Municipal Authority

The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.

 

The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.

  • Five members, serving five-year terms
  • Meetings are on the 2nd Monday of the month at 7:00 P.M.
  • All township meetings are held at the Township Building and open to the public
Authority Members Term Expiration Date
Kevin Cummings, Chairman 2026
John Stipe, Vice Chairman
2029
Dana Pizzarro, Secretary 2026
Sean Ellsworth, Assistant Secretary/Treasurer 2028
Walter Wujcik, Treasurer 2028
Pennoni Associates, Engineer
Patrick M. McKenna, Esq.
Peter Hicks, BoS Liaison
Kevin Miller, Staff Liaison

 

Municipal Authority Genealogy

Audits

Documents

Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.

MA 10-8-18 draft 1

DRAFT 1 EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY 2 MEETING MINUTES 3 October 8, 2018 4 5 The East Goshen Township Municipal Authority held their regular public meeting on Monday, 6 October 8, 2018 at 7:00 pm at the East Goshen Township building. Members in attendance were: 7 Chairman Jack Yahraes, Dana Pizarro, Phil Mayer and Kevin Cummings. Also in attendance were: 8 Jon Altshul (Asst. Township Manager), Mark Miller (Public Works Director), Michael Ellis 9 (Pennoni), Carmen Battavio (Supervisor) and Walter Wujcik (Conservancy Board). 10 11 COMMON ACRONYMS: 12 BFES – Big Fish Environmental Services MA- Municipal Authority 13 BOS – Board of Supervisors NPDES – National Pollutant Discharge Elimination System 14 CB – Conservancy Board PC – Planning Commission 15 DEP – Department of Environmental Protection PM – Prevention Maintenance 16 EPA – Environmental protection Agency PR – Park & Recreation Board 17 HC – Historical Commission RCSTP – Ridley Creek Sewer Treatment Plant 18 I&I – Inflow & Infiltration SBR – Sequencing Batch Reactor 19 LCSTP – Lockwood Chase Sewer Treatment Plant SSO – Sanitary System Overflow 20 WAS – Waste Activated Sludge 21 22 Call to Order & Pledge of Allegiance 23 Jack called the meeting to order at 7:00 pm and led those present in the Pledge of Allegiance. There 24 was a moment of silence to remember our troops and first responders. 25 Jack asked if anyone would be recording the meeting. There was no response. 26 27 Chairman’s Report 28 1. Jack mentioned that the PMAA has a course for “One Mark” which ties in with “One Call” and he 29 feels someone from the Township should attend. 30 2. Phil attended the West Goshen Sewer Authority meeting. The West Goshen Board of Supervisors 31 approved a rate increase in September. It will take effect Q2 2019. West Goshen was awarded a 32 $220,000 grant for an aeration system. They had an emergency switch gear problem at Washington 33 Street Pump Station. They plan to replace all of the switch gears. 34 35 36 Sewer Reports 37 1. Director of Public Works, Mark Miller’s report for August: 38 Monthly Flows: The average daily flow to West Goshen was 748,000 gallons per day. No 39 problems to report. 40 Meters: The meters are being read on a daily basis. We have had a power problem with the 41 Paoli Pike meter; however I believe we corrected the problem. 42 C.C. Collection: The month has been very busy. We had some problems with the Barkway 43 Pump Station. The pumps were not pumping to capacity. We found Pump #1 was burned out 44 and Pump #2 was very weak. We pulled both pumps out and sent them to Deckman for 45 repair. Both pump cutters were jammed up with towels. I would recommend that we speed 46 up the process of installing the Muffin Monster. The original plans called for us to install the 47

MA 10-8-18 draft 2

Muffin Monster in the wet well. However, the wet well is getting crowded. I would 1 recommend that we do a separate manhole for the Muffin Monster. 2 3 We also had problems with the Ashbridge Pump Station. After checking the amperage, we 4 found pump #2 pulling more amps than pump #1. We pulled the pump and sent it to 5 Deckmens. I checked the records and found that the pumps at Ashbridge are the original 6 pumps that were built in 1985 and installed in 1987. This will make them 33 years old. 7 Being that the pump housings have been submerged in sewage for that long, I would 8 recommend that we order a new pump now at a cost of $23,686.00 with 8 to 12 weeks 9 delivery time. Then in 2019 order a second pump. These pumps are very hard to get parts 10 for. If you recall, over the years we have always tried to keep spare internal parts on the 11 shelves so they are readily available. We also televised several suspicious areas where we 12 thought we were getting INI. We did find that a manhole between Wyllpen Place and the 13 station was taking in ground water. 14 R.C. Collection: The pumping station was visited on a daily basis with no problems to report. 15 Mr. Brandolini called to report a problem with his lateral. We televised it and found that the 16 lateral has pulled apart on the house side of the trap. Mr. Brandolini was told what was found 17 and that, when his plumber makes the repair, he is to contact the Public Works Department to 18 inspect the repairs. Pipe Data View has been contacted to come in and televise areas of 19 concern in Quad #2 and Quad #4. 20 Ridley Creek: We installed the rebuilt blower. I have received pricing to install a Splitter 21 Cooling System for the control room in the older building. 2019 budget 22 Alarms: We responded to 23 alarms for September. 23 PA One Calls: We received 97 PA One calls for September. 24 Rainfall: September rainfall total was 9.81 inches. 25 26 2. Pennoni Engineer’s Report for September 27 Invoices 28

• Invoices with summaries are provided under separate cover. 29

Ridley Creek Sewage Treatment Plant (RCSTP) 30

• Caustic soda pilot study – A summary and recommendations report has been prepared and 31 will be issued prior to the October MA meeting. 32

• SBR Coatings – 33

o Following the September MA meeting, we prepared a revised budgetary cost estimate 34 for a reduced scope to only coat the portions of walls that are not currently coated. 35 Removal and replacement of existing CIM coatings were deleted from the cost 36 estimate as was coating installation on the tank floors. The revised estimate is 37 attached with reduced quantities; unit prices were not changed. Revised grand total is 38 $220,000. We also provided updates on the applicable cost projections for the 5-year 39 Capital Improvement Plan. 40

MA 10-8-18 draft 3

o Contact information for Chase Corporation (CIM manufacturer) was provided to the 1 Township to conduct further discussions on detailed scope and to obtain updated 2 pricing from the manufacturer. 3

o We will conduct a visual inspection of the concrete and coating conditions in the next 4 tank when it is taken offline, which we understand is tentatively scheduled for 5 November. 6

o It is our understanding that the warranty expires in October 2019. 7

RCSTP and Pump Stations’ O&M Manual 8

• We recommend the Manual be revisited in July-August 2018 to determine if updates are 9 needed and/or if new information has become available to incorporate now that it has been in 10 place for one full year. 11 12 Supplee Valley Pipe Lining 13 We processed a final payment application and reviewed contract closeout documents from 14 SWERP, and we submitted a final payment recommendation letter. 15 16 Barkway Pump Station Grinder 17 • We have revisited the approach to installation of the Muffin Monster inside the wet well with 18 Mark Miller and the equipment vendor due to recent accessibility issues within the wet well 19 experienced by the Public Works Department during emergency pump replacements. 20 Installation of an upstream Muffin Monster within a prefabricated manhole is being explored 21 again in more detail as a result. An updated equipment quote of $58,000 was obtained from 22 the vendor for the manhole system. For reference, the wet well mounted system material cost 23 is $33,450, so the outside unit is approximately $25,000 more. However, the Township has 24 received a $32,309 grant for the project from the PA DCED Small Water and Sewer Grant 25 program, which would help to offset this additional cost. 26 • Our design was 95% complete for the Internal Muffin Monster. If the manhole system is to 27 be pursued, we would need to revise the design and plans, coordinate with the vendor, 28 perform a limited field survey to determine existing sewer elevations for design of the 29 manhole location and depth as well as topography, obtain PA One Call utility information, 30 prepare a limited existing site plan, and provide notification of the proposed system to DEP. 31 We propose this additional effort for a lump sum of $7,000. 32 33 Ashbridge Pump Station Force Main 34 • Test pits will be performed to identify backfill conditions along Manley Road with one test pit 35 on Edith Road, as recommended by the Municipal Authority, when weather permits. No 36 update since our last report. 37

Tallmadge Drive Sewer Main Replacement 38

• The contractor provided all required insurance and bonding documents, and the contract has 39 been executed. A pre-construction meeting was held on October 2. The contractor is 40

MA 10-8-18 draft 4

planning to start the work in mid-November and he anticipates 2 weeks to complete the 1 project. The contract allows for 20 consecutive calendar days. 2 3 Hersheys Mill Pump Station – Mike mentioned that it is at capacity. 4 5 I&I Support and Reporting 6 • We intended to analyze meter data and submit the next semi-annual I&I report following 7 completion of the Supplee Valley pipe lining project so that the impact of that project can be 8 assessed. However, there have been issues with obtaining instantaneous meter data from the 9 permanent collection system meters. If instantaneous data is not available, we will preform a 10 limited analysis of all permanent meters based on daily flow data and we will prepare a semi- 11 annual I&I report accordingly. We propose to make a summary Powerpoint presentation at a 12 MA meeting once the next report is submitted. 13

New Connections 14

• No activity since last report. 15

West Goshen Sewer System Consultation 16 • No activity since last report. 17 Capital Improvement Planning 18 We provided updated cost information for the SBR Coatings as discussed above. 19 20 RCSTP Caustic Soda Pilot Study Results and Recommendations/Draft 21 Mike provided copies of the draft of the above report. It contained the results report dated October 5, 22 2018, the pre-study memo dated February 10, 2017 with alternatives, PA Dept of Environmental 23 Protection letter dated April 19, 2017, and 5 charts showing before and after numbers. Mike 24 explained the documents and how the results will change the way the soda ash is put into the tanks. 25 26 27 3. Big Fish Environmental Services – Scott’s report showed that the Ridley Creek sewage 28 treatment plant outfall 001 and 002 achieved compliance with the permitted effluent discharge 29 limitations during the month of August 2018. Discharge to the Applebrook irrigation lagoon 30 continued during the month. Chemical usage utilized for total phosphorus removal, pH and total 31 alkalinity remained consistent with previous months. No significant mechanical or operational issues 32 were observed during operation of sludge dewatering equipment or SBR treatment process. 33 Comments: Dana pointed out there are no comments on Table 4. Kevin asked about the UV lights. 34 Mark will talk to Scott. 35 36 Approval of Minutes 37 The minutes of the September 10, 2018 meeting were approved as corrected. 38 39 Approval of Invoices 40 1. Dana moved to approve payment of the following Pennoni invoices: 41 Pennoni invoice #823030 $ 200.75 42 Pennoni invoice #823031 $ 4,618.50 43 Pennoni invoice #823033 $ 1,333.75 44 Phil seconded the motion. The motion passed unanimously. 45

MA 10-8-18 draft 5

2. Phil moved to approve payment of Gawthrop Invoice #199945 in the amount of $500. Dana 1 seconded the motion. The motion passed unanimously. 2 3. The Payment Application #3 to SWERP for Supplee Valley in the amount of $21,614.20 was 3 discussed. Mike explained that this is updated for work that wasn’t anticipated. Kevin made a 4 motion to approve Payment Application #3 in the amount of $21,614.20 and Change Order #3. Phil 5 seconded the motion. The motion passed unanimously. 6 7 Liaison Reports 8 Conservancy Board – Walter reported that they are going to do a clean up in Clymers Woods for the 9 Fall project. 10 Board of Supervisors – Carmen reported the WEGO negotiations are ongoing. 11 12 Financial Reports 13 Jon Altshul provided the following written report: 14 In September, the Municipal Authority recorded $29,985 in income (a $30,000 transfer from Sewer 15 Operating, net of banking fees) and $10,839 in expenses including $8,382 from the Q3 administrative 16 overhead charge back, for a positive variance of $19,147. The fund balance is $20,741. 17 Jon had the contract for the PA DCED Small Water and Sewer Grant. Phil moved to authorize the 18 Chairman to sign the PA DCED Small Water and Sewer contract for the grant in the amount of 19 $32,309. Kevin seconded the motion. The motion passed unanimously. 20 21 Goals 22 Newsletter – Phil will write an article for the next newsletter, which is due November 1st. 23 24 New Business 25 1. Pump replacement for Ashbridge Pump Station - Mark commented that the Ashbridge pumps are 26 33 years old and we need to consider replacing them. He would like to buy one now and one next 27 year. Jon advised him to use the funds allocated for Ashbridge repairs for 2018 and buy 2 pumps 28 now. Kevin made a motion to use the $50,000 in the 2018 budget to by 2 pumps for the Ashbridge 29 Pump Station in lieu of maintenance repairs at Ashbridge. Dana seconded the motion. The motion 30 passed unanimously. 31 32 2. Barkway Pump Station – Mike explained that they need additional funds to revise the design. 33 Kevin moved to approve additional funds for the Barkway Pump Station design revision not to 34 exceed $7,000. Phil seconded the motion. The motion passed unanimously. 35 36 Adjournment 37 There being no further business, Dana moved to adjourn the meeting. Phil seconded the motion. The 38 meeting was adjourned at 8:30 p.m. The next regular meeting will be held on Monday, 39 November 12, 2018 at 7:00 pm. 40 41 Respectfully submitted, 42 43 44 Ruth Kiefer 45 Recording Secretary 46