Municipal Authority

The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.

 

The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.

  • Five members, serving five-year terms
  • Meetings are on the 2nd Monday of the month at 7:00 P.M.
  • All township meetings are held at the Township Building and open to the public
Authority Members Term Expiration Date
Kevin Cummings, Chairman 2026
John Stipe, Vice Chairman
2029
Dana Pizzarro, Secretary 2026
Sean Ellsworth, Assistant Secretary/Treasurer 2028
Walter Wujcik, Treasurer 2028
Pennoni Associates, Engineer
Patrick M. McKenna, Esq.
Peter Hicks, BoS Liaison
Kevin Miller, Staff Liaison

 

Municipal Authority Genealogy

Audits

Documents

Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.

EAST GOSHEN MUNICIPAL AUTHORITY

November 8, 2021

7:00 PM

Meeting will be held in the building!

1. CALL TO ORDER/PLEDGE OF ALLEGIANCE/MOMENT OF SILENCE a. Ask if anyone will be taping the meeting

2. CHAIRMAN'S REPORT/OTHER MEMBERS REPORTS

3. SEWER REPORTS

a. Director of Public Works Repmi. b. Pennoni Engineer's Repo1t. c. Big Fish Environmental Repo1t

4. APPROVAL OF MINUTES

a. October 11, 2021

5. APPROVAL OF INVOICES

Pennoni Invoice # 1091962 Pennoni Invoice # 1091966 Pennoni Invoice #1091967 Beyond Components Invoice #351097-4 Connection Invoice #71730296

6. LIAISON REPORTS

7. FINANCIAL REPORTS - (David Ware) Finance Director

a. October Financial Repmt

8. OLD BUSINESS

a. Mike Ellis -Westtown Way Pump Station

b. UV update

F:\Data\Shared Data\Agendas\Municipal Authority\2021\11-08-2021 - .doc

$ 10,456.00 $ 1,227.17 $ 1,656.25 $ 845.34 Paid $ 131.50 Paid

9. 2021 Goals:

Goal Status January, February, March, April and May, June, July August, September and October were all in compliance Ridley Creek Plant Compliance and met all requirements Continue to Monitor Upgrades at WGSTP and Westtown Way Pump Station July 7th meeting On Going

Continue to Implement Infiltration and Inflow On Going for the Sewer System Caustic Soda Project 75% complete - Public Works is building the shelving Mike Ellis is currently working on the Project Replace sewer line Hershey Mill Estates trunk Engineer will bring you up to date under old business. line replacement Mark has met with residents to keep them up to date Hunt Country Pump Station Mag Meter On-Hold Replacement Hunt Country Pump Station Muffin Monster On Hold Replacement

On Hold Hunt Country Pump Station Bypass Pump

Hibberd Lane is on line. Ridley Creek Plant is the next meter, In the process of replacing the meter at the Three new meters for Ridley Creek Collection plant.

10. NEW BUSINESS

a. Sewage Treatment Agreement for 75, 79 and 81 Line Road. Information will be in the packet

b. Sewer Extension Study

11. CAPACITY REQUESTS

12. ANY OTHER MATTER

13. CORRESPONDENCE AND REPORTS OF INTEREST

14. PUBLIC COMMENT

15. ADJOURNMENT

F:\Data\Shared Data\Agendas\Municipal Authority\2021\l 1808-2021 - .doc

AREA CODE 61 0

692-7171

November 5, 2021

EAST GOSHEN MUNICIPAL AUTHORITY

EAST GOSHEN TOWNSHIP

15B0 PAOL.l Pll<E, WEST CHESTER, PA 193B0-6199

To: Municipal Authority

From: Mark Miller

Re: October 2021 Monthly Report

Monthly Flows:

Meters:

C.C. Collection:

R.C. Collection:

The average daily flow to West Goshen was 714,030 per day.

The meters were read on a daily basis. We have had technical issues with the Hibberd Lane meter, John Laidly has been working with the factory.

The pumping station were visited on a daily basis. As part of our routine maintenance we pulled pumps at each station. There were sent to

Deckmen Electric for the seals and bearings to be looked over along with oil changes as well. Lenni has been on site performing maintenance checks of the pump station facilities. We had no problems to report for the month.

The same work was done to the two stations that was done at the Chester Creek stations. We made repairs to laterals in the Rossmore

Development. Some of the cleanout were broken off and both were in the storm water swales taking on water.

Ridley Creek Plant: Public Works performed routine maintenance was performed with no problems to report. Lenni Electric started the preventive maintenance of the electrical components, so far they have found some minor problems. We had Pipe Data View come out and clean the sewer main at the

Hershey Mill tennis courts up to Tanglewood Drive. We have done this every quarter to prevent the line from backing up due to grease building up.

Alarms: We responded to 23 alarms for October.

PA One Calls: We responded to over 61 PA One Calls for the month October.

Monthly Rainfall: 3.90 inches of rain for the month of October.

Lateral repairs or Caps: We repaired 4 laterals and inspected them.

EAST GOSHEN MUNICIPAL AUTHORITY

ENGINEER'S REPORT

November 5, 2021

Ridley Creek Sewage Treatment Plant (RCSTP)

Christiana Executive Campus 121 Continental Drive, Suite 207 Newark, DE 19713

T: 302-655-4451

F: 302-654-2895

www.pennoni.com

• Caustic Soda Conversion -We are reviewing vendor quotes and will recommend a tank and chemical feed pump vendor at the December MA meeting. We also initiated design of the shelving for the pumps, which will be constructed by Public Works, but final layout will need to be determined in concert with the feed pump vendor based on suction and discharge piping and valving layouts. The plans have been updated to address the operator's comments. We also received comments from a chemical supplier, and we are evaluating if any other improvements or revisions are needed to meet their requirements. We will then provide the plans to the controls contractor and electrician for pricing.

• UV Disinfection System -We previously met with the Glasco UV system rep and received a quote and product information for their recommended vertical replacement system. We met with the Trojan system vendor, Kappe, on October 13 at the plant, and we are currently reviewing their recommendations and pricing for their horizontal system. Both Glasco and Trojan systems will require raising the walls of the UV channel and increasing the hydraulic grade of flow so we will perform a field hydraulics test with the assistance of the operator. We also received product information on Enaqua's system as a 3rd consideration, but it does not appear upon initial review that the system will

be compatible, even with the aforementioned channel height modifications.

• NPDES Permit Renewal - We prepared and submitted the application to DEP on November 1 in accordance with the deadline. The lab has not yet provided all of the sampling results. Upon receipt, the comprehensive influent and effluent sampling data will be provided to DEP to supplement the application. DEP will begin their review upon receipt of that data.

Ridley Creek Collection System Permanent Meters

• No activity since our last report.

Westtown Way Pump Station

• No activity since our last report.

Sanitary Sewer Pipe Rehab

• Supplee Valley-No activity since our last report.

• Hershey's Mill Estates -

o We expect to submit the PADEP General Permit GP-11 application for waterway impacts in early November. This permitting typically takes 90-120 days for review.

o We are coordinating scheduling with Mark Miller for the subsurface groundwater and rock test pits. Our geotechnical engineers will be on-site to observe and to be perform limited hand augers as well.

1&1 Program

• No activity since our last report.

EGMAU21001 East Goshen Municipal Authority

New Connections

November 5, 2021 Page 2 Engineer's Report

• We completed and submitted the study report of costs and feasibility for public sewer extensions to ten unsewered neighborhoods.

Industrial Pretreatment Ordinance

• No activity since our last report. As discussed at the May MA meeting, a headworks study with sampling at the RCSTP can be conducted to set contaminant limits. Consideration should be given to

budgeting for the headworks study and sampling in 2022.

END OF REPORT

P:\Projects\EGMA\Memos to Board\2021\Engineers Report 2021-11-05.docx

RCSTP Monthly Operations Report:

November 2021

Environmental Services Inc.

Executive Summary1

The Ridley Creek sewage treatment plant outfall 001 achieved compliance with the permit discharge limitations for the month of September 2021. All supplemental reports were submitted with the DMR. Discharge to the Applebrook irrigation lagoon remained in service. Chemical usage utilized for pH and total alkalinity remained consistent with previous months. Aluminium sulfate solution volumes slightly decreased during October (3 gal/day) as compared to September to achieve phosphorus removal. No significant mechanical or operational issues were observed during operation of sludge dewatering equipment or SBR treatment process. There were no odor complaints during the month.

Treatment Process Operation

Table 1 illustrates the final effluent composite sample data reported for outfall 001 for the September 2021 DMR.

Table 1 September 2021- Final Effluent-Outfall 001

Flow CBODs TSS NH4•N Phosphorus,Total Fecal Coliform

NPDES Permit MGD lbs/ lbs/ lbs/ lbs/ Geo Discharge Limitations Average mg/L month mg/L month mg/L month mg/L month Geo Mean Mean

0.75 20 125 10 131 2.5 44 0,5 3 200 1,000 40 15 Sample Date September 7, 2021 0.242 2.5 5.0 3 6.1 0.100 0.20 0.10 0.20 1 0.0000 September 14, 2021 0.253 2.7 5.7 2

4.2

0.100 0.21 0.10 0.21 September 21, 2021 0.264 2.7 5.9 4 8.8 0.100 0.22 0.10 0.22 1 0.0000 September 28, 2021 0.290 2.0 4.8 6 14.5 0.114 0.28 0.10 0.24 1 0.0000

Average 0.262 2.5 5.4 4 8.4 0.104 0.23 0.10 0.22 1 0.0 Minimum 0.242 2.0 4.8 2 4.2 0.100 0.20 0.10 0.20 1 0.0 Maximum 0.290 2.7 5.9 6 14.5 0.114 0.28 0.10 0.24 1 0,0

Compliance with the NPDES discharge permit was achieved during September. The monthly average total phosphorus was reported as 0.10 mg/L as compared to the permit limitation of 0.5 mg/L. The TSS samples were consistently in single digits and well below the weekly maximum of 15 mg/L. The monthly average TSS was reported as 4 mg/L as compared to the discharge limitation of 10 mg/L. The TSS weekly averages are presented below in Table 2.

Table 2 September 2021 Final Effluent Weeklv TSS Averaaes

Week 1 3 mail Week2 2 mail Week3 4 mqil Week4 6 mQil

The final effluent test results demonstrate that the biological treatment process performed well

during September and October. Sequencing batch reactors (SBRs) numbered 2, 3 and 4 were in service. Process monitoring of each SBR included ammonia as N, nitrite as N, Nitrate as N, COD, SSV, MlSS and total phosphorus. Daily analysis of the final effluent flow equalization grab sample for total phosphorus is ongoing. Sample collection and analysis of the influent wastewater

collected at the influent pump station wet well is ongoing.

Discharge to the Applebrook irrigation lagoon, outfall 002 continued through October.

Table 3 presents the available pollutant data for the Applebrook discharge reported as outfall 002 on the September 2021 DMR.

Table 3 September 2021-Applebrook - Out Fall 002

Flow CBODs TSS NH4-N Phosphorus,Total Fecal Coliform

NPDES Permit MGD lbs/ lbs/ lbs/ lbs/ Geo

Discharge limitations Average mg/L month mg/L month mg/L month mg/L month Geo Mean Mean

0,135 25 30 2.5 44 0,5 3 200 1,000

40 45

September 7, 2021 0.0560 2.5 1.17 3 1.40 0.100 0.05 0.10 0.05 1 0.0000

September 14, 2021 0.0551

2.7

1.24 2 0.92 0.100 0.05 0.10 0.05

September 21, 2021 0.0525 2.7 1.18 4 1.75 0.100 0.04 0.10 0.04 1 0.0000

Seotember 28. 2021 0.0535 2.0 0.89 6 2.68 0.114 0.05 0.10 0.04 1 0.0000

Average 0.054 2.5 1.1 4 1.7 0.104 0.05 0.10 0.05 1 0.0000

Minimum 0.054 2.0 0.9 2 0.9 0.100 0.04 0.10 0.04 1 0.0000

Maximum 0.054 2.7 1.2 6 2,7 0.114 0.05 0.10 0.05 1 0.0000

The influent wastewater pollutant concentrations and loading entering the wastewater treatment facility generally remained within the design concentration and organic loading values. The monthly average weekly concentrations were generally observed to be less than the design parameters for the treatment process.

Table 4 presents the available pollutant data for the influent wastewater collected at the doghouse manhole during September 2021.

Page 2 of6

Table 4 September 2021- Influent Wastewater

Phosphorus,Total,

Flow BODs TSS NH4-N TKN, mg/L mg/L

Design Basis mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day

MGD Average 335 2,098 320 2,001 32 200 48 301 9.1 57

Sample Date

September 7, 2021 0.406 188 636 320 1,083 32,5 110 38.3 130 4.2 14.2

September 14, 2021 0.419 205 716 297 1,037 33.2 116 46,6 163 6,0 21.0

September 21, 2021 0.406 245 829 283 958 36.5 124 45.4 154 6.1 20.6

September 28, 2021 0.426 280.0 995 330 1,172 35.6 126 47.5 169 4.9 17.4

Average 0.4141 230 794 308 1,063 34 119 44.5 154 5.3 18.3

Minimum 0.4058 188 636 283 958 33 110 38.3 130 4.2 14,2

Maximum 0.4259 280 995 330 1,172 37 126 47.5 169 6.1 21.0

The foam on the SBR surface reduced to approximately 5% to 10% coverage of the surface area. The foam thickness is approximately 3 to 4 inches with a light to medium brown color. These conditions may contribute to a decrease in clarity within the final effluent post flow equalization

basins; however, the clarity is improved after passing through the disc filters. The operation strategy is to lower the MLSS to maintain a F:M ratio of 0.06 while ensuring the ammonia effluent discharge concentration remains within the seasonal limit of 2.5 mg/L

Table 5 illustrates the available data for the final effluent composite sample data reported for

outfall 001 for use with the October 2021 DMR.

Table 5 October 2021- Final Effluent• Outfall 001

Flow CBOD5 TSS NH4-N Phosphorus,Total Fecal Coliform

NPDES Permit MGD lbs/ lbs/ lbs/ lbs/ Geo Discharge Limitations Average mg/L month mg/L month mg/l month mg/l month Geo Mean Mean

0.75 20 125 10 131 7.0 44 0.5 3.0 200 1,000

40 15 Sample Date October 5, 2021 0.261 2.8 6.1 3 6.5 0.100 0.22 0.10 0.22 1 0.0000

October 12, 2021 0.277 2.0 4.6 2 4,6 0.100 0.23 0.15 0.35 1 0.0000

October 19, 2021 0.228 -cc .· ... ,.· , ' --- , ;

_

_ -:, \; ?:_-:'.ii': _ :--- --- :: -,_-,, ____ , ... . > . ·•· .. ,- -,-:

-- -- ' .• . . October 26, 2021 0.268 . · .... :,-- ::>\-, >> . ./ '_)'--:>- . ,, •·\ ; ,;;.t\>" .'\ ,•,;;; ,?, · .. ·

Average 0,259 2.4 5,4 3 5,6 0.100 0.22 0.13 0.28 1 0.0

Minimum 0.228 2.0 4.6 2 4.6 0.100 0,22 0.10 0,22 1 0,0

Maximum 0.277 2.8 6.1 3 6.5 0.100 0.23 0.15 0.35 1 0,0

Page 3 of6

Table 6 presents the available pollutant data for the Applebrook discharge reported as outfall 002 on the October 2021 DMR.

Flow

NPDES Permit MGD Discharge limitations Average

0.135

October 5, 2021 0.0484

October 12, 2021 0.0535

October 19, 2021 0.0439

October 26 2021 0.0455

Average 0.048 Minimum 0.046 Maximum 0.046

Table 6 October 2021- Applebrook • Out Fall 002

CBODs TSS

lbs/ lbs/ mg/l month mg/l month

25 30

40 45 2.8 1.13 3 1.21 2.0 0.89 2 0.89

··• c-;- ;: •.. · ..

,,,

'

2.4 1.0 3 1.1 2.0 0.9 2 0.9 2.8 1.1 3 1.2

NH,•N

mg/l

7.0

0.100 0.100 , .

,' •·

0.100 0.100 0.100

lbs/ month

44

0,04 0.04 I

1-:·:; . . .

0.04 0.04 0.04

Phosphorus,Total

mg/l

0,5

0.50 0.00

,.,, ' ./.:: . ..

0.25 0.00 0.50

lbs/ month

3

0.20 0.00

',

'

'

'

'i.::'__-··•.·:.·'.'.··

0.10 0,00 0.20

Fecal Coliform

Geo

Geo Mean Mean

200 1,000

1 0.0000 1 0.0000 "/";'.'_c_·:t>; . -:.·':- >:.

I< .:·t . >: .:· .. . ·.·•.

1 0.0000 1 0.0000 1 0.0000

Table 7 represents the influent wastewater collected at the doghouse manhole during October 2021. The influent wastewater pollutant loadings remain within the design criteria for the treatment process and equipment.

Design Basis

Sample Date October 5, 2021 October 12, 2021 October 19, 2021 October 26, 2021

Average Minimum Maximum

PADEP

No activity

Flow

MGD Average

0.368 0.410 0.357 0.398 0.3832 0.3565 0.4100

Table 7

October 2021- Influent Wastewater

BODs TSS

mg/l lbs/day mg/l lbs/day

335 2,098 320 2,001

224 687 355 1,090 327 1,118 377 1,289

' ',,

' .. •. < ' ' ·•·· > ·::-<:••·.

',,,, ··:-- ;. ,,-. <-:'· _: ::-":.·.·:

276 903 366 1,189 224 687 355 1,090 327 1,118

377

1,289

Page 4 of 6

NH4·N

mg/l

,,'

32

33.4 28.8 ••••••

' .,.·

31 29 33

lbs/day

200

103 98 ,,,. '

. ···--<··

100 98 103

TKN, mg/l

mg/l lbs/day

48 301

52.4 161 44,0 150

.•.. ' . ' ,,,, .,.··

,,·,,, ,' :\·. ·":;./,- :- :_·::_:-.:.'. ··:;·\···

48.2 156 44,0 150 52.4 161

Phosphorus,Total,

mg/l

mg/l lbs/day

9,1 57

6.2 19.0 7.8 26.7 • < > •; ',,•·_,,., '>·,··.·.· . ::< .. '.·

7.0 22.8 6.2 19.0 7.8 26.7

Pennoni Associates

Provided Daily Effluent Monitoring supplemental reports for the NPDES permit renewal application as requested.

Significant Rainfall

During October, there were eight (8) days when rainfall occurred. There were three (3) events of rainfall exceeding 0.50 inches.

These events occurred on:

October 5th

October 26th

October 30th

0.58 inches

1.00 inch

1.25 inches

A total of 3.95 inches of rainfall were measured during the month.

Plant operations were adjusted to manage the precipitation to prevent exceedances of the permitted discharge limitations for Outfall 001. Adjustments included reducing aeration minutes per cycle, extending decant minutes per cycle and reducing settling times.

Minor Preventative Maintenance

Flushed chemical feed lines to the SBRs.

Cleaned final effluent weir trough daily

Skimmed surface of disc filters daily

Drained and cleaned disc filters bi-weekly

Cleaned buildings and laboratory

Chemical Usage:

October 2021

Chemical Daily Average

Soda Ash, pounds 300

Aluminium Sulfate solution, gal 66.7

Page 5 of6

Total Monthly

9,600

2,066

Flow data:

October 2021

Flow Meter Location Total Volume for Average Daily Daily Maximum Month, MG Flow, gpd Flow, gpd

Influent Wastewater to 12.893 415,911 489,210 Screening Building*

Influent Wastewater to 13.031 SBRs* 420.364 485.504

Internal Recycle** 0.402 12,983 103,470

Treated Effluent to Disc 13.103 422,685 488,704 Filters

Final Effluent Discharge

8.281 267,129 329,000

Applebrook Golf Course 1.532 49,417 55,936

During October, the average monthly influent wastewater flow measured at the "field" flow meter was 415,911 gallons//day as compared to the influent flow into the SBRs as 420,364 gallon/day. The difference between the daily averages is 4,454 gpd, with the "field" flow meter measurements recorded as less than the influent to the SBR. These values would be considered typical as the flow volume into the SBRs includes internal recycle flows from the centrifuge and disk filters.

Maintenance and Repair Activities

October 13th

Tim Daly, Mike Ellis, and Erika Addison were onsite from Pennoni, as well as Evan Walters from Kappe, to discuss using a Trojan brand UV system. Evan was promoting the Trojan 3000 plus system. This would most likely require raising the wall height on the channel, and Evan had

talked about bringing in a portable UV system to set up while the work was being completed so that we could maintain our level of disinfection.

October 20th

Technicians from Lenni Electric were on site performing the annual inspection of all of the

control panels. They completed the inspections on the 21st.

October 26th

1.00" rain

Steve Walker from the Township changed the filter and the oil in the air compressor

Matthew arrived at the facility around 8:30PM to monitor the plant in consideration of the

weather forecast of anywhere from 1.5" to 3 or 4" of rain depending on the news station. Fortunately, as the night went on, the forecasted amount of rain rapidly decreased, with only receiving one (1) inch of rain between 8pm and 8am. The plant performed well with its normal rain settings and maintained a fairly clear effluent.

Page 6 of6

3800-FM-BCW0462 12/2016 pennsylvania if'A DEPARTMENT OF ENVIRONMENTAL ,as PROTECTION

NAME: EAST GOSHEN MUNI AUTH CHESTER CNTY

ADDRESS: 1580 PAOLI PIKE, WEST CHESTER PA, 19380107

FACILITY: RIDLEY CREEK STP

LOCATION: 1751 TOWNE DR, WEST CHESTER PA, 19380

STAGE: '--Ficcn-=•lccE:::ffl=u•:::nc.:t ______________ _

PARAMETERS REPORTED VALUES . ···-····------ - -- ·-

PARAMETER

Dissolved Oxygen (00300) S.i,mple Measurement

PQrm!t Roqolrcment

pH(00400) Sample Mea$uremc,nt

Pormtt Roqulromcmt

Total Suspended Solids (00530) S.wnplo Monsurement

Permit Requirement

Ammori&-Nltrogcn (00610) Sample MoHurcmcnt (May-Oct) Permlt Roqulrement

T ot3I Phosphon.J$ (00665) Sample Measurement

Penni! Roqulrement

Flow (50050) Sample Me asurement

Pennlt Roqulrcmont

Fecal Collfonn (74055) Somplo Measurement

Permit Requirement

Faclllty Par.11metor

Commetnls

Carbonaceous Biochemical Oxygen Demand (CBODS) (80082) Sample Measurement (May-Ool) Pcnn!l Roqulrcmcol

FKlll1'f Sampling Point Comments

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION

BUREAU OF CLEAN WATER

DISCHARGE MONITORING REPORT (DMR)

PA0050504 001

PERMIT NUMBER OUTFALL NUMBER

MONITORING PERIOD

YEAR MO DAY YEAR MO DAY

FROM I 2021 09 01 TO 2021 09 30

Reporting Frequency:

DMR Effective From:

DMR Effective To:

Permit Expires:

Permit Application Due:

No Discharge:

QUANTITY OR LOADING QUANTITY OR CONCENTRATION

VALUE VALUE UNITS VALUE VALUE VALUE UNITS ... ... ... 6.29 ... ... mg/L ... ... 5.0 ... ...

M ... ... ... 7.06 ... 7.81 s.u. ... ... 6.0 ... 9.0 M• Ma, • 15 lbs/day ... 3.a 6.0 mg/I.

62 94 ... 10.0 15.0 Avg Mo WldyA"" Avg Mo Wkly Avg

<.2 ... lbs/ day ... < .1 ... mg/L

16 ... ...

2.5

...

Avg Mo A""Mo

< .2 ... lbs/day ... <.1 ... mg/L

3.0 ... ... .5 ...

A,gMo Avg Mo

.3 .958 MGD ... ... ... ..

Monitor& Report Monitor& Report ... ... ...

A,gMo Oaity Max ... ... ... ... <1 1 CFU/100 ml ... ... ... 200 ,ooo Geo Mean IMAX

Monthly

09/01/2021

09/30/2021

04/30/2022

11/01/2021 -

D

SAMPLING FREQUENCY

Hday

Hday

1/day

1/ day

1/woek

1/woek

1/week

1/woek

1/week

1/week

Continuous

ConlinUOU$

1M'eok

1/woek

A samplo taken 9/14'21 was not Included as the res.ult was >2,419. There wa:s a new sample OOllector who contaminated the sample by sampling lnc:omlctly.

<5 10 I Jbslday I ... <2 4 mg/L 1/week

62 .. ... 10 15 1/woek A""Mo WldyA,g Avg Mo Wl(;lyAvg

Privacy Policy I Security Policy Copyright ©2016 Commonwealth of Pennsylvania. All Rights Reserved

SAMPLING TYPE

Grab

Grab

Grab

G,ab

24-Hr ComposJte

24-Hr Composite

24-Hr Composite

24-Hr Composite

24-HrComposil&

24--HrCompo$lltl

Measured

Measured

Grab

G,ab

24-HrComposlte

24-Hr Compos ite

3800-FM-BCW0462 12/2016 pennsylvania if"A DEPARTMENT OF ENVJRONMENTAL '&!, PROTcCTION

NAME: EAST GOSHEN MUNI AUTH CHESTER CNTY

ADDRESS: 1580 PAOLI PIKE, WEST CHESTER PA, 19380-Q107

FACILITY: RIDLEY CREEK STP

LOCATION: 1751 TOWNE DR, WEST CHESTER PA, 19380

STAGE: '--F-'-in'-'a'-I E=ffl=u.::•ncct:.._ ______________ _

PARAMETERS REPORTED VALUES • ,u-••••-•-••- ••-• -•••-- •••----

PARAMETER

Ois.solllecl OxygAn (00300) Sampla Measurement

Permit RoQulromont

pH(00400) Sample Measurement

Pormlt Roqull'Cmont

Total Suspondod Solids (00530) Samplo Moasuromont

Permil Requirement

Ammonia-Nitrogen (00610} Sample Measurement {May-Oct) Permn Requirement

Tolal PhosphoM: (00665) Sample Mea,uremM\l

Permll Requirement

Flow (50050) Sample Measuremenl

Ponnlt Roqulrc,mont

Feeol Coliform (74055) Sample Me.:isurement

Pennit Roqulreme-nl

FaclUty Paramoter

Comments

Carbonaceous Sloehemlcal Oxygen Demond (CSODS) (80082) Sample Measl.N'ement (May-Oct) Pcnnit Requirement

F.clllty Įmpllng Point Commonts

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION

BUREAU OF CLEAN WATER

DISCHARGE MONITORING REPORT (DMR)

PA0050504 002

PERMIT NUMBER OUTFALL NUMBER

MONITORING PERIOD

YEAR MO DAY YEAR MO DAY

FROM I 2021 09 01 TO 2021 09 30

Reporting Frequency:

DMR Effective From:

DMR Effective To:

Permit Expires:

Permit Application Due:

No Discharge:

QUANTITY OR LOADING QUANTITY OR CONCENTRATION

VALUE VALUE UNITS VALUE VALUE VALUE UNITS ... . .. ... 8.29 ... ... moJL ... ...

5.0 ... ...

M• ... ... ... 7.08 ... 7.81 s.u. - ... 6.0 - 9.0 M• M""

8 15 lbs/d.iy ... , . 6.0 mg/L

62 94 ... 10.0 15.0 A"9Mo WklyA,g Avg Mo Wl<lyAvg

< .2 ... lb'1day ... < ,1 ... mg/L

16 ... ... 2.5 . ..

A"9Mo Avg Mo

<.2 ... lbs/day ... < .1 ... mg/L

3.0 ... ... .5 ...

Avg Mo Avg Mo

.05229 . 06248 MGO ... ... ... ...

Monitor& Reporl Monltor& Report ... ... ...

Avg Mo O:iityMax ... ... ... ... < 1.0 1.0 CFU/100 ml - ... ... 200 1000 Geo Mean IMAX

Monthly

09/01/2021

09/30/2021

04/30/2022

11/01/2021 -

D

SAMPLING FREQUENCY

1/day

1/day

1/day

1/day ,_,

1/week

1/Wffk

1/week

1/week

1/Week

Continuous

Contini.IOU$

1/Week

1/woek

A sampfo taken 9/14/21 was not lndudod as tho rcsutt was >2,419. There was a new sample oollector who contaminated tho sampk, by sampling lncormclly.

<5 10 lbsldey ... < 2 4 mglL I 1Jweek

62 94 ... 10 15 1/woek A"9Mo WktyAvg Avg Mo WklyA,g

Privacy Policy I Security Policy Copyright ©2016 Commonwealth of Pennsylvania. All Rights Reserved

SAMPLING TYPE

Grab

Gmb

Grab

Grab

24-HrCompos)te

24-HrComposite

24-HrComposlto

24-Hr Composite

24-Hr Composite

24-Hr Composite

Measured

Measured

Grab

G,.b

I 24-Hr Comp0$ile

24-Hr Cornposiĭ

3800-FM-BCW046212/2016 pennsylvania iiF'A DEPARTMENT OF ENVIRONMENTAL '.m!J' PROTECTION

NAME: EAST GOSHEN MUNI AUTH CHESTER CNTY

ADDRESS: 1580 PAOLI PIKE, WEST CHESTER PA, 19380-6107

FACILITY: RIDLEY CREEK STP

LOCATION: 1751 TOWNE DR, WEST CHESTER PA, 19380

STAGE: Raw Sewage Influent

PARAMETERS REPORTED VALUES

PARAMETER

Biod'lemicat Oxygen Demand (8005) (00310) Sample Measurement

Permit ROQuiromont

Total Suspe™1ed Sopds (00530) Sample Measurement

Permit Requlremont

F.:aclllty SampUng Point Commonb

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION

BUREAU OF CLEAN WATER

DISCHARGE MONITORING REPORT (DMR)

PA0050504 001

PERMIT NUMBER OUTFALL NUMBER

MONITORING PERIOD

YEAR MO OAY YEAR MO DAY

FROM I 2021 09 01 TO 2021 09 30

Reporting Frequency:

DMR Effective From:

DMR Effective To:

Permit Expires:

Permit Application Due:

No Discharge:

QUANTITY OR LOADING QUANTITY OR CONCENTRATION

VALUE VALUE UNITS VALUE VALUE VALUE UNITS

507 ... lbs/day ... 230 ... mg/I.

Monltor&Roport ... ·- Monitor& Report ...

Avg Mo Avg Mo

673 ... ]b:sldBy ... 308 ... mg/I.

Monltor&Roport ... - Monltor&Ropotl ...

Avg Mo A,gMo

Privacy Policy I Security Policy Copyright ©2016 Commonwealth of Pennsylvania. All Rights Reserved

Monthly

09/01/2021

09/30/2021

04/30/2022

11/01/2021 -□

SAMPLING FREQUENCY SAMPLING TYPE

1/week 24-Hr Composite

1/Weok 24-Hr Composite ,_, 24-Hr Composite ,_, 24-Hr Compostto

3800-FM-BCW0462 12/2016 pennsylvania if"A DEPARTMENT OF ENVIRONMENTAL ,a, PROTECTION

ATTACHMENT DETAILS

FlloNamo

2021 SEP DMR 001.ldsx

SEP 2021 lnfuent Process Control.xis

2021 SEP SSR.Jtls

2021 SEP OMR 002.xts.x

PERMIT VIOLATIONS

Nonąomplianeo ID Evont Start 0:110 I Evont End Dato

UNAUTHORIZED DISCHARGES

P.:iramctor UmltTypo

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION

BUREAU OF CLEAN WATER

DISCHARGE MONITORING REPORT (DMR)

Att:ichmont Typo UpmdodTlmo

Dally Efnuent Monitoring Form 2021-10-27T17:22:06-04:00

lnftt>ent ;:md Process Control Fem, 2021-10-27T17:23:39-04:00

Sewage Sludgo I Biosolids Production and Disposal Fom, 2021-10-27T17:23:05-04:00

Dally Effluent MonllOling Form 2021-10-27T17:22:37-04:00

Roportod Y.aluo Pormlt Limit Unit Sampling Point C:1uao Of Non-Compliance

Atulchmont Commonts

CorroctivoActlon Comments

Non-Complbnco ID Event Sbrt D:ito I Event End Dato I Dato and Tlmo Dlscovcrod Substance Oiseharge-d

Event Loc.,Uon Volumo(g:11) Duration (hrs) I Rocolvlng Waters I Impact On Waters C:auso 01 Dlsch:lrgo Dato and Time DEP Notlfted

Or.Illy

Comments

OTHER PERMIT VIOLATIONS

Non-Compll:,nco ID Non-Compll:inco Typo S:,mpllng Point Paramotor Roportod Value PonnltUmlt Comments

COMMENT DETAILS

Comments ()ponitor N:amo Oporator Cortlflc:,tlon Number Oporotor Contact Number

Scott A. TO'M<lr T0390 (345)-325-3282

SUBMISSION INFORMATION

SUBMITTED BY "'Pursuant to the Pennsylvania Electronic Transactions Act - Act 69, effective January 15, 2002, you are about to engage in an TELEPHONE DATE GREENPORT USER electronic transaction with the Commonwealth of Pennsylvania. You are submitting official information. You certify under Scott Towler penalty of law that this document and all attachments were prepared under your direction or supervision in accordance with a

system designed to assure that qualified personnel gather and evaluate the information submitted. Based on your inquiry of (345) 325-3282 2021 10 27

towlersc

the person or persons who manage the system or those persons directly responsible for gathering the information, the information submitted is, to the best of your knowledge and belief, true. accurate and complete. You are aware that any false SUBMITTED BY statement may be subject to substantial civil and criminal penalties, including 18 P.S. section 4904 (relating to unswom FULL NAME AREA CODE NUMBER YEAR MO DAY

falsification to authorities).

Privacy Policy I Security Policy Copyright ©2016 Commonwealth of Pennsylvania. All Rights Reserved

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39

40 41

42 43 44 45

DRAFT EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY

MEETING MINUTES

October 11, 2021

The East Goshen Township Municipal Authority held their regular meeting on Monday, October 11, 2021 at 7:00 pm. at the Township Building. Members in attendance were: Dana Pizarro, Chairman; Jack Yahraes Vice Chairman; Phil Mayer, and Walter Wujcik.

Also in attendance were: Mark Miller (Director of Public Works), David Ware (Financial Director), Mike Ellis (Pennoni), Robert Jefferson (Gawthrop), Michael Lynch (Township Supervisor), and Scott Towler (Big Fish).

COMMON ACRONYMS: BFES - Big Fish Environmental Services BOS - Board of Supervisors CB - Conservancy Board DEP - Department of Environmental Protection EPA - Environmental protection Agency HC - Historical Commission I&I - Inflow & Infiltration LCSTP - Lockwood Chase Sewer Treatment Plant

Call to Order & Pledge of Allegiance

MA- Municipal Authority NP DES - National Pollutant Discharge Elimination System

PC - Planning Commission PM - Prevention Maintenance PR-Park & Recreation Board RCSTP -Ridley Creek Sewer Treatment Plant SBR - Sequencing Batch Reactor SSO - Sanitmy System Ove,jlow

WAS - Waste Activated Sludge

Dana called the meeting to order at 7:00 pm and led those present in the Pledge of Allegiance.

He asked for a moment of silence for our military around the world, police, and First Responders. Dana asked if anyone would be recording the meeting. There was no response.

Chairman's Report Phil reported that he attended the West Goshen meeting. They have 360 homes in the township that are not connected to public sewer. They are moving their banking from Fulton to TD because of fees. They are considering sharing the banking fees with other users of their system. They started up and are testing the Comag. Their pH is high for now. They had several overflows during the storms. The biggest was at the Westtown Way Pump Station.

Sewer Reports 1. Director of Public Works, Mark Miller's report for September 2021 Monthly Flows: The average daily flow to West Goshen was 700,530 gallons per day.

Meters: The meters were read on a daily basis. We have a signal issue with the Hibberd Lane meter. John Laidley has been working with the meter representative to correct the problem

C.C. Collection - We have been checking the pump stations on a daily basis with no real

problems to report. We televised and cleaned Christine Lane as part of our routine maintenance. We were notified of a lateral blockage at 309 Reservoir Road. We made several attempts to clear it with a plunger but ended up using the Jetter and various cameras to get it

MA 10-11-21 draft I

I cleared. We found a lot of decorative stone in the lateral. We also mowed the sewer right of 2 ways and inspected manholes while clearing the right of ways.

3 R.C. Collection - The pump station was visited on a daily basis. The mag meter was taken out 4 by the flood at the Hershey Mill Station. John Laidly has ordered a new flow meter and will 5 install it once it is delivered. We mowed the sewer right of ways and inspected the manholes 6 along the creek.

7 Ridley Creek Plant - Routine maintenance was performed with no problems this month.

8 Alarms: We responded to 18 alarms in September. 9 PA One Calls: We responded to over 56 PA One Calls for the month of September. IO Rainfall: I 0.62 inches of rain for the month of September. 11 Lateral Repairs or Caps: We repaired 2 laterals and inspected them. 12 13 2. Pennoni Engineer's Report for September dated October 7, 2021

14 Ridley Creek Sewage Treatment Plant (RCSTP)

15 • Caustic Soda Conversion - We attended a meeting at the RCSTP on September 14 with the 16 operator and controls contractor to review the plans. We revised the plans thereafter to address 17 comments, specifically adding a 5th chemical feed pump that will feed caustic soda into the WAS 18 piping en route to the sludge holding tanks, updating controls logic, and specifying diaphragm instead

19

of peristaltic pumps. We have obtained three quotes for tanks and are continuing to coordinate with 20 vendors to obtain quotes for the chemical feed pumps. The equipment costs are generally coming in 21 on budget so far. Updated plans are expected to be submitted to the Township for review the week of 22 October 11 and for use by the controls contractor and electrician to provide pricing for their aspects 23 of construction. We are planning to present the equipment quotes to the MA at the November 24 meeting for purchase authorization.

25 • UV Disinfection System - this is discussed later on the agenda.

26 • We coordinated with the operator to perform sampling for the NPDES Permit Renewal 27 application. The application is prepared with the exception of sampling results. It will be submitted 28 before the November 1 deadline.

29 Ridley Creek Collection System Permanent Meters

30 • No activity since our last report.

31 Westtown Way Pump Station

32 • We performed a very cursory evaluation of bids and bidders, evaluated potential costs for

33

EGMA budgeting, and communicated with HRG for status updates on the award process.

34

35 Sanitary Sewer Pipe Rehab

36 • Supplee Valley - No activity since our last report.

MA 10-11-21 draft 2

1 • Hershey's Mill Estates -

2 1. We have prepared the PADEP General Permit GP-I I application for waterway impacts, and we 3 expect to submit to P ADEP the week of October 11. This permitting typically takes 90-120 days 4 for review.

5 2. We are coordinating scheduling with Mark Miller for the subsurface groundwater and rock test 6 pits. Our geotechnical engineers will be on-site to observe and to perform limited hand augers as 7 well.

8 3. Lastly, we are preparing an updated opinion of probable construction cost.

9

10 I&I Program

11 • No activity since our last report.

12

13 New Connections

14 • We performed an updated study of the costs and feasibility for public sewer extension to several 15 unsewered neighborhoods to estimate the costs of extension vs. on-site system replacement. A 16 letter report was submitted. There are 324 homes with on-site systems in EG. The average cost 17 for connection to public sewer is $60,000.00.

18 • 1344 Morstein Road - We performed an initial evaluation of the feasibility of connecting to 19 public sewer per an inquiry by the property owner.

20 21 Industrial Pretreatment Ordinance 22 • No activity since our last repott. As discussed at the May MA meeting, a headworks study with sampling 23 at the RCSTP needs to be conducted to set contaminant limits. There will not be a notable cost savings to 24 perform the sampling as patt of the ongoing NPDES Permit Renewal sampling since the sampling will be 25 significantly different. Consideration should be given to budgeting for the headworks study and sampling 26 in 2022. 27 28 29 3. Big Fish Environmental Services - 3 0 The Ridley Creek sewage treatment plant outfall 001 achieved compliance with the permit discharge 31 limitations for the month of August 2021. All supplemental reports were submitted with the DMR. 32 Discharge to the Apple brook irrigation lagoon remained in service. Chemical usage utilized for pH 33 and total alkalinity remained consistent with previous months. Aluminium sulfate solution volumes 34 slightly increased during September as compared to August to achieve phosphorus removal. No 35 significant mechanical or operational issues were observed during operation of sludge dewatering 36 equipment or SBR treatment process. There were no odor complaints during the month. 3 7 The RCSTP stayed in compliance during the Ida storm. Scott is preparing the data for Pennoni. They 38 switched labs to Suburban Testing.

39 40

MA 10-11-21 draft 3

1 Approval of Minutes 2 Jack moved to approve the September 13, 2021 minutes as amended. Phil seconded the motion. The 3 motion passed unanimously. 4 5 Approval of Invoices 6 Phil moved to approve payment of the 5 Pennoni invoices totaling $11,432.86. Walter 7 seconded the motion. The motion passed unanimously. 8 9 Liaison Reports 10 1. Conservancy Board- Walter reported that three trees have been replaced in Clymer's Wood. 11 They will select a day to do the mulching. He spoke about the Toddlers Trick or Treat event 12 scheduled for October 29. Jason would like to have one or two members of each ABC attend in 13 costume to greet the families and explain what their ABC does for EG. 14 2. Board of Supervisors -Mike Lynch mentioned that they are considering setting up a new 15 infrastructure account. They did not approve the PPA through the COG regarding municipal energy 16 because it required a 15 year commitment. The Federal stimulus money will go toward MA 17 upgrades. They reviewed 2 ordinance updates. They approved hiring an additional Public Works 18 Department employee. 19 20 Financial Reports 21 1. September Financial Report - Dave Ware reviewed the following report: 22 In September, the Municipal Authority recorded $24,148 in revenues (transfers from Sewer 23 Operating and Sewer Capital Reserve) and $21,391 in expenses (primarily for HM Estates sewer 24 engineering/design/permitting), for a positive variance of $2,758. As of September 30, 2021, the 25 fund balance was $25,336. Dave explained that the rate increase in July was for the budget year 26 2021. Mike Lynch spoke about raising rates vs getting bonds. The Capital Reserve Fund and 27 infrastructure was discussed. The older asbestos cement pipes are being gradually replaced. 28 2. Westtown Way Pump Station -Dave reviewed his report dated 10/11/21. He will present it to the 29 BOS. HRG will supply more detail. There is $2,134,593 remaining to be paid for this project. 30 31 Old Business 32 1. UV Update - Mike Ellis reported that they met with the Glasco UV system rep and received a 33 quote and product information for their recommended vertical replacement system. We also 34 contacted a Glasco UV reference, Les Harvey, the operator of the Humbolt Industrial Park WWTP in 35 Hazelton, PA, who provided positive first-hand operating, cleaning, and maintenance experience 36 information about the existing Glasco vertical UV system. As requested by the MA, we also initiated 37 research of other product alternatives for due diligence, and we have been in contact with Enaqua as 38 well as the Trojan system vendor, Kappe. A site visit with Public Works, the operator, and Kappe is 39 scheduled for October 13 to evaluate the feasibility of Trojan as a replacement UV system. 40 Coordination with Enaqua is ongoing. Mike explained the ve1iical system.

41 2. Hershey Mill Trunk Line -The cost estimate for this project was originally about $900,000. It 42 has increased to $1,456,000. Dave reviewed the different costs. Mike Ellis explained that they took 43 the average cost and added 15% contingency. This is a more complicated job. Mike Lynch asked

44 Mark Miller for input. Mark explained where the shale is located. In 2011 on the Lochwood project, 45 they did rock borings. He compared rocks and elevation at Lochwood vs HM. They are using iron 46 piping at HM. There is one way in and out but depending on circumstances they could have a second 4 7 way through the HM Dam. Mike Ellis feels the labor will be the bigger cost.

MA 10-11-21 draft 4

1 2 3 Goals 4 Dana reviewed the goals. 5 6 New Business 7 1. Magmeter at Hershey Mill - The magmeter at Hershey Mill Pump Station was flooded during the 8 Ida storm. It will be $5,000.00 for a new one. 9 10 Capacity Request 11 1. 1344 Morstein Road - Mark explained the request from Kyong-aie Thomas at 1344 Morstein 12 Road. She has a verbal easement with her neighbor. When Mark receives the official easement, he 13 will send it to Robert for review. 14 15 Any Other Matter - None 16 17 Correspondence- None 18 19 Public Comment - None 20 21 Adjournment 22 There being no further business Phil moved to adjourn the meeting. Walter seconded the motion. 23 The motion passed unanimously. The meeting was adjourned at 8:40 pm. 24 The next regular meeting will be held on Monday, November 8, 2021 at 7:00 pm. 25 26 Respectfully submitted, 27 28 29 Ruth Kiefer, Recording Secretary

MA 10-11-21 draft 5

Mark Miller East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380-6199

For Services Rendered Through 10/17/2021

INVOICE Remit Payment To: Pennoni Associates Inc.

P.O. Box 827328 Philadelphia, PA 19182-7328

Invoice No : 1091962 Invoice Date : 10/28/2021

Project: EGMAU21001 Project Name : 2021 General

Services

October Engineer's Report; preparation for and attendance at October MA meeting including review of RCSTP operator's report. Reviewed bid results for Westtown Way Pump Station; and coordinated with HRG and East Goshen on award recommendations, bidder reference checks, bid discrepancies, and budgeting including construction and soft costs. Continued coordination with vendors, operator, and M. Miller for RCSTP UV disinfection system replacement product evaluations including review of Glasco's quote, Glasco UV reference check, field meeting with Kappe (Trojan system rep), field measurements and existing conditions sketch of UV channel as requested by vendors, discussions with a third vendor (Enaqua), and initial evaluation of hydraulic feasibility for use of Glasco's vertical UV system. Continued study and cost estimates for public sewer extensions to unsewered neighborhoods including concept layout of gravity vs. low pressure sewer alternatives for neighborhoods not included in the 2006 study; researched onlot/septic system replacement costs; and prepared draft report.

Billing Limits

Total Billings

Limit

Labor

Authority Engineer Senior Professional Project Professional Associate Professional Graduate Professional Sr. Engineering Technician

Totals Total Labor

Current 10,456.00

Hours

21.75 6.75 1.75 5.00 66.75 2.00 104.00

Prior 19,827.25

Rate 132.00 125.00 111.00 97.00 88.00 94.00

To-Date 30,283.25 40,000.00

Amount 2,871.00 843.75 194.25 485.00 5,874.00 188.00 10,456.00

Total this Invoice

10,456.00

$10,456.00

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

Project: Pennoni Job No.: Invoice No: Invoice Period:

Initial Authorization: Contract Amount:

Previously Invoiced: Current Invoice:

Invoiced to Date ($): Invoiced to Date(%): Remaining Budget($): Remaining Budget(%):

Budget by Phase:

Phase Name: Phase Budget:

Previously Invoiced: Current Invoice: Invoiced to Date($):

Invoiced to Date(%):

West Goshen Sewer System Consultation

EGMAU21001 Invoice Summary

Invoice Date 10/28/2021

EGMAU21001 2021 General Services 1091962 9/20/2021

$ 30,000.00

$ 40,000.00

$ 19,827.25

$ 10,456.00

$ 30,283.25

$ 9,716.75 24%

2021 General Services $430,000.00

$ 19,827.25

$ 10,456.00 $ 30,283.25

to 10/17/2021 Date: 10/28/2021

Remaining Budget($): $ Remaining Budget(%):

9,716.75

24%

Comments: October Engineer's Report; preparation for and attendance at October MA meeting including review of RCSTP operator's report. Reviewed bid results for Westtown Way Pump Station; and coordinated with HRG and East Goshen on award recommendations, bidder reference checks, bid discrepancies, and budgeting including construction and soft costs. Continued coordination with vendors, operator, and M. Miller for RCSTP UV disinfection system replacement product evaluations including review of Glasco's quote, Glasco UV reference check, field meeting with Kappe (Trojan system rep), field measurements and existing conditions sketch of UV channel as requested by vendors, discussions with a third vendor (Enaqua), and initial evaluation of hydraulic feasibility for use of Glasco's vertical UV system. Continued study and cost estimates for public sewer extensions to unsewered neighborhoods including concept layout of gravity vs. low pressure sewer alternatives for neighborhoods not included in the 2006 study; researched onloVseptic system replacement costs; and prepared draft report.

Mark Miller East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380-6199

For Services Rendered Through 10/17/2021

Phase 04: Prepared construction cost estimate.

INVOICE

Phase 05: Continued preparation of PADEP GP-11 permit application.

Contract Phase Code I Name Amount

01 •. Wetland & Watercourse Investigation $6,750.00 02 -- Phase I Bog Turtle Habitat Assessment $6,750.00 03 --Survey $17,200.00 04 -- Design $26,100.00 05 •· Permitting $8,000.00 07 -- Geotechnical NTE $10,000.00 Total: $74,800.00

Remit Payment To: Pennoni Associates Inc.

P.O. Box 827328 Philadelphia, PA 19182-7328

Invoice No : 1091966 Invoice Date: 10/28/2021

Project : EGMAU21004 Project Name : HM Estates Sewer

Design & Permitting

Previously % Complete Billed Complete To Date

$6,750.00 100.00% $6,750.00 $6,750.00 100.00% $6,750.00 $17,200.00 100.00% $17,200.00 $23,751.00 93.25% $24,338.58 $3,200.00 47.99% $3,839.59 $1,400.25 14.00% $1,400.25 $66,571.75 $67,798.92

Amount Due This Invoice

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

Amount This Invoice

$0.00 $0.00 $0.00 $587.58 $639.59

$0.00 $1,227.17

$1,227.17

West Goshen HM Estates Sewer Design Permitting

EGMAU21004 Invoice Summary

Project: Pennoni Job No.: Invoice No: Invoice Period:

Initial Authorization: Contract Amount: Previously Invoiced: Current Invoice: Invoiced to Date($): Invoiced to Date(%): Remaining Budget($): Remaining Budget(%):

Budget by Phase:

Phase Name: Phase Budget: Previously Invoiced: Current Invoice: Invoiced to Date($): Invoiced to Date(%):

Invoice Date 10/28/2021

EGMAU21004 HM Estates Sewer Design & Permitting

1091966 9/20/2021 to $ 64,800.00 Date: $ 74,800.00 $ 66,571.75 $ 1,227.17 $ 67,798.92 91% $ 7,001.08 9%

HM Estates Sewer Design & Permitting

$ 74,800.00 $ $ $

66,571.75 1,227.17 67,798.92

Remaining Budget($): $ Remaining Budget(%):

91% 7,001.08 9%

Comments: Phase 04: Prepared construction cost estimate.

10/17/2021 10/28/2021

Phase 05: Continued preparation of PADEP GP-11 permit application.

Mark Miller East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380-6199

For Services Rendered Through 10/17/2021

INVOICE Remit Payment To: Pennoni Associates Inc.

P.O. Box 827328 Philadelphia, PA 19182-7328

Invoice No: 1091967 Invoice Date : 10/28/2021

Project : EGMAU21005 Project Name : RCSTP NPDES

Permit Renewal

Continued preparation of permit application forms, reviewed sampling results, and analyzed DMR data.

Billing Limits

Total Billings

Limit Remaining

Labor

Project Professional Associate Professional

Totals Total Labor

Current 1,656.25

Hours

2.25 14.50 16.75

Prior 2,036.75

Rate 111.00 97,00

To-Date 3,693.00 7,000.00 3,307.00

Amount

249.75 1,406.50 1,656.25 1,656.25

Total this Invoice =====$1,6==5=6=.2a=5

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

Project: Pennoni Job No.: Invoice No: Invoice Period:

Initial Authorization: Contract Amount: Previously Invoiced: Current Invoice: Invoiced to Date($): Invoiced to Date(%): Remaining Budget($): Remaining Budget(%):

Budget by Phase:

Phase Name: Phase Budget: Previously Invoiced: Current Invoice: Invoiced to Date($): Invoiced to Date(%):

RCSTP NPDES Permit Renewal EGMAU21005 Invoice Summary

Invoice Date 10/28/2021

EGMAU21005 RCTP NPDES Permit Renewal

1091967 9/20/2021 to $ 7,000.00 Date: $ 7,000.00 $ 2,036.75 $ 1,656.25 $ 3,693.00 53% $ 3,307.00 47%

RCTP NPDES Permit Renewal

$ 7,000.00 $ 2,036.75 $ 1,656.25 $ 3,693.00

Remaining Budget ($): $ Remaining Budget(%):

53% 3,307.00 47%

10/17/2021 10/28/2021

Comments: Continued preparation of permit applications forms, reviewed sampling results and analyzed DMR data.

INVOICE

SOLD TO: EGl0O0

EAST GOSHEN TOWNSHIP 1580 PAOLI PIKE

Tel: 800.971.4242 beyondcomponents.com

ORIGINAL SHIP TO:

. . . . : I l • I • WEST CHESTER, PA 19380

PURCHASE ORDER SHIP VIA PAYMENT TERMS I CSR#

17785 UPS Ground Net 30 Days

Packing Slip# 234915

QTY ORDERED I QTY SHIPPED I MANUFACTURE DESCRIPTION I PRICE

160 160

160 160

10 10

10 10

50 50

50 50

Harting

09-15-000-6202 ()

Han D F Crimp Contact Ag AWG 18 Harting

09-15-000-6102 ( )

Han D M Crimp Contact Ag AWG 18 Harting

09-16-042-3001 ()

Han DD 42 Pos. M Insert Crimp Harting

09 16 042 3101

Han 42DD-BU-C Wireexpress

6G-1801-03-RHS

AWG18 TFFN RED Wireexpress

6G-1801-06-ROHS

AWG18 TFFN BLUE

( )

()

()

203

09/29/2021

INVOICE NO

351097-4

PAGE

1

UNIT/ EXTENDED

$0.97000/EACH

155.20

$0.78000/EACH

124.80

$20.69000/EACH

206.90

$25.70000/EACH

257.00

$0.88000/ft

44.00

$0.88000/ft

44.00

Remit To: Beyond Components Inc

5 CARL THOMPSON ROAD WESTFORD, MA 01886

SALE AMOUNT: 831.90 13.44 0.00 Phone:610-518-9511 Fax: 610-518-9520

"We are the KING of Terminal Blocks

selling 32 brands!"

DELIVERY: SALES TAX:

TOTAL: $845.34

NOTICE: Any claim of shortage or damaged goods must be made within 10 days of shipment. Beyond Components™ will not accept responsibility after this period.

C6nnection-

Govc60KrE'cl'foN. INC. 7503 STANDISH PLACE ROCKVILLE MD 20855 PLEASE ENCLOSE ATTACHED REMITTANCE

RECEIPT WITH YOUR PAYMENT Federal ID No. Invoice No. 52-1837891 71730296 Invoice Date

08/19/2021 REMIT TO ADDRESS GOVCONNECTION, INC. DBA CONNECTION PO BOX 536477 PITTSBURGH PA 15253-5906

Company retains a purchase money security Interest In

Equipment until payment Is made In full.

1oz - #10 - J300306 - 1257 - 2106 EAST GOSHEN TOWNSHIP 1580 PAOLI PIKE WEST CHESTER PA 19380-6107

,11111,11,,111111•1111•11•l•ll11•1111lll,111111•1111l11••1l111l11

CORP. SALES (800)800-0019 CREDIT DEPT (800)294-0268

Date of Order

" .

Account ·No. Order No. Customer Purchase Order No.

08/09/2021 60922803 EGT 008052021.1 21292230

_________ Quantity ________

Back Item No. Description Ordered Ordered Shiooed

Shipped To: EAST GOSHEN TOWNSHIP 1580 PAOLI PIKE WEST CHESTER PA 19380

CUSTOMER SERV (800)800-0019

Terms Date Shipped Shipped Via

Net 30 08/19/2021 UPS - GROUND

COMMERCIAL

Unit Price Extension

10 10 41151952 EndPt SecEnt Lie/Supp 1-99D 13.1500 131.50 MFG# SES-SUB-1-99

*******'** PLEASE NOTE EFT INSTRUCTIONS *********• For electronic funds transfer, please remit to Citizens Bank: ACH Payments: ABA # 2110-70175, Account# 1310873272 WIRE Payments: ABA #0115-00120, Account# 1310873272 Please include invoice number(s) in the transmitted information.

PLEASE SEND remit information to REMIT@CONNECTION.COM

"We provide more timely and accurate information to the business community by sharing our accounts receivable information with credit bureaus"

APPROVED BY:. ___ _ DATE'PAID: _____ _ g!:bTo: Rt?f: ,&2

Merchandise Sales Tax Shipping/Packaging

131.50

HICKS, BIANCA

Order No.

60922803

GOVCONNECTION, INC. DBA CONNECTION

Ordered By

PO BOX 536477 PITTSBURGH PA 15253-5906

Susan D'amore

Company

00005

Backordered items will be shipped and Invoiced to you as soon as they are available.

Page # 1

Account No. Invoice No.

21292230 71730296

Invoice Total

131.50

Invoice Total

131.50

PLEASE ENCLOSE THIS REMITTANCE

RECEIPT WITH YOUR PAYMENT

00005 21292230 717302960000013150

1oz - 1110 - J300306 - 1257 - 21

Memo

To:

From: Re: Date:

Municipal Authority Dave Ware MA September 2021 Financial Report

November 4, 2021

In October, 2021, the Municipal Authority recorded $5,245 in revenues (transfer from Sewer Operating) and $11,911 in expenses (General Services, and UV System Connections), for a negative variance of

($6,666). As of October 31, 2021, the fund balance was $18,670.

A complete list of 2021 YTD MA revenues and expenses is attached.

I will see you all at the meeting on November 8, 2021 at 7PM.

U:\dware\municipal authority\

EAST GOSHEN TOWNSHIP

Other Funds October 2021 Municipal Authority

Annual Y-T-D Y-1-D Y-1-D M-1-D M·T·D M-1-D Account Title Acct I Budget Budget Actual Variance Budget Actual Variance ---------------------------------------- ------------ ----------- ----------- -------------- -------------- ----------- -------------- --------------

REVENUE

INTEREST EARNINGS 07341 1000 2 .53 2 .53 0 .23 0 .23

DCED GRAN! 07354 0400 152,980 152,980 (152,980.00)

C.C. TAPPING FEES 07364 1100 2,060.00 2,060.00

R.C,IAPPING FEES 07364 1110 11,508.00 11,508.00

CO!rnECTIOII FEES - SEWER 07364 1130 1,127.52 1,127.52

MISCELLAIIEOUS REVENUE 07380 1000 565 565 2,664.48 2,099.48

!RANSIER !ROM SEWER OPERATING 07392 0500 279,915 279,915 71,624.91 1208,290.10) 5,244.75 5,244.75

!RANSIER !ROM SEWER CAP RESERVE 07392 0900 122,000 85,189 178,365.32 93,176.22 25,578 (25,577.99) --------- ----------- -------------- -------------- ----------- -------------- --------------

TOTAL REVEIIIJE 555,460 518,649 267,352.76 (251,296.35) 25,578 5,244.98 (20,333.01)

EXPENSES

ADMIIIISIRAUVE WAGES 07424 1400 30,000 22,500 23,135.82 (635.82)

MISCELLAIIEOOS EXPENSE 07424 3000 1,518.25 (1,518.25)

MlJNIC .AUTH. -AUDITING 07424 3110 9,440 9,440 10,000.00 (560.00)

ENGINEERING SERVICES 07424 3130 60,900 51,626 38,130.06 13,495.67 4,437 5,244.75 (808.04)

LEGAL SERVICES 07424 3140 8,120 5,747 7,913.82 (2,166.92) 944 943.52

CAP.REPLACEMENT R.C. 07424 7490 110,984.77) 10,984.77

RELIIIING 07426 3001 130,000 130,000 129,999.99

BARKWAY PIIMP STATION CAPITAL 07429 1501 5,117.00 (5,117.00)

ASNBRIDGE PIIMP SIAIIOII CAPITAL 01429 1502 30,324.00 (30,324.00)

HERSHEYS MILL PIIMP STATIOII CAPITAL 07429 1503 75,352.79 (75,352.79) 1,679.61 (1,679.61)

HUN! CO PIIMP STATION CAPITAL 01429 1504 87,000 87,000 8,277.00 78,723.00

RCSIP CAPITAL 01429 1505 230,000 119,098 65,925.98 53,172.41 34,556 4,951.84 29,604.22 Bank Fees 07491 5001 345.00 (345,00) 34.50 (34.50) --------- ----------- --------------------------------------- ----------------------------

TOTAL EXPEIISES 555,460 425,411 255,054.95 170,356.06 39,936 11,910.70 28,025.59

--------- ----------- -------------- -------------- ----------- -------------- --------------

NET RESULT FROM OPERATIONS 93,238 12,297.81 (80,940.29) (14,358) (6,665.72) 7,692.58

MUNICIPAL AUTHORITY October 31, 2021 YTD Financials

Account# I Description IPer jsrclTrx# I Debits I credits !Balance loate I check# I Name I Description I Description 2 07341-1000 BEGINNING BALANCE 07341-1000 INTEREST EARNINGS 2101 JE 76976 34.50 1/5/2021 BANK FEES REIMBURSE S/R FOR DEC. 2020 BANK FEES 07341-1000 INTEREST EARNINGS 2102 JE 77346 34.SO 2/8/2021 REVERSE REVERSE & CORRECTTRX. 76976 BANK FEE CHARGES 07341-1000 INTEREST EARNINGS 2102 JE 77356 0.49 2/8/2021 INTEREST INTEREST EARNED JANUARY 2021 7100.1035 07341-1000 INTEREST EARNINGS 2102 JE 77638 0.44 2/28/2021 INTEREST INTEREST EARNED FEBRUARY 2021 7100.1035 07341-1000 INTEREST EARNINGS 2103 JE 78076 0.47 3/31/2021 INTEREST INTEREST EARNED MARCH 2021 7100.103 07341-1000 INTEREST EARNINGS 2104 JE 78492 0.16 5/3/2021 INTEREST INTEREST EARNED APRIL 2021 7100.1035 07341-1000 INTEREST EARNINGS 2105 JE 78908 0.19 5/31/2021 INTEREST INTEREST EARNED MAY 2021 7100.1035 07341-1000 INTEREST EARNINGS 2106 JE 79382 0.10 6/30/2021 INTEREST INTEREST EARNED JUNE 2021 7100.1035 07341-1000 INTEREST EARNINGS 2107 JE 79787 0.11 7/31/2021 INTEREST INTEREST EARNED JULY 2021 7100.1035 07341-1000 INTEREST EARNINGS 2108 JE 80222 0.13 8/31/2021 INTEREST INTEREST EARNED AUGUST 2021 7100.1035 07341-1000 INTEREST EARNINGS 2109 JE 80628 0.21 9/30/2021 INTEREST INTEREST EARNED SEPT. 2021 7100.1035 07341-1000 INTEREST EARNINGS 2110 JE 81001 0.23 10/31/2021 INTEREST INTEREST EARNED OCTOBER 2021 7100.1035 07364-110D BEGINNING BALANCE 07364-1100 C.C. TAPPING FEES 21D5 RE 78657 2,000.00 5/12/2021 78657 1 TAP IN FEE 1331 E STRASBURG RD C.C. TAPPING FEES D7364-1100 C.C. TAPPING FEES 2105 RE 78659 60.00 5/12/2021 78659 1 SEWER INSP.1331 E STRASBURG RD C.C. TAPPING FEES 07364-1110 BEGINNING BALANCE 07364-1110 R.C.TAPPING FEES 2106 RE 79365 2,000.00 6/30/2021 79365 1 TAP IN FEE FOR 1471 BOOT ROAD R.C.TAPPING FEES 07364-1110 R.C.TAPPING FEES 2106 RE 79366 60.00 6/30/2021 79366 1 SEWER INSPECT FOR 1471 BOOT RD R.C.TAPPING FEES 07364-1110 R.C.TAPPING FEES 2108 RE 79949 2,000.0D 8/13/2021 79949 1 TAP IN FEE-1725 TOWNE DR R.C.TAPPING FEES 07364-1110 R.C.TAPPING FEES 2108 RE 79950 150.00 8/13/2021 79950 1 SEWER lNSPECTION-1725 TOWNE DR R.C.TAPPING FEES 07364-1110 R.C.TAPPING FEES 2108 RE 80074 7,148.00 8/24/2021 80074 1 932 N CHESTER RD - TAP IN FEE R.C.TAPPING FEES 07364-1110 R.C.TAPPtNG FEES 2108 RE 8007S lS0.00 8/24/2021 80075 1 932 N CHESTER RD SEWER INSPECT R.C.TAPPING FEES 07364-1130 BEGINNING BALANCE 07364-1130 CONNECTION FEES - SEWER 2101 CR 77256 423.00 1/28/2021 2694 STOFFLET, MICHAEL 07364-1130 CONNECTION FEES - SEWER 2101 JE 772S7 141.12 1/28/2021 PINE ROCK ANNUAL PINE ROCK INSTALLMENT INTERST PORTION-STOFFLET 07364•1130 CONNECTION FEES- SEWER 2102 CR 77466 423.00 2/17/2021 745 JACOBS, ROBERT & CHERYL 07364-1130 CONNECTION FEES - SEWER 2102 JE 77467 141.12 2/17/2021 PINE ROCK ANNUAL PINE ROCK INSTALLMENT INTEREST PORTION -JACOBS 07364-1130 CONNECTION FEES- SEWER 2103 CR 77801 423.00 3/11/2021 4276 GEORGE SMITH & CHRISTINA CONLE D7364-1130 CONNECTION FEES - SEWER 2103 CR 78004 423.00 3/26/2021 8842992 PAPPANO, JOSEPH & PATRICIA 07364-1130 CONNECTION FEES -SEWER 21D3 JE 77802 141.12 3/11/2021 PINEROCK INTEREST PORTION - CONLEY SMITH 07364-1130 CONNECTION FEES - SEWER 2103 JE 78005 141.12 3/26/2021 PINE ROCK ANNUAL PINE ROCK INSTALLMENT INTEREST PORTION - PAPPAN□ 07380-1000 BEGINNING BALANCE 07380-1000 MISCELLANEOUS REVENUE 2101 JE 77257 141.12 1/28/2021 PINE ROCK ANNUAL PINE ROCK INSTALLMENT INTERST PORTION - STOFFLET 07380-1000 MISCELLANEOUS REVENUE 2102 JE 77467 141.12 2/17/2021 PINE ROCK ANNUAL PINE ROCK INSTALLMENT INTEREST PORTION -JACOBS 07380-1000 MISCELLANEOUS REVENUE 2103 JE 77802 141.12 3/11/2021 PINEROCK lNTEREST PORTION - CONLEY SMITH 07380-1000 MISCELLANEOUS REVENUE 2103 JE 78D05 141.12 3/26/2021 PINE ROCK ANNUAL PINE ROCK INSTALLMENT INTEREST PORTION- PAPPAN□ 07380-1000 MISCELLANEOUS REVENUE 2108 RE 79894 2,100.00 8/10/2021 79894 1 REFUND- COLONIAL ELEC. 10/2020 MISCELLANEOUS REVENUE 07392-0500 BEGINNING BALANCE 07392-0500 TRANSFER FROM SEWER OPERATING 2101 JE 77062 66.00 1/12/2021 XFER XFER $ FROM SEWER TO MA RE: JANUARY EXPENSES 07392-0500 TRANSFER FROM SEWER OPERATING 2101 JE 77072 0.01 1/13/2021 ADJUST ADJUSTTRX. 76744 07392-0500 TRANSFER FROM SEWER OPERATING 2102 JE 77393 3,031.25 2/9/2021 XFER XFER FUNDS TO MA FROM SEWER & SEWER CAP. RE:FEB 2021 EXP. 07392-0500 TRANSFER FROM SEWER OPERATING 2103 JE 77621 2,S25.00 3/1/2021 XFER XFER $TO MA FROM SEWER RE: MA EXPENSES 07392-0500 TRANSFER FROM SEWER OPERATING 2103 JE 77775 3,813.00 3/10/2021 XFER XFER $TOMA FROM SEWER FUND 07392-0500 TRANSFER FROM SEWER OPERATING 2103 JE 77959 S,9S5.00 3/24/2021 XFER XFER $ FROM OS TO 07 MA 07392-0500 TRANSFER FROM SEWER OPERATING 2103 JE 78050 7,373.83 3/31/2021 XFER XFER $ TO MA FROM 05 07392-0SOO TRANSFER FROM SEWER OPERATING 2104 JE 78253 13,737.91 4/15/2021 XFER XFER $ FR: SEWER OPER. TO MA 07392-0SOO TRANSFER FROM SEWER OPERATING 2105 JE 78480 2,158.00 5/3/2021 XFER XFER $ FROM SEWER TO MA TO COVER EXPENSE 07392-0500 TRANSFER FROM SEWER OPERATING 2105 JE 78625 3,141.2S 5/12/2021 XFER XFER $ FROM SEWER & SEWER CAP. RESERVE TO MA 07392-0500 TRANSFER FROM SEWER OPERATING 2106 JE 79162 6,550.41 6/16/2021 XFER XFER $ SEWER & SEWER CAPJTAL TO MUN.AUTH. 07392-D50D TRANSFER FROM SEWER OPERATING 2106 JE 79359 7,569.21 6/30/2021 XFER XFER $ FROM 05 TO 07 07392-0500 TRANSFER FROM SEWER OPERATING 2107 JE 79501 5,291.06 7/13/2021 XFER XFER $ FROM SEWER & SEWER CAP. RESERVE TO MA 07392-0500 TRANSFER FROM SEWER OPERATING 2109 JE 80367 4,194.75 9/14/2021 XFER MA XFER $ FROM 09 & 05 TO 07MA RE: EXPENSES 07392-0500 TRANSFER FROM SEWER OPERATING 2109 JE 80494 973.SO 9/22/2021 XFER XFER $ FROM 05 TO 07 MA TO COVER 9/22/21 EXPENSES 07392-0500 TRANSFER FROM SEWER OPERATING 2110 JE 80789 5,244.75 10/15/2021 XFER XFER $ FROM SEWER TO MA TO COVER SEPT.MA EXPENSES 07392-0900 BEGINNING BALANCE

U:\DWare\Municlpal Authority\10 October 2021\0ctober 2021 YTD Financials 1of3

MUNICIPAL AUTHORITY October 31, 2021 YTD Financials

ccount# I Description IPer lsrclTrx# loebits I credits I Balance I Date I check# I Name I Description I Description 2 )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2102 JE 77393 12,162.92 2/9/2021 XFER XFER FUNDS TO MA FROM SEWER & SEWER CAP. RE:FEB 2021 EXP. )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2102 JE 77434 l5,03S.91 2/12/2021 XFER XFER $ FROM 09 TO 07 )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2103 JE 77623 15,721.12 3/1/2021 XFER XFER $ FROM SEWER CAPITAL TO MA RE: EXPENSES )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2103 JE 77777 10,188.22 3/10/2021 XFER XFER $TO MA FROM SEWER CAP. RESERVE )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2103 JE 77779 5,785.09 3/10/2021 XFER XFER $TO MA FROM SEWER CAP. RESERVE )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2103 JE 77827 382.02 3/12/2021 XFER RETURN$ TO 09 FROM 07 RE: XFER ERROR 2/9/21 )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2103 JE 77957 922.95 3/24/2021 XFER XFER $ FROM 09 TO 07 MA )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2104 JE 78255 33,111.72 4/15/2021 XFER XFER $ FR: SEWER CAPITAL TO MA )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2104 JE 78369 926.66 4/26/2021 XFER XFER $ FROM SEWER CAPITAL 09 - MUNIClPALAUTH. 07 )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2105 JE 78625 16,313.20 5/12/2021 XFER XFER $ FROM SEWER & SEWER CAP. RESERVE TO MA )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2105 JE 78746 31,885.04 5/19/2021 XFER XFER $ FROM SEWER CAP.RESERVE TO MUN.AUTHORITY )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2105 JE 78802 2,859.50 5/25/2021 XFER XFER $TO MA FROM SEWER CAPITAL )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2106 JE 79162 9,985.87 6/16/2021 XFER XFER $ SEWER & SEWER CAPITAL TO MUN.AUTH. )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2106 JE 79231 1,049.82 6/22/2021 XFER XFER $ FROM 09 SEWER CAPTITAL TO 07 MUN.AUTH. )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2107 JE 79501 3,819.33 7/13/2021 XFER XFER $ FROM SEWER & SEWER CAP. RESERVE TO MA )7392-0900 TRANSFER FROM SEWER CAP RESERVE 2109 JE 80367 18,979.99 9/14/2021 XFER MA XFER $ FROM 09 & 05 TO 07MA RE: EXPENSES )7424-1400 BEGINNING BALA.NCE )7424-1400 ADMINISTRATIVE WAGES 2103 CD 78032 7,373.83 3/30/2021 3264 EAST GOSHEN TOWNSHIP - GENERAL QTR.1-2021 REIMBURSEMENT J7424-l400 ADMINISTRATIVE WAGES 2106 CD 79318 7,569.21 6/28/2021 3281 EAST GOSHEN TOWNSHIP - GENERAL Q2 - 2021 MA REIMBURSEMENT J7424-1400 ADMINISTRATlVE WAGES 2109 CD 80586 8,192.78 9/29/2021 3289 EAST GOSHEN TOWNSHIP - GENERAL Q3-202l QUARTERLY RE\MBURSEMENT -MA )7424-3000 BEGINNING BALA.NCE :)7424-3000 MISCELLA.NEOUS EXPENSE 2103 CD 77949 638.00 3/24/2021 3261 DELA.WARE RIVER BASIN COMMISSION 2021 ANNUAL FEE J7424-3000 MlSCELLA.NEOUS EXPENSE 2104 CD 78161 880.25 4/8/2021 3265 PA MUNICIPAL AUTHORlTIES ASSOC 2021 ACTIVE MEMBERSHIP DUES 07424-3110 BEGINNING BALA.NCE 07424-3110 MUNIC.AUTH.-AUDITING 2102 CD 77571 2,525.00 2/26/2021 3253 MAILLIE FALCONtERO & CO. PROGRESS BILLING AUDIT EGT MUN.AUTH 07424-3110 MUNIC.AUTH.-AUD!TING 2103 CD 77949 5,317.00 3/24/2021 3263 MAILLIE FALCONIERO & CO. FINANCIAL STMTS. & AUDIT 2020 07424-3110 MUNIC.AUTH.-AUD!TING 2104 CD 78451 2,158.00 4/29/2021 3271 MAILLIE FALCONIERO & CO. BAL. DUE RE: MUNIC!PAL AUTH. 2020 AUDIT 07424-3130 BEGINN\NG BALA.NCE 07424-3130 ENGINEERING SERVICES 2101 CD 77095 66.00 1/12/2021 3243 PENNON! ASSOCIATES INC. SERVICES THRU 12/6/20 GEN.SERVICES 07424-3130 ENGINEERING SERVICES 2102 CD 77394 3,031.25 2/9/2021 3245 PENNON! ASSOCIATES INC. SERVICE THRU 12/31/20 2020 GEN.SERV 07424-3130 ENGINEERING SERVICES 2103 CD 77786 2,973.00 3/10/2021 3259 PENNON! ASSOCIATES INC. SERVICES THRU 2/14/21 2020 CHAP.94 07424-3130 ENGINEERING SERVICES 2104 CD 78252 11,300.81 4/15/2021 3268 PENNONI ASSOCIATES INC. SERVICES THRU 3/21/21 RCSTP CAUSTIC SODA CONVERSlON 07424-3130 ENGINEERING SERVICES 2105 CD 78624 3,141.25 5/12/2021 3272 PENNONI ASSOCIATES INC. SERVICES THRU 4/18/212020 CHAP.94 07424-3130 ENGINEERING SERVICES 2106 CD 79161 4,038.00 6/16/2021 3278 PENNONI ASSOCIATES INC. SERVICES THRU 5/16/21 2021 GEN.SERV 07424-3130 ENGINEERING SERVICES 2107 CD 79500 4,046.75 7/13/2021 3283 PENNON! ASSOCIATES INC. SERVICE THRU 6/20/21 RCSTP NP DES PERMIT RENEWAL 07424-3130 ENGINEERING SERVICES 2109 CD 80366 3,754.75 9/14/2021 3285 PENNON! ASSOCIATES INC. SERVICE THRU 7/18/212021 GEN.SERV. 07424-3130 ENGINEERING SERVICES 2109 CD 80490 533.50 9/22/2021 3288 PENNON! ASSOCIATES INC. SERVICE THRU l/17/21 2020 CHAP.94 07424-3130 ENGINEERING SERVICES 2110 CD 80787 5,244.75 10/15/2021 3290 PENNON! ASSOCIATES !NC. SERVlCES THRU 9/19/212021 GEN.SERV 07424-3140 BEGINNING BALA.NCE 07424-3140 LEGAL SERVICES 2103 CD 77786 840.00 3/10/2021 3258 GAWTHROP GREENWOOD & HAL5TED LEGALSERV. - DECEMBER 2020 07424-3140 LEGALSERVICES 2104 CD 78252 2,437.10 4/15/2021 3267 GAWTHROP GREENWOOD & HAL5TED LEGAL SERVICE - 2/5-2/9/21 GEN.AUTH 07424-3140 LEGAL SERVICES 2106 CD 79161 2,512.41 6/16/2021 3277 GAWTHROP GREENWOOD & HALSTED LEGAL SERV\CE 4/9-4/13/21 GEN.AUTH. 07424-3140 LEGAL SERVICES 2107 CD 79500 1,244.31 7/13/2021 3282 GAWTHROP GREENWOOD & HALSTED LEGAL SERV\CE 6/3-6/28/21 GEN.AUTH. 07424-3140 LEGAL SERVICES 2109 CD 80366 440.00 9/14/2021 3284 GAWTHROP GREENWOOD & HALSTED LEGAL SERVICE 7/12/21 GEN.AUTHORITY 07424-3140 LEGAL SERVICES 2109 CD 80490 440.00 9/22/2021 3287 GAWTHROP GREENWOOD & HALSTED LEGAL SERVICE 8/6-8/9/21 GEN.AUTH. 07424-7490 BEGINNING BALA.NCE 07424-7490 CAP.REPLA.CEMENT R.C. 2109 JE 80532 10,984.77 9/27/2021 REFUND REFUND RE: DUPLICATE PAYMENT - 43831 07429-1501 BEGINNING BALANCE 07429-1501 BARKWAY PUMP STATION CAPITAL 2104 CD 78252 5,117.00 4/15/2021 3266 DECKMAN MOTOR & PUMP INC. REBUILT HYDROMAT!C PUMPS 07429-1502 BEGINNING BALANCE 07429-1502 ASHBRIDGE PUMP STATION CAPITAL 2105 CD 78743 30,324.00 5/19/2021 3273 DECKMAN MOTOR & PUMP INC. REBUILT FAIRBANKS MORSE PUMP- ASHBRIDGE - S/N 1495773-0 07429-1503 BEGINNING BALANCE 07429-1503 HERSHEY$ MILL PUMP STATION CAPITAL 2103 CD 77786 5,815.53 3/10/2021 3259 PENNON! ASSOCIATES INC. SERVICES THRU 2/14/21 HM ESTATES SEWER DESIGN & PERMITTING 07429-1503 HERSHEY$ MILL PUMP STATION CAPITAL 2104 CD 78252 2,786.00 4/15/2021 3266 DECKMAN MOTOR & PUMP \NC. REBUILT HYDROMATIC PUMPS 07429-1503 HERSHEY$ MILL PUMP STATION CAPITAL 2104 CD 78359 (91.96) 4/26/2021 3269 COLONIAL ELECTRIC SUPPLY CRED. RE: PARALLEL REEL AXLE 07429-1503 HERSHEYS MILL PUMP STATION CAPITAL 210S CD 78624 12,338.20 5/12/2021 3272 PENNON! ASSOCIATES INC. SERV.THRU 4/18/21 HM ESTATES SEWER

U:\DWare\Municipal Authority\10 October 2021\0ctober 2021 YTD Financials 2 of 3

MUNICIPAL AUTHORITY October 31, 2021 YTD Financials

ccount # I Description !Per lsrclTrx# !Debits I credits I Balance I Date I check# jName I Description I Description 2 )7429-1503 HERS HEYS MILL PUMP STATION CAPITAL 2109 CD 80366 15,879.99 9/14/2021 3285 PENNON! ASSOCIATES INC. SERVICETHRU 7/18/21 HM ESTATES SEWER DESIGN & PERMITTING )7429-1503 HERSHEYS MILL PUMP STATION CAPITAL 2109 JE 80368 36,945.42 9/14/2021 RECLASS RECLASS PENNONI/ HM ESTATE PAYMENT- VARIOUS 2021 )7429-1503 HERSHEY$ MILL PUMP STATION CAPITAL 2110 CD 80787 1,679 .61 10/15/2021 3290 PENNON! ASSOCIATES INC. SERV.THRU 9/19/21 HM ESTATES SEWER DESIGN & PERMITTING )7429-1504 BEGINNING BALANCE )7429-1504 HUNT CO PUMP STATION CAPITAL 2104 CD 78252 6,831 .00 4/15/2021 3266 DECKMAN MOTOR & PUMP INC. REBUILT HYDROMATIC PUMPS ]7429-1504 HUNT CO PUMP STATION CAPITAL 2106 CD 79161 790.00 6/16/2021 3276 DECKMAN MOTOR & PUMP INC. REBUILT HYDROMATIC PUMP ]7429-1504 HUNT CO PUMP STATION CAPITAL 2106 CD 79183 656.00 6/21/2021 3279 DECKMAN MOTOR & PUMP INC. REBUILT-HYDROMATIC PUMP )7429-1505 BEGINNING BALANCE )7429-1505 RCSTP CAPITAL 2102 CD 7739 4 462 .00 2/9/2021 3244 MAIN LINE CONCRETE 2 YDS CONCRETE 4000 PSI )7429-1505 RCSTP CAPITAL 2102 CD 77394 5,552 .50 2/9 /2021 3245 PENNON! ASSOCIATES INC. SERVICE THRU 1/17/21 HERSH. MILL ESTATES SEWER REPLACEMENT )7429-1505 RCSTP CAPITAL 2102 CD 77394 5,766.40 2/9/2021 3246 XYLEM DEWATERING SOLUTIONS INC. 8 X50' HEAVY DUTY LAYFLAT HOSE" )7429-1505 RCSTP CAPITAL 2102 CD 77433 1,647.00 2/12/2021 3247 COLONIAL ELECTRIC SUPPLY HAMMOND ELECTRIC BOX )7429-1505 RCSTP CAPITAL 2102 CD 77433 7,004.16 2/12/2021 3248 HANSON AGGREGATES PENNSYLVANIA LLC 203 .31 TONS 1/4 STONE" )7429-1505 RCSTP CAPITAL 2102 CD 77433 472.50 2/12/2021 3249 HICKS BROTHERS LLC 63 SMALL BALES OF STRAW )7429-1505 RC5TP CAPITAL 2102 CD 77433 127.05 2/12/2021 3250 KNOX EQUIPMENT RENTALS INC. MULCHER RENTALl/21/21 HIBBERD LANE )7429-1505 RCSTP CAPITAL 2102 CD 77433 2,258.00 2/12/2021 3251 TRENCHTECH INC. SHORE RENT & NYLON LIFTING SLING 1/7-1/20/21 J7429-1S05 RCSTP CAPITAL 2102 CD 77433 3,527.20 2/12/2021 3252 XYLEM DEWATERING SOLUT\ONS INC. ORI- PRIME PUMP, HOSES & SUCTION SCREEN RENTAL )7429-1505 RCSTP CAPITAL 2102 CD 77620 542 .92 3/1/2021 3254 COLONIAL ELECTRIC SUPPLY PVC CONDUITS, PANELS, LOCKNUT$ & VARIOUS ELECTRICAL PARTS )7429-1505 RCSTP CAPITAL 2102 CD 77620 1,112 .20 3/1/2021 3255 EXETER SUPPLY COMPANY INC MAX ADAPTERS (4) )7429-1505 RCSTP CAPITAL 2102 CD 77620 14,066.00 3/1/2021 3256 FOLEY INC. TRACK LOADER RENTAL 1/11-1/20/21 )7429-1505 RCSTP CAPITAL 2103 CD 77786 5,761 .00 3/10/2021 3257 FOLEY INC. EXCAVATOR, COUPLER & BUCKET RENTAL 1/11-1/28/21 HIBBERD LANE )7429-1505 RCSTP CAPITAL 2103 CD 77786 4,372 .69 3/10/2021 3259 PENNON! ASSOCIATES INC. SERVICES THRU 2/14/21 RCSTP CAUST!C SODA CONVERSION :J7429-1505 RCSTP CAPITAL 2103 CD 77786 24.09 3/10/2021 3260 YALE ELECTRIC SUPPLY CO NON- METALLIC CONNECTORS, COUPLING & BLACK WIRING 07429-1505 RCSTP CAPITAL 2103 CD 77949 922.95 3/24/2021 3262 LEC- LENNI ELECTRIC CORPORATION RACK FOR FLOW METER- HIBBERD 07429-1505 RCSTP CAPITAL 2104 CD 78252 18 ,377.72 4/15/2021 3268 PENNON! ASSOCIATES INC. SERV. THRU 3/21/21 HM ESTATES SEWER 07429-1505 RCSTP CAPITAL 2104 CD 78359 401.60 4/26/2021 3269 COLONIAL ELECTRIC SUPPLY PVC CONDU!TS, BELL ENDS, STEEL LOCK NUTS & POLE RISERS 07429-1505 RCSTP CAPITAL 2104 CD 78359 617.02 4/26/2021 3270 XYLEM DEWATERING SOLUTIONS INC. SALES TAX RE: INVOICE#401064279 07429-1505 RCSTP CAPITAL 2105 CD 78624 3,975 .00 5/12/2021 3272 PENNONI ASSOCIATES INC. SERV.THRU 4/18/21 RCSTP CAUSTC SODA 07429-1505 RCSTP CAPITAL 2105 CD 78743 1,561.04 5/19/2021 3274 YALE ELECTRIC SUPPLY CO WIRE, POLE RISER & PARTS FOR PECO CONDUIT 07429-1505 RCSTP CAPITAL 2105 CD 78797 2,859.50 5/25/2021 3275 LEC- LENNI ELECTRIC CORPORATION ELECTRICAL SERVICE RE: HIBBERD LANE FLOW METER 07429-1505 RCSTP CAPITAL 2106 CD 79161 9,195.87 6/16/2021 3278 PENNONI ASSOCIATES INC. SERV. THRU 5/16/21 2021 HM ESTATES SEWER DESIGN 07429-1505 RCSTP CAPITAL 2106 CD 79183 393.82 6/21/2021 3280 HIGHWAY MATERIALS INC. 7.53 TONS 9.5mm, 0 .3<3,H HIBBERD LN METER 07429-1505 RC STP CAPITAL 2107 CD 79500 3,819.33 7/13/2021 3283 PENNON! ASSOCIATES INC. SERVICE THRU 6/20/21 HM ESTATES SEWER DESIGN & PERMITTING 07429-1505 RCSTP CAPITAL 2109 CD 80366 3,100 .00 9/14/2021 3286 WARD LANDSCAPE SERVICES INC. PLANT & MULCH 12 SKIP LAURELS - HIBBARD LANE 07429-1505 RCSTP CAPITAL 2109 JE 80368 36,945.42 9/14/2021 RECLASS RECLASS PENNONI/HM ESTATE PAYMENT- VARIOUS 2021 07429-1505 RCSTP CAPITAL 2110 CD 80787 3,975.00 10/15/2021 3290 PENNON! ASSOCIATES INC. SERVICES THRU 9/19/21 RCSTP CAUSTIC SODA CONVERSION 07429-1505 RCSTP CAPITAL 2110 CD 80870 845.34 10/21/2021 3291 BEYOND COMPONENTS INC. UV SYSTEM 07429-1505 RCSTP CAPITAL 2110 CD 80870 131.50 10/21/2021 3292 GOVCONNECTlON INC. UV SYSTEM CONNECTORS 07491-5001 BEGINNING BALANCE 07491-5001 Bank Fees 2102 EX 77369 34.50 2/9/2021 77369 1 REIMB. 5/ R -JAN.2021 BANK FEES Bank Fees 07491-5001 Bank Fees 2102 JE 77346 34.50 2/8/2021 REVERSE REVERSE & CORRECT TRX. 76976 BANK FEE CHARGES 07491-5001 Bank Fees 2103 EX 77652 34.50 3/2/2021 77652 1 REIMB. S/ R - FEB.2021 BANK FEES Bank Fees 07491-5001 Bank Fees 2104 EX 78095 34.50 4/1/2021 78095 1 REIMB.5/ R-3/2021 BANK FEES Bank Fees 07491-5001 Bank Fees 2105 EX 78504 34.50 5/4/2021 78504 1 REJMB. S/R FOR APRIL BANK FEES Bank Fees 07491*5001 Bank Fees 2106 EX 78925 34.50 6/2/2021 78925 1 RE\MB. 5/ R MAY 2021 BANK FEES Bank Fees 07491-5001 Bank Fees 2107 EX 79392 34 .50 7/1/2021 79392 1 JUNE 2021 BANK FEES Bank Fees 07491-5001 Bank Fees 2108 EX 79797 34.50 8/2/2021 79797 1 REIMBURSE 5/R-JULY BANK FEES Bank Fees 07491-5001 Bank Fees 2109 EX 80231 34.50 9/1/2021 80231 1 AUGUST 2021 BANK FEE Bank Fees 07491-5001 Bank Fees 2110 EX 80639 34.50 10/4/2021 80639 1 REIMB.5/ R FOR 9/2021 BANK FEES Bank Fees

U:\DWare\Municipal Authority\10 October 2021\0ctober 2021 YTD Financials 3 of 3

EAST GOSHEN TOWNSHIP

MUNICIPAL AUTHORITY

RESOLUTION NO. __ -2021

A RESOLUTION OF THE BOARD OF THE EAST GOSHEN TOWNSHIP MUNICIPAL

AUTHORITY, CHESTER COUNTY, PENNSYLVANIA, APPROVING AN INTERMUNICIPAL SEWAGE TREATMENT AGREEMENT WITH WILLISTOWN TOWNSHIP AND EAST GOSHEN TOWNSHIP TO ALLOW THREE LOTS ALONG

LINE ROAD TO DISCHARGE SEWAGE INTO THE EAST GOSHEN TOWNSHIP

PUBLIC SEWER SYSTEM.

WHEREAS, East Goshen Municipal Authority (the "Municipal Authority") is a municipal authority organized in the Commonwealth of Pennsylvania pursuant to the Municipality Authorities Act, 53 Pa.C.S. §5601 et seq., which owns the sewage collection and treatment system in East Goshen Township (the "Sewer System");

WHEREAS, East Goshen Township ("East Goshen") is a township of the second class which leases the Sewer System from the Municipal Authority and operates the same;

WHEREAS, three properties located at 75, 79 and 81 Line Road in Willistown Township (the "Willistown Properties") are connected to the Ridley Creek Sewage Collection System which is part of the Sewer System;

WHEREAS, East Goshen and the Municipal Authority permitted the Willistown Properties to connect to the Sewer System but there was never an intergovernmental agreement in place for the same;

NOW THEREFORE BE IT RESOLVED BY THE BOARD OF THE EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY as follows:

SECTION 1. Municipal Authority hereby approves the Sewage Treatment Agreement attached hereto as Exhibit "A" ("lntermunicipal Agreement"), by which East Goshen and the Municipal Authority grant to Willistown Township the right to discharge sewage waste from the Willistown Properties into the Sewer System for treatment.

SECTION 2. Duration. The lntermunicipal Agreement shall not expire and shall be in effect for as long as the Willistown Properties are connected to the Sewer System.

SECTION 3. Purpose and Objectives. The purpose of the Agreement is to memorialize the approval by East Goshen, the Municipal Authority and Willistown of the connection of the Willistown Properties to the Sewer System and address each parties' respective obligations related to providing sewer service to such properties.

SECTION 4. The lntermunicipal Agreement attached hereto as Exhibit "A" sets forth the organizational structure necessary to implement the Agreement, and the manner in which the Willistown Properties at issue shall be connected to the Sewer System.

RESOLVED AND ADOPTED by the Board of Supervisors of East Goshen, Chester County, Pennsylvania, this 8th day of November, 2021.

Walter Wujcik, Secretary Dana Pizzaro, Chairman

Jack E. Yahraes, Vice Chairman

Walter Wujcik

Kevin R. Cummings

Phil Mayer

2

SEWAGE TREATMENT AGREEMENT

THIS AGREEMENT, made the __ day of _________ __, 2021 by and among EAST GOSHEN TOWNSHIP ("East Goshen"), EAST GOSHEN MUNICIPAL AUTHORITY ("East Goshen Authority") and WILLISTOWN TOWNSHIP (Willistown").

WITNESSETH:

WHEREAS, 75, 79, and 81 Line Road, Malvern, PA 19533 (the "Properties") are three improved lots currently located in Willistown which discharge sanitary sewage into the East Goshen Sewage System that is owned by the East Goshen Authority; and

WHEREAS, the purpose of this Agreement is to affirm and set forth the terms and conditions by which the sanitary sewage generated by the Properties shall be received and treated by East Goshen at the Ridley Creek Sewage Treatment Plant.

NOW, THEREFORE, the parties hereto, each binding itself, its successors and assigns, and each representing that it has the proper legal authority to enter into this Agreement, do mutually represent, covenant and agree as follows:

1. East Goshen and East Goshen Authority grant Willistown the right to discharge sanitary sewage wastes from the Properties into the East Goshen Sewage System for treatment. Such discharge shall be made into East Goshen's Ridley Creek Sewage Collection System located in East Goshen. No other sanitary sewage from Willistown shall be discharged into the East Goshen Sewage System. East Goshen and East Goshen Authority agree that sufficient sewage capacity has been allocated in the East Goshen

Sewage System to receive and treat the sanitary sewage generated by the Properties.

2. East Goshen and East Goshen Authority reserve the right at any time to divert the sanitary sewage from the Properties to any other treatment facility of the East Goshen Sewage System. Willistown reserves the right at any time to divert the sanitary sewage from the Properties to any other treatment facility in its system, in which event East Goshen's and East Goshen Authority's obligation to receive the sanitary sewage wastes from the Properties pursuant to this Agreement shall terminate.

3. East Goshen shall be responsible for the maintenance and repair for the entire collection system which collects and conveys sanitary sewage from the Properties including the portion within Willistown. Willistown hereby grants East Goshen and/or East Goshen Authority the right to enter upon its streets and/or easements, as necessary, in order to effect repairs or perform maintenance on the collection system which collects and conveys sanitary sewage from the Properties. East Goshen and/or East Goshen Authority shall repair and restore all disturbed areas of land in Willistown resulting from such repair and maintenance.

4. Willistown agrees to permit no discharges into the collection system which collects and conveys sanitary sewage from the Properties other than domestic waste and agrees to abide by all East Goshen's and East Goshen Authority's regulations governing the

discharge of waste into the East Goshen Sewage System.

5. Willistown shall be responsible for the billing of the Properties for sewage service provided by East Goshen. East Goshen shall bill Willistown on a calendar quarter basis at the regular residential sewer rental charge established according to the East Goshen sewer rate ordinance or resolution for treatment of the sanitary sewage generated by the Properties. Payment shall be made by Willistown within 30 days of delivery of the bill.

IN WITNESS WHEREOF, the parties have caused these presents to be executed the day and year first written above.

ATTEST: EAST GOSHEN TOWNSHIP

BY: ____________ _

David Shuey, Chairman

ATTEST: EAST GOSHEN MUNICIPAL AUTHORITY

BY: _____________ _

Dana Pizarro, Chair

ATTEST: WILLISTOWN TOWNSHIP

BY: _____________ _

Mark Miller

From: Sent: To:

Subject: Attachments:

Vince Donohue <vdonohue@lambmcerlane.com> Thursday, October 28, 2021 10:05 AM

Patrick M. McKenna (pmckenna@gawthrop.com); Kristin S. Camp (kcamp@buckleyllp.com); Derek Davis; Mark Miller FW: Aqua - Willistown Sewer - EGT & EGMA Issue 26. Exhibit F12 - 2003-00-00 Sewage Treatment Agreement.pdf; Pro-Forma Sewage Treatment Agreement -East Goshen and Willistown - 75, 79, and 81 Line Rd.docx

All, just following up on my email below. Thanks.

From: Vince Donohue Sent: Thursday, October 21, 2021 11:01 AM To: Patrick M. McKenna (pmckenna@gawthrop.com) <pmckenna@gawthrop.com>; Kristin S. Camp

(kcamp@buckleyllp.com) <kcamp@buckleyllp.com>; Derek Davis (ddavis@eastgoshen.org) <ddavis@eastgoshen.org>; Mark Miller <mmiller@eastgoshen.org> Subject: Aqua - Willistown Sewer - EGT & EGMA Issue

Derek, Mark, Kristin & Pat -

I hope all is well. We are representing Aqua in connection with its acquisition of Willistown Township's sanitary sewer system. One of the issues that has arisen involves three residential prope1ties in Willistown Township that send flows to East Goshen for treatment. 75, 79 and 81 Line Road (right on the border between WT and EGT) are served by the treatment plant in Clocktower Woods. The PUC has raised a deficiency with the application indicating that there should be a written intermunicipal agreement among WT and EGT/EGMA for the services provided to these three properties.

Interestingly, in 2003, when Vince D' Annunzio developed 79 Line Road, Willistown sent him to EG to confirm the availability of sewer. EGMA's minutes from 2003 approving the connection are attached ("Exhibit F12" pdf), as is the letter from Rick Smith to D' Annunzio referenced in those minutes. As a result of EGMA's approval and the letter, which was copied to Willistown's manager at the time, the Sewage Treatment

Agreement draft was created, which is also attached at the end of the attached PDF. No one - including East Goshen - has a signed copy of that Agreement.

So, in order to satisfy the PUC's deficiency regarding this issue, we have drafted the attached template Sewage Treatment Agreement to document the existing arrangement among WT, EGT and EGMA for the three prope1ties. The draft mirrors the 2003 unsigned version included with the attached PDF.

We are asking that EGT and EGMA consider the draft for approval.

Let me know if either of you has any questions about this. Thanks,

Vin

Vincent T. Donohue

L A M B M c E R L /\ N E

0c

AT T O IHH Y S AT L AW

Direct: 610.701.4429 Cell: 610.416.8841 Fax: 610.692.0877

1

24 E. Market St. PO Box 565 West Chester, PA 19381 www.lambmcerlane.com

vCard Bio Linkedln

This e-mail contains PRIVILEGED AND CONFIDENTIAL INFORMATION intended only for the use of the Individual(s) named above. If you are not the intended recipient of this e-mail, or the employee or agent responsible for delivering this to the intended recipient, you are hereby notified that any dissemination or copying of this e-mail is strictly prohibited. If you have received this e-mail in enor, please immediately notify us by telephone at 610.430.8000 or notify us by e-mail at info@lambmcerlane.com.

2

EXHIBITF12

SEWAGE TREATMENT AGREEMENT, DATED 2003,

BY AND BETWEEN EAST GOSHEN TOWNSHIP,

EAST GOSHEN MUNICIPAL AUTHORITY,

AND THE TOWNSHIP OF WILLISTOWN

68

EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY MEETING

MINUTES August 11, 2003

The East Goshen Township Municipal ,Authority held their regularly scheduled meeting on Monday, August 11, 2003 at 7:00 PM at the East Goshen Township Building. Members in attendance were Chairman Joseph Mccawley, Francis Beck, John Graham, Kevin Cummings and Robert Koski. Also present were Authority Engineer David Linahan. Planning Commission Liaison Jack Y ahraes, Township Solicitor Robert Adams, Township Manager Rick Smith and Board of Supervisor Carmen Battavio.

1, CALL TO ORDER

The Chairman called the meeting to order at 7:00 PM and led those present in the Pledge of Allegiance.

b LIAISON REPORTS

Planning Commission (Jack Yahraes) -reported that David DellaPorta, developer of the Fedor property has requested the Township change the zolllng for the 3 properties just north of the Fedor property. If approved it would increase the number of units from 134 to 184.

Board of Supervisors (Bob Koski) -reported that the Board of Supervisors adopted a resolution at their August Meeting asking Jackie Weber, Chairman of the Historical Commission to resign. He also noted that two other members of the Historical Commission had tendered their resignations from the Commission. * APPROVALOFMINUTES

Kevin Cummings moved to approve the Minutes of July 14, 2003 as corrected. Fran Beck seconded the motion. There was no public comment. The motion carried unanimously.

i APPROVAL OF INVOICES

A. The Yerkes bill for the month of June 2003 was not submitted.

B. John Graham moved to approve payment of Gawthrop, Greenwood & Halsted biU

for the month of June 2003 in the amount of$894.18. Fran Beck seconded the motion. There was no public comment. The motion carried unanimously.

C: \Documents ond SelfingY)joycet\Loca/ Settings\Temporary llliernet Files\OLK26lmominutes081103final.doc Minutes

69

--------------------------------__ ·- ---,-[,

-..----.. .., ..... r-\--]-----------------------------._, __ -:. -... ._-:..

FINANCIAL REPORTS

Bob Koski made a motion to convert the $1,128,000.00 DVRFA Loan to a Guaranteed

Revenue Note at the 15 year fixed rate of 3.754% with the maturity date of October 25th 2018. John Graham seconded the motion. There was no public comment. The motion carried unanimously.

OLD BUSINESS

A. Goals for 2003 -Rick Smith will change the DVRF A Loan Goal to reflect a

change converting from a variable rate to a fixed rate. The loan will continue to be monitored monthly. B. Ridley Creek Expansion -Dave Linahan gave an overview of the information

sent by Bob Smith of Riordan Materials Corp. with regards to the MBR System. Included were references to be contacted along with Engineer Firms for peer

reviews. Dave suggested that Mr. Thomas Milnes be used for the peer review as he has extensive experience with MBR Systems. Joe Mccawley ,vill contact Mr. Milnes for a proposal on the project. Joe McCawley also shared a draft proposal from Pennoni Associates outlining their peer review proposal. Pennoni Associates has in-depth international experience with waste management system and should be considered.

Kevin Cummings made a motion giving Rick Smith the authority to contact JetTech to negotiate a rate for a pilot program with the MBR System for the East Goshen Township. Fran Beck seconded the motion. There was no public comment. The motion carried unanimously.

Joe McCawley also received a letter from Bill Schoenhut of Marshall Stevens ,vith a draft proposal to appraise the value of the Ridley Creek Plans. Mr. Schoenhut's letter will be distributed at the September Municipal Authorities Meeting.

L. NEW BUSINESS

Bob Adams presented an amended capacity reservation agreement between East Goshen and Synthes. Joe McCawley executed the sewage capacity agreement with Bob Koski attesting to the agreement. Bob Ad;ims will record the amendment.

Ii. CAPACITY REPORTS

Vincent D' Annunzio of Vintage Development was present for the Municipal Authority Meeting and submitted a request for sewer capacity for 79-1,ine Road -Lot #2. John Graham made a motion approving Mr. D' Annuzio's request provided that the connection meet the standards set by East Goshen Township and is also approved by Willistown Township. Bob Koski seconded the motion. There was no public comment. The motion

carried unanimously. Rick Smith will send a letter of approval to Mr. D' Annunzio.

C:\Docu11Unts and StttingsVoyce{IJ.AC(J./ Settin.gs\Ttmporary lnternt.J Files\OLK26\mamlnutes08/ /03fina.l.doc Minutes

____ --.::::: ::

·.·•--· . .:... _____ -·-._. _______ _ _____ -·-.-. __ _ _____ -··-.-. __ _ -----::····-.·-,_1

·-··-_. _____ --.::: !-' -·-... __ . ..· .. _____ -·-.,,. __ ._

...;,

--.:::::-_· -----_. ,, ----- \·--:., _____ :::> _____ -··.,,,. __ ·,. -·-.. , ..... ^ -----__,_' ----- ,._,_ .... . ..... _____ -, ... _ _____ -: . .__:_ -· ' _____ -: .... ·.:. _____ -\._.

-· •• >. •• :. --

--

-... -

.

... .. : S- _____ -... _. -------: .. R:.,,. -----_ ..... :., ----- _` .. :.

' -----_.·, _____ \_. _ _____ .--S\:. _____ ... \.

·, -----'-\.> •·.'

\. ----'--_.·::._

\. -....,..----\:' _____ \;. ----------------------'· ;----------------------------'· ---,-------------------------------------------------__ \;, '-------------------------------------------------\(

August 15, 2003

Vincent J. D Annunzio Vintage Development company 63 Chesnut Road Paoli PA 19301

Re: 79 Line Road

Dear Vince:

At their meeting on August 11, 2003, the Municipal Authority approved your request to connect your lot at 79 Line Road in Willistown Township to the East Goshen Township public sewer system subject to the following conditions.

I. The Authority will require conformation from Willistown Township that they are

in agreement with your request. 2. The method of connection needs to be approved by the Authority Engineer. 3. You would be responsible for obtaining all permits required to connect to the public sewer. 4. You would be responsible for all construction, and inspection costs associated with connecting to the public sewer. 5. Payment of the tapping fee of $2,000 to East Goshen Municipal Authority and a $60 inspection fee payable to East Goshen Township.

By way of this letter, I am advising Hugh Murray, Willistown Township Manager, of your request and the Authority's decision. With respect to condition #1 I would

encourage you to contact him directly to see what would be required from his end.

Please give me a call at 610-692-7171 if you have any questions or need additional

information.

Since.rely,

Louis F. Smith, Jr. Township Manager

cc: Hugh Murray, Township Manager

F:\Data\Shared Data\Willistown\Sewer\79 Line Road\Lettcr re capacity 79 Line Road 081503.doc

Mr. Hugh Murray, Township Manager

Willistown Township 688 Sugartown Road Malvern PA I 9355

EGMAU21001

East Goshen Municipal Authority Attn: Mark Miller, Public Works Director

1580 Paoli Pike West Chester, PA 19380

RE: Sewer Extension Study

November 5, 2021

Christiana Executive Campus 121 Continental Drive, Suite 207 Newark, DE 19713

T: 302-655-4451

F: 302-654-2895

www.pennoni.com

Charter Chase, Brookmont, Goshen Downs, Indian Hills, Millstream Drive, Raewyck Drive, Ivy Lane, Old Orchard Lane, Joshua Drive, Great Oak Circle

Dear Mr. Miller:

This letter report provides a limited study revisiting the 2007 East Goshen Township Sewage Facilities

Management Plan (Act 537) for public sewer extensions to Brookmont and Charter Chase, and it evaluates extensions within the northern portion of East Goshen to Goshen Downs, Indian Hills, Millstream Drive,

Raewyck Drive, Ivy Lane, Old Orchard Lane, Joshua Drive, and Great Oak Circle for the first time. The purpose of this study is to estimate the potential costs to connect the neighborhoods to public sewer for consideration by the East Goshen Municipal Authority and subject property owners.

EXECUTIVE SUMMARY

The following Table 1 summarizes the sewer extension study alternatives and cost opinions. The cost opinions represents the initial probable costs of each alternative. These costs do not include possible downstream Township pump station upgrades or tapping fees and assume the property owners will be responsible for the full costs. However, there are grant programs that could be pursued to offset the costs.

The costs of public sewer extensions can be compared to the costs of replacing an On-Lot Disposal System

(OLDS) at the end of its useful life, assuming there is adequate land area and soils to do so. OLDS replacement alternatives typically include gravity septic systems, sand mounds, at-grade systems, or drip irrigation systems.

Replacement costs for these systems typically range from $15,000-$35,000 depending on several factors such as soil permeability and the type of system to be installed. Gravity septic systems typically fall at the low end of this range while sand mounds, at-grade, and drip irrigation systems are at the high end.

EGMAU21001 November 5, 2021 East Goshen Municipal Authority

Table 1- Cost Opinion Summary Table

Opinion of Alternative Probable Costs Low Pressure Sewer to Barkway Pump $4,618,000 Station Charter Chase Low Pressure Sewer to Hershey's Mill $5,181,000 Pump Station Low Pressure Sewer to Pond View Lane $2,247,000 Brookmont Gravity Sewer with Grinder Pumps to

Pond View Lane $2,554,000

Gravity Sewer with Grinder Pumps to $4,218,000 Goshen Downs Hershey's Mill Pump Station Low Pressure Sewer to Hershey's Mill $4,096,000 Pump Station Millstream Gravity Sewer to Tanglewood Drive $1,833,000 Drive Low Pressure Sewer to Tanglewood Drive $1,427,000

Gravity Sewer with Grinder Pumps to Line $2,103,000 Indian Hills Road and Taylor Avenue Low Pressure Sewer to Line Road $2,017,000 Raewyck Drive Low Pressure Sewer to Taylor Avenue $914,000

Ivy Lane Gravity Sewer to Rossmore Drive $529,000 Low Pressure Sewer to Rossmore Drive $359,000

Old Orchard Gravity Sewer with Grinder Pumps to $617,000 Shandon Place Lane $440,000 Low Pressure Sewer to Shandon Place Joshua Drive Low Pressure Sewer to Culbertson Circle $1,208,000

Great Oak Circle Low Pressure Sewer to Morstein Road $522,000

TOTAL EDUs TOTAL FLOW (at 225 gpd/EDU)

Page 2 Sewer Extension Study

Estimated Cost Properties Per Property

$48,000 98 $53,000

$55,000 41 $63,000

$56,000 76 $54,000

24

$77,000 $60,000

41 $52,000

$50,000 15 $61,000

4 $133,000

$90,000

7 $89,000

$63,000

18 $68,000

8 $66,000 332 74,700 gpd

The probable costs for sewer extension range from $48,000 to $90,000 per property. While this is greater than a typical OLDS replacement cost (if OLDS replacement is feasible), it is important to consider that the life expectancy of an OLDS is 20-30 years, whereas the life expectancy of a public sewer is over 50 years. It should also be noted for a public sewer extension that the property owners are only responsible for the building sewer pipe (from the right-of-way to the house) and grinder pump, where applicable.

2007 ACT 537 PLAN BACKGROUND

In 2007, a series of alternatives were evaluated for Charter Chase and Brookmont to replace existing OLDS's with public sewer. On April 25, 2007, the Township Board of Supervisors voted unanimously to maintain the existing OLDS's, while noting that public sewer offers more protective measures of human health, water

resources, and the natural environment. No action was taken for those two neighborhoods for the following reasons as cited in 2007 from the East Goshen Township Sewage Facilities Management Plan:

1. Existing wastewater disposal needs: Replacement disposal areas have been able to be sited on the properties and sufficient area remains on most properties as they average 1 acre in size each; the neighborhood drinking water supply is from a public water supply system and there are no known

EGMAU21001 East Goshen Municipal Authority

November 5, 2021 Page 3 Sewer Extension Study

water supply wells within the neighborhoods or within the vicinity of the neighborhoods, the risk of illness due to drinking water contamination is minimal; and there are no known violations of either the NPDES discharge criteria or the Clean Streams Law.

2. Operation and maintenance considerations: Property owners are familiar with OLDS operation and maintenance, and the Township ordinance requiring system pumping at least every three years helps ensure systems are properly maintained.

3. Cost-effectiveness: Lowest life-cycle cost of all alternatives considered.

4. Available management and administrative systems: The Township has the existing management and administrative systems needed already in place.

5. Available financing methods: Private financing is available for funding the replacement of an OLDS.

6. Environmental soundness and compliance with natural resource planning and preservation programs:

Continued use of OLDS will not change present "environmental soundness" or compliance with natural resource planning and preservation programs.

DESCRIPTION OF ALTERNATIVES

For each of the ten neighborhoods in this current study, a brief desktop analysis was completed utilizing available GIS topography and imagery to identify alternatives which would allow the neighborhoods to connect to existing public sewer. This study does not include detailed design alternatives such as the ones produced for Brookmont and Charter Chase in 2007 but does provide insight about the sewer alternatives and probable costs.

Each of the following alternatives was evaluated with significant considerations to minimizing the costs to the property owners. For this reason, alternatives requiring new Township pump stations were avoided entirely. Some neighborhoods have more alternatives than others due to the feasibility of implementing gravity vs. low pressure (i.e. grinder pump} systems and connection to the Ridley Creek vs. Chester Creek Service Areas. Each neighborhood has varying topographical features which either support or oppose different sewer systems. Alternatives that were considered but found to be infeasible are not included in the study.

An exhibit for each alternative has been developed to provide a visual along with the description. The exhibits are included as enclosures to this report. Additionally, a Township sewer map is included to display each of the study areas, pump stations and treatment facilities in a regional context.

1. Charter Chase

A. Low Pressure Sewer to Barkway Pump Station (Exhibit 1, Alternative 1): Construct LPS (Low Pressure Sewer} within the neighborhood and out to the Barkway Pump Station. The LPS would be installed within the road rights-of-way (ROWs). The neighborhood's wastewater will discharge to the Chester Creek (West Goshen) Service Area.

B. Low Pressure Sewer to Hadleigh Drive (Exhibit 1, Alternative 2): Construct LPS within the neighborhood and out to Greenhill Road to the existing gravity system east of Hadleigh Drive, which subsequently discharges to Hershey's Mill Pump Station. The LPS would be installed within road ROWs. Under this alternative, the neighborhood's wastewater will discharge to the Ridley Creek Service Area.

• If Goshen Downs was also to be sewered, a sub alternative is that the Charter Chase system could tie into the new sewers from Goshen Downs, which will also run along Greenhill Road.

EGMAU21001 East Goshen Municipal Authority

2. Brookmont

November 5, 2021 Page 4 Sewer Extension Study

A. Low Pressure Sewer to Pond View Lane (Exhibit 2A): Construct LPS within the neighborhood and out to Pond View Lane for discharge into the gravity sewer at Pond View Lane. The LPS would be installed within road ROWs. A short gravity section between Line Road and Pond View Lane would be installed through a wooded easement. The wastewater will discharge to the Ridley Creek Service Area.

8. Gravity Sewer with Grinder Pumps to Pond View Lane (Exhibit 28): Construct gravity sewer within the neighborhood through Line Road, to the existing gravity sewer at Pond View Lane. The gravity sewer

would be installed in both road ROWs and easements with grinder pumps to supplement properties at low elevations. The wastewater will discharge to the Ridley Creek Service Area.

3. Goshen Downs

A. Gravity Sewer with Grinder Pumps to Hadleigh Drive (Exhibit 3A): Construct gravity sewer within the neighborhood through Patterson Circle to the existing gravity sewer at Hadleigh Drive, which subsequently discharges to the Hershey's Mill Pump Station. Areas with low elevation would be supplemented with grinder pumps and LPS lines which would pump to the new gravity mains. Approximately six easements would be needed, including easements from homeowners on Hadleigh

Drive. The wastewater would discharge to the Ridley Creek Service Area.

8. Low Pressure Sewer to Hershey's Mill Pump Station (Exhibit 38): Construct LPS within the neighborhood and out to Greenhill Road to the existing gravity system at Hadleigh Drive, which subsequently discharges to the Hershey's Mill Pump Station. The LPS would be installed entirely in the road ROWs. The wastewater would discharge to the Ridley Creek Service Area.

• There is an alternative possibility of tying into existing sewer on Hadleigh Drive directly from the Patterson Lane cul-de-sac to reduce the length of LPS piping. At least two easements would be needed, including one from a homeowner on Hadleigh Drive.

4. Millstream Drive

A. Gravity Sewer to Tanglewood Drive (Exhibit 4A): Construct gravity sewer within the neighborhood where about half of the properties' sewer would be conveyed along Millstream Drive and along the Tributary to Ridley Creek to an existing sewer at Tanglewood Drive. At least two easements would be needed. The other half of the properties' sewer would travel along Millstream Drive and out to

Hershey Mill Road where it would connect to an existing sewer at Tanglewood Drive. The wastewater would travel to the Hershey's Mill Pump Station and discharge to the Ridley Creek Service Area.

8. Low Pressure Sewer to Tanglewood Drive (Exhibit 48): Construct LPS within the neighborhood and out to Hershey Mill Road to Tanglewood Drive. The LPS would be installed in the road ROWs. The wastewater would travel to Hershey's Mill Pump Station and discharge to the Ridley Creek Service Area.

5. Indian Hills

A. Gravity Sewer with Grinder Pumps to Line Road and Taylor Avenue (Exhibit SA): Construct gravity sewer within the neighborhood where Oneida Lane and Seneca Drive would flow out to Warrior Road and connect to existing sewer at Line Road. Iroquois Lane would be a separate gravity system which would flow west on Warrior Road and connect to existing sewer at Taylor Avenue. The section of

Warrior Road between Iroquois Lane and Seneca Drive would be supplemented by grinder pumps and

EGMAU21001 East Goshen Municipal Authority

November 5, 2021 Page 5 Sewer Extension Study

would also flow out to existing sewer at Taylor Avenue. All sewers would be within road ROWs. The wastewater would discharge to the Ridley Creek Service Area.

8. Low Pressure Sewer to Line Road (Exhibit 58): Construct LPS within the neighborhood out to the existing gravity system at Line Road. The LPS would be installed entirely in the road ROWs. The wastewater would discharge to the Ridley Creek Service Area.

6. Raewyck Drive

A. Low Pressure Sewer to Taylor Avenue (Exhibit 6): Construct LPS within the neighborhood to the existing gravity system at Taylor Avenue. The LPS would be installed in the road ROWs and between at least two parcels via easements in a forested area to connect to Taylor Avenue. The wastewater would discharge to the Ridley Creek Service Area.

7. Ivy Lane

A. Gravity Sewer to Rossmore Drive (Exhibit 7A): Construct gravity sewer within the neighborhood to the existing gravity system at Rossmore Drive. The gravity sewer would be installed in the road ROW and between two parcels at the end of the cul-de-sac to Rossmore Drive via three to five easements, including at least one easement on Rossmore Drive. The wastewater would discharge to the Ridley Creek Service Area.

B. Low Pressure Sewer to Rossmore Drive {Exhibit 78): Construct LPS within the neighborhood to the existing gravity system at Rossmore Drive following the same route, easements, and connection point as Alternative 7 A.

8. Old Orchard Lane

A. Gravity Sewer with Grinder Pomps to Shandon Place (Exhibit BA): Construct gravity sewer within the neighborhood to the existing gravity system at Shandon Place. The gravity sewer would be installed in the road ROWs and via three to five easements between the Old Orchard Lane cul-de-sac and Shandon Lane, including at least one easement on Shandon Lane. Grinder Pumps would be used to supplement houses at low elevations. The wastewater would discharge to the Ridley Creek Service Area.

B. Low Pressure Sewer to Shandon Place (Exhibit 88): Construct LPS within the neighborhood to the existing gravity system at Shandon Place following the same route, easements, and connection point as Alternative 8A.

9. Joshua Drive

A. Low Pressure Sewer to Culbertson Circle (Exhibit 9): Construct LPS within the neighborhood and along Greenhill Road to the existing gravity system at Culbertson Circle. The LPS would be installed in the road ROWs and potentially between multiple parcels via easements on and adjacent to Culbertson Circle. The wastewater would discharge to the Chester Creek Service Area.

• If Charter Chase were to be sewered, a sub alternative is that the Joshua Drive system could tie into the new sewers from Charter Chase at Waterford Road.

EGMAU21001 East Goshen Municipal Authority

10. Great Oak Circle

November 5, 2021 Page 6 Sewer Extension Study

A. Low Pressure Sewer to Morstein Road (Exhibit 10): Construct LPS within the neighborhood, out to the

existing gravity sewer in Morstein Road or Amstel Way. The LPS would be installed in the road ROWs. The wastewater would be conveyed to the Barkway Pump Station and into the Chester Creek Service Area.

• If Charter Chase were to be sewered, a sub alternative is that the Great Oak Circle system could tie into the new sewers from Charter Chase at Waterford Road.

WASTEWATER FACILITIES CAPACITY

Certain existing Township pump stations and wastewater facilities may require upgrades to accommodate these additional flows. As noted previously, costs for such upgrades are not included in Table 1 since determination of such upgrades is beyond the scope of this study. However, to determine if pump stations would have adequate capacity, a brief analysis of the 2019 Chapter 94 Reports was performed to assess the current flows and capacities. The 2019 Reports were used instead of the 2020 Reports due to irregular flows during the height of the COVID-19 pandemic in 2020.

According to the West Goshen Chapter 94 Report, the Barkway Pump Station receives an Average Annual Flow of 10,685 gpd with a Peak Flow of 26,830 gpd. The pump station has a permitted capacity of 86,000 gpd so it would not require an upgrade with the addition of Charter Chase, Joshua Drive, and Great Oak Circle. According to the Ridley Creek Chapter 94 Report, the Hershey's Mill Pump Station receives an Average Annual

Flow of 74,610 gpd with a Peak Flow of 137,596 gpd. The pump station has a permitted capacity of 83,000 gpd. It therefore cannot accommodate significant additional flow so it would require an upgrade with the addition of Goshen Downs and Millstream Drive.

As summarized in the table below, West Goshen would receive an additional 27,900 gpd and Ridley Creek an additional 46,800 gpd from these sewer extensions. Therefore, these sewer extensions would not exceed the

Ridley Creek STP capacity or the West Goshen intermunicipal agreement capacity.

Table 2 - Projected Additional Flow

Properties Added Flow (gpd) Pump Station Service Area (at 225 gpd/EDU) Chester Creek (West Goshen) Service Area

Charter Chase 98 22,050 Barkway West Goshen Joshua Drive 18 4,050 Barkway West Goshen Great Oak Circle 8 1,800 Barkway West Goshen

West Goshen Total 124 27,900 gpd Ridley Creek Service Area

Brookmont 41 9,225 N/A Ridley Creek Goshen Downs 76 17,100 Hershey's Mill Ridley Creek Millstream Drive 24 5,400 Hershey's Mill Ridley Creek Indian Hills 41 9,225 N/A Ridley Creek Raewyck Drive 15 3,375 N/A Ridley Creek Ivy Lane 4 900 N/A Ridley Creek Old Orchard Lane 7 1,575 N/A Ridley Creek

Ridley Creek Total 208 46,800 gpd

EGMAU21001 November 5, 2021 East Goshen Municipal Authority

Page 7 Sewer Extension Study

If you should have any questions, please do not hesitate to contact me.

Sincerely,

PENNONI ASSOCIATES INC .

/rmf

. Ellis, PE

Engineer

Enclosures: Exhibit 1- Charter Chase (Low Pressure Sewer to Barkway / Hershey's Mill Pump Station) Exhibit 2A -Brookmont (Low Pressure Sewer to Pond View Lane) Exhibit 2B -Brookmont (Gravity Service+ Grinder Pumps to Pond View Lane) Exhibit 3A - Goshen Downs (Gravity Service+ Grinder Pumps to Hadleigh Drive) Exhibit 3B - Goshen Downs (Low Pressure Sewer to Hershey's Mill Pump Station) Exhibit 4A - Millstream Drive (Gravity Sewer to Tanglewood Drive) Exhibit 4B -Millstream Drive (Low Pressure Sewer to Tanglewood Drive) Exhibit SA -Indian Hills (Gravity Service+ Grinder Pumps to Line Road and Taylor Avenue)

Exhibit SB - Indian Hills (Low Pressure Sewer to Line Road) Exhibit 6 - Raewyck Drive (Low Pressure Sewer to Taylor Avenue) Exhibit 7A-Ivy Lane (Gravity Sewer to Rossmore Drive) Exhibit 7B -Ivy Lane (Low Pressure Sewer to Rossmore Drive) Exhibit 8A -Old Orchard Lane {Gravity Sewer+ Grinder Pumps to Shandon Place) Exhibit 8B-Old Orchard Lane (Low Pressure Sewer to Shandon Place) Exhibit 9 -Joshua Drive (Low Pressure Sewer to Culbertson Circle) Exhibit 10 - Great Oak Circle (Low Pressure Sewer to Morstein Road) Exhibit 11 -East Goshen Study Areas Map Cost Opinion - Charter Chase (Low Pressure Sewer to Barkway Pump Station) Cost Opinion - Charter Chase (Low Pressure Sewer to Hershey's Mill Pump Station) Cost Opinion - Brookmont {Low Pressure Sewer to Pond View Lane) Cost Opinion - Brookmont (Gravity Service+ Grinder Pumps to Pond View Lane) Cost Opinion - Goshen Downs (Gravity Service+ Grinder Pumps to Hadleigh Drive) Cost Opinion -Goshen Downs (Low Pressure Sewer to Hershey's Mill Pump Station) Cost Opinion - Millstream Drive (Gravity Sewer to Tanglewood Drive) Cost Opinion -Millstream Drive (Low Pressure Sewer to Tanglewood Drive) Cost Opinion - Indian Hills (Gravity Service+ Grinder Pumps to Line Road and Taylor Avenue) Cost Opinion - Indian Hills (Low Pressure Sewer to Line Road) Cost Opinion - Raewyck Drive {Low Pressure Sewer to Taylor Avenue) Cost Opinion - Ivy Lane {Gravity Sewer to Rossmore Drive) Cost Opinion -Ivy Lane {Low Pressure Sewer to Rossmore Drive) Cost Opinion -Old Orchard Lane (Gravity Sewer+ Grinder Pumps to Shandon Place) Cost Opinion -Old Orchard Lane {Low Pressure Sewer to Shandon Place) Cost Opinion -Joshua Drive (Low Pressure Sewer to Culbertson Circle) Cost Opinion - Great Oak Circle (Low Pressure Sewer to Morstein Road)

EGMAU21001 East Goshen Municipal Authority

cc: Derek Davis, Township Manager Dave Ware, Finance Director Mike Lynch, Supervisor

November 5, 2021 Page 8 Sewer Extension Study

U:\Accounts\EGMAU\EGMAU21001 - 2021 General Services\DOC PREP\Sewer Extension Study\Sewer Extension Study Letter:

v!. .. ·

·\ I

[

, ---".·

'": ,:\ .

'. -

,· :. _ _ .. ,

'\• ... \i ·,

;...:., - Q) C: C: 0 co E _J 3: 0 Q) > ---o <( C: NO - a.. ·- 0 :e- .c: Cf) >< a.. w_J

-'"l '

:'),/

b\ .

-. ;\ . ..,. ·<·

Grinder Pum? Connections

Lf)' (Y)' ,LrJ ! (:)'

!

V-,' \\ \ \ 1 Exhibit 2B (Brookmont): Gravity + Grinder Pumps to Pond View Lane

[Map of parcel boundaries, roadways, and proposed sewer lines with flow direction arrows, green nodes, and dashed/solid green lines labeled LPS.]

Exhibit 3A (Goshen Downs):
Gravity + LPS to Hadleigh Drive

Map labels: LPS

[Map of parcel boundaries, roadways, and proposed low-pressure sewer lines with flow direction arrows, green nodes, and green lines labeled LPS.]

Exhibit 3B (Goshen Downs):
LPS to Hadleigh Drive

Map labels: LPS

Exhibit 4A (Millstream Drive): Gravity Sewer to Tanglewood Drive

'-''-' '

....--..

(]) >

·;:: (]) 0 > E·c ro o

(]) "'O s..... 0 en o= 3: JQ ---- 0) al C

'q" ..., ■- 0 .c ..... :c (/) >< a.. w _J

Exhibit SA (Indian Hills): Gravity + Grinder Pumps to Line Road and Taylor Avenue.

[ l_J_ II L\j(_ ""111111111

-

Cf)

I

"O ·- ro "O 0 E -m Lt) ·-

■- 0 .c +J :E C/) >< a.. W-1

. . ..-..

Q) > ·c 0 Q) ::J (..) C >, Q)

ro s.... 0::: 0 .._ >, <D ro .., r

■- 0 .c ...... :c Cl) >< a.. w _J

[Map of parcel boundaries, roadways, and proposed gravity sewer line with flow direction arrow, green nodes, and dashed/solid green lines.]

Exhibit 7A (Ivy Lane): Gravity Sewer to Rossmore Drive.

. Q) . . > .-. __

Q) s.... C: 0 ro © .....J s.... o > E (/) cc (/) " & ..., ■- 0 .c ....., ■-.c: (f) >< CL w .....J

/i'_

Exhibit BA (Old Orchard Lane): Gravity Sewer+ Grinder Pumps to Shandon Place.

Exhibit 8B (Old Orchard Lane): LPS to Shandon Place.

Q) Q) - > ·- ·- "- () 0 CO C

:J .c t en a, 0 ..c -, - ._,, :J en O

:t::o .0.....,

■- Cl) .r:. 0.. ...J

Exhibit 10 (Great Oak Circle): Low

Pressure Sewer to Morstein Road

EAST GOSHEN STUDY AREAS

MAP

Legend D Study Areas

- PUMP STATION D SEWAGE TREATMENT PLANT

SANITARY MANHOLES

PERMANENT METERS

PORTABLE METERS (2020)

-- SANITARY SEWER

-- FORCEMAIN

-- TOWNSHIP BOUNDARY

0Parcels D PONDS & LAKES

-- RIVERS D EAST WHITELAND SERVICE AREA D HERSHEY'S MILL SERVICE AREA D RIDLEY CREEK SERVICE AREA D WEST GOSHEN SERVICE AREA D WESTTOWN SERVICE AREA

,p;;;;;;;,;;j, =----==

';...-=='5·'";;..-==='·;; "';..---....;•.·1

1 lndi • 1.0001 .. 1

Cost Opinion - Charter Chase (Low Pressure Sewer to Barkway Pump Station) Cost Item Unit Unit Price Quantity Cost Low Pressure Sewer LF $125.00 9300 $ 1,162,500 Driveway Repaving SY $80.00 408 $ 32,640 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 5800 $ 580,000 Lawn Restoration LS $5,000.00 1 $ 5,000 Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000 Stream Crossing LS $20,000.00 2 $ 40,000 Survey and Layout LS $10,000.00 1 $ 10,000 Grinder Pump and Installation EA $15,000.00 98 $ 1,470,000 Subtotal Construction Cost $ 3,330,140 Mobilization/Demobilization % 6% $ 200,000 Contingency % 20% $ 667,000 Construction Cost Opinion $ 4,197,140 Leg a I/ Adm i nistrative/Engi nee ring % 10% $ 420,000 Opinion of Probable Project Cost for Public Improvements $ 4,617,140 Cost of Public Improvements per Property 98 $ 47,200.00 Opinion of Probable Project Cost for each Property Owner $ 48,000.00

Cost Opinion - Charter Chase (Low Pressure Sewer to Hershey's Mill Pump Station) Cost Item Unit Unit Price Quantity Cost Low Pressure Sewer LF $125.00 11300 $ 1,412,500 Driveway Repaving SY $80.00 440 $ 35,200 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 7133 $ 713,333 Lawn Restoration LS $5,000.00 1 $ 5,000 Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000 Stream Crossing LS $20,000.00 3 $ 60,000 Survey and Layout LS $10,000.00 1 $ 10,000 Grinder Pump EA $15,000.00 98 $ 1,470,000

Subtotal Construction Cost $ 3,736,033 Mobilization/Demobilization % 6% $ 225,000 Contingency % 20% $ 748,000 Construction Cost Opinion $ 4,709,033 Leg a I/ Adm i nistrative/Engi neeri ng % 10% $ 471,000 Opinion of Probable Project Cost for Public Improvements $ 5,180,033 Cost of Public Improvements per Property 98 $ 52,900.00 Opinion of Probable Project Cost for each Property Owner $ 53,000.00

Cost Opinion - Brookmont (Low Pressure Sewer to Pond View Lane) Cost Item Unit Unit Price Quantity Cost Low Pressure Sewer LF $125.00 4825 $ 603,125 Driveway Repaving SY $80.00 184 $ 14,720 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 3217 $ 321,667 Lawn Restoration LS $5,000.00 1 $ 5,000 Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000 Stream Crossing LS $20,000.00 1 $ 20,000 Survey and Layout LS $10,000.00 1 $ 10,000 Grinder Pump and Installation EA $15,000.00 41 $ 615,000 Subtotal Construction Cost $ 1,619,512 Mobilization/Demobilization % 6% $ 98,000 Contingency % 20% $ 324,000 Construction Cost Opinion $ 2,041,512 Leg a I/ Administrative/Engineering % 10% $ 205,000 Opinion of Probable Project Cost for Public Improvements $ 2,246,512 Cost of Public Improvements per Property

41 $ 54,800.00 Opinion of Probable Project Cost for each Property Owner $ 55,000.00

Cost Opinion - Brookmont (Gravity Service+ Grinder Pumps to Pond View Lane) Cost Item Unit Unit Price Quantity Cost

(Gravity Sewer) Install 10" Sanitary Pipe LF $250.00 4349 $ 1,087,250

Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 3217 $ 321,667

Driveway Repaving SY $80.00 184 $ 14,720

Survey and Layout LS $10,000.00 1 $ 10,000

Lawn Restoration LS $5,000.00 1 $ 5,000

Erosion and Sediment Control LS $5,000.00 1 $ 5,000

Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000

Stream Crossing LS $20,000.00 1 $ 20,000

Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000

Manhole EA $7,000.00 15 $ 105,000

Grinder Pump EA $15,000.00 9 $ 135,000

Lateral Installation EA $3,500.00 32 $ 112,000

Subtotal Construction Cost $ 1,840,637

Mobilization/Demobilization % 6% $ 111,000

Contingency % 20% $ 369,000

Construction Cost Opinion $ 2,320,637

Leg a I/ Administrative/Engineering % 10% $ 233,000

Opinion of Probable Project Cost for Public Improvements $ 2,553,637

Cost of Public Improvements per Property 41 $ 62,300.00

Opinion of Probable Project Cost for each Property Owner $ 63,000.00

Cost Opinion - Goshen Downs (Gravity Service+ Grinder Pumps to Hadleigh Drive) Cost Item Unit Unit Price Quantity Cost Low Pressure Sewer LF $125.00 3618 $ 452,250 Gravity Sewer - 10" Sanitary Pipe LF $250.00 5386 $ 1,346,500 Driveway Repaving SY $80.00 336 $ 26,880 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 4363 $ 436,333 Survey and Layout LS $10,000.00 1 $ 10,000 Lawn Restoration LS $5,000.00 1 $ 5,000 Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000 Grinder Pump and Installation EA $15,000.00 31 $ 465,000 Lateral Installation EA $3,500.00 45 $ 157,500 Manhole EA $7,000.00 16 $ 112,000 Subtotal Construction Cost $ 3,041,463 Mobilization/Demobilization % 6% $ 183,000 Contingency % 20% $ 609,000 Construction Cost Opinion $ 3,833,463 Legal/ Ad min istrative/Engi neeri ng % 10% $ 384,000 Opinion of Probable Project Cost for Public Improvements $ 4,217,463 Cost of Public Improvements per Property 76 $ 55,500.00 Opinion of Probable Project Cost for each Property Owner $ 56,000.00

Cost Opinion - Goshen Downs (Low Pressure Sewer to Hershey's Mill Pump Station) Cost Item Unit Unit Price Quantity Cost Low Pressure Sewer LF $125.00 9089 $ 1,136,125 Driveway Repaving SY $80.00 336 $ 26,880 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 6059 $ 605,933 Lawn Restoration LS $5,000.00 1 $ 5,000 Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000 Survey and Layout LS $10,000.00 1 $ 10,000 Grinder Pump and Installation EA $15,000.00 76 $ 1,140,000 Subtotal Construction Cost $ 2,953,938 Mobilization/Demobilization % 6% $ 178,000 Contingency % 20% $ 591,000 Construction Cost Opinion $ 3,722,938 Leg a I/ Adm in istrative/Engineeri ng % 10% $ 373,000 Opinion of Probable Project Cost for Public Improvements $ 4,095,938 Cost of Public Improvements per Property 76 $ 53,900.00 Opinion of Probable Project Cost for each Property Owner $ 54,000.00

Cost Opinion - Millstream Drive (Gravity Sewer to Tanglewood Drive) Cost Item Unit Unit Price Quantity Cost

Gravity Sewer - 10" Sanitary Pipe LF $250.00 3560 $ 890,000 Driveway Repaving SY $80.00 88 $ 7,040 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 2040 $ 204,000 Lawn Restoration LS $5,000.00 1 $ 5,000 Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Stream Crossing LS $20,000.00 1 $ 20,000 Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000 Survey and Layout LS $10,000.00 1 $ 10,000 Lateral Installation EA $3,500.00 24 $ 84,000 Manhole EA $7,000.00 10 $ 70,000

Subtotal Construction Cost $ 1,320,040 Mobilization/Demobilization % 6% $ 80,000 Contingency % 20% $ 265,000 Construction Cost Opinion $ 1,665,040 Legal/ Ad mi nistrative/Enginee ring % 10% $ 167,000 Opinion of Probable Project Cost for Public Improvements $ 1,832,040

Cost of Public Improvements per Property 24 $ 76,400 Opinion of Probable Project Cost for each Property Owner $ 77,000.00

Cost Opinion - Millstream Drive (Low Pressure Sewer to Tanglewood Drive) Cost Item Unit Unit Price Quantity Cost Low Pressure Sewer LF $125.00 3110 $ 388,750 Driveway Repaving SY $80.00 88 $ 7,040 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 2073 $ 207,333 Lawn Restoration LS $5,000.00 1 $ 5,000 Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Stream Crossing LS $20,000.00 1 $ 20,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000 Survey and Layout LS $10,000.00 1 $ 10,000 Grinder Pump and Installation EA $15,000.00 24 $ 360,000 Subtotal Construction Cost $ 1,028,123 Mobilization/Demobilization % 6% $ 62,000 Contingency % 20% $ 206,000 Construction Cost Opinion $ 1,296,123 Leg a I/ Administrative/Engineering % 10% $ 130,000 Opinion of Probable Project Cost for Public Improvements $ 1,426,123 Cost of Public Improvements per Property 24 $ 59,500 Opinion of Probable Project Cost for each Property Owner $ 60,000.00

Cost Opinion - Indian Hills {Gravity Service+ Grinder Pumps to Line Road and Taylor Avenue) Cost Item Unit Unit Price Quantity Cost Gravity Sewer - 10" Sanitary Pipe LF $250.00 3320 $ 830,000 Low Pressure Sewer LF $125.00 500 $ 62,500 Driveway Repaving SY $80.00 168 $ 13,440 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 2547 $ 254,667 Lawn Restoration LS $5,000.00 1 $ 5,000 Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000 Stream Crossing LS $20,000.00 1 $ 20,000 Survey and Layout LS $10,000.00 1 $ 10,000 Lateral Installation EA $3,500.00 35 $ 122,500 Manhole EA $7,000.00 11 $ 77,000 Grinder Pump and Installation EA $15,000.00 6 $ 90,000

Subtotal Construction Cost $ 1,515,107 Mobilization/Demobilization % 6% $ 91,000 Contingency % 20% $ 304,000 Construction Cost Opinion $ 1,910,107 Legal/ Ad min istrative/Engineeri ng I % 10% $ 192,000 Opinion of Probable Project Cost for Public Improvements $ 2,102,107 Cost of Public Improvements per Property 41 $ 51,300 Opinion of Probable Project Cost for each Property Owner $ 52,000.00

Cost Opinion - Indian Hills {Low Pressure Sewer to Line Road) Cost Item Unit Unit Price Quantity Cost

Low Pressure Sewer LF $125.00 4070 $ 508,750 Driveway Repaving SY $80.00 168 $ 13,440 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 2713 $ 271,333

Lawn Restoration LS $5,000.00 1 $ 5,000

Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000

Survey and Layout LS $10,000.00 1 $ 10,000 Grinder Pump Station EA $15,000.00 41 $ 615,000

Subtotal Construction Cost $ 1,453,523 Mobilization/Demobilization % 6% $ 88,000

Contingency % 20% $ 291,000

Construction Cost Opinion $ 1,832,523

Legal/ Ad min istrative/Engi neeri ng % 10% $ 184,000 Opinion of Probable Project Cost for Public Improvements $ 2,016,523

Cost of Public Improvements per Property 41 $ 49,200 Opinion of Probable Project Cost for each Property Owner $ 50,000.00

Cost Opinion - Raewyck Drive (Low Pressure Sewer to Taylor Avenue) Cost Item Unit Unit Price Quantity Cost Low Pressure Sewer LF $125.00 2100 $ 262,500 Driveway Repaving SY $80.00 48 $ 3,840 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 933 $ 93,333 Lawn Restoration LS $5,000.00 1 $ 5,000 Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000 Survey and Layout LS $10,000.00 1 $ 10,000 Grinder Pump and Installation EA $15,000.00 15 $ 225,000

Subtotal Construction Cost $ 629,673 Mobilization/Demobilization % 6% $ 38,000 Contingency % 20% $ 126,000 Construction Cost Opinion $ 793,673 Leg a I/ Admi nistrative/Engi neeri ng % 15% $ 120,000 Opinion of Probable Project Cost for Public Improvements $ 913,673 Cost of Public Improvements per Property 15 $ 60,912 Opinion of Probable Project Cost for each Property Owner $ 61,000.00

Cost Opinion - Ivy Lane ( Gravity Sewer to Rossmore Drive) Cost Item Unit Unit Price Quantity Cost

Gravity Sewer - 10" Sanitary Pipe LF $250.00 930 $ 232,500

Driveway Repaving SY $80.00 32 $ 2,560

Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 227 $ 22,667

Lawn Restoration LS $5,000.00 1 $ 5,000

Erosion and Sediment Control LS $5,000.00 1 $ 5,000

Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000

Stream Crossing LS $20,000.00 1 $ 20,000

Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000

Survey and Layout LS $10,000.00 1 $ 10,000

Lateral Installation EA $3,500.00 4 $ 14,000

Manhole EA $7,000.00 4 $ 28,000

Subtotal Construction Cost $ 364,727

Mobilization/Demobilization % 6% $ 22,000

Contingency % 20% $ 73,000

Construction Cost Opinion $ 459,727

Legal/ Ad min istrative/Enginee ring % 15% $ 69,000

Opinion of Probable Project Cost for Public Improvements $ 528,727

Cost of Public Improvements per Property 4 $ 132,200

Opinion of Probable Project Cost for each Property Owner $ 133,000.00

Cost Opinion - Ivy Lane (Low Pressure Sewer to Rossmore Drive) Cost Item Unit Unit Price Quantity Cost Low Pressure Sewer LF $125.00 930 $ 116,250 Driveway Repaving SY $80.00 32 $ 2,560 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 227 $ 22,667 Lawn Restoration LS $5,000.00 1 $ 5,000 Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000 Survey and Layout LS $10,000.00 1 $ 10,000 Grinder Pump and Installation EA $15,000.00 4 $ 60,000

Subtotal Construction Cost $ 246,477 Mobilization/Demobilization % 6% $ 15,000 Contingency % 20% $ 50,000 Construction Cost Opinion $ 311,477 Leg a I/ Adm in istrative/Engi neeri ng % 15% $ 47,000 Opinion of Probable Project Cost for Public Improvements $ 358,477 Cost of Public Improvements per Property 4 $ 89,619 Opinion of Probable Project Cost for each Property Owner $ 90,000.00

Cost Opinion - Old Orchard Lane (Gravity Service+ Grinder Pumps to Shandon Place) Cost Item Unit Unit Price Quantity Cost Gravity Sewer - 10" Sanitary Pipe LF $250.00 1000 $ 250,000 Driveway Repaving SY $80.00 24 $ 1,920 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 247 $ 24,667 Lawn Restoration LS $5,000.00 1 $ 5,000 Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000 Stream Crossing LS $20,000.00 1 $ 20,000 Survey and Layout LS $10,000.00 1 $ 10,000 Lateral Installation EA $3,500.00 5 $ 17,500 Manhole EA $7,000.00 5 $ 35,000 Grinder Pump and Installation EA $15,000.00 2 $ 30,000

Subtotal Construction Cost $ 424,087 Mobilization/Demobilization % 6% $ 26,000 Contingency % 20% $ 85,000 Construction Cost Opinion $ 535,087 Legal/ Administrative/Engineering % 15% $ 81,000 Opinion of Probable Project Cost for Public Improvements $ 616,087

Cost of Public Improvements per Property 7 $ 88,100 Opinion of Probable Project Cost for each Property Owner $ 89,000.00

Cost Opinion - Old Orchard Lane (Low Pressure Sewer to Shandon Place} Cost Item Unit Unit Price Quantity Cost Low Pressure Sewer LF $125.00 1000 $ 125,000 Driveway Repaving SY $80.00 24 $ 1,920 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 247 $ 24,667 Lawn Restoration LS $5,000.00 1 $ 5,000 Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000 Survey and Layout LS $10,000.00 1 $ 10,000 Grinder Pump and Installation EA $15,000.00 7 $ 105,000 Subtotal Construction Cost $ 301,587 Mobilization/Demobilization % 6% $ 19,000 Contingency % 20% $ 61,000 Construction Cost Opinion $ 381,587 Legal/ Administrative/Engineering % 15% $ 58,000 Opinion of Probable Project Cost for Public Improvements $ 439,587 Cost of Public Improvements per Property 7 $ 62,798 Opinion of Probable Project Cost for each Property Owner $ 63,000.00

Cost Opinion - Joshua Drive (Low Pressure Sewer to Culbertson Circle) Cost Item Unit Unit Price Quantity Cost Low Pressure Sewer LF $125.00 2865 $ 358,125 Driveway Repaving SY $80.00 80 $ 6,400 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 1533 $ 153,333 Lawn Restoration LS $5,000.00 1 $ 5,000 Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Tree Removal and Site Preparation LS $15,000.00 1 $ 15,000 Survey and Layout LS $10,000.00 1 $ 10,000 Grinder Pump and Installation EA $15,000.00 18 $ 270,000 Subtotal Construction Cost $ 832,858 Mobilization/Demobilization % 6% $ 50,000 Contingency % 20% $ 167,000 Construction Cost Opinion $ 1,049,858 Leg a I/ Adm i nistrative/Engi neeri ng % 15% $ 158,000 Opinion of Probable Project Cost for Public Improvements $ 1,207,858 Cost of Public Improvements per Property 18 $ 67,103 Opinion of Probable Project Cost for each Property Owner $ 68,000.00

Cost Opinion - Great Oak Circle (Low Pressure Sewer to Morstein Road) Cost Item Unit Unit Price Quantity Cost Low Pressure Sewer LF $125.00 1000 $ 125,000 Driveway Repaving SY $80.00 32 $ 2,560 Roadway Restoration (5" Base Course, 1.5" Wearing Course) SY $100.00 667 $ 66,667 Lawn Restoration LS $5,000.00 1 $ 5,000 Erosion and Sediment Control LS $5,000.00 1 $ 5,000 Temporary Facilities/Traffic Control LS $10,000.00 1 $ 10,000 Tree Removal and Site Preparation LS $15,000.00 1 $ lS,000 Survey and Layout LS $10,000.00 1 $ 10,000 Grinder Pump and Installation EA $15,000.00 8 $ 120,000 Subtotal Construction Cost $ 359,227 Mobilization/Demobilization % 6% $ 22,000 Contingency % 20% $ 72,000 Construction Cost Opinion $ 453,227 Legal/ Administrative/Engineering % 15% $ 68,000 Opinion of Probable Project Cost for Public Improvements $ 521,227 Cost of Public Improvements per Property 8 $ 65,153 Opinion of Probable Project Cost for each Property Owner $ 66,000.00

610-692-7171

www.eastgoshen.org BOARD OF SUPERVISORS

EAST GOSHEN TOWNSHIP

CHESTER COUNTY 1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

October 28, 2021

Dear Property Owner:

The purpose of this letter is to inform you that the Township has received a Zoning Hearing Board application from Imperial Marble and Granite located at 1311 West Chester Pike, West Chester, PA 19380. The applicant is requesting dimensional relief from the sign ordinance regulating signs in the Community Commercial (C-1) zoning district. The applicant is also asking for a variance from the definition of "Sign" in the zoning ordinance.

The ordinance section subject to the requested relief is §240-6 Definitions (Sign), and §240- 22P(4) requirements for wall signs.

Pursuant to Township policy, property owners within 1000 feet of the subject property are notified of Zoning Hearing Board application submissions and the meeting date when the application will be discussed.

This Zoning Hearing Board Application will be reviewed on:

• November 3, 2021 - Planning Commission meeting (7:00 PM) • November 16, 2021 - Board of Supervisors (7:00 PM) • December 14, 2021- Zoning Hearing (7:30 PM)

Meetings and hearings are held at the Township Building, are open to the public, and subject to change without further written notice by the Township. The application is available for review at the Township building during normal business hours. Please give me a call at or email me at mgordon@eastgoshen.org if you have any questions or need additional information.

Sincerely,

Mark A. Gordon Township Zoning Officer

Cc: All Township Authorities, Boards and Commissions

Want more information about the latest news in the Township and surrounding area? East Goshen Township and Chester County offer two valuable resources to stay informed about important local issues. East Goshen communicates information by email about all Township news through Constant Contact. To sign up, go to www.eastgoshen.org and click the "E-notification & Emergency Alert" button on the left side of the homepage. Chester County offers an emergency notification system called ReadyChesco, which notifies residents about public safety emergencies in the area via text, email and cell phone call. Signing up is a great way to keep you and your loved ones safe when disaster strikes. Visit www.readychesco.org to sign up today!

F:\Data\Shared Data\Property Management\53-6\53-6-61.1 (1311 West Chester Pike)\ZHB Application\1000 foot letter for ZHB app 10272021.doc

FYI Virtual

Conference

Schedule

_ Tuesday,...Nmrembell.16--'---

• Caffellilated Conversations - Open Networking • Ethics (1 l?DH) • Improving Revenue Collections During a Panden'\Jc - Lessons Learned • Strategies fof Implementing Act 43 Imposing New Requirements for Millti-FafJlllY Billings {1 POiit) • Ask the Managers Panel

Thursday, Nouember 18

• Caffelmated Conversations - Open Networking • Redevelopimg a Resilient City • How Capital lrnprovement Plans Can Help Authorities Survive COVID-19 and Other Finalileial Challer,iges (1 PDH` • Tell it to the J111dge (1 CLE) • Ask the Solicitor Panel

Visit our website

for the full

schedule

WWW.MUN IC I PA LAUTH ORITI ES. 0 RG

Registration

Member Pricing: □$175

Non-Member Pricing: □$250

Not able to attend?

□Check, made payable to PMM is enclosed. □Visa □Mastercard □Discover

Credit Card:

Register to receive the recording!

Card No.:

For more information & updates,

please visit the website at: www.municipalauthorltles.org/

Exp.: ____ _

Security code: ____ _

Name: ____________________________ _ Authority/Firm: ________________________ _ Address: __________________________ _

City, State & Zip: ______________ Phone: ______ _

E-mail: ___________________________ _

Name: ----------------------------- Authority/Firm:------------------------­ Address: -----------------------------

City, State & Zip: ______________ Phone: ______ _ E-mail:-----------------------------

Name: ____________________________ _ Authority/Firm: ________________________ _ Address: ____________________________ _

City, State & Zip: ______________ Phone: ______ _

E-mail: ___________________________ _

Please note: Agenda is subject to change .

.,;a Rl'II PMM · 1000 North Front Street, Suite 401 · Wormleysburg, PA 17043 .. II lW 717.737.7655 · 717.737.8431 (fax)· info@municipalauthorities.org • www.municipalauthorities.org

TheAuthorities

f'ENNKYLVAMIA MUN1C1PtLL AUTI tORITIES /J S:.OCIAI ION

Date & Time:

Location:

Topics:

RSVP:

Menu:

PMAA REGION 1 DINNER MEETING

Thursday, November 18, 2021 6:30 pm Cocktails & Hors d'oeuvres- 7:30 pm Dinner

Presidential Caterers of Distinction 2910 DeKalb Pike (Route 202), East Norriton, PA 19401-1596

Update on Legislative Issues affecting Authorities PMAA Staff via virtual connection

Update on-Water & Sewer Industry.:.. iilTERN PROGRAM Shannon Drosnock, Montgomery Township Sewer Authority

Cyber Security

Update on Cyber Security Programs available through Cybersecurity and Infrastructure Agency (CISA} Updates on Legal Issues Steve Hann

Closing Comments- Michael Sullivan

Monday, November 1, 2021 - PLEASE.

$50.00 per person**

Buffet including Baby Spinach Salad, Carving Display of Roast Beef, Roasted Chicken Saltimbocca, Grilled Mahi Mahi, Pasta Primavera and Ice Cream

Please return this reservation form with payment to: Attn: Ritajean Joyce North Wales Water Authority, P.O. Box 1339, North Wales PA 19454

PLEASE MAKE ALL CHECKS PAYABLE TO 11PMAA REGION 1"' - For-additionaHnformation-or-assistance-please contact-Ritajean-Joyce-at-(nS-}^-69_ ... 4836-x--11.47

or by email at: riovce@nwwater.com

Authority (or Company) Name: _________________________ _

Contact Information: Email. ____________ Phone. _________ _

Guests Attending:

** IF YOU PREVIOUSLY SENT IN DINNER MONIES FOR THE 2020 DINNER MEETING THAT WAS CANCELLED. PLEASE CONTACT RITAJEAN **

A

TheA tho ities

1'1:.NNSYLVANIA MUNIOPAL AU I HORfflES AS SOCIA I ION

o y ha\\fe c py of e 2 2 -2022 M cpa ity rtes Act?

A complete edition of the law governing

municipal

Includes all amendments, related laws and

-- -- au-therm-es- -

a subject index _L

+-for--easy-roference - -

Updated every

two years corresponding to the completion of ---the-legis-1-ative

session

TheAuthorities

PENNWI V;\NiA MUtHCtP111 /\UHiORITIES 1\SSOCl:TfON

Complete the order form and return it, with payment, to:

e PMAA 1000 N. Front Street, Suite 401 Wormleysburg, PA 17043

• i nfo@mu n ici palautho rities.org

• Fax: 717.737.8431

Order Form

Name·------------------------------------------------------------

Authority /Firm: ------------------------------------------------------

Address·-----------------------------------------------------------

City, State, Zip:---------------------------- Phone: __________________ _

Number of copies (between 1 - 4): __ x$29=$ __ _

Number of copies (5 or more): __ x$25=$ __ _

A check in the amount of$ is included. ---

Exp: ___ _ Security Code: ___ _

WWW.MUN ICI PA LAUTH ORITI ES.ORG

Types of payment accepted

Checks 1 payable to

PMAA

accepted:

Visa, MC Discover

Virtual

Conference

. . - . .

Earn 1 CLE credit.

. • ,. ..,,'!' ',r.. • .

NOVEMBER16 NOVEMBER17 NOVEMBER18

· 8:30AM • 8:30AM 8:30AM . ·

.

· · ·

ij

·l .. ·.•_,

.

' - .-. . ·J .

':'. .J:.. ·..... ' ' : . ' • ..!· . " . .· -'-... •. /:..' !- , .... . "#\-;$;;:tfj).-_"-j -· -.:.,- - .. 1:7:-ti::.rl,,. 1 ::_.:_ ·_ -: .•• .! .. ., . . .. ,.:,i..f"'··'.·:v.,.:;;q. l'# REGISTER-,TODA'Y.iiONL•INE:··: WWW. M_ UN IC I PALA.UTH OR (r1'.ES%ORG/

. _,;_ .. ,.·, • ·t:} .:· .. • .:-:-:

Registration

Member Pricing: □$175

Non-Member Pricing: □$250

Not able to attend?

□Check, made payable to PMM is enclosed. □Visa □Mastercard □Discover

Credit Card:

Register to receive the recording!

Name:

For more information & updates,

please visit the website at: www.municipalauthorlties.org/

Card No.:

Exp.: ____ _

Security code: ____ _

------------------------------ Authority/Firm:------------------------­ Address:------------------------------

City, State & Zip: ______________ Phone: ______ _

E-mail: ___ -________________________ _

Name: _____________________________ _ Authority/Firm: ________________________ _ Address: ___________________________ _

City, State & Zip: ____________ _ Phone: _______ _

E-mail: ____________________________ _

Name: _____________________________ _ Authority/Firm: ________________________ _ Address: ____________________________ _

City, State & Zip: ______________ Phone: ______ _ E-mail: ____________________________ _

Please note: Agenda is subject to change.

a:I R'II PMAA · 1000 North Front Street, Suite 401 · Wormleysburg, PA 17043 a II U1J 717.737.7655 · 717.737.8431 (fax)· info@municipalauthoritles.org • www.municipalauthorities.org