Municipal Authority

The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.

 

The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.

  • Five members, serving five-year terms
  • Meetings are on the 2nd Monday of the month at 7:00 P.M.
  • All township meetings are held at the Township Building and open to the public
Authority Members Term Expiration Date
Kevin Cummings, Chairman 2026
John Stipe, Vice Chairman
2029
Dana Pizzarro, Secretary 2026
Sean Ellsworth, Assistant Secretary/Treasurer 2028
Walter Wujcik, Treasurer 2028
Pennoni Associates, Engineer
Patrick M. McKenna, Esq.
Peter Hicks, BoS Liaison
Kevin Miller, Staff Liaison

 

Municipal Authority Genealogy

Audits

Documents

Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.

F:\Data\Shared Data\Agendas\Municipal Authority Agendas\2023 MA Agendas\10-16-23\Agenda Materials\10-16-2023 Agenda.doc

EAST GOSHEN MUNICIPAL AUTHORITY

October 16, 2023

7:00

1. CALL TO ORDER/PLEDGE OF ALLEGIANCE/MOMENT OF SILENCE • Ask if anyone will be taping the meeting 2. CHAIRMAN’S REPORT/OTHER MEMBERS’ REPORTS

3. SEWER REPORTS • Director of Public Work’s Report • Pennoni Engineer’s Report • Big Fish Environmental Report 4. APPROVAL OF MINUTES • September 11, 2023 5. APPROVAL OF INVOICES • Pennoni Invoice #1190712 $464.50 • Pennoni Invoice #1190713 $1,716.50 • Pennoni Invoice #1190714 $10,769.75 • Pennoni Invoice #1190715 $13,951.25 • Gawthrop Greenwood Invoice #277578 $1,146.00 • Gawthrop Greenwood Invoice #279612 $658.50 • Mainline Concrete & Supply Invoice #525430 $159.75 (paid) • Gap Power Invoice #1870216 $2977.97 (paid) 6. LIAISON REPORTS 7. FINANCIAL REPORTS a. September 2023

8. OLD BUSINESS

F:\Data\Shared Data\Agendas\Municipal Authority Agendas\2023 MA Agendas\10-16-23\Agenda Materials\10-16-2023 Agenda.doc

9. 2023 Goals: Goal Status

Ridley Creek plant compliance

January, February, March, April, May, June, July, August, & September were in compliance and met all requirements.

Continue to implement infiltration and inflow for the sewer system

Ongoing.

RCSTP UV Disinfection System

Waiting for pumps to be delivered.

10. NEW BUSINESS • Approval of 2024 fees for legal services • TR Moser: Miller Property / Hershey Mill Pump Station 11. CAPACITY REQUESTS

12. ANY OTHER MATTER 13. CORRESPONDENCE AND REPORTS OF INTEREST 14. PUBLIC COMMENT 15. ADJOURNMENT

EAST GOSHEN MUNICIPAL AUTHORITY

EAST GOSHEN TOWNSHIP

1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199 610-692-7171

To: Municipal Authority From: Mark Miller Re: October 16, 2023, Monthly Report Monthly Flows: The average daily flow to West Goshen was 726,075 per day. Meters: Were read on a daily basis with no problems to report C.C. Collection: The pump stations were visited on daily basis with no problems to report. C.C. Interceptor: We inspected the lids and castings while we were clearing the right of way. R.C. Collection: The pump stations were visited on a daily basis with no problems to report. Ridley Creek Plant: • Applebrook pump burned up and was replaced • Met with Erika from Pennoni to go over the work that needs to be done for the new generator • New UV System o Temporary tank channel arrived o Pumps, hose, and control panels are ordered o Third pump ordered as a designated spare in case one of main pumps goes down Alarms: 12 (storm-related) PA One Calls: 194 Monthly Rainfall: 5.80” Lateral Repairs or Caps: Four repairs done on private systems. Inspections done by Public Works. We are picking up the repairs on the PA One Calls.

Christiana Executive Campus 121 Continental Drive, Suite 207 Newark, DE 19713

T: 302-655-4451 F: 302-654-2895

www.pennoni.com EAST GOSHEN MUNICIPAL AUTHORITY

ENGINEER’S REPORT

October 13, 2023

Ridley Creek Sewage Treatment Plant (RCSTP)

• Caustic Soda Conversion – Once the outdoor emergency shower is installed, the tank can be put into operation. We also prepared a draft O&M Manual information for the system that was submitted to the Township and operator for review.

During a site visit on October 4, it was noticed that the tank’s outside insulation was cracked in some locations and loose/peeling off in others. We contacted the supplier, Pyrz, to alert them of this issue. Pyrz then contacted the manufacturer, Assmann, to have this issue resolved. Assmann will ship Pyrz needed materials for repairs. After the materials are received, Pyrz will schedule a site visit to re-apply the insulation and add the mastic paint to repair the parts that have come loose. It will take about a half day of work to allow the spray insulation to set and coat it.

• UV Disinfection System – The temporary channel was delivered to the Township on August 24. As of September 29, Glasco stated that the units have been fabricated but have not been tested yet. A date for testing the units has not been set. After testing is complete, the UV system would be able to be shipped in about two weeks. We are still awaiting a definitive delivery date.

We continued coordination with vendors and obtained additional cost quotes for the bypass pumps with control boxes. Quotes for the jib crane were previously obtained. The Township has placed orders for the jib crane and submersible pumps with control boxes. The lead times for the jib crane and pumps are 3-4 weeks after orders are placed. We are waiting on definitive delivery dates for the products. .

An updated tentative construction schedule follows:

o Initiate Temporary Bypass Work – Week of October 23, 2023 o Delivery of Permanent UV Equipment – Mid-to-Late October 2023 o Delivery of Jib Crane and Bypass Pumps – Early-Mid November 2023 o Complete Temporary Bypass Work and Initiate Use of Bypass System – December 20, 2023 o Two Week Trial and Sampling of Temporary Bypass System – December 20, 2023-January 3,

2024 o Township to Perform Concrete Channel Work – January 8-February 29, 2024 o 2nd Notice to Proceed to Contractors: Permanent Work – March 1, 2024 o Redirect Flow back to Permanent Channel (30 days of 2nd NTP) – April 1, 2024 o Two Week Trial of New UV System in Permanent Channel –April 1-15, 2024 o Install Second UV Module into Permanent Channel – April 16, 2024 o Two Week Trial of Second New UV System in Permanent Channel – April 17-May 1, 2024 o Construction Completed – Early May 2024

EGMAU23001 October 13, 2023 Page 2 East Goshen Municipal Authority Engineer’s Report

P:\Projects\EGMA\Memos to Board\2023\Engineers Report 2023-10-13.docx

• Generator #2 Replacement – Premium Power Services released the Cummins’ 500 kW diesel generator for fabrication in early March 2023. The lead times on the generator and ATS are 43 weeks and 22 weeks respectively, so we expect delivery of the entire system around January 2024.

A site meeting with Pennoni and the Township was held on October 4 to discuss the options for the new generator layout. It was decided that installing the new generator slightly north of the existing generator’s location would require the least amount of labor and be the most cost-effective option. We are preparing electrical and structural concrete pad plans for this layout.

• Operating Cost Analysis – We are continuing to coordinate with Scott Towler for the evaluation of industry WWTP operating costs in an effort to benchmark RCSTP costs against other similar WWTPs.

Sanitary Sewer Pipe Rehab

• Chester Creek Sewer Rehab – The contractor, Insituform, provided their bonds and insurance documents. All were found acceptable. The contract was subsequently executed. A pre-construction meeting with the contractor was held on September 27. The Notice to Proceed letter is anticipated to be issued by the end of October.

• Hershey’s Mill Estates – Most punchlist work and permanent restoration is complete. There are a few remaining minor punchilst items that were identified in a subsequent inspection of which we will notify the contractor.

• Ridley Creek Exposed Sewer Rehab – A full PADEP permit application has been prepared and will be submitted to PADEP in follow-up to the emergency authorization now that construction has been completed.

New Connections

• 1010 Hershey Mill Road (Moser) – No activity since our last report.

• 301 Reservoir Road (5-Lot Residential Subdivision) – No activity since our last report.

• 1712 E. Boot Road – No activity since our last report.

• 14 Reservoir Road – No activity since our last report.

END OF REPORT

RCSTP Monthly Operations Report

October 2023

Executive Summary The Ridley Creek sewage treatment plant outfall 001 has met all effluent limitations regarding water quality for September 2023. All supplemental reports were submitted for August 2023, with the eDMR Discharge to the Applebrook irrigation lagoon restarted on September 21st. Chemical usage utilized for total alkalinity remained consistent with previous months. Aluminum sulfate solution volumes increased slightly to a daily average of 72.5 from the previous standard of 68.6 gallons per day. No significant mechanical or operational issues were observed during the sludge dewatering equipment or SBR treatment process. Sludge dewatering experienced no mechanical issues impacting production. There were no odor complaints during the month.

Table 1

Treatment Process Operation

Table 1 illustrates the final effluent composite sample data reported for outfall 001 for September 2023. The monthly average total phosphorus was reported as 0.14 mg/L compared to the permit limitation of 0.50 mg/L. The TSS samples were consistently in single digits. The results remain below the weekly maximum of 15 mg/L. The monthly average TSS is reported as 4.3 mg/L compared to the discharge limitation of 10 mg/L.

The final effluent test results demonstrate that the biological treatment performed well during September. The sequencing batch reactors (SBRs) numbered 2, 3, and 4 were in service. Process monitoring of each SBR included ammonia as N, nitrite as N, Nitrate as N, COD, SSV, MLSS, and total phosphorus. Daily analysis of the final effluent flow equalization grabs samples

Flow

MGD

Average mg/L

lbs/

month mg/L

lbs/

month mg/L

lbs/

month mg/L

lbs/

month mg/L

lbs/

month

Geo

Mean

Geo

Mean

0.75 10 62 Report Report 10 62 2.5 44 0.5 3 200 1,000

Inst. Max 20 94 15 94 5 1

Sample Date

September 6, 2023 0.000 2.0 0.0 7.15 0.0 4.0 0.0 0.10 0.00 0.12 0.00 1 0.0000

September 12, 2023 0.000 2.0 0.0 11.0 0.0 4.0 0.0 0.10 0.00 0.14 0.00 6 0.7782

September 19, 2023 0.026 2.0 0.4 7.31 1.6 5.2 1.1 0.10 0.02 0.14 0.03 13 1.1139

September 26, 2023 0.036 2.0 0.6 7.71 2.3 4.0 1.2 0.10 0.03 0.14 0.04 11 1.0414

Average 0.015 2.0 0.3 8.29 1.0 4.3 0.6 0.10 0.01 0.14 0.02 8 0.7334

Minimum 0.000 2.0 0.0 7.15 0.0 4.0 0.0 0.10 0.00 0.12 0.00 1 0.0000

Maximum 0.036 2.0 0.6 11.00 2.3 5.2 1.2 0.10 0.03 0.14 0.04 13 1.1139

TSS NH4-N Total Phosphorus

September 2023- Final Effluent - Outfall 001

NPDES Permit

Discharge

Limitations

CBOD5 Total Nitrogen Fecal Coliform

Page 2 of 4

for total phosphorus is ongoing. Sample collection and analysis of the influent wastewater collected at the influent pump station wet well continues.

Discharge to the Applebrook irrigation lagoon, outfall 002, started September 21st.

Table 2 illustrates the final effluent composite sample data reported for outfall 002 for September 2023.

Table 2

The influent wastewater pollutant concentrations and loading entering the wastewater treatment facility generally remained within the design concentration and organic loading values. The TSS and CBOD5 monthly average weekly concentrations were generally observed to be within the design parameters for the treatment process.

Table 3 presents the pollutant data for the influent wastewater collected at the doghouse manhole during September 2023.

Table 3

Flow

MGD

Average mg/L

lbs/

month mg/L

lbs/

month mg/L

lbs/

month mg/L

lbs/

month mg/L

lbs/

month

Geo

Mean

Geo

Mean

0.135 25 Report Report 30 7.0 44 0.5 3 200 1,000

40 45

September 6, 2023 0.0367 2.0 0.6 7.15 2.19 4.00 1.22 0.10 0.00 0.12 0.00 1 0.0000

September 12, 2023 0.0381 2.0 0.6 11.00 3.50 4.00 1.27 0.10 0.00 0.14 0.00 6 0.7782

September 19, 2023 0.0000 2.0 0.0 7.31 0.00 5.20 0.00 0.10 0.02 0.14 0.03 13 1.1139

September 26, 2023 0.0000 2.0 0.0 7.71 0.00 4.00 0.00 0.10 0.03 0.14 0.04 11 1.0414

Average 0.0187 2.0 0.31 8.29 1.42 4.30 0.62 0.10 0.01 0.14 0.02 8 0.7334

Minimum 0.0000 2.0 0.00 7.15 0.00 4.00 0.00 0.10 0.00 0.12 0.00 1 0.0000

Maximum 0.0381 2.0 0.64 11.00 3.50 5.20 1.27 0.10 0.03 0.14 0.04 13 1.1139

Fecal Coliform

September 2022 - Applebrook - Out Fall 002

NPDES Permit

Discharge

Limitations

CBOD5 Total Nitrogen TSS NH4-N Phosphorus,Total

Flow

mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day mg/L lbs/day

335 2,098 NA NA 320 2,001 32 200 48 301 9.1 57

September 6, 2023 0.276 215 495 204 470 154 354 39.0 90 55.1 127 5.6 12.9

September 12, 2023 0.292 241 587 278 677 264 643 35.7 87 54.4 132 5.88 14.3

September 19, 2023 0.250 246 513 296 617 220 459 35.0 73 50.5 105 5.64 11.8

September 26, 2023 0.284 615 1,457 616 1,459 985 2,333 32.3 77 78.9 187 9.37 22.2

Average 0.276 329 763 349 806 406 947 35.5 82 59.7 138 6.63 15.3

Minimum 0.250 215 495 204.0 470 154 354 32.3 73 50.5 105 5.61 11.8

Maximum 0.292 615 1,457 616 1,459 985 2,333 39.0 90 78.9 187 9.37 22.2

Sample Date

TKN, mg/L

Phosphorus,Total,

mg/L

MGD

Average

September 2023 - Influent Wastewaster

Design Basis

BOD5 CBOD5 TSS NH4-N

Page 3 of 4

The foam on the SBR surface remained consistent during September, with approximately 5% to 15% coverage of the surface area. The foam thickness is approximately 2 inches and is light to medium brown. These conditions may contribute to a decrease in clarity within the final effluent post-flow equalization basins; however, the clarity is improved after passing through the disc filters. The operation strategy is to lower the MLSS to maintain a F:M ratio 0.06 while ensuring the ammonia effluent discharge concentration remains within the 2.5 mg/L seasonal limits.

PA DEP

No activity

Pennoni Associates

The UV system replacement project continues.

Significant Rainfall

During September, there were eleven (11) days when rainfall occurred and three (3) days where rainfall exceeded 0.5 inches in 24 hours.

September 10th 0.50 inches

September 18th 1.35 inches

September 24th 0.53 inches

September 25th 1.60 inches

Continuous rainfall from September 23rd through September 27th for a total of 2.63 inches.

The total rainfall for September was a total 5.04 inches.

Chemical Data

September 2023

Chemical Daily Average Total Monthly

Soda Ash, pounds 290 9,000

Aluminum Sulfate solution, gal 72.5 2,176

Sludge Dewatering, gal* 19,755 375,347

*19 days of sludge dewatering

Minor Preventative Maintenance

Flushed chemical feed lines to the SBRs.

Cleaned final effluent weir trough daily.

Skimmed surface of disc filters daily

Drained and cleaned disc filters bi-weekly.

Cleaned buildings and laboratory.

Flow Data

Page 4 of 4

September 2023

Flow Meter Location Total Volume for

Month, MG

Average Daily

Flow, gpd

Daily Maximum

Flow, gpd

Influent Wastewater to

Screening Building* 9.488 316,259 493,600

Influent Wastewater to

SBRs* 11.070 369,000 519,292

Internal Recycle** 1.582 51,040 82,893

Treated Effluent to Disc

Filters 10.831 361,048 480,871

Final Effluent Discharge

8.41 280,000 369,000

Applebrook Golf Course 0.409 13,467 42,048

MA 9-11-23 draft 1

DRAFT 1 EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY 2 MEETING MINUTES 3 September 11, 2023 4 5 The East Goshen Township Municipal Authority held their regular meeting on Monday, 6 September 11, 2023 at 7:00 pm. at the Township Building. Members in attendance are indicated in 7 BOLD: 8 Kevin Cummings, Chairman 9 Dana Pizarro, Vice Chairman 10 Jack Yahraes 11 Carmen Battavio 12 Walter Wujcik 13 14 Also in attendance were: Mark Miller (Director of Public Works), Mike Ellis (Pennoni 15 representative), Ellen Koopman (Attorney), Dave Ware (Finance Director), and Michael Lynch 16 (Township Supervisor). 17 18 19 COMMON ACRONYMS: 20 ATS – Automatic Transfer Switch 21 BFES – Big Fish Environmental Services MA- Municipal Authority 22 BOS – Board of Supervisors NPDES – National Pollutant Discharge Elimination System 23 CB – Conservancy Board PC – Planning Commission 24 DEP – Department of Environmental Protection PM – Prevention Maintenance 25 EPA – Environmental protection Agency PR – Park & Recreation Board 26 HC – Historical Commission RCSTP – Ridley Creek Sewer Treatment Plant 27 I&I – Inflow & Infiltration SBR – Sequencing Batch Reactor 28 LCSTP – Lockwood Chase Sewer Treatment Plant SSO – Sanitary System Overflow 29 PWD – Public Works Department WAS – Waste Activated Sludge 30 31 Call to Order & Pledge of Allegiance 32 Kevin called the meeting to order at 7:00 pm and led those present in the Pledge of Allegiance. 33 He asked for a moment of silence for our First Responders and Military and to remember 9/11 22 34 years ago.. 35 He asked if anyone would be recording the meeting. There was no response. 36 37 38 Chairman’s Report 39 Kevin asked about the grant. Dave mentioned that prevailing wages should have been paid to the 40 contractors. He isn’t sure if this will affect the grant. He mentioned other possible grants. 41 42 43 SEWER REPORTS 44 1. Director of Public Works, Mark Miller’s report for September 11, 2023 45 46 Monthly Flows – The average daily flow to West Goshen was 732,643 gallons per day. 47 48 Meters: The meters were read on a daily basis. 49

MA 9-11-23 draft 2

Allied Control was onsite to perform the quarterly calibration on the interceptor meters. 1 Lynn noticed a low flow reading at the Hibberd Lane Meter. We went and rebooted the 2 meter, but it was still reading low. John Laidley was notified, and he came out ad ran a diagnostic 3 check on the meter. 4 5 C.C. Collection: The pump stations were visited on a daily basis with no problems to report. 6 7 C.C. Interceptor: Was inspected as part of our routine maintenance. The line was mowed and 8 vegetation was removed from around the manhole. 9 10 R.C. Collection: The pumping stations were checked on a daily basis with no problems to report. 11 12 Ridley Creek Plant: 13 • Routine maintenance was performed. 14 • We had another problem with the pump for Applebrook. It appears that the overload block 15 burned up. 16 • On August 28th, we came in at 2:00 am and pumped the final effluent pit down and utilized 17 Pipe Data View to clean the tank. We are also looking at how many spikes we have taken 18 from PECO. 19 • Number 2 generator broke a drive belt and the idler puller went bad and had to be replaced. 20 21 Hershey Mill Trunk Line: We met with the contractor last week and walked the line. He is 22 scheduled to come after Labor Day to lay topsoil and seed various areas. They will begin to remove 23 the filter sock in the areas that are established. 24 25 Westtown Way Pump Station: I stopped down last Wednesday and there was nothing going on. 26 They are still waiting on materials. Dave and I have a meeting at the end of the month with Mike 27 Moffa and the other partners. 28 29 Alarms: 12 were received 30 31 PA 1 Calls: 57 for the month 32 33 Monthly Rainfall: 2.40 inches of rain for the month of August. 34 35 Lateral Repairs or Caps: 1 lateral repair (Linden Lane) & 10 caps 36 37 38 2. Pennoni Engineer’s Report dated September 8, 2023 39 40 41

Ridley Creek Sewage Treatment Plant (RCSTP) 42

• Caustic Soda Conversion – Once the outdoor emergency shower is installed, the tank can be 43 put into operation. We also prepared draft O&M Manual information for the system that will 44 be submitted to the Township and operator for review. 45

MA 9-11-23 draft 3

• UV Disinfection System – The temporary channel was delivered to the Township on August 1 24. As of August 15, Glasco stated about 3-4 weeks were still needed for fabrication of the 2 UV modules before delivery, and we are awaiting a definitive delivery date. 3

The contractors, Lenni and Zimmerman, provided their bonds and insurance documents. All 4 were found acceptable. The contracts were subsequently executed. 5

A pre-construction meeting with both contractors, John Laidley (controls contractor), Big 6 Fish, Pennoni, and the Township was held on August 15. The 1st Notice to Proceed letters for 7 the temporary work will be issued within the upcoming week. 8

We coordinated with vendors and obtained cost quotes for the jib crane and the bypass pumps 9 with control boxes. We obtained three quotes for the jib crane, and we understand the 10 Township has placed an order. We obtained two quotes for the purchase of two submersible 11 pumps and control boxes, and we are awaiting a third at the time of this report. Purchasing is 12 less expensive than renting for the expected 5-month duration of construction. The lead times 13 for the jib crane and pumps are 3-4 weeks after orders are placed. 14

An updated tentative construction schedule follows: 15

o 1st Notice to Proceed to Contractors: Temporary Bypass Work – September 11-12, 16 2023 17 o Initiate Temporary Bypass Work – Week of September 11, 2023 18 o Delivery of Permanent UV Equipment – Mid-September 2023 19 o Delivery of Jib Crane and Bypass Pumps – Early-Mid October 2023 20 o Complete Temporary Bypass Work and Initiate Use of Bypass System – November 8, 21 2023 22 o Two Week Trial and Sampling of Temporary Bypass System – November 8-22, 2023 23 o Township to Perform Concrete Channel Work – November 27, 2023-January 18, 2024 24 o 2nd Notice to Proceed to Contractors: Permanent Work – January 19, 2024 25 o Redirect Flow back to Permanent Channel (30 days of 2nd NTP) – February 29, 2024 26 o Two Week Trial of New UV System in Permanent Channel – February 29-March 14, 27 2024 28 o Install Second UV Module into Permanent Channel – March 18, 2024 29 o Two Week Trial of Second New UV System in Permanent Channel – March 19-April 30 2, 2024 31 o Construction Completed – Early April 2024 32

• Generator #2 Replacement – Premium Power Services released the Cummins’ 500 kW diesel 33 generator for fabrication in early March 2023. The lead times on the generator and ATS are 34 43 weeks and 22 weeks respectively, so we expect delivery of the entire system around 35 January 2024. We have initiated design for the electrical installation and are evaluating the 36 need for slab replacement/modifications. We will prepare a slab design if needed. 37

• Operating Cost Analysis – We are continuing to coordinate with Scott Towler for the 38 evaluation of industry WWTP operating costs in an effort to benchmark RCSTP costs against 39 other similar WWTPs. 40

MA 9-11-23 draft 4

Sanitary Sewer Pipe Rehab 1

• Chester Creek Sewer Rehab – The bid went live on PennBID on August 17, and a virtual pre- 2 bid meeting occurred on August 23. We responded to bidders’ questions and issued one 3 addendum. Bids were opened on PennBID on September 7. There were 3 bids. We provided 4 an award recommendation and bid tabulation. 5

• Hershey’s Mill Estates – Punchlist work and permanent restoration is ongoing, and we have 6 been performing part-time construction observation. 7

• Ridley Creek Exposed Sewer Rehab – A full PADEP permit application has been prepared 8 and will be submitted to PADEP in follow-up to the emergency authorization now that 9 construction has been completed. 10

New Connections 11

• 1010 Hershey Mill Road (Moser) – We reviewed revised Land Development Plans and 12 provided comments on the proposed sanitary sewer extension. We met virtually thereafter 13 with the design consultant to discuss resolution of the comments. 14

• 301 Reservoir Road (5-Lot Residential Subdivision) – No activity since our last report. 15

• 1712 E. Boot Road – No activity since our last report. 16

• 14 Reservoir Road – No activity since our last report. 17

18 3. Big Fish Environmental Services – 19 The Ridley Creek sewage treatment plant outfall 001 has met all effluent limitations regarding water 20 quality for August 2023. All supplemental reports were submitted for the month of July 2023 with the 21 eDMR. Discharge to the Applebrook irrigation lagoon was discontinued on August 19th. Chemical 22 usage utilized for total alkalinity remained consistent with previous months. Aluminum sulfate 23 solution volumes decreased slightly to a daily average of 68.8from the previous average of 71.6 24 gallons per day. No significant mechanical or operational issues were observed during the sludge 25 dewatering equipment or SBR treatment process. Sludge dewatering experienced some mechanical 26 issues impacting production. There were no odor complaints during the month. 27 28 Approval of Minutes 29 The minutes of the August 14, 2023 meeting were approved as amended. 30 31 Approval of Invoices 32 1. Walater moved to approve payment of the Lenni Invoice #230571 in the amount of $18,930.40 33 which has been paid. Jack seconded the motion. The motion passed unanimously. 34 35 Liaison Reports 36 1. Conservancy Board – Walter reported that the CRC Watersheds gave their presentation to plant 37 125 trees in Applebrook. The BOS approved it. 38 1. Board of Supervisors – Mike Lynch reported that the BOS will be discussing the General Fund 39 Budget at the meeting tomorrow. 40

MA 9-11-23 draft 5

1 Financial Reports 2 Dave Ware presented the following report: 3 Year to date August 2023, the Municipal Authority recorded $514,158 in revenues (primarily from 4 Sewer Operating transfers and Sewer Capital Reserve transfers and tapping fees) and $510,928 in 5 expenses (Engineering Services, Audit fees, Administrative Wages, Hershey’s Mill Estates Sewer 6 costs, Caustic Soda project costs, capital costs at the Ridley Creek Sanitary Treatment Plant, capital 7 improvements to the Westtown Way Pump station, auditor and legal fees). The net result of 8 operations is $3,229. As of August 31, 2023, the fund balance was ($38,575). This negative balance 9 is a function of balance versus cash reporting. There is $46,977 in invoices being held so the actual 10 cash balance is $3,229. 11 Dave mentioned that next week he will have his all other funds report including sewer. 12 13 Old Business 14 None 15 16 Goals 17 The Goals were reviewed. Hershey Mill Estates is completed. 18 19 New Business – None 20 21 Capacity Requests - None 22 23 Any Other Matter – 24 Chester Creek Interceptor – Bids came in. The budget is $260,000. Public Works videoed 4,900 25 liner feet down the stream. Additional items may change when there is more definitive information. 26 27 Correspondence- None 28 29 Public Comment - None 30 31 Adjournment 32 There being no further business Jack moved to adjourn the meeting. Walter seconded the motion. 33 The motion passed unanimously. The meeting was adjourned at 7:41 pm. 34 The next regular meeting will be held on Monday, October 9, 2023 at 7:00 pm. 35 36 Respectfully submitted, 37 38 39 Ruth Kiefer, Recording Secretary 40

[Logo: Pennoni]

INVOICE

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

Mark Miller
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199

Invoice No : 1190712
Invoice Date : 09/28/2023
Project : EGMAU20004
Project Name : RCSTP Caustic Soda Conversion

For Services Rendered Through 09/17/2023

Compiled documentation for O&M manual for caustic system. Attended on-site meeting with Township, operator, and controls integrator regarding controls logic in preparation for start-up.

Phase Code / Name Contract Amount Previously Billed % Complete Complete To Date Amount This Invoice
01 -- Design and Permitting $26,500.00 $26,500.00 100.00% $26,500.00 $0.00
02 -- Construction Phase Services est. $5,400.00 $2,253.25 $2,717.75 $464.50
Total : $31,900.00 $28,753.25 $29,217.75 $464.50

Phase: 02 -- Construction Phase Services

Labor

Class Hours Rate Amount
Authority Engineer 2.00 149.00 298.00
Associate Professional 1.50 111.00 166.50
Labor 464.50

Phase Subtotal: $464.50

Amount Due This Invoice: $464.50

[Stamp: APPROVED BY: [signature] 9/28/23
DATE PAID:
CHECK #:
CHARGED TO: 07-429-1520]

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

West Goshen RCSTP Caustic Soda Conversion
EGMAU20004 Invoice Summary
Invoice Date 9/27/2023

Project: EGMAU20004
Pennoni Job No.: RCSTP Caustic Soda Conversion
Invoice No: 1190712
Invoice Period: 6/19/2023 to 9/17/2023
Initial Authorization: $ 31,900.00 Date: 9/27/2023
Contract Amount: $ 31,900.00
Previously Invoiced: $ 28,753.25
Current Invoice: $ 464.50
Invoiced to Date ($): $ 29,217.75
Invoiced to Date (%): 92%
Remaining Budget ($): $ 2,682.25
Remaining Budget (%): 8%

Budget by Phase:

Phase Name: RCSTP Caustic Soda Conversion
Phase Budget: $ 31,900.00
Previously Invoiced: $ 28,753.25
Current Invoice: $ 464.50
Invoiced to Date ($): $ 29,217.75
Invoiced to Date (%): 92%
Remaining Budget ($): $ 2,682.25
Remaining Budget (%): 8%

Comments: Compiled documentation for O&M manual for caustic system. Attended on-site meeting with Township, operator, and controls integrator regarding controls logic in preparation for start-up.

[Logo: Pennoni]

INVOICE

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

Mark Miller
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199

Invoice No : 1190713
Invoice Date : 09/28/2023
Project : EGMAU21004
Project Name : HM Estates Sewer Design & Permitting

For Services Rendered Through 09/17/2023

Construction Admin & Inspections: Punchlist site visit, and inspections of restoration work.

Phase Code / Name Contract Amount Previously Billed % Complete Complete To Date Amount This Invoice
01 -- Wetland & Watercourse Investigation $6,750.00 $6,750.00 100.00% $6,750.00 $0.00
02 -- Phase I Bog Turtle Habitat Assessment $6,750.00 $6,750.00 100.00% $6,750.00 $0.00
03 -- Survey $17,200.00 $17,200.00 100.00% $17,200.00 $0.00
04 -- Design $26,100.00 $26,100.00 100.00% $26,100.00 $0.00
05 -- Permitting $8,000.00 $8,000.00 100.00% $8,000.00 $0.00
06 -- Property Line Stakeout est. $5,000.00 $7,520.50 $7,520.50 $0.00
07 -- Geotechnical NTE $10,000.00 $6,271.25 62.71% $6,271.25 $0.00
08 -- Bid Assistance NTE $9,690.50 $9,690.50 100.00% $9,690.50 $0.00
09 -- Construction Admin & Inspection NTE $60,000.00 $49,886.00 86.00% $51,602.50 $1,716.50
Total : $149,490.50 $138,168.25 $139,884.75 $1,716.50

Phase: 09 -- Construction Admin & Inspection

Labor

Class Hours Rate Amount
Authority Engineer 1.25 149.00 186.25
Staff Professional 11.25 117.00 1,316.25
Sr. Eng Tech 2.00 107.00 214.00
Labor 1,716.50

Phase Subtotal: $1,716.50

Amount Due This Invoice: $1,716.50

[Stamp: APPROVED BY: [signature] 9/28/23
DATE PAID:
CHECK #:
CHARGED TO: 19-409-6050]

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

West Goshen HM Estates Sewer Design Permitting
EGMAU21004 Invoice Summary
Invoice Date 9/27/2023

Project: EGMAU21004
Pennoni Job No.: HM Estates Sewer Design & Permitting
Invoice No: 1190713
Invoice Period: 6/19/2023 to 9/17/2023
Initial Authorization: $ 64,800.00 Date: 9/27/2023
Contract Amount: $ 149,490.50
Previously Invoiced: $ 138,168.25
Current Invoice: $ 1,716.50
Invoiced to Date ($): $ 139,884.75
Invoiced to Date (%): 94%
Remaining Budget ($): $ 9,605.75
Remaining Budget (%): 6%

Budget by Phase:

Phase Name: HM Estates Sewer Design & Permitting
Phase Budget: $ 149,490.50
Previously Invoiced: $ 138,168.25
Current Invoice: $ 1,716.50
Invoiced to Date ($): $ 139,884.75
Invoiced to Date (%): 94%
Remaining Budget ($): $ 9,605.75
Remaining Budget (%): 6%

Comments: Construction Admin & Inspections: Punchlist site visit, and inspections of restoration work.

[Logo: Pennoni]

INVOICE

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

Mark Miller
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199

Invoice No : 1190714
Invoice Date : 09/28/2023
Project : EGMAU22004
Project Name : RCSTP UV Replacement

For Services Rendered Through 09/17/2023

Phase 01, Professional Services for Design & Bid Assistance: Completed 1st construction solicitation services including preparing Addendum #1, responding to bidders' questions, conducting bid opening, reviewing electrical contract bids (no bids for general contract) and providing award recommendation, and contacting general contractors to determine reasons for not bidding. Revised general contract bid document and conducted 2nd solicitation including a 2nd pre-bid meeting at the site, responding to prospective bidder's questions, conducting bid opening, reviewing bids, resolving tie bids, and providing award recommendation.

Phase 02, Construction Phase Services: Sent award letters to contractors, prepared for and conducted pre-construction meeting with contractors, attended separate pre-construction field meeting with Public Works about concrete wall raising design, responded to Public Works' questions, reviewed contractor's insurance and bonding documents, issued Notice to Proceed letters to contractors, obtained job crane quotes and provided purchase recommendation memo, and obtained initial bypass pump purchase quotes.

Phase 01 Professional Services

Labor

Class Hours Rate Amount
Authority Engineer 4.25 149.00 633.25
Senior Professional 13.75 145.00 1,993.75
Graduate Professional 9.50 102.00 969.00
Associate Professional 1.50 111.00 166.50
Engineering Tech 2.75 90.00 247.50
Totals 31.75 4,010.00
Total Labor 4,010.00
Billing Limits Current Prior To-Date
Total Billings 4,010.00 39,885.75 43,895.75
Limit 44,000.00
Remaining 104.25

Total this Phase: $4,010.00

Phase 02 Construction Phase Services

Labor

Class Hours Rate Amount
Authority Engineer .75 149.00 111.75

Continued on next page...

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

RCSTP UV Replacement
EGMAU22004 Invoice Summary
Invoice Date 09/27/2023

Project: EGMAU22004
Pennoni Job No.: RCSTP UV Replacement
Invoice No: 1190714
Invoice Period: 6/9/2023 to 9//17/2023
Initial Authorization: $ 30,000.00 Date: 9/27/2023
Contract Amount: $ 54,000.00
Previously Invoiced: $ 39,885.75
Current Invoice: $ 10,769.75
Invoiced to Date ($): $ 50,655.50
Invoiced to Date (%): 94%
Remaining Budget ($): $ 3,344.51
Remaining Budget (%): 6%

Budget by Phase:

Phase Name: RCSTP UV Replacement 1129796
Phase Budget: $ 54,000.00
Previously Invoiced: $ 39,885.75
Current Invoice: $ 10,769.75
Invoiced to Date ($): $ 50,655.50
Invoiced to Date (%): 94%
Remaining Budget ($): $ 3,344.51
Remaining Budget (%): 6%

Comments: Phase 01, Professional Services for Design & Bid Assistance: Completed 1st construction solicitation services including preparing Addendum #1, responding to bidders' questions, conducting bid opening, reviewing electrical contract bids (no bids for general contract) and providing award recommendation, and contacting general contractors to determine reasons for not bidding. Revised general contract bid document and conducted 2nd solicitation including a 2nd pre-bid meeting at the site, responding to prospective bidder's questions, conducting bid opening, reviewing bids, resolving tie bids, and providing award recommendation.
Phase 02, Construction Phase Services: Sent award letters to contractors, prepared for and conducted pre-construction meeting with contractors, attended separate pre-construction field meeting with Public Works about concrete wall raising design, responded to Public Works' questions, reviewed contractor's insurance and bonding documents, issued Notice to Proceed letters to contractors, obtained job crane quotes and provided purchase recommendation memo, and obtained initial bypass pump purchase quotes.

Project EGMAU22004 RCSTP UV Replacement Invoice 1190714
Senior Professional 22.50 145.00 3,262.50
Associate Professional 30.50 111.00 3,385.50
Totals 53.75 6,759.75
Total Labor 6,759.75
Billing Limits Current Prior To-Date
Total Billings 6,759.75 0.00 6,759.75
Limit 10,000.00
Remaining 3,240.25

Total this Phase: $6,759.75

Total this Invoice: $10,769.75

[Stamp: APPROVED BY: [signature] 9/28/23
DATE PAID:
CHECK #:
CHARGED TO: 07-429-1505]

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

[Logo: Pennoni]

INVOICE

Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328

Mark Miller
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199

Invoice No : 1190715
Invoice Date : 09/28/2023
Project : EGMAU23001
Project Name : 2023 General Services

For Services Rendered Through 09/17/2023

Prepared August and September Engineer's Reports. Reviewed August and September RCSTP operator's reports. Prepared for and attended August and September MA meetings. Evaluated opportunities for open LSA grant cycle.

Chester Creek Interceptor Sewer Rehab: Completed bid document, prepared cost estimate, conducted solicitation on PennBID, conducted pre-bid meeting, responded to prospective bidders' questions, prepared Addendum #1, conducted bid opening, reviewed bids, prepared bid tabulation, issued award recommendation, issued award letter to awarded contractor, and reviewed contractor's bonds and insurance documents.

RCSTP Generator #2 Replacement: Field visit and site meeting to establish existing wiring and other conditions and replacement scoping, and initiated preparation of design and plans for generator and ATS replacement.

Billing Limits Current Prior To-Date
Total Billings 13,951.25 16,859.50 30,810.75
Limit 42,000.00
Remaining 11,189.25

Labor

Class Hours Rate Amount
Authority Engineer 15.00 149.00 2,235.00
Senior Professional 20.00 145.00 2,900.00
Staff Professional 40.25 117.00 4,709.25
Associate Professional 37.00 111.00 4,107.00
Totals 112.25 13,951.25
Total Labor 13,951.25

Total this Invoice: $13,951.25

[Stamp: APPROVED BY: [signature] 9/28/23
DATE PAID:
CHECK #:
CHARGED TO: 07-424-3130]

INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.

2023 General Services
EGMAU23001Invoice Summary
Invoice Date 9/27/2023

Project: EGMAU23001
Pennoni Job No.: 2023 General Services
Invoice No: 1190715
Invoice Period: 7/17/2023 to 9/17/2023
Initial Authorization: $ 42,000.00 Date: 9/27/2023
Contract Amount: $ 42,000.00
Previously Invoiced: $ 16,859.50
Current Invoice: $ 13,951.25
Invoiced to Date ($): $ 30,810.75
Invoiced to Date (%): 73%
Remaining Budget ($): $ 11,189.25
Remaining Budget (%): 27%

Budget by Phase:

Phase Name: 2023 General Services
Phase Budget: $ 42,000.00
Previously Invoiced: $ 16,859.50
Current Invoice: $ 13,951.25
Invoiced to Date ($): $ 30,810.75
Invoiced to Date (%): 73%
Remaining Budget ($): $ 11,189.25
Remaining Budget (%): 27%

Comments: Prepared August and September Engineer's Reports. Reviewed August and September RCSTP operator's reports. Prepared for and attended August and September MA meetings. Evaluated opportunities for open LSA grant cycle.

Chester Creek Interceptor Sewer Rehab: Completed bid document, prepared cost estimate, conducted solicitation on PennBID, conducted pre-bid meeting, responded to prospective bidders' questions, prepared Addendum #1, conducted bid opening, reviewed bids, prepared bid tabulation, issued award recommendation, issued award letter to awarded contractor, and reviewed contractor's bonds and insurance documents.

RCSTP Generator #2 Replacement: Field visit and site meeting to establish existing wiring and other conditions and replacement scoping, and initiated preparation of design and plans for generator and ATS replacement.

[Logo: Gawthrop Greenwood, PC Attorneys at Law]

(p) 610-696-8225
(f) 610-344-0922
gglaw@gawthrop.com
www.gawthrop.com

GAWTHROP GREENWOOD CLIENT INVOICE

Please Mail checks to:
P.O. Box 562
West Chester, PA 19381-0562

To Make a Payment with a Credit Card, please visit:
https://secure.lawpay.com/pages/gawthrop/operating

East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380

Page: 1
09/08/2023
Client No: 6604-001M
Invoice No: 277578

General Authority Services

Fees

Date Timekeeper Description Hours Amount
08/11/2023 PMM Email from L. Werkheiser regarding meeting materials. 0.20 41.00
08/14/2023 EBK Review and analyze meeting materials
Travel to/from and attend meeting
2.00 390.00
PMM Emails (3) from D. Ware and M. Ellis regarding Small Sewer and Water reimbursement. 0.60 123.00
08/15/2023 EBK Review and respond to email from D Ware regarding Caustic Soda grant
Review and analyze materials from D Ware
Email exchange with D Ware regarding scheduling of call
Call with Township staff regarding grant, bidding requirements generally
1.70 331.50
EBK Review and respond to email from D Ware regarding telephonic bids, research issue and email to D Ware regarding findings 0.60 117.00
PMM Telephone conference with M. Miller, D. Davis and D. Ware regarding caustic soda project and grant requirements. 0.30 61.50
08/17/2023 EBK Organize thoughts on implications of issues related to bidding and caustic soda project. 0.20 n/c
08/22/2023 PMM Message from M. Ellis. 0.20 41.00
08/23/2023 PMM Message to M. Ellis regarding small sewer and water grant. 0.20 41.00
For Current Services Rendered 5.80 1,146.00

East Goshen Municipal Authority
General Authority Services

Page: 2
09/08/2023
Client No: 6604-001M
Invoice No: 277578

Recapitulation

Timekeeper Hours Hourly Rate Total
Patrick M. McKenna, Esquire 1.50 $205.00 $307.50
Ellen B. Koopman, Esquire 4.30 195.00 838.50
Previous Balance $2,140.00
Total Current Charges 1,146.00
08/28/2023 Payment -2,140.00
Balance Due $1,146.00

[Stamp: APPROVED BY: [signature] 10/11/23
DATE PAID:
CHECK #:
CHARGED TO: 07-424-3140]

To ensure proper credit, please write your client number on your check when returning payment.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.

[Logo: Gawthrop Greenwood, PC Attorneys at Law]

(p) 610-696-8225
(f) 610-344-0922
gglaw@gawthrop.com
www.gawthrop.com

GAWTHROP GREENWOOD CLIENT INVOICE

Please Mail checks to:
P.O. Box 562
West Chester, PA 19381-0562

To Make a Payment with a Credit Card, please visit:
https://secure.lawpay.com/pages/gawthrop/operating

East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380

Page: 1
09/08/2023
Client No: 6604M

Previous Balance Fees Expenses Payments Balance
6604-001 General Authority Services
2,140.00 1,146.00 0.00 -2,140.00 $1,146.00

To ensure proper credit, please write your client number on your check when returning payment.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.

[Logo: Gawthrop Greenwood, PC Attorneys at Law]

(p) 610-696-8225
(f) 610-344-0922
gglaw@gawthrop.com
www.gawthrop.com

GAWTHROP GREENWOOD CLIENT INVOICE

Please Mail checks to:
P.O. Box 562
West Chester, PA 19381-0562

To Make a Payment with a Credit Card, please visit:
https://secure.lawpay.com/pages/gawthrop/operating

East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380

Page: 1
10/06/2023
Client No: 6604-001M
Invoice No: 279612

[Stamp: APPROVED BY: [signature] 10/11/23
DATE PAID:
CHECK #:
CHARGED TO: 07-424-3140]

General Authority Services

Fees

Date Timekeeper Description Hours Amount
09/07/2023 PMM Telephone conference with D. Davis. 0.20 41.00
09/08/2023 PMM Review and analyze email string regarding award for Chester Creek Interceptor work; Review and analyze award letter from Pennoni regarding same; Email from L. Werkheimer regarding bid bond; Email from L. Werkheimer regarding meeting agenda and materials; Review and analyze same; Emails (3) from D. Ware and M. Ellis regarding Pa Local Share Grant for interceptor work. 1.30 266.50
09/11/2023 EBK Review and analyze meeting materials
Email to/from D Ware regarding meeting agenda and line item for Lenni invoice
Travel to/from and attend monthly meeting
1.80 351.00
For Current Services Rendered 3.30 658.50

Recapitulation

Timekeeper Hours Hourly Rate Total
Patrick M. McKenna, Esquire 1.50 $205.00 $307.50
Ellen B. Koopman, Esquire 1.80 195.00 351.00
Previous Balance $1,146.00
Total Current Charges 658.50
Balance Due $1,804.50

East Goshen Municipal Authority
General Authority Services

Page: 2
10/06/2023
Client No: 6604-001M
Invoice No: 279612

To ensure proper credit, please write your client number on your check when returning payment.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.

[Logo: Gawthrop Greenwood, PC Attorneys at Law]

(p) 610-696-8225
(f) 610-344-0922
gglaw@gawthrop.com
www.gawthrop.com

GAWTHROP GREENWOOD CLIENT INVOICE

Please Mail checks to:
P.O. Box 562
West Chester, PA 19381-0562

To Make a Payment with a Credit Card, please visit:
https://secure.lawpay.com/pages/gawthrop/operating

East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380

Page: 1
10/06/2023
Client No: 6604M

Previous Balance Fees Expenses Payments Balance
6604-001 General Authority Services
1,146.00 658.50 0.00 0.00 $1,804.50

To ensure proper credit, please write your client number on your check when returning payment.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.

[Logo: MAINLINE CONCRETE & SUPPLY EST. 1978]
1001 BOOT ROAD
DOWNINGTOWN, PA 19335
PHONE: 610 269 5556
www.mainlineconcrete.com

Order Taker : ATM ACCT # EAS30 INV # 525430
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE
WEST CHESTER, PA 19380
PO # DATE 09/06/23
(610) 692-7171
QUANTITY PRODUCT CODE MATERIAL UNIT PRICE EXTENSION
15 EA ROD #4 X 20' ROD 1/2 x 20 FT (#4)
150 pcs. per ton
10.65 159.75

[Stamp: APPROVED BY: MM [signature] 10/11/23
DATE PAID:
CHECK #:
CHARGED TO: 07-429-1505
UV Project OK to pay]

[Stamp: PAID]

SUB TOTAL 159.75 SALES TAX 0.00 TOTAL AMOUNT 159.75 AMOUNT PAID

MAIN LINE CONCRETE & SUPPLY INC. ASSUMES NO RESPONSIBILITY FOR SLUMP, STRENGTH OR QUALITY OF CONCRETE AFTER WATER IS ADDED AT THE JOB SITE. ALL DELIVERIES ARE SUBJECT TO THE GENERAL TERMS AND CONDITIONS ON THE REVERSE SIDE. BY SIGNING BELOW, THE PURCHASER AND ALL AGENTS, SERVANTS, AND EMPLOYEES THEREOF, AGREE TO THE GENERAL TERMS AND CONDITIONS ON THE REVERSE SIDE AND THAT THE GOODS WERE RECEIVED IN GOOD CONDITION AND THE SERVICES WERE RENDERED IN A GOOD AND WORKMANLIKE MANNER.

RECEIVED BY:
(SIGNATURE) (PRINT NAME) (DATE)
CAUTION - CONCRETE CAUSES SKIN IRRITATION AND IS INJURIOUS TO EYES
(SEE REVERSE SIDE FOR FURTHER CAUTION INFORMATION)

EAST GOSHEN TOWNSHIP

Invoice

[Logo: GAPPOWER Quietly Equipping You]
5399 Lincoln Hwy,
Gap, PA 17527
717-442-8970
www.gappower.com
Pay Online by ACH or Credit Card, Mail a Check, or Phone a Credit Card

Invoice Number Date Page
1870216 9/21/2023 1 of 1

[Barcode]

Bill To:
East Goshen Township
1580 Paoli Pike
West Chester, PA 19380

Ship To:
Pickup

Customer ID Sales Person P.O. Number Ship Date Ship Via Terms
EASGO3965 GideonS UV 9/21/2023 Pickup Net 55 days
Ordered Shipped Item Description Unit Price Extended
1.00 1.00 RB441T RB441T "Twintier" Rebar Tier #7 to #7
Serial # 23214118I
$2541.77 $2,541.77
1.00 1.00 TW1061T Box TW1061T Tie Wire for RB441T/RB611T, 30 COILS
145 MINIMUM TIES PER COIL
265 MAXIMUM TIES PER COIL
$297.28 $297.28
1.00 1.00 JPL91450A Battery (RB398, RB518, RB441T) $169.00 $169.00

[Stamp: APPROVED BY: [signature] [signature] 10/11/23
DATE PAID:
CHECK #:
CHARGED TO: 07429-1505
UV system]

[Stamp: PAID]

DEWALT PROMOS ARE THE HOT TICKET AT GAP POWER ........TAKE A LOOK..... GRAB A DEAL THAT WORKS FOR YOU.

Discount Terms: (1% if paid by 10th / 25th of the month)
If paid by 10/10/2023 you may deduct $30.08 - Discounted Balance: $2,977.97.
All past due invoices will be subject to a finance charge of 1.50% per month, annual rate of 18.00%

Customer Signature: [signature]

Thank You!

Subtotal 3,008.05
Freight -
Sales Tax Exempt
TOTAL 3,008.05
Amount Paid 0.00
Balance Due 3,008.05 $2,977.97

Memo

To: Municipal Authority
From: Dave Ware
Re: MA September 2023 YTD Financial Report
Date: October 12, 2023

YTD September 2023, the Municipal Authority recorded $545,467 in revenues (primarily from Sewer Operating transfers, Sewer Capital Reserve transfers, and tapping fees) and $541,910 in expenses (Engineering Services, Audit Fees, Administrative Wages, Hershey’s Mill Estates Sewer costs, Caustic Soda project costs, capital costs at the Ridley Creek Sanitary Treatment Plant, capital improvements to the Westtown Way Pump station and auditor and legal fees). The net result of operations is $3,557. As of September 30, 2023, the fund balance was ($50,947). This negative balance is a function of balance versus cash reporting. There is $59,676 in invoices being held so the actual cash balance is $8,729.

Attached is a complete list of 2023 full year MA revenues and expenses.

U:\dware\municipal authority\

EAST GOSHEN TOWNSHIP

Municipal Authority Fund

September 2023

Account Id Account Description Annual Budget Current YTD Prior YTD
REVENUE
07-341-1000 INTEREST EARNINGS 0.00 194.52 2.51
07-354-0400 DCED GRANT 152,980.00 0 0
07-364-1100 C.C. TAPPING FEES 2,300.00 0.00 2,300.00
07-364-1110 R.C.TAPPING FEES 2,000.00 5,180.56 1,195.68
07-364-1130 CONNECTION FEES - SEWER 1,000.00 563.76 563.76
07-380-1000 MISCELLANEOUS REVENUE 282.24 282.24 282.24
07-392-0500 TRANSFER FROM SEWER OPERATING 100,000.00 75,366.79 73,216.90
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 1,471,553.00 463,879.06 125,499.35
Total Revenue 1,730,115.24 545,466.93 203,060.44
EXPENSES
07-424-1400 ADMINISTRATIVE WAGES 32,055.45 29,687.04 25,116.15
07-424-3000 MISCELLANEOUS EXPENSE 1,748.79 1,655.25 1,665.25
07-424-3110 MUNIC.AUTH.-AUDITING 10,815.00 10,500.00 10,250.00
07-424-3130 ENGINEERING SERVICES 47,250.00 25,522.00 34,398.75
07-424-3140 LEGAL SERVICES 8,400.00 5,432.50 5,320.00
07-424-7440 R.C. CAPITAL-STP 355,793.00 0.00 0.00
07-424-7490 CAP.REPLACEMENT R.C. 488,847.00 0.00 0.00
07-426-3001 RELINING 260,000.00 0.00 0.00
07-429-1501 BARKWAY PUMP STATION CAPITAL 0.00 0.00 2,215.00
07-429-1502 ASHBRIDGE PUMP STATION CAPITAL 0.00 0.00 11,493.05
07-429-1503 HERSHEYS MILL PUMP STATION CAPITAL 78,000.00 10,240.62 29,390.17
07-429-1504 HUNT CO PUMP STATION CAPITAL 0.00 0.00 1,870.00
07-429-1505 RCSTP CAPITAL 260,000.00 136,083.88 87,335.45
07-429-1510 HERSHEY'S MILL ESTATES PROJECT 0.00 90,113.64 0.00
07-429-1520 RCSTP - CAUSTIC SODA 0.00 50,412.49 0.00
07-429-6100 WEST GOSHEN CAPITAL 187,206.00 182,262.24 0.00
07-492-0100 TRANSFER TO GENERAL FUND 0.00 0.00 212.99
Total Expenses 1,730,115.24 541,909.66 209,266.81
Net Result From Operations 0.00 3,557.27 -6,206.37

Municipal Authority

YTD Revenues and Expenses thru 9/30/2023

Account NumberAccount DescriptionDateTypeTransaction Data/CommentAmount
07-341-1000INTEREST EARNINGS01/31/23Revenue JournalINTEREST EARNED JAN 20232.65
07-341-1000INTEREST EARNINGS02/28/23Revenue JournalINTEREST EARNED FEBRUARY 20236.32
07-341-1000INTEREST EARNINGS03/31/23Revenue JournalINTEREST EARNED MARCH 202323.37
07-341-1000INTEREST EARNINGS04/30/23Revenue JournalINTEREST EARNED APRIL 202312.47
07-341-1000INTEREST EARNINGS05/31/23Revenue JournalINTEREST EARNED MAY 202332.83
07-341-1000INTEREST EARNINGS06/30/23Revenue JournalINTEREST EARNED JUNE 202367.17
07-341-1000INTEREST EARNINGS07/31/23Revenue JournalINTEREST EARNED JULY 202310.61
07-341-1000INTEREST EARNINGS08/31/23Revenue JournalINTEREST EARNED AUGUST 20239.11
07-341-1000INTEREST EARNINGS09/30/23Revenue JournalINTEREST EARNED SEPTEMBER 202329.99
07-364-1110R.C.TAPPING FEES01/01/23Revenue Journal1577 COLONIAL LN297.84
07-364-1110R.C.TAPPING FEES02/01/23Revenue Journal1577 COLONIAL LN297.84
07-364-1110R.C.TAPPING FEES03/01/23Revenue Journal1577 COLONIAL LN297.84
07-364-1110R.C.TAPPING FEES04/03/23Revenue Journal1577 COLONIAL LN297.84
07-364-1110R.C.TAPPING FEES05/01/23Revenue Journal1577 COLONIAL LN297.84
07-364-1110R.C.TAPPING FEES06/01/23Revenue Journal1577 COLONIAL LN297.84
07-364-1110R.C.TAPPING FEES06/28/23Revenue JournalTAP IN FEE 1712 E BOOT RD2,000.00
07-364-1110R.C.TAPPING FEES06/28/23Revenue JournalSEWER INSPECTION FEE 1712 E BOOT RD500.00
07-364-1110R.C.TAPPING FEES07/03/23Revenue Journal1577 COLONIAL LN297.84
07-364-1110R.C.TAPPING FEES08/01/23Revenue Journal1577 COLONIAL LN297.84
07-364-1110R.C.TAPPING FEES09/01/23Revenue Journal1577 COLONIAL LN297.84
07-364-1130CONNECTION FEES - SEWER01/27/23Revenue JournalCONNECTION FEE INSTALLMENT INV# 12838281.88
07-364-1130CONNECTION FEES - SEWER03/23/23Revenue JournalCONNECTION FEE INSTALLMENT INV# 12839281.88
07-380-1000MISCELLANEOUS REVENUE01/27/23Revenue JournalPINE ROCK INTEREST PORTION - STOFFLET141.12
07-380-1000MISCELLANEOUS REVENUE03/23/23Revenue JournalPINE ROCK INTEREST PORTION - PAPPANO141.12
07-392-0500TRANSFER FROM SEWER OPERATING01/20/23Revenue JournalXFER TO 07 FROM 05 RE: MA EXPENSES3,384.75
07-392-0500TRANSFER FROM SEWER OPERATING01/30/23Revenue JournalXFER $ TO MA07 FROM 05-SEWER14,572.43
07-392-0500TRANSFER FROM SEWER OPERATING01/31/23Revenue JournalXFER $ FROM 05 TO 07 RE: MA EXPENSES3,000.00
07-392-0500TRANSFER FROM SEWER OPERATING02/17/23Revenue JournalXFER TO 07 FROM 05 RE: EXPENSES36,455.37
07-392-0500TRANSFER FROM SEWER OPERATING02/23/23Revenue JournalXFER FROM 05 SEWER OPERATING TO 07 MA2,877.00
07-392-0500TRANSFER FROM SEWER OPERATING03/22/23Revenue JournalXFER FROM 05 SEWER OPERATING TO 07 MA715.00
07-392-0500TRANSFER FROM SEWER OPERATING03/23/23Revenue JournalXFER FROM 05 SEWER OPERATING TO 07 MA880.25
07-392-0500TRANSFER FROM SEWER OPERATING03/24/23Revenue JournalXFER TO 07 FROM 05 RE: EXPENSES6,738.25
07-392-0500TRANSFER FROM SEWER OPERATING03/29/23Revenue JournalXFER FROM 05 SEWER OPERATING TO 07 MA8,000.00
07-392-0500TRANSFER FROM SEWER OPERATING03/31/23Revenue JournalXFER FROM 05 SEWER OPERATING TO 07 MA8,944.84
07-392-0500TRANSFER FROM SEWER OPERATING04/17/23Revenue JournalFROM 05 SEWER OP TO 07 MA4,992.75
07-392-0500TRANSFER FROM SEWER OPERATING05/10/23Revenue JournalXFER FROM 05 SEWER OPERATING TO 07 MA707.00
07-392-0500TRANSFER FROM SEWER OPERATING05/10/23Revenue JournalXFER FROM 05 SEWER OPERATING TO 07 MA5,627.50
07-392-0500TRANSFER FROM SEWER OPERATING06/08/23Revenue JournalXFER FROM 05 SEWER OPERATING TO 07 MA1,253.25
07-392-0500TRANSFER FROM SEWER OPERATING06/30/23Revenue JournalXFER FROM 05 SEWER OPERATING TO 07 MA10,398.41
07-392-0500TRANSFER FROM SEWER OPERATING07/13/23Revenue JournalXFER FROM 05 SEWER OPERATING TO 07 MA1,041.00
07-392-0500TRANSFER FROM SEWER OPERATING08/08/23Revenue JournalXFER FROM 05 SEWER OPERATING TO 07 MA60.00

Page 1 of 5

Municipal Authority

YTD Revenues and Expenses thru 9/30/2023

Account Number Account Description Date Type Transaction Data/Comment Amount
07-392-0500 TRANSFER FROM SEWER OPERATING 08/24/23 Revenue Journal XFER FROM 05 SEWER OPERATING TO 07 MA 5,040.00
07-392-0500 TRANSFER FROM SEWER OPERATING 09/27/23 Revenue Journal XFER FROM 05 SEWER OPERATING TO 07 MA 10,343.79
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 01/12/23 Revenue Journal XFER $ FROM 09 TO 07 TO COVER CAP.EXP. 41,381.95
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 01/20/23 Revenue Journal XFER TO 07 FROM 09 RE: MA EXPENSES 11,730.76
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 01/30/23 Revenue Journal XFER $ TO MA07 FROM 09- SEWER CAP 5,221.00
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 02/10/23 Revenue Journal FROM 09 SEWER CAP RESERVE TO 07 MA 115,362.26
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 02/23/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 8,690.50
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 03/01/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 20,201.84
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 03/09/23 Revenue Journal XFER $ TO 07 FROM 09 1,264.96
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 03/22/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 1,961.86
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 03/24/23 Revenue Journal XFER TO 07 FROM 09 RE: EXPENSES 11,080.96
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 03/29/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 5,221.00
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 04/05/23 Revenue Journal XFER FROM 09 SEWER OP TO 07 MA 1,041.75
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 04/21/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 977.06
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 04/25/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 4,801.50
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 04/26/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 252.28
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 04/28/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 688.81
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 05/04/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 5,069.52
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 05/10/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 1,953.58
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 05/19/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 66,899.98
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 06/08/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 56,078.05
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 06/13/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 450.18
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 06/20/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 888.22
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 07/03/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 6,746.00
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 07/11/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 209.00
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 07/13/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 824.50
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 08/08/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 22.12
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 08/24/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 5,626.50
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 08/31/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 18,930.40
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 09/07/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 17,500.00
07-392-0900 TRANSFER FROM SEWER CAP RESERVE 09/22/23 Revenue Journal XFER FROM 09 SEWER CAP TO 07 MA 3,137.72
Total Revenue 545,466.93
07-424-1400 ADMINISTRATIVE WAGES 03/31/23 Pay Check: 3402 23-00878 QTR 1 2023 MA CHARGE BACK 8,944.84
07-424-1400 ADMINISTRATIVE WAGES 06/30/23 Pay Check: 3431 23-01745 QTR 2 2023 MA CHARGE BACK 10,398.41
07-424-1400 ADMINISTRATIVE WAGES 09/29/23 Expd QTR 3 2023 MA CHARGE BACK 10,343.79
07-424-3000 MISCELLANEOUS EXPENSE 03/22/23 Pay Check: 3395 23-00707 2023 ANNUAL DAILY DISCHARGE CA 715.00
07-424-3000 MISCELLANEOUS EXPENSE 03/23/23 Expd REIMBURSE 01 FOR 07 CC EXPENSE 880.25
07-424-3000 MISCELLANEOUS EXPENSE 08/08/23 Expd REIMBURSE 01 FOR 07 CC EXPENSE 60.00
07-424-3110 MUNIC.AUTH.-AUDITING 02/15/23 Pay Check: 3389 23-00406 PROGRESS BILLING EGT MUA123122 1,793.00

Page 2 of 5

Municipal Authority

YTD Revenues and Expenses thru 9/30/2023

Account Number Account Description Date Type Transaction Data/Comment Amount
07-424-3110 MUNIC.AUTH.-AUDITING 03/29/23 Pay Check: 3401 23-00870 PROGRESS BILLING AUD EGT MUA 8,000.00
07-424-3110 MUNIC.AUTH.-AUDITING 05/10/23 Pay Check: 3417 23-01270 PROGRESS BILLING AUDIT EGT MUA 707.00
07-424-3130 ENGINEERING SERVICES 01/20/23 Pay Check: 3379 23-00111 SERV.THRU 12/18/22 GEN.SERV.22 3,384.75
07-424-3130 ENGINEERING SERVICES 02/23/23 Pay Check: 3392 23-00443 SERV THRU 011523 GEN SERVICES 2,294.00
07-424-3130 ENGINEERING SERVICES 03/24/23 Pay Check: 3399 23-00816 SERV THRU 021223 CHAPTER 94 RE 2,246.00
07-424-3130 ENGINEERING SERVICES 03/24/23 Pay Check: 3399 23-00815 SERV THRU 021223 GENERAL SERVI 3,482.75
07-424-3130 ENGINEERING SERVICES 04/17/23 Pay Check: 3406 23-01018 SERV THRU 031923 GENERAL SERVI 2,614.75
07-424-3130 ENGINEERING SERVICES 04/17/23 Pay Check: 3406 23-01019 SERV THRU 031923 CHAPTER 94 RE 1,654.50
07-424-3130 ENGINEERING SERVICES 05/10/23 Pay Check: 3420 23-01302 SERV THRU 041623 2023 GEN SERV 3,663.25
07-424-3130 ENGINEERING SERVICES 05/10/23 Pay Check: 3420 23-01303 SERV THRU 041623 2022 CHAPT 94 1,377.25
07-424-3130 ENGINEERING SERVICES 06/08/23 Pay Check: 3425 23-01576 SERV THRU 051423 2023 GEN SERV 1,253.25
07-424-3130 ENGINEERING SERVICES 07/13/23 Pay Check: 3435 23-01882 SERV THRU 061823 2023 GEN SERV 651.50
07-424-3130 ENGINEERING SERVICES 08/24/23 Pay Check: 3437 23-02177 SERV THRU 071623 2023 GEN SERV 2,900.00
07-424-3140 LEGAL SERVICES 02/23/23 Pay Check: 3391 23-00442 LEGAL SERV. JAN 2023 GEN AUTH 583.00
07-424-3140 LEGAL SERVICES 03/24/23 Pay Check: 3398 23-00812 LEGAL SERV FEB 2023 GEN AUTHOR 389.50
07-424-3140 LEGAL SERVICES 03/24/23 Pay Check: 3398 23-00813 LEGAL SERV DEC 2022 GEN AUTHOR 620.00
07-424-3140 LEGAL SERVICES 04/17/23 Pay Check: 3405 23-01020 LEGAL SERV MARCH 2023 GEN AUTH 431.00
07-424-3140 LEGAL SERVICES 04/17/23 Pay Check: 3405 23-01017 LEGAL SERV FEB 2023 GEN AUTH 292.50
07-424-3140 LEGAL SERVICES 05/10/23 Pay Check: 3419 23-01304 LEGAL SERV APRIL 2023 GEN AUTH 587.00
07-424-3140 LEGAL SERVICES 07/13/23 Pay Check: 3434 23-01883 LEGAL SERV MAY 2023 GEN AUTH 389.50
07-424-3140 LEGAL SERVICES 08/24/23 Pay Check: 3436 23-02176 LEAL SERV JUNE 2023 GEN AUTH 348.50
07-424-3140 LEGAL SERVICES 08/24/23 Pay Check: 3436 23-02175 LEGAL SERV JULY 2023 GEN AUTH 1,791.50
07-429-1503 HERSHEYS MILL PUMP STATION CAPITAL 01/20/23 Pay Check: 3379 23-00110 SERV.THRU 12/18/22 HM EST SEWR 9,690.50
07-429-1503 HERSHEYS MILL PUMP STATION CAPITAL 02/06/23 Pay Check: 3385 23-00331 STONE, AASHTO #57 550.12
07-429-1505 RCSTP CAPITAL 01/10/23 Pay Check: 3377 23-00030 CONDUITS, STRAPS, LOCKNUTS + 1,161.95
07-429-1505 RCSTP CAPITAL 01/10/23 Pay Check: 3378 23-00075 PULSAFEEDER - RCSPT CAUSTIC SO 40,220.00
07-429-1505 RCSTP CAPITAL 01/20/23 Pay Check: 3379 23-00109 SERV.THRU 12/18/22 RCSTP SODA 861.51
07-429-1505 RCSTP CAPITAL 01/20/23 Pay Check: 3379 23-00112 SERV.THRU 12/18/22 RCSTP UV 1,178.75
07-429-1505 RCSTP CAPITAL 01/27/23 Pay Check: 3380 23-00151 HELIFLOW 408 PD BLOWER 5,221.00
07-429-1505 RCSTP CAPITAL 02/06/23 Pay Check: 3384 23-00305 50HP 3540RPM BALDOR MOTOR 4,683.69
07-429-1505 RCSTP CAPITAL 03/24/23 Pay Check: 3399 23-00817 SERV THRU 021223 RCSTP CAU SOD 4,144.21
07-429-1505 RCSTP CAPITAL 03/29/23 Pay Check: 3400 23-00827 HELIFLOW 408 LHBD BLOWER 5,221.00
07-429-1505 RCSTP CAPITAL 06/08/23 Pay Check: 3422 23-01548 UV DISINFECTION SYS PYMT- 30% 40,495.80
07-429-1505 RCSTP CAPITAL 06/08/23 Pay Check: 3425 23-01575 SERV THRU 051423 RCSTP UV REPL 5,770.00
07-429-1505 RCSTP CAPITAL 06/08/23 Pay Check: 3425 23-01573 SERV THRU 051423 RCSTP CAU SOD 37.25
07-429-1505 RCSTP CAPITAL 07/13/23 Pay Check: 3435 23-01881 SERV THRU 061823 RCSTP CAU SOD 824.50
07-429-1505 RCSTP CAPITAL 08/24/23 Pay Check: 3437 23-02178 SERV THRU 060823 RCSTP UV REPL 5,626.50
07-429-1505 RCSTP CAPITAL 09/07/23 Pay Check: 3439 23-02333 PARTIAL PYMT RC GENERATOR SUPP 17,500.00
07-429-1505 RCSTP CAPITAL 09/22/23 Pay Check: 3440 23-02474 441T TWINTIER REBAR TYING TOOL 3,008.05
07-429-1505 RCSTP CAPITAL 09/22/23 Pay Check: 3440 23-02474 441T TWINTIER REBAR TYING TOOL -30.08
07-429-1505 RCSTP CAPITAL 09/22/23 Pay Check: 3441 23-02452 ROD 1/2X20' UV PROJECT 159.75

Page 3 of 5

Municipal Authority

YTD Revenues and Expenses thru 9/30/2023

Account NumberAccount DescriptionDateTypeTransaction Data/CommentAmount
07-429-1510HERSHEY'S MILL ESTATES PROJECT02/21/23ExpdRECLASS HERSH.MILL EST. PURCH.23-001486,904.64
07-429-1510HERSHEY'S MILL ESTATES PROJECT02/21/23ExpdRECLASS HERSH.MILL EST. PURCH.23-00364430.00
07-429-1510HERSHEY'S MILL ESTATES PROJECT02/21/23ExpdRECLASS HERSH.MILL EST. PURCH.23-004291,708.22
07-429-1510HERSHEY'S MILL ESTATES PROJECT02/21/23ExpdRECLASS HERSH.MILL EST. PURCH.23-0041217,817.91
07-429-1510HERSHEY'S MILL ESTATES PROJECT02/21/23ExpdRECLASS HERSH.MILL EST. PURCH.23-004113,771.00
07-429-1510HERSHEY'S MILL ESTATES PROJECT02/21/23ExpdRECLASS HERSH.MILL EST. PURCH.23-003816,498.99
07-429-1510HERSHEY'S MILL ESTATES PROJECT02/21/23ExpdRECLASS HERSH.MILL EST. PURCH.23-004154,866.25
07-429-1510HERSHEY'S MILL ESTATES PROJECT02/21/23ExpdRECLASS HERSH.MILL EST. PURCH.23-001532,642.00
07-429-1510HERSHEY'S MILL ESTATES PROJECT02/21/23ExpdRECLASS HERSH.MILL EST. PURCH.23-001525,025.79
07-429-1510HERSHEY'S MILL ESTATES PROJECT02/23/23Pay Check: 339223-00444 SERV THRU 011523 HM ESTATES SW8,690.50
07-429-1510HERSHEY'S MILL ESTATES PROJECT02/28/23Pay Check: 339323-00536 STONE, AASHTO #57 329.79 TON8,244.78
07-429-1510HERSHEY'S MILL ESTATES PROJECT02/28/23Pay Check: 339323-00534 STONE, AASHTO #57 251.05 TON6,276.27
07-429-1510HERSHEY'S MILL ESTATES PROJECT02/28/23Pay Check: 339323-00535 STONE, AASHTO #57 227.23 TON5,680.79
07-429-1510HERSHEY'S MILL ESTATES PROJECT03/09/23Pay Check: 339423-00582 SPLIT COUPLERS305.40
07-429-1510HERSHEY'S MILL ESTATES PROJECT03/09/23Pay Check: 339423-00581 SEWER HUB ADAPTERS,COUPLERS +959.56
07-429-1510HERSHEY'S MILL ESTATES PROJECT03/22/23Pay Check: 339623-00723 36" MARMAC POLYSEAL COUPLER803.20
07-429-1510HERSHEY'S MILL ESTATES PROJECT03/22/23Pay Check: 339723-00731 JOHN DEERE 550K RENTL 2/28-3/1434.50
07-429-1510HERSHEY'S MILL ESTATES PROJECT03/22/23Pay Check: 339723-00730 JOHNDEERE 550K RENTL 2/23-2/24724.16
07-429-1510HERSHEY'S MILL ESTATES PROJECT03/24/23Pay Check: 339923-00814 SERV THRU 021223 HM ESTATES SE6,936.75
07-429-1510HERSHEY'S MILL ESTATES PROJECT04/25/23Pay Check: 341023-01141 SINGLE SIDED STRAW MAT,PINS1,407.00
07-429-1510HERSHEY'S MILL ESTATES PROJECT04/25/23Pay Check: 341023-01141 SINGLE SIDED STRAW MAT,PINS-14.07
07-429-1520RCSTP - CAUSTIC SODA04/05/23Pay Check: 340323-00889 VARIOUS PURCHASES- SEE NOTES215.75
07-429-1520RCSTP - CAUSTIC SODA04/05/23Pay Check: 340423-00906 ROD 5/8 X 20 FT-CAUSTIC SODA826.00
07-429-1520RCSTP - CAUSTIC SODA04/21/23Pay Check: 340723-01081 3" TWISTER CORE BITS441.00
07-429-1520RCSTP - CAUSTIC SODA04/21/23Pay Check: 340723-01081 3" TWISTER CORE BITS-4.41
07-429-1520RCSTP - CAUSTIC SODA04/21/23Pay Check: 340823-01056 GALV CAP, GFCI RCPT, GREY COVR168.21
07-429-1520RCSTP - CAUSTIC SODA04/21/23Pay Check: 340823-01057 GALV CAP, STEEL CLAMPBACK372.26
07-429-1520RCSTP - CAUSTIC SODA04/25/23Pay Check: 340923-01131 PVC CONDBY, DEV BOX, CTD CPLG890.32
07-429-1520RCSTP - CAUSTIC SODA04/25/23Pay Check: 341123-01112 (30) BUSS FUSES2,160.00
07-429-1520RCSTP - CAUSTIC SODA04/25/23Pay Check: 341123-01144 GALV BLCK CAP,COMPRESSION CPLG286.08
07-429-1520RCSTP - CAUSTIC SODA04/25/23Pay Check: 341123-01128 IRON THRDED T BODY, SHEET STEE72.17
07-429-1520RCSTP - CAUSTIC SODA04/26/23Pay Check: 70023-01151 CAUSTIC SODA-(2) HVY DUTY TARP252.28
07-429-1520RCSTP - CAUSTIC SODA04/28/23Pay Check: 341223-01177 BLINE SS CHANNEL SLOTTED HOLES374.17
07-429-1520RCSTP - CAUSTIC SODA04/28/23Pay Check: 341223-01176 EMT HW STRAP, MACH SCREW ANCHOR233.47
07-429-1520RCSTP - CAUSTIC SODA04/28/23Pay Check: 341223-01175 GALV RED CAP, COMM SWITCH,81.17
07-429-1520RCSTP - CAUSTIC SODA05/03/23Pay Check: 341323-01225 PVC BELL END PIPE, PVC COUPLING2,574.00
07-429-1520RCSTP - CAUSTIC SODA05/03/23Pay Check: 341423-01227 10 YD CONCRETE 4500 PSI1,930.00
07-429-1520RCSTP - CAUSTIC SODA05/03/23Pay Check: 341523-01219 (30) BLINE EMT-HW STRAP83.82
07-429-1520RCSTP - CAUSTIC SODA05/03/23Pay Check: 341523-01212 OUTLET BOX, SS SWITCH,HW STRAP481.70
07-429-1520RCSTP - CAUSTIC SODA05/10/23Pay Check: 341623-01276 SCH 40 2" PIPE, 2" COUPLING1,030.64
07-429-1520RCSTP - CAUSTIC SODA05/10/23Pay Check: 341623-01275 CORP BALL STOP, SERVICE SADDLE905.59

Page 4 of 5

Municipal Authority

YTD Revenues and Expenses thru 9/30/2023

Account Number Account Description Date Type Transaction Data/Comment Amount
07-429-1520 RCSTP - CAUSTIC SODA 05/10/23 Pay Check: 3418 23-01295 TAYMAC GRY METAL INUSE COVER 17.35
07-429-1520 RCSTP - CAUSTIC SODA 06/08/23 Pay Check: 3423 23-01553 RC WWTP CHEMICAL STORAGE TANK 6,415.00
07-429-1520 RCSTP - CAUSTIC SODA 06/08/23 Pay Check: 3424 23-01554 RIDLEY CREEK-RAN CONDUIT 2,008.00
07-429-1520 RCSTP - CAUSTIC SODA 06/08/23 Pay Check: 3424 23-01555 RIDLEY CR-RAN CONDUIT FOR TANK 1,352.00
07-429-1520 RCSTP - CAUSTIC SODA 06/13/23 Pay Check: 3428 23-01617 BALL CORP STOP, BRASS THRD NIPL 450.18
07-429-1520 RCSTP - CAUSTIC SODA 06/20/23 Pay Check: 3429 23-01658 BRASS THREADED NIPPLE&COUPLING 57.22
07-429-1520 RCSTP - CAUSTIC SODA 06/20/23 Pay Check: 3430 23-01654 PULSAFEEDER TUBING & KOPKIT 831.00
07-429-1520 RCSTP - CAUSTIC SODA 07/03/23 Pay Check: 3432 23-01739 RC WWTP CHEMICAL STORAGE TANK 6,746.00
07-429-1520 RCSTP - CAUSTIC SODA 07/11/23 Pay Check: 3433 23-01860 GATE & POST- BLAST PRIMER 209.00
07-429-1520 RCSTP - CAUSTIC SODA 08/08/23 Expd REIMBURSE 01 FOR 07 CC EXPENSE 22.12
07-429-1520 RCSTP - CAUSTIC SODA 08/31/23 Pay Check: 3438 23-02291 RC PIPING FOR CAUSTICSODA TANK 18,930.40
07-429-6100 WEST GOSHEN CAPITAL 02/06/23 Pay Check: 3383 23-00366 WWPS PYMT LAST INSTALLMENT 115,362.26
07-429-6100 WEST GOSHEN CAPITAL 05/19/23 Pay Check: 3421 23-01363 2022 WG SEWER AUTH BOND FUND E 19,143.34
07-429-6100 WEST GOSHEN CAPITAL 06/12/23 Pay Check: 3427 23-01364 2022 WG SEWER AUTH TAPPING FEE 47,756.64
Total Expense 541,909.66
Net Operating 3,557.27

Page 5 of 5

AREA CODE 610
692-7171

EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP

1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

Moser Construction Management LLC
TR Moser, Managing Member
1171 Lancaster Ave, Ste 201
Berwyn, PA 19312

April 18, 2023

Dear Mr. Moser,

The Municipal Authority has consulted with the township engineer, Pennoni Associates, regarding the additional sewer flow that would result from the proposed new housing on the Miller Property on Hershey Mill Road. Pennoni determined that the following four upgrades will need to be done at the Hershey Mill Pump Station in order to accommodate the additional flow:

  1. PUMP CONTROL PANEL: $37,641 (including labor) Provide, install, and commission one pump control panel to include variable frequency drive (VFD) speed control, pump alternation, alarm monitoring for pump and wet well level conditions, and HMI operator interface.
  2. VARIABLE FREQUENCY DRIVE: $14,852 (including labor) Provide, install, and commission two VFDs. VFDs would operate two submersible sewer pumps rated five horsepower.
  3. LEVEL SENSOR: $4,271 (including labor) Provide, install, and commission one radar level sensor (RLS). The RLS is a maintenance-free wet well level monitor that would integrate with the existing pump control panel.
  4. STATION FLOW DATA LOGGER: $6,557 (including labor) Provide, install, and commission one station flow data log recorder, which would connect into existing flow meter.

East Goshen Township will cover the cost of the station flow data logger. If you are willing cover the: 1) pump control panel, 2) variable frequency drive, and 3) level sensor for a total of $56,764, I will place the order. Additionally, you will be responsible for the sewer tap-in fee ($2,000) and sewer inspection ($500) for each new home.

If you agreeable to the above, please sign here and return a copy of this letter to me:

Signature: ________________________________________ Date: _________________

Best regards,
[Signature]
Mark S Miller
Director of Public Works
East Goshen Township