Municipal Authority

The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.

 

The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.

  • Five members, serving five-year terms
  • Meetings are on the 2nd Monday of the month at 7:00 P.M.
  • All township meetings are held at the Township Building and open to the public
Authority Members Term Expiration Date
Kevin Cummings, Chairman 2026
John Stipe, Vice Chairman
2029
Dana Pizzarro, Secretary 2026
Sean Ellsworth, Assistant Secretary/Treasurer 2028
Walter Wujcik, Treasurer 2028
Pennoni Associates, Engineer
Patrick M. McKenna, Esq.
Peter Hicks, BoS Liaison
Kevin Miller, Staff Liaison

 

Municipal Authority Genealogy

Audits

Documents

Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.

EAST GOSHEN MUNICIPAL AUTHORITY
January 14, 2019
7:00 PM

  1. CALL TO ORDER/PLEDGE OF ALLEGIANCE/MOMENT OF SILENCE Ask if anyone will be taping the meeting; Election of 2019 Officers
  2. CHAIRMAN’S REPORT/OTHER MEMBERS REPORTS
  3. SEWER REPORTS Director of Public Works Report.; Pennoni Engineer’s Report.; Big Fish Environmental Report.
  4. APPROVAL OF MINUTES December 10, 2018
  5. APPROVAL OF INVOICES E-mail summary from Pennoni $ 582.21 Pennoni Invoice #839068 $ 2,677.00 Pennoni Invoice #839069 $ 301.50 Pennoni Invoice #839070 $ 2,187.00 Pennoni Invoice #839085 $ 9,082.00 Pennoni Invoice #839095 $ 384.06 – Pd Dec. Gawthrop Invoice #202493 $ 440.00 Gawthrop Invoice #203528 $ 11,830.72 JWC Environ. Invoice #95288
  6. LIAISON REPORTS
  7. FINANCIAL REPORTS December Financial Report
  8. OLD BUSINESS
  9. GOALS

F:\Data\Shared Data\Agendas\Municipal Authority\2019\1-14-19 - .doc

  1. Continue to monitor the upgrades at West Goshen Sewer Plant. Jack and Phil have been attending meetings.de
  2. Continue to implement the I&I Plan – 3-8-2018 completed
  3. Submit articles for the newsletter – The fall newsletter included an article about flushable wipes; the winter newsletter was submitted with an article about the improvements at WGSTP.
  1. NEW BUSINESS Notice of Deficiencies & Resolution Requirements – Tallmadge Dr.; E-mail summary from Pennoni for payment Application #1 & #2; Payment Application #1 – Tallmadge Drive – Approval of $42,431.40; Payment Application #2 – Tallmadge Drive – Approval of $21,326.40
  2. CAPACITY REQUESTS
  3. ANY OTHER MATTER
  4. CORRESPONDENCE AND REPORTS OF INTEREST
  5. PUBLIC COMMENT
  6. ADJOURNMENT

F:\Data\Shared Data\Agendas\Municipal Authority\2019\1-14-19 - .doc

AREA CODE 610
692-7171

EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

January 11, 2019

To: Municipal Authority
From: Mark Miller
Re: December 2018 Monthly Report

Monthly Flows: The average daily flow to West Goshen was 817,000 gallons per day. No problems to report.

Meters: We have been reading the meters on a daily basis, the flows are running high.

C.C. Collection: We have been inspecting the entire collection system. We have been pulling manholes in the middle of the night to try and locate the infiltration. So far we have repaired 24 sewer laterals and found 3 manholes that need attention due to significant inflow. On the Ashbridge system we have three laterals to excavate which are scheduled for next week. We are scheduled to install the portable flow meters on the Chester Creek system as well as the R.C. Collection system.

R.C. Collection: We have three point repairs to do in Hershey’s Mill Estates, we also have to dig two laterals that are broken and taking in significant inflow. We also have to replace several castings and lids that are in bad shape. As I stated in the Chester Creek report, we will be installing portable meters on this system as well. We have been working in the early morning hours trying to locate inflow. So far it has paid off. We have to pull the pumps at Hershey’s Mill pump station for preventive maintenance.

Ridley Creek: The new screen has arrived and should be installed in the next two weeks. The flow meter arrived yesterday and is scheduled to be installed next week weather permitting. As you can see the flows are up as well. We have been repairing laterals as we inspect them. Once we get the Ashbridge system and Hershey Mill Estates tightened up then we will being hitting the Ridley Creek system.

Alarms: We responded to 22 alarms for the month of December.

PA One Calls: We received 40 PA One calls in December.

Rainfall: December rainfall total was 6.00 inches.

Laterals: 5 lateral repairs reported for December

I was notified last week that Deckman Electric is closing at the end of February. I have already started looking for a new shop to do our pump work.

[Photograph looking down into an open sewer manhole showing active water infiltration streaming from the manhole wall, marked with red drawn arrows pointing toward the leaks.]

Photograph looking down inside a concrete manhole shaft, with four red arrows pointing to cracks and water infiltration along the lower interior concrete wall.

Pennoni

Christiana Executive Campus
121 Continental Drive, Suite 207
Newark, DE 19713
T: 302-655-4451
F: 302-654-2895

www.pennoni.com

EAST GOSHEN MUNICIPAL AUTHORITY
ENGINEER'S REPORT

January 10, 2019

Invoices

  • Invoices with summaries are provided under separate cover.

Ridley Creek Sewage Treatment Plant (RCSTP)

  • No activity since last report.

RCSTP and Pump Stations' O&M Manual

  • We recommend the Manual be revisited to determine if updates are needed and/or if new information has become available to incorporate now that it has been in place for over one year.

Barkway Pump Station Grinder

  • We have continued redesign and vendor coordination for an external Muffin Monster in a prefabricated manhole. Project-specific manhole details are currently being prepared by the vendor. Upon receipt of the details, the plans can be finalized, and the Township can order equipment. The lead time for the equipment is about 4 months.

Ashbridge Pump Station Force Main

  • Test pits will be performed to identify backfill conditions along Manley Road with one test pit on Edith Lane, as recommended by the Municipal Authority, when weather permits. No update since our last report.

Tallmadge Drive Sewer Main Replacement

  • The contractor completed work on December 19, 2018. However, major and minor deficiencies that require monitoring and/or repair were identified during manhole vacuum testing and post-construction pipe televising. We prepared an agreement regarding the deficiencies and required repairs that was signed by the contractor (enclosed with our Pay Application #1 recommendation letter).
  • A repair pre-construction meeting was conducted between Pennoni, Mark Miller, and the contractor on January 10. The contractor will begin repair of major deficiencies on January 16 and is expected to take 3 days to complete. The contractor will repair approximately 30 LF of pipe with a severe sag, repair the newly installed manhole such that it passes a vacuum test, and repair the abandoned downstream drop connection pipe stub, which is leaking groundwater. The pipes will be re-televised immediately upon completion of the repair work.
  • Minor deficiencies, including minor sags (10% or less), were also noted at two locations within the replaced pipes. The contractor will re-televise the pipes again in April to determine if the sags have increased, and if so, will perform repairs at that time.
  • The contractor has submitted two invoices for consideration at the January MA meeting. The first invoice is for a 50% contract payment for work completed and the second invoice is for an additional 25% contract payment to be paid immediately following acceptance of the aforementioned major deficiency repairs.

EGMAU19001
East Goshen Municipal Authority

January 10, 2019

Page 2
Engineer's Report

I&I Support and Reporting

  • We analyzed permanent meter data and expect to issue a semi-annual I&I report prior to the January MA meeting. We also provided assistance to the Township on contractors for manhole injection grouting to eliminate infiltration sources.

New Connections

  • No activity since last report.

West Goshen Sewer System Consultation

  • No activity since last report.

Hershey's Mill Pump Station

  • We continued to evaluate electrical problems via discussions with the generator mechanic and evaluation of electrical test data provided by the mechanic. We prepared a letter recommending the PECO transformer be replaced with a larger transformer.
  • We initiated evaluation of sizing for a replacement generator, and we are preparing a conceptual site exhibit to determine if the generator can be sited externally (instead of inside the control building).

P:\Projects\EGMA\Memos to Board\2019\Engineers Report 2019-01-10.docx

Big Fish
Environmental Services Inc.

RCSTP Monthly Operations
Report:
January 2019

Executive Summary

The Ridley Creek sewage treatment plant outfall 001 achieved compliance with the permit discharge limitations for the month of December 2018. Discharge to the Applebrook irrigation lagoon remained off line during December 2018. Chemical usage utilized for total phosphorus removal, pH and total alkalinity remained consistent with previous months. No significant mechanical or operational issues were observed during operation of sludge dewatering equipment or SBR treatment process.

Treatment Process Operation

Table 1 illustrates the revised final effluent composite sample data reported for outfall 001 for the November 2018 DMR.

Table 1

November 2018 - Final Effluent - Out Fall 001
NPDES Permit
Discharge Limitations
Flow CBOD5 TSS NH4-N Phosphorus,Total
, mg/L
Fecal Coliform
MGD
Average
mg/L lbs/
month
mg/L lbs/
month
mg/L lbs/
month
mg/L lbs/
month
Geo Mean Geo
Mean
0.75 20
40
125 10
42
131 7 44 0.5 3 200 1,000
Sample Date
November 1, 2018 0.369 4 12.3
November 6, 2018 0.544 2.0 9.1 2 9.1 0.111 0.50 0.10 0.45 1 0.0000
November 13, 2018 0.594 2.7 13.4 2 9.9 0.100 0.50 0.13 0.64 1 0.0000
November 15, 2018 0.655 4 21.9
November 20, 2018 0.556 3.5 16.2 2 9.3 0.129 0.60 0.10 0.46 1 0.0000
November 23, 2018 0.524 4 17.5 0.00
November 27, 2018 0.595 2.0 9.9 2 9.9 0.184 0.91 0.15 0.74 2 0.3010
November 29, 2018 0.565 1 4.7
Average 0.578 2.6 12.2 3 12.9 0.131 0.50 0.12 0.58 1 0.0753
Minimum 0.524 2.0 9.1 2 9.1 0.100 0.00 0.10 0.45 1 0.0000
Maximum 0.655 3.5 16.2 4 21.9 0.184 0.91 0.15 0.74 2 0.3010

BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 1 of 7

Big Fish
Environmental Services Inc.

RCSTP Monthly Operations
Report:
January 2019

The treatment process performed well during December with no abnormalities. The process monitoring, and control data indicates the facility will remain within compliance of the NPDES permit.

There was no discharge to the Applebrook outfall 002 during November 2018.

The monthly average influent wastewater pollutant concentrations and loading entering the wastewater treatment facility remained within the design concentrations. There were periodic BOD5 and TSS sample concentration atypically less than “normal” conditions. Although these samples are collected from the influent flow meter located prior to the Screening Building which excludes the internal recycle flows, debris can accumulate around the sampler suction line impacting the pollutant concentrations measured.

Table 2 presents the available pollutant data for the influent wastewater collected at the doghouse manhole during November 2018.

Table 2

November 2018 - Influent Wastewater
Design Basis Flow BOD5 TSS NH4-N TKN, mg/L Phosphorus,Total,
mg/L
MGD
Average
mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day
335 2,098 320 2,001 32 200 48 301 9.1 57
Sample Date
November 6, 2018 0.665 58.8 326 63 349 21.2 118 27.0 150 4.7 26.1
November 13, 2018 0.657 122 677 28 155 19.8 109 19.0 104 2.6 14.4
November 20, 2018 0.657 305 1,692 148 821 27.2 149 27.2 149 4.5 25.0
November 27, 2018 0.723 138 765 118 654 19.6 118 18.2 110 3.1 17.2
Average 0.676 156 865 89 495 22.0 123 22.9 128 3.7 20.7
Minimum 0.657 59 326 28 155 19.6 109 18.2 104 2.6 14.4
Maximum 0.723 305 1,692 148 821 27.2 149 27.2 150 4.7 26.1

Continued maintenance activities of cleaning the alum static mixer injector, flushing of the alum chemical piping to the SBRs and weekly draining and cleaning of the disc filters.

BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 2 of 7

Big Fish
Environmental Services Inc.

RCSTP Monthly Operations
Report:
January 2019

The foam on the SNR surface remained consistent at approximately 75% to 100% coverage of the surface area. The foam thickness is approximately 3 to 4 inches with a light to medium brown color. The colder water temperatures within the SBRs historically contributes increasing the foam concentrations.

Sequencing batch reactors (SBRs) numbered 1, 3 and 4 are in service during November and December, as well as January. Process monitoring of each SBR included ammonia as N, nitrite as N, Nitrate as N, COD, SSV, MLSS and total phosphorus. Daily analysis of the final effluent flow equalization grab sample is total phosphorus is ongoing. Sample collection and analysis of the influent wastewater collected at the influent pump station wet well is ongoing.

Table 3 1 illustrates the available final effluent composite sample data reported for outfall 001 for the December 2018 DMR.

Table 3

December 2018 - Final Effluent - Outfall 001
NPDES Permit
Discharge Limitations
Flow CBOD5 TSS NH4-N Phosphorus,Total
, mg/L
Fecal Coliform
MGD
Average
mg/L lbs/
month
mg/L lbs/
month
mg/L lbs/
month
mg/L lbs/
month
Geo Mean Geo
Mean
0.75 20
40
125 10
42
131 2.5 44 0.5 3 200 1,000
Sample Date
December 4, 2018 0.523 2.0 8.7 2 8.7 0.189 0.82 0.10 0.44 1 0.0000
December 6, 2018 0.516 1 4.3
December 11, 2018 0.451 2.8 10.5 2 7.5 0.236 0.89 0.10 0.38 1 0.0000
December 13, 2018 0.424 2 7.1
December 18, 2018 0.491 2.0 8.2 2 8.2 0.363 1.49 0.23 0.94 1 0.0000
December 27, 2019 0.610 1 5.1
December 27, 2018 0.545 2.0 9.1 1 4.5 1.410 6.41 0.00 1 0.0000
Average 0.509 2.2 9.1 2 6.5 0.550 2.40 0.14 0.44 1 0.0000
Minimum 0.424 2.0 8.2 1 4.3 0.189 0.82 0.10 0.00 1 0.0000
Maximum 0.610 2.8 10.5 2 8.7 1.410 6.41 0.23 0.94 1 0.0000

There was no discharge to the Applebrook outfall 002 during December 2018.

BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 3 of 7

Big Fish
Environmental Services Inc.

RCSTP Monthly Operations
Report:
January 2019

Table 4 presents the available pollutant data for the influent wastewater collected at the doghouse manhole during December 2018

Table 4

December 2018 - Influent Wastewater
Design Basis Flow BOD5 TSS NH4-N TKN, mg/L Phosphorus,Total,
mg/L
MGD
Average
mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day
335 2,098 320 2,001 32 200 48 301 9.1 57
Sample Date
December 4, 2018 0.614 154 788 110 563 16.9 86 21.3 109 2.6 13.3
December 11, 2018 0.534 132 675 92 471 22.2 99 25.0 111 2.8 14.3
December 18, 2018 0.563 216 1,105 146 747 22.4 105 25.2 118 3.4 17.4
December 27, 2019 0.759 132 675 136 696 30.2 191 31.0 196 3.6 18.4
Average 0.617 159 811 121 619 22.9 120 25.6 134 3.1 15.9
Minimum 0.534 132 675 92 471 16.9 86 21.3 109 2.6 13.3
Maximum 0.759 216 1,105 146 747 30.2 191 31.0 196 3.6 18.4

Addition of aluminum sulfate solution to the SBRs to assist with phosphorus removal continued. Soda ash assists towards maintaining SBR pH concentrations above 7.0 standard units and assists to replenish alkalinity consumed during the nitrification process and aluminum sulfate solution addition.

Significant Rainfall

During December, there were ten (10) days when rainfall occurred. Four (4) storm events resulting in a daily precipitation amount equal to or greater than 0.50 inches measured during a 24-hour period as well as consecutive days of precipitation exceeding 0.5 inches of rainfall. A total of 8.96 inches of rainfall measured during the month. These events occurred on:

December 2nd 0.57 inches
December 16th 1.18 inches
December 21st 1.96 inches
December 28th 1.02 inches

BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 4 of 7

Big Fish
Environmental Services Inc.

RCSTP Monthly Operations
Report:
January 2019

Plant operations were adjusted to manage the precipitation to prevent exceedances of the permitted discharge limitations for Outfall 001. Adjustments included reducing aeration minutes per cycle, extending decant minutes per cycle and reducing settling times.

2018 Rainfall Measured at RCSTP

Year : 2018
Month Precipitation,
inches
January 2.53
February 6.02
March 3.56
April 4.95
May 6.06
June 2.12
July 7.41
August 9.61
September 10.52
October 3.27
November 8.96
December 5.64
Year to Date 70.65

The average annual rainfall for West Chester, PA is typically 47.1 inches as compared to the national average of 39 inches. Rainfall measured at RCSTP for the 2018 calendar year was 23.55 inches above the typical average. As a result, the soil is saturated and groundwater table is elevated.

PA DEP

No activity.

Solids Dewatering and Disposal:

December 2018
Gallons of sludge dewatered 279,182
Number of dumpsters 4

*Seventeen (17) days of centrifuge operation

A decrease of 27,551 gallons of sludge was dewatered during December as compared to November.

BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 5 of 7

Big Fish
Environmental Services Inc.

RCSTP Monthly Operations
Report:
January 2019

Chemical Usage:

December 2018
Chemical Daily Average Total Monthly
Soda Ash 300 9,000
Aluminum Sulfate solution 48.1 1,442
Polymer (centrifuge) 0.85 14.5 gallons

*Seventeen (17) days of centrifuge of operation

The alum feed increased by an average of 48.3 gallons per day during November. This is attributed to the lower water temperatures and reduced biological activity.

Flow data:

December 2018
Flow Meter Location Total Volume
for Month, MG
Average Daily
Flow, gpd
Daily Maximum
Flow, gpd
Influent Wastewater to Screening Building* Flow Meter removed for rebuild
Influent Wastewater to SBRs 20.083 647,849 904,576
Internal Recycle NA NA NA
Treated Effluent to Disc Filters 19.746 636,969 903,168
Final Effluent Discharge 16.620 536,129 756,000
Applebrook Golf Course 0 0 0

Influent wastewater flow measurements to the SBRs are bring used for DMR and Chapter 94 reporting. These flow measurements are typically 10 to 15% above the flow from the community when the internal recycle flow volumes are removed. For example, the December influent flow measurements into the SBR averaged 0.648 MGD, which is 86.4% of the average daily hydraulic design for the SBRs of 0.750 MGD, with all four (4) SBRs in service. The plant utilized three (3) SBRs during December and achieved compliance with all effluent discharge limitations within the NPDES permit.

Minor Preventative Maintenance

Flushed chemical feed lines to the SBRs.

Cleaned final effluent weir trough daily

Skimmed surface of disc filters daily

BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 6 of 7

Big Fish
Environmental Services Inc.

RCSTP Monthly Operations
Report:
January 2019

Drained and cleaned disc filters bi-weekly

Major Preventative Maintenance Activities

UV System

Parts were identified to repair and replace the electrical connections at a considerable savings as compared to sending the UV banks to Siemens for rebuilding. Replacing one UV bank with plant staff is recommended and proposed to be evaluated for a period of two months.

Influent Flow Meter located in the “field”

The meter remains at the factory for repair.

Screening Building

The parts to replace the screening basket have been received. Replacement of the screening basket and brush are scheduled for January.

UV Alarm on December 21, 2018

Responded to find the UV alarm was for insufficient lamps on. Two (2) ballasts were replaced. The alarm settings were adjusted in the UV PLC. Parts were ordered to repair the B3 UV module.

The problem with blowing so many ballasts, and damaging the plugs is due to the frequent cycling of the lag UV banks (in this case Bank B). The ballasts should only be used if they are going to cycle on once per day. Currently, the lag UV bank cycles on 8-10 times per day. This is probably shortening the lives of the lag bank ballasts. Another plug on Bank B that is melting. In the meantime, both UV banks will remain on continuously.

A meeting with the vendor providing the UV system supplies was scheduled.

BIG FISH ENVIRONMENTAL SERVICES, INC. 1554 Paoli Pike #262, West Chester PA 19380-6102
Page 7 of 7

DRAFT
EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
MEETING MINUTES
December 10, 2018

The East Goshen Township Municipal Authority held their regular public meeting on Monday, December 10, 2018 at 7:00 pm at the East Goshen Township building. Members in attendance were: Chairman Jack Yahraes, Phil Mayer, Kevin Cummings and Dana Pizarro. Also in attendance were: Jon Altshul (Asst. Township Manager), Mark Miller (Public Works Director), Michael Ellis (Pennoni), Scott Towler (Plant Operator), Carmen Battavio (Supervisor), Patrick McKenna (Attorney), and Walter Wujcik (Conservancy Board).

COMMON ACRONYMS:

BFES – Big Fish Environmental Services MA- Municipal Authority
BOS – Board of Supervisors NPDES – National Pollutant Discharge Elimination System
CB – Conservancy Board PC – Planning Commission
DEP – Department of Environmental Protection PM – Prevention Maintenance
EPA – Environmental protection Agency PR – Park & Recreation Board
HC – Historical Commission RCSTP – Ridley Creek Sewer Treatment Plant
I&I – Inflow & Infiltration SBR – Sequencing Batch Reactor
LCSTP – Lockwood Chase Sewer Treatment Plant SSO – Sanitary System Overflow
WAS – Waste Activated Sludge

Call to Order & Pledge of Allegiance

Jack called the meeting to order at 6:50 pm and led those present in the Pledge of Allegiance. There was a moment of silence to remember our troops and first responders.
Jack asked if anyone would be recording the meeting. There was no response.

Chairman's Report

1. Phil mentioned that at the West Goshen meeting last week construction is done. He feels East Goshen should get a credit. They didn't discuss storm water management but did mention that they have a new township water ordinance.
Jon distributed copies of the West Goshen Sewer Authority Project cost report dated September 25, 2018. He commented that East Goshen does not pay miscellaneous fees.

Sewer Reports

1. Director of Public Works, Mark Miller's report for November:

Monthly Flows: The average daily flow to West Goshen was 833,000 gallons per day. No problems to report.
Meters: The meters were calibrated two weeks ago. The field meter at Ridley was been removed and sent back to HACH for repairs. The temporary flow meter that was at the Hershey Mill Pump Station has been removed. I'm waiting on John Laidly to forward me the data.
C.C. Collection: The pump stations were visited on a daily basis with no problems to report. We cleaned and televised 3,850 linear feet of pipe in various developments. The sump connection that we located has been disconnected. When I met with the resident, I inspected the line and viewed that the pump has been removed from the system. The new pumps that we had to order to replace the pumps at the Barkway Pump Station have arrived and will be

MA 12-10-18 draft

1

installed next week. The Public Works Department has been going out in the middle of the night and pulling manholes to locate high flows and then isolating them. We are trying to locate INI, so far we have located 5 sources of infiltration.
R.C. Collection: We televised and cleaned the following developments: Lochwood Chase, Fairway Village and Bittersweet Development. We located 4 areas of infiltration all have been repaired. We located a large leak at the sewer lateral at the Blacksmith Shop. On Thursday of last week we repaired a significant leak in Hershey Mill Development. We also attacked the Ridley Creek system as well. We were looking for infiltration.
Ridley Creek: We cleaned the grit chamber in the screen building and also cleaned the brush and bamboo form the fence line.
Tallmadge Drive sewer replacement has been interesting to say the least. The contractor has cored the manhole and installed some pipe. This is not going very fast. Matt and I are inspecting the site on a daily basis. We are currently waiting for some elevation work to get completed. Mike explained in more detail what they are doing.
1603 East Boot Road has been connected to our sewer system.
Alarms: We responded to 23 alarms for November.
PA One Calls: We received 64 PA One calls for November.
Rainfall: November rainfall total was 8.15 inches.

2. Pennoni Engineer's Report for November

Invoices

  • Invoices with summaries are provided under separate cover.

Ridley Creek Sewage Treatment Plant (RCSTP)

  • No activity since last report.

RCSTP and Pump Stations' O&M Manual

  • We recommend the Manual be revisited to determine if updates are needed and/or if new information has become available to incorporate now that it has been in place for over one year.

Supplee Valley Pipe Lining

  • Prevailing wage discrepancies were resolved by the contractor, which was the final closeout item needed to make final payment. It is our understanding that final payment was made to the contractor thereafter.

Barkway Pump Station Grinder

  • We have initiated redesign and vendor coordination for an external Muffin Monster in a prefabricated manhole.

Ashbridge Pump Station Force Main

  • Test pits will be performed to identify backfill conditions along Manley Road with one test pit on Edith Road, as recommended by the Municipal Authority, when weather permits. No update since our last report.

MA 12-10-18 draft

2

Tallmadge Drive Sewer Main Replacement

  • The contractor began work on November 26. Groundwater and wet/loose soil conditions have dramatically impacted the contractor's progress and have caused him to fall behind his proposed schedule. The size of trench restoration and associated trenching, aggregate and paving costs are increasing as a result.
  • The contractor has completed installation of the 125 LF downstream pipe run and the replacement manhole. However, the pipe run was installed too high due to a contractor survey error. The contractor will coordinate with a surveyor at his own expense to determine if the upstream run can be installed at an acceptable, shallower slope to compensate for the higher downstream piping.
  • Construction will likely run past the required December 14 contract cutoff completion date (20 consecutive calendar days). An exact completion date will not be known until the survey has occurred. The contractor will notify residents of updates to the construction schedule.
  • The Public Works Department will install temporary hot mix asphalt paving upon completion of the work.

I&I Support and Reporting

  • It has been determined that instantaneous meter data is not available for the permanent meters, so, we have initiated a limited analysis of all permanent meters based on daily flow data, and we are preparing a semi-annual I&I report accordingly. The Township is coordinating with the metering company to add instantaneous metering capabilities if possible. No update since our last report.

New Connections

  • No activity since last report.

West Goshen Sewer System Consultation

  • No activity since last report.

Hershey's Mill Pump Station

  • We continued to evaluate electrical problems via discussions with the generator mechanic and evaluation of electrical test data provided by the mechanic. Our updated observations and recommendations will be provided separately.

3. Big Fish Environmental Services –

Scott's report showed that the Ridley Creek sewage treatment plant outfalls 001 and 002 is anticipate to achieve compliance with the permitted effluent discharge limitations during the month of November 2018. Discharge to the Applebrook irrigation lagoon remained off line during November 2018. Chemical usage utilized for total phosphorus removal, pH and total alkalinity remained consistent with previous months. No significant mechanical or operational issues were observed during operation of sludge dewatering equipment or SBR treatment process.
Scott revised DMR to the state and refiled. Rainfall flows have been higher. Average flows were discussed but still in compliance. He provided before and after photos of the corrective action work. It looks good. He recommends replacement of just the roto mat screen. They have a brush in stock.

MA 12-10-18 draft

3

Approval of Minutes

The minutes of the November 19, 2018 meeting were approved as amended.

Approval of Invoices

1. There was discussion of invoice #832261 for $1,889.25. Mike explained that they had additional time associated with Hershey Mill. He feels they will need $5,000.00 more which will increase the total from $23,000.00 to $28,000.00. Kevin recommended that the bills be paid as they are received for the rest of the year. He pointed out that the above invoice is incorrect because it shows $28,000.00 as the contract amount and not $23,000.00. Kevin moved to approve payment of the following Pennoni invoices and adjust the contract amount as per future invoices:

Pennoni invoice #832260 $ 113.75
Pennoni invoice #832261 $ 1,889.25
Pennoni invoice #832262 $ 332,25
Pennoni invoice #832263 $ 552.25

Phil seconded the motion. The motion passed unanimously.

Liaison Reports

Conservancy Board – Walter reported that they did the work at Clymers Woods on December 5th. In January they will select a date for the Keep East Goshen Beautiful Day.
Board of Supervisors – Carmen reported that the budget was adopted. They approved our contract with WEGO Police. There will be a public meeting in January for the open space amendment. They are conducting interviews for ABCs vacancies. Also they started a Pipeline Committee and a Sustainability Committee. Carmen thanked everyone for coming to the Holiday party and wished them all a Happy New Year.

Financial Reports

Jon Altshul provided the following written report:
In November, the Municipal Authority recorded -$14.65 in revenues (banking fees) and $9,966 in expenses, including $7,790 for general engineering, $1,381 for Tallmadge Drive engineering and $796 for legal expenses for a negative variance of $9,981. As of November 30th, the fund balance was $6,573.
Jon provided the 2019 proposed Municipal Authority budget and reviewed it. Phil moved that the MA approve the 2019 budget dated December 4, 2018. Dana seconded the motion. The motion passed unanimously.

New Business

1. Maillie Auditor fees - The fees for 2018 were $9,400.00. The fees for 2019 will increase by $250.00 to a total of $9,650. Kevin moved to continue to use Maillie as our auditor in the amount of $9,650.00 for 2019. Phil seconded the motion. The motion passed unanimously.
2. Pennoni 2019 Fees – Mike commented that they are requesting for continue as engineer with an increase of 3% which is consistent with the cost of living. Kevin moved to retain Pennoni as our Municipal Engineer at 2018 rates pending a 3% increase if approved by the BOS. Then the MA will accept the increase. Dana seconded the motion. The motion passed unanimously.
3. Roto Mat Screen - Dana moved to approve the repair of the roto mat screen segment in the amount of $11,208.00 and $1,000.00 for installation for a total of $12,208.00. Phil seconded the motion. The motion passed unanimously.

MA 12-10-18 draft

4

Adjournment

There being no further business, Phil moved to adjourn the meeting. Dana seconded the motion. The meeting was adjourned at 8:10 p.m. The next regular meeting will be held on Monday, January 14, 2019 at 7:00 pm.

Respectfully submitted,

Ruth Kiefer
Recording Secretary

MA 12-10-18 draft

5

Sue Smith

From: Michael Ellis <MEllis@Pennoni.com>
Sent: Thursday, January 10, 2019 3:34 PM
To: rsmith@eastgoshen.org; Jon Altshul; Mark Miller (mmiller@eastgoshen.org)
Cc: 'ssmith@eastgoshen.org'
Subject: Pennoni Invoices - Municipal Authority - December 2018
Attachments: EGMA Invoices (12-2018).pdf

Hi Rick, Jon, and Mark,

Our Municipal Authority invoices for December are attached. Please include this email with our invoices in the MA packet to describe two of the invoices:

  1. 2018 General Services, Project EGMAU18001 – The previously approved hourly rate budget was $23,000 as noted in the invoice. As discussed at the December MA meeting, the electrical evaluation of the Hershey's Mill PS issues extended our year-to-date general consultation effort beyond that budget. As reflected in this Final Invoice for this activity, the actual total effort for the year is $26,190. Please note this is less than the $28,000 that had been projected at the MA meeting. We propose the MA increase the budget to $26,190 consistent with this effort. *FYI, to decrease the potential for adjustments in 2019, the general consultation budget for 2019 was set at $27,000 to be consistent with the actual effort in 2017 and 2018.
  2. Tallmadge Dr Sewer, Project EGMAU18004 – The estimated hourly rate fee on this project was initially approved at $9,000 as noted in the invoice. However, the actual effort has exceeded that due to the extended construction schedule, extent of needed contractor oversight during construction, and to address numerous deficiencies in the completed work requiring repairs. The attached invoice is for a total effort as of 12/30/18 of $12,348.75. We anticipate the total effort will end up being around $16,000-$18,000 following the performance of 2-3 days of repair work next week, acceptance testing thereafter, final televising and any repairs in April, and processing final invoices and closeout documentation. We recommend the budget be increased accordingly to $18,000.

Please call me if you have any questions.

Thanks,
Mike

Michael Ellis, PE
Municipal Division Manager

Pennoni
121 Continental Drive, Suite 207 | Newark, DE 19713
Direct: +1 (302) 351-5236 | Mobile: +1 (302) 561-4235
www.pennoni.com | MEllis@Pennoni.com

[Pennoni Logo: PARTNERS FOR WHAT'S POSSIBLE]

1

[Pennoni Logo]

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice # : 839068
Invoice Date : 01/10/2019
Project : EGMAU17006
Project Name : Barkway PS Muffin Monster

For Services Rendered through: 12/30/2018

Continued design and plan revisions for Muffin Monster prefabricated manhole system, and coordinated with vendor for equipment specifications and details.

Phase Code / Name Contract
Amount
Previously
Billed
%
Complete
Complete
To Date
Amount
This Invoice
**** -- Professional Services $16,000.00 $9,421.29 62.52% $10,003.50 $582.21
Total : $16,000.00 $9,421.29 $10,003.50 $582.21
Amount Due This Invoice $582.21

[Signature: OK Jon Altshul 1/11/19]

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority
EGMAU17006 Invoice Summary

Invoice Date 1/10/2019

Project: EGMAU17006
Pennoni Job No.: Barkway PS Muffin Monster
Invoice No: 839068
Invoice Period: 10/15/2018 to 12/30/2018
Initial Authorization: $ 9,000.00 Date: 1/10/2019
Contract Amount: $ 16,000.00
Previously Invoiced: $ 9,421.29
Current Invoice: $ 582.21
Invoiced to Date ($): $ 10,003.50
Invoiced to Date (%): 63%
Remaining Budget ($): $ 5,996.50
Remaining Budget (%): 37%

Budget by Phase:

Phase Name: Barkway PS Muffin Monster
Phase Budget: $ 16,000.00
Previously Invoiced: $ 9,421.29
Current Invoice: $ 582.21
Invoiced to Date ($): $ 10,003.50
Invoiced to Date (%): 63%
Remaining Budget ($): $ 5,996.50
Remaining Budget (%): 37%

Comments: Continued design and plan revisions for Muffin Monster prefabricated manhole system, and coordinated with vendor for equipment specifications and details.

[Pennoni Logo]

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice # : 839069
Invoice Date : 01/10/2019
Project : EGMAU18002
Project Name : 2018 I&I Support and Reports

For Services Rendered through: 12/30/2018

FINAL INVOICE

Analyzed collection and conveyance systems' flow meter data, initiated preparation of semi-annual I&I Report #18, and continued scoping for Hershey's Mill Pump Station capacity upgrade including discussion with a developer's contractor to respond to scope and feasibility questions.

Phase : **** -- Professional Services

Total Phase : **** -- Professional Services Labor : 2,677.00
Expense : 0.00
Phase Total : 2,677.00
Amount Due This Invoice $2,677.00
Fee : 11,000.00
Prior Billings : 6,938.75
Current Billings : 2,677.00
Total Billings : 9,615.75

[Signature: OK Jon Altshul 1/11/19]

Phase : **** -- Professional Services

Labor

Class Hours/
Units
Rate Amount
Authority Engineer 2.00 123.00 246.00
Senior Professional 2.00 117.00 234.00
Associate Professional 15.25 91.00 1,387.75
Engineering Technician 9.75 83.00 809.25
Labor Total: 29.00 2,677.00
Total Phase : **** -- Professional Services Labor : $2,677.00
Expense : $0.00
Total Project : EGMAU18002 -- 2018 I&I Support and Reports Labor : $2,677.00
Expense : $0.00

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority
EGMAU18002 Invoice Summary

Invoice Date 1/10/2019

Project: EGMAU18002
Pennoni Job No.: 2018 I&I Support and Reports
Invoice No: 839069
Invoice Period: 11/12/2018 to 12/30/2018
Initial Authorization: $ 11,000.00 Date: 1/10/2019
Contract Amount: $ 11,000.00
Previously Invoiced: $ 6,938.75
Current Invoice: $ 2,677.00
Invoiced to Date ($): $ 9,615.75
Invoiced to Date (%): 87%
Remaining Budget ($): $ 1,384.25
Remaining Budget (%): 13%

Budget by Phase:

Phase Name: 2018 I&I Support and Reports
Phase Budget: $ 11,000.00
Previously Invoiced: $ 6,938.75
Current Invoice: $ 2,677.00
Invoiced to Date ($): $ 9,615.75
Invoiced to Date (%): 87%
Remaining Budget ($): $ 1,384.25
Remaining Budget (%): 13%

Comments: analyzed collection and conveyance systems' flow meter data, initiated preparation of semi-annual I&I Report #18, and continued scopeing for Hershey's Mill Pump Station capacity upgrade including discussion with developer's contractor to respond to scope and feasibility questions.

[Pennoni Logo]

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.
Invoice # : 839070
Invoice Date : 01/10/2019
Project : EGMAU18005
Project Name : Hershey's Mill Generator Replace

For Services Rendered through: 12/30/2018

Initiated analysis of replacement generator sizing and preparation of conceptual site plan for external generator.

Phase : 01 -- Concept Design

Total Phase : 01 -- Concept Design Labor : 301.50
Expense : 0.00
Phase Total : 301.50
Amount Due This Invoice $301.50
Fee : 5,000.00
Prior Billings : 0.00
Current Billings : 301.50
Total Billings : 301.50

[Signature: OK Jon Altshul 1/11/19]

Phase : 01 -- Concept Design

Labor

Class Hours/
Units
Rate Amount
Authority Engineer 1.50 123.00 184.50
Senior Professional 1.00 117.00 117.00
Labor Total: 2.50 301.50
Total Phase : 01 -- Concept Design Labor : $301.50
Expense : $0.00
Total Project : EGMAU18005 -- Hershey's Mill Generator Replace Labor : $301.50
Expense : $0.00

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority
EGMAU18005 Invoice Summary
Invoice Date 1/10/2019

Project: EGMAU18005
Pennoni Job No.: Hershey's Mill Generator Replacement
Invoice No: 839070
Invoice Period: NTP to 12/30/2018
Initial Authorization: $ 5,000.00 Date: 1/10/2019
Contract Amount: $ 5,000.00
Previously Invoiced: $ -
Current Invoice: $ 301.50
Invoiced to Date ($): $ 301.50
Invoiced to Date (%): 6%
Remaining Budget ($): $ 4,698.50
Remaining Budget (%): 94%

Budget by Phase:

Phase Name: Hershey's Mill Generator Replacement
Phase Budget: $ 5,000.00
Previously Invoiced: $ -
Current Invoice: $ 301.50
Invoiced to Date ($): $ 301.50
Invoiced to Date (%): 6%
Remaining Budget ($): $ 4,698.50
Remaining Budget (%): 94%

Comments: Inititated analysis of replacement generator sizing and preparation of conceptual site plan for external generator.

[Pennoni logo]

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328

Louis F. Smith, Twp Mgr.
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199

Invoice # : 839085
Invoice Date : 01/10/2019
Project : EGMAU18001
Project Name : 2018 General Services

For Professional Services Rendered through:12/30/2018

OK
Jon Altshul
1/11/19

FINAL INVOICE

Prepared November and December Engineer's Reports, reviewed RCSTP operator's reports, prepared for and attended November and December MA meetings, and provided alternative WWTP sampling labs for consideration to Township.

Hershey's Mill Pump Station electrical assessment: Continued evaluation of VFD, generator, and other electrical issues including coordination with repair technicians on electric load testing, transformer sizing, and service line splicing concerns; submitted memo summarizing November electrical site visit and recommendations; initiated letter to Township recommending larger transformer.

Phase Code Phase Name Fee Type Contract Amount Previously Billed Current Billing Total Billing
**** Professional Services NTE $ 23,000.00 $ 24,003.00 $ 2,187.00 $ 26,190.00
Subtotal: $ 24,003.00 $ 2,187.00 $ 26,190.00
Total: $ 24,003.00 $ 2,187.00 $ 26,190.00
Total Amount Due $ 2,187.00

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

Project : EGMAU18001 -- 2018 General Services
Invoice # : 839085

...Continued from previous page

Phase : **** -- Professional Services

Rate Schedule Labor

Class / Employee Name Hours Rate Amount
Associate Professional 0.25 91.00 22.75
Authority Engineer 13.50 123.00 1,660.50
Engineering Technician 3.25 83.00 269.75
Senior Professional 2.00 117.00 234.00
Rate Schedule Labor 2,187.00
Total Phase : **** -- Professional Services 2,187.00
Total Project : EGMAU18001 -- 2018 General Services 2,187.00

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
Pennoni Associates Inc.
Page: 2

East Goshen Municipal Authority
EGMAU18001 Invoice Summary
Invoice Date 1/10/2019

Project: EGMAU18001
Pennoni Job No.: 2018 General Services
Invoice No: 839085
Invoice Period: 11/12/2018 to 12/30/2018
Initial Authorization: $ 18,000.00 Date: 1/10/2019
Contract Amount: $ 23,000.00
Previously Invoiced: $ 24,003.00
Current Invoice: $ 2,159.00
Invoiced to Date ($): $ 26,162.00
Invoiced to Date (%): 114%
Remaining Budget ($): $ (3,162.00)
Remaining Budget (%): -14%

Budget by Phase:

Phase Name: 2018 General Services
Phase Budget: $ 23,000.00
Previously Invoiced: $ 24,003.00
Current Invoice: $ 2,159.00
Invoiced to Date ($): $ 26,162.00
Invoiced to Date (%): 114%
Remaining Budget ($): $ (3,162.00)
Remaining Budget (%): -14%

Comments: FINAL INVOICE

Prepared November and December Engineer's Reports, reviewed RCSTP operator's reports, prepared for and attended November and December MA meetings, and provided alternative WWTP sampling labs for consideration to Township.

Hershey's Mill Pump Station electrical assessment: Continued evaluation of VFD, generator, and other electrical issues including coordination with repair technicians on electric load testing, transformer sizing, and service line splicing concerns; submitted memo summarizing November electrical site visit and recommendations; initiated letter to Township recommending larger transformer.

[Pennoni logo]

INVOICE

Newark, DE
302-655-4451 Fax: 302-654-2895

Remit Payment To:
Pennoni
P.O. Box 827328
Philadelphia, PA 19182-7328

East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Attention: Louis F. Smith, Twp Mgr.

Invoice # : 839095
Invoice Date : 01/10/2019
Project : EGMAU18004
Project Name : Tallmadge Dr Sewer Constr Phase

For Services Rendered through: 12/30/2018

Pre-construction services consisting of shop drawing reviews, bypass pumping approach, schedule coordination, project contact list, and preparation of resident's notice. Construction services consisting of on-site observation of work and testing from 11/20/18 through 12/19/18 and engineering office support. Reviewed post-construction sewer videos, coordinated approach and schedule to resolve pipe and manhole deficiencies, prepared a Notice of Deficiencies letter to the contractor, and processed Pay Applications #1 and #2.

Phase : **** -- Professional Services

Labor : 9,082.00
Expense : 0.00
Phase Total : 9,082.00
Amount Due This Invoice $9,082.00

OK
Jon Altshul
1/11/19

Fee : 9,000.00
Prior Billings : 3,266.75
Current Billings : 9,082.00
Total Billings : 12,348.75

Phase : **** -- Professional Services
Labor

Class Hours/Units Rate Amount
Authority Engineer 10.75 123.00 1,322.25
Senior Professional 0.25 117.00 29.25
Associate Professional 21.25 91.00 1,933.75
Sr. Engineering Technician 63.50 89.00 5,651.50
Engineering Technician 1.75 83.00 145.25
Labor Total: 97.50 9,082.00
Total Phase : **** -- Professional Services Labor : $9,082.00
Expense : $0.00
Total Project : EGMAU18004 -- Tallmadge Dr Sewer Constr Phase Labor : $9,082.00
Expense : $0.00

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

East Goshen Municipal Authority
EGMAU18004 Invoice Summary
Invoice Date 1/10/2019

Project: EGMAU18004
Pennoni Job No.: Tallmadge Drive Sewer Construction Phase
Invoice No: 839095
Invoice Period: 11/12/2018 to 12/30/2018
Initial Authorization: $ 9,000.00 Date: 1/10/2019
Contract Amount: $ 9,000.00
Previously Invoiced: $ 3,266.75
Current Invoice: $ 9,082.00
Invoiced to Date ($): $ 12,348.75
Invoiced to Date (%): 137%
Remaining Budget ($): $ (3,348.75)
Remaining Budget (%): -37%

Budget by Phase:

Phase Name: Tallmadge Drive Sewer Construction Phase
Phase Budget: $ 9,000.00
Previously Invoiced: $ 3,266.75
Current Invoice: $ 9,082.00
Invoiced to Date ($): $ 12,348.75
Invoiced to Date (%): 137%
Remaining Budget ($): $ (3,348.75)
Remaining Budget (%): -37%

Comments: Pre-construction services consisting of shop drawing reviews, bypass pumping approach, schedule coordination, project contact list, and preparation of resident's notice. Construction services consisting of on-site observation of work and testing from 11/20/18 through 12/19/18 and engineering office support. Reviewed post-construction sewer videos, coordinated approach and schedule to resolve pipe and manhole deficiencies, prepared a Notice of Deficiencies letter to the contractor, and processed Pay Applications #1 and #2.

[Gawthrop Greenwood, PC logo]
Gawthrop Greenwood, PC
Attorneys at Law
17 East Gay Street, Suite 100 | (p) 610-696-8225
West Chester, PA 19381-0562 | (f) 610-344-0922
gglaw@gawthrop.com | www.gawthrop.com

Page: 1
Date: 01/08/2019
Client No: 6604-001M
Invoice No. 203528

East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380

General Authority Services

Fees

Date Staff Description Hours Amount
12/07/2018 PMM Email from S Smith with meeting materials. 0.20
12/10/2018 PMM Review and analyze meeting packet in preparation for Authority meeting; Attend Board meeting. 1.50
12/21/2018 SLF Telephone call from M Ellis regarding performance bond question. 0.30
12/28/2018 PMM Email from J Altshul regarding Tallmadge Drive. 0.20
For Current Services Rendered 2.20 440.00

Recapitulation

Timekeeper Hours Hourly Rate Total
Stacey L. Fuller 0.30 $200.00 $60.00
Patrick M. McKenna 1.90 200.00 380.00
Previous Balance $384.06
Total Current Charges 440.00
12/26/2018 Payment -384.06
Balance Due $440.00

To ensure proper credit, please write client number on your check when returning payment. Thank You.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.

[Gawthrop Greenwood, PC logo]
Gawthrop Greenwood, PC
Attorneys at Law
17 East Gay Street, Suite 100 | (p) 610-696-8225
West Chester, PA 19381-0562 | (f) 610-344-0922
gglaw@gawthrop.com | www.gawthrop.com

Page: 1
Date: 12/05/2018
Client No: 6604-001M
Invoice No. 202493

East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380

General Authority Services

Fees

Date Staff Description Hours Amount
11/19/2018 JKW Prepare for meeting; Attend meeting. 2.00
For Current Services Rendered 2.00 400.00

Recapitulation

Timekeeper Hours Hourly Rate Total
Jessica K. Wiesak 2.00 $200.00 $400.00

Expenses

CREDIT MEMO: Ref: J Wiesak mileage on invoice no. 200550 dated 10/8/18. -15.94
Total Credits for Expenses -15.94

Previous Balance $795.94
Total Current Charges 384.06
11/29/2018 Payment -715.94
11/29/2018 Payment -80.00
Total Payments -795.94
Balance Due $384.06

To ensure proper credit, please write client number on your check when returning payment. Thank You.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.

Pd. Dec. mtg.

[JWC Environmental logo]
2850 S. Red Hill Ave., STE 125
Santa Ana, CA 92705
(949) 833-3888

Invoice No: 95288
Date: 12/26/2018
Order No: S031631
Page No: 1
F.O.B: Origin
Sold To Ship To
East Goshen Township
1580 Paoli Pike
West Chester , PA 19380
US
East Goshen Township
1580 Paoli Pike
West Chester , PA 19380
US

TIN: 45-2771126
DUNNS# 61-059-2388

CUSTOMER ID CUSTOMER PO PAYMENT TERMS FREIGHT TERMS
6005886 2018.86 NET 30 DAYS Freight: Billed
SALES REP ID SHIPPING METHOD SHIP DATE INVOICE DUE DATE
035 Old Dominion Freight Line 12/26/2018 1/25/2019
LI# QUANTITY PART DESCRIPTION TX UNIT PRICE EXTENDED PRICE
ORD SHP BCK
1 1 1 0 AMC0109-3235-480-06-S SCREEN, SEGMENT 6MM PRF 35DG XE SS $11,208.90 $11,208.90
2 1 1 0 TARIFF Tariff Surcharge
Recently, the US Government, has implemented the following trade restrictions:
Section 232, June 1, 2018: Restrictions on steel mill (25%) and aluminum articles (10%). All countries of origin except Argentina, Australia, Brazil, and South Korea.
Section 301, July 6, 2018 Restrictions on products from China, 25%
The tariff surcharge represents the increased cost of manufacturing our products as a result of the government-imposed trade restrictions.
$294.79 $294.79

screen replacement

APPROVED BY: MDM
DATE PAID:
CHECK #:
CHARGED TO: 05422-3700
09409-7400
09409-7400
07424-7440

SUB TOTAL: $11,503.69
TARIFF TOTAL: $294.79
SALES TAX: $0.00
SHIPPING & HANDLING CHARGES: $327.03
TOTAL AMOUNT DUE: $11,830.72

PLEASE REFERENCE THIS INVOICE NUMBER ON YOUR CHECK AND REMIT TO: JWC Environmental Inc.
P.O. Box 848853
Los Angeles, CA 90084-8853

IF PAYING BY ACH OR WIRE:

ACH/WIRE INSTRUCTIONS
BANK NAME: WELLS FARGO
ADDRESS: IRVINE, CA.
ABA#: 121000248
ACCOUNT #: 4123519118
ACCOUNT NAME: JWC Environmental Inc.

[JWC Environmental logo]
2850 S. Red Hill Ave., STE 125
Santa Ana, CA 92705
(949) 833-3888

Invoice No: 95288
Date: 12/26/2018
Order No: S031631
Page No: 1
F.O.B: Origin
Sold To Ship To
East Goshen Township
1580 Paoli Pike
West Chester , PA 19380
US
East Goshen Township
1580 Paoli Pike
West Chester , PA 19380
US

TIN: 45-2771126
DUNNS# 61-059-2388

CUSTOMER ID CUSTOMER PO PAYMENT TERMS FREIGHT TERMS
6005886 2018.86 NET 30 DAYS Freight: Billed
SALES REP ID SHIPPING METHOD SHIP DATE INVOICE DUE DATE
035 Old Dominion Freight Line 12/26/2018 1/25/2019
LI# QUANTITY PART DESCRIPTION TX UNIT PRICE EXTENDED PRICE
ORD SHP BCK

Subject: Tariff Surcharge

Dear Valued JWC Environmental Customer,

The U.S. government has imposed new steel tariffs on imported raw steel (section 232) and certain imported product (section 301). JWC is committed to continuously improving efficiency which includes managing costs, and when possible protecting our customers from the adverse impacts of rising input costs. Unfortunately, due to the rapid nature of these new tariffs JWC must take action to recover some of these cost increases.

Given the uncertain nature of these market dynamics, JWC will not be increasing our base prices. Instead, JWC has implemented a “Tariff Surcharge”. The surcharge will be a flat rate of 2.63% which will cover a portion of JWC’s increase costs due to the new tariffs and will remain separate and transparent from base prices.

Using this method, JWC can quickly adapt to any future actions. If the tariffs are expanded or reduced JWC will be able to adjust the surcharge accordingly.

[JWC Environmental logo]
2600 S. Garnsey Street
Santa Ana, CA 92707

PACKLIST

Packlist ID: 92657
Date: 12/26/2018
Page: 1

S031631

Sold To Address Ship To Address
East Goshen Township
1580 Paoli Pike
West Chester , PA 19380
US
East Goshen Township
1580 Paoli Pike
West Chester , PA 19380
US
CUSTOMER ID F.O.B.
6005886 Origin
SALES REP ID OUR ORDER NUMBER
035 S031631
QUANTITY CUSTOMER PART NO. OUR WORK ORDER NO.
ORD SHP BCK
1.00 1.00 0.00

Screen Replacement
Capital Replacem--

Ship Weight: 0.00

1.00 1.00 0.00

Ship Weight: 0.00

Recently, the US Government, has implemented the following trade restrictions:
Section 232, June 1, 2018: Restrictions on steel mill (25%) and aluminum articles (10%). All countries of origin except Argentina, Australia, Brazil, and South Korea.
Section 301, July 6, 2018 Restrictions on products from China, 25%
The tariff surcharge represents the increased cost of manufacturing our products as a result of the government-imposed trade restrictions.

0.00 1.00 0.00 SALESTAX Avalara Sales Tax

Ship Weight: 0.00

Shipped Unit of Measure:

APPROVED BY: MDM
DATE PAID:
CHECK #:
CHARGED TO: 05422-
Ridley Creek

RECEIVED BY: ___________________

[JWC Environmental logo]
2600 S. Garnsey Street
Santa Ana, CA 92707

PACKLIST

Packlist ID: 92657
Date: 12/26/2018
Page: 2
Sold To Address Ship To Address
East Goshen Township
1580 Paoli Pike
West Chester , PA 19380
US
East Goshen Township
1580 Paoli Pike
West Chester , PA 19380
US
CUSTOMER ID CUSTOMER PO PAYMENT TERMS F.O.B.
6005886 2018.86 NET 30 DAYS Origin
SALES REP ID SHIPPING METHOD SHIP DATE OUR ORDER NUMBER
035 Old Dominion Freight Line 12/26/2018 S031631
QUANTITY PART ID DESCRIPTION CUSTOMER PART NO. OUR WORK ORDER NO.
ORD SHP BCK

ORDER SPECIFICATIONS

EM/MM
****************************************
AMA3200-480
SN: 105661-3-1
****************************************

RECEIVED BY: ___________________

Memo

To: Municipal Authority
From: Jon Altshul
Re: MA December Financial Report
Date: January 11, 2019

In December, the Municipal Authority recorded 19,985 in revenues (a $20,000 transfer from Sewer Operating minus banking fees) and $12,635 in expenses, including $8,382 for the Q4 overhead chargeback, for a positive variance of $7,350. As of December 31st, the fund balance was $13,923.

For tonight’s meeting, I seek your recommendation on whether the Tallmadge Drive and RCSTP screen replacement expenses should be paid by the MA (via reimbursement from the Township’s sewer funds) or via the Sewer Operating and Sewer Capital Reserve funds. These projects were not included in the MA’s 2019 budget—Tallmadge because it was budgeted by the Township for last year and the screen because it was an emergency repair. In addition, for the purposes of our financial statements both projects will be accrued back to 2018 for accounting purposes.

EAST GOSHEN TOWNSHIP
Other Funds
December 2018
Municipal Authority

Account Title Acct # Annual Budget Y-T-D Budget Y-T-D Actual Y-T-D Variance M-T-D Budget M-T-D Actual M-T-D Variance
REVENUE
INTEREST EARNINGS 07341 1000 10 10 (144.97) (154.97) (14.65) (14.65)
CAPITAL RESERVE-INTEREST 07341 1010
INTEREST EARNED - CONSTRUCTION 07341 1020 50 50 613.94 563.94
DCED GRANT 07354 0400
C.C. TAPPING FEES 07364 1100 8,000 8,000 (8,000.00) 4,000 (4,000.00)
R.C.TAPPING FEES 07364 1110 2,000 2,000 4,000.00 2,000.00
M.C. LOAN PAYMENTS 07364 1120
CONNECTION FEES - SEWER 07364 1130 1,692 1,692 1,127.52 (564.48) 846 (846.00)
MISCELLANEOUS REVENUE 07380 1000 564.51 564.51
TRANSFER FROM GENERAL ACCT 07392 0100 71.30 71.30
TRANSFER FROM SEWER OPERATING 07392 0500 89,853 75,853 110,000.00 34,147.00 6,322 20,000.00 13,678.00
TRANSFER FROM SEWER CAP RESV 07392 0501
TRANSFER-ANNUAL CAP.RESERVE 07392 0510
GRANT REVENUE 07392 0800
LOAN PROCEEDS - SEWER PROJECT 07392 0804
TRANSFER FROM SEWER CAP RESERVE 07392 0900
TOTAL REVENUE 101,605 87,605 116,232.30 28,627.30 11,168 19,985.35 8,817.35
EXPENSES
ADMINISTRATIVE WAGES 07424 1400 32,411 32,411 33,085.38 (674.38) 8,103 8,382.36 (279.36)
R.C. LOAN ISSUANCE COSTS 07424 1500
MISCELLANEOUS EXPENSE 07424 3000 2,500 2,500 2,317.00 183.00 209 981.00 (772.00)
MUNIC.AUTH.-AUDITING 07424 3110 9,384 9,384 9,400.00 (16.00)
ENGINEERING SERVICES 07424 3130 43,260 43,260 73,406.96 (30,146.96) 3,605 2,335.25 1,269.75
LEGAL SERVICES 07424 3140 4,600.00 (4,600.00) 384.06 (384.06)
W.G. C.C.STP-UPGRADE 07424 7400
MANHOLE COVER REPLACEMENTS 07424 7405
C.C. CAPITAL - METERS 07424 7410
C.C. CAPITAL- COLLECTION 07424 7420
C.C. CAPITAL- INTERCEPTOR 07424 7430
CAPITAL PROJ.-ENGINEERING 07424 7431
R.C. CAPITAL-STP 07424 7440
R.C. CAPITAL - COLLECTION 07424 7450
R.C.-CAP. PROJ.-ENGINEER 07424 7451
CAP.REPLACEMENT R.C. 07424 7490
CAPITAL REPLACEMENT ASHBRIDGE 07424 7491
HERSHEY MILL STATION - ENGINEER 07426 1000
HERSHEY MILL STATION - CONSTRUCTION 07426 2000
TALLMADGE DRIVE 07426 3000 14,000 14,000 19,232.75 (5,232.75) 1,167 552.25 614.72

Report Date 1812 01/11/19 8 : 33 AM

EAST GOSHEN TOWNSHIP
Other Funds
December 2018
Municipal Authority

Account Title Acct # Annual Budget Y-T-D Budget Y-T-D Actual Y-T-D Variance M-T-D Budget M-T-D Actual M-T-D Variance
RESERVOIR PUMP STATION - ENGINEER 07428 1000 188.00 (188.00)
RESERVOIR PUMP STATION CONSTRUCTION 07428 2000
WEST GOSHEN CAPITAL 07429 6100 59,736 59,736 102,339.08 (42,603.08)
M.C.-DVRFA-DEBT SERVICE 07471 1000
M.A.-R.C. DEBT SERVICE 07471 1010
DVRFA PUMPING STATIONS - PRINCIPAL 07471 2000
M.C.-DVRFA-INTEREST PAYMN 07472 1000
M.A.-R.C. INTEREST 07472 1010
DVRFA PUMPING STATIONS - INTEREST 07472 2000
TRANSFER TO GENERAL FUND 07492 0100 71.30 (71.30)
TRANSFER TO SEW.OPERATING 07492 0500
TRF TO SEWER SINKING FUND 07492 0550
TRANSFER TO AUTHORITY CAP FUND 07492 0990
TOTAL EXPENSES 161,291 161,291 244,640.47 (83,349.47) 13,084 12,634.92 448.75
NET RESULT FROM OPERATIONS (59,686) (73,686) (128,408.17) (54,722.17) (1,916) 7,350.43 9,266.10

Report Date 1812 01/11/19 8 : 33 AM

2018 ALL MUNICIPAL AUTHORITY TRANSACTIONS

Account # Description Per Src Debits Credits Balance Date Check# Name Description Description 2 Description 3
07341-1000BEGINNING BALANCE-
07341-1000INTEREST EARNINGS1801JE-0.312/2/2018INTERESTINTEREST EARNED JANUARY 201807 FUND
07341-1000INTEREST EARNINGS1802JE-0.202/14/2018INTERESTINTEREST ADJ. FROM JAN.20187105.2
07341-1000INTEREST EARNINGS1802JE-0.543/5/2018INTERESTINTEREST EARNED FEBRUARY 201807 FUND
07341-1000INTEREST EARNINGS1803EX15.00-3/5/201862192 1REIMBURSE S/R FOR BANK FEESINTEREST EARNINGS
07341-1000INTEREST EARNINGS1803JE-0.474/2/2018INTERESTINTEREST EARNED MARCH 201807 FUND
07341-1000INTEREST EARNINGS1804EX15.00-4/2/201862551 1REIMB.S/R FOR 3/2018 BANK FEESINTEREST EARNINGS
07341-1000INTEREST EARNINGS1804JE-0.555/1/2018INTERESTINTEREST EARNED APRIL 201807 FUND
07341-1000INTEREST EARNINGS1805EX15.00-5/1/201862911 1REIMBURSMT- 4/2018 BANK FEESINTEREST EARNINGS
07341-1000INTEREST EARNINGS1805EX15.00-6/1/201863388 1BANK FEES - MAY 2018INTEREST EARNINGS
07341-1000INTEREST EARNINGS1805EX-15.006/5/2018REVERSEREVERSE TRX 63388 EXPENSE TOBE ENTERED IN JUNE NOT MAY
07341-1000INTEREST EARNINGS1805JE-0.516/1/2018INTERESTINTEREST EARNED MAY 201807 FUND
07341-1000INTEREST EARNINGS1806EX15.00-6/5/201863459 1REIMBURSE S/R FOR MAY '18 FEESINTEREST EARNINGS
07341-1000INTEREST EARNINGS1806JE-0.407/3/2018INTERESTINTEREST EARNED JUNE 20187100.1035
07341-1000INTEREST EARNINGS1807EX15.00-7/3/201863820 5REIMBURSE S/R - 5/2018 BK.FEESINTEREST EARNINGS
07341-1000INTEREST EARNINGS1807EX-15.007/30/201864317 1REVERSE EXP.TRX 63820M&T BANK - GEN'L CHKG # 9852637421
07341-1000INTEREST EARNINGS1807EX15.00-7/30/201864322 1REIMBURSE S/R 6/2018 BK.FEESINTEREST EARNINGS
07341-1000INTEREST EARNINGS1807JE-0.408/2/2018INTERESTINTEREST EARNED JULY 20187100.1035
07341-1000INTEREST EARNINGS1808EX15.00-8/3/201864289 1REIMBURSE S/R - 7/2018 BK FEESINTEREST EARNINGS
07341-1000INTEREST EARNINGS1808JE-0.149/4/2018INTERESTINTEREST EARNED AUGUST 20187100.1035
07341-1000INTEREST EARNINGS1809JE15.00-9/5/2018BANK FEESREIMBURSE S/R FOR AUGUST 2018BANK FEES
07341-1000INTEREST EARNINGS1809JE-0.4110/1/2018INTERESTINTEREST EARNED SEPT.20187100.1035
07341-1000INTEREST EARNINGS1810JE15.00-10/1/2018REIMBURSEREIMBURSE S/R FOR SEPT.2018BANK FEES
07341-1000INTEREST EARNINGS1810JE-0.4011/1/2018INTERESTINTEREST EARNED OCTOBER 20187100.1035
07341-1000INTEREST EARNINGS1811JE15.00-11/1/2018BANK FEESREIMBURSE S/R FOR OCTOBER 2018BANK FEES
07341-1000INTEREST EARNINGS1811JE-0.3511/30/2018INTERESTINTEREST EARNED NOVEMBER 20187100.1035
07341-1000INTEREST EARNINGS1812JE15.00-12/3/2018BANK FEESREIMBURSE S/R FOR NOV.2018BANK FEES
07341-1000INTEREST EARNINGS1812JE-0.3512/31/2018INTERESTINTEREST EARNED DECEMBER 20187100.1035
07341-1020BEGINNING BALANCE-
07341-1020INTEREST EARNED - CONSTRUCTI1801JE-391.642/2/2018INTERESTINTEREST EARNED JANUARY 201807 FUND
07341-1020INTEREST EARNED - CONSTRUCTI1802JE-69.313/5/2018INTERESTINTEREST EARNED FEBRUARY 201807 FUND
07341-1020INTEREST EARNED - CONSTRUCTI1803JE-81.664/2/2018INTERESTINTEREST EARNED MARCH 201807 FUND
07341-1020INTEREST EARNED - CONSTRUCTI1804JE-71.305/1/2018INTERESTINTEREST EARNED APRIL 201807 FUND
07341-1020INTEREST EARNED - CONSTRUCTI1805JE-0.036/1/2018INTERESTINTEREST EARNED MAY 201807 FUND
07364-1110BEGINNING BALANCE-
07364-1110R.C.TAPPING FEES1807RE-2,000.007/13/2018ROBERTSTAP IN FEE FOR MARLIN DRR.C.TAPPING FEES
07364-1110R.C.TAPPING FEES1810RE-2,000.0010/30/201865507 1TAP IN FEE -1603 E BOOT RDR.C.TAPPING FEES
07364-1130BEGINNING BALANCE-
07364-1130CONNECTION FEES - SEWER1801CR-423.001/25/20182572STOFFLET, MICHAEL
07364-1130CONNECTION FEES - SEWER1802CR-423.002/13/2018494JACOBS, ROBERT & CHERYL
07364-1130CONNECTION FEES - SEWER1802CR-423.002/27/2018148GEORGE SMITH & CHRISTINA CONLE
07364-1130CONNECTION FEES - SEWER1802JE282.24-2/13/2018PINE ROCKANNUAL PINE ROCK INSTALLMENTJACOBS & STOFFLET INTEREST
07364-1130CONNECTION FEES - SEWER1802JE141.12-2/27/2018PINE ROCKANNUAL PINE ROCK INSTALLMENT
07364-1130CONNECTION FEES - SEWER1803CR-423.003/23/201811373243PAPPANO, JOSEPH & PATRICIA
07364-1130CONNECTION FEES - SEWER1803JE141.12-3/23/2018PINE ROCKANNUAL PINE ROCK INSTALLMENTRC214 PAPPANO
07380-1000BEGINNING BALANCE-
07380-1000MISCELLANEOUS REVENUE1802JE-282.242/13/2018PINE ROCKANNUAL PINE ROCK INSTALLMENTJACOBS & STOFFLET INTEREST
07380-1000MISCELLANEOUS REVENUE1802JE-141.122/27/2018PINE ROCKANNUAL PINE ROCK INSTALLMENT
07380-1000MISCELLANEOUS REVENUE1803JE-141.123/23/2018PINE ROCKANNUAL PINE ROCK INSTALLMENTRC214 PAPPANO
07380-1000MISCELLANEOUS REVENUE1808JE-0.038/16/2018DEPOSITDEPOSIT CK.7100.1035 TO CLOSEOUT FULTON 7105.2000
07392-0100BEGINNING BALANCE-
07392-0100TRANSFER FROM GENERAL ACCT1805JE-71.306/7/2018XFERXFER $ TO MA REGARDING DEPOSITERROR 5/10/18
07392-0500BEGINNING BALANCE-
07392-0500TRANSFER FROM SEWER OPERAT1803JE-30,000.003/29/2018XFERXFER $ FROM SEWER TO MUNICIPALTO COVER EXPENSES
07392-0500TRANSFER FROM SEWER OPERAT1806JE-30,000.006/22/2018XFERXFER $ FROM SEWER TO MA
07392-0500TRANSFER FROM SEWER OPERAT1809JE-30,000.009/12/2018XFERXFER FROM SEWER TO M.A.9/12/2018
07392-0500TRANSFER FROM SEWER OPERAT1812JE-20,000.0012/28/2018XFERXFER $ FROM SEWER TO MA12/28/2018
07424-1400BEGINNING BALANCE-
Account # Description Per Src Debits Credits Balance Date Check# Name Description Description 2
07424-1400ADMINISTRATIVE WAGES1803CD8,160.33--3/26/20183121EAST GOSHEN TOWNSHIP - GENERA1ST QTR.2018 REIMBURSEMENT - MA
07424-1400ADMINISTRATIVE WAGES1806CD8,160.33--6/21/20183129EAST GOSHEN TOWNSHIP - GENERA2ND QTR.2018 REIMBURSEMENT - MA
07424-1400ADMINISTRATIVE WAGES1809CD8,382.36--9/28/20183135EAST GOSHEN TOWNSHIP - GENERAQTR.3 2018 REIMBURSEMENT - MUN.AUTH
07424-1400ADMINISTRATIVE WAGES1812CD8,382.36--12/28/20183142EAST GOSHEN TOWNSHIP - GENERA4TH QTR.2018 REIMBURSEMENT - MA
07424-3000BEGINNING BALANCE-
07424-3000MISCELLANEOUS EXPENSE1801CD100.00--1/31/20183114COMMONWEALTH FINANCING AUTHGRANT APPLIC. DCED - WATER & SEWERPROGRAM FOR BARKWAY
07424-3000MISCELLANEOUS EXPENSE1805CD1,236.00--5/30/20183125DELAWARE RIVER BASIN COMMISSIANNUAL FEE D-2000-030 CP WASTEWATER DISCHARGE
07424-3000MISCELLANEOUS EXPENSE1812CD981.00--12/20/20183141PENNSYLVANIA MUNICIPAL AUTHOR2019 ACTIVE MEMBERSHIP DUES
07424-3110BEGINNING BALANCE-
07424-3110MUNIC.AUTH.-AUDITING1803CD6,964.00--3/22/20183120MAILLIE FALCONIERO & CO.PROGRESS BILLING - M.AUTHORITY 2017FINANCIAL STATEMENTS
07424-3110MUNIC.AUTH.-AUDITING1804CD2,436.00--4/17/20183123MAILLIE FALCONIERO & CO.EXAMINATION 2017 MA FINANCIAL STMTS
07424-3130BEGINNING BALANCE-
07424-3130ENGINEERING SERVICES1801CD12,523.56--1/24/20183113PENNONI ASSOCIATES INC.SERV.THRU 12/10/17 2017 GENERALSERVICES
07424-3130ENGINEERING SERVICES1802CD5,415.00--2/15/20183115PENNONI ASSOCIATES INC.SERVICES THRU 1/14/18 -2017 GENERAL
07424-3130ENGINEERING SERVICES1802CD552.50--2/22/20183117PENNONI ASSOCIATES INC.SERVICE THRU 1/14/18 SUPPLEE VAL.
07424-3130ENGINEERING SERVICES1803CD11,749.08--3/15/20183118PENNONI ASSOCIATES INC.SERVICES THRU 2/11/18 2018 GEN.SERV
07424-3130ENGINEERING SERVICES1806CD9,622.25--6/7/20183126PENNONI ASSOCIATES INC.SERVICES THRU 4/15/18 SUPPLEE VAL.
07424-3130ENGINEERING SERVICES1806CD7,503.93--6/12/20183127PENNONI ASSOCIATES INC.SERVICES THRU 5/20/18 BARKWAY PS
07424-3130ENGINEERING SERVICES1807CD16,679.82--7/11/20183130PENNONI ASSOCIATES INC.SERVICES THRU 6/17/18 BARKWAY
07424-3130ENGINEERING SERVICES1807JE-10,556.75-7/10/2018RECLASSRECLASS TALLMADGE DR EXPENSES
07424-3130ENGINEERING SERVICES1808CD3,619.00--8/15/20183132PENNONI ASSOCIATES INC.PROF.SERV. THRU 8/5/18 2018 GENERAL
07424-3130ENGINEERING SERVICES1809CD1,134.50--9/11/20183133PENNONI ASSOCIATES INC.SERVICES THRU 8/12/18 SUPPLEE VAL.
07424-3130ENGINEERING SERVICES1810CD4,839.25--10/10/20183136PENNONI ASSOCIATES INC.SERVICES THRU 9/16/18 SUPPLEE VALL.
07424-3130ENGINEERING SERVICES1811CD7,789.57--11/26/20183138PENNONI ASSOCIATES INC.SERVICE THRU 10/14/18 2018 I&I
07424-3130ENGINEERING SERVICES1812CD2,335.25--12/11/20183139PENNONI ASSOCIATES INC.SERVICES THRU 11/11/18 SUPPLEE VALL
07424-3140BEGINNING BALANCE-
07424-3140LEGAL SERVICES1801CD680.00--1/24/20183112GAWTHROP GREENWOOD & HALSTELEGAL SERVICES DEC. 2017 GEN.AUTH.
07424-3140LEGAL SERVICES1802CD240.00--2/22/20183116GAWTHROP GREENWOOD & HALSTELEGAL SERVICE - JAN.2018 GEN.AUTH.
07424-3140LEGAL SERVICES1803CD400.00--3/19/20183119GAWTHROP GREENWOOD & HALSTELEGAL SERVICE - FEBRUARY 2018
07424-3140LEGAL SERVICES1804CD380.00--4/17/20183122GAWTHROP GREENWOOD & HALSTELEGAL SERVICE 3/12/18
07424-3140LEGAL SERVICES1805CD480.00--5/16/20183124GAWTHROP GREENWOOD & HALSTELEGAL SERVICE - APRIL 2018 GEN.AUTH
07424-3140LEGAL SERVICES1806CD440.00--6/18/20183128GAWTHROP GREENWOOD & HALSTELEGAL SERV.- MAY 2018 GEN.AUTHORITY
07424-3140LEGAL SERVICES1807CD300.00--7/30/20183131GAWTHROP GREENWOOD & HALSTELEGAL SERVICE JUNE 2018 GEN.AUTHOR.
07424-3140LEGAL SERVICES1809CD500.00--9/14/20183134GAWTHROP GREENWOOD & HALSTELEGAL SERVICE 8/9-8/13/18 GEN.AUTH.
07424-3140LEGAL SERVICES1811CD795.94--11/26/20183137GAWTHROP GREENWOOD & HALSTELEGAL SERV. 9/7-9/10/18 GEN. AUTH.
07424-3140LEGAL SERVICES1812CD384.06--12/20/20183140GAWTHROP GREENWOOD & HALSTELEGAL SERVICE - 11/19/18 GEN.AUTH.
07426-3000BEGINNING BALANCE-
07426-3000TALLMADGE DRIVE1807CD1,980.00--7/11/20183130PENNONI ASSOCIATES INC.SERVICE THRU 6/17/18 2018 TALLMADGE
07426-3000TALLMADGE DRIVE1807JE10,556.75--7/10/2018RECLASSRECLASS TALLMADGE DR EXPENSES
07426-3000TALLMADGE DRIVE1808CD2,607.25--8/15/20183132PENNONI ASSOCIATES INC.PROF.SERV. THRU 8/5/18 2018 TALLMDG
07426-3000TALLMADGE DRIVE1809CD822.00--9/11/20183133PENNONI ASSOCIATES INC.SERV.THRU 8/12/18 TALLMADGE- GEN.SERVICE 2018
07426-3000TALLMADGE DRIVE1810CD1,333.75--10/10/20183136PENNONI ASSOCIATES INC.SERVICES THRU 9/16/18 TALLMADGE
07426-3000TALLMADGE DRIVE1811CD1,280.75--11/26/20183138PENNONI ASSOCIATES INC.SERVICE THRU 10/14/18 TALLMDGE
07426-3000TALLMADGE DRIVE1812CD552.25--12/11/20183139PENNONI ASSOCIATES INC.SERV. THRU 11/11/18 TALLMADGE SEWER
07428-1000BEGINNING BALANCE-
07428-1000RESERVOIR PUMP STATION - ENG1802CD142.50--2/22/201822016PENNONI ASSOCIATES INC.SERVICE THRU 1/14/18 RESERV.RD PS
07428-1000RESERVOIR PUMP STATION - ENG1806CD45.50--6/7/20183126PENNONI ASSOCIATES INC.SERVICES THRU 4/15/18 RESERVOIR RDFINAL INVOICE
07429-6100BEGINNING BALANCE-
07429-6100WEST GOSHEN CAPITAL1801CD30,050.70--1/24/201822015WEST GOSHEN SEWER AUTHORITY16.67% OF COST - ENHANCED CHEMICALADDITION
07429-6100WEST GOSHEN CAPITAL1802CD3,664.01--2/22/201822017WEST GOSHEN SEWER AUTHORITY16.67% - ENHANCED CHEMICAL ADDITION& ANAEROBIC DIGESTER RE
07429-6100WEST GOSHEN CAPITAL1803CD(3,664.01)--3/15/201822017WEST GOSHEN SEWER AUTHORITYVOID CK. 2017
07429-6100WEST GOSHEN CAPITAL1804CD72,288.38--4/13/201822018WEST GOSHEN SEWER AUTHORITY2017 SEWER SYSTEM REPAIR PROJECT.16667 % EAST GOSHEN SH.
07492-0100BEGINNING BALANCE-
07492-0100TRANSFER TO GENERAL FUND1805CD71.30--5/10/201822019EAST GOSHEN TOWNSHIP - GENERAXFER TO GENERAL TO CLOSE ACCOUNT
07492-0500BEGINNING BALANCE-
07492-0500TRANSFER TO SEW.OPERATING1806JE30,000.00--6/22/2018XFERXFER FROM SEWER TO MA
07492-0500TRANSFER TO SEW.OPERATING1806JE-30,000.00-6/22/2018REVERSEREVERSE TRX 63662

[Pennoni logo]
Christiana Executive Campus
121 Continental Drive, Suite 207
Newark, DE 19713
T: 302-655-4451
F: 302-654-2895
www.pennoni.com

January 3, 2019

EGMAU18004

Randall Weaver
Iron Eagle Excavating
35 Ann Street
Highspire, PA 17034

Re: Notice of Deficiencies & Resolution Requirements
Tallmadge Drive Sewer Replacement, Contract No. TD-2018-2
East Goshen Municipal Authority, Chester County, PA

Dear Mr. Weaver:

On behalf of the East Goshen Municipal Authority, you are hereby notified of the following deficiencies in the work performed for the subject contract, based on field testing, visual observation, and sewer video footage, and documented herein are the corrective actions that have been verbally discussed:

MH R-034 to MH R-033

  1. 0' to 26' – Severe sag (30-40%)
  2. 6' – Infiltration runner at solid coupling joint
  3. 235' to 260' – Minor sag (±10%)
  4. 340' to 353' – Minor sag (±10%)
  5. 380' to 400' (last 20' of run into MH R-033) – Water sitting in pipe; however, this may be backup from the bypass pump hose partially blocking the downstream manhole channel during the televising
  6. MR R-033 failed the vacuum test

MH R-033 to MH R-032

  1. 0' to 14' – Minor sag (±10%)
  2. MH R-032 – The abandoned pipe has an infiltration runner into the manhole

Items 1, 2, 6, and 8 must be repaired by January 25, 2019, including the replacement of any temporary pavement removed. Items 1 and 2 shall be corrected via excavated repair. Item 8 shall be repaired by the installation of a screw plug as well as brick and mortar. Vacuum testing and television of the repaired manhole and severely sagging pipe, respectively, shall be performed within three days following construction. A pre-construction meeting shall be conducted at the site at least seven days prior to work between the Township, Pennoni, and Iron Eagle Excavating.

Items 3, 4, and 7, which include minor sags totaling approximately 52 linear feet, may be repaired now or re-evaluated at the end of March 2019. If you choose to re-evaluate, the re-evaluation must occur by sewer televising performed by the same company that performed the original televising with the same equipment and under the exact same bypass pump conditions. If, at the end of March, the sags in these areas have not increased, these pipe sections can be found acceptable. However, if any additional sagging is observed, that section of pipe will need to be repaired.

It is unclear if item 5 is an actual issue. This area needs to be re-evaluated by televising when the January repairs are made and repaired if needed to eliminate sags and standing water.

EGMAU18004 January 3, 2019 Page 2
Randall Weaver Tallmadge Drive Sewer Replacement

Further, the entirety of the contract work shall be re-televised after all repairs are performed. Any minor sag repairs must be completed by the end of April 2019. No work will be considered to be accepted until all repairs are satisfactorily completed and final re-televising is performed and determined acceptable by the owner. Performance and payment bonds shall remain in place until that time.

If you have any questions or need additional information, please call.

Sincerely,
PENNONI ASSOCIATES INC.

Michael J. Ellis
Michael J. Ellis, PE
Authority Engineer

/edj

cc: Rick Smith, Township Manager
Jon Altshul, Assistant Township Manager
Mark Miller, Public Works Director
Patrick McKenna, Gawthrop Greenwood
East Goshen Municipal Authority

U:\Accounts\EGMAU\EGMAU18004 - Tallmadge Dr Sewer Constr Phase\COMMUNICATIONS\SENT\Notice of Deficiencies 1.3.2019.docx

Please sign below with your acknowledgement to these repair conditions.

ACKNOWLEDGEMENT:

Randall Weaver, Iron Eagle Excavating
Randall Weaver

DATE: 1/4/2019

Sue Smith

From: Jon Altshul <jaltshul@eastgoshen.org>
Sent: Friday, January 11, 2019 8:17 AM
To: Sue Smith
Subject: FW: Tallmadge Dr Sewer - Pay Recommendations #1 and #2
Attachments: Payment App #1 Recommendation Ltr 2019.01.09.pdf; Payment App #2 Recommendation Ltr 2019.01.09.pdf

Jon Altshul
Director of Finance & Assistant Township Manager
East Goshen Twp
jaltshul@eastgoshen.org
610-692-7171
Get all the latest news on East Goshen. Sign up for Constant Contact™ today!

[Township of East Goshen Chester County, Pennsylvania Incorporated 1817 seal]

From: Michael Ellis [mailto:MEllis@Pennoni.com]
Sent: Wednesday, January 09, 2019 10:07 PM
To: rsmith@eastgoshen.org; Jon Altshul; Mark Miller (mmiller@eastgoshen.org)
Cc: Eric Jenson; Matthew McAloon
Subject: Tallmadge Dr Sewer - Pay Recommendations #1 and #2

Hi Rick, Jon, and Mark,

Please find attached our recommendation letters for Payment Applications #1 and #2 for consideration at the MA meeting. If approved by the MA, we recommend Application #1 be paid next week, and Application #2 be paid upon completion of the initial rehab work. That work is scheduled to be performed next week so that payment could occur the following week.

Please call if you have any questions or comments.

Thanks,
Mike

Michael Ellis, PE
Municipal Division Manager

Pennoni
121 Continental Drive, Suite 207 | Newark, DE 19713
Direct: +1 (302) 351-5236 | Mobile: +1 (302) 561-4235
www.pennoni.com | MEllis@Pennoni.com

1

Pennoni

Christiana Executive Campus
121 Continental Drive, Suite 207
Newark, DE 19713
T: 302-655-4451
F: 302-654-2895
www.pennoni.com

January 9, 2019

EGMAU18004

Rick Smith, Township Manager
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380

RE: Payment Application No. 1 Recommendation Letter
Tallmadge Drive Sewer Replacement, Contract No. TD-2018-2

Dear Mr. Smith:

The Contractor, Iron Eagle Excavating, Inc., has submitted the first invoice for work completed on this project. The invoice is for $42,431.40, which is approximately equal to 50% of the contract value.

Deficiencies were observed in the work performed when the manhole vacuum testing and pipe televising were performed in December 2018. Following discussions with the Township and the Contractor, a Notice of Deficiencies (enclosed), dated January 3, 2019, was submitted to the Contractor which noted the observed issues and required resolutions. It was discussed that an initial payment of 50% of the contract value would be provided for the work completed, an additional 25% of the contract value would be provided immediately following the correction of major deficiencies by January 25, 2019, and the final 25% of the contract value would be considered following repair of minor deficiencies, or acceptance, if conditions have not changed in retesting in April 2019.

We therefore recommend an initial payment of $42,431.40.

If you have any questions, please contact me at your convenience.

Sincerely,

PENNONI ASSOCIATES INC.

Michael J. Ellis, PE
Authority Engineer

/edj

Enclosures: Invoice #106
Payment Application 1 Tabulation
Notice of Deficiencies (Acknowledged by Contractor)

cc: Jon Altshul, Assistant Township Manager
Mark Miller, Public Works Director
East Goshen Municipal Authority

U:\Accounts\EGMAU\EGMAU18004 - Tallmadge Dr Sewer Constr Phase\CONSTRUCTION\PAY APPS\Payment App #1 Recommendation Ltr 2019.01.09.docx

Invoice

Iron Eagle Excavating
35 ann street
Highspire, PA 17034

Date Invoice #
1/4/2019 106

Bill To

Item Date Description Job site Rate Hours Amount
Excavating 1/4/2019 Sanitary Sewer Bypass Pumping and Flow Control Tallmadge Drive 2,250.00 1 2,250.00
Excavating 1/4/2019 Furnish and install 8" Dia. SDR26 PVC Gravity Sewer Pipe Tallmadge Drive 38,346.00 1 38,346.00
Excavating 1/4/2019 Furnish and Install 4" Dia. SDR26 PVC Sewer Lateral Tallmadge Drive 4,000.00 1 4,000.00
Excavating 1/4/2019 Connection to Existing Sanitary Sewer Manholes Tallmadge Drive 1,500.00 1 1,500.00
Excavating 1/4/2019 Miscellaneous Excavation and Backfill Tallmadge Drive 1,050.00 1 1,050.00
Excavating 1/4/2019 Retainage 10% Tallmadge Drive -4,714.60 1 -4,714.60
Total $42,431.40

Payment Application 1 Tabulation

Contract No. TD-2018-2: Tallmadge Drive Sewer Replacement

Iron Eagle Excavating

NUMBER DESCRIPTION ESTIMATED QUANTITY/UNIT UNIT COST AMOUNT QUANTITY REQUIRED QUANTITY PAID QUANTITY REMAINING AMOUNT PAID AMOUNT REMAINING PERCENT REMAINING COMMENT
BASE BID
1 Sanitary Sewer Bypass Pumping and Flow Control 1 L.S. $4,500.00 $4,500.00 1.00 0.50 0.50 $2,250.00 $2,250.00 50.00% Bypass required to repair manhole and upstream runner
2 Furnish and Install Precast Concrete Manhole 1 EA. $6,500.00 $6,500.00 1.00 0.00 1.00 $0.00 $6,500.00 100.00% Manhole failed vacuum test
3 Furnish and Install 8" Dia. SDR26 PVC Gravity Sewer Pipe 527 L.F. $124.50 $65,611.50 527 308 219 $38,346.00 $27,265.50 41.56% Various unacceptable sags in pipes
4 Furnish and Install 4" Dia. SDR26 PVC Sewer Lateral 40 L.F. $100.00 $4,000.00 40 40 0 $4,000.00 $0.00 0.00% Pay in full
5 Connection to Existing Sanitary Sewer Manholes 1 L.S. $3,000.00 $3,000.00 1.00 0.50 0.50 $1,500.00 $1,500.00 50.00% Downstream connection not sufficient due to leak
6 Demolition of Drop Connection Concrete Encasement 1 C.Y. $400.00 $400.00 0 0 0 $0.00 $0.00 0.00% No concrete encasement encountered
7 Miscellaneous Excavation and Backfill 20 C.Y. $10.00 $200.00 105 105 0 $1,050.00 $0.00 0.00% Pay in full + Additional Quantity
8 Rock Removal 75 C.Y. $10.00 $750.00 0 0 0 $0.00 $0.00 0.00% No rock encountered
TOTAL BASE BID (BASED ON ESTIMATED QUANTITIES) $84,961.50 $47,146.00 $37,515.50 44.16%

$4,714.60 10% Retainage of Amount Completed (Paid)
$42,431.40 Final Amount Paid
$42,530.10 Amount Remaining Including Retainage

Pennoni

Christiana Executive Campus
121 Continental Drive, Suite 207
Newark, DE 19713
T: 302-655-4451
F: 302-654-2895
www.pennoni.com

January 9, 2019

EGMAU18004

Rick Smith, Township Manager
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380

RE: Payment Application No. 2 Recommendation Letter
Tallmadge Drive Sewer Replacement, Contract No. TD-2018-2

Dear Mr. Smith:

The Contractor, Iron Eagle Excavating, Inc., has submitted a second invoice for work on this project. The invoice is for $21,326.40, which is approximately equal to 25% of the contract value. This invoice is being submitted for payment immediately upon completion of the following repairs, which are required to be completed by January 25, 2019: repair of 26-linear foot severe sag immediately downstream of MH R-034, repair of infiltration runner immediately downstream of MH R-034, review of potential 20-linear foot sag immediately preceding replaced MH R-033 and repair if needed, repair of replaced MH R-033 manhole such that it passes a vacuum test, and repair of the abandoned MH R-032 pipe to stop the groundwater leak.

Deficiencies were observed in the work performed when the manhole vacuum testing and pipe televising were performed in December 2018. Following discussions with the Township and the Contractor, a Notice of Deficiencies, dated January 3, 2019, was submitted to the Contractor which noted the observed issues and required resolutions. It was discussed that an initial payment of 50% of the contract value would be provided for the work completed, an additional 25% of the contract value would be provided immediately following the correction of major deficiencies by January 25, 2019, and the final 25% of the contract value would be considered following repair of minor deficiencies, or acceptance, if conditions have not changed in retesting in April 2019.

We therefore recommend approval of payment in the amount of $21,326.40, conditioned that payment not be made until the required January repairs are completed and determined acceptable by the Township.

If you have any questions, please contact me at your convenience.

Sincerely,

PENNONI ASSOCIATES INC.

Michael J. Ellis, PE
Authority Engineer

/edj

EGMAU18004 January 9, 2019 Page 2
East Goshen Township Tallmadge Drive Sewer Replacement

Enclosures: Invoice #107
Payment Application 2 Tabulation

cc: Jon Altshul, Assistant Township Manager
Mark Miller, Public Works Director
East Goshen Municipal Authority

U:\Accounts\EGMAU\EGMAU18004 - Tallmadge Dr Sewer Constr Phase\CONSTRUCTION\PAY APPS\Payment App #2 Recommendation Ltr 2019.01.09.docx

Invoice

Iron Eagle Excavating
35 ann street
Highspire, PA 17034

Date Invoice #
1/4/2019 107

Bill To
East Goshen Township

Item Date Description Job site Rate Hours Amount
Excavating 1/4/2019 Sanitary Sewer Bypass Pumping and Flow Control Tallmadge Drive 4,500.00 4,500.00
Excavating 1/4/2019 Furnish and Install Precast Manhole Tallmadge Drive 6,500.00 6,500.00
Excavating 1/4/2019 Furnish and Install 4" Dia. SDR26 PVC Sewer Lateral Tallmadge Drive 4,000.00 4,000.00
Excavating 1/4/2019 Furnish and Install 8" Dia. SDR26 PVC Gravity Sewer Pipe Tallmadge Drive 51,792.00 51,792.00
Excavating 1/4/2019 Connection to Existing Manholes Tallmadge Drive 3,000.00 3,000.00
Excavating 1/4/2019 Miscellaneous Excavation and Backfill Tallmadge Drive 1,050.00 1,050.00
Excavating 1/4/2019 Retainage 10% Tallmadge Drive -7,084.20 -7,084.20
Excavating 1/4/2019 Previously Paid Tallmadge Drive -42,431.40 -42,431.40
Total $21,326.40

Payment Application 2 Tabulation

Contract No. TD-2018-2: Tallmadge Drive Sewer Replacement

Iron Eagle Excavating

ITEM NUMBER DESCRIPTION ESTIMATED QUANTITY/UNIT UNIT COST AMOUNT QUANTITY REQUIRED QUANTITY PAID QUANTITY REMAINING AMOUNT PAID AMOUNT REMAINING PERCENT REMAINING COMMENT
BASE BID
1 Sanitary Sewer Bypass Pumping and Flow Control 1 L.S. $4,500.00 $4,500.00 1.00 1.00 0.00 $4,500.00 $0.00 0.00% Pay in full
2 Furnish and Install Precast Concrete Manhole 1 EA. $6,500.00 $6,500.00 1.00 1.00 0.00 $6,500.00 $0.00 0.00% Pay in full
3 Furnish and Install 8" Dia. SDR26 PVC Gravity Sewer Pipe 527 L.F. $124.50 $65,611.50 527 416 111 $51,792.00 $13,819.50 21.06% Repair 10% sags (if required)
4 Furnish and Install 4" Dia. SDR26 PVC Sewer Lateral 40 L.F. $100.00 $4,000.00 40 40 0 $4,000.00 $0.00 0.00% Pay in full
5 Connection to Existing Sanitary Sewer Manholes 1 L.S. $3,000.00 $3,000.00 1.00 1.00 0.00 $3,000.00 $0.00 0.00% Pay in full
6 Demolition of Drop Connection Concrete Encasement 1 C.Y. $400.00 $400.00 0 0 0 $0.00 $0.00 0.00% No concrete encasement encountered
7 Miscellaneous Excavation and Backfill 20 C.Y. $10.00 $200.00 105 105 0 $1,050.00 $0.00 0.00% Pay in full + Additional Quantity
8 Rock Removal 75 C.Y. $10.00 $750.00 0 0 0 $0.00 $0.00 0.00% No rock encountered
TOTAL BASE BID (BASED ON ESTIMATED QUANTITIES) $84,961.50 $70,842.00 $13,819.50 16.27%

$7,084.20 10% Retainage of Amount Completed (Paid)
$63,757.80 75% Payout Value
$42,431.40 Previously Paid
$21,326.40 Payment this Application #2
$21,203.70 Amount Remaining Including Retainage