Municipal Authority
The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.
The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.
- Five members, serving five-year terms
- Meetings are on the 2nd Monday of the month at 7:00 P.M.
- All township meetings are held at the Township Building and open to the public
| Authority Members | Term Expiration Date |
| Kevin Cummings, Chairman | 2026 |
| John Stipe, Vice Chairman |
2029 |
| Dana Pizzarro, Secretary | 2026 |
| Sean Ellsworth, Assistant Secretary/Treasurer | 2028 |
| Walter Wujcik, Treasurer | 2028 |
| Pennoni Associates, Engineer | |
| Patrick M. McKenna, Esq. | |
| Peter Hicks, BoS Liaison | |
| Kevin Miller, Staff Liaison |
Documents
Back to the list | Open the original PDF
Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.
EAST GOSHEN MUNICIPAL AUTHORITY
April 11, 2016
7:00 PM
- CALL TO ORDER/PLEDGE OF ALLEGIANCE/MOMENT OF SILENCE Ask if anyone will be taping the meeting?
- CHAIRMAN’S REPORT/OTHER MEMBERS REPORTS
- SEWER REPORTS Director of Public Works Report; Pennoni Engineer’s Report; Big Fish Environmental Inc. Report with DMR’s
- APPROVAL OF MINUTES March 14, 2016
- APPROVAL OF INVOICES a. William Wood Company $1,000.00 has been paid b. Gawthrop Invoice #142725 $1,523.50 has been paid c. Pennoni Invoice #682656 $1,576.25 d. Pennoni Invoice #682703 $2,396.50 e. Pennoni Invoice #682658 $1,955.75 f. Pennoni Invoice #682659 $ 778.00 g. Pennoni Invoice #682660 $ 761.75 h. Pennoni Invoice #682661 $2,996.25
- LIAISON REPORTS
- FINANCIAL REPORTS March 2016 Report
- OLD BUSINESS
- GOALS Operate the Ridley Creek Sewer Treatment Plant in compliance with NPDES Permit requirements. January, February; Continue to implement the formal Inflow (surface water) & Infiltration (ground water), (collectively “I&I”) Plan to reduce the amount of I&I into the sewer system.
F:\Data\Shared Data\Agendas\Municipal Authority\2016\4-11-16.doc
- Respond to capacity requests within 45 days. Develop an operation manual for Ridley Creek Sewer Treatment Plant and pump stations. 943 Cornwallis Drive
- Submit topical articles of interest for the East Goshen newsletter.
- Attend West Goshen Municipal Authority meetings to keep informed of planned capital expenditures and operation compliance. January, February
- NEW BUSINESS Act 537Application for Exemption for 943 Cornwallis Drive; Force Main Reservoir Road Pump Station; Increase Manhole Lining Budget
- CAPACITY REQUESTS
- ANY OTHER MATTER
- CORRESPONDENCE AND REPORTS OF INTEREST
- PUBLIC COMMENT
- ADJOURNMENT
F:\Data\Shared Data\Agendas\Municipal Authority\2016\4-11-16.doc
AREA CODE 610
692-7171
EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199
April 8, 2016
To: Municipal Authority
From: Mark Miller
Re: March 2016 Monthly Report
Monthly Flows: The average daily flow to West Goshen was 872,000.
Meters: The meters have been read on a daily basis. The portable meters have been installed at various locations in the Township.
Chester Creek Pump: The pumping stations were visited on a routine basis with no problems to report.
Hunt Country Pump: Was visited on a daily basis. I ordered the equipment for the wet well. I have been working with MGK Inc. on scheduling the wet well work.
C.C. Collection: We were notified of sewer lateral backup at 1517 Brian Drive, we found the trap stack full; the crew plunged the lateral and cleared the blockage. We televised the lateral but we were not able to get to the main. It was decided that we excavate the lateral and install a cleanout. We had another lateral clog on Christine Lane when a tree fell and crushed the cleanout stand pipe. We were able to get the line open however; the home owner will have to get a plumber to install a new trap and cleanout. We televised the "A" portion on Eastwick Circle.
R.C. Collection: We completed the repairs on the collection system.
R.C. Plant: We finished the re-piping of the utility water pit and installed the rebuilt pump. Scott had sent me a list of items that needed repairs and parts lists.
Lockwood Plant: The monitoring wells have been sealed as required by the County. The only items we have left are the removal of some spray heads and fencing.
Alarms: We responded to 16 alarms for March.
PA One Calls: We received 55 Pa One calls March.
EGMA 1601
Pennoni
MEMORANDUM
TO: East Goshen Municipal Authority Board
Rick Smith, Township Manager
FROM: Michael Ellis, P.E.
Authority Engineer
DATE: April 8, 2016
SUBJECT: Engineer’s Report
Invoices
- Invoices with summaries are provided under separate cover.
Ridley Creek Sewage Treatment Plant (RCSTP)
- The NPDES Permit expires on February 28, 2017. The permit renewal application is due to PADEP by September 1, 2016. We anticipate initiating work on the renewal application within the next two weeks.
Reservoir Road Pump Station
- PADEP previously issued the permits for the Ridley Creek GP-5 “Utility Line Stream Crossings” and GP-8 “Temporary Road Crossings (across streams)” and for the pump station site floodplain filling work.
- We are still awaiting PADEP response for the Chester Creek Small Projects Joint Permit for the pump station site and Chester Creek utility crossing.
- PPL-IES approved the petroleum pipeline crossing. Approvals were already received from Williams-Transco and Sunoco. All pipeline companies have now approved the proposed crossings.
- The PennDOT Highway Occupancy Permit application for force main construction along and across E. Strasburg Road and Rt. 352 was resubmitted to address comments from our field meeting with PennDOT representatives. PennDOT reviewed and provided additional comments that we are in the process of addressing.
- The NPDES Permit application was submitted to the Chester County Conservation District on March 21, 2016.
- The Water Quality Management Permit application will be submitted to PADEP on April 8, 2016.
Page 1 of 2
P:\Projects\EGMA\Memos to Board\2016\Memo to EGMA Board 2016-04-08.docx
EGMA 1601
- The tentative schedule follows: Estimated Date Submitted PADEP GP and JP Permit applications November 19, 2015 Submitted NPDES Permit application March 21, 2016 Submit PADEP WQM Permit application April 8, 2016 Resubmit PennDOT HOP application by April 15, 2016 PennDOT Permit issuance Late April 2016 PADEP and CCCD Permit issuances June-July 2016
RCSTP and Pump Stations’ O&M Manual
- We continued preparation of the Sewer System Operations and Maintenance (O&M) Manual including reformatting to address comments from the Township Manager.
Sanitary Sewer Manhole Rehabilitation
- We have evaluated alternative manhole interior rehabilitation products and set up a field visit with the PW Department to observe an alternative product for equivalency.
Chapter 94 Reports
- The Ridley Creek STP and West Goshen Service Area Reports were completed and submitted to PADEP on March 30, 2016. The Westtown Service Area Report was completed and submitted to Westtown Township on March 25, 2016.
Page 2 of 2
P:\Projects\EGMA\Memos to Board\2016\Memo to EGMA Board 2016-04-08.docx
Big Fish Environmental Services Inc.
Ridley Creek Sewage Treatment Plant
Monthly Operations Report: March 2016
Executive Summary
The Ridley Creek sewage treatment plant outfall 001 achieved compliance with the NPDES discharge permit during February 2016. Discharge to Applebrook was discontinued during February. Chemical usage utilized for total phosphorus removal, pH and total alkalinity remained consistent with previous months. The sludge grinder was observed to periodically become clogged with “rags and debris.’ The grinder and sludge pump were disassembled several times during the month to remove “rags” and debris. The grinder will be removed for installation of a head and shear plate assembly. No mechanical or operational issues were observed regarding the centrifuge sludge dewatering equipment.
Treatment Process Operation
During February 2016, there were no exceedances of the final effluent discharge limitations for outfall 001. Additional TSS samples were collected twice per week to allow for a means to calculate a weekly average. The total phosphorus monthly average concentration of 0.23 mg/L as compared to the permitted limitation of 0.50 mg/L. Table 1 illustrates the final effluent composite sample data reported for the February 2016 eDMR.
Table 1
February 2016 - Final Effluent - Out Fall 001
| NPDES Permit Discharge Limitations | Flow | CBOD5 | TSS | NH4-N | Phosphorus,Total , mg/L | Fecal Coliform | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | Geo Mean | Geo Mean | |
| Discharge Limitations | 0.75 | 20 | 125 | 10 | 131 | 7 | 44 | 0.5 | 3 | 200 | 1,000 |
| Instantaneous Maximum | 40 | 42 | |||||||||
| Sample Date | |||||||||||
| February 2, 2016 | 0.409 | 2.9 | 9.9 | 4 | 14 | 7.09 | 24.18 | 0.21 | 0.72 | 1 | 0.0000 |
| February 5, 2016 | 0.559 | 1 | 5 | ||||||||
| February 9, 2016 | 0.390 | 2.0 | 6.5 | 1 | 3 | 3.40 | 11.06 | 0.18 | 0.59 | 2 | 0.3010 |
| February 12, 2016 | 0.491 | 1 | 4 | ||||||||
| February 16, 2016 | 0.699 | 2.0 | 11.7 | 2 | 12 | 3.38 | 19.70 | 0.16 | 0.93 | 1 | 0.0000 |
| February 18, 2016 | 0.413 | 3 | 10 | ||||||||
| February 23, 2016 | 0.432 | 2.4 | 8.6 | 5 | 18 | 3.044 | 10.97 | 0.10 | 0.36 | 1 | 0.0000 |
| February 25, 2016 | 0.577 | 3 | 14 | ||||||||
| Average | 0.496 | 2.3 | 9.2 | 3 | 10 | 4.229 | 16.48 | 0.16 | 0.65 | 1 | 0.0753 |
| Minimum | 0.390 | 2.0 | 6.5 | 1 | 3 | 3.044 | 10.97 | 0.10 | 0.36 | 1 | 0.0000 |
| Maximum | 0.699 | 2.9 | 11.7 | 5 | 18 | 7.090 | 24.18 | 0.21 | 0.93 | 2 | 0.3010 |
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 1 of 6
Big Fish Environmental Services Inc.
Ridley Creek Sewage Treatment Plant
Monthly Operations Report: March 2016
Discharge to Applebrook, Outfall 002, continued to remain off line during February 2016. Table 2 illustrates the influent composite sample data reported for the February 2016.
Table 2
February 2016 - Influent Wastewater
| Design Basis | Flow | BOD5 | TSS | NH4-N | TKN, mg/L | Phosphorus,Total, mg/L | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | |
| Design Basis | 335 | 2,098 | 320 | 2,001 | 32 | 200 | 48 | 301 | 9.1 | 57 | |
| Sample Date | |||||||||||
| February 2, 2016 | 0.495 | 272 | 1,124 | 196 | 810 | 30.1 | 124 | 42.2 | 174 | 5.7 | 24 |
| February 9, 2016 | 0.488 | 193 | 797 | 122 | 504 | 23.7 | 98 | 36.7 | 149 | 3.9 | 16 |
| February 16, 2016 | 0.961 | 179 | 739 | 186 | 768 | 31.6 | 131 | 38.6 | 309 | 4.0 | 17 |
| February 23, 2016 | 0.543 | 164 | 677 | 346 | 1,429 | 25.9 | 107 | 31.2 | 141 | 3.9 | 16 |
| Average | 0.622 | 202 | 834 | 213 | 878 | 27.8 | 115 | 37.2 | 194 | 4.4 | 18 |
| Minimum | 0.488 | 164 | 677 | 122 | 504 | 23.7 | 98 | 31.2 | 141 | 3.9 | 16 |
| Maximum | 0.961 | 272 | 1124 | 346 | 1429 | 31.6 | 131 | 42.2 | 309 | 5.7 | 24 |
Table 3 presents the available Outfall 001 final effluent data for the month of March 2016. During March, the presence of foam conditions on the surface of the SBRs remained consistent with the previous month with foam concentrations ranging from 25% to 60% of the area. This is attributed to decreasing water temperatures supporting conditions for growth of filamentous bacteria. Increasing the F:M ratio and decreasing MLSS concentrations is employed to assist in managing the increase in filamentous growth.
During March, there are no anticipated exceedances of the permitted limitations for Outfall 001. There was no discharge from outfall 002. Split sampling of the composite sample collected by Applied Laboratory Services (ALS) is ongoing for comparative analysis and daily results.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 2 of 6
Big Fish Environmental Services Inc.
Ridley Creek Sewage Treatment Plant
Monthly Operations Report: March 2016
Table 3
March 2016 - Final Effluent - Out Fall 001
| NPDES Permit Discharge Limitations | Flow | CBOD5 | TSS | NH4-N | Phosphorus,Total , mg/L | Fecal Coliform | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | Geo Mean | Geo Mean | |
| Discharge Limitations | 0.75 | 20 | 125 | 10 | 131 | 7 | 44 | 0.5 | 3 | 200 | 1,000 |
| Instantaneous Maximum | 40 | 42 | |||||||||
| Sample Date | |||||||||||
| March 1, 2016 | 0.403 | 2.6 | 8.7 | 4 | 13 | 3.48 | 11.70 | 0.24 | 0.81 | 1 | 0.0000 |
| March 3, 2016 | 0.425 | 2 | 7 | ||||||||
| March 8, 2016 | 0.398 | 2.6 | 8.6 | 3 | 10 | 0.250 | 0.83 | 0.18 | 0.60 | 1 | 0.0000 |
| March 10, 2016 | 0.339 | 2 | 6 | ||||||||
| March 15, 2016 | 0.384 | 2.4 | 7.7 | 4 | 13 | 0.146 | 0.47 | 0.20 | 0.64 | 1 | 0.0000 |
| March 17, 2016 | 0.406 | 1 | 3 | ||||||||
| March 22, 2016 | 0.341 | 0.26 | 0.74 | ||||||||
| March 24, 2016 | 0.311 | ||||||||||
| March 29, 2016 | 0.351 | 0.27 | 0.79 | ||||||||
| March 31, 2016 | 0.302 | ||||||||||
| Average | 0.366 | 2.5 | 8.4 | 3 | 9 | 1.292 | 4.33 | 0.23 | 0.71 | 1 | 0.0000 |
| Minimum | 0.302 | 2.4 | 7.7 | 1 | 3 | 0.146 | 0.47 | 0.18 | 0.60 | 1 | 0.0000 |
| Maximum | 0.425 | 2.6 | 8.7 | 4 | 13 | 3.480 | 11.70 | 0.27 | 0.81 | 1 | 0.0000 |
The influent wastewater pollutant concentrations and loading entering the wastewater treatment facility remained within the design concentrations. Composite samples are collected at the influent doghouse manhole and influent wet well. The influent flow meter reading is collected from the influent flow meter located prior to the Screening Building, excluding the internal recycle flows.
Table 4 presents the available pollutant data for the influent wastewater collected at the doghouse manhole during March 2016.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 3 of 6
Big Fish Environmental Services Inc.
Ridley Creek Sewage Treatment Plant
Monthly Operations Report: March 2016
Table 4
March 2016 - Influent Wastewater
| Design Basis | Flow | BOD5 | TSS | NH4-N | TKN, mg/L | Phosphorus,Total, mg/L | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | |
| Design Basis | 335 | 2,098 | 320 | 2,001 | 32 | 200 | 48 | 301 | 9.1 | 57 | |
| Sample Date | |||||||||||
| March 1, 2016 | 0.518 | 104 | 449 | 73 | 315 | 27.7 | 120 | 35.5 | 153 | 2.9 | 13 |
| March 8, 2016 | 0.512 | 147 | 635 | 168 | 725 | 30.9 | 133 | 35.9 | 153 | 4.3 | 19 |
| March 15, 2016 | 0.520 | 138 | 596 | 420 | 1,813 | 24.7 | 107 | 29.6 | 128 | 3.2 | 14 |
| March 22, 2016 | 0.461 | ||||||||||
| March 29, 2016 | 0.446 | ||||||||||
| Average | 0.491 | 130 | 560 | 220 | 951 | 27.8 | 120 | 33.7 | 145 | 3.5 | 15 |
| Minimum | 0.446 | 104 | 449 | 73 | 315 | 24.7 | 107 | 29.6 | 128 | 2.9 | 13 |
| Maximum | 0.520 | 147 | 635 | 420 | 1813 | 30.9 | 133 | 35.9 | 153 | 4.3 | 19 |
Sequencing batch reactors (SBRs) numbered 1, 3 and 4 were in service during February and March. Preparations to place SBR 2 were initiated during late March. The SBR is scheduled to be placed in service during April. Process monitoring of each SBR included ammonia as N, nitrite as N, Nitrate as N, COD, SSV, MLSS and total phosphorus. Daily analysis of the final effluent flow equalization grab sample is total phosphorus is ongoing. Sample collection and analysis of the influent wastewater collected at the influent pump station wet well is ongoing.
Addition of aluminum sulfate solution to the SBRs to assist with phosphorus removal continued. The volume of aluminum sulfate solution to the SBRs creased to from 70.3 gpd to 73.0 gpd. Soda ash daily addition increased from 417 lbs./day to 452 lbs./day. Soda ash assists towards maintaining SBR pH concentrations above 7.0 standard units and assists to replenish alkalinity consumed during the nitrification process and aluminum sulfate solution addition.
SBR No. 2 remains out of service as a treatment unit. Minor repairs will be scheduled during April. Repairs include:
- Repair alum piping within SBR
- Replace two (2) decanter valves
- Reinstall dissolved oxygen probe
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 4 of 6
Big Fish Environmental Services Inc.
Ridley Creek Sewage Treatment Plant
Monthly Operations Report: March 2016
Solids Dewatering and Disposal: March 2016
| Sludge Dewatering Summary | |
|---|---|
| Gallons of sludge dewatered | 282,595 |
| Number of dumpsters | 5 |
*Eighteen (18) days of centrifuge operation
Flow data:
| March 2016 | |||
|---|---|---|---|
| Flow Meter Location | Total Volume for Month, MG | Average Daily Flow, gpd | Daily Maximum Flow, gpd |
| Influent Wastewater to Screening Building* | 15.425 | 497,572 | 732,790 |
| Influent Wastewater to SBRs | 15.081 | 486,478 | 632,384 |
| Internal Recycle | 0.604 | 19,480 | 256,063 |
| Treated Effluent to Disc Filters | 14.884 | 480,130 | 636,480 |
| Final Effluent Discharge | 11.729 | 378,355 | 519,000 |
| Applebrook Golf Course | No Discharge | No Discharge | No Discharge |
Chemical Usage:
| March 2016 | ||
|---|---|---|
| Chemical | Daily Average | Total Monthly |
| Soda Ash | 452 | 13,100 |
| Aluminum Sulfate solution | 73.0 | 2,263 |
| Polymer (centrifuge) | 0.84 | 19.32 |
*twenty three (23) days of centrifuge operation
During March, sludge wasting to the sludge holding tanks and decanting of the sludge holding tanks was ongoing. Process monitoring included pH, total alkalinity and total solids.
Sludge holding tank No. 1 was in service. The level transducer is out of service. The level transducer is scheduled for replacement during April. The level transmitter will be changed from pressure level sensor to an ultra-sonic level sensor. The average total solids concentration was 0.82%. The average pH was 5.76 S.U. with an average total alkalinity of 50 mg/L. Zero gallons of supernatant were decanted during the month. 500 pounds of soda ash were added.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 5 of 6
Big Fish Environmental Services Inc.
Ridley Creek Sewage Treatment Plant
Monthly Operations Report: March 2016
Sludge holding tank No. 2 was in service. The level at the beginning of the month was 9.88 feet and the level at the end was 9.30. The average total solids concentration was 0.94%. The average pH was 6.86 S.U. with an average total alkalinity of 155 mg/L. Zero pounds of soda ash were added. Zero gallons of supernatant were decanted.
PA DEP
No activity
Significant Storm/Hydraulic Loading Events
During March, there were three (3) storm events resulting in a daily precipitation amount equal to or greater than 0.4 inches measured during a 24 hour period. A total of 2.45 inches of rainfall were measured during the month. These events occurred on the following dates:
- March 13 th : 0.79 inches
- March 14 th : 0.78 inches
- March 27 th : 0.42 inches
Plant operations were adjusted to manage the precipitation to prevent exceedances of the permitted discharge limitations for Outfall 001.
Minor Repairs and Preventative Maintenance
March 16, 2016: Repaired the back wash pump for disc filter number 1. Replaced the coupling for the motor and pump assembly.
March 21, 2016: Disassembled the sludge grinder for the sludge pump for the centrifuge. Removed “rags” and debris.
March 23, 2016: Disassembled the sludge grinder for the sludge pump for the centrifuge. Removed “rags” and debris.
March 28, 2016: Transferred the contents of SBR 2 to SHT 2.
BIG FISH ENVIRONMENTAL SERVICES, INC. 801 General Sterling Drive, West Chester PA 19382
Page 6 of 6
Draft
EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
MEETING MINUTES
March 14, 2016
The East Goshen Township Municipal Authority held their regular public meeting on Monday, March 14, 2016 at 7:00 pm at the East Goshen Township building. Members in attendance were: Chairman Dana Pizarro, Jack Yahraes, Ed McAssey and new member Phil Mayer. Also in attendance were: Rick Smith (Township Manager), Mike Ellis (Pennoni), Carmen Battavio (Township Supervisor), Jessica Wiesak (Attorney) and Walter Wujcik (Conservancy Board).
COMMON ACRONYMS:
BFES – Big Fish Environmental Services
BOS – Board of Supervisors
CB – Conservancy Board
DEP – Department of Environmental Protection
EPA – Environmental protection Agency
HC – Historical Commission
I&I – Inflow & Infiltration
LCSTP – Lockwood Chase Sewer Treatment Plant
MA- Municipal Authority
NPDES – National Pollutant Discharge Elimination System
PC – Planning Commission
PM – Prevention Maintenance
PR – Park & Recreation Board
RCSTP – Ridley Creek Sewer Treatment Plant
SBR – Sequencing Batch Reactor
SSO – Sanitary System Overflow
WAS – Waste Activated Sludge
Call to Order & Pledge of Allegiance
Dana called the meeting to order at 7:00 pm and led those present in the Pledge of Allegiance. There was a moment of silence to remember the troops and all veterans.
Dana asked if anyone would be recording the meeting. There was no response.
CHAIRMAN’S/MEMBERS REPORTS
- Ed reported that he attended the West Goshen Sewer Authority meeting. He provided copies of the 2016 budget and Capitalization Policy and minutes of the March 2, 2016 meeting. Ed reported the HRG is going to build a simulation model of the process.
- Jack mentioned that a flyer for the PMAA Spring Workshop is in the packet.
Sewer Reports
- Director of Public Works, Mark Miller presented the following report: Monthly Flows: The average daily flow to West Goshen was 850,000 to 900,000 gallons per day. It was over One Million for 10 days. It dropped once everything settled down. We also installed the portable meters at the new locations. Meters: The meters were calibrated on the first of the month. I’m currently working with Allied Control and Lenni Electeic on the logistics for the Ridley Creek flow meters. C.C. Collection: We were notified of a problem on Heather Lane. The resident thought his lateral was backing up. We inspected the pipe and the clean-out pipe had pulled out of the tee. We pushed the pipe back into the tee. This is the second time we have replaced the tee. R.C. Collection – The leaks that we located on Cornwallis Drive have been repaired. Our next area will be the Ridley Creek interceptor line from Paoli Pike and Line Road to the plant. We will also inspect the Applebrook carriage homes and the Applebrook Reserve.
F:\Data\Shared Data\Minutes\Municipal Authority\2016\MA 3-14-16 draft.doc
1
We placed an order for 2’ and 4’ risers as well as casting and lids, as we need to raise several castings in low areas.
R.C. Plant: We had to pull the utility water pump for repairs. While pulling the pump we found the piping to be in bad shape plus all of the gaskets were blown out. We pulled the piping and replaced it as well as the gaskets and hardware. The pump went to Deckman’s for repairs. The estimate to repair the pump was $3,890.00. The cost to replace the pump is $8,300.00. I gave the ok to repair the pump.
We also pulled the number 1 lift station pump for routine maintenance. The bearings on the top end need to be replaced. In order to get to the bearings, the pump had to be completely pulled down. The cost for the repairs is $5,000.00. I gave them the ok for the repairs. If we were to send the pump back to FLYGHT for repairs, the cost could be $7,800.00. Once the pump returns we will install it and pull pump 2 for maintenance. Lenni Electric was called in to replace the UPS boxes on the filters. Lenni has also been on site going thru all of the electrical components.
While we were working on the utility water piping, Dave Wolfinger showed for a surprise inspection. He said he found the plant to be in good working condition and was impressed with the preventive maintenance being done.
When we did the work at the plant, we needed to rent a 6 inch trailer pump to bypass the flow. I would recommend that we purchase a trailer mounted pump in the 2017 budget. As you know, most of our problems with sewer flows are weather related. If we had a full blown pump failure at the plant, we would not be able to pump the effluent. The nearest pump is 2.5 hours away in New Jersey and then there is no guarantee they will have what we need. We could also use the pump to bypass pump the interceptor lines and pump stations if need be. When we were working at the plant, the DEP showed up for an inspection. The inspector was very surprised that we did not own a large pump and hinted that we should consider purchasing one.
Action Items: MUFFIN MONSTER repair – discuss upgrades at Hunt Country pump station.
Sewer Lateral: 5 sewer laterals repaired for the month by plumbers.
Alarms: We responded to 37 alarms for February.
PA One Calls: We received 50 PA One calls for February.
2. Pennoni Engineer’s Report
Mike Ellis provided the following report:
Invoices: Invoices with summaries are provided under separate cover.
Ridley Creek Sewage Treatment Plant (RCSTP):
No activity since the last report.
Reservoir Rd Pump Station:
PADEP issued the permits for the Ridley Creek GP-5 “Utility Line Stream Crossings” and GP-8 “Temporary Road Crossings (across streams)” and for the pump station site floodplain filling work.
We are awaiting PADEP response for the Chester Creek Small Projects Joint Permit for the pump station site and the Chester Creek Utility crossing.
Williams-Transco and Sunoco have approved the petroleum pipeline crossings. We are still awaiting a response from PPL-IEC.
F:\Data\Shared Data\Minutes\Municipal Authority\2016\MA 3-14-16 draft.doc
2
We met with PennDOT at the site to review the Highway Occupancy Permit application for force main construction along and across E. Strasburg Rd. and Rt. 352. We revised the application thereafter, to address PennDOT’s comments, including eliminating the proposed closure of Rt. 352 and utilizing traffic control instead, and we expect to resubmit the revised application on March 14.
We are finalizing edits to the NPDES Permit Application and plans based on comments from the Chester County Conservation District, and we expect to submit the revised documents the week of March 14.
The Water Quality Management Park II Permit Application will be submitted to PADEP after the plans are revised to address CCCD’s comments.
We revised the sanitary sewer easement exhibit for 1636 Bow Tree Drive to address comments from the Solicitor.
The tentative schedule follows:
| Activity | Estimated Date |
|---|---|
| Submitted PADEP GP and JP Permit application | November 19, 2015 |
| Submit revised PennDOT HOP application | March 14 2016 |
| Submit revised NPDES Permit Application | Week of March 14, 2016 |
| Submit PADEP WQM Part II Permit application | Week of March 14, 2016 |
| PennDOT Permit issuance | April 2016 |
| PADEP & CCCD Permit issuances | May 2016 |
RCSTP and Pump Stations’ O&M Plan
We continued preparation of the Sewer System Operations and Maintenance (O&M) Manual and will provide a draft of the Manual’s current status for review by the Township and Municipal Authority on March 14.
White Chimneys Manhole Rehabilitation
We prepared a draft bid document, cost estimate, and map exhibit for interior rehabilitation of numerous manholes that are deteriorated from hydrogen sulfide. The scope included manholes in the White Chimneys neighborhood that are downstream of the Ashbridge Pump Station force main discharge and manholes along Cornwallis Drive that are downstream of the Hershey’s Mill Pump Station discharge. We performed additional field observations in both locations to determine the specific manholes to be rehabilitated. Manholes downstream of the Barkway and Hunt Country Pump Station may also be added subject to field observation of conditions.
Chapter 94 Reports
We have continued preparation of the reports. The Westtown Tributary Municipality Report has been submitted to the Township for review and we anticipated submitting the Ridley Creek STP and West Goshen reports for review the week of March 14.
Connections
We reviewed a plan submission for proposed connection of two new houses at 943 Cornwallis Drive via gravity laterals.
Manhole Rehabilitation – The estimate dated March 12, 2016 shows an estimated total cost of $104,470.
3. Big Fish Environmental Services
– Scott’s report showed that the Ridley Creek sewage treatment plant outfall 001 achieved compliance with the NPDES discharge permit during January 2016. Discharge to Applebrook was discontinued during January. Chemical usage
F:\Data\Shared Data\Minutes\Municipal Authority\2016\MA 3-14-16 draft.doc
3
utilized for total phosphorus removal, pH and total alkalinity remained consistent with previous months. No mechanical or operational issues were observed during operation of sludge dewatering equipment.
During February, there were 5 storm events resulting in a daily precipitation amount equal to or greater than 0.4 inches measured during a 24 hour period. A total of 4.68 inches of rainfall were measured during the month. These events occurred on the following dates:
- February 2 0.78 inches
- February 15 0.43 inches
- February 16 1.04 inches
- February 23 0.54 inches
- February 24 1.42 inches
Plant operations were adjusted to manage the precipitation to prevent exceedances of the permitted discharge limitation for Outfall 001.
On February 4, the SBR set points were adjusted as follows to manage the elevated hydraulic loadings as a result of rain and snow melt. At an influent flow of approx. 564.25 gpm, which is equivalent to 812,520 gpd, the following SBR adjustments were incorporated:
- Sludge wasting still off to all 3 SBRs
- Minimum aeration time 120 minutes per cycle
- Maximum aeration time 180 minutes per cycle
- Minimum react time was set at 60 minutes per cycle. The previous setting was 75 mins per cycle, however, the setting was adjusted during the evening of Feb 3 as part of the response for maximum SBR decant alarms.
On February 8, the React settings were returned to the initial settings from 60 to 75 minutes per cycle.
On February 9, the settle settings were returned to the initial settings from 45 to 60 minutes per cycle.
Minor repairs and preventative maintenance were:
February 3 – The alum line to the disc filters blew apart at injector site. All liquid was contained in alum containment area. Removed the LMI pump from service and isolated piping. Jim scheduled for troubleshooting the malfunction for Feb 4th.
February 4 – The pump suction strainer on hard piping between alum tank and pumps had solidified. Cleaned and Replaced. This task has been added to the preventative maintenance schedule. Replaced effluent sampler suction drive tubing.
February 16 – Power failures reported prior to arriving on site. Both generators operated approx. 1 hour. Responded to Siemens Panel (Max decant) Alarm last evening after heavy rain came through. SBR adjustments: Decreased minimum React from 90 to 60 mins per cycle. Decreased settle time from 60 to 30 mins per cycle.
February 17 – Mark Miller’s Township crew performed the following tasks:
- Removed influent pump #1 for overhaul and rebuild.
- Removed utility water pump #1 for overhaul and rebuild.
- Replaced a leaking gasket for Utility Pump #2.
- Lenni Electric electricians removed the UPS from disc filter #1 control pan for replacement.
- Electrician (Joe) installed new UPS units in both Disc Filter control panels.
February 18 – Completed the disassembly of the sludge pump and piping to remove blockages as a result of “rag” build up. The shear plat on the sludge grinder is recommended for replacement.
F:\Data\Shared Data\Minutes\Municipal Authority\2016\MA 3-14-16 draft.doc
4
February 23 – Sludge Tank #1 level transducer failed. A replacement transducer is planned.
Approval of Minutes
Jack moved to accept the minutes of February 8, 2016. Ed seconded the motion. The motion passed unanimously.
Approval of Invoices
- Ed moved to approve payment of the following Pennoni invoices: Pennoni #678096 $ 311.25; Pennoni #678097 $ 1,623.50; Pennoni #678098 $ 1,868.25; Pennoni #678099 $ 1,155.25; Pennoni #678100 $ 2,209.50; Pennoni #678101 $ 3,248.75; Pennoni #678618 $ 1,392.75 Jack seconded the motion. There was discussion of status of project budgets. The motion passed unanimously.
- Ed moved to approve payment of Gawthrop Greenwood invoice #141172 for $480.00 which has already been paid. Jack seconded the motion. The motion passed unanimously.
Liaison Reports
Conservancy Board – Walter reminded everyone that Keep East Goshen Beautiful Day is Saturday April 2, 2016, raindate April 9, 2016. They are planning a spring planting.
Board of Supervisors – Carmen reported that the WEGO Police Department should receive accreditation by the end of March. Auditors examine everything. He feels this may become a requirement.
On Tuesday March 22, 2016 there will be a meeting at the Fire Hall at 7:00 pm regarding the Milltown/Reservoir Dam. The engineers report is on the Township web site.
The BOS approved the Park Master Plan.
Financial Reports
Jon Altshul provided the following written report:
In February, the Municipal Authority recorded $8,521 in revenues (primarily from a tap-in fee for 957 Cornwallis Dr.) and $26,762 in expenses, (including $19,313 for Reservoir Road Pump Station engineering) and $6,969 for non-capital engineering, for a negative variance of -$18,241. As of February 29, the fund balance was $1,446,108, of which $1,396,773 is in the main construction account.
Goals
Goals for 2016 were discussed.
New Business
- The capacity request for 943 Cornwallis Drive was discussed. Jack moved to approve the request. Dana seconded the motion. The motion passed unanimously.
- Mark reported that the Muffin Monster has been in operation since 2009 and needs to be rebuilt. He contacted Charlie Deckman about rebuilding the unit. However, it was
F:\Data\Shared Data\Minutes\Municipal Authority\2016\MA 3-14-16 draft.doc
5
cheaper to swap out with JWC, the manufacture. The cost will be $21,151 with shipping. Mark’s crew will install it. Ed moved to approve this request for $21,151 for a new Muffing Monster. Jack seconded the motion. The motion passed unanimously.
3. Mark reported it is time to close the wells at the Lochwood Treatment Plant. It is less than $10,000.00 which he authorized.
4. Mark reported that for bypass pumping we need a 6” or 8” trailer mounted pump. He wants to put it in the 2017 budget. It will cost about $40,000 including hoses,etc. Jack asked Mark to put together a comparison to present to the BOS.
5. Hunt Country is the oldest pump station and needs rehabilitation. Mark received a quote from J.T.Seeley & Co. Mark will install the components from the Reserve pump station. He sent the control panel to John Laidley to update some of the electronics since it has been in place for 35 years. The quote from Seeley is $13,626. The cost to upgrade the existing pumps by Deckmen will be $2,500 per pump. He will meet with MGK to get a price to gut and install the new rail system and pumps.
6. Pat Mckenna, attorney, is working on the easement from Donald Pusey, 1636 bow Tree Drive. They have to get an appraisal of the property.
Adjournment
There being no further business, Jack moved to adjourn the meeting. Phil seconded the motion. The motion passed unanimously. The meeting was adjourned at 8:05 pm. The next meeting will be held on Monday, April 11, 2016 at 7:00 pm.
Respectfully submitted,
Ruth Kiefer
Recording Secretary
F:\Data\Shared Data\Minutes\Municipal Authority\2016\MA 3-14-16 draft.doc
6
John Strickland II
PA/DE Certified General Appraiser
William S. Wood III
PA Certified General Appraiser
Broker of Record
Mary Kay Davis Sweeney
Office Manager
WILLIAM WOOD COMPANY, LLC
120 West Market Street
West Chester, Pennsylvania 19382
610-692-3966
Fax 610-692-8325
David E. Adams
Heidi S. Phillips
Timothy J. Mingey
Kimberlee A. Baker
Timothy C. Graham
INVOICE
MARCH 17, 2016
Rick Smith, Township Manager
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380
File: 16-0184
JUST COMPENSATION VALUE of
| 1636 Bow Tree Drive | $ 1,000.00 |
|---|
3-17-16
OK TO PAY
Reservoir Rd Pump STATION
Gawthrop Greenwood, PC
Attorneys at Law
17 East Gay Street, Suite 100
West Chester, PA 19381-0562
gglaw@gawthrop.com
(p) 610-696-8225
(f) 610-344-0922
www.gawthrop.com
Page: 1
03/10/2016
Client No: 6604-001R
Invoice No: 142725
East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380
COPY
General Authority Services
Fees
| Date | Timekeeper | Description | Hours | Amount |
|---|---|---|---|---|
| 02/01/2016 | JKW | Review file; Draft easement agreement for sanitary sewer. | 2.00 | |
| 02/02/2016 | JKW | Complete draft Easement Agreement. | 0.70 | |
| 02/08/2016 | PMM | Review and analyze meeting packet in preparation for meeting; Attend Authority meeting. | 2.50 | |
| 02/12/2016 | JKW | Revise Easement Agreement. | 0.50 | |
| 02/15/2016 | PMM | Email to R Smith regarding Pusey sewer easement. | 0.20 | |
| 02/16/2016 | PMM | Email from R Smith regarding revisions to Pusey easement. | 0.20 | |
| 02/16/2016 | OC | Obtain copy of Deed at the Recorder of Deeds. | 0.30 | |
| 02/17/2016 | JKW | Revise easement per direction of R Smith; review Pusey deed. | 0.40 | |
| 02/18/2016 | PMM | Emails to/from R Smith regarding revised Pusey Easement Agreement and deed to property. | 0.40 | |
| 02/19/2016 | PMM | Emails from/to R Smith regarding Pusey Easement. | 0.20 | |
| 02/24/2016 | PMM | Emails from/to R Smith regarding revision to contract with Pennoni for arbitration. | 0.40 | |
| For Current Services Rendered | 7.80 | 1,522.50 | ||
East Goshen Municipal Authority
General Authority Services
Page: 2
03/10/2016
Client No: 6604-001R
Invoice No: 142725
Recapitulation
| Timekeeper | Hours | Hourly Rate | Total |
|---|---|---|---|
| Jessica K. Wiesak | 3.60 | $200.00 | $720.00 |
| Patrick M. McKenna | 3.90 | 200.00 | 780.00 |
| Office Clerk | 0.30 | 75.00 | 22.50 |
Expenses
| Recorder of Deeds - Copies | 1.00 |
|---|---|
| Total Expenses Thru 02/29/2016 | 1.00 |
| Total Current Charges | 1,523.50 |
|---|---|
| Balance Due | $1,523.50 |
PAID
ok RS 3-15-16
THIS INVOICE HAS BEEN PAID
To ensure proper credit, please write client number on your check when returning payment. Thank You.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.
Pennoni
INVOICE
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice #: 682656
Invoice Date: 03/30/2016
Project: EGMA1504
Project Name: Reservoir Rd PS Design & Permitting
For Services Rendered through: 3/20/2016
Attended PennDOT HOP application field review meeting with PennDOT representatives, revised plans to address PennDOT and CCCD’s NPDES comments; resubmitted HOP application; and revised NPDES application documents including Post Construction Stormwater Report and E&S Narrative.
Phase : 11 -- Final Design
| Total Phase : 11 -- Final Design | Labor : | 962.50 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 962.50 |
Phase : 12 -- Permitting
| Total Phase : 12 -- Permitting | Labor : | 613.75 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 613.75 |
| Amount Due This Invoice | $1,576.25 |
|---|
| Fee : | 136,316.25 |
|---|---|
| Prior Billings : | 132,768.50 |
| Current Billings : | 1,576.25 |
| Total Billings : | 134,344.75 |
ok RS 4/8
Continued on next page...
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
Project : EGMA1504 -- Reservoir Rd PS Design & Permitting
Invoice # : 682656
...Continued from previous page
Phase : 11 -- Final Design
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Engineering Technician II | 12.50 | 77.00 | 962.50 |
| Labor Total: | 12.50 | 962.50 |
| Total Phase : 11 -- Final Design | Labor : | $962.50 |
|---|---|---|
| Expense : | $0.00 |
Phase : 12 -- Permitting
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 4.75 | 115.00 | 546.25 |
| Staff Engineer | 0.75 | 90.00 | 67.50 |
| Labor Total: | 5.50 | 613.75 |
| Total Phase : 12 -- Permitting | Labor : | $613.75 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMA1504 -- Reservoir Rd PS Design & Permitting | Labor : | $1,576.25 |
| Expense : | $0.00 |
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
Pennoni Associates Inc.
Page: 2
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date 3/30/2016
| Project: | EGMA1504 | ||
|---|---|---|---|
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 682656 | ||
| Invoice Period: | 1/22/2016 | to | 3/20/2016 |
| Initial Authorization: | $ 167,120.00 | Date: | 3/30/2016 |
| Contract Amount: | $ 167,120.00 | ||
| Previously Invoiced: | $ 156,339.75 | ||
| Current Invoice: | $ 3,972.75 | ||
| Invoiced to Date ($): | $ 160,312.50 | ||
| Invoiced to Date (%): | 96% | ||
| Remaining Budget ($): | $ 6,807.50 | ||
| Remaining Budget (%): | 4% |
Budget by Phase:
| Phase Name: | Final Design | Phase 11 |
|---|---|---|
| Phase Budget: | $ 61,500.00 | |
| Previously Invoiced: | $ 56,748.50 | |
| Current Invoice: | $ 962.50 | |
| Invoiced to Date ($): | $ 57,711.00 | |
| Invoiced to Date (%): | 94% | |
| Remaining Budget ($): | $ 3,789.00 | |
| Remaining Budget (%): | 6% |
Comments: Attended PennDOT HOP application field review meeting with PennDOT representatives, revised plans to address PennDOT and CCCD's NPDES comments; resubmitted HOP application; and revised NPDES application documents including Post Construction Stormwater Report and E&S Narrative.
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date 3/30/2016
| Project: | EGMA1504 | ||
|---|---|---|---|
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 682656 | ||
| Invoice Period: | 2/15/2016 | to | 3/20/2016 |
| Initial Authorization: | $ 167,120.00 | Date: | 3/30/2016 |
| Contract Amount: | $ 167,120.00 | ||
| Previously Invoiced: | $ 156,339.75 | ||
| Current Invoice: | $ 3,972.75 | ||
| Invoiced to Date ($): | $ 160,312.50 | ||
| Invoiced to Date (%): | 96% | ||
| Remaining Budget ($): | $ 6,807.50 | ||
| Remaining Budget (%): | 4% |
Budget by Phase:
| Phase Name: | Permitting | Phase 12 |
|---|---|---|
| Phase Budget: | $ 28,610.50 | |
| Previously Invoiced: | $ 24,977.50 | |
| Current Invoice: | $ 613.75 | |
| Invoiced to Date ($): | $ 25,591.25 | |
| Invoiced to Date (%): | 89% | |
| Remaining Budget ($): | $ 3,019.25 | |
| Remaining Budget (%): | 11% |
Comments: Attended PennDOT HOP application field review meeting with PennDOT representatives, revised plans to address PennDOT and CCCD's NPDES comments; resubmitted HOP application; and revised NPDES application documents including Post Construction Stormwater Report and E&S Narrative.
[Logo: Pennoni]
INVOICE
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328
| East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380-6199 Attention: Louis F. Smith, Twp Mgr. |
Invoice # : 682703 Invoice Date : 03/30/2016 Project : EGMA1504 Project Name : Reservoir Rd PS Design & Permitting |
|---|
For Services Rendered through: 3/20/2016
Phase 05 - Completed permanent and temporary easement exhibit and legal description, submitted documents to Township, and revised exhibit to address Solicitor's comments.
Phase : 05 -- 1636 Bow Tree Dr Bndry Survey & Eas
| Contract Amount | $4,020.00 | |
|---|---|---|
| Percent Complete | 100.00% | |
| Contract Amount Completed | $4,020.00 | |
| Less Previous Billed | $(1,623.50) | |
| Phase Subtotal | $2,396.50 | |
| Amount Due This Invoice | $2,396.50 |
[Handwritten: ok RS 4/8]
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMA1504 Invoice Summary
Invoice Date 3/30/2016
| Project: | EGMA1504 | ||
|---|---|---|---|
| Pennoni Job No.: | Reservoir Rd PS Design & Permitting | ||
| Invoice No: | 682703 | ||
| Invoice Period: | 2/15/2016 | to | 3/20/2016 |
| Initial Authorization: | $ 167,120.00 | Date: | 3/30/2016 |
| Contract Amount: | $ 167,120.00 | ||
| Previously Invoiced: | $ 156,339.75 | ||
| Current Invoice: | $ 3,972.75 | ||
| Invoiced to Date ($): | $ 160,312.50 | ||
| Invoiced to Date (%): | 96% | ||
| Remaining Budget ($): | $ 6,807.50 | ||
| Remaining Budget (%): | 4% |
Budget by Phase:
| Phase Name: | 1636 Bow Tree Dr Boundary & Esmnts | Phase 05 |
|---|---|---|
| Phase Budget: | $ 4,020.00 | |
| Previously Invoiced: | $ 1,623.50 | |
| Current Invoice: | $ 2,396.50 | |
| Invoiced to Date ($): | $ 4,020.00 | |
| Invoiced to Date (%): | 100% | |
| Remaining Budget ($): | $ - | |
| Remaining Budget (%): | 0% |
Comments: Phase 05 - Completed permanent and temporary easement exhibit and legal description, submitted documents to Township, and revised exhibit to address Solicitor's comments.
Reservoir Road Pump Station Design & Permitting
INVOICE SUMMARY
For Services Rendered through: 3/20/2016
| Task No. | Activity | Contract Amount* | Invoiced Effort thru 2/14/2016 | Remaining Budget ($) | Remaining Budget (%) | Completed? |
|---|---|---|---|---|---|---|
| 1 | Concept Design | $13,655.75 | $13,655.75 | - | - | Yes |
| 2 | DEP WQM Pre-App. Meeting | $1,300.00 | $1,300.00 | - | - | Yes |
| 3 | Existing Conditions Survey | $22,783.75 | $22,783.75 | - | - | Yes |
| 4 | Sewer Stakeout in Easements | $0.00 | $0.00 | - | - | Scope eliminated |
| 5 | 1636 Bow Tree Dr. Boundary Survey & Easement | $4,020.00 | $4,020.00 | - | - | Yes |
| 6 | Additional Boundary Surveys & Easements | $0.00 | $0.00 | - | - | Scope eliminated |
| 7 | Geotechnical Borings | $4,000.00 | $4,000.00 | - | - | Yes |
| 8 | Install Permanent Survey Benchmarks | $0.00 | $0.00 | - | - | Scope eliminated |
| 9 | Progress Design | $29,450.00 | $29,450.00 | - | - | Yes |
| 10 | Infiltration Testing | $1,800.00 | $1,800.00 | - | - | Yes |
| 11 | Final Design | $61,500.00 | $57,711.00 | $3,789.00 | 6% | No |
| 12 | Permitting | $28,610.50 | $25,591.25 | $3,019.25 | 11% | No |
| TOTAL | $167,120.00 | $160,311.80 | $6,808.25 | 4% | ||
*After 12/14/2015 approved re-allocation of task budgets.
[Logo: Pennoni]
INVOICE
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328
| East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380-6199 Attention: Louis F. Smith, Twp Mgr. |
Invoice # : 682658 Invoice Date : 03/30/2016 Project : EGMA1505 Project Name : RCSTP and Pump Station O&M Manual |
|---|
For Services Rendered through: 3/20/2016
Continued preparation of O&M Manual, primarily pump station information from individual pump station manuals; and submitted progress draft of O&M Manual to Township for review.
Phase : **** -- Professional Services
| Total Phase : **** -- Professional Services | Labor : | 1,955.75 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 1,955.75 | |
| Amount Due This Invoice | $1,955.75 | |
| Fee : | 12,500.00 |
|---|---|
| Prior Billings : | 2,594.00 |
| Current Billings : | 1,955.75 |
| Total Billings : | 4,549.75 |
Phase : **** -- Professional Services
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 0.25 | 115.00 | 28.75 |
| Project Engineer | 11.25 | 97.00 | 1,091.25 |
| Senior Engineering Technician | 1.00 | 85.00 | 85.00 |
| Graduate Engineer | 9.75 | 77.00 | 750.75 |
| Labor Total: | 22.25 | 1,955.75 |
| Total Phase : **** -- Professional Services | Labor : | $1,955.75 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMA1505 -- RCSTP and Pump Station O&M Manual | Labor : | $1,955.75 |
| Expense : | $0.00 |
[Handwritten: ok RS 4/8]
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMA1505 Invoice Summary
Invoice Date 03/30/2016
| Project: | EGMA1505 | ||
|---|---|---|---|
| Pennoni Job No.: | RCSTP & Pump Station O&M Manual | ||
| Invoice No: | 682658 | ||
| Invoice Period: | 2/15/2016 | to | 3/20/2016 |
| Initial Authorization: | $ 12,500.00 | Date: | 3/30/2016 |
| Contract Amount: | $ 12,500.00 | ||
| Previously Invoiced: | $ 2,594.00 | ||
| Current Invoice: | $ 1,955.75 | ||
| Invoiced to Date ($): | $ 4,549.75 | ||
| Invoiced to Date (%): | 36% | ||
| Remaining Budget ($): | $ 7,950.25 | ||
| Remaining Budget (%): | 64% |
Budget by Phase:
| Phase Name: | RCSTP & Pump Station O&M Manual |
|---|---|
| Phase Budget: | $ 12,500.00 |
| Previously Invoiced: | $ 2,594.00 |
| Current Invoice: | $ 1,955.75 |
| Invoiced to Date ($): | $ 4,549.75 |
| Invoiced to Date (%): | 36% |
| Remaining Budget ($): | $ 7,950.25 |
| Remaining Budget (%): | 64% |
Comments: Continued preparation of O&M Manual, primarily pump station information from individual pump station manuals; and submitted progress draft of O&M Manual to Township for review.
[Logo: Pennoni]
INVOICE
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328
| East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380-6199 Attention: Louis F. Smith, Twp Mgr. |
Invoice # : 682659 Invoice Date : 03/30/2016 Project : EGMA1601 Project Name : 2016 General Services |
|---|
For Services Rendered through: 3/20/2016
Prepared March Engineer's Report and prepared for and attended March MA meeting. Ashbridge PS Force Main Terminal Manhole C226 alternatives analysis for manhole rehab vs. replacement and submission of draft alternatives letter to Township Sizing and cost evaluation of potential bypass pump to purchase for RCSTP Influent Pump Station and other pump stations. General sewer system assistance including I&I located along Cornwallis Drive, Hunt Country PS grease problems, RCSTP pump piping deterioration, and upcoming RCSTP NPDES permit renewal.
Phase : **** -- Professional Services
| Total Phase : **** -- Professional Services | Labor : | 778.00 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 778.00 | |
| Amount Due This Invoice | $778.00 | |
| Fee : | 12,300.00 |
|---|---|
| Prior Billings : | 1,644.00 |
| Current Billings : | 778.00 |
| Total Billings : | 2,422.00 |
Phase : **** -- Professional Services
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 5.50 | 115.00 | 632.50 |
| Project Engineer | 1.50 | 97.00 | 145.50 |
| Labor Total: | 7.00 | 778.00 |
| Total Phase : **** -- Professional Services | Labor : | $778.00 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMA1601 -- 2016 General Services | Labor : | $778.00 |
| Expense : | $0.00 |
[Handwritten: ok RS 4/8]
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMA1601 Invoice Summary
Invoice Date 03/30/2016
| Project: | EGMA1601 | ||
|---|---|---|---|
| Pennoni Job No.: | 2016 General Services | ||
| Invoice No: | 682659 | ||
| Invoice Period: | 2/15/2016 | to | 3/20/2016 |
| Initial Authorization: | $ 12,300.00 | Date: | 3/30/2016 |
| Contract Amount: | $ 12,300.00 | ||
| Previously Invoiced: | $ 1,644.00 | ||
| Current Invoice: | $ 778.00 | ||
| Invoiced to Date ($): | $ 2,422.00 | ||
| Invoiced to Date (%): | 20% | ||
| Remaining Budget ($): | $ 9,878.00 | ||
| Remaining Budget (%): | 80% |
Budget by Phase:
| Phase Name: | 2016 General Services |
|---|---|
| Phase Budget: | $ 12,300.00 |
| Previously Invoiced: | $ 1,644.00 |
| Current Invoice: | $ 778.00 |
| Invoiced to Date ($): | $ 2,422.00 |
| Invoiced to Date (%): | 20% |
| Remaining Budget ($): | $ 9,878.00 |
| Remaining Budget (%): | 80% |
Comments: Prepared March Engineer's Report and prepared for and attended March MA meeting. Ashbridge PS Force Main Terminal Manhole C226 alternatives analysis for manhole rehab vs. replacement and submission of draft alternatives letter to Township. Sizing and cost evaluation of potential bypass pump to purchase for RCSTP Influent Pump Station and other pump stations. General sewer system assistance including I&I located along Cornwallis Drive, Hunt Country PS grease problems, RCSTP pump piping deterioration, and upcoming RCSTP NPDES permit renewal.
[Logo: Pennoni]
INVOICE
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328
| East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380-6199 Attention: Louis F. Smith, Twp Mgr. |
Invoice # : 682660 Invoice Date : 03/30/2016 Project : EGMA1603 Project Name : 2015 Chapter 94 Reports |
|---|
For Services Rendered through: 3/20/2016
Continued preparation of Chapter 94 Reports and submitted Westtown Tributary Report to Township for review.
Phase : **** -- Professional Services
| Total Phase : **** -- Professional Services | Labor : | 761.75 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 761.75 | |
| Amount Due This Invoice | $761.75 | |
| Fee : | 15,000.00 |
|---|---|
| Prior Billings : | 4,121.00 |
| Current Billings : | 761.75 |
| Total Billings : | 4,882.75 |
Phase : **** -- Professional Services
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 1.75 | 115.00 | 201.25 |
| Project Engineer | 3.00 | 97.00 | 291.00 |
| Graduate Engineer | 3.50 | 77.00 | 269.50 |
| Labor Total: | 8.25 | 761.75 |
| Total Phase : **** -- Professional Services | Labor : | $761.75 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMA1603 -- 2015 Chapter 94 Reports | Labor : | $761.75 |
| Expense : | $0.00 |
[Handwritten: ok RS 4/8]
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMA1603 Invoice Summary
Invoice Date 03/30/2016
| Project: | EGMA1603 | ||
|---|---|---|---|
| Pennoni Job No.: | 2015 Chapter 94 Reports | ||
| Invoice No: | 682660 | ||
| Invoice Period: | 2/15/2016 | to | 3/20/2016 |
| Initial Authorization: | $ 15,000.00 | Date: | 3/30/2016 |
| Contract Amount: | $ 15,000.00 | ||
| Previously Invoiced: | $ 4,121.00 | ||
| Current Invoice: | $ 761.75 | ||
| Invoiced to Date ($): | $ 4,882.75 | ||
| Invoiced to Date (%): | 33% | ||
| Remaining Budget ($): | $ 10,117.25 | ||
| Remaining Budget (%): | 67% |
Budget by Phase:
| Phase Name: | 2015 Chapter 94 Reports |
|---|---|
| Phase Budget: | $ 15,000.00 |
| Previously Invoiced: | $ 4,121.00 |
| Current Invoice: | $ 761.75 |
| Invoiced to Date ($): | $ 4,882.75 |
| Invoiced to Date (%): | 33% |
| Remaining Budget ($): | $ 10,117.25 |
| Remaining Budget (%): | 67% |
Comments: Continued preparation of Chapter 94 Reports and submitted Westtown Tributary Report to Township for review.
[Logo: Pennoni]
INVOICE
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328
| East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380-6199 Attention: Louis F. Smith, Twp Mgr. |
Invoice # : 682661 Invoice Date : 03/30/2016 Project : EGMA1604 Project Name : White Chimneys MH Lining Bid Doc |
|---|
For Services Rendered through: 3/20/2016
Field observations and measurements of manholes along/behind Cornwallis Drive to add to project scope; field observations of manholes off interceptor in White Chimneys to confirm rehab is not needed; vendor coordination; prepared bid document and technical specifications; updated cost estimate to include additional Cornwallis Drive manholes; updated exhibit of White Chimneys manholes to be lined and created exhibit of Cornwallis Drive manholes; and submitted draft bid document and cost estimate to Township for review.
Phase : **** -- Professional Services
| Total Phase : **** -- Professional Services | Labor : | 2,996.25 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 2,996.25 | |
| Amount Due This Invoice | $2,996.25 | |
| Fee : | 4,400.00 |
|---|---|
| Prior Billings : | 1,392.75 |
| Current Billings : | 2,996.25 |
| Total Billings : | 4,389.00 |
Phase : **** -- Professional Services
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 5.00 | 115.00 | 575.00 |
| Project Engineer | 18.00 | 97.00 | 1,746.00 |
| Senior Engineering Technician | 5.00 | 85.00 | 425.00 |
| Engineering Technician II | 3.25 | 77.00 | 250.25 |
| Labor Total: | 31.25 | 2,996.25 |
| Total Phase : **** -- Professional Services | Labor : | $2,996.25 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMA1604 -- White Chimneys MH Lining Bid Doc | Labor : | $2,996.25 |
| Expense : | $0.00 |
[Handwritten: ok RS 4/8]
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMA1601 Invoice Summary
Invoice Date 03/30/2016
| Project: | EGMA1604 | ||
|---|---|---|---|
| Pennoni Job No.: | White Chimneys MH Lining Bid Doc | ||
| Invoice No: | 682661 | ||
| Invoice Period: | 2/15/2016 | to | 3/20/2016 |
| Initial Authorization: | $ 4,400.00 | Date: | 3/30/2016 |
| Contract Amount: | $ 4,400.00 | ||
| Previously Invoiced: | $ 1,392.75 | ||
| Current Invoice: | $ 2,996.25 | ||
| Invoiced to Date ($): | $ 4,389.00 | ||
| Invoiced to Date (%): | 100% | ||
| Remaining Budget ($): | $ 11.00 | ||
| Remaining Budget (%): | 0% |
Budget by Phase:
| Phase Name: | White Chimneys MH Lining Bid Doc |
|---|---|
| Phase Budget: | $ 4,400.00 |
| Previously Invoiced: | $ 1,392.75 |
| Current Invoice: | $ 2,996.25 |
| Invoiced to Date ($): | $ 4,389.00 |
| Invoiced to Date (%): | 100% |
| Remaining Budget ($): | $ 11.00 |
| Remaining Budget (%): | 0% |
Comments: Field observations and measurements of manholes along/behind Cornwallis Drive to add to project scope; field observations of manholes off interceptor in White Chimneys to confirm rehab is not needed; vendor coordination; prepared bid document and technical specifications; updated cost estimate to include additional Cornwallis Drive manholes; updated exhibit of White Chimneys manholes to be lined and created exhibit of Cornwallis Drive manholes; and submitted draft bid document and cost estimate to Township for review.
Memo
To: Municipal Authority
From: Jon Altshul
Re: MA March Financial Reports
Date: April 5, 2016
In March, the Municipal Authority recorded $25,110 in revenues (primarily from a $25,000 transfer from the Sewer Operating Fund) and $22,038 in expenses (including $7,705 for the quarterly administrative charge-back, $9,875 for general engineering services, and $2,935 for Reservoir Road Pump Station engineering), for a positive variance of $3,072. As of March 31st, the fund balance was $1,449,120, of which $1,393,945 is in the main construction account.
A complete list of all year-to-date expenses and revenues is provided.
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
March 2016
| Account Title | Acct # | Annual Budget | Month To Date Actual | Year To Date Actual |
|---|---|---|---|---|
| MUNICIPAL AUTHORITY BEGINNING FUND BALANCE | 1,446,108.40 | |||
| RCSTP BUDGET | ||||
| REVENUE | ||||
| INTEREST EARNED - RCSTP EXPANSION | 07341 1020 | 1,500.00 | 109.26 | 323.41 |
| GRANT REVENUE | 07392 0800 | 0.00 | 0.00 | 0.00 |
| TOTAL REVENUE | 1,500.00 | 109.26 | 323.41 | |
| EXPENSES | ||||
| R.C.-CAP. PROJ.-ENGINEER | 07424 7451 | 0.00 | ||
| R.C. CAP EXPANSION GEN'L CONTRACTOR | 07424 7452 | 0.00 | ||
| R.C. CAP EXPANSION - ELECTRICAL | 07424 7453 | 0.00 | ||
| R.C. CAP EXP CONTINGENCY CAPITAL | 07424 7454 | 0.00 | ||
| R.C. CAP EXP CONTINGENCY ONGOING | 07424 7455 | 0.00 | ||
| R.C. CAP EXP ADDITIONAL CONTINGENCY | 07424 7456 | 0.00 | ||
| TRANSFER TO SEWER SINKING FUND | 07492 0550 | 0.00 | ||
| TRANSFER TO AUTHORITY CAP FUND | 07492 0990 | 0.00 | ||
| TOTAL EXPENSES | 0.00 | 0.00 | 0.00 | |
| RCSTP NET RESULT | 1,500.00 | 109.26 | 323.41 | |
OPERATING BUDGET
U:\bmccool\2016\Municipal Authority\2016 - 03 - Municipal Authority Report.xlsx
Page 1 of 3
04/05/2016
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
March 2016
| Account Title | Acct # | Annual Budget |
Month To Date Actual |
Year To Date Actual |
|---|---|---|---|---|
| REVENUE | ||||
| INTEREST EARNINGS | 07341 1000 | 10.00 | 0.51 | 1.45 |
| C.C. TAPPING FEES | 07364 1100 | 4,000.00 | 0.00 | 0.00 |
| R.C.TAPPING FEES | 07364 1110 | 4,000.00 | 0.00 | 12,152.00 |
| CONNECTION FEES - SEWER | 07364 1130 | 0.00 | 0.00 | 845.64 |
| MISCELLANEOUS REVENUE | 07380 1000 | 0.00 | 0.00 | 423.36 |
| TRANSFER FROM SEWER OPERATING | 07392 0500 | 93,832.00 | 25,000.00 | 25,000.00 |
| TOTAL REVENUE | 101,842.00 | 25,000.51 | 38,422.45 | |
| EXPENSES | ||||
| ADMINISTRATIVE WAGES | 07424 1400 | 0.00 | 7,705.49 | 7,705.49 |
| MISCELLANEOUS EXPENSE | 07424 3000 | 3,000.00 | 0.00 | 1,641.62 |
| MUNIC.AUTH.-AUDITING | 07424 3110 | 9,500.00 | 0.00 | 0.00 |
| ENGINEERING SERVICES | 07424 3130 | 38,500.00 | 9,874.50 | 16,843.50 |
| LEGAL SERVICES | 07424 3140 | 9,000.00 | 1,523.50 | 2,403.50 |
| M.C.-DVRFA-DEBT SERVICE | 07471 1000 | 24,920.00 | 0.00 | 0.00 |
| M.C.-DVRFA-INTEREST PAYMN | 07472 1000 | 3,172.00 | 0.00 | 0.00 |
| M.C.-DVRFA-INTEREST PAYMN | 07472 1010 | 0.00 | 0.00 | 0.00 |
| TOTAL EXPENSES | 88,092.00 | 19,103.49 | 28,594.11 | |
| OPERATING NET RESULT | 13,750.00 | 5,897.02 | 9,828.34 | |
U:\bmccool\2016\Municipal Authority\2016 - 03 - Municipal Authority Report.xlsx Page 2 of 3 04/05/2016
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA
Municipal Authority
March 2016
| Account Title | Acct # | Annual Budget |
Month To Date Actual |
Year To Date Actual |
|---|---|---|---|---|
| CAPITAL BUDGET | ||||
| REVENUE | ||||
| LOAN PROCEEDS-SEWER PROJECT | 07393 1001 | 0.00 | 0.00 | 0.00 |
| TRANSFER FROM SEWER CAP RESERVE | 07392 0900 | 0.00 | 0.00 | 0.00 |
| TOTAL REVENUE | 0.00 | 0.00 | 0.00 | |
| EXPENSES | ||||
| MARYDELL PUMP STATION - ENGINEER | 07425 1000 | 0.00 | 0.00 | 0.00 |
| MARYDELL PUMP STATION -CONSTRUCTION | 07425 2000 | 0.00 | 0.00 | 0.00 |
| MANHOLE COVER REPLACEMENTS | 07424.7405 | 0.00 | 0.00 | 0.00 |
| C.C. CAPITAL - COLLECTION | 07424.7420 | 0.00 | 0.00 | 0.00 |
| LOCHWOOD ABANDONMENT ENGINEER | 07424 7475 | 0.00 | 0.00 | 0.00 |
| LOCHWOOD ABANDONMENT CONSTRUCTION | 07424 7476 | 0.00 | 0.00 | 0.00 |
| LOCHWOOD ELIMINATION PHASE 2 | 07424 7477 | 0.00 | 0.00 | 0.00 |
| HERSHEY MILL STATION - ENGINEER | 07426 1000 | 0.00 | 0.00 | 0.00 |
| HERSHEY MILL STATION - CONSTRUCTION | 07426 2000 | 0.00 | 0.00 | 0.00 |
| RESERVE PUMP STATION - ENGINEER | 07427 1000 | 0.00 | 0.00 | 0.00 |
| RESERVE PUMP STATION - CONSTRUCTION | 07427 2000 | 0.00 | 0.00 | 0.00 |
| RESERVOIR PUMP STATION - ENGINEER | 07428 1000 | 0.00 | 2,934.75 | 22,248.00 |
| RESERVOIR PUMP STATION CONSTRUCTION | 07428 2000 | 0.00 | 0.00 | 0.00 |
| ASBSTOS CONCRETE ENGINEERING | 07429 3130 | 25,000.00 | 0.00 | 0.00 |
| DIVERSION PROJ.- LEGAL | 07429 3166 | 0.00 | 0.00 | 0.00 |
| TOTAL EXPENSES | 25,000.00 | 2,934.75 | 22,248.00 | |
| CAPITAL NET RESULT | (25,000.00) | (2,934.75) | (22,248.00) | |
| MUNICIPAL AUTHORITY ENDING FUND BALANCE | 1,449,179.93 | |||
U:\bmccool\2016\Municipal Authority\2016 - 03 - Municipal Authority Report.xlsx Page 3 of 3 04/05/2016
East Goshen Township General Ledger
Report Date 04/05/16 GL Transaction Details PAGE 1
MGRP18 run by BRIAN 1 : 35 PM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07341-1000 INTEREST EARNINGS | 0.00 | |||||||||
| 1601 | JE | 51240 | 0.43 | 02/01/16 | INTEREST | INTEREST EARNED JANUARY 2016 07 FUND |
||||
| 1601 | 0.00 | 0.43 | -0.43 | |||||||
| 1602 | 51651 | 0.51 | 03/01/16 | INTEREST | INTEREST EARNED FEBRUARY 2016 07 FUND |
|||||
| 1602 | 0.00 | 0.51 | -0.94 | |||||||
| 1603 | 52095 | 0.51 | 04/04/16 | INTEREST | INTEREST EARNED MARCH 2016 07 FUND |
|||||
| 1603 | 0.00 | 0.51 | -1.45 | |||||||
| 07341-1000 | **** | *** | ***** | 0.00 | 1.45 | -1.45 | ||||
| 07341-1020 INTEREST EARNED - RCSTP EXPANSION | 0.00 | |||||||||
| 1601 | 51240 | 110.59 | 02/01/16 | INTEREST | INTEREST EARNED JANUARY 2016 07 FUND |
|||||
| 1601 | 0.00 | 110.59 | -110.59 | |||||||
| 1602 | 51651 | 103.56 | 03/01/16 | INTEREST | INTEREST EARNED FEBRUARY 2016 07 FUND |
|||||
| 1602 | 0.00 | 103.56 | -214.15 | |||||||
| 1603 | 52095 | 109.26 | 04/04/16 | INTEREST | INTEREST EARNED MARCH 2016 07 FUND |
|||||
| 1603 | 0.00 | 109.26 | -323.41 | |||||||
| 07341-1020 | **** | *** | ***** | 0.00 | 323.41 | -323.41 | ||||
| 07364-1110 R.C.TAPPING FEES | 0.00 | |||||||||
| 1601 | CR | 51204 | 5,004.00 | 01/28/16 | 1247 | 7875 | 1 SUNNY RIDGE FARMS LLC | |||
| 1601 | 0.00 | 5,004.00 | -5,004.00 | |||||||
East Goshen Township General Ledger
Report Date 04/05/16 GL Transaction Details PAGE 2
MGRP18 run by BRIAN 1 : 35 PM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07364-1110 | 1602 | RE | 51557 | 7,148.00 | 02/23/16 | 51557 | 1 | TAP IN FEE-957 CORNWALLIS DR | ||
| 1602 | 0.00 | 7,148.00 | -12,152.00 | |||||||
| 07364-1110 | **** | *** | ***** | 0.00 | 12,152.00 | -12,152.00 | ||||
| 07364-1130 CONNECTION FEES - SEWER | 0.00 | |||||||||
| CR | 51318 | 423.00 | 02/05/16 | 804 | 9354 | 1 GEORGE SMITH & CHRISTINA CONLE | ||||
| 51322 | 423.00 | 02/05/16 | 344 | 9356 | 1 JACOBS, ROBERT & CHERYL | |||||
| 51357 | 423.00 | 02/08/16 | 2435 | 9355 | 1 STOFFLET, MICHAEL | |||||
| JE | 51319 | 141.12 | 02/05/16 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | |||||
| 51323 | 141.12 | 02/05/16 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | ||||||
| 51358 | 141.12 | 02/08/16 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | ||||||
| 1602 | 423.36 | 1,269.00 | -845.64 | |||||||
| 07364-1130 | **** | *** | ***** | 423.36 | 1,269.00 | -845.64 | ||||
| 07380-1000 MISCELLANEOUS REVENUE | 0.00 | |||||||||
| 51319 | 141.12 | 02/05/16 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | ||||||
| 51323 | 141.12 | 02/05/16 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | ||||||
| 51358 | 141.12 | 02/08/16 | PINE ROCK | ANNUAL PINE ROCK INSTALLMENT | ||||||
| 1602 | 0.00 | 423.36 | -423.36 | |||||||
| 07380-1000 | **** | *** | ***** | 0.00 | 423.36 | -423.36 | ||||
| 07392-0500 TRANSFER FROM SEWER OPERATING | 0.00 | |||||||||
| 1603 | 52022 | 25,000.00 | 03/28/16 | DEPOSIT | DEPOSIT TO MUNICIPAL ACCT. | |||||
| 1603 | 0.00 | 25,000.00 | -25,000.00 | |||||||
| 07392-0500 | **** | *** | ***** | 0.00 | 25,000.00 | -25,000.00 | ||||
| 07424-1400 ADMINISTRATIVE WAGES | 0.00 | |||||||||
| CD | 51990 | 7,705.49 | 03/24/16 | 3013 | 425 | EAST GOSHEN TOWNSHIP - GENERAL Q1 2016 REIMBURSEMENT FROM MUN.A |
||||
| 1603 | 7,705.49 | 0.00 | 7,705.49 | |||||||
East Goshen Township General Ledger
Report Date 04/05/16 GL Transaction Details PAGE 3
MGRP18 run by BRIAN 1 : 35 PM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07424-1400 | **** | *** | ***** | 7,705.49 | 0.00 | 7,705.49 | ||||
| 07424-3000 MISCELLANEOUS EXPENSE | 0.00 | |||||||||
| 1601 | 50894 | 978.00 | 01/04/16 | 3004 | 2132 | PENNSYLVANIA MUNICIPAL AUTHORITIES ASSOC 2016 ACTIVE MEMBERSHIP DUES |
||||
| 51002 | 163.62 | 01/18/16 | 3005 | 2967 | SAFEGUARD CHECK ORDER FEE |
|||||
| 51028 | 500.00 | 01/14/16 | 3006 | 2737 | COMMONWEALTH OF PA NPDES PERMITS -CHAP.92A 2016 PERMIT# PA0050504 |
|||||
| 1601 | 1,641.62 | 0.00 | 1,641.62 | |||||||
| 07424-3000 | **** | *** | ***** | 1,641.62 | 0.00 | 1,641.62 | ||||
| 07424-3130 ENGINEERING SERVICES | 0.00 | |||||||||
| 1602 | 51394 | 5,905.25 | 02/10/16 | 3008 | 1052 | PENNONI ASSOCIATES INC. SERVICES THRU 1/17/16 RCSTP & PU STATION O&M MANUAL |
||||
| 51527 | 1,063.75 | 02/23/16 | 3010 | 1052 | PENNONI ASSOCIATES INC. SERV.THRU 12/13/16 2015 GEN.SER |
|||||
| 1602 | 6,969.00 | 0.00 | 6,969.00 | |||||||
| 1603 | 51813 | 9,874.50 | 03/15/16 | 3012 | 1052 | PENNONI ASSOCIATES INC. SERVICES THRU 2/14/16 RCSTP PS O |
||||
| 1603 | 9,874.50 | 0.00 | 16,843.50 | |||||||
| 07424-3130 | **** | *** | ***** | 16,843.50 | 0.00 | 16,843.50 | ||||
| 07424-3140 LEGAL SERVICES | 0.00 | |||||||||
| 1601 | 51149 | 400.00 | 12/17/15 | 3007 | 528 | GAWTHROP GREENWOOD & HALSTED LEGAL SERVICES 12/14/15 - GEN.AU |
||||
| 1601 | 400.00 | 0.00 | 400.00 | |||||||
| 1602 | 51503 | 480.00 | 02/19/16 | 3009 | 528 | GAWTHROP GREENWOOD & HALSTED LEGAL SERVICE 1/11-1/29/16 GEN.A |
||||
| 1602 | 480.00 | 0.00 | 880.00 | |||||||
East Goshen Township General Ledger
Report Date 04/05/16 GL Transaction Details PAGE 4
MGRP18 run by BRIAN 1 : 35 PM
| Acct # | Per | Src | Trx # | Debits | Credits | Beg/End Bal | Date | Check/Ref # | ID # | Name/Description |
|---|---|---|---|---|---|---|---|---|---|---|
| 07424-3140 | 1603 | CD | 51813 | 1,523.50 | 03/15/16 | 3011 | 528 | GAWTHROP GREENWOOD & HALSTED LEGAL SERVICE FEB.2016 - GEN. AU |
||
| 1603 | 1,523.50 | 0.00 | 2,403.50 | |||||||
| 07424-3140 | **** | *** | ***** | 2,403.50 | 0.00 | 2,403.50 | ||||
| 07428-1000 RESERVOIR PUMP STATION - ENGINEER | 0.00 | |||||||||
| 1602 | 51395 | 2,565.50 | 02/10/16 | 103 | 1052 | PENNONI ASSOCIATES INC. SERVICE THRU 1/17/16 RESERV.RD.P |
||||
| 51528 | 16,747.75 | 02/23/16 | 104 | 1052 | PENNONI ASSOCIATES INC. SERVICE THRU 12/13/15 RESERV.RD |
|||||
| 1602 | 19,313.25 | 0.00 | 19,313.25 | |||||||
| 1603 | 51812 | 1,934.75 | 03/15/16 | 105 | 1052 | PENNONI ASSOCIATES INC. SERV. THRU 2/14/16 RESERV.RD PS PENNDOT HOP |
||||
| 52048 | 1,000.00 | 03/30/16 | 106 | 1496 | WILLIAM WOOD CO. SEWER EASEMENT -1636 BOW TREE DR |
|||||
| 1603 | 2,934.75 | 0.00 | 22,248.00 | |||||||
| 07428-1000 | **** | *** | ***** | 22,248.00 | 0.00 | 22,248.00 | ||||
| Grand Total | 51,265.47 | 39,169.22 | 12,096.25 | |||||||
[Logo: pennsylvania DEPARTMENT OF ENVIRONMENTAL PROTECTION]
March 22, 2016
[Stamp: RECEIVED MAR 28 2016 BY ______]
Mr. Rick Smith
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380
Re: Act 537, Application for Exemption
943 Cornwallis Drive Subdivision
DEP Code No. 1-15919-238-E
East Goshen Township
Chester County
Dear Mr. Smith:
The Department of Environmental Protection (DEP) has received the above-referenced subdivision plan. This letter confirms DEP’s determination that the above-referenced project is exempt from the requirement to revise the Official Plan for new land development. This determination is based in part on municipal and other sign-offs. The project is located at 943 Cornwallis Drive, in East Goshen Township, Chester County.
This project proposes a 2 lot residential subdivision. The existing dwelling will be demolished and 2 new single-family dwellings will be constructed.
The project will be connected to the East Goshen Municipal Authority collection system and will generate an additional 275 gallons of sewage per day to be treated at the East Goshen Municipal Authority Wastewater Treatment Facility.
Any person aggrieved by this action may appeal, pursuant to Section 4 of the Environmental Hearing Board Act, 35 P.S. Section 7514, and the Administrative Agency Law, 2 Pa. C.S. Chapter 5A, to the Environmental Hearing Board, Second Floor, Rachel Carson State Office Building, 400 Market Street, P.O. Box 8457, Harrisburg, PA 17105-8457, 717.787.3483. TDD users may contact the Board through the Pennsylvania Relay Service, 800.654.5984. Appeals must be filed with the Environmental Hearing Board within 30 days of receipt of written notice of this action unless the appropriate statute provides a different time period. Copies of the appeal form and the Board’s rules of practice and procedure may be obtained from the Board. The appeal form and the Board’s rules of practice and procedure are also available in braille or on audiotape from the Secretary to the Board at 717.787.3483. This paragraph does not, in and of itself, create any right of appeal beyond that permitted by applicable statutes and decisional law.
Southeast Regional Office
2 East Main Street | Norristown, PA 19401-4915 | 484.250.5970 | Fax 484.250.5971 | www.depweb.state.pa.us
AREA CODE 610
692-7171
EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199
March 18, 2016
Mr. Donald Pusey
1636 Bow Tree Drive
West Chester PA 19380
Dear Mr. Pusey:
As I noted in my letter of March 2, 2016 the force main for the Reservoir Road Pump Station will have to cross the corner of your property that is next to the pond. This means the Authority will need to acquire an easement from you to install the force main.
The Authority engaged William Wood Company to conduct an appraisal and they have determined that the Just Compensation for the Temporary and Permanent Easement is $690.00. Please consider this letter as a formal offer from the Municipal Authority to acquire the easement from you for $690.00.
I have enclosed a copy of the appraisal and the easement for your review. If the offer is acceptable please contact me and we can set up a time for executing the agreement and payment of the compensation.
Please give me a call at 610-692-7171 or e-mail me at rsmith@eastgoshen.org if you have any questions.
Sincerely,
[Signature: Rick]
Louis F. Smith, Jr.
Township Manager
Enclosures
F:\Data\Shared Data\ABC'S\Municipal Authority\Projects\Reservoir Road PS\Easement\Letter 031816.doc
Rick Smith
From: Michael Ellis <MEllis@Pennoni.com>
Sent: Thursday, April 07, 2016 11:47 PM
To: rsmith@eastgoshen.org
Cc: Mark Miller (mmiller@eastgoshen.org); Nathan M. Cline; 'ssmith@eastgoshen.org'; Sherrie Ball
Subject: Pennoni Invoices - Municipal Authority - March 2016
Attachments: Current Invoices (2016-03).pdf
Hi Rick,
Current Municipal Authority invoices are attached.
Please note that we are up against the budget on the Manhole Lining project due to the addition of the Cornwallis Drive, Barkway, and Hunt Country manholes to the original White Chimneys scope, in addition to the alternative product evaluation. I anticipate the effort to visit the alternative product manholes on Tuesday, finalize the bid doc accordingly (90% draft was previously submitted), perform site visits to quantify the Barkway and Hunt Country manholes to be lined, and to provide limited bid assistance will be an additional $2,500-$3,000. This would take the total project value to approx $6,900-$7,400. Would this require MA approval?
Please call or email me if you have any questions.
Thanks,
Mike
Michael Ellis, PE
Municipal Division Manager
Pennoni
121 Continental Drive, Suite 207 | Newark, DE 19713
Direct: 302-351-5236 | Mobile: 302-561-4235
www.pennoni.com | MEllis@Pennoni.com
[Logo: Pennoni 50th PARTNERS FOR WHAT'S POSSIBLE]
[Handwritten note:
4-8-16
Recommend we increase budget
Rick]
1