Municipal Authority
The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.
The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.
- Five members, serving five-year terms
- Meetings are on the 2nd Monday of the month at 7:00 P.M.
- All township meetings are held at the Township Building and open to the public
| Authority Members | Term Expiration Date |
| Kevin Cummings, Chairman | 2026 |
| John Stipe, Vice Chairman |
2029 |
| Dana Pizzarro, Secretary | 2026 |
| Sean Ellsworth, Assistant Secretary/Treasurer | 2028 |
| Walter Wujcik, Treasurer | 2028 |
| Pennoni Associates, Engineer | |
| Patrick M. McKenna, Esq. | |
| Peter Hicks, BoS Liaison | |
| Kevin Miller, Staff Liaison |
Documents
Back to the list | Open the original PDF
Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.
EAST GOSHEN MUNICIPAL AUTHORITY
July 9, 2018
7:00 PM
- CALL TO ORDER/PLEDGE OF ALLEGIANCE/MOMENT OF SILENCE Ask if anyone will be taping the meeting
- CHAIRMAN’S REPORT/OTHER MEMBERS REPORTS
- SEWER REPORTS Director of Public Works Report.; Pennoni Engineer’s Report.; Big Fish Environmental Report.
- APPROVAL OF MINUTES June 11, 2018
- APPROVAL OF INVOICES Invoice Amount Pennoni Invoice #808974 $ 581.48 Pennoni Invoice #808975 $ 327.75 Pennoni Invoice #808976 $ 4,869.00 Pennoni Invoice #808977 $ 30.75 Gawthrop Greenwood Invoice #196673 $ 440.00
- LIAISON REPORTS
- FINANCIAL REPORTS June Financial Report; Analysis of Pennoni Engineering Budget
- OLD BUSINESS
- GOALS Continue to monitor the upgrades at West Goshen Sewer Plant. Jack and Phil have been attending meetings.de; Continue to implement the I&I Plan – 3-8-2018 completed
F:\Data\Shared Data\Agendas\Municipal Authority\2018\7-9-18.doc
- Submit articles for the newsletter - none
- NEW BUSINESS Discuss the preliminary proposed CIP; Approval for the purchase to replace modems at metering stations
- CAPACITY REQUESTS
- ANY OTHER MATTER
- CORRESPONDENCE AND REPORTS OF INTEREST
- PUBLIC COMMENT
- ADJOURNMENT
F:\Data\Shared Data\Agendas\Municipal Authority\2018\7-9-18.doc
AREA CODE 610
692-7171
EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199
July 6, 2018
To: Municipal Authority
From: Mark Miller
Re: June 2018 Monthly Report
Monthly Flows: The average daily flow to West Goshen was 782,000 gallons per day. No problems to report.
Meters: The meters are being read on a daily basis, we had to clean the meter pits as part of our maintenance.
C.C. Collection: The pump stations were checked on a daily basis. There were no problems at any of the pump stations for the month of June. We received a call for a cloged lateral at 612 Marydell Dr. We tried to plunge the line but that was unsuccessful so we tried to jet the lateral; after several attempts we cleared the lateral. Aqua Water will be replacing the water lines in Marydell, so we cleaned and televised the lines and physically marked the laterals. We cleaned and televised 6500lf of pipe.
R.C. Collection: The pump station was visited on a daily basis; the wet well was cleaned twice this month due to excessive grease build up. We cleaned and televised the sewer lines in the Hadleigh Development in preparation of the road paving.
Ridley Creek: Blower B1B failed and has been removed and taken to Deckens for repair. Scott asked me to get the influent meter checked as is was reading high. John Laidly was notified and came out; removed the probe and placed it back in service. John recommended that we plug the influent line so he can calibrate the meter. I ordered a plug in the event he decides to plug the line.
Lateral Repairs: We received 11 requests for sewer caps between both systems.
Alarms: We responded to 25 alarms for June which were all various issues.
PA One Calls: We received 74 PA One calls June.
Pennoni
Christiana Executive Campus
121 Continental Drive, Suite 207
Newark, DE 19713
T: 302-655-4451
F: 302-654-2895
www.pennoni.com
EAST GOSHEN MUNICIPAL AUTHORITY
ENGINEER'S REPORT
July 5, 2018
Invoices
- Invoices with summaries are provided under separate cover.
Ridley Creek Sewage Treatment Plant (RCSTP)
- Caustic soda pilot study – We are analyzing study data in coordination with Big Fish. We anticipate a summary report will be issued prior to the August MA meeting.
RCSTP and Pump Stations' O&M Manual
- We recommend the Manual be revisited in July-August 2018 to determine if updates are needed and/or if new information has become available to incorporate.
Supplee Valley Pipe Lining
- SWERP completed lining of all contracted sewers on February 21. They subsequently installed supplemental lateral saddle liners in 3 of 6 locations in April that were approved via change order. One of the lateral locations cannot be lined or grouted due to the severe angle of connection between the lateral and the main; however, this location only had a very minor infiltration leak. We are continuing to coordinate with the PW Department and SWERP to evaluate the feasibility of installing saddles in the other two difficult-to-access laterals as well as the one spot repair lateral liner that was approved via change order. Lastly, the contractor still needs to perform injection grouting in two manholes. Once we resolve the accessibility, we will pursue a schedule from the contractor to complete the work. No update since our last report. Accessibility has been resolved, but SWERP has not provided a schedule to complete the work.
Barkway Pump Station Grinder
- We met with Mark Miller on June 5 to review our design plans. We are re-evaluating the feasibility of coring the wet well to run the hydraulic lines rather than entering through the top of the wet well steel hatch. However, a site investigation is required to accurately determine coring feasibility due to inconsistencies in how the foundation is shown on the original pump station design plans. The design plans will be finalized thereafter. No update since our last report.
Ashbridge Pump Station Force Main
- Test pits will be performed to identify backfill conditions along Manley Road with one test pit on Edith Road, as recommended by the Municipal Authority, when weather permits. No update since our last report.
Tallmadge Drive Sewer Main Replacement
- We revised the bid document for re-bid including insurance changes as discussed at the June MA meeting. The first advertisement will be issued on July 9, and the following re-bid schedule is proposed: Bids Due = August 7; Award = August 13
EGMAU18001
July 5, 2018
Page 2
East Goshen Municipal Authority
Engineer's Report
- Contract Execution = late August
- Construction = Anytime between late August and December 15 (must be completed within 20 consecutive days)
I&I Support and Reporting
- We intend to analyze meter data and submit the next semi-annual I&I report following completion of the Supplee Valley pipe lining project so that the impact of that project can be assessed. That report will likely be issued in the July-August timeframe. We propose to make a summary Powerpoint presentation at a MA meeting immediately thereafter. No update since our last report.
New Connections
- We reviewed two revised plan submissions for a proposed residential grinder pump sewer connection at 1506 Meadowbrook Lane.
West Goshen Sewer System Consultation
- No activity since last report.
C:\Users\ssmith.EGT\AppData\Local\Microsoft\Windows\INetCache\Content.Outlook\UKYSSHOT\Engineers Report 2018-07-05.docx
EGMAU18001
July 5, 2018
Page 3
East Goshen Municipal Authority
Engineer's Report
Big Fish Environmental Services Inc.
RCSTP Monthly Operations Report:
June 2018
Executive Summary
The Ridley Creek sewage treatment plant outfall 001 achieved compliance with the permitted effluent discharge limitations for during the month of May 2018. Discharge to the Applebrook storm water lagoon continued during the month. Chemical usage utilized for total phosphorus removal, pH and total alkalinity remained consistent with previous months. No significant mechanical or operational issues were observed during operation of sludge dewatering equipment or SBR treatment process.
Treatment Process Operation
Table 1 illustrates the final effluent composite sample data reported for the May 2018 DMR.
Table 1
May 2018 - Final Effluent - Out Fall 001
| NPDES Permit Discharge Limitations | Flow | CBOD5 | TSS | NH4-N | Phosphorus,Total , mg/L | Fecal Coliform | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | Geo Mean | Geo Mean | |
| 0.75 | 20 40 |
125 | 10 42 |
131 | 2.5 | 44 | 0.5 | 3 | 200 | 1,000 | |
| Sample Date | |||||||||||
| May 1, 2018 | 0.210 | 4.3 | 7.5 | 3 | 5.3 | 0.251 | 0.44 | 0.31 | 0.54 | 1 | 0.0000 |
| May 4, 2018 | 0.210 | 6 | 10.5 | ||||||||
| May 8, 2018 | 0.209 | 2.0 | 3.5 | 2 | 3.5 | 0.100 | 0.17 | 0.17 | 0.30 | 2 | 0.3010 |
| May 15, 2018 | 0.241 | 5.0 | 10.0 | 5 | 10.0 | 0.100 | 0.20 | 0.23 | 0.46 | 2 | 0.3010 |
| May 18, 2018 | 0.243 | 6 | 12.2 | ||||||||
| May 22, 2018 | 0.278 | 4.2 | 9.7 | 4 | 9.3 | 0.176 | 0.41 | 0.20 | 0.46 | 1 | 0.0000 |
| May 29, 2018 | 0.207 | 5.6 | 9.7 | 3 | 5.2 | 0.100 | 0.41 | 0.19 | 0.33 | 1 | 0.0000 |
| Average | 0.228 | 4.2 | 8.2 | 4 | 8.4 | 0.119 | 0.30 | 0.20 | 0.39 | 2 | 0.1505 |
| Minimum | 0.207 | 2.0 | 3.5 | 2 | 3.5 | 0.100 | 0.17 | 0.17 | 0.30 | 1 | 0.0000 |
| Maximum | 0.278 | 5.6 | 10.0 | 6 | 12.2 | 0.251 | 0.44 | 0.31 | 0.54 | 2 | 0.3010 |
The total phosphorus monthly average was reported as 0.20 mg/L as compared to the permitted limitation of 0.50 mg/L. Total phosphorus discharge concentrations ranged from 0.17 to 0.31 mg/L. The ammonia as nitrogen monthly concentration was reported as 0.119 mg/L as compared to the permit discharge limitation of 2.5 mg/L. The ammonia as N weekly maximum was 0.251 mg/L. The total suspended
BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 1 of 9
Big Fish Environmental Services Inc.
RCSTP Monthly Operations Report:
June 2018
solids (TSS) monthly concentration was reported as 4 mg/L as compared to the permit discharge limitation of 10 mg/L. The weekly maximum concentration was 6 mg/L as compared to the permit discharge limitation of 15 mg/L.
Table 2 illustrates the final effluent composite sample data reported for the May 2018 DMR.
Table 2
May 2018 - Applebrook - Out Fall 002
| NPDES Permit Discharge Limitations | Flow | CBOD5 | TSS | NH4-N | Phosphorus,Total , mg/L | Fecal Coliform | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | Geo Mean | Geo Mean | |
| 0.75 | 20 40 |
125 | 21 42 |
131 | 7 | 44 | 0.5 | 3 | 200 | 1,000 | |
| Sample Date | |||||||||||
| May 1, 2018 | 0.1426 | 4.3 | 5.1 | 3 | 3.6 | 0.251 | 0.299 | 0.31 | 0.37 | 1 | 0.0000 |
| May 4, 2018 | 0.1490 | 6 | 7.5 | ||||||||
| May 8, 2018 | 0.1423 | 2.0 | 2.4 | 2 | 2.4 | 0.100 | 0.119 | 0.17 | 0.20 | 2 | 0.3010 |
| May 15, 2018 | 0.1367 | 5.0 | 5.7 | 5 | 5.7 | 0.100 | 0.114 | 0.23 | 0.26 | 2 | 0.3010 |
| May 18, 2018 | 0.1131 | 6 | 5.7 | ||||||||
| May 22, 2018 | 0.1388 | 4.2 | 4.9 | 4 | 4.6 | 0.176 | 0.204 | 0.20 | 0.23 | 1 | 0.0000 |
| May 29, 2018 | 0.1353 | 5.6 | 6.3 | 3 | 3.4 | 0.100 | 0.113 | 0.19 | 0.21 | 1 | 0.0000 |
| Average | 0.1368 | 4.2 | 4.9 | 4 | 4.7 | 0.145 | 0.170 | 0.22 | 0.26 | 1 | 0.1204 |
| Minimum | 0.1131 | 2.0 | 2.4 | 2 | 2.4 | 0.100 | 0.113 | 0.17 | 0.20 | 1 | 0.0000 |
| Maximum | 0.1490 | 5.6 | 6.3 | 6 | 7.5 | 0.251 | 0.299 | 0.31 | 0.37 | 2 | 0.3010 |
The monthly average influent wastewater pollutant concentrations and loading entering the wastewater treatment facility remained within the design concentrations. Composite samples are collected at the influent doghouse manhole and influent wet well. The influent flow meter reading is collected from the influent flow meter located prior to the Screening Building, excluding the internal recycle flows.
Table 3 presents the available pollutant data for the influent wastewater collected at the doghouse manhole during May 2018.
BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 2 of 9
Big Fish Environmental Services Inc.
RCSTP Monthly Operations Report:
June 2018
Table 3
May 2018 - Influent Wastewater
| Design Basis | Flow | BOD5 | TSS | NH4-N | TKN, mg/L | Phosphorus,Total, mg/L | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | |
| 335 | 2,098 | 320 | 2,001 | 32 | 200 | 48 | 301 | 9.1 | 57 | ||
| Sample Date | |||||||||||
| May 1, 2018 | 0.560 | 175 | 818 | 262 | 1,224 | 32.1 | 150 | 33.5 | 157 | 5.6 | 26.2 |
| May 8, 2018 | 0.474 | 114 | 69 | 29.1 | 49.8 | 3.8 | |||||
| May 15, 2018 | 0.483 | 135 | 631 | 116 | 542 | 28.2 | 114 | 33.1 | 133 | 4.4 | 20.6 |
| May 22, 2018 | 0.536 | 209 | 977 | 264 | 1,234 | 30.0 | 134 | 25.8 | 115 | 5.9 | 27.6 |
| May 29, 2018 | 0.452 | 345 | 1,612 | 392 | 1,832 | 31.4 | 118 | 39.3 | 148 | 7.1 | 33.2 |
| Average | 0.501 | 196 | 1,009 | 221 | 1208 | 30.2 | 129 | 36.3 | 138 | 5.4 | 26.9 |
| Minimum | 0.452 | 114 | 631 | 69 | 542 | 28.2 | 114 | 25.8 | 115 | 3.8 | 20.6 |
| Maximum | 0.560 | 345 | 1,612 | 392 | 1832 | 32.1 | 150 | 49.8 | 157 | 7.1 | 33.2 |
Table 4 presents the available Outfall 001 final effluent data for the month of June 2018. Continued maintenance activities of cleaning the alum static mixer injector, flushing of the alum chemical piping to the SBRs and weekly draining and cleaning of the disc filters. The alum feed to the SBRs was frequently increased to improve the total phosphorus removal.
BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 3 of 9
Big Fish Environmental Services Inc.
RCSTP Monthly Operations Report:
June 2018
Table 4
June 2018 - Final Effluent - Out Fall 001
| NPDES Permit Discharge Limitations | Flow | CBOD5 | TSS | NH4-N | Phosphorus,Total , mg/L | Fecal Coliform | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | Geo Mean | Geo Mean | |
| 0.75 | 20 40 |
125 | 10 42 |
131 | 2.5 | 44 | 0.5 | 3 | 200 | 1,000 | |
| Sample Date | |||||||||||
| June 5, 2018 | 0.211 | 4.0 | 7.0 | 4 | 7.0 | 0.150 | 0.26 | 0.26 | 0.46 | 1 | 0.0000 |
| June 12, 2018 | 0.232 | 4.2 | 8.1 | 3 | 5.8 | 0.299 | 0.58 | 0.32 | 0.62 | 1 | 0.0000 |
| June 19, 2018 | 0.176 | 3.5 | 5.1 | 4 | 5.9 | 0.605 | 0.89 | 0.28 | 0.41 | 1 | 0.0000 |
| June 22, 2018 | 2 | 0.0 | |||||||||
| June 26, 2018 | 4 | 0.0 | 0.24 | 0.00 | |||||||
| June 28, 2018 | |||||||||||
| Average | 0.206 | 3.9 | 6.6 | 3 | 2.9 | 0.452 | 0.73 | 0.28 | 0.34 | 1 | 0.0000 |
| Minimum | 0.176 | 3.5 | 5.1 | 2 | 0.0 | 0.150 | 0.26 | 0.24 | 0.00 | 1 | 0.0000 |
| Maximum | 0.232 | 4.2 | 8.1 | 4 | 7.0 | 0.605 | 0.89 | 0.32 | 0.62 | 1 | 0.0000 |
The facility is anticipated to achieve compliance with the discharge permit limitations during the month of June 2018. Split sampling of the composite sample collected by Applied Laboratory Services (ALS) is ongoing for comparative analysis and daily results.
During June, the presence of foam conditions on the surface of the SBRs remained consistent at approximately 75% coverage of the surface area. The foam thickness is approximately 3 to 4 inches with a light to medium brown color. The warmer water temperatures within the SBRs, coupled with raising the food to mass ratios, the foam concentrations have decreased.
Table 5 presents the available June data for Outfall 002, Applebrook. The discharge limitations for Outfall 002 are anticipated to remain within compliance with the NPDES permit. Discharge to Applebrook, Outfall 002 was 4,343,728 gallons during June.
BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 4 of 9
Big Fish Environmental Services Inc.
RCSTP Monthly Operations Report:
June 2018
Table 5
June 2018 - Applebrook - Out Fall 002
| NPDES Permit Discharge Limitations | Flow | CBOD5 | TSS | NH4-N | Phosphorus,Total , mg/L | Fecal Coliform | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | mg/L | lbs/month | Geo Mean | Geo Mean | |
| 0.75 | 20 40 |
125 | 21 42 |
131 | 7 | 44 | 0.5 | 3 | 200 | 1,000 | |
| Sample Date | |||||||||||
| June 5, 2018 | 0.1362 | 4.0 | 4.5 | 4 | 4.5 | 0.150 | 0.170 | 0.26 | 0.30 | 1 | 0.0000 |
| June 12, 2018 | 0.1462 | 4.2 | 5.1 | 3 | 3.7 | 0.299 | 0.365 | 0.32 | 0.39 | 1 | 0.0000 |
| June 19, 2018 | 0.1476 | 3.5 | 4.3 | 4 | 4.9 | 0.605 | 0.745 | 0.28 | 0.34 | 1 | 0.0000 |
| June 22, 2018 | 2 | 0.0 | |||||||||
| June 26, 2018 | 4 | 0.0 | 0.24 | 0.00 | |||||||
| June 28, 2018 | |||||||||||
| Average | 0.1433 | 3.9 | 4.7 | 3 | 2.6 | 0.351 | 0.427 | 0.28 | 0.26 | 1 | 0.0000 |
| Minimum | 0.1362 | 3.5 | 4.3 | 2 | 0.0 | 0.150 | 0.170 | 0.24 | 0.00 | 1 | 0.0000 |
| Maximum | 0.1476 | 4.2 | 5.1 | 4 | 4.9 | 0.605 | 0.745 | 0.32 | 0.39 | 1 | 0.0000 |
Table 6 presents the available pollutant data for the influent wastewater collected at the doghouse manhole during June 2018.
Table 6
June 2018 - Influent Wastewater
| Design Basis | Flow | BOD5 | TSS | NH4-N | TKN, mg/L | Phosphorus,Total, mg/L | |||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | |
| 335 | 2,098 | 320 | 2,001 | 32 | 200 | 48 | 301 | 9.1 | 57 | ||
| Sample Date | |||||||||||
| June 5, 2018 | 0.476 | 124 | 492 | 174 | 691 | 28.9 | 115 | 28.0 | 111 | 3.3 | 13.1 |
| June 12, 2018 | 0.699 | 115 | 457 | 54 | 214 | 33.8 | 197 | 40.3 | 235 | 4.8 | 19.1 |
| June 19, 2018 | 0.515 | 211 | 838 | 103 | 409 | 38.3 | 165 | 36.0 | 155 | 4.8 | 19.1 |
| June 26, 2018 | 0.537 | ||||||||||
| Average | 0.557 | 150 | 596 | 110 | 438 | 33.7 | 159 | 34.8 | 167 | 4.3 | 17.1 |
| Minimum | 0.476 | 115 | 457 | 54 | 214 | 28.9 | 115 | 28.0 | 111 | 3.3 | 13.1 |
| Maximum | 0.699 | 211 | 838 | 174 | 691 | 38.3 | 197 | 40.3 | 235 | 4.8 | 19.1 |
BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 5 of 9
Big Fish Environmental Services Inc.
RCSTP Monthly Operations Report:
June 2018
Sequencing batch reactors (SBRs) numbered 2, 3 and 4 were in service during May and June. Process monitoring of each SBR included ammonia as N, nitrite as N, Nitrate as N, COD, SSV, MLSS and total phosphorus. Daily analysis of the final effluent flow equalization grab sample is total phosphorus is ongoing. Sample collection and analysis of the influent wastewater collected at the influent pump station wet well is ongoing.
Addition of aluminum sulfate solution to the SBRs to assist with phosphorus removal continued. Soda ash assists towards maintaining SBR pH concentrations above 7.0 standard units and assists to replenish alkalinity consumed during the nitrification process and aluminum sulfate solution addition.
Significant Rainfall
During June, there were eight (8) days when rainfall occurred. Six (6) storm events resulting in a daily precipitation amount equal to or greater than 0.5 inches measured during a 24-hour period as well as consecutive days of precipitation exceeding 0.5 inches of rainfall. A total of 2.12 inches of rainfall measured during the month. These events occurred on:
June 2nd 0.12 inches
June 3rd 0.61 inches
June 4th 0.59 inches
Three (3) consecutive days of rainfall for a total of 1.32 inches
June 11th >1.00 inch
June 28th 0.53 inches
Plant operations were adjusted to manage the precipitation to prevent exceedances of the permitted discharge limitations for Outfall 001. Adjustments included reading aeration minutes per cycle, extending decant minutes per cycle and reducing settling times.
PA DEP
No activity
Solids Dewatering and Disposal:
| June 2018 | |
|---|---|
| Gallons of sludge dewatered | 230,622 |
| Number of dumpsters | 4 |
*fifteen (15) days of centrifuge operation
BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 6 of 9
Big Fish Environmental Services Inc.
RCSTP Monthly Operations Report:
June 2018
Chemical Usage:
| June 2018 | ||
|---|---|---|
| Chemical | Daily Average | Total Monthly |
| Soda Ash | 295 | 9,000 |
| Aluminum Sulfate solution | 49.2 | 1,427 |
| Polymer (centrifuge) | 0.85 | 12.75 |
*Fifteen (15) days of centrifuge operation
Flow data:
| June 2018 | |||
|---|---|---|---|
| Flow Meter Location | Total Volume for Month, MG | Average Daily Flow, gpd | Daily Maximum Flow, gpd |
| Influent Wastewater to Screening Building* | 16.492 | 549,737 | 722,150 |
| Influent Wastewater to SBRs | 13.489 | 499,643 | 602,240 |
| Internal Recycle | Na | Na | Na |
| Treated Effluent to Disc Filters | 13.446 | 448,213 | 602,880 |
| Final Effluent Discharge | 6.037 | 201,233 | 358,000 |
| Applebrook Golf Course | 4.343 | 144,791 | 172,832 |
The field flow meter recorded elevated flows as compared to the flow meter measuring flow to the SBRs on an average of 100,000 gpd. Periodic inspection of the flow meter (without confined space entry) has been imitated during June to visually check for debris on the flow meter resulting in flow measurement errors. The filed flow meter was removed and recalibrated.
Minor Preventative Maintenance
- Flushed chemical feed lines to the SBRs.
- Cleaned piping within SBR building
- Cleaned final effluent weir trough daily
- Skimmed surface of disc filters daily
- Drained and cleaned disc filters bi-weekly
BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 7 of 9
Big Fish Environmental Services Inc.
RCSTP Monthly Operations Report:
June 2018
Major Preventative Maintenance Activities
Centrifuge
Contacted Alfa Laval to exchange tool. No response as of 6/28/2018.
Blower B1B
This blower is on the blowers used to provide air to the sludge holding and final effluent post flow equalization tanks. Assistance was provided to the electricians to turn the blowers on for inspection of the wiring. The blower is planned for removal and sent out for repair or replacement.
SBR 1
In preparation for putting SBR 1 online, the following tasks were completed:
- Replaced a 20-foot section of the alum feed line that was cracked.
- Unclogged the alum feed line near the feed point of a clog. We used the snake that is on site.
- Checked the decant valves, and replaced one that would not close. (We have 2 working spares, and a 3rd that probably will work after it soaks for a couple of days.)
- Removed, cleaned, and replaced the air relief valves on the decanter log.
- Installed the new Hach Sc200 controller, and new Hach LDO probe. (The probe was air calibrated in the bag, and the analog output to the Siemens control panel was confirmed.)
- We set up the WAS check valve so that we can pump WAS from SBR#2 to SBR#1.
On June 27th, the tank equalization process was initiated during the morning by opening the Influent valve to both tanks. When SBR 1 and SBR 2 tank volumes have equalized, transfer of the remaining contents of SBR 2 began using the SBR 2 sludge pump. SBR 1 sludge pumped was removed from the resting flange to prevent the pump impeller from spinning backwards. The transfer was completed at approximately 9:00 PM. McGovern was on site on June 28th at 7:00 AM to
BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 8 of 9
Big Fish Environmental Services Inc.
RCSTP Monthly Operations Report:
June 2018
begin the cleaning of the walls, floors and removal of the remaining contents. SBR 2 is ready for inspection and repairs.
SBR 3 is tentatively planned for removal on July 26th and SBR 4 on August 23rd.
Actuators for supplying Aluminum sulfate solution to the SBRs
We contacted the manufacturer of the Electric Valve Actuator on the alum feed system to the SBRs and have not received a response. There doesn't appear to be a difference in any of the part numbers between the new and old actuators. There is an internal difference in the number of cams on the motor shaft. There are two cams on the motor shaft with two micro-switches hanging above. These cams rotate with the shaft and activate the switches when the valve reaches the appropriate positions. There were an additional two cams and switches on the actuator that failed, however, they were removed and placed on one of the new replacement actuators. The new actuators only have two cams and two switches, while the alum valves in operation have four cams and switches. There might have been an add-on when they were originally ordered installed.
One actuator was repaired by swapping the capacitor out of the valve that Mark retrieved from the parts closet. It would be helpful if we could get four (4) new capacitors.
Recommended Projects
Summary
Recommend the installation of intake louvres, approximately floor to ceiling, on the wall where the blowers are located. On the opposite wall, installation of an exhaust fan. The configuration proposed would be like that of the blower room where the blowers for the SBRs are located.
Background
The blower room, where air is provided to the sludge holding and final effluent flow equalization tanks, has an internal temperature over 100 degrees Fahrenheit. Also located within the room are the disc filter feed pumps (dry mounted submersible pumps with cooling jackets), motor control panel for the blowers and an adjacent room housing motor control panel number 2, influent pump control panel and fine screen control panel. A small air conditioner is used to assist towards lowering the temperature in the small room where MCC no. 2 is located.
This excessive heat contributes to premature failure of the equipment.
BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 9 of 9
DRAFT
EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
MEETING MINUTES
June 11, 2018
The East Goshen Township Municipal Authority held their regular public meeting on Monday, June 11, 2018 at 7:00 pm at the East Goshen Township building. Members in attendance were: Chairman Jack Yahraes, Dana Pizarro, Kevin Cummings and Phil Mayer. Also in attendance were: Mark Miller (Director of Public Works), Jon Altshul (Asst. Township Manager), Stacey L. Fuller (attorney), Mike Ellis (Pennoni), Scott Towler (Plant Operator), and Walter Wujcik (Conservancy Board).
COMMON ACRONYMS:
| BFES – Big Fish Environmental Services | MA- Municipal Authority |
|---|---|
| BOS – Board of Supervisors | NPDES – National Pollutant Discharge Elimination System |
| CB – Conservancy Board | PC – Planning Commission |
| DEP – Department of Environmental Protection | PM – Prevention Maintenance |
| EPA – Environmental protection Agency | PR – Park & Recreation Board |
| HC – Historical Commission | RCSTP – Ridley Creek Sewer Treatment Plant |
| I&I – Inflow & Infiltration | SBR – Sequencing Batch Reactor |
| LCSTP – Lockwood Chase Sewer Treatment Plant | SSO – Sanitary System Overflow |
| WAS – Waste Activated Sludge |
Call to Order & Pledge of Allegiance
Jack called the meeting to order at 7:00 pm and led those present in the Pledge of Allegiance. There was a moment of silence to remember our troops and first responders.
Jack asked if anyone would be recording the meeting. There was no response.
Chairman's Report
Phil attended the West Goshen meeting. On July 11 they had a sewer tank overflow during a storm. They have a phone system to notify but it didn't work. At the EPA meeting they agreed that $75,000 in landscaping will be done. They still have to get Federal EPA approval. The $12,5 M fine payment from Sunoco for the Mariner pipeline was set up for grants for the 85 municipalities along the route. West Goshen is submitting a grant request for the $75,000. West Whiteland and Westtown agreements are not signed. Rates were discussed. Phil provided copies of the graph of quarterly rates for all townships.
Sewer Reports
- Director of Public Works, Mark Miller's report for May: Monthly Flows: The average daily flow to West Goshen was 771,000 gallons per day. No problems to report. Meters: The meters are being read on a daily basis. No problems to report C.C. Collection: The pump stations were checked on a daily basis. Routine maintenance was performed at each station. Franc Environmental was utilized to clean and vacuum the wet wells. The floats were pulled up and cleaned at all the pump stations and the plant. R.C. Collection: The station was visited on a daily basis. We continue to have a build-up of rags in the basket.
MA 6-11-18 draft 1
R.C. Plant: Equipment and parts were dropped off for Scott’s personnel to rebuild the centrifuge. The meter seems to be working correctly. The filter feed pump was rebuilt and reinstalled. .
Alarms: We responded to 10 alarms for May, which were all various issues.
PA One Calls: We received 68 PA One calls for May.
Lateral Repairs: We replaced 8 caps and found that 2 required pushing the stacks back into the tee.
Note: Aqua PA has notified us that they will be replacing the water main in Marydell. We will be cleaning and televising the lines and marking laterals as part of the PA One Call. This way they will have accurate locations. We will mark the depth and location of each lateral and main.
- Pennoni Engineer’s Report for May Mike Ellis provided the following report. Invoices Invoices with summaries are provided under separate cover. Multi-Year Capital Planning We performed a field visit to the Hunt Country Pump Station and began to evaluate concepts and budgetary costs for adding a Muffin Monster and flow meter to the station. We also performed field visits to obtain information on the Hershey’s Mill Pump Station emergency generator and the RCSTP generators in order to evaluate concepts and budgetary costs for generator replacements. We will provide concepts and budgetary costs prior to the July MA Meeting. The following list of future sewer system capital improvement projects (previously discussed at the November 2017 MA meeting) is updated to include the aforementioned projects (items 9-12 below), item #8 and some updates to other projects in italics: Supplee Valley Sewer System Pipe Lining - Nearly complete construction; Barkway Pump Station Muffin Monster – Submitted a grant application; planned to be constructed in 2018 if the grant is awarded or budgeted for 2019 if it is not awarded.; Ashbridge Pump Station Fore Main Rehabilitation; Tallmadge Drive Sewer Main Replacement – See project update hereafter; RCSTP SBR Tank Coatings – Tentatively planning to coat one tank per year from 2021-2014; RCSTP Caustic Soda Treatment Change – Tentatively planning to budget for 2020; Waterview Sewer System Rehabilitation; Ridley Creek Collection System 3 Permanent Gravity Sewer Meters – Tentatively budgeting for 2019.; Hunt Country Pump Station Muffin Monster – Consider budgeting for 2019; Hunt Country Pump Station Flow Meter – Consider budgeting for 2019; RCSTP Generator Replacement – Consider budgeting for 2019; Hershey’s Mill Pump Station Generator Replacement – Consider budgeting for 2019 Ridley Creek Sewage Treatment Plant (RCSTP) Caustic soda pilot study – The trial began on February 28 and concluded on May 6. Analysis of sampling data is ongoing and we are preparing a letter report of the results, potential
MA 6-11-18 draft 2
permanent caustic soda feed concept and capital cost estimate, and a cost benefit analysis of caustic soda vs. soda ash.
- Dutchland is scheduled to re-coat the core holes in SBR#1 on June 8, 2018 so that the tank can be put back into operation.
RCSTP and Pump Stations' O&M Manual
- We recommend the Manual be revisited in July-August 2018 to determine if updates are needed and/or if new information has become available to incorporate.
Supplee Valley Pipe Lining
- SWERP completed lining of all contracted sewers on February 21. They subsequently installed supplemental lateral saddle liners in 3 of 6 locations in April that were approved via change order. One of the lateral locations cannot be lined or grouted due to the severe angle of connection between the lateral and the main; however, this location only had a very minor infiltration leak. We are continuing to coordinate with the PW Department and SWERP to evaluate the feasibility of installing saddles in the other two difficult to access laterals as well as the one spot repair lateral liner that was approved via change order. Lastly, the contractor still needs to perform injection grouting in two manholes. Once we resolve the accessibility, we will pursue a schedule from the contractor to complete the work.
Barkway Pump Station Grinder
- We met with Mark Miller on June 5 to review our design plans. We are re-evaluating the feasibility of coring the wet well to run the hydraulic lines rather than entering through the top of the wet well steel hatch. However, a site investigation is required to accurately determine coring feasibility due to inconsistencies in how the foundation is shown on the original pump station design plans. The design plans will be finalized thereafter.
Ashbridge Pump Station Force Main
- Test pits will be performed to identify backfill conditions along Manley Road with one test pit on Edith Road, as recommended by the Municipal Authority, when weather permits. No update since our last report.
Tallmadge Drive Sewer Main Replacement
- We notified bidders that all bids were rejected.
- We have updated the bid document for re-bid in the following ways and met with Mark Miller on June 5 to review the changes: Bid items clearly indicate the Township will purchase aggregate materials and have them delivered and clarify that the cost of those materials shall not be included in the contractor bid prices.; A unit price bid item for "rock removal" was added.; A flexible schedule is proposed allowing the contractor to perform the work anytime before December 15, 2018.
MA 6-11-18 draft 3
- The contractor shall backfill with all 2A stone. The Township will perform all temporary and permanent paving.
- The contractor’s insurance coverage requirements have been reduced.
- We have prepared an updated opinion of probable cost based on the bid document changes, original bid prices, and conversations with the contractors following the first bid.
- The following re-bid schedule is proposed: Advertise = July 9 Bids Due = August 7 Award = August 13 Contract Execution = late August Construction = Anytime between late August and December 15 (must be completed within 20 consecutive days)
I&I Support and Reporting
- We intend to analyze meter data and submit the next semi-annual I&I report following completion of the Supplee Valley pipe lining project so that the impact of that project can be assessed. That report will likely be issued in the July-August timeframe. We propose to make a summary Powerpoint presentation at the MA meeting immediately thereafter. No update since our last report.
New Connections
- We discussed our comments on the proposed residential grinder pump sewer connection plans at 1506 Meadowbrook Lane via grinder pump with the applicant’s design consultant and we are awaiting a revised plan submission.
West Goshen Sewer System Consultation
- No activity since last report.
3. Big Fish Environmental Services – Scott’s report showed that the Ridley Creek sewage treatment plant outfall 001 achieved compliance with the permitted effluent discharge limitations during the month of April 2018. Discharge to the Applebrook storm water lagoon continued during the month. Chemical usage utilized for total phosphorus removal, pH and total alkalinity remained consistent with previous months. The caustic solution addition pilot study for pH control was completed on May 6th. No significant mechanical or operational issues were observed during operation of sludge dewatering equipment or SBR treatment process.
Approval of Minutes
The minutes of the May 14, 2018 meeting were approved as corrected.
Approval of Invoices
1. Kevin moved to approve payment of the following Pennoni invoices:
- Pennoni #803811 $ 168.68
- Pennoni #803812 $ 964.00
- Pennoni #803813 $6,309.75
- Pennoni #803814 $ 61.50
Dana seconded the motion. The motion passed unanimously.
There was discussion to move the Talmadge Drive project into a new budget item.
MA 6-11-18 draft 4
Liaison Reports
Conservancy Board - Walter reported that at the meeting this week they will discuss locations for bat houses. They did a site walk with the Marydell Pond Committee. Jon is applying for permits for this project.. They hope to have the permits by 9/1 so dredging can start. They discussed location of a foray for future sediment removal.
Financial Reports
Jon Altshul provided the following written report:
In May, the Municipal Authority recorded $57 in income (a $71 transfer from the now closed capital account offset by the cost of Positive Pay) and $1,787 in expenses (primarily annual fees to the Delaware River Basin Commission) for a negative variance of $1,730. To clarify, due to my oversight the Pennoni invoices approved at the May MA meeting were not processed until June. Therefore this report understates May expenses by $10,148.
In addition, earlier this week, I discovered a rather large discrepancy in the Sewer Operating Fund budget, fortunately one that works in the Township/MA’s benefit. Due to an error in the underlying debt service amortization schedule, the Township over-budgeted the principal payment on the 2008 MA note (for the Ridley Creek upgrade) by $187,000. As a result, it is likely that the Sewer Operating Fund will finish the year with a substantial surplus.
As of May 31st, the MA fund balance was $20,797, all of which is in the operating account.
Old Business
Insurance for Talmadge Drive – The insurance specs revision for Talmadge Drive project were reviewed. Discussed #1 Contractors Workers Comp insurance reduce to $100,000. #2 General Liability aggregate reduced to $1,000,000. Kevin feels the liability should be $2,000,000. Deductible changed from $0 to $5,000. Mike reported they were strongly advised not to reduce the class of the insurance company.
Adjournment
There being no further business, Dana moved to adjourn the meeting. Kevin seconded the motion. The meeting was adjourned at 8:15 p.m. The next regular meeting will be held on Monday, July 9, 2018 at 7:00 pm.
Respectfully submitted,
Ruth Kiefer
Recording Secretary
MA 6-11-18 draft 5
Pennoni
INVOICE
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice #: 808974
Invoice Date: 06/28/2018
Project: EGMAU17006
Project Name: Barkway PS Muffin Monster
For Services Rendered through: 6/17/2018
Review meeting with Mark Miller about near-final design plan submission; and follow-up evaluation of hydraulic lines routing and generator capacity.
| Phase Code / Name | Contract Amount | Previously Billed | % Complete | Complete To Date | Amount This Invoice |
|---|---|---|---|---|---|
| **** -- Professional Services | $9,000.00 | $7,769.99 | 92.79% | $8,351.47 | $581.48 |
| Total : | $9,000.00 | $7,769.99 | $8,351.47 | $581.48 |
Amount Due This Invoice: $581.48
[Handwritten: ok MSM 7/6/2018]
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMAU17006 Invoice Summary
Invoice Date 5/24/2018
| Project: | EGMAU17006 | ||
|---|---|---|---|
| Pennoni Job No.: | Barkway PS Muffin Monster | ||
| Invoice No: | 808974 | ||
| Invoice Period: | 5/21/2018 | to | 6/17/2018 |
| Initial Authorization: | $ 9,000.00 | Date: | 6/28/2018 |
| Contract Amount: | $ 9,000.00 | ||
| Previously Invoiced: | $ 7,769.99 | ||
| Current Invoice: | $ 581.48 | ||
| Invoiced to Date ($): | $ 8,351.47 | ||
| Invoiced to Date (%): | 93% | ||
| Remaining Budget ($): | $ 648.53 | ||
| Remaining Budget (%): | 7% |
Budget by Phase:
| Phase Name: | Barkway PS Muffin Monster |
|---|---|
| Phase Budget: | $ 9,000.00 |
| Previously Invoiced: | $ 7,769.99 |
| Current Invoice: | $ 581.48 |
| Invoiced to Date ($): | $ 8,351.47 |
| Invoiced to Date (%): | 93% |
| Remaining Budget ($): | $ 648.53 |
| Remaining Budget (%): | 7% |
Comments: Review meeting with Mark Miller about near-final design plan submission; and follow-up evaluation of hydraulic lines routing and generator capacity.
INVOICE
Pennoni
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328
| East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380-6199 Attention: Louis F. Smith, Twp Mgr. |
Invoice # : 808975 Invoice Date : 06/28/2018 Project : EGMAU17007 Project Name : Supplee Valley CIPPL Construction |
|---|
For Services Rendered through: 6/17/2018
Review of additional alternative manhole grouting material submittals; and determination of approach to completing remaining lateral repairs and schedulding with PW Director and contractor.
Phase : **** -- Professional Services
| Total Phase : **** -- Professional Services | Labor : | 327.75 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 327.75 | |
| Amount Due This Invoice | $327.75 |
| Fee : | 15,000.00 |
|---|---|
| Prior Billings : | 13,783.00 |
| Current Billings : | 327.75 |
| Total Billings : | 14,110.75 |
Phase : **** -- Professional Services
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 1.00 | 123.00 | 123.00 |
| Associate Professional | 2.25 | 91.00 | 204.75 |
| Labor Total: | 3.25 | 327.75 |
| Total Phase : **** -- Professional Services | Labor : | $327.75 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMAU17007 -- Supplee Valley CIPPL Construction | Labor : | $327.75 |
| Expense : | $0.00 |
[Handwritten: ok MLM 7/6/2018]
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMAU17007 Invoice Summary
Invoice Date 6/28/2018
| Project: | EGMAU17007 | ||
|---|---|---|---|
| Pennoni Job No.: | Supplee Valley CIPPL Construction | ||
| Invoice No: | 808975 | ||
| Invoice Period: | 5/21/2018 | to | 6/17/2018 |
| Initial Authorization: | $ 12,000.00 | Date: | 6/28/2018 |
| Contract Amount: | $ 15,000.00 | ||
| Previously Invoiced: | $ 13,783.00 | ||
| Current Invoice: | $ 327.75 | ||
| Invoiced to Date ($): | $ 14,110.75 | ||
| Invoiced to Date (%): | 94% | ||
| Remaining Budget ($): | $ 889.25 | ||
| Remaining Budget (%): | 6% |
Budget by Phase:
| Phase Name: | Supplee Valley CIPP |
|---|---|
| Phase Budget: | $ 15,000.00 |
| Previously Invoiced: | $ 13,783.00 |
| Current Invoice: | $ 327.75 |
| Invoiced to Date ($): | $ 14,110.75 |
| Invoiced to Date (%): | 94% |
| Remaining Budget ($): | $ 889.25 |
| Remaining Budget (%): | 6% |
Comments: Review of additional alternative manhole grouting material submittals; and determination of approach to completing remaining lateral repairs and schedulding with PW Director and contractor.
INVOICE
Pennoni
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328
| East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380-6199 Attention: Louis F. Smith, Twp Mgr. |
Invoice # : 808976 Invoice Date : 06/28/2018 Project : EGMAU18001 Project Name : 2018 General Services |
|---|
For Services Rendered through: 6/17/2018
Phase **** Professional Services - Prepared June Engineer's Report; reviewed June RCSTP operator's report; prepared for and attended June MA meeting; analyzed RCSTP caustic soda trial sampling data following completion of study and initiated summary report; coordinated with Dutchland for re-coating of core holes in SBR #1 and observed work on-site; site visit to Hunt Country Pump Station for initial scoping of future Muffin Monster and flow meter improvements; site visits to RCSTP and Hershey's Mill Pump Station for initial scoping of future generator replacements; initiated budgetary cost estimating for aforementioned RCSTP, Hunt Country PS, and Hershey's Mill PS capital improvements; and reviewed Township's long-range sewer system capital projects' financial forecast and provided comments. Phase **** Total Effort To-Date = $10,637.75
Phase 01 Tallmadge Drive Sewer Replacement - Modified plans and specifications in preparation for re-bidding, prepared re-bid schedule, evaluated insurance coverage modifications with insurance carrier, emailed proposed insurance changes to the MA and Township for review, attended meeting with PW Director to review proposed project changes, and updated cost estimate. Phase 01 Total Effort To-Date = $10,556.75
Phase : **** -- Professional Services
| Total Phase : **** -- Professional Services | Labor : | 2,889.00 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 2,889.00 |
Phase : 01 -- Tallmadge Drive Sewer Replacement
| Total Phase : 01 -- Tallmadge Drive Sewer Replacement | Labor : | 1,980.00 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 1,980.00 | |
| Amount Due This Invoice | $4,869.00 |
| Fee : | 30,000.00 |
|---|---|
| Prior Billings : | 16,325.50 |
| Current Billings : | 4,869.00 |
| Total Billings : | 21,194.50 |
[Handwritten: ok MLM 7/6/2018]
Continued on next page...
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
Project : EGMAU18001 -- 2018 General Services
Invoice # : 808976
...Continued from previous page
Phase : **** -- Professional Services
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 8.75 | 123.00 | 1,076.25 |
| Senior Professional | 6.00 | 117.00 | 702.00 |
| Associate Professional | 10.25 | 91.00 | 932.75 |
| Sr. Engineering Technician | 2.00 | 89.00 | 178.00 |
| Labor Total: | 27.00 | 2,889.00 |
| Total Phase : **** -- Professional Services | Labor : | $2,889.00 |
|---|---|---|
| Expense : | $0.00 |
Phase : 01 -- Tallmadge Drive Sewer Replacement
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 1.75 | 123.00 | 215.25 |
| Senior Professional | 0.50 | 117.00 | 58.50 |
| Associate Professional | 18.75 | 91.00 | 1,706.25 |
| Labor Total: | 21.00 | 1,980.00 |
| Total Phase : 01 -- Tallmadge Drive Sewer Replacement | Labor : | $1,980.00 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMAU18001 -- 2018 General Services | Labor : | $4,869.00 |
| Expense : | $0.00 |
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
Pennoni Associates Inc. Page: 2
East Goshen Municipal Authority
EGMAU18001 Invoice Summary
Invoice Date 6/28/2018
| Project: | EGMAU18001 | ||
|---|---|---|---|
| Pennoni Job No.: | 2018 General Services | ||
| Invoice No: | 808976 | ||
| Invoice Period: | 5/21/2018 | to | 6/17/2018 |
| Initial Authorization: | $ 18,000.00 | Date: | 6/28/2018 |
| Contract Amount: | $ 26,820.25 | ||
| Previously Invoiced: | $ 16,325.50 | ||
| Current Invoice: | $ 4,869.00 | ||
| Invoiced to Date ($): | $ 21,194.50 | ||
| Invoiced to Date (%): | 79% | ||
| Remaining Budget ($): | $ 5,625.75 | ||
| Remaining Budget (%): | 21% |
Budget by Phase:
| Phase Name: | 2018 General Services |
|---|---|
| Phase Budget: | $ 26,820.25 |
| Previously Invoiced: | $ 16,325.50 |
| Current Invoice: | $ 4,869.00 |
| Invoiced to Date ($): | $ 21,194.50 |
| Invoiced to Date (%): | 79% |
| Remaining Budget ($): | $ 5,625.75 |
| Remaining Budget (%): | 21% |
Comments: Phase **** Professional Services - Prepared June Engineer's Report; reviewed June RCSTP operator's report; prepared for and attended June MA meeting; analyzed RCSTP caustic soda trial sampling data following completion of study and initiated summary report; coordinated with Dutchland for re-coating of core holes in SBR #1 and observed work on-site; site visit to Hunt Country Pump Station for initial scoping of future Muffin Monster and flow meter improvements; site visits to RCSTP and Hershey's Mill Pump Station for initial scoping of future generator replacements; initiated budgetary cost estimating for aforementioned RCSTP, Hunt Country PS, and Hershey's Mill PS capital improvements; and reviewed Township's long-range sewer system capital projects' financial forecast and provided comments. Phase **** Total Effort To-Date = $10,637.75
Phase 01 Tallmadge Drive Sewer Replacement - Modified plans and specifications in preparation for re-bidding, prepared re-bid schedule, evaluated insurance coverage modifications with insurance carrier, emailed proposed insurance changes to the MA and Township for review, attended meeting with PW Director to review proposed project changes, and updated cost estimate. Phase 01 Total Effort To-Date = $10,556.75
INVOICE
Pennoni
Newark, DE
302-655-4451 Fax: 302-654-2895
Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328
| East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380-6199 Attention: Louis F. Smith, Twp Mgr. |
Invoice # : 808977 Invoice Date : 06/28/2018 Project : EGMAU18002 Project Name : 2018 I&I Support and Reports |
|---|
For Services Rendered through: 6/17/2018
Coordination with Township for analysis of instantaneous permanent meter data.
Phase : **** -- Professional Services
| Total Phase : **** -- Professional Services | Labor : | 30.75 |
|---|---|---|
| Expense : | 0.00 | |
| Phase Total : | 30.75 | |
| Amount Due This Invoice | $30.75 |
| Fee : | 11,000.00 |
|---|---|
| Prior Billings : | 2,502.00 |
| Current Billings : | 30.75 |
| Total Billings : | 2,532.75 |
Phase : **** -- Professional Services
Labor
| Class | Hours/Units | Rate | Amount |
|---|---|---|---|
| Authority Engineer | 0.25 | 123.00 | 30.75 |
| Labor Total: | 0.25 | 30.75 |
| Total Phase : **** -- Professional Services | Labor : | $30.75 |
|---|---|---|
| Expense : | $0.00 | |
| Total Project : EGMAU18002 -- 2018 I&I Support and Reports | Labor : | $30.75 |
| Expense : | $0.00 |
[Handwritten: ok MLM 7/6/2018]
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
East Goshen Municipal Authority
EGMAU18002 Invoice Summary
Invoice Date 6-28-2018
| Project: | EGMAU18002 | ||
|---|---|---|---|
| Pennoni Job No.: | 2018 I&I Support and Reports | ||
| Invoice No: | 808977 | ||
| Invoice Period: | 5/21/2018 | to | 6/17/2018 |
| Initial Authorization: | $ 11,000.00 | Date: | 6/28/2018 |
| Contract Amount: | $ 11,000.00 | ||
| Previously Invoiced: | $ 2,502.00 | ||
| Current Invoice: | $ 30.75 | ||
| Invoiced to Date ($): | $ 2,532.75 | ||
| Invoiced to Date (%): | 23% | ||
| Remaining Budget ($): | $ 8,467.25 | ||
| Remaining Budget (%): | 77% |
Budget by Phase:
| Phase Name: | 2018 I&I Support and Reports |
|---|---|
| Phase Budget: | $ 11,000.00 |
| Previously Invoiced: | $ 2,502.00 |
| Current Invoice: | $ 30.75 |
| Invoiced to Date ($): | $ 2,532.75 |
| Invoiced to Date (%): | 23% |
| Remaining Budget ($): | $ 8,467.25 |
| Remaining Budget (%): | 77% |
Comments: Coordination with Township for analysis of instantaneous permanent meter data.
Gawthrop Greenwood, PC
Attorneys at Law
17 East Gay Street, Suite 100
West Chester, PA 19381-0562
gglaw@gawthrop.com
(p) 610-696-8225
(f) 610-344-0922
www.gawthrop.com
| East Goshen Municipal Authority 1580 Paoli Pike West Chester PA 19380 |
Page: 1 06/07/2018 Client No: 6604-001M Invoice No. 196673 |
|---|
General Authority Services
Fees
| Date | Timekeeper | Description | Hours | Amount |
|---|---|---|---|---|
| 05/11/2018 | PMM | Email from M Ellis regarding Tallmadge Drive bid status with memo and supporting documents; Review and analyze same. | 0.40 | |
| 05/14/2018 | PMM | Review file and analyze meeting packet in preparation for Authority meeting. | 0.30 | |
| SLF | Preparation for and attendance at meeting. | 1.50 | ||
| For Current Services Rendered | 2.20 | 440.00 | ||
Recapitulation
| Timekeeper | Hours | Hourly Rate | Total |
|---|---|---|---|
| Stacey L. Fuller | 1.50 | $200.00 | $300.00 |
| Patrick M. McKenna | 0.70 | 200.00 | 140.00 |
| Previous Balance | $480.00 |
|---|---|
| Total Current Charges | 440.00 |
| 05/21/2018 Payment | -480.00 |
| Balance Due | $440.00 |
To ensure proper credit, please write client number on your check when returning payment. Thank You.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.
Memo
| To: | Municipal Authority |
|---|---|
| From: | Lynn LeBlanc |
| Re: | MA June Financial Report |
| Date: | July 03, 2018 |
In June, the Municipal Authority recorded $13,167 in income (including $30,000 from a transfer from the Sewer Operating Fund) and $11,917 in expenses, for a positive variance of $2,962.99.
I have also included in your packet a memo with recommendations for amending the 2018 MA budget, as well as Mark's recommendations for long-range capital planning.
As of June 30th, the MA fund balance was $25,009.78.
EAST GOSHEN TOWNSHIP
Other Funds
June 2018
Municipal Authority
| Account Title | Acct # | Annual Budget | Y-T-D Budget | Y-T-D Actual | Y-T-D Variance | M-T-D Budget | M-T-D Actual | M-T-D Variance |
|---|---|---|---|---|---|---|---|---|
| REVENUE | ||||||||
| INTEREST EARNINGS | 07341 1000 | 10 | 5 | (57.42) | (62.42) | (15.00) | (15.00) | |
| CAPITAL RESERVE-INTEREST | 07341 1010 | |||||||
| INTEREST EARNED - CONSTRUCTION | 07341 1020 | 50 | 50 | 613.94 | 563.94 | |||
| DCED GRANT | 07354 0400 | |||||||
| C.C. TAPPING FEES | 07364 1100 | 8,000 | 4,000 | (4,000.00) | 4,000 | (4,000.00) | ||
| R.C.TAPPING FEES | 07364 1110 | 2,000 | 2,000 | (2,000.00) | 2,000 | (2,000.00) | ||
| M.C. LOAN PAYMENTS | 07364 1120 | |||||||
| CONNECTION FEES - SEWER | 07364 1130 | 1,692 | 846 | 1,127.52 | 281.52 | 846 | (846.00) | |
| MISCELLANEOUS REVENUE | 07380 1000 | 564.48 | 564.48 | |||||
| TRANSFER FROM GENERAL ACCT | 07392 0100 | 71.30 | 71.30 | |||||
| TRANSFER FROM SEWER OPERATING | 07392 0500 | 75,853 | 37,926 | 60,000.00 | 22,074.00 | 6,321 | 30,000.00 | 23,679.00 |
| TRANSFER-ANNUAL CAP.RESERVE | 07392 0510 | |||||||
| GRANT REVENUE | 07392 0800 | |||||||
| LOAN PROCEEDS - SEWER PROJECT | 07392 0804 | |||||||
| TRANSFER FROM SEWER CAP RESERVE | 07392 0900 | |||||||
| TRANSFER FROM RCSTP BUDGET | 07392 0990 | |||||||
| LOAN PROCEEDS-SEWER PROJECT | 07393 1001 | |||||||
| TOTAL REVENUE | 87,605 | 44,827 | 62,319.82 | 17,492.82 | 13,167 | 29,985.00 | 16,818.00 | |
| EXPENSES | ||||||||
| ADMINISTRATIVE WAGES | 07424 1400 | 32,411 | 16,205 | 16,320.66 | (115.66) | 8,103 | 8,160.33 | (57.33) |
| R.C. LOAN ISSUANCE COSTS | 07424 1500 | |||||||
| MISCELLANEOUS EXPENSE | 07424 3000 | 2,500 | 1,250 | 1,336.00 | (86.00) | 209 | 209.00 | |
| MUNIC.AUTH.-AUDITING | 07424 3110 | 9,384 | 9,384 | 9,400.00 | (16.00) | |||
| ENGINEERING SERVICES | 07424 3130 | 43,260 | 21,630 | 47,366.32 | (25,736.32) | 3,605 | 17,126.18 | (13,521.18) |
| LEGAL SERVICES | 07424 3140 | 2,620.00 | (2,620.00) | 440.00 | (440.00) | |||
| W.G. C.C.STP-UPGRADE | 07424 7400 | |||||||
| MANHOLE COVER REPLACEMENTS | 07424 7405 | |||||||
| C.C. CAPITAL - METERS | 07424 7410 | |||||||
| C.C. CAPITAL- COLLECTION | 07424 7420 | |||||||
| C.C. CAPITAL- INTERCEPTOR | 07424 7430 | |||||||
| CAPITAL PROJ.-ENGINEERING | 07424 7431 | |||||||
| R.C. CAPITAL-STP | 07424 7440 | |||||||
| R.C. CAPITAL - COLLECTION | 07424 7450 | |||||||
| R.C.-CAP. PROJ.-ENGINEER | 07424 7451 | |||||||
| R.C. CAP EXPANSION GEN'L CONTRACTOR | 07424 7452 | |||||||
| R.C. CAP EXPANSION - ELECTRICAL | 07424 7453 | |||||||
| R.C. CAP EXP CONTINGENCY CAPITAL | 07424 7454 | |||||||
| R.C. CAP EXP CONTINGENCY ONGOING | 07424 7455 | |||||||
Report Date 1806 07/03/18 8 : 06 AM
EAST GOSHEN TOWNSHIP
Other Funds
June 2018
Municipal Authority
| Account Title | Acct # | Annual Budget | Y-T-D Budget | Y-T-D Actual | Y-T-D Variance | M-T-D Budget | M-T-D Actual | M-T-D Variance |
|---|---|---|---|---|---|---|---|---|
| R.C. CAP EXP ADDITIONAL CONTINGENCY | 07424 7456 | |||||||
| LOCHWOOD - CAPITAL -STP | 07424 7460 | |||||||
| LOCHWOOD-CAPITAL-COLLECT. | 07424 7470 | |||||||
| LOCHWOOD ABANDONMENT ENGINEER | 07424 7475 | |||||||
| LOCHWOOD ABANDONMENT CONSTRUCTION | 07424 7476 | |||||||
| LOCHWOOD ELIMINATION PHASE 2 | 07424 7477 | |||||||
| CAP.REPLACEMENT R.C. | 07424 7490 | |||||||
| CAPITAL REPLACEMENT ASHBRIDGE | 07424 7491 | |||||||
| MARYDELL PUMP STATION - ENGINEER | 07425 1000 | |||||||
| MARYDELL PUMP STATION -CONSTRUCTION | 07425 2000 | |||||||
| HERSHEY MILL STATION - ENGINEER | 07426 1000 | |||||||
| HERSHEY MILL STATION - CONSTRUCTION | 07426 2000 | |||||||
| RESERVE PUMP STATION - ENGINEER | 07427 1000 | |||||||
| RESERVE PUMP STATION - CONSTRUCTION | 07427 2000 | |||||||
| RESERVOIR PUMP STATION - ENGINEER | 07428 1000 | 188.00 | (188.00) | 45.50 | (45.50) | |||
| RESERVOIR PUMP STATION CONSTRUCTION | 07428 2000 | |||||||
| ASBESTOS CONCRETE ENGINEERING | 07429 3130 | |||||||
| DIVERSION PROJ.- LEGAL | 07429 3166 | |||||||
| WEST GOSHEN CAPITAL | 07429 6100 | 59,736 | 59,736 | 102,339.08 | (42,603.08) | |||
| M.C.-DVRFA-DEBT SERVICE | 07471 1000 | |||||||
| M.A.-R.C. DEBT SERVICE | 07471 1010 | |||||||
| DVRFA PUMPING STATIONS - PRINCIPAL | 07471 2000 | |||||||
| M.C.-DVRFA-INTEREST PAYMN | 07472 1000 | |||||||
| M.A.-R.C. INTEREST | 07472 1010 | |||||||
| DVRFA PUMPING STATIONS - INTEREST | 07472 2000 | |||||||
| TRANSFER TO GENERAL FUND | 07492 0100 | 71.30 | (71.30) | |||||
| TRANSFER TO SEW.OPERATING | 07492 0500 | |||||||
| TRF TO SEWER SINKING FUND | 07492 0550 | |||||||
| TRANSFER TO AUTHORITY CAP FUND | 07492 0990 | |||||||
| TOTAL EXPENSES | 147,291 | 108,205 | 179,641.36 | (71,436.36) | 11,917 | 25,772.01 | (13,855.01) | |
| NET RESULT FROM OPERATIONS | (59,686) | (63,378) | (117,321.54) | (53,943.54) | 1,250 | 4,212.99 | 2,962.99 |
Report Date 1806 07/03/18 8 : 39 AM
June 2018 Municipal Authority Financial Report - YTD REVENUES & EXPENDITURES
January 1, 2018 Fund Balance 142,331.32
| Account # | Description | Per | Debits | Credits | Date | Name | Description |
|---|---|---|---|---|---|---|---|
| 07341-1000 | BEGINNING BALANCE | ||||||
| 07341-1000 | INTEREST EARNINGS | 1801 | 0 | 0.31 | 2/2/2018 | INTEREST EARNED JANUARY 2018 | 07 FUND |
| 07341-1000 | INTEREST EARNINGS | 1802 | 0 | 0.2 | 2/14/2018 | INTEREST ADJ. FROM JAN.2018 | 7105.2 |
| 07341-1000 | INTEREST EARNINGS | 1802 | 0 | 0.54 | 3/5/2018 | INTEREST EARNED FEBRUARY 2018 | 07 FUND |
| 07341-1000 | INTEREST EARNINGS | 1803 | 15 | 0 | 3/6/2018 | REIMBURSE S/R FOR BANK FEES | INTEREST EARNINGS |
| 07341-1000 | INTEREST EARNINGS | 1803 | 0 | 0.47 | 4/2/2018 | INTEREST EARNED MARCH 2018 | 07 FUND |
| 07341-1000 | INTEREST EARNINGS | 1804 | 15 | 0 | 4/2/2018 | REIMB.S/R FOR 3/2018 BANK FEES | INTEREST EARNINGS |
| 07341-1000 | INTEREST EARNINGS | 1804 | 0 | 0.55 | 5/1/2018 | INTEREST EARNED APRIL 2018 | 07 FUND |
| 07341-1000 | INTEREST EARNINGS | 1805 | 15 | 0 | 5/1/2018 | REIMBURSMT- 4/2018 BANK FEES | INTEREST EARNINGS |
| 07341-1000 | INTEREST EARNINGS | 1805 | 15 | 0 | 6/1/2018 | BANK FEES - MAY 2018 | INTEREST EARNINGS |
| 07341-1000 | INTEREST EARNINGS | 1805 | 0 | 15 | 6/5/2018 | REVERSE TRX 63388 EXPENSE TO | BE ENTERED IN JUNE NOT MAY |
| 07341-1000 | INTEREST EARNINGS | 1805 | 0 | 0.51 | 6/1/2018 | INTEREST EARNED MAY 2018 | 07 FUND |
| 07341-1000 | INTEREST EARNINGS | 1806 | 15 | 0 | 6/5/2018 | REIMBURSE S/R FOR MAY '18 FEES | INTEREST EARNINGS |
| 07341-1020 | BEGINNING BALANCE | ||||||
| 07341-1020 | INTEREST EARNED - CONSTRUCTION | 1801 | 0 | 391.64 | 2/2/2018 | INTEREST EARNED JANUARY 2018 | 07 FUND |
| 07341-1020 | INTEREST EARNED - CONSTRUCTION | 1802 | 0 | 69.31 | 3/5/2018 | INTEREST EARNED FEBRUARY 2018 | 07 FUND |
| 07341-1020 | INTEREST EARNED - CONSTRUCTION | 1803 | 0 | 81.66 | 4/2/2018 | INTEREST EARNED MARCH 2018 | 07 FUND |
| 07341-1020 | INTEREST EARNED - CONSTRUCTION | 1804 | 0 | 71.3 | 5/1/2018 | INTEREST EARNED APRIL 2018 | 07 FUND |
| 07341-1020 | INTEREST EARNED - CONSTRUCTION | 1805 | 0 | 0.03 | 6/1/2018 | INTEREST EARNED MAY 2018 | 07 FUND |
| 07364-1130 | BEGINNING BALANCE | ||||||
| 07364-1130 | CONNECTION FEES - SEWER | 1801 | 0 | 423 | 1/25/2018 | STOFFLET, MICHAEL | |
| 07364-1130 | CONNECTION FEES - SEWER | 1801 | 0 | 423 | 2/13/2018 | JACOBS, ROBERT & CHERYL | |
| 07364-1130 | CONNECTION FEES - SEWER | 1802 | 0 | 423 | 2/27/2018 | GEORGE SMITH & CHRISTINA CONLE | |
| 07364-1130 | CONNECTION FEES - SEWER | 1802 | 282.2 | 0 | 2/13/2018 | ANNUAL PINE ROCK INSTALLMENT | JACOBS & STOFFLET INTEREST |
| 07364-1130 | CONNECTION FEES - SEWER | 1802 | 141.1 | 0 | 2/27/2018 | ANNUAL PINE ROCK INSTALLMENT | |
| 07364-1130 | CONNECTION FEES - SEWER | 1803 | 0 | 423 | 3/23/2018 | PAPPANO, JOSEPH & PATRICIA | |
| 07364-1130 | CONNECTION FEES - SEWER | 1803 | 141.1 | 0 | 3/23/2018 | ANNUAL PINE ROCK INSTALLMENT | RC214 PAPPANO |
| 07380-1000 | BEGINNING BALANCE | ||||||
| 07380-1000 | MISCELLANEOUS REVENUE | 1802 | 0 | 282.24 | 2/13/2018 | ANNUAL PINE ROCK INSTALLMENT | JACOBS & STOFFLET INTEREST |
| 07380-1000 | MISCELLANEOUS REVENUE | 1802 | 0 | 141.12 | 2/27/2018 | ANNUAL PINE ROCK INSTALLMENT | |
| 07380-1000 | MISCELLANEOUS REVENUE | 1803 | 0 | 141.12 | 3/23/2018 | ANNUAL PINE ROCK INSTALLMENT | RC214 PAPPANO |
| 07392-0100 | BEGINNING BALANCE | ||||||
| 07392-0100 | TRANSFER FROM GENERAL ACCT | 1805 | 0 | 71.3 | 6/7/2018 | XFER $ TO MA REGARDING DEPOSIT | ERROR 5/10/18 |
| 07392-0500 | BEGINNING BALANCE | ||||||
| 07392-0500 | TRANSFER FROM SEWER OPERATING | 1803 | 0 | 30000 | 3/29/2018 | XFER $ FROM SEWER TO MUNICIPAL | TO COVER EXPENSES |
| 07392-0500 | TRANSFER FROM SEWER OPERATING | 1806 | 0 | 30000 | 6/22/2018 | XFER $ FROM SEWER TO MA | |
| 07424-1400 | BEGINNING BALANCE | ||||||
| 07424-1400 | ADMINISTRATIVE WAGES | 1803 | 8160 | 0 | 3/26/2018 | EAST GOSHEN TOWNSHIP - GENERAL | 1ST QTR.2018 REIMBURSEMENT - MA |
| 07424-1400 | ADMINISTRATIVE WAGES | 1806 | 8160 | 0 | 6/21/2018 | EAST GOSHEN TOWNSHIP - GENERAL | 2ND QTR.2018 REIMBURSEMENT - MA |
| 07424-3000 | BEGINNING BALANCE | ||||||
| 07424-3000 | MISCELLANEOUS EXPENSE | 1801 | 100 | 0 | 1/31/2018 | COMMONWEALTH FINANCING AUTHORITY | GRANT APPLIC. DCED - WATER & SEWER |
| 07424-3000 | MISCELLANEOUS EXPENSE | 1805 | 1236 | 0 | 5/30/2018 | DELAWARE RIVER BASIN COMMISSION | ANNUAL FEE D-2000-030 CP WASTE |
| 07424-3110 | BEGINNING BALANCE | ||||||
| 07424-3110 | MUNIC.AUTH.-AUDITING | 1803 | 6964 | 0 | 3/22/2018 | MAILLIE FALCONIERO & CO. | PROGRESS BILLING - M.AUTHORITY 2017 |
| 07424-3110 | MUNIC.AUTH.-AUDITING | 1804 | 2436 | 0 | 4/17/2018 | MAILLIE FALCONIERO & CO. | EXAMINATION 2017 MA FINANCIAL STMTS |
| 07424-3130 | BEGINNING BALANCE | ||||||
| 07424-3130 | ENGINEERING SERVICES | 1801 | 12524 | 0 | 1/24/2018 | PENNONI ASSOCIATES INC. | SERV.THRU 12/10/17 2017 GENERAL |
| 07424-3130 | ENGINEERING SERVICES | 1802 | 5415 | 0 | 2/15/2018 | PENNONI ASSOCIATES INC. | SERVICES THRU 1/14/18 -2017 GENERAL |
| 07424-3130 | ENGINEERING SERVICES | 1802 | 552.5 | 0 | 2/22/2018 | PENNONI ASSOCIATES INC. | SERVICE THRU 1/14/18 SUPPLEE VAL. |
| 07424-3130 | ENGINEERING SERVICES | 1803 | 11749 | 0 | 3/15/2018 | PENNONI ASSOCIATES INC. | SERVICES THRU 2/11/18 2018 GEN.SERV |
| Account # | Description | Per | Debits | Credits | Date | Name | Description |
|---|---|---|---|---|---|---|---|
| 07424-3130 | ENGINEERING SERVICES | 1806 | 9622 | 0 | 6/7/2018 | PENNONI ASSOCIATES INC. | SERVICES THRU 4/15/18 SUPPLEE VAL. |
| 07424-3130 | ENGINEERING SERVICES | 1806 | 7504 | 0 | 6/12/2018 | PENNONI ASSOCIATES INC. | SERVICES THRU 5/20/18 BARKWAY PS |
| 07424-3140 | BEGINNING BALANCE | ||||||
| 07424-3140 | LEGAL SERVICES | 1801 | 680 | 0 | 1/24/2018 | GAWTHROP GREENWOOD & HALSTED | LEGAL SERVICES DEC. 2017 GEN.AUTH. |
| 07424-3140 | LEGAL SERVICES | 1802 | 240 | 0 | 2/22/2018 | GAWTHROP GREENWOOD & HALSTED | LEGAL SERVICE - JAN.2018 GEN.AUTH. |
| 07424-3140 | LEGAL SERVICES | 1803 | 400 | 0 | 3/19/2018 | GAWTHROP GREENWOOD & HALSTED | LEGAL SERVICE - FEBRUARY 2018 |
| 07424-3140 | LEGAL SERVICES | 1804 | 380 | 0 | 4/17/2018 | GAWTHROP GREENWOOD & HALSTED | LEGAL SERVICE 3/12/18 |
| 07424-3140 | LEGAL SERVICES | 1805 | 480 | 0 | 5/16/2018 | GAWTHROP GREENWOOD & HALSTED | LEGAL SERVICE - APRIL 2018 GEN.AUTH |
| 07424-3140 | LEGAL SERVICES | 1806 | 440 | 0 | 6/18/2018 | GAWTHROP GREENWOOD & HALSTED | LEGAL SERV.- MAY 2018 GEN.AUTHORITY |
| 07428-1000 | BEGINNING BALANCE | ||||||
| 07428-1000 | RESERVOIR PUMP STATION - ENGINEEF | 1802 | 142.5 | 0 | 2/22/2018 | PENNONI ASSOCIATES INC. | SERVICE THRU 1/14/18 RESERV.RD PS |
| 07428-1000 | RESERVOIR PUMP STATION - ENGINEEF | 1806 | 45.5 | 0 | 6/7/2018 | PENNONI ASSOCIATES INC. | SERVICES THRU 4/15/18 RESERVOIR RD |
| 07429-6100 | BEGINNING BALANCE | ||||||
| 07429-6100 | WEST GOSHEN CAPITAL | 1801 | 30051 | 0 | 1/24/2018 | WEST GOSHEN SEWER AUTHORITY | 16.67% OF COST - ENHANCED CHEMICAL |
| 07429-6100 | WEST GOSHEN CAPITAL | 1802 | 3664 | 0 | 2/22/2018 | WEST GOSHEN SEWER AUTHORITY | 16.67% - ENHANCED CHEMICAL ADDITION |
| 07429-6100 | WEST GOSHEN CAPITAL | 1803 | -3664 | 0 | 3/15/2018 | WEST GOSHEN SEWER AUTHORITY | VOID CK. 2017 |
| 07429-6100 | WEST GOSHEN CAPITAL | 1804 | 72288 | 0 | 4/13/2018 | WEST GOSHEN SEWER AUTHORITY | 2017 SEWER SYSTEM REPAIR PROJECT |
| 07492-0100 | BEGINNING BALANCE | ||||||
| 07492-0100 | TRANSFER TO GENERAL FUND | 1805 | 71.3 | 0 | 5/10/2018 | EAST GOSHEN TOWNSHIP - GENERAL | XFER TO GENERAL TO CLOSE ACCOUNT |
| 07492-0500 | BEGINNING BALANCE | ||||||
| 07492-0500 | TRANSFER TO SEW.OPERATING | 1806 | 30000 | 0 | 6/22/2018 | XFER FROM SEWER TO MA | |
| 07492-0500 | TRANSFER TO SEW.OPERATING | 1806 | 0 | 30000 | 6/22/2018 | REVERSE TRX 63662 |
June 30, 2018 Fund Balance 25,009.78
Memo
| To: | Municipal Authority |
|---|---|
| From: | Jon Altshul |
| Re: | Analysis of Pennoni engineering budget |
| Date: | June 20, 2018 |
At the June 11, 2018 MA meeting, the Authority asked me to analyze and provide recommendations on the engineering budget for various MA projects. The table below shows how various MA projects were budgeted in 2018. In addition, a detailed worksheet of all Pennoni invoices for the MA is presented on the last page.
| Project/Category | Amount Budgeted (Total; including Engineering) | Fund Budgeted | Actual MA Engineering Costs 2018 YTD | Notes |
|---|---|---|---|---|
| Barkway P/S | $89,500 | Sewer Operating | 3,087.32 | No grant revenue budgeted; assumes more expensive option chosen (which it wasn't) |
| Tallmadge Drive | $30,000 | Sewer Operating | 12,049.25 | Originally assumed work performed in house |
| Supplee Valley Relining | $100,000* | Sewer Operating | 10,288.25 | We budget $100,000 per year; Supplee Valley represents 2 years of budget allocation |
| Ashbridge Force Main | $50,000 | Sewer Capital | 3,431.25 | |
| General Engineering | $43,260 | Municipal Authority | 47,554.32* | Excluding Barkway, Tallmadge Drive, Supplee Valley & Ashbridge, $18,698 has been spent on MA engineering |
With 20/20 hindsight, these projects should have been budgeted directly in the Municipal Authority, rather than in the Sewer Operating and Sewer Capital funds, with revenue being transferred to the MA from those two funds.
Options for the MA's Consideration
1) Do nothing and continue to charge the invoices to the budgeted fund/line items. Even with the Supplee Valley relining and the Tallmadge Drive project, the sewer fund may end the year with a small surplus, due to the Township over-budgeting for debt service on the 2008 MA note. This is therefore the easiest option for both the MA & the Township.
2) The Municipal Authority amends its 2018 budget to reflect higher engineering costs for capital projects as outlined below. However, in the interest of simplicity, the Township does not amend the Sewer Fund budget to offset the higher revenue requirements (i.e. increase the transfer from Sewer Operating to the MA) and the Sewer Fund pays for the MA projects as was originally budgeted. Under this scenario, new line items would be created in the MA to track these specific engineering expenses.
| Proposed Change to MA Budget for engineering capital costs | |
|---|---|
| Barkway P/S | +9,000 |
| Tallmagde Drive | +18,000 |
| Supplee Valley Relining | +11,505 |
| Ashbridge Force Main | No change |
| Transfer from Sewer Fund (Revenue) | +38,505 |
| NET TOTAL | - |
Additionally, there is a third option, whereby both the 2018 MA and the Township’s Sewer Operating Fund budgets are both amended to more accurately align expected costs and inter-fund transfers as of June and charge all construction costs to the Municipal Authority. However, this would be administratively challenging and would cause the Sewer Operating Fund to be unbalanced. I would therefore recommend against that third option. However, as part of the 2019 budget process, I would recommend that all sewer-related capital costs be budgeted and charged to the Municipal Authority budget with an appropriate offsetting transfer from the Township’s sewer fund.
If the MA wishes to go with Option #2, below find a proposed motion:
Mr. Chairman, I move that we amend the 2018 Municipal Authority budget to create the following capital line items with the following budgeted level: Barkway Pump Station Engineering, $9,000; Tallmadge Drive Engineering, $18,000; and Relining Engineering, $11,505. I further move that we increase the line item “Transfer from Sewer Operating Fund” by $38,505 from $75,853 to $114,358 and that Township staff transfer expenses already incurred in the General Engineering line item to the new line items just created.
PENNONI ASSOCIATES INC. Engineer Services 2018
| Budget | Sub# | Description | Invoice # | Check # | Check Date | Amount | Total |
|---|---|---|---|---|---|---|---|
| 07424 | 3130 | SERV.THRU 12/10/17 2017 GENERAL / ASHBRIDGE | 782383 | 3113 | 1/24/2018 | 3,298.00 | |
| 07424 | 3130 | SERVICES THRU 1/14/18 -2017 GENERAL/ ASHBRIDGE | 786300 | 3115 | 2/15/2018 | 133.25 | 3,431.25 |
| 07424 | 3130 | SERV.THRU 12/10/17 BARKWAY MUF.MONS | 782386 | 3113 | 1/24/2018 | 2,802.81 | |
| 07424 | 3130 | SERVICE THRU 2/11/18 BARKWAY PS MUF | 789506 | 3118 | 3/15/2018 | 115.83 | |
| 07424 | 3130 | SERVICES THRU 5/20/18 BARKWAY PS | 803811 | 3127 | 6/12/2018 | 168.68 | 3,087.32 |
| 07424 | 3130 | SERVICES THRU 1/14/18 2017 CHAP.94 | 786307 | 3115 | 2/15/2018 | 1,341.75 | |
| 07424 | 3130 | SERVICE THRU 2/11/18 2017 CHAP.94 | 789510 | 3118 | 3/15/2018 | 1,173.00 | |
| 07424 | 3130 | SERVICES THRU 4/15/18 2017 CHAP.94 | 799468 | 3126 | 6/7/2018 | 3,408.25 | 5,923.00 |
| 07424 | 3130 | SERV.THRU 12/10/17 2017 GENERAL | 782383 | 3113 | 1/24/2018 | 1,993.75 | |
| 07424 | 3130 | SERVICES THRU 1/14/18 -2017 GENERAL | 786300 | 3115 | 2/15/2018 | 743.75 | |
| 07424 | 3130 | SERVICES THRU 1/14/18 2018 GEN.SERV | 786305 | 3115 | 2/15/2018 | 123.00 | |
| 07424 | 3130 | SERVICES THRU 2/11/18 2018 GEN.SERV | 789508 | 3118 | 3/15/2018 | 2,043.75 | |
| 07424 | 3130 | SERVICES THRU 4/15/18 2018 GEN.SERV | 799477 | 3126 | 6/7/2018 | 2,076.00 | |
| 07424 | 3130 | SERVICES THRU 5/20/18 2018 GEN.SERV | 803813 | 3127 | 6/12/2018 | 1,329.50 | 8,309.75 |
| 07424 | 3130 | SERVICES THRU 1/14/18 2018 I&I | 786306 | 3115 | 2/15/2018 | 1,297.75 | |
| 07424 | 3130 | SERVICES THRU 2/11/18 2018 I&I REPT | 789509 | 3118 | 3/15/2018 | 1,112.00 | |
| 07424 | 3130 | SERVICES THRU 4/15/18 2018 I&I SUPP | 799467 | 3126 | 6/7/2018 | 30.75 | |
| 07424 | 3130 | SERVICES THRU 5/20/18 2018 I&I | 803814 | 3127 | 6/12/2018 | 61.50 | 2,502.00 |
| 07428 | 1000 | SERVICE THRU 1/14/18 RESERV.RD PS | 786299 | 22016 | 2/22/2018 | 142.50 | |
| 07428 | 1000 | SERVICES THRU 4/15/18 RESERVOIR RD | 799471 | 3126 | 6/7/2018 | 45.50 | 188.00 |
| 07424 | 3130 | SERVICES THRU 1/14/18 2017 SEMI-ANN | 786301 | 3115 | 2/15/2018 | 1,775.50 | 1,775.50 |
| 07424 | 3130 | SERV.THRU 12/10/17 SUPPLEE VAL.PIPE | 782384 | 3113 | 1/24/2018 | 956.50 | |
| 07424 | 3130 | SERVICE THRU 1/14/18 SUPPLEE VAL. | 786302 | 3117 | 2/22/2018 | 552.50 | |
| 07424 | 3130 | SERVICE THRU 2/11/18 SUPPLEE VALLEY | 789507 | 3118 | 3/15/2018 | 7,304.50 | |
| 07424 | 3130 | SERVICES THRU 4/15/18 SUPPLEE VAL. | 799466 | 3126 | 6/7/2018 | 510.75 | |
| 07424 | 3130 | SERVICES THRU 5/20/18 SUPPLEE VALL | 803812 | 3127 | 6/12/2018 | 964.00 | 10,288.25 |
| 07424 | 3130 | SERV.THRU 12/10/17 2017 GENERAL /TALLMADGE | 782383 | 3113 | 1/24/2018 | 3,472.50 | |
| 07424 | 3130 | SERVICES THRU 4/15/18 2018 GEN.SERV/ TALMADGE | 799477 | 3126 | 6/7/2018 | 3,596.50 | |
| 07424 | 3130 | SERVICES THRU 5/20/18 2018 GEN.SERV/ TALMADGE | 803813 | 3127 | 6/12/2018 | 4,980.25 | 12,049.25 |
| TOTATL | 47,554.32 | ||||||
Memo
| To: | Municipal Authority |
|---|---|
| From: | Jon Altshul |
| Re: | Preliminary Proposed CIP for Discussion |
| Date: | June 22, 2018 |
Attached find Mark's “wish list” of sewer capital improvements and purchases, as well as a spreadsheet laying out these costs by year through 2024.
Other than a noticeable bump in 2020 for the caustic soda injection system project, the total annual costs are fairly stable, meaning that this work plan can be absorbed into the existing sewer rate model with only a minimal impact on rates. Moreover, the $250,000 figure for the caustic soda project may be high.
We can discuss more on July 9th.
Proposed Sewer Capital Improvement Program, as of 6/22/18
| Project | 2018 Adopted | 2018 Re-est | 2019 | 2020 | 2021 | 2022 | 2023 | 2024 | Notes |
|---|---|---|---|---|---|---|---|---|---|
| Barkway P/S | 89,500 | 9,000 | 67,000 | May have offsetting grant revenue | |||||
| Ashbridge Force Main | 50,000 | 50,000 | Sewer Cap Reserve (no impact on rates) | ||||||
| Tallmadge Dr | 30,000 | 85,000 | |||||||
| HM P/S Generator | 75,000 | Sewer Cap Reserve (no impact on rates) | |||||||
| Mag Meter Hunt Country PS | 8,000 | ||||||||
| Bypass Pump Connection | 5,000 | ||||||||
| RC Collection Meters | 12,000 | 12,000 | |||||||
| RC Generator | 150,000 | ||||||||
| SBR Tank Rehab | 130,000 | 130,000 | 130,000 | 130,000 | Sewer Cap Reserve (no impact on rates) | ||||
| Pipe/Manhole Lining | 100,000 | 160,000 | 130,000 | 130,000 | 130,000 | 130,000 | 130,000 | 130,000 | |
| Caustic Soda System | 250,000 | ||||||||
| Total | 269,500 | 304,000 | 439,000 | 392,000 | 268,000 | 260,000 | 260,000 | 260,000 | |
| Total net of projects paid from SW Cap Reserve | 219,500 | 254,000 | 214,000 | 392,000 | 268,000 | 260,000 | 260,000 | 260,000 |
Jon
Below is my wish list for sewer work over the next 5 years
Meters
2018 Replace Modems on Meters. $8,600.00
Chester Creek Collection
2019 Muffin Monster at Bark way pump station.
2019 Replace Generator at Hershey Mill Pump Station $75,000.00 (NOTE) If need be we can defer until 2020
We may have to modify the building for the generator. If so all work would be done in house.
Ridley Creek System
2020-2021 Mag Meter for Hunt Country Pump Station. $8,000.00
Bypass Pump Connection. $5,000.00
2019-2020 - 3 Meters on the collection system $12,000.00 each
Ridley Creek Plant
2019 Replace generator and switch gear $150,000.00
Refurbish SBR Tanks starting in 2021 doing one tank per year $130,000.00
2020 -2021 Caustic Soda injection system and storage tank $250,000.00 [Handwritten: ? PRICE]
Pipe Lining
Consider increase the amount to $130,000.00 per year.
2019 -2020 Waterview Farms
2021-22-23-24 Marydell/Pinoaks Farms
2025-2026 Grand-Oak Development
2027 Hershey Mill Estates
2028 Milltown
2029-2030 Line Interceptor from Strasburg Road to Westtown Way.
I would like your approval to replace the modems at the five metering stations. As you know ACS is responsible for the maintenance of the meters. We were informed back in May by Verizon that the 3 G modems would need replaced. Our cost will be $6,880.00 West Goshen will share in the Westtown Way meter cost.
ACS
ALLIED CONTROL SERVICES, INC.
611 GARFIELD AVE. • P.O. BOX 234 • WEST POINT, PA 19486
Phone: 215-699-2855
Fax: 215-699-9030
[Logos: UL 508A / 698A Registered Firm; Rockwell Automation Recognized System Integrator; csia control system integrators association]
NJ Electrical Lic #14734 / DE Electrical Lic #T1-0004854 / MD Electrical Lic #9097 / WV Electrical Lic #043488 / VA Electrical Lic #2710066014
11 June 2018
East Goshen TWP M.A
1580 Paoli Pike
West Chester PA 19380
Attn: Mr. Mark Miller
Reference: 3G Cellular Upgrades
Dear Mark:
Per your request, we are pleased to offer this proposal for the above referenced project. This quotation reflects materials and installation for the 5 existing sites that are currently communicating via 3G and require upgrading to 4G to remain functional.
| Item | Description | Price | Qty | Total |
|---|---|---|---|---|
| 1 | Turnkey Installation Sierra Wireless 4G Modems and associated antennas, jumpers, and misc. hardware for 5 locations. | $8,600.00 | Lot | $8,600.00 |
| Total | $8,600.00 | |||
DELIVERY : 1 Week, shipping included
TERMS : Net 30 Days From Date Of Invoice
VALIDITY : Pricing is firm for orders received within sixty (60) days of this quotation.
If you have any questions regarding our quotation or if you would like to proceed with the project, please contact Lee Mace or Paul Mamzic Jr. at 1-800-441-4844.
Best Regards,
Paul Mamzic
Paul Mamzic Jr.
Page 1 of 1
[Logo: The Authorities PENNSYLVANIA MUNICIPAL AUTHORITIES ASSOCIATION]
FYI
Notification of Voter Delegate
[Stamp: RECEIVED JUN 11 2018 By______]
| TO: | PMAA Member Authorities |
|---|---|
| FROM: | Douglas E. Bilheimer Executive Director |
| DATE: | June 8, 2018 |
The PMAA Board of Directors’ voted April 18, 1994, to implement, by its resolution, certain administrative recommendations set forth by the PMAA By-Law Revision Committee. These do not require prior amendment of the By-Laws because the existing By-Laws (Article IX, Sections 1 and 2) do provide the basic authorization for voting at meetings: one vote per active member to be cast by a delegate chosen by its own board of directors. The procedures approved by the Board are as follows:
- Fifteen days before the meeting, each member authority will notify the Executive Director of the name of its official voting at the meeting and also the name of an alternate delegate, both of whom have been approved by the members’ Board of Directors. The delegates shall either be an elected or an appointed official of the applicable authority.
- As part of the registration procedure at the Annual Meeting, the named delegate shall be handed a “card”, which he or she may hold up to cast the vote of that authority. It shall be the responsibility of each delegate, in the event he or she is not on the floor, to hand the card to the appropriate alternate delegate.
- The presiding officer at the Annual Meeting shall have the discretion in each vote to designate voting by voice, by a show of delegate cards, or by written ballot, unless upon motion duly made and adopted the Body itself votes to require written ballots.
- In pursuance of the powers of the presiding officer, the President may designate a time limit for floor remarks by each person speaking, which shall be stated by the presiding officer at the opening of the meeting.
Please note, this form does not need returned to our office if no one from your authority is attending the conference.
DEB/kaw
Attachment
1000 North Front Street • Wormleysburg, Pennsylvania 17043
717.737.7655 • 717.737.8431 (f) • info@municipalauthorities.org
municipalauthorities.org
FYI
Notification of Voting Delegate & Alternate
Our Authority’s Board of Directors hereby name the following individuals to serve as Voting Delegate and Alternate Delegate:
Voting Delegate
Name: __________________________________________________
Title: ___________________________________________________
Alternate Delegate
Name: __________________________________________________
Title: ___________________________________________________
Authority submitting this information:
Authority: __________________________________________________
Address: ____________________________________________________
City: ___________________________ State: ________ Zip: ________
Designated Voting Delegate or Alternate Delegate will receive an identification card at the Registration Booth at the PMAA Annual Conference.
Please note this form must be returned to the PMAA office by Wednesday, August 15, 2018.