________
Signature of SEO    Date
____________________ / ________
Name (Print)    Certification #
Telephone # ____________________

(3) I certify that each lot in this subdivision is at least 1 acre in size
____________________ / ________
(Signature of Project Applicant/Agent)    Date

d. Public Sewerage Service (i.e., ownership by municipality or authority)
Based upon written documentation, I certify that the facilities proposed for use have capacity and that no overload exists or is projected within 5 years. (Attach documents.)
____________________ / ________
(Signature of Municipal Official)    Date
____________________ / ________
Name (Print)    Title
________________________________________
Municipality (must be same as in 2.b.)
Telephone # ____________________

- 6 -

PNDI Project Environmental Review Receipt      Project Search ID: 20160219550188

1. PROJECT INFORMATION

Project Name: 943 Cornwallis
Date of review: 2/19/2016 10:55:27 AM
Project Category: Development,Residential,subdivision which will contain 1-2 lots with 1-2 single family living units
Project Area: 2.8 acres
County: Chester Township/Municipality: East Goshen
Quadrangle Name: WEST CHESTER ~ ZIP Code: 19380
Decimal Degrees: 39.998784 N, -75.549632 W
Degrees Minutes Seconds: 39° 59' 55.6" N, -75° 32' 58.7" W

[Project location map showing a polygonal parcel boundary along Cornwallis Dr, near King George Ct and Del Vacchio Landscape & Garden Center. Labels: Cornwallis Dr, King George Ct, Del Vacchio Landscape & Garden Center, Google, Map data ©2016 Google]

2. SEARCH RESULTS

Agency Results Response
PA Game Commission No Known Impact No Further Review Required
PA Department of Conservation and Natural Resources Potential Impact FURTHER REVIEW IS REQUIRED, See Agency Response
PA Fish and Boat Commission No Known Impact No Further Review Required
U.S. Fish and Wildlife Service No Known Impact No Further Review Required

As summarized above, Pennsylvania Natural Diversity Inventory (PNDI) records indicate there may be potential impacts to threatened and endangered and/or special concern species and resources within the project area. If the response above indicates "No Further Review Required" no additional communication with the respective agency is required. If the response is "Further Review Required" or "See Agency Response," refer to the appropriate agency comments below. Please see the DEP Information Section of this receipt if a PA Department of Environmental Protection Permit is required.

Page 1 of 5

PNDI Project Environmental Review Receipt    Project Search ID: 20160219550188

Note that regardless of PNDI search results, projects requiring a Chapter 105 DEP individual permit or GP 5, 6, 7, 8, 9 or 11 in certain counties (Adams, Berks, Bucks, Carbon, Chester, Cumberland, Delaware, Lancaster, Lebanon, Lehigh, Monroe, Montgomery, Northampton, Schuylkill and York) must comply with the bog turtle habitat screening requirements of the PASPGP.

RESPONSE TO QUESTION(S) ASKED

Q1: "Will the entire project area (including any discharge), plus a 300 feet buffer around the project area, all occur in or on an existing building, parking lot, driveway, road, road shoulder, street, runway, paved area, railroad bed, maintained (periodically mown) lawn, crop agriculture field or maintained orchard?"
Your answer is: 3. Unknown

3. AGENCY COMMENTS

Regardless of whether a DEP permit is necessary for this proposed project, any potential impacts to threatened and endangered species and/or special concern species and resources must be resolved with the appropriate jurisdictional agency. In some cases, a permit or authorization from the jurisdictional agency may be needed if adverse impacts to these species and habitats cannot be avoided.

These agency determinations and responses are valid for two years (from the date of the review), and are based on the project information that was provided, including the exact project location; the project type, description, and features; and any responses to questions that were generated during this search. If any of the following change: 1) project location, 2) project size or configuration, 3) project type, or 4) responses to the questions that were asked during the online review, the results of this review are not valid, and the review must be searched again via the PNDI Environmental Review Tool and resubmitted to the jurisdictional agencies. The PNDI tool is a primary screening tool, and a desktop review may reveal more or fewer impacts than what is listed on this PNDI receipt. The jursidiction agencies strongly advise against conducting surveys for the species listed on the receipt prior to consultation with the agencies.

PA Game Commission

RESPONSE: No Impact is anticipated to threatened and endangered species and/or special concern species and resources.

PA Department of Conservation and Natural Resources

RESPONSE: Further review of this project is necessary to resolve the potential impacts(s). Please send project information to this agency for review (see WHAT TO SEND).

DCNR Species: (Note: The PNDI tool is a primary screening tool, and a desktop review may reveal more or fewer species than what is listed below. After desktop review, if a botanical survey is required by DCNR, we recommend the DCNR Botanical Survey Protocols, available here: http://www.gis.dcnr.state.pa.us/hgis-er/PNDI_DCNR.aspx.)
Scientific Name: Fimbristylis annua
Common Name: Annual Fimbry
Current Status: Threatened
Proposed Status: Threatened

Scientific Name: Sensitive Species**

Page 2 of 5

PNDI Project Environmental Review Receipt    Project Search ID: 20160219550188

Common Name:
Current Status: Threatened
Proposed Status: Threatened

Scientific Name: Symphyotrichum depauperatum
Common Name: Serpentine Aster
Current Status: Threatened
Proposed Status: Threatened

PA Fish and Boat Commission

RESPONSE: No Impact is anticipated to threatened and endangered species and/or special concern species and resources.

U.S. Fish and Wildlife Service

RESPONSE: No impacts to federally listed or proposed species are anticipated. Therefore, no further consultation/coordination under the Endangered Species Act (87 Stat. 884, as amended; 16 U.S.C. 1531 et seq. is required. Because no take of federally listed species is anticipated, none is authorized. This response does not reflect potential Fish and Wildlife Service concerns under the Fish and Wildlife Coordination Act or other authorities.

* Special Concern Species or Resource - Plant or animal species classified as rare, tentatively undetermined or candidate as well as other taxa of conservation concern, significant natural communities, special concern populations (plants or animals) and unique geologic features.
** Sensitive Species - Species identified by the jurisdictional agency as collectible, having economic value, or being susceptible to decline as a result of visitation.

WHAT TO SEND TO JURISDICTIONAL AGENCIES

If project information was requested by one or more of the agencies above, send the following information to the agency(s) seeking this information (see AGENCY CONTACT INFORMATION).

Check-list of Minimum Materials to be submitted:
_____SIGNED copy of this Project Environmental Review Receipt
_____Project narrative with a description of the overall project, the work to be performed, current physical characteristics of the site and acreage to be impacted.
_____Project location information (name of USGS Quadrangle, Township/Municipality, and County)
_____USGS 7.5-minute Quadrangle with project boundary clearly indicated, and quad name on the map

The inclusion of the following information may expedite the review process.
_____A basic site plan(particularly showing the relationship of the project to the physical features such as wetlands, streams, ponds, rock outcrops, etc.)
_____Color photos keyed to the basic site plan (i.e. showing on the site plan where and in what direction each photo was taken and the date of the photos)
_____Information about the presence and location of wetlands in the project area, and how this was determined

Page 3 of 5

PNDI Project Environmental Review Receipt    Project Search ID: 20160219550188

(e.g., by a qualified wetlands biologist), if wetlands are present in the project area, provide project plans showing the location of all project features, as well as wetlands and streams

4. DEP INFORMATION

The Pa Department of Environmental Protection (DEP) requires that a signed copy of this receipt, along with any required documentation from jurisdictional agencies concerning resolution of potential impacts, be submitted with applications for permits requiring PNDI review. For cases where a "Potential Impact" to threatened and endangered species has been identified before the application has been submitted to DEP, the application should not be submitted until the impact has been resolved. For cases where "Potential Impact" to special concern species and resources has been identified before the application has been submitted, the application should be submitted to DEP along with the PNDI receipt. The PNDI Receipt should also be submitted to the appropriate agency according to directions on the PNDI Receipt. DEP and the jurisdictional agency will work together to resolve the potential impact(s). See the DEP PNDI policy at http://www.naturalheritage.state.pa.us.

Page 4 of 5

PNDI Project Environmental Review Receipt    Project Search ID: 20160219550188

5. ADDITIONAL INFORMATION

The PNDI environmental review website is a preliminary screening tool. There are often delays in updating species status classifications. Because the proposed status represents the best available information regarding the conservation status of the species, state jurisdictional agency staff give the proposed statuses at least the same consideration as the current legal status. If surveys or further information reveal that a threatened and endangered and/or special concern species and resources exist in your project area, contact the appropriate jurisdictional agency/agencies immediately to identify and resolve any impacts.

For a list of species known to occur in the county where your project is located, please see the species lists by county found on the PA Natural Heritage Program (PNHP) home page (www.naturalheritage.state.pa.us). Also note that the PNDI Environmental Review Tool only contains information about species occurrences that have actually been reported to the PNHP.

6. AGENCY CONTACT INFORMATION

PA Department of Conservation and Natural Resources
Bureau of Forestry, Ecological Services Section
400 Market Street, PO Box 8552, Harrisburg, PA. 17105-8552
Fax:(717) 772-0271

U.S. Fish and Wildlife Service
Pennsylvania Field Office
110 Radnor Rd; Suite 101, State College, PA 16801
NO Faxes Please.

PA Fish and Boat Commission
Division of Environmental Services
450 Robinson Lane, Bellefonte, PA. 16823-7437
NO Faxes Please

PA Game Commission
Bureau of Wildlife Habitat Management
Division of Environmental Planning and Habitat Protection
2001 Elmerton Avenue, Harrisburg, PA. 17110-9797
Fax:(717) 787-6957

7. PROJECT CONTACT INFORMATION

Name: Scott Andress
Company/Business Name: Edward B. Walsh and Assoc., Inc.
Address: 125 Dowlin Forge Rd.
City, State, Zip: Exton, PA 19341
Phone: (610) 903 0042    Fax: (610) 903 0080
Email: sandress@ebwalshinc.com

8. CERTIFICATION

I certify that ALL of the project information contained in this receipt (including project location, project size/configuration, project type, answers to questions) is true, accurate and complete. In addition, if the project type, location, size or configuration changes, or if the answers to any questions that were asked during this online review change, I agree to re-do the online environmental review.

Scott Andress Edward B. Walsh and Assoc., Inc. Agent
applicant/project proponent signature

2/19/16
date

Page 5 of 5

PROJECT NARRATIVE

It is proposed to develop 943 Cornwallis Drive into two residential dwelling lots. The property consists of approximately 2.5 acres with a dwelling and driveway. The exiting dwelling is currently served by public sewer and an individual drinking water well.

Lot #1 will be a new dwelling to replace the existing dwelling. This lot will be served with public sewer and a well.

Lot #2 will be for the new lot and proposed dwelling to be served by public sewer and a well.

The total flow for the project is 550 gallons per day; however new sewage flows are only for Lot#2 for a total new flow of 275 gallons per day or 1 EDU.

WEST CHESTER QUADRANGLE PENNSYLVANIA 7.5-MINUTE SERIES

The National Map US Topo

943 Cornwallis Drive

Coordinates: 75°30' | 40°00' | 250 000 FEET | 4427 | 4426 | 4425 | 4424 | 457 | 456 | 455 | 2 590 000 FEET | 454 | 32'30" | 453 | 452

Places and Features: Sugartown, Dutton-Mill, Wyllpen-Farms, Hilloch Manor, Windmere Place, Hunt Country, Clock Tower Woods, Applebrook Golf Course, Bow Tree, Rocky Hill, Ashbridge Farms, White Chimneys, E Goshen Bible Cem, Goshenville, Marydell Farms, Pin Oak Farms, Rockland Village I and II, Milltown, Milltown Reservoir, Grand Oak Run, Meriweather Farms, Goshen Terrace, Strasburg Court, West Goshen, Ashbridge Run, Ridley Cr, George Smedley Run, Shugart Run, Benoni Run, Sinkler Lake, Hunters Run, E Br Chester Cr

Roads and Streets: PROVIDENCE RD, SUGARTOWN RD, GOSHEN RD, FARM LN, DUTTON MILL RD, GREEN LN, ROSELAWN LN, CHOWNING DR, LINE RD, MANLEY RD, E HILLTOP RD, WOODCREST RD, BOOT RD, E STRASBURG RD, HUNTER CIR, FOX XING, STILL RD, EDITH RD, THORNCROFT DR, TOWNE DR, PEACH TREE DR, CLOCK TOWER DR, E BOOT RD, HIBBERD LN, BOW TREE DR, SCOFIELD LN, BEAUMONT CIR, CHRISTINE LN, MARGO LN, ELDRIDGE DR, HERRON LN, Route 352, Route 3, VISTA DR, CORNWALLIS DR, SARATOGA DR, MARYDELL DR, BARKER DR, GATESWOOD DR, RICHARD DR, ANNE DR, ALISON DR, MISAK DR, BRIAN DR, COOPER CIR, GLENBROOK LN, LOCHWOOD LN, WATERVIEW RD, GENERALS WAY, LARCH LN, RESERVOIR RD, BALDWIN DR, PARK AVE, MEADOWBROOK LN, CHERRY LN, LINDEN LN, ENTERPRISE DR, PAOLI PIKE, MARK DR, CHANDLER DR, CARRIAGE DR, CLOVER LN, HEATHER LN, GRAND OAK LN, GOSHEN PKWY, ELLIS LN, GATEWAY LN, RICHMOND RD, BOX ELDER DR, JOY LN, HAWTHORNE LN, KINGSWAY RD, BOULDER LN, SYLVAN RD, ROBERTS LN, GLEN AVE, PENN LN, DAVID LN

PRELIMINARY/FINAL CONSTRUCTION IMPROVEMENT PLAN

PLAN OF SUBDIVISION FOR 943 CORNWALLIS DRIVE

EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PA.

Edward B. Walsh & Associates, Inc.
CIVIL ENGINEERS & SURVEYORS
LIONVILLE PROFESSIONAL CENTER
125 Dowlin Forge Rd.
Exton, Pennsylvania 19341
Phone: 610-903-0060
Fax: 610-903-0080

Project-4170
Date-10/22/15
Scale-1"=40'
Drawn- D.B.
Checked- A.J.B.
Sheet- 3 OF 6
Plotted: 2/19/2016
File: P:\d\4170\4170-B.pro

LEGEND

  • 430 — EXISTING INDEX CONTOUR
  • EXISTING INTERIOR CONTOUR
  • 426 — PROPOSED CONTOUR
  • 415.25 + — PROPOSED SPOT ELEVATION
  • EXISTING INLET
  • PROPOSED INLET
  • EXISTING STORM SEWER PIPE
  • PROPOSED STORM SEWER PIPE
  • EXISTING FLARED END SECTION
  • EXISTING SANITARY MANHOLE
  • S — EXISTING SANITARY SEWER PIPE
  • S — PROPOSED SANITARY SEWER PIPE
  • E — EXISTING ELECTRIC LINE
  • E — PROPOSED ELECTRIC LINE
  • SOILS BOUNDARY LINE
  • EXISTING EDGE OF PAVING
  • PROPOSED EDGE OF PAVING/DRIVEWAY
  • EXISTING SIGN
  • EXISTING CONCRETE
  • PROPOSED CONCRETE
  • EXISTING STRUCTURE
  • PROPOSED STRUCTURE
  • TO BE CONSTRUCTED BY OTHERS
  • EXISTING DECIDUOUS TREE
  • EXISTING EVERGREEN TREE

Plan Details

CORNWALLIS DRIVE POSTED SPEED LIMIT = 25 MPH

BENCH MARK SAN. MH RIM 416.27

CAR PULLOVER AREA | 20' WIDE SAN. LATERAL EASEMENT | CONNECT TO EXISTING MAIN WITH A SADDLE TYPE CONNECTION

EX. RIGHT-OF-WAY | ROAD CENTERLINE | PROPOSED RIGHT OF WAY LINE

Lot 1: FF 422.00, BSMT 413.00, GAR 420.67 | 2 STORY FRAME DWELLING TO BE REMOVED | METAL SHED TO BE REMOVED | CLEANOUT (TYP) | 6" PVC ROOF DRAIN (TYP)

Lot 2: FF 430.00, BSMT 421.00, GAR 428.67 | 30'x15' STONE RECHARGE BED | YARD DRAIN | TENT/SHED TO BE REMOVED | PROPOSED WELL | WIRE FENCE | POST & RAIL WOOD FENCE

NOTE: THE DISTURBED AREAS ON LOT 2 ARE TO BE STABILIZED WITH AMENDED SOILS TO MEET THE STORMWATER RUNOFF VOLUME REDUCTION REQUIREMENTS.

NOTES

1. ALL ROOF DRAINS MUST DRAIN TO THE STORMWATER MANAGEMENT SYSTEMS.

SOILS CLASSIFICATION

  • CaB - CALIFON LOAM, 3 TO 8 PERCENT SLOPES. HYDROLOGIC SOIL GROUP "C".
  • GdB - GLADSTONE GRAVELLY LOAM, 3 TO 8 PERCENT SLOPES. HYDROLOGIC SOIL GROUP "B".
  • UugB - URBAN LAND-UDORTHENTS, SCHIST AND GNEISS COMPLEX, 0 TO 8 PERCENT SLOPES. HYDROLOGIC SOIL GROUP "C".

ACT 287 as amended SERIAL NUMBER 20152781576

Edward B. Walsh & Associates, Inc. does not guarantee the accuracy of the locations for existing subsurface utility lines, structures, etc. shown on the plans, nor does E. B. Walsh & Assoc., Inc. guarantee that all subsurface utility lines, structures, etc. are shown.

Contractor shall verify the location and elevations of all subsurface utility lines, structures, etc. before the start of work, by calling the Pennsylvania One Call System at 1-800-242-1776.

UTILITIES NOTIFIED

  • GOSHEN TOWNSHIP
  • INTERSTATE ENERGY
  • TEXAS EASTERN
  • COMCAST-FIBER
  • COMCAST CABLE
  • VERIZON EASTERN
  • AQUA PA
  • PECO CTVL

PENNSYLVANIA ONE CALL SYSTEM, INC. 1-800-242-1776 STOP-CALL BEFORE YOU DIG

IT IS THE CONTRACTOR'S RESPONSIBILITY TO VERIFY ALL EXACT LOCATIONS AND ELEVATIONS OF ALL UNDERGROUND UTILITIES AND OTHER STRUCTURES BEFORE THE START OF CONSTRUCTION ON THIS PROJECT. THIS NOTICE APPLIES TO INFORMATION FOR THIS PROJECT INCLUDING PLANS OF SAME PREPARED BY OTHERS, E.G. UTILITY COMPANY PLANS. THIS NOTICE IS GIVEN AS PER ACT 287 OF THE COMMONWEALTH OF PENNSYLVANIA. SERIAL # 20152781576

UPI NO. 53-4-57

GRAPHIC SCALE: 40 0 40 80 120 160 feet

PRELIMINARY/FINAL CONSTRUCTION IMPROVEMENT PLAN

PLAN OF SUBDIVISION FOR 943 CORNWALLIS DRIVE

EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PA.

Edward B. Walsh & Associates, Inc.
CIVIL ENGINEERS & SURVEYORS
LIONVILLE PROFESSIONAL CENTER
125 Dowlin Forge Rd.
Exton, Pennsylvania 19341
Phone: 610-903-0060
Fax: 610-903-0080

Project-4170
Date-10/22/15
Scale-1"=40'
Drawn- D.B.
Checked- A.J.B.
Sheet- 3 OF 6
Plotted: 2/19/2016
File: P:\d\4170\4170-B.pro

LEGEND

  • 430 — EXISTING INDEX CONTOUR
  • EXISTING INTERIOR CONTOUR
  • 426 — PROPOSED CONTOUR
  • 415.25 + — PROPOSED SPOT ELEVATION
  • EXISTING INLET
  • PROPOSED INLET
  • EXISTING STORM SEWER PIPE
  • PROPOSED STORM SEWER PIPE
  • EXISTING FLARED END SECTION
  • EXISTING SANITARY MANHOLE
  • S — EXISTING SANITARY SEWER PIPE
  • S — PROPOSED SANITARY SEWER PIPE
  • E — EXISTING ELECTRIC LINE
  • E — PROPOSED ELECTRIC LINE
  • SOILS BOUNDARY LINE
  • EXISTING EDGE OF PAVING
  • PROPOSED EDGE OF PAVING/DRIVEWAY
  • EXISTING SIGN
  • EXISTING CONCRETE
  • PROPOSED CONCRETE
  • EXISTING STRUCTURE
  • PROPOSED STRUCTURE
  • TO BE CONSTRUCTED BY OTHERS
  • EXISTING DECIDUOUS TREE
  • EXISTING EVERGREEN TREE

Plan Details

CORNWALLIS DRIVE POSTED SPEED LIMIT = 25 MPH

BENCH MARK SAN. MH RIM 416.27

CAR PULLOVER AREA | 20' WIDE SAN. LATERAL EASEMENT | CONNECT TO EXISTING MAIN WITH A SADDLE TYPE CONNECTION

EX. RIGHT-OF-WAY | ROAD CENTERLINE | PROPOSED RIGHT OF WAY LINE

Lot 1: FF 422.00, BSMT 413.00, GAR 420.67 | 2 STORY FRAME DWELLING TO BE REMOVED | METAL SHED TO BE REMOVED | CLEANOUT (TYP) | 6" PVC ROOF DRAIN (TYP)

Lot 2: FF 430.00, BSMT 421.00, GAR 428.67 | 30'x15' STONE RECHARGE BED | YARD DRAIN | TENT/SHED TO BE REMOVED | PROPOSED WELL | WIRE FENCE | POST & RAIL WOOD FENCE

NOTE: THE DISTURBED AREAS ON LOT 2 ARE TO BE STABILIZED WITH AMENDED SOILS TO MEET THE STORMWATER RUNOFF VOLUME REDUCTION REQUIREMENTS.

NOTES

1. ALL ROOF DRAINS MUST DRAIN TO THE STORMWATER MANAGEMENT SYSTEMS.

SOILS CLASSIFICATION

  • CaB - CALIFON LOAM, 3 TO 8 PERCENT SLOPES. HYDROLOGIC SOIL GROUP "C".
  • GdB - GLADSTONE GRAVELLY LOAM, 3 TO 8 PERCENT SLOPES. HYDROLOGIC SOIL GROUP "B".
  • UugB - URBAN LAND-UDORTHENTS, SCHIST AND GNEISS COMPLEX, 0 TO 8 PERCENT SLOPES. HYDROLOGIC SOIL GROUP "C".

ACT 287 as amended SERIAL NUMBER 20152781576

Edward B. Walsh & Associates, Inc. does not guarantee the accuracy of the locations for existing subsurface utility lines, structures, etc. shown on the plans, nor does E. B. Walsh & Assoc., Inc. guarantee that all subsurface utility lines, structures, etc. are shown.

Contractor shall verify the location and elevations of all subsurface utility lines, structures, etc. before the start of work, by calling the Pennsylvania One Call System at 1-800-242-1776.

UTILITIES NOTIFIED

  • GOSHEN TOWNSHIP
  • INTERSTATE ENERGY
  • TEXAS EASTERN
  • COMCAST-FIBER
  • COMCAST CABLE
  • VERIZON EASTERN
  • AQUA PA
  • PECO CTVL

PENNSYLVANIA ONE CALL SYSTEM, INC. 1-800-242-1776 STOP-CALL BEFORE YOU DIG

IT IS THE CONTRACTOR'S RESPONSIBILITY TO VERIFY ALL EXACT LOCATIONS AND ELEVATIONS OF ALL UNDERGROUND UTILITIES AND OTHER STRUCTURES BEFORE THE START OF CONSTRUCTION ON THIS PROJECT. THIS NOTICE APPLIES TO INFORMATION FOR THIS PROJECT INCLUDING PLANS OF SAME PREPARED BY OTHERS, E.G. UTILITY COMPANY PLANS. THIS NOTICE IS GIVEN AS PER ACT 287 OF THE COMMONWEALTH OF PENNSYLVANIA. SERIAL # 20152781576

UPI NO. 53-4-57

GRAPHIC SCALE: 40 0 40 80 120 160 feet

3800-CD-BPNPSM0359    2/2015

1. Development Information

Name of Development: 943 Cornwallis Drive
Developer Name: T. Richard Moser Land Developers, LP
Address: 1171 Lancaster Avenue, Suite 201
Berwyn, PA 19312
Telephone #: 610-725-0812
Email: NA

2. Location of Development

a. County: Chester
b. Municipality: East Goshen
c. Address or Coordinates: 943 Cornwallis Drive, West Chester, PA 19380
d. Tax Parcel #: 53-4-57
e. USGS Quad Name: West Chester
inches up: 23 over: 7 from bottom right corner of map.
f. Located in a High Quality/Exceptional Value watershed?
☒ Yes      ☐ No

3. Type of Development Proposed (check appropriate box)

☒ Residential      ☐ Multi-Residential
Describe: 2 lot residential subdivision of approx. 2.6 acres.
☐ Commercial      ☐ Institutional
Describe: ________________________________
☐ Brownfield Site Redevelopment
☐ Other (specify): ________________________________

4. Size

a. # of lots: 2      # of EDUs: 1
b. # of lots since 5/15/72: 0
c. Development Acreage: 2.6
d. Remaining Acreage: 0

5. Sewage Flows: 275 gpd

6. Proposed Sewage Disposal Method (check applicable boxes)

a. ☒ Sewerage System
    ☒ Existing (connection only)      ☐ New (extension)
    ☒ Public      ☐ Private
    ☐ Pump Station(s)/Force Main      ☐ Gravity
    Name of existing system being extended: East Goshen Municipal Authority
    Interceptor Name: Route 352
    Treatment Facility Name: East Goshen Township
    NPDES Permit #: PA0050504

b. ☐ Construction of Treatment Facility
    ☐ With Stream Discharge
    ☐ With Land Application (not including IRSIS)
    ☐ Other
    ☐ Repair?
    Name of waterbody where point of discharge is proposed (if stream discharge): ________________________________

c. ☐ Onlot Sewage Disposal Systems (check appropriate box)
    ☐ Individual onlot system(s) (including IRSIS)
    ☐ Community onlot system
    ☐ Large-Volume onlot system
d. ☐ Retaining tanks
    Number of Holding Tanks: ________
    Number of Privies: ________

7. ☐ Request Sewage Facilities Planning Module forms in electronic format

8. Request for Planning Exemption

a. Protection of rare, endangered or threatened species
Check one:
☒ The "PNDI Project Environmental Review Receipt" is attached.
or
☐ A completed "PNDI Project Planning & Environmental Review Form," (PNDI Form) is attached. I request DEP staff to complete the required PNDI search for my project. I realize that my planning exemption will be considered incomplete and that the DEP processing of my planning exemption request will be delayed, until a "PNDI Project Environmental Review Receipt" and all supporting documentation from jurisdictional agencies (when necessary) is/are received by DEP.
Applicant or Consultant Initials: ________

b. ☒ Plot Plan Attached      ☐ Site Reports Attached

c. Onlot Disposal Systems
(1) I certify that the Official Plan shows this area as an onlot service area.
________________________________ / ____________
(Signature of Municipal Official)      Date
________________________________ / ____________
Name (Print)      Title
Municipality (must be same as in 2.b.): ____________________
Telephone #: ____________________

(2) I certify that each lot in this subdivision has been tested and is suitable for both a primary and replacement sewage disposal system.
________________________________ / ____________
Signature of SEO      Date
________________________________ / ____________
Name (Print)      Certification #
Telephone #: ____________________

(3) I certify that each lot in this subdivision is at least 1 acre in size
________________________________ / ____________
(Signature of Project Applicant/Agent)      Date

d. Public Sewerage Service (i.e., ownership by municipality or authority)
Based upon written documentation, I certify that the facilities proposed for use have capacity and that no overload exists or is projected within 5 years. (Attach documents.)
________________________________ / ____________
(Signature of Municipal Official)      Date
________________________________ / ____________
Name (Print)      Title
Municipality (must be same as in 2.b.): ____________________
Telephone #: ____________________

- 6 -

PNDI Project Environmental Review Receipt    Project Search ID: 20160219550188

1. PROJECT INFORMATION

Project Name: 943 Cornwallis
Date of review: 2/19/2016 10:55:27 AM
Project Category: Development, Residential, subdivision which will contain 1-2 lots with 1-2 single family living units
Project Area: 2.8 acres
County: Chester      Township/Municipality: East Goshen
Quadrangle Name: WEST CHESTER ~ ZIP Code: 19380
Decimal Degrees: 39.998784 N, -75.549632 W
Degrees Minutes Seconds: 39° 59' 55.6" N, -75° 32' 58.7" W

Map showing the project location along Cornwallis Drive, with project boundary outlined, near King George Court and Del Vacchio Landscape & Garden Center.

Map Labels: Cornwallis Dr, King George Ct, Del Vacchio Landscape & Garden Center, Google, Map data ©2016 Google.

2. SEARCH RESULTS

Agency Results Response
PA Game Commission No Known Impact No Further Review Required
PA Department of Conservation and Natural Resources Potential Impact FURTHER REVIEW IS REQUIRED, See Agency Response
PA Fish and Boat Commission No Known Impact No Further Review Required
U.S. Fish and Wildlife Service No Known Impact No Further Review Required

As summarized above, Pennsylvania Natural Diversity Inventory (PNDI) records indicate there may be potential impacts to threatened and endangered and/or special concern species and resources within the project area. If the response above indicates "No Further Review Required" no additional communication with the respective agency is required. If the response is "Further Review Required" or "See Agency Response," refer to the appropriate agency comments below. Please see the DEP Information Section of this receipt if a PA Department of Environmental Protection Permit is required.

Page 1 of 5

PNDI Project Environmental Review Receipt    Project Search ID: 20160219550188

Note that regardless of PNDI search results, projects requiring a Chapter 105 DEP individual permit or GP 5, 6, 7, 8, 9 or 11 in certain counties (Adams, Berks, Bucks, Carbon, Chester, Cumberland, Delaware, Lancaster, Lebanon, Lehigh, Monroe, Montgomery, Northampton, Schuylkill and York) must comply with the bog turtle habitat screening requirements of the PASPGP.

RESPONSE TO QUESTION(S) ASKED

Q1: "Will the entire project area (including any discharge), plus a 300 feet buffer around the project area, all occur in or on an existing building, parking lot, driveway, road, road shoulder, street, runway, paved area, railroad bed, maintained (periodically mown) lawn, crop agriculture field or maintained orchard?"
Your answer is: 3. Unknown

3. AGENCY COMMENTS

Regardless of whether a DEP permit is necessary for this proposed project, any potential impacts to threatened and endangered species and/or special concern species and resources must be resolved with the appropriate jurisdictional agency. In some cases, a permit or authorization from the jurisdictional agency may be needed if adverse impacts to these species and habitats cannot be avoided.

These agency determinations and responses are valid for two years (from the date of the review), and are based on the project information that was provided, including the exact project location; the project type, description, and features; and any responses to questions that were generated during this search. If any of the following change: 1) project location, 2) project size or configuration, 3) project type, or 4) responses to the questions that were asked during the online review, the results of this review are not valid, and the review must be searched again via the PNDI Environmental Review Tool and resubmitted to the jurisdictional agencies. The PNDI tool is a primary screening tool, and a desktop review may reveal more or fewer impacts than what is listed on this PNDI receipt. The jursidiction agencies strongly advise against conducting surveys for the species listed on the receipt prior to consultation with the agencies.

PA Game Commission

RESPONSE: No Impact is anticipated to threatened and endangered species and/or special concern species and resources.

PA Department of Conservation and Natural Resources

RESPONSE: Further review of this project is necessary to resolve the potential impacts(s). Please send project information to this agency for review (see WHAT TO SEND).

DCNR Species: (Note: The PNDI tool is a primary screening tool, and a desktop review may reveal more or fewer species than what is listed below. After desktop review, if a botanical survey is required by DCNR, we recommend the DCNR Botanical Survey Protocols, available here: http://www.gis.dcnr.state.pa.us/hgis-er/PNDI_DCNR.aspx.)
Scientific Name: Fimbristylis annua
Common Name: Annual Fimbry
Current Status: Threatened
Proposed Status: Threatened

Scientific Name: Sensitive Species**

Page 2 of 5

PNDI Project Environmental Review Receipt    Project Search ID: 20160219550188

Common Name:
Current Status: Threatened
Proposed Status: Threatened

Scientific Name: Symphyotrichum depauperatum
Common Name: Serpentine Aster
Current Status: Threatened
Proposed Status: Threatened

PA Fish and Boat Commission

RESPONSE: No Impact is anticipated to threatened and endangered species and/or special concern species and resources.

U.S. Fish and Wildlife Service

RESPONSE: No impacts to federally listed or proposed species are anticipated. Therefore, no further consultation/coordination under the Endangered Species Act (87 Stat. 884, as amended; 16 U.S.C. 1531 et seq. is required. Because no take of federally listed species is anticipated, none is authorized. This response does not reflect potential Fish and Wildlife Service concerns under the Fish and Wildlife Coordination Act or other authorities.

* Special Concern Species or Resource - Plant or animal species classified as rare, tentatively undetermined or candidate as well as other taxa of conservation concern, significant natural communities, special concern populations (plants or animals) and unique geologic features.
** Sensitive Species - Species identified by the jurisdictional agency as collectible, having economic value, or being susceptible to decline as a result of visitation.

WHAT TO SEND TO JURISDICTIONAL AGENCIES

If project information was requested by one or more of the agencies above, send the following information to the agency(s) seeking this information (see AGENCY CONTACT INFORMATION).

Check-list of Minimum Materials to be submitted:
_____SIGNED copy of this Project Environmental Review Receipt
_____Project narrative with a description of the overall project, the work to be performed, current physical characteristics of the site and acreage to be impacted.
_____Project location information (name of USGS Quadrangle, Township/Municipality, and County)
_____USGS 7.5-minute Quadrangle with project boundary clearly indicated, and quad name on the map

The inclusion of the following information may expedite the review process.
_____A basic site plan(particularly showing the relationship of the project to the physical features such as wetlands, streams, ponds, rock outcrops, etc.)
_____Color photos keyed to the basic site plan (i.e. showing on the site plan where and in what direction each photo was taken and the date of the photos)
_____Information about the presence and location of wetlands in the project area, and how this was determined

Page 3 of 5

PNDI Project Environmental Review Receipt    Project Search ID: 20160219550188

(e.g., by a qualified wetlands biologist), if wetlands are present in the project area, provide project plans showing the location of all project features, as well as wetlands and streams

4. DEP INFORMATION

The Pa Department of Environmental Protection (DEP) requires that a signed copy of this receipt, along with any required documentation from jurisdictional agencies concerning resolution of potential impacts, be submitted with applications for permits requiring PNDI review. For cases where a "Potential Impact" to threatened and endangered species has been identified before the application has been submitted to DEP, the application should not be submitted until the impact has been resolved. For cases where "Potential Impact" to special concern species and resources has been identified before the application has been submitted, the application should be submitted to DEP along with the PNDI receipt. The PNDI Receipt should also be submitted to the appropriate agency according to directions on the PNDI Receipt. DEP and the jurisdictional agency will work together to resolve the potential impact(s). See the DEP PNDI policy at http://www.naturalheritage.state.pa.us.

Page 4 of 5

PNDI Project Environmental Review Receipt    Project Search ID: 20160219550188

5. ADDITIONAL INFORMATION

The PNDI environmental review website is a preliminary screening tool. There are often delays in updating species status classifications. Because the proposed status represents the best available information regarding the conservation status of the species, state jurisdictional agency staff give the proposed statuses at least the same consideration as the current legal status. If surveys or further information reveal that a threatened and endangered and/or special concern species and resources exist in your project area, contact the appropriate jurisdictional agency/agencies immediately to identify and resolve any impacts.

For a list of species known to occur in the county where your project is located, please see the species lists by county found on the PA Natural Heritage Program (PNHP) home page (www.naturalheritage.state.pa.us). Also note that the PNDI Environmental Review Tool only contains information about species occurrences that have actually been reported to the PNHP.

6. AGENCY CONTACT INFORMATION

PA Department of Conservation and Natural Resources
Bureau of Forestry, Ecological Services Section
400 Market Street, PO Box 8552, Harrisburg, PA. 17105-8552
Fax:(717) 772-0271

U.S. Fish and Wildlife Service
Pennsylvania Field Office
110 Radnor Rd; Suite 101, State College, PA 16801
NO Faxes Please.

PA Fish and Boat Commission
Division of Environmental Services
450 Robinson Lane, Bellefonte, PA. 16823-7437
NO Faxes Please

PA Game Commission
Bureau of Wildlife Habitat Management
Division of Environmental Planning and Habitat Protection
2001 Elmerton Avenue, Harrisburg, PA. 17110-9797
Fax:(717) 787-6957

7. PROJECT CONTACT INFORMATION

Name: Scott Andress
Company/Business Name: Edward B. Walsh and Assoc., Inc.
Address: 125 Dowlin Forge Rd.
City, State, Zip: Exton, PA 19341
Phone: (610) 903 0042    Fax: (610) 903 0080
Email: sandress@ebwalshinc.com

8. CERTIFICATION

I certify that ALL of the project information contained in this receipt (including project location, project size/configuration, project type, answers to questions) is true, accurate and complete. In addition, if the project type, location, size or configuration changes, or if the answers to any questions that were asked during this online review change, I agree to re-do the online environmental review.

Scott Andress Edward B. Walsh and Assoc., Inc. Agent
applicant/project proponent signature

2/19/16
date

Page 5 of 5

PROJECT NARRATIVE

It is proposed to develop 943 Cornwallis Drive into two residential dwelling lots. The property consists of approximately 2.5 acres with a dwelling and driveway. The exiting dwelling is currently served by public sewer and an individual drinking water well.

Lot #1 will be a new dwelling to replace the existing dwelling. This lot will be served with public sewer and a well.

Lot #2 will be for the new lot and proposed dwelling to be served by public sewer and a well.

The total flow for the project is 550 gallons per day; however new sewage flows are only for Lot#2 for a total new flow of 275 gallons per day or 1 EDU.

WEST CHESTER QUADRANGLE PENNSYLVANIA 7.5-MINUTE SERIES

The National Map US Topo

943 Cornwallis Drive

Map Coordinates and Grid Labels

75°30' 40°00' 32'30"

2 590 000 FEET 250 000 FEET

452 453 454 455 456 457

4427 4426 4425 4424

Communities, Subdivisions, and Landmarks

  • Sugartown
  • Hunt Country
  • Clock Tower Woods
  • Applebrook Golf Course
  • E Goshen Bible Cem
  • Goshenville
  • Grand Oak Run
  • Dutton Mill
  • Wyllpen Farms
  • Bow Tree
  • Marydell Farms
  • Pin Oak Farms
  • Rocky Hill
  • Ashbridge Farms
  • Windmere Place
  • Hilloch Manor
  • White Chimneys
  • Rockland Village I and II
  • Meriweather Farms
  • Goshen Terrace
  • Strasburg Court
  • Milltown
  • West Goshen

Hydrography

  • Ashbridge Run
  • Shugart Run
  • Benoni Run
  • Ridley Cr
  • Sinkler Lake
  • Hunters Run
  • George Smedley Run
  • E Br Chester Cr
  • Milltown Reservoir

Roads and Highways

  • PROVIDENCE RD
  • SUGARTOWN RD
  • DUTTON MILL RD
  • ROSELAWN LN
  • CHOWNING DR
  • GREEN LN
  • BOOT RD
  • LINE RD
  • GOSHEN RD
  • FARM LN
  • TOWNE DR
  • THORNCROFT DR
  • PEACH TREE DR
  • CLOCK TOWER DR
  • E BOOT RD
  • HIBBERD LN
  • VISTA DR
  • CORNWALLIS DR
  • SARATOGA DR
  • GENERALS WAY
  • MEADOWBROOK LN
  • CHANDLER DR
  • CARRIAGE DR
  • CLOVER LN
  • HEATHER LN
  • GRAND OAK LN
  • CHERRY LN
  • LINDEN LN
  • GOSHEN PKWY
  • ENTERPRISE DR
  • PAOLI PIKE
  • MARYDELL DR
  • BARKER DR
  • ELDRIDGE DR
  • BOW TREE DR
  • GATESWOOD DR
  • LARCH LN
  • RESERVOIR RD
  • ELLIS LN
  • GATEWAY LN
  • RICHMOND RD
  • FARMINGTON LN
  • BOX ELDER DR
  • JOY LN
  • KINGSWAY RD
  • HAWTHORNE LN
  • MARK DR
  • BALDWIN DR
  • COOPER CIR
  • RICHARD DR
  • HERRON LN
  • SCOFIELD LN
  • BEAUMONT CIR
  • E STRASBURG RD
  • HUNTER CIR
  • FOX XING
  • MANLEY RD
  • CHRISTINE LN
  • MARGO LN
  • STILL RD
  • EDITH RD
  • E HILLTOP RD
  • WOODCREST RD
  • ANNE DR
  • BRIAN DR
  • ALISON DR
  • MISAK DR
  • GLENBROOK LN
  • LOCHWOOD LN
  • WATERVIEW RD
  • PARK AVE
  • BOULDER LN
  • SYLVAN RD
  • ROBERTS LN
  • GLEN AVE
  • PENN LN
  • WESTBROOK
  • DAVID LN
  • Route 3
  • Route 352

Contour Elevations

300 350 400 450 500

PRELIMINARY/FINAL CONSTRUCTION IMPROVEMENT PLAN

PLAN OF SUBDIVISION FOR 943 CORNWALLIS DRIVE

EAST GOSHEN TOWNSHIP CHESTER COUNTY, PA.

LEGEND

  • 430 EXISTING INDEX CONTOUR
  • EXISTING INTERIOR CONTOUR
  • 432 PROPOSED CONTOUR
  • 94.68 + PROPOSED SPOT ELEVATION
  • EXISTING INLET
  • PROPOSED INLET
  • EXISTING STORM SEWER PIPE
  • PROPOSED STORM SEWER PIPE
  • EXISTING FLARED END SECTION
  • EXISTING SANITARY MANHOLE
  • S EXISTING SANITARY SEWER PIPE
  • S PROPOSED SANITARY SEWER PIPE
  • E EXISTING ELECTRIC LINE
  • E PROPOSED ELECTRIC LINE
  • SOILS BOUNDARY LINE
  • EXISTING EDGE OF PAVING
  • PROPOSED EDGE OF PAVING/DRIVEWAY
  • EXISTING SIGN
  • EXISTING CONCRETE
  • PROPOSED CONCRETE
  • EXISTING STRUCTURE
  • PROPOSED STRUCTURE
  • TO BE CONSTRUCTED BY OTHERS
  • EXISTING DECIDUOUS TREE
  • EXISTING EVERGREEN TREE

Plan Annotations

BENCH MARK SAN. MH RIM 416.27

CORNWALLIS DRIVE POSTED SPEED LIMIT = 25 MPH

  • DRIVEWAY
  • COMPASS POST
  • 40.70'
  • 129.38'
  • N46°37'00"W 93.36'
  • N46°53'14"W 40.31'
  • N46°45'14"W 145.68'
  • 30" CMP/FES INV. 406.14
  • 18' WIDE CARTWAY
  • 33' EX. RIGHT-OF-WAY
  • TYPE "M" INLET T.G. 415.29 INV. (IN) 411.60 18" HDPE INV. (OUT) 411.01 18" HDPE
  • 18" HDPE
  • ROAD CENTERLINE
  • OUTLET PIPE
  • 25'
  • N37°23'00"W 492.34'
  • R=705.00' 7°42'17"
  • GdB
  • 17.15'
  • POLE PECO 92255/UG
  • DRIVEWAY

NOTE: THE D WITH A VOLUM

ACT 287 and Utilities Notified

ACT 287 as amended SERIAL NUMBER 20152781576

Edward B. Walsh & Associates, Inc. does not guarantee the accuracy of the locations for existing subsurface utility lines, structures, etc. shown on the plans, nor does E. B. Walsh & Assoc., Inc. guarantee that all subsurface utility lines, structures, etc. are shown.

Contractor shall verify the location and elevations of all subsurface utility lines, structures, etc. before the start of work, by calling the Pennsylvania One Call System at 1-800-242-1776.

UTILITIES NOTIFIED

  • GOSHEN TOWNSHIP
  • INTERSTATE ENERGY
  • TEXAS EASTERN
  • COMCAST-FIBER
  • COMCAST CABLE
  • VERIZON EASTERN
  • AQUA PA
  • PECO CTVL

UPI NO. 53-4-57

PENNSYLVANIA ONE CALL SYSTEM, INC. 1-800-242-1776 STOP - CALL BEFORE YOU DIG!

CaB GdB UugB

IT IS THE CONTRACTOR'S RESPONSIBILI EXACT LOCATIONS AND ELEVATIONS OF UTILITIES AND OTHER STRUCTURES BEF CONSTRUCTION ON THIS PROJECT. TH INFORMATION FOR THIS PROJECT INCLU PREPARED BY OTHERS, E.G. UTILITY CO NOTICE IS GIVEN AS PER ACT 287 OF OF PENNSYLVANIA. SERIAL # 20152781

Title Block

Edward B. Walsh & Associates, Inc. CIVIL ENGINEERS & SURVEYORS

LIONVILLE PROFESSIONAL CENTER
125 Dowlin Forge Rd.
Exton, Pennsylvania 19341
Phone: 610-903-0060
Fax: 610-903-0080

EBW

Field Value
Project 4170
Date 10/22/15
Scale 1"=40' NTS
Drawn D.B.
Checked A.J.B.
Sheet 3 OF 6
Plotted 2/19/2016
File F:\JB\4170\4170-B.pro

610-692-7171
www.eastgoshen.org

FYI

BOARD OF SUPERVISORS

EAST GOSHEN TOWNSHIP

CHESTER COUNTY
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

March 8, 2016

Dear Property Owner:

The purpose of this letter is to inform you that The Township Planning Commission is going to discuss a possible amendment to the Township Zoning Ordinance regarding swimming Pool Setbacks for Single-family open space developments (§240-32.Q and §240-36) at their meeting on Wednesday, March 16, 2016 at 7 PM.

The Sorrell Hill Development on Line Road is a Single-family open space development and the standard swimming pool setbacks make it very difficult for any of the properties within that development to comply with the current requirements; even if a very small pool is considered. The Sorrell Hill development is the only Single-family open space development within East Goshen Township.

The purpose of the Planning Commission's discussion on this matter is to discuss solutions that meet the spirit of the existing ordinance for swimming pools while taking into consideration the unique development type and reduced lot sizes permitted within a Single-family open space development. The current regulation requires that: Pools shall be located behind the building setback line and in no case shall the edge of water be closer than 25 feet to any lot line. This being said, each single family home in the Sorrell Hill development has its own lot lines within the boundary of the development.

Specifically, the Planning Commission will be considering options of how to amend the zoning ordinance so that swimming pools can be accommodated within Single-family open space developments. For example, requiring a minimum 25 foot swimming pool setback from the development boundary would be in keeping with the current zoning requirements and would not impact those residential uses which abut Single-family open space developments.

Pursuant to Township policy, I've sent this letter to all properties within 1000 feet of the Sorrell Hill Development.

The East Goshen Township Planning Commission will meet on Wednesday March 16, 2016 at 7:00 PM to discuss this matter.

All meetings are held at the Township Building and are open to the public. Information on this request is available for review during normal business hours. Please give me a call at 610-692-7171 or email me at mgordon@eastgoshen.org if you have any questions, need additional information or require special accommodations to participate in the meeting.

Sincerely,

Mark A. Gordon
Township Zoning Officer

Cc: All Township Authorities, Boards and Commissions
David R. Burman, Township Manager, Willistown Township (via E-mail Only)

F:\Data\Shared Data\Property Management\53-2\53-2-45.3 (905 Sorrell Hill)\1000 foot letter 03082016.doc

AREA CODE 610
692-7171

EAST GOSHEN MUNICIPAL AUTHORITY

EAST GOSHEN TOWNSHIP

1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

March 2, 2016

Mr. Donald Pusey
1636 Bow Tree Drive
West Chester PA 19380

Dear Mr. Pusey:

The East Goshen Municipal Authority is in the final phase of a series of projects to address the sewer needs of the Township. By way of background the sewage from those properties on public sewer in East Goshen Township is treated at one of three sewer treatment plants. The Authority has an agreement with West Goshen Township to treat 1 million gallons per day (MGD) at their plant. The Authority owns and operates the Ridley Creek Sewer Plant which has .75 MGD of capacity. The Authority also has an agreement with Westtown Township to treat the sewage from the Summit House and Cider Knoll Condominiums. In order to address our future sewer needs, the Authority may need to transfer sewage to the Ridley Creek Sewer Treatment Plant.

The Authority has contracted with Pennoni Associates to design a pump station that will transfer sewage to the Ridley Creek Sewer Treatment Plant. We are presently in the design and permitting stage of this project. At the present time we are under our limit at West Goshen and the construction of this pump station will not occur until the flow to West Goshen approaches 1 MGD. While we do not anticipate that this will happen in the near future, the Authority believes it prudent to have all of the plans and permits in place for the construction of the pump station, since our agreement with West Goshen imposes a significant financial penalty if we exceed 1 MCD for a specific period of time.

The pump station will be constructed on the Township property at the north-east corner of Reservoir Road and Strasburg Road. The force main would run east under East Strasburg Road to Misak Drive. It would then run under Misak Drive to the cul-de-sac. It would then follow the existing sewer easement between Misak Drive and Anne Drive. The force main would then run east under Anne Drive, crossing North Chester Road, then run under Bow Tree Drive to the Township open space. It would go around the north side of the pond, cross Ridley Creek and connect to the sewer line that runs between Bowtree and Cocktower.

The purpose of this letter is to advise you that Pennoni has concluded that the force main will have to cross the corner of your property that is next to the pond. This means the Authority would need to acquire an easement from you to install the force main. Attached is a copy of the easement plan for your review.

The Authority has engaged William Wood Associates to conduct an appraisal to determine the value of the easement. As part of the appraisal process they will be taking photographs of your property. Once the Authority it has received the appraisal, I expect that it will make you a formal offer to acquire the easement.

Please give me a call at 610-692-7171 or e-mail me at rsmith@eastgoshen.org if you have any questions.

Sincerely,

Louis F. Smith, Jr.
Township Manager

Enclosure

F:\Data\Shared Data\ABC'S\Municipal Authority\Projects\Reservoir Road PS\Concept Design\Letter to Residents 010915.doc

SANITARY SEWER EASEMENT PLAN

RESERVOIR ROAD PUMP STATION AND FORCE MAIN

RESERVOIR ROAD AT EAST STRASBURG ROAD
WEST CHESTER, PA

EAST GOSHEN MUNICIPAL AUTHORITY
1580 PAOLI PIKE
WEST CHESTER, PA 19380

EXHIBIT #1
SHEET 1 OF 1

Title Block and Metadata

Field Value
PROJECT EGMA1504
DATE 2016-01-27
DRAWING SCALE 1"=30'
DRAWN BY AMA
APPROVED BY JWH

0 30' 60'

ALL DOCUMENTS PREPARED BY PENNONI ASSOCIATES ARE INSTRUMENTS OF SERVICE IN RESPECT OF THE PROJECT. THEY ARE NOT INTENDED OR REPRESENTED TO BE SUITABLE FOR REUSE BY OWNER OR OTHERS ON THE EXTENSIONS OF THE PROJECT OR ON ANY OTHER PROJECT. ANY REUSE WITHOUT WRITTEN VERIFICATION OR ADAPTATION BY PENNONI ASSOCIATES FOR THE SPECIFIC PURPOSE INTENDED WILL BE AT OWNERS SOLE RISK AND WITHOUT LIABILITY OR LEGAL EXPOSURE TO PENNONI ASSOCIATES; AND OWNER SHALL INDEMNIFY AND HOLD HARMLESS PENNONI ASSOCIATES FROM ALL CLAIMS, DAMAGES, LOSSES AND EXPENSES ARISING OUT OF OR RESULTING THEREFROM.

50TH Pennoni
PENNONI ASSOCIATES INC.
Christiana Executive Campus
121 Continental Drive, Suite 207
Newark, DE 19713
T 302.655.4451
F 302.654.2895

LEGEND

  • TEMPORARY CONSTRUCTION EASEMENT
  • PERMANENT EASEMENT
  • FM FORCE MAIN

REVISIONS

NO. DESCRIPTION DATE BY

Plan Annotations

LANDS N/F
DONALD A. PUSEY
1636 BOW TREE DR.
TAX PARCEL #
53-4L-112

LANDS N/F
EAST GOSHEN TWP.
TAX PARCEL #
53-4L-18

  • PROPERTY LINE (TYPICAL)
  • 20' SANITARY SEWER EASEMENT
  • BOW TREE DRIVE
  • TWP. ROW
  • NORTH
  • (N 87°20'45" W - DEED)
  • N 86°19'22" E 163.84'
  • N 86°19'22" E 183.51'
  • N 43°23'54" E 45.08'
  • POB TCE
  • S 86°19'22" W 19.07'
  • POB PE
  • 5' MIN
  • 2.13'
  • S 08°25'08" E 16.56'
  • N 43°29'41" E 20.88'
  • S 08°25'08" E 14.24'
  • S 86°19'22" W 16.49'
  • FM

W:\PROJECTS\EGMA\EGMA1504-RESERVOIR RD PS DESIGN PERMITTING\DESIGN\V\EGMA1504-V-EXHIBIT1.DWG
PLOTTED: 1/27/2016 1:19:15 PM, BY: ANDREW ALCARO
PLOTSTYLE: PENNONI NCS.STB, PROJECT STATUS: ----

610-692-7171
www.eastgoshen.org

FYI

BOARD OF SUPERVISORS

EAST GOSHEN TOWNSHIP
CHESTER COUNTY
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

March 7, 2016

Dear Property Owner:

The purpose of this letter is to inform you that Tecniplast USA, owner of 1345 Enterprise Dr. West Chester, PA 19380, has submitted a request to amend their 2010 Conditional Use approval with regard to the required off street parking for their Multi-Use Building. The Township Board of Supervisors will entertain this request at their meeting on March 15, 2016.

Condition 3 of the approval allows the applicant to modify the amount of approved parking spaces so long as they demonstrate compliance with the ordinance. In 2011 the Township amended the Off Street Parking and Loading requirements for Multi Use Buildings and Tecniplast USA has demonstrated that they can meet the new requirements pursuant to condition 3 of the approval.

Pursuant to Township policy, property owners and residents within 1000 feet of the subject property are notified of these types of requests.

The meeting date and time scheduled for the review and discussion of this request is outlined below.

March 15, 2016 - Board of Supervisors meeting (7:00 pm)

More information on this request will be posted to the Township Website on Friday 3/11/2015 with the meeting agenda and packet at http://eastgoshen.org/boards/board-of-supervisors.

All meetings are held at the Township Building and are open to the public. Information on this request is available for review during normal business hours. Please give me a call at 610-692-7171 or email me at mgordon@eastgoshen.org if you have any questions, need additional information or require special accommodations to participate in the meeting.

Sincerely,

[Signature]

Mark A. Gordon
Township Zoning Officer

Cc: All Township Authorities, Boards and Commissions

F:\Data\Shared Data\Property Management\53-4\53-4-171 (1345 Enterprise Dr.)\CU Amendment 2016\1000 foot letter 03072016.doc

FYI

WEST GOSHEN SEWER AUTHORITY
REGULAR MEETING

March 2, 2016

The regular meeting of the West Goshen Sewer Authority was held on Wednesday, March 2, 2016 at the West Goshen Township Administration Building. Those present were:

Authority
Ron Rothrock
Dan Tierney
Theodore Murphy

Supervisor

Administration
Casey LaLonde
Dave Woodward
Mike Moffa

Unruh, Turner
Ross Unruh

Glace Associates, Inc.
Max Stoner

The regular meeting of the Authority was called to order at 7:30 P.M. by Vice-Chairman Ron Rothrock.

Dave Johnson and Phil Corvo were not in attendance. Ed McAssey from East Goshen was in attendance. Josh Fox from HRG, Inc. was in attendance.

Ed McAssey stated that East Goshen's plant was operating well. They have been doing some inspections and have found some manholes that need to be repaired or replaced.

Ted Murphy motioned to approve the February 3, 2016 meeting minutes, seconded by Dan Tierney motion approved.

Ron Rothrock mentioned that the Authority will need to have someone take over as Recording Secretary due to Tina resigning from the position. No one from the Authority was willing to take on the position so Casey LaLonde is going to check and see if anyone from the office staff would be interested in filling the position.

Mike Moffa gave the Wastewater Superintendent report, process model testing will begin on March 6. Josh Fox from HRG explained in more detail what the process model is for and how the data will be used.

Ross Unruh presented the Solicitor's Report for the month. The judge agreed to put the case in civil suspense and signed the order on 1/6/14. At this point all technical details for testing are being handled by Dan Smith, Max Stoner and John Scott in conjunction with EPA and DEP. DEP conducted monitoring/testing the stream and collecting data in three locations from 11/13 until 11/14. Lincoln Independence Park deeds have the wrong tax parcel #'s. The draft report from Dan Smith from Connestoga was received for the stream testing. The 3rd report was

1

sent/filed to EPA and River Keepers on 7/6/15. Authorities submission to the EPA was sent on 10/30/15 for the TMDL. The update to the EPA was sent 1/6/16. There will be a conference call 3/4/16 with Dan Smith, Ross, Max and Mike Moffa. A meeting is scheduled for Thursday, March 10, with EPA.
Ron Rothrock made a motion to authorize Steve Miano to have Count III of the Complaint dismissed, seconded by Dan Tierney, motion approved.

Ted Murphy made a motion that Ross Unruh record the right of ways for Lincoln Independence Park, seconded by Dan Tierney, motion passed.

Dan Tierney made a motion to approve the proposed budget for 2016, seconded by Ted Murphy, motion approved.

Ron Rothrock made a motion to accept the capitalization policy for the West Goshen Sewer Authority, seconded by Ted Murphy, motion approved.

Max Stoner gave the Engineers report dated March 2, 2016: (See report for details)

  1. Current Items Goose Creek Stream Study/TMDL Permit Issues The TMDL issues are continuing on. Sampling is being done by the plant staff. Conference call 3/18/15 with new EPA representative. Algae testing done 4/17/15. Received raw data from testing DEP conducted. GHD is conducting a stream walk and habitat survey.; Capital Expenditure Schedule Have reviewed the report from HRG and a summary of initial review was done. Meeting was held on 2/16 at the plant & Woodcrest PS; Methane Gas Burner GEM Mechanical installed the boiler. There is oil leaking from the new boiler, as well as the valve being propped up with 2x4's. Has yet to be repaired by GEM Mechanical.; Structural Review of STP Buildings & Tanks The secondary anaerobic digester cover to be replaced and a new roof with new flashing be placed on the operations building. Membrane roof on Ops building. Bid plans and specs should be prepared for the projects should be completed over the winter and work should be done in late spring or summer of 2016. Dan Swartz provided a scope of work and proposal of $9,800.00 to design drawings and specifications.; Secondary Digester Cover – a budget proposal was received from the manufacturer's rep for the Dystor cover, it was $500,000 for the supplier to install or $300,000 for the material plus a contractor installation cost. HRG report suggested switchover to aerobic digestion process, this should be evaluated in further detail.; Operations Building Roof Replacement A manufacturer's rep from Firestone visited the site in mid-November to provide recommendations to replace the existing roof. Should

2

be done regardless of the type of digestion process selected.

  1. Sludge Dewatering Project Two budgetary prices were received last month.
  2. Emergency Generator & Storage Tanks at WWTP A firm was called in to test the storage tanks on-site and to recommend what steps should be taken to upgrade the facilities to today’s standards. The tank is not leaking and can either be abandoned or removed. The emergency generator was recently serviced and was placed in full load, found to be in good operating condition and parts are still available. The staff and consultants are looking at several scenarios including possibly installing two smaller generators rather than a single large one.
  3. Downing Avenue (Woodcrest Area) Pumping Station #10 Obtained budget pricing from several manufacturers to provide a suction lift pumping station with a small building.
  1. Developments – See Engineers Report Shadeland Woods (29 & Boot); Woodlands at Graystone (Jerrehian Large Tract); Goshen Leisure Development (6 bldgs. N. Hagerty) – waiting on escrow money; Lincoln Independence Park (831 Lincoln Ave); Arbours at West Goshen (Ward Ave); Jerrehian (3 lot); Wexford Mews (Wexford/Kirkland); 825 Goshen Road (Zarelli); 415 Goshen Road (Gavin); Liberty Tools (Saunders Ln); Kirkland Woods (Kirkland/Ashbridge); Traditions of West Goshen (Boot Rd); Pica Restaurant (Rt3); Summit Realty (Rt3 & Five Pts); Laurel Ridge (Glen White 1320 Pottstown Pk); Arbours Square West Goshen; 702 Old Westtown Road; West Chester University; Ice Line/Howell (700 Lawrence)

Ted Murphy would like to have HRG do all the engineering work for projects that need to be done throughout the West Goshen Wastewater System due to the past record of Glace and Associates, Ron Rothrock feels as though Glace is the engineer of record for the Sewer Authority and they should do the work. Mike Moffa, Wastewater Superintendent, was asked what his preference in the matter is and Mike stated that he would like to have HRG do all the work for the treatment plant, pump stations and collections. He stated that Glace has been the engineer for many years and he appreciates all the work they have done but he feels HRG is very knowledgeable and he is happy with the work and insight they have provided to this date.

3

Final Clarifier #3 – Ted Murphy made a motion to authorize Evans Engineering to prepare plans and specifications for $9,800 pending inspection of the tank once it is drained, seconded by Dan Tierney, motion approved.

Grit System – Josh Fox said they are leaning towards the Grit King, a final design should be completed in a week to week and a half.

Transformer and Generator – Steve from Brandywine Electrical informed Max that Peco would be responsible for the maintenance of the transformers. The electric cost at the plant would be cheaper for the township however more for the pump stations due to less usage. The township and/or authority would be responsible for paying for an electrician for the work and any labor that is done by the treatment plant employees. Max said he is waiting to receive Peco’s cost analysis on replacing the transformer at the plant. The refined concept for the treatment plant generator replacement would be two generators as well as a transfer switch. Ron Rothrock would like to see a detailed plan with cost estimates for the generator replacement before agreeing to have HRG move forward. Josh from HRG, that an agreement would need to be approved at the April meeting to have the generator work move forward without any delays.

Ted Murphy stated that the TMDL issue is not a reason to delay every repair or replacement because not everything encompassed would affect the TMDL.

Ted Murphy made a motion to approve the transformers at Westtown Way Pump Station and Washington Street Pump Station, seconded by Dan Tierney, motion passed.

Collection System – Ron would like to have a better idea of where we are with collections system inspection project and would like to see a plan of what is going to be done.

Ron Rothrock motioned to authorize HRG to design the manholes for the sewer line from Westtown Township to the sewer plant, and to prepare the bid package for replacement of three manholes, rehabilitation of one and the lining of the pipes, seconded by Ted Murphy, motion passed.

Downing Pump Station (#10) – a suction lift pumping station with a small building to upgrade the station is what has been determined.

Ron Rothrock made a motion to authorize Glace & Associates to prepare preliminary design, obtain permitting from the required governmental agencies and prepare final design which shall include a bid package for the Authorities action at a future meeting, seconded by Dan Tierney. Motion was passed unanimously however Ted Murphy does not agree with Glace & Associates doing the work.

4

The following invoices were moved for approval by Ron Rothrock, seconded by Ted Murphy and unanimously approved:

ADMINISTRATIVE EXPENSES:

PAYEE PURPOSE AMOUNT
Unruh General Representation $ 3,643.00
Tina Charron 1st quarter – Recording Secretary $ 270.00
Dan Tierney 1st quarter – Treasurer
Supplies - Treasurer
$ 250.00
$ 392.14

DEVELOPER ACCOUNTS:

PAYEE DEVELOPER AMOUNT
Unruh Lincoln Independence Park $ 100.00
Unruh Arbours @ West Goshen Ph.2 $ 80.00
$

On a motion by Ron Rothrock and seconded by Ted Murphy, the following requisitions were approved for payment.

TAPPING FEE FUND:

REQUISITION # PAYEE PURPOSE AMOUNT
1703 Glace & Associates TMDL
Upgrade Dewatering Facil.
P.S. #10 - Woodcrest
Coordinate w/ Township
Upgrade Authority Drawings
$ 1,368.75
1,127.50
3,337.44
6,307.50
8,994.50
1702 Unruh, Turner, Burke & Frees TMDL $ 2,360.00
1701 Hangley TMDL $ 2,962.50

5

Resident Shaun Walsh would like to think it would be beneficial to keep things on a scheduled plan to keep things up to date as to not have this happen again as far equipment being outdated and in need of repair.

FULTON FINANCIAL BALANCES (as of January 31, 2016)
Total all accounts - $ 6,335,752.87

There being no further business, on a motion by Dan Tierney seconded by Ted Murphy, the meeting was adjourned at 9:09 p.m.

Respectfully submitted,

Tina Charron, Recording Secretary

6

2016 PMAA Spring
Management Workshops

East & West locations for traveling convenience

Hotel Hershey
Hershey, PA
Wednesday, April 13, 2016

Nemacolin Woodlands
Farmington, PA
Wednesday, April 20, 2016

Tentative Agenda

Attention Engineers:
Earn 3 PDHs for attending this workshop!

8:15 - 9:00 Registration/Welcome 9:00 - 9:30 PMAA Legislative/Regulatory Update Government Relations staff will address recent legislative and regulatory issues impacting authorities. This includes environmental bills, bills amending the Municipality Authorities Act, and financial bills. An update will be provided on proposed drinking water regulations, water quality issues, and the re-boot of the Chesapeake Bay program in PA (east location only). 9:30 - 10:15 DEP Regulatory Update Representatives of the PA Department of Environmental Protection (DEP) and will present both water and wastewater regulatory updates. These updates will include information on pending revisions to the Consumer Confidence Reports (CCR) and other drinking water and wastewater regulations. 10:15 - 10:30 SRBC Update (East Location Only) SRBC presenter will provide guidance to Authority managers and consultants in selecting and overseeing hydrogeologic consultants that will be doing work related to the Commission’s regulatory requirements. They will also cover the selection process (including interviewing multiple consultants), Authority board review of work proposed and completed by the hydrogeologist to meet the Commission’s regulatory requirements, and invoice review. 10:30 - 11:00 Are Confined Spaces Hidden at Your Facility? At an Authority facility, confined spaces can be present, which often can present a hazard to untrained employees. In fact, injury rates and falls can often be double or triple the rate of the private sector facilities. The presenter will address statistics and describe real-life confined space studies. A review of related private sector OSHA regulations, equipment options and inspection breakdowns will also be included. Presenter will also address written confined space programs, air monitoring and rescue plans. 11:00 - 11:30 The Bigger, Better COSTARS Program -Update, Overview & Training PA public authorities spent more than $91million using the COSTARS Program in FY 2014, saving local taxpayers more than $18 million. The presenter will provide an overview of the program, an update of COSTARS & State Contracts, and will include step-by-step instruction on how to access, read, and utilize state & COSTARS contracts. 11:30 – 12:30 Delinquencies Panel Panel of authority managers, solicitors and consultants will address the various tools and methods available to authorities in dealing with the ever-present, problematic delinquent ratepayers every system encounters. 12:30 - 1:00 Solicitors Update PMAA solicitors will address recent litigation involving Pennsylvania municipal authorities. 1:00 - 2:00 Lunch

Pennsylvania Municipal Authorities Association
1000 North Front Street, Suite 401, Wormleysburg, PA 17043
(717) 737-7655 ● (717) 737-8431 Fax ● email: info@municipalauthorities.org ● www.municipalauthorities.org

FYI

#3020
BOD, Metabolism, Sludge Production and ORP

#3562
Microbiology of Anaerobic Digesters

You should attend if you are a:
Certified wastewater operators
technicians
engineers.

Course Description

First Part: This course reviews the different types of BOD and their impact upon the treatment process, (DO demand, nutrient demand, etc.) the different types of metabolism or degradation of BOD (aerobic, anoxic and anaerobic), and their consequences such as permit compliance or violation and treatment upset; sludge production and factors affecting sludge production and ORP as an operational tool to monitor and regulate bacterial activity (metabolism).

The second half: of the course reviews five areas of concern related to the microbiology and successful operation of anaerobic digesters, including causes and corrective operational measures for foam and scum production.

We hope to see you there!

Instructor: Michael Gerardi

Wastewater Microbiologist

Michael has developed and offered numerous wastewater biology courses in the United States, Canada, Caribbean and Europe. He has over 35 years experience in the wastewater treatment profession and has authored seven wastewater microbiology texts for John Wiley and Sons. He has performed microscopic analyses of wastewater samples and provided troubleshooting services for numerous municipal and industrial wastewater treatment facilities. He managed the Williamsport Sanitary Authority wastewater treatment facilities for 10 years.

Topics to be Covered:

  • Descriptions, sources and impact of BOD, cBOD, soluble cBOD, nBOD, colloidal BOD and particulate BOD
  • Descriptions, occurrence and consequences of aerobic, anoxic and anaerobic conditions
  • Comparison of domestic and industrial wastewater
  • Roles of aerobic and anearobic digesters
  • Factors contributin to increase/decrease in sludge production
  • Description and use of ORP for process control
  • Bacteria involved in degradation of soluble, colloidal and particulate BODs
  • Acceptable operating conditions
  • BODs compatible for anaerobic digestion
  • Upset conditions commonly experienced with anaerobic digesters
  • Troubleshooting and process control measures

Event Details

When:
April 12, 2016
8:00 am - 4:00 pm
(Registration 7:30 am)
Lunch Provided

Where / Class Location:
Holiday Inn Lansdale
1750 Sumneytown Pike
Kulpsville, Pa 19443
Montgomery County

A street map showing the location of Holiday Inn Lansdale on Sumneytown Pike near Kulpsville, Bustard Rd, Towamencin Ave, and Forty Foot Rd.

Driving Directions

From I-476: Take Lansdale Exit 31 off of Interstate 476. Make left on to Sumneytown Pike and Hotel is on the right.

Questions:

Contact the PRWA Office at (814) 353-9302 Ext. 107 or 108
Fax (814) 353-9341

We are now active on these Social Media Websites:
Find us on Facebook: Search: Pennsylvania Rural Water Association
Twitter: Search: PA Rural Water

610-692-7171
www.eastgoshen.org

FYI

BOARD OF SUPERVISORS

EAST GOSHEN TOWNSHIP
CHESTER COUNTY
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

February 22, 2016

Dear Property Owner:

The purpose of this letter is to inform you that T. Richard Moser Land Developers LP, equitable owner of 943 Cornwallis Dr., West Chester, PA 19380, has submitted a Subdivision Application for the property at 943 Cornwallis Drive, West Chester, PA 19380. The plan proposes to subdivide the 2.6 acre lot into two residential building lots.

Pursuant to Township policy, property owners and residents within 1000 feet of the subject property are notified of subdivision application submissions.

The application and plan will be reviewed and discussed at the following meetings:

  • March 2, 2016 - Planning Commission Meeting (7:00 pm)
  • March 9, 2016 - Conservancy Board (7:00 PM)
  • March 14, 2016 - Municipal Authority (7:00 PM)
  • April 6, 2016 - Planning Commission (7:00 PM)
  • April 19, 2016 - Board of Supervisors (7:00 PM)

All meetings are held at the Township Building and are open to the public. The meeting dates and times above are subject to change without further written notice to surrounding property owners. The plans and application are available for public review at the Township building during normal business hours. Please give me a call if you have any questions, need a special accommodation to participate in the meeting or if need additional information.

Sincerely,

[Signature]

Mark A. Gordon
Township Zoning Officer

Cc: Township Authority, Boards and Commissions

F:\Data\Shared Data\Property Management\53-4\53-4-57 (943 Cornwallis Dr.)\2016 SD Application\1000 foot letter SD Plan 02192016.doc

Register Now!

FYI

Register Now!

2016 PMAA Board Member Training

Central Location
Thursday, March 3
Radisson Hotel Harrisburg
1150 Camp Hill Bypass
Camp Hill, PA 17011

East Location
Thursday, March 10
Holiday Inn
Allentown – I-78
7736 Adrienne Drive
Breinigsville, PA 18031
(Fogelsville Exit on I-78)

West Location
Thursday, March 17
Doubletree by Hilton
Pittsburgh, Cranberry
910 Sheraton Drive
Mars, PA 16046

Schedule: 8:30 – Registration   9:00 – 1:00 – Program   1:00 – Luncheon

Are you a “new” Authority Board Member appointed this year or in recent years? Are you a veteran Board Member ready for a refresher on the wide landscape of responsibilities in which you have been entrusted? Perhaps you are an Authority professional or consultant guiding your Board through these responsibilities.

These training sessions are specially designed to provide a broad overview of key powers, duties, and responsibilities for Authority Board Members. Session presentations will include:

  • Government Relations Update. What are the latest laws, regulations, and legislative proposals impacting your Authority’s operations, implementation issues and costs?
  • Municipality/Authority Relations. You have been appointed to lead an autonomous entity charged with providing a vital service to the community. Sometimes other Municipal needs may conflict with Authority responsibilities. Learn where Municipality/Authority cooperation can be mutually beneficial, and where gray areas may lead to complicating issues.
  • Authority Finance. From day to day cash management to various financing options, Board Members must stay abreast of financial practices and fiscal responsibilities of your Authority’s operations.
  • Understanding the Key Elements of Public Official Ethics. Attorneys from the Ethics Commission will provide an overview of ethical standards and recent Ethics Commission rulings impacting Municipal Authority officials.
  • Municipal Solicitors’ Panel. Local solicitors will address attendees on various issues and topics including the Municipality Authorities Act, developer agreements, and the Open Records Act. Attendees are urged to come prepared with questions for the panel. This segment of the program has been approved for PA CLE and municipal solicitors are encouraged to attend.

See other side for registration form.

Pennsylvania Municipal Authorities Association
1000 North Front Street, Suite 401, Wormleysburg, PA 17043
717-737-7655 ✱ Fax: 717-737-8431 ✱ info@municipalauthorities.org ✱ www.municipalauthorities.org ✱ February 17, 2016