Municipal Authority
The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.
The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.
- Five members, serving five-year terms
- Meetings are on the 2nd Monday of the month at 7:00 P.M.
- All township meetings are held at the Township Building and open to the public
| Authority Members | Term Expiration Date |
| Kevin Cummings, Chairman | 2026 |
| John Stipe, Vice Chairman |
2029 |
| Dana Pizzarro, Secretary | 2026 |
| Sean Ellsworth, Assistant Secretary/Treasurer | 2028 |
| Walter Wujcik, Treasurer | 2028 |
| Pennoni Associates, Engineer | |
| Patrick M. McKenna, Esq. | |
| Peter Hicks, BoS Liaison | |
| Kevin Miller, Staff Liaison |
Documents
Back to the list | Open the original PDF
Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.
EAST GOSHEN MUNICIPAL AUTHORITY
August 12, 2024
7:00
- CALL TO ORDER/PLEDGE OF ALLEGIANCE/MOMENT OF SILENCE Ask if anyone will be taping the meeting
- CHAIRMAN'S REPORT/OTHER MEMBERS' REPORTS
- APPOINTMENT OF OFFICERS
- SEWER REPORTS Director of Public Work's Report; Pennoni Engineer's Report; Big Fish Environmental Report
- APPROVAL OF MINUTES July 15, 2024
- APPROVAL OF INVOICES
| Company | Invoice # | Amount | Paid? |
|---|---|---|---|
| Pennoni | 1233192 | $113.00 | |
| Pennoni | 1233193 | $339.00 | |
| Pennoni | 1233194 | $5,142.50 | |
| Pennoni for Insituform Technologies - Chester Creek Interceptor Inspection & Repair | Payment Application #5 | $11,348.00 | |
| JWC Environmental | 119462 | $27,691.19 | paid |
| West Goshen Sewer Authority | EG23-B | $95.64 | paid |
| West Goshen Sewer Authority | EG23-T | $31,392.87 | paid |
| Gawthrop Greenwood | 293953 | $315.00 |
- LIAISON REPORTS
- FINANCIAL REPORTS July 2024
- OLD BUSINESS
F:\Data\Shared Data\Agendas\Municipal Authority Agendas\2024 MA Agendas\08-12-24\Meeting Materials\08-12-2024 Agenda.doc
- 2024 Goals:
| Goal | Status |
|---|---|
| Ridley Creek plant compliance | January through July were in compliance with PADEP permit requirements. |
| Continue to implement infiltration and inflow for the sewer system | Ongoing. |
| RCSTP UV Disinfection System Construction Completion | The UV replacement is 99% complete. |
| Municipal Authority representative to attend West Goshen MA meetings. West Goshen MA meets 1st Wed of each month at 6pm at the West Goshen Township Building. | Attend meetings on quarterly basis. |
| Long-term sustainability | Continue development of 10-year sustainability plan and study sewer rates annually. Currently under development with completion by May. |
- NEW BUSINESS Discuss EnerG Test quote for $9,144 (Mike Ellis); Approval to advertise for Supplee Valley pipe lining (Mike Ellis)
- CAPACITY REQUESTS
- ANY OTHER MATTER
- CORRESPONDENCE AND REPORTS OF INTEREST
- PUBLIC COMMENT
- ADJOURNMENT
F:\Data\Shared Data\Agendas\Municipal Authority Agendas\2024 MA Agendas\08-12-24\Meeting Materials\08-12-2024 Agenda.doc
EAST GOSHEN MUNICIPAL AUTHORITY
EAST GOSHEN TOWNSHIP
1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199
610-692-7171
Date: August 12, 2024
To: Municipal Authority
From: Kevin Miller
Re: Monthly Report
Monthly Flows: The average daily flow to West Goshen was 795,367 per day.
Meters:
- Were read on a daily basis
- No issues found with operating meters
C.C. Collection:
- All pump stations were visited on a daily basis.
C.C. Interceptor:
- Mowed & maintained
R.C. Collection:
- Routine maintenance was performed on a daily basis.
- Public Works crew pulled all manholes and inspected and marked out sewer lines in the Clocktower development in preparation for upcoming Riggs/Distler utility work.
Ridley Creek Plant:
- Cleaned grit chamber
- Jetted and flushed inflow pipe to the plant
Applebrook Golf Course:
- PW crew replaced the Applebrook pump and it is now pumping 36,500 gallons per day.
Alarms: 6
PA One Calls: 73
Monthly Rainfall: 2.80”
Lateral Repairs or Caps: 4: 1 – Wentworth, 1 – Reservoir Rd, 1 – Baldwin Dr, & 1 – Katherine Ln
Pennoni
EAST GOSHEN MUNICIPAL AUTHORITY
ENGINEER'S REPORT
August 9, 2024
Ridley Creek Sewage Treatment Plant (RCSTP)
- Caustic Soda Conversion – Matt Mullin provided as-built photos of the caustic soda plumbing. We updated the as-built plans accordingly with the provided plumbing information and submitted the revised as-built plans to PADEP on July 23. We previously prepared a draft O&M Manual for the system that was submitted to the Township and operator for review. We will set up a meeting to review now that the system is up and running so that the Manual can be finalized.
- UV Disinfection System – On June 20, Lenni installed power to the jib crane and relocated the control panel to its permanent location, but it was discovered that the cords to connect the second UV module to the control panel are too short. Pennoni has since been coordinating with Glasco to obtain a new, longer cord for the module. Glasco picked up the temporary UV module cords to modify them to the correct length on July 25. Glasco will modify the temporary cords and return them in early August. After the new cords are installed, the two-week trial of the second UV module will begin. Glasco will also be scheduled to perform a post-startup inspection of the permanent UV installation. The temporary system has been fully disassembled. Pennoni informed Glasco on June 25 that the temporary channel is ready for pickup and for them to coordinate with Mark Miller on the specific day and time of the pickup. An updated tentative construction schedule follows with completed work in italics: Delivery of Permanent UV Equipment – October 30, 2023; Delivery of Bypass Pumps and Hoses – Week of November 13, 2023; Initiate Temporary Bypass Work – Mid-November 2023; Complete Temporary Bypass Work and Initiate Use of Bypass System – January 23, 2024; Two Week Trial and Sampling of Temporary Bypass System – completed February 9, 2024; Township to Perform Concrete Channel Work – completed late-March 2024 (end of initial curing); 2nd Notice to Proceed to Contractors: Permanent Work – Mid-March 2024; Redirect Flow back to Permanent Channel (±30 days of 2nd NTP) – April 24, 2024; Two Week Trial of New UV System in Permanent Channel – April 24 – May 8, 2024; Install Second UV Module into Permanent Channel –- June 11, 2024; Two Week Trial of Second New UV System in Permanent Channel – August 13 – 27, 2024; Construction Completed –Late August 2024
- Generator #2 Replacement – No activity by Pennoni since the last report.
- Electrical Supply Evaluation – We received a quote from EnerG Test for the installation of a power meter on the incoming electric supply line for $9,144.00. The testing would be performed for 25 days and will monitor and log power usage, voltage, phase, and other components of the electric supply. EnerG Test's engineers will analyze the results and provide a report within 30 days of completion of the monitoring. The report will address if there are unusual power/voltage spikes or drops and other anomalies. We recommend that their scope also include recommendations in their report to address any observed deficient conditions. For example, if the voltage is extremely inconsistent, a line conditioner (which acts as an electric filter) may be recommended on the main supply line. If problems are identified on the main feed, their report and recommendations can be provided to PECO to substantiate the problem with a request for PECO to implement the recommendations. Their proposal requires that arc flash labeling be on any electric equipment that they will be in contact with. Labeling is not on the Main Distribution Panel (MDP), so it will need to be installed before they install the power meter. A short circuit and arc flash analysis was performed as part of the RCSTP expansion in 2011. Labels were provided at that time, but there is not a label currently on the MDP. The Township will need to have the labels printed and attached to the MDP, and they should be attached to other applicable equipment while at it
Christiana Executive Campus
121 Continental Drive, Suite 207
Newark, DE 19713
T: 302-655-4451
www.pennoni.com
Page 1 of 2
EGMAU24001
East Goshen Municipal Authority August 9, 2024 Engineer's Report
Page 2 of 2
if other equipment is not currently labeled either. We can forward an electronic copy of the report that includes the labels from 2011.
Separate of the power monitoring – An updated arc flash study should be performed in the near future since it has been over five years since the last study and there have been electrical equipment changes, most notably the replacement of both generators. We could obtain a quote, and this be considered in 2025 budgeting. We anticipate it can occur separate of and after the power monitoring.
Sanitary Sewer Pipe Rehab
- Chester Creek Sewer Rehab – The Contractor, Insituform, has completed all work. We processed the fifth and final payment application and provided a payment recommendation letter. We also reviewed the Contractor's Maintenance Bond, Statement of Surety, and Contractor's Release and found all documents satisfactory. After approval of the final payment application, this project will be fully complete.
- Supplee Valley Pipe Lining – The next sewer rehabilitation project is planned to be installation of cured-in-place pipe liners in the remaining un-lined sewers in Supplee Valley as well as some manhole lining. We are finalizing the bid document and have updated the construction cost estimate. We anticipate the cost will be approximately $400,000, and we are coordinating with Dave Ware and Mark Miller on the available budget to establish Base Bid vs. Add Items. Funding from the planned 2025 Pipe Lining budget item is expected to be needed in conjunction with 2024 budget to cover the full cost of this work in one construction contract. The project is therefore proposed to be advertised in late August, bids due in late September, award consideration by the MA In October, and construction to occur in late 2024-early 2025 with all invoicing and payments to occur in 2025.
New Connections
- Millstone Meadows (1010 Hershey Mill Road) – We reviewed a revised Land Development Plan submission and issued a comment letter on July 25. In addition to other Land Development comments, a few minor sanitary sewer design comments remain outstanding.
- 301 Reservoir Road (5-Lot Residential Subdivision) – We assisted the Design Engineer with response to PADEP's comments on the Sewage Facilities Planning mailer. Responses were provided to PADEP, and PADEP issued a Planning exemption letter on August 6.
- 1712 E. Boot Road – No activity by Pennoni since our last report. The service piping was previously installed, but we are not aware if the grinder pump has been installed.
- 14 Reservoir Road – PADEP approved the Sewage Facilities Planning Mailer exemption on June 5. We received a new plan submission and provided a comment letter on July 12. Amongst other things, two sanitary sewer design comments remain outstanding.
Capital Improvement Plan
- We prepared a 1 st draft of a 20+ year capital improvement plan that includes pipe lining, manhole lining, pump station upgrades, metering, wastewater treatment plant upgrades and equipment replacement, and other improvements. The plan is currently under review with Finance and Public Works. We anticipate the plan will be iteratively edited over the next few weeks, and an updated draft will be presented to the MA in September.
END OF REPORT
Big Fish Environmental Services Inc.
RCSTP Monthly Operations Report
August 2024
Executive Summary
The Ridley Creek sewage treatment plant outfall 001 met all effluent limitations regarding water quality for June 2024. All supplemental reports were submitted for July 2024. Caustic usage increased to 54 gallons from 51 per day last month. Aluminum sulfate solution volumes decreased to 68.8 gallons per day from the previous standard of 70.5 gallons per day. No significant mechanical or operational issues were observed during the sludge dewatering equipment or SBR treatment process. Sludge dewatering experienced no mechanical issues impacting production. There were no odor complaints during the month.
Table 1
July 2024- Final Effluent - Outfall 001
| NPDES Permit Discharge Limitations | Flow | CBOD5 | Total Nitrogen | TSS | NH4-N | Total Phosphorus | Fecal Coliform | Ultraviolet light intesity | Copper, Total | Zinc, Total | ||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/ month | mg/L | lbs/ month | mg/L | lbs/ month | mg/L | lbs/ month | mg/L | lbs/ month | Geo Mean | Geo Mean | ||||
| 0.75 | 10 | 62 | Report | Report | 10 | 62 | 2.5 | 44 | 0.5 | 3 | 200 | 1,000 | ||||
| Inst. Max | 20 | 94 | 15 | 94 | 5 | 1 | Report | Report | Report | |||||||
| Sample Date | ||||||||||||||||
| July 2, 2024 | 0.240 | 2.0 | 4.0 | 9.16 | 18.3 | 4.0 | 8.0 | 0.10 | 0.20 | 0.12 | 0.24 | 1 | 0.0000 | NS | 0.002 | 0.033 |
| July 9, 2024 | 0.217 | 2.0 | 3.6 | 7.42 | 13.4 | 4.0 | 7.2 | 0.10 | 0.18 | 0.30 | 0.54 | 1 | 0.0000 | NS | NS | NS |
| July 16, 2024 | 0.289 | 2.0 | 4.8 | 10.10 | 24.3 | 4.0 | 9.6 | 0.10 | 0.24 | 0.14 | 0.34 | 1 | 0.0000 | NS | NS | NS |
| July 23, 2024 | 0.250 | 2.0 | 4.2 | 7.36 | 15.3 | 4.8 | 10.0 | 0.10 | 0.21 | 0.14 | 0.29 | 1 | 0.0000 | NS | NS | NS |
| July 30, 2024 | ||||||||||||||||
| Average | 0.249 | 2.0 | 4.2 | 8.51 | 17.9 | 4.2 | 8.7 | 0.10 | 0.21 | 0.18 | 0.35 | 1 | 0.0000 | NA | NA | NA |
| Minimum | 0.217 | 2.0 | 3.6 | 7.36 | 13.4 | 4.0 | 7.2 | 0.10 | 0.18 | 0.12 | 0.24 | 1 | 0.0000 | NA | NA | NA |
| Maximum | 0.289 | 2.0 | 4.8 | 10.10 | 24.3 | 4.8 | 10.0 | 0.10 | 0.24 | 0.30 | 0.54 | 1 | 0.0000 | NA | NA | NA |
Treatment Process Operation
Table 1 illustrates the final effluent composite sample data reported for outfall 001 for July 2024. The monthly average total phosphorus was reported as 0.18 mg/L compared to the permit limitation of 0.50 mg/L. The TSS samples consistently showed single digits. The results remain below the weekly maximum of 15 mg/L. The monthly average TSS is reported as 4.2 mg/L compared to the discharge limitation of 10 mg/L.
The final effluent test results demonstrate that the biological treatment performed well during July. The sequencing batch reactors (SBRs) numbered 2, 3, and 4 were in service.
Table 2 represents the influent wastewater data entering the wastewater treatment facility collected at the doghouse manhole adjacent to the influent pump station.in July, 2024
Table 2
July 2024 - Influent Wastewater
| Design Basis | Flow | BOD5 | CBOD5 | TSS | NH4-N | TKN, mg/L | Phosphorus,Total, mg/L | ||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | mg/L | lbs/day | |
| 335 | 2,098 | NA | NA | 320 | 2,001 | 32 | 200 | 48 | 301 | 9.1 | 57 | ||
| Sample Date | |||||||||||||
| July 2, 2024 | 0.298 | 483 | 1,200 | 379 | 942 | 580 | 1,441 | 32.4 | 81 | 94.6 | 235 | 12.9 | 32.1 |
| July 9, 2024 | 0.383 | 615 | 1,964 | 485 | 1,549 | 880 | 2,811 | 36.6 | 117 | 92.5 | 295 | 11.80 | 37.7 |
| July 16, 2024 | 0.383 | 1,180 | 3,769 | 689 | 2,201 | 900 | 2,875 | 39.5 | 126 | 135.0 | 431.2 | 16.90 | 54.0 |
| July 23, 2024 | 0.372 | 625 | 1,939 | 496 | 1,539 | 690 | 2,141 | 39.5 | 123 | 66.8 | 207.2 | 12.40 | 38.5 |
| July 30, 2024 | |||||||||||||
| Average | 0.359 | 726 | 2,218 | 512 | 1,558 | 763 | 2,317 | 37 | 112 | 97.2 | 292 | 13.50 | 40.6 |
| Minimum | 0.298 | 483 | 1,200 | 379.0 | 942 | 580 | 1,441 | 32 | 81 | 66.8 | 207 | 11.80 | 32.1 |
| Maximum | 0.383 | 1,180 | 3,769 | 689 | 2,201 | 900 | 2,875 | 40 | 126 | 135.0 | 431 | 16.90 | 54.0 |
Table 3 represents the water quality data of the flow pumped to Applebrook Golf Course in July 2024
Table 3
July 2024 - Applebrook - Out Fall 002
| NPDES Permit Discharge Limitations | Flow | CBOD5 | Total Nitrogen | TSS | NH4-N | Phosphorus,Total | Fecal Coliform | ||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| MGD Average | mg/L | lbs/ month | mg/L | lbs/ month | mg/L | lbs/ month | mg/L | lbs/ month | mg/L | lbs/ month | Geo Mean | Geo Mean | |
| 0.135 | 25 | Report | Report | 30 | 7.0 | 44 | 0.5 | 3 | 200 | 1,000 | |||
| 40 | 45 | ||||||||||||
| July 2, 2024 | 0.0220 | 2.0 | 0.37 | 9.16 | 18.33 | 4.0 | 0.73 | 0.10 | 0.02 | 0.12 | 0.02 | 1 | 0.0000 |
| July 9, 2024 | 0.0290 | 2.0 | 0.48 | 7.42 | 1.79 | 4.0 | 0.97 | 0.10 | 0.02 | 0.30 | 0.07 | 1 | 0.0000 |
| July 16, 2024 | 0.0270 | 2.0 | 0.45 | 10.10 | 2.27 | 4.0 | 0.90 | 0.10 | 0.02 | 0.14 | 0.03 | 1 | 0.0000 |
| July 23, 2024 | 0.0280 | 2.0 | 0.47 | 7.36 | 1.72 | 4.8 | 1.12 | 0.10 | 0.02 | 0.14 | 0.03 | 1 | 0.0000 |
| July 30, 2024 | |||||||||||||
| Average | 0.0265 | 2.0 | 0.44 | 8.51 | 6.03 | 4.2 | 0.9 | 0.10 | 0.02 | 0.18 | 0.04 | 1 | 0.0000 |
| Minimum | 0.0220 | 2.0 | 0.37 | 7.36 | 1.72 | 4.0 | 0.7 | 0.10 | 0.02 | 0.12 | 0.02 | 1 | 0.0000 |
| Maximum | 0.0290 | 2.0 | 0.48 | 10.10 | 18.33 | 4.8 | 1.1 | 0.10 | 0.02 | 0.30 | 0.07 | 1 | 0.0000 |
Page 2 of 4
PA DEP
No activity
Pennoni Associates
No activity
Significant Rainfall
During July, there were nine (9) days when rainfall occurred.
One (1) event exceeded 0.50 inches of rain in a 24-hour period:
7/22/24: 0.57”
Total Rainfall for July was 3.02 inches
Chemical Data
| Chemical | July 2024 | |
|---|---|---|
| Daily Average | Total Monthly | |
| Caustic Soda, gal | 53.68 | 1,664 |
| Aluminum Sulfate solution, gal | 68.8 | 2,133 |
| Sludge Dewatering, gal* | 21,570 | 539,257 |
*25 days of sludge dewatering
There was an increase of 102,991 gallons of sludge dewatering during July compared to June.
Minor Preventative Maintenance
Flushed chemical feed lines to the SBRs.
Cleaned final effluent weir trough daily.
Skimmed surface of disc filters daily
Drained and cleaned disc filters bi-weekly.
Cleaned buildings and laboratory.
Major Repairs or Upgrades
-Applebrook pump replaced
-SBR 1 blower installed
Upcoming Repairs or Upgrades
Page 3 of 4
- Influent channel Muffin Monster to be replaced
-Disk filter pump to be rebuilt
Flow Data
| Flow Meter Location | July 2024 | ||
|---|---|---|---|
| Total Volume for Month, MG | Average Daily Flow, gpd | Daily Maximum Flow, gpd | |
| Influent Wastewater to Screening Building | 10.729 | 346,105 | 420,110 |
| Influent Wastewater to SBRs | 11.178 | 360,591 | 412,688 |
| Internal Recycle | 0.544 | 17,533 | 49,078 |
| Treated Effluent to Disc Filters | 10.792 | 348,149 | 404,672 |
| Final Effluent Discharge | 7.445 | 240,000 | 297,000 |
| Applebrook Golf Course | 0.830 | 26,789 | 33,232 |
The plant hydraulic design loading is 745,000 gpd.
There were no high-flow events during July
Page 4 of 4
DRAFT
EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
MEETING MINUTES
July 15, 2024
The East Goshen Township Municipal Authority held their regular meeting on Monday, July 15, 2024 at 7:00 pm. at the Township Building.
Members in attendance are indicated in BOLD:
Dana Pizarro, Chairman
Walter Wujcik, Vice Chairman
Jack Yahraes
Carmen Battavio
Kevin Cummings
Also in attendance were: Mark Miller (Director of Public Works), Michele Truitt (Supervisor)
Dave Ware (Finance Director), Robert Jefferson (Attorney) and Erika Addison (Pennoni).
COMMON ACRONYMS:
| ATS – Automatic Transfer Switch | MA- Municipal Authority |
|---|---|
| BFES – Big Fish Environmental Services | NPDES – National Pollutant Discharge Elimination System |
| BOS – Board of Supervisors | PC – Planning Commission |
| CB – Conservancy Board | PM – Prevention Maintenance |
| DEP – Department of Environmental Protection | PR – Park & Recreation Board |
| EPA – Environmental protection Agency | RCSTP – Ridley Creek Sewer Treatment Plant |
| HC – Historical Commission | SBR – Sequencing Batch Reactor |
| I&I – Inflow & Infiltration | SSO – Sanitary System Overflow |
| LCSTP – Lockwood Chase Sewer Treatment Plant | WAS – Waste Activated Sludge |
| PWD – Public Works Department |
Call to Order & Pledge of Allegiance
Dana called the meeting to order at 7:00 pm and led those present in the Pledge of Allegiance.
Dana asked for a moment of silence for our troops, police, EMTs and first responders.
Dana asked if anyone would be recording the meeting. There was no response.
Chairman's Report/Other Members Report
None
SEWER REPORTS
1. Director of Public Works, Mark Miller's report for July 15, 2024.
Monthly Flows – The average daily flow to West Goshen was 833,288 gallons per day.
Meters: The meters were read on a daily basis.
• Flows are down mainly because of the lack of rain and our infiltration repairs.
MA 7-15-24 draft 1
C.C. Collection:
- All pump stations were visited on a daily basis.
- As you may know, we pull pumps on a six-month rotation. In January we pull the number 2 pumps, and in July we pull number 1 pumps.
- This month we started at the Barkway Pump Station and when we pulled the number 2 pump, the rail system collapsed.
- This is being treated as an emergency as we currently have the station held together with rubber bands and bailing twine. Kevin and I met with John Roddy from MGK on July 8 th to come up with a permanent repair.
- Once we got Barkway situated, the crew moved on to the other stations, pulling and installing the pumps. Since moving on from Deckman, we are trying another pump servicing vendor as we were not happy with the last one we used. I reached out to Phoenixville Sewer to see what they were using since the moved on from Deckman and they are using BDS Electric
- We reached out to BDS Electric who has several locations, and they are very interested in doing the work. We dropped off six pumps to BDS to get a repair estimate.
C.C. Interceptor:
- Nothing to report.
R.C. Collection:
- Routine maintenance was performed on a daily basis.
- We pulled the pumps at Hershey Mill and Hunt Country.
- On Sunday, 7/7/24, we received a seal failure at the Hershey Mill Station. Kevin checked the wires, and the ohm reading indicated a seal failure. The pump was pulled and washed down.
- We drained the oil from the pump and found water in the oil sample. The pump was shipped off to BDS Electric.
Ridley Creek Plant
UV Systen
- The Public Works Department assisted the plant operator with much-needed cleanup after the UV installation.
- The new UV is fully operational.
- We are awaiting a startup date from Glasco to go over the unit.
- We have an issue with the length of one of the cords. Mike Ellis reached out to Glasco for a replacement.
Applebrook Golf Course
- Jared from Applebrook Golf Course asked if we could send them more water.
- We are currently pumping 32,000 gallons a day.
- The present pump is the original pump.
- The 2 nd pump burnt up and a replacement will cost $7,000.00. Jared approved the purchase, so I placed the order with BDS Electric.
- The new pump will triple the flow to Applebrook, and should be here by the end of the week of July 15 th .
MA 7-15-24 draft 2
Alarms: 8
PA 1 Calls: 60
Monthly Rainfall: 2.55”
Lateral Repairs or Caps: 2 (in Bow Tree)
2. Pennoni Engineer's Report dated July 15, 2024
Ridley Creek Sewage Treatment Plant (RCSTP)
- Caustic Soda Conversion – Pyrz performed the tank repairs to the tank's outside insulation. Matt Mullin provided as-built photos of the caustic soda plumbing on July 10. We are currently updating the as-built plans accordingly with the provided plumbing information. We previously prepared a draft O&M Manual for the system that was submitted to the Township and operator for review. We will set up a meeting to review now that the system is up and running so that the Manual can be finalized. UV Disinfection System – Zimmerman installed the jib crane and the second UV module, shrouds, and guides on June 11. On June 20, Lenni installed power to the jib crane and relocated the control panel to its permanent location, but it was discovered that the cords to connect the second UV module to the control panel are too short. Pennoni contacted Glasco on June 25 in regard to obtaining a new, longer cord for the module. Glasco responded on July 2 stating that they would review and provide a response accordingly. We contacted Glasco on July 10 for an update on the cords and are waiting for a response. After this issue is resolved, the two week trial of the second UV module will begin. Glasco will also be scheduled to perform a post-startup inspection of the permanent UV installation. The temporary system has been fully disassembled. Pennoni informed Glasco on June 25 that the temporary channel is ready for pickup and for them to coordinate with Mark Miller on the specific day and time of the pickup. An updated tentative construction schedule follows with completed work in italics: Delivery of Permanent UV Equipment – October 30, 2023; Delivery of Bypass Pumps and Hoses – Week of November 13, 2023; Initiate Temporary Bypass Work – Mid-November 2023; Complete Temporary Bypass Work and Initiate Use of Bypass System – January 23, 2024; Two Week Trial and Sampling of Temporary Bypass System – completed February 9, 2024; Township to Perform Concrete Channel Work – completed late-March 2024 (end of initial curing); 2nd Notice to Proceed to Contractors: Permanent Work – Mid-March 2024; Redirect Flow back to Permanent Channel (±30 days of 2nd NTP) – April 24, 2024; Two Week Trial of New UV System in Permanent Channel – April 24 – May 8, 2024; Install Second UV Module into Permanent Channel –- June 11, 2024
MA 7-15-24 draft 3
- Two Week Trial of Second New UV System in Permanent Channel – July 17 – 31, 2024
- Construction Completed –Early-Mid August 2024
We processed Lenni's third payment application and certified payrolls for weeks 1 through 30 for the temporary and permanent electrical work completed and provided a payment recommendation letter on July 10.
We processed Zimmerman's second payment application and certified payrolls for weeks 1 through 3 for the temporary and permanent general contract work and provided a payment recommendation letter on July 10.
- Generator #2 Replacement – No activity by Pennoni since the last report.
- Electrical Surge Evaluation – The Municipal Authority has requested that the electric supply into the plant be evaluated. We recommend that a data logger be installed on the PECO main supply line into the plant. The preferred location to do the testing would be at the Main Distribution Panel (MDP) which is outside near the PECO Transformer. We spoke with Lenni Electric, who concurs with this recommendation, but has not previously installed data loggers before. We are currently reaching out to other parties to install a data logger and to obtain quotes. After which, we can evaluate the type(s) of equipment needed to mitigate any adverse power conditions.
Sanitary Sewer Pipe Rehab
- Chester Creek Sewer Rehab – The Contractor, Insituform, has completed all work. The Contractor still needs to provide the final payment application, closeout documents, and remaining prevailing wage certifications in order to mark the project as completed.
- Supplee Valley Pipe Lining – The next sewer rehabilitation project is planned to be installation of cured-in-place pipe liners in the remaining un-lined sewers in Supplee Valley. The sewers have been televised. Public Works will provide the videos to Pennoni for review, and we will then prepare a bid document. The goal is to construct this work by the end of 2024.
New Connections
- Millstone Meadows (1010 Hershey Mill Road) – No activity by Pennoni since the last report.
- 301 Reservoir Road (5-Lot Residential Subdivision) – The Applicant submitted the Sewage Facilities Planning Mailer to PADEP on July 11.
- 1712 E. Boot Road – No activity by Pennoni since our last report. The service piping was previously installed, but we are not aware that the grinder pump has been installed.
- 14 Reservoir Road – PADEP approved the Sewage Facilities Planning Mailer exemption on June 5. We received a new plan submission that is currently under review.
MA 7-15-24 draft 4
Capital Improvement Plan
- We met with Mark Miller and Dave Ware to discuss long term capital improvement planning. Cost estimates were prepared for pipe lining neighborhoods with asbestos cement pipe. Pipe lining has been prioritized by neighborhood. We are creating a 20+ year capital improvement plan to include pipe lining, manhole lining, pump station upgrades, and wastewater treatment plant upgrades. A draft will be submitted before the August MA meeting for discussion.
Barkway Pump Station
- We are evaluating pump sizing for a diesel bypass pump. We are also contacting vendors for quotes for the bypass pump and for replacement of the submersible pumps.
3. Big Fish Environmental Services –
The Ridley Creek sewage treatment plant outfall 001 met all effluent limitations regarding water quality for June 2024. All supplemental reports were submitted for June 2024. Caustic usage increased to 51 gallons per day from 40 gallons per day last month. Aluminum sulfate solution volumes decreased to a daily average of 70.5 gpd from the previous standard of 74.8 gallons per day. No significant mechanical or operational issues were observed during the sludge dewatering equipment or SBR treatment process. Sludge dewatering experienced no mechanical issues impacting production. There were no odor complaints during the month.
Approval of Minutes
The minutes of the June 10, 2024 meeting were approved.
Approval of Invoices
1. Kevin moved to approve payment of the following Pennoni invoices:
| • Invoice # 1229134 | $ 595.00 |
|---|---|
| • Invoice # 1229135 | $ 463.75 |
| • Credit for Invoice #1221070 & applied to #1229135 | -$226.00 |
| • Invoice #1229136 | $1,412.50 |
| • Invoice #1229137 | $5,109.75 |
Walter seconded the motion. The motion passed unanimously.
2. Kevin moved to approve Payment Application #2 for Zimmerman Environmental RCSTP UV Disinfection System Replacement in the amount of $52,769.70. Waler seconded the motion. The motion passed unanimously.
3. Kevin moved to approve Payment Application #3 for Lenni Electric RCSTP UV Disinfection System Replacement in the amount of $10,110.42. Jack seconded the motion. The motion passed unanimously.
MA 7-15-24 draft 5
4. Walter moved to approve payment of Change Order #2 for Chester Creek Interceptor Inspection & Repair in the amount of $4,360.00. Jack seconded the motion. The motion passed unanimously.
5. Jack moved to approve payment of the following Gawthrop Greenwood invoices:
- Invoice #291598 in the amount of $492.00
- Invoice #293276 in the amount of $1,048.00
Walter seconded the motion. The motion passed unanimously.
6. Kevin moved to approve payment of the Lenni Electric invoice #240631 in the amount of $267.50. Walter seconded the motion. The motion passed unanimously.
Liaison Reports
1. Board of Supervisors - Michele reported that we had a very successful Community Day. She thanked the sponsors and Jason Lang, Director of Parks & Recreation. The BOS will only meet once in July and August. They approved an increase in sewer rates. They will meet every Tuesday in September to work on the budget.
Financial Reports
Dave Ware provided the following report:
Year to date June 2024, the Municipal Authority recorded $402,803.49 in revenues (primarily from Sewer Capital Reserve and Sewer Operating transfers) and $397,824.84 in expenses (RCSTP UV replacement capital costs, Flygt pump, Chester Creek Interceptor work by Insituform Technologies, engineering and audit expenses). The net result of operations is $4,978.65. As of June 30, 2024, the fund balance was $12,540.81.
Old Business
None
Goals – The goals were reviewed.
New Business
1. Memo from Kevin Miller regarding the Barkway Pump Station. They were doing regular maintenance on Pump #1 when the guide rails and flange collapsed. The issue was temporarily resolved but his recommendation is to overhaul the interior of the wet well to meet updated needs. Mark reported that they spoke with MGK Industries Inc., and it will cost $54,560.00 for 3 pumps (1 will be a spare) and about 6 weeks to get everything. Jack moved to approve the purchase of 3 pumps not to exceed $60,000.00. Walter seconded the motion. The motion passed unanimously.
Any Other Matter -
1. Maillie Audit Review Letter – Dale Umbenhauer represented Maillie. Kevin pointed out his concern about wording in the letter regarding risks. Dale explained the new standards they are required to use now. If there were any risks due to fraud, etc., it would require a separate letter. He assured the MA members that there are no problems.
MA 7-15-24 draft 6
2. Greenhill Sewer Authority – Erika needs to determine the cost of this proposed project. DEP notification was discussed.
Correspondence- None
Public Comment - None
Adjournment
There being no further business Jack moved to adjourn the meeting. Walter seconded the motion. The motion passed unanimously. The meeting was adjourned at 8:00 pm.
The next regular meeting will be held on Monday, August 12, 2024 at 7:00 p.m.
Respectfully submitted,
Ruth Kiefer, Recording Secretary
MA 7-15-24 draft 7
Pennoni
INVOICE
Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328
Mark Miller
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Invoice No : 1233192
Invoice Date : 07/25/2024
Project : EGMAU20004
Project Name : RCSTP Caustic Soda Conversion
For Services Rendered Through 07/14/2024
Updated as-built drawings based on updated plumbing information from RCSTP operator.
| Phase Code / Name | Contract Amount | Previously Billed | % Complete | Complete To Date | Amount This Invoice |
|---|---|---|---|---|---|
| 01 -- Design and Permitting | $26,500.00 | $26,500.00 | 100.00% | $26,500.00 | $0.00 |
| 02 -- Construction Phase Services est. | $5,400.00 | $3,463.50 | $3,576.50 | $113.00 | |
| Total : | $31,900.00 | $29,963.50 | $30,076.50 | $113.00 |
Phase: 02 -- Construction Phase Services
Labor
| Class | Hours | Rate | Amount |
|---|---|---|---|
| Associate Professional | 1.00 | 113.00 | 113.00 |
| Labor | 113.00 | ||
| Phase Subtotal | $113.00 | ||
| Amount Due This Invoice | $113.00 |
Outstanding Invoices
| Number | Date | Balance |
|---|---|---|
| 1229134 | 6/26/2024 | 595.00 |
| Total | 595.00 |
APPROVED BY: [signature] 7/25/24
DATE PAID:
CHECK #:
CHARGED TO: 07-429-1520
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
West Goshen RCSTP Caustic Soda Conversion
EGMAU20004 Invoice Summary
Invoice Date 7/25/2024
| Project: | EGMAU20004 | ||
|---|---|---|---|
| Pennoni Job No.: | RCSTP Caustic Soda Conversion | ||
| Invoice No: | 1233192 | ||
| Invoice Period: | 6/17/2024 | to | 7/14/2024 |
| Initial Authorization: | $ 31,900.00 | Date: | 7/25/2024 |
| Contract Amount: | $ 31,900.00 | ||
| Previously Invoiced: | $ 29,963.50 | ||
| Current Invoice: | $ 113.00 | ||
| Invoiced to Date ($): | $ 30,076.50 | ||
| Invoiced to Date (%): | 94% | ||
| Remaining Budget ($): | $ 1,823.50 | ||
| Remaining Budget (%): | 6% |
Budget by Phase:
| Phase Name: | RCSTP Caustic Soda Conversion |
|---|---|
| Phase Budget: | $ 31,900.00 |
| Previously Invoiced: | $ 29,963.50 |
| Current Invoice: | $ 113.00 |
| Invoiced to Date ($): | $ 30,076.50 |
| Invoiced to Date (%): | 94% |
| Remaining Budget ($): | $ 1,823.50 |
| Remaining Budget (%): | 6% |
Comments: Updated as-built drawings based on updated plumbing information from RCSTP operator.
Pennoni
INVOICE
Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328
Mark Miller
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Invoice No : 1233193
Invoice Date : 07/25/2024
Project : EGMAU22004
Project Name : RCSTP UV Replacement
For Services Rendered Through 07/14/2024
Coordinated with Glasco for longer UV module cords. Processed Lenni's pay application #3 and Zimmerman's pay application #2.
Phase 02 Construction Phase Services
Labor
| Class | Hours | Rate | Amount |
|---|---|---|---|
| Associate Professional | 3.00 | 113.00 | 339.00 |
| Totals | 3.00 | 339.00 | |
| Total Labor | 339.00 |
Billing Limits
| Current | Prior | To-Date | |
|---|---|---|---|
| Total Billings | 339.00 | 15,346.50 | 15,685.50 |
| Limit | 16,000.00 | ||
| Remaining | 314.50 | ||
| Total this Phase | $339.00 | ||
| Total this Invoice | $339.00 |
Outstanding Invoices
| Number | Date | Balance |
|---|---|---|
| 1229135 | 6/26/2024 | 463.75 |
| Total | 463.75 |
APPROVED BY: [signature] 7/25/24
DATE PAID:
CHECK #:
CHARGED TO: 07-429-1505
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
RCSTP UV Replacement
EGMAU22004 Invoice Summary
Invoice Date 07/25/2024
| Project: | EGMAU22004 | ||
|---|---|---|---|
| Pennoni Job No.: | RCSTP UV Replacement | ||
| Invoice No: | 1233193 | ||
| Invoice Period: | 6/17/2024 | to | 7/14/2024 |
| Initial Authorization: | $ 30,000.00 | Date: | 7/25/2024 |
| Contract Amount: | $ 60,000.00 | ||
| Previously Invoiced: | $ 59,242.25 | ||
| Current Invoice: | $ 339.00 | ||
| Invoiced to Date ($): | $ 59,581.25 | ||
| Invoiced to Date (%): | 99% | ||
| Remaining Budget ($): | $ 418.75 | ||
| Remaining Budget (%): | 1% |
Budget by Phase:
| Phase Name: | RCSTP UV Replacement |
|---|---|
| Phase Budget: | $ 60,000.00 |
| Previously Invoiced: | $ 59,242.25 |
| Current Invoice: | $ 339.00 |
| Invoiced to Date ($): | $ 59,581.25 |
| Invoiced to Date (%): | 99% |
| Remaining Budget ($): | $ 418.75 |
| Remaining Budget (%): | 1% |
Comments: Coordinated with Glasco for longer UV module cords. Processed Lenni's pay application #3 and Zimmerman's pay application #2.
Pennoni
INVOICE
Remit Payment To:
Pennoni Associates Inc.
P.O. Box 827328
Philadelphia, PA 19182-7328
Mark Miller
East Goshen Municipal Authority
1580 Paoli Pike
West Chester, PA 19380-6199
Invoice No : 1233194
Invoice Date : 07/25/2024
Project : EGMAU24001
Project Name : 2024 General Services
For Services Rendered Through 07/14/2024
Submitted July Engineer's Report.
Continued hydraulic analysis of Ridley Creek collection system to convey potential diversion from Hershey Mill community's wastewater treatment plant.
Prepared draft long-term Capital Improvement Plan project list and budget estimates. Attended meeting with Township staff to review Plan. Created map of neighborhoods proposed for pipe lining. Initated updates to Plan based on staff comments.
Additional work on Chester Creek Interceptor construction project that was beyond Pennoni's original project scope: Processed change order and final payment.
Barkway Pump Station: Reserarched historical plans for pump replacements and wet well upgrades. Analyzed bypass pump siziing. Contacted vendor for quote for new bypass pump and replacement submersible pumps.
Evaluated potentisl DCED grant opportunities for future pipe lining work.
| Billing Limits | Current | Prior | To-Date |
|---|---|---|---|
| Total Billings | 5,142.50 | 12,259.50 | 17,402.00 |
| Limit | 42,000.00 | ||
| Remaining | 24,598.00 |
::::::::Authority Engineer::
Labor
| Labor | Hours | Rate | Amount |
|---|---|---|---|
| Township Engineer | .25 | 153.00 | 38.25 |
| Authority Engineer | 8.25 | 153.00 | 1,262.25 |
| Associate Professional | 34.00 | 113.00 | 3,842.00 |
| Totals | 42.50 | 5,142.50 | |
| Total Labor | 5,142.50 |
APPROVED BY: [Signature] 7/25/24
DATE PAID:
CHECK #:
CHARGED TO: 07-424-3130
Total this Invoice $5,142.50
Continued on next page...
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
| Project | Project Code | Description | Type | Status |
|---|---|---|---|---|
| Project | EGMAU24001 | 2024 General Services | Invoice | <Draft> |
Outstanding Invoices
| Number | Date | Balance |
|---|---|---|
| 1229137 | 6/26/2024 | 5,109.75 |
| Total | 5,109.75 |
INVOICES DUE ON RECEIPT. Invoices outstanding over 30 days will have a Service Charge of 1 1/2% per month.
2024 General Services
EGMAU24001 Invoice Summary
Invoice Date 07/25/2024
| Description | Amount | Reference | Date/Range |
|---|---|---|---|
| Project: | EGMAU24001 | ||
| Pennoni Job No.: | 2024 General Services | ||
| Invoice No: | 1233194 | ||
| Invoice Period: | 6/17/2024 | to | 7/14/2024 |
| Initial Authorization: | $ 42,000.00 | Date: | 7/25/2024 |
| Contract Amount: | $ 42,000.00 | ||
| Previously Invoiced: | $ 12,259.50 | ||
| Current Invoice: | $ 5,142.50 | ||
| Invoiced to Date ($): | $ 12,259.50 | ||
| Invoiced to Date (%): | 29% | ||
| Remaining Budget ($): | $ 29,740.50 | ||
| Remaining Budget (%): | 71% |
Budget by Phase:
| Phase Summary | Amount |
|---|---|
| Phase Name: | 2024 General Services |
| Phase Budget: | $ 42,000.00 |
| Previously Invoiced: | $ 12,259.50 |
| Current Invoice: | $ 5,142.50 |
| Invoiced to Date ($): | $ 12,259.50 |
| Invoiced to Date (%): | 29% |
| Remaining Budget ($): | $ 29,740.50 |
| Remaining Budget (%): | 71% |
Comments: Submitted May and June Engineer's Reports. Reviewed agenda packets and RCSTP operator's reports in preparation for May and June MA meetings. Attended May MA meeting.
Planning for Supplee Valley CIPPL project with Township staff. Initiated preparation of bid document.
RCSTP project updates w/ M. Miller. Evaluated actual caustic soda usage volume for first month of operation in comparison to that projected in study (actual is less than projected). Initiated evaluation of alternatives to monitor and data log electrical spikes at RCSTP.
Initiated preparation of 10-year Capital Improvement Plan project list and budget estimates.
Initiated hydraulic analysis of Ridley Creek collection system to convey potential diversion flows from Hershey Mill community's wastewater treatment plant. Responded to questions on possible diversion from Hershey Mill community representatives.
Additional work on Chester Creek Interceptor construction project that was not part of Pennoni's original project scope: performed review of post-construction pipe lining video, inspection of pipe lining punchlist work, and processed Change Order #2 and Pay Application #4.
Pennoni
July 26, 2024
EGMAU23003
East Goshen Municipal Authority
Attn: Mark Miller, Director of Public Works
1580 Paoli Pike
West Chester, PA 19380
RE: Payment Application #5 Recommendation
Chester Creek Interceptor Inspection and Repair, Contract No. CCSS-2023
Dear Mr. Miller:
The Contractor, Insituform Technologies, LLC, has submitted the fifth and final invoice for work completed for the subject project. We have reviewed the work-in-progress, including lateral reinstatements, and we confirm that the described work has been completed.
We have reviewed the attached Payment Application #5 provided by the Contractor, and we recommend payment in the amount of $11,348.00. Overall, the contract is 100% complete.
The Contractor closeout documents are attached, consisting of the Statement of Surety, Contractor's Release, Maintenance Bond, and President Officer Appointment Letter. The Contractor previously submitted the Maintenance Bond, and we note that the 2-year maintenance period began at the date of substantial completion, which was May 20, 2024.
The certified payrolls for the entire project are also attached.
If you have any questions, please contact me at your convenience.
Sincerely,
PENNONI ASSOCIATES INC.
[Signature]
Michael J. Ellis, PE
Associate Vice President
/ela
Enclosures: Application and Certification for Payment #5
Payment Estimate #5
Closeout Documents
Certified Payrolls
cc: Shivon Shiwpal, Insituform Technologies
Dave Ware, Township Finance Director
Derek Davis, Township Manager
Christiana Executive Campus | T: 302-655-4451 | www.pennoni.com
121 Continental Drive, Suite 207 | Page 1 of 1
Newark, DE 19713
APPLICATION AND CERTIFICATE FOR PAYMENT
AIA DOCUMENT G702 (Instructions on reverse side) PAGE 1 OF 2
| TO | PROJECT | APPLICATION | Distribution |
|---|---|---|---|
| TO: East Goshen Municipal Authority 1580 Paoli Pike West Chester, PA 19380 |
PROJECT: Chester Creek Interceptor Contract No: CCSS-2023 |
APPLICATION NO: 5 - Final PERIOD TO: 5/18/2024 - 7/5/2024 |
Distribution to: [ ] Owner [ ] Engineer [ ] Contractor [ ] |
| FROM: Insituform Technologies, LLC 580 Goddard Ave Chesterfield, MO 63005 |
VIA (ENGINEER): Pennoni Associates Inc. Christiana Executive Campus 121 Continental DR, Suite 207 Newark, DE 19713 |
Engineer's PROJECT NO: CONTRACT DATE: |
CONTRACTOR'S APPLICATION FOR PAYMENT
Application is made for Payment, as shown below, in connection with the Contract, Continuation Sheet, AIA Document G703, is attached.
| CHANGE ORDER SUMMARY | ||
|---|---|---|
| Change Orders approved in previous months by Owner | ADDITIONS | DEDUCTIONS |
| TOTAL | $ 12,750.00 | $ 16,400.00 |
| Approved this Month: Number CO 2, Date Approved 7/10/2024 | $ 7,000.00 | $ 2,640.00 |
| TOTALS | $ 19,750.00 | $ 19,040.00 |
| Net change by Change Orders | $ 710.00 | |
| Line Item | Amount |
|---|---|
| 1 ORIGINAL CONTRACT SUM | $ 214,850.00 |
| 2 Net Change by Change Orders | $ 710.00 |
| 3 CONTRACT SUM TO DATE | $ 215,560.00 |
| 4 TOTAL COMPLETED & STORED TO DATE (Column G on G703) | $ 215,560.00 |
| 5 RETAINAGE: a. 0% of Completed Work (Column D+E on G703): $ - b. % of Stored Material (Column F on G703): Total Retainage (Line 5a + 5b or Total in Column I of G703) |
$ - |
| 6 TOTAL EARNED LESS RETAINAGE (Line 4 less Line 5 Total) | $ 215,560.00 |
| 7 LESS PREVIOUS CERTIFICATES FOR PAYMENT (Line 6 from previous Certificate) | 204,212.00 |
| 8 CURRENT PAYMENT DUE | $ 11,348.00 |
| 9 BALANCE TO FINISH, PLUS RETAINAGE (Line 3 less Line 6) | $ - |
The undersigned Contractor certifies that to the best of the Contractor's knowledge, information and belief the Work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for Work for which previous Certificates for Payment were issued and payments received from the Owner, and that current payment shown herein is now due.
CONTRACTOR: Insituform Technologies, LLC
By: [Signature]
Date: 7/11/2024
Subscribed and sworn to before me this 11th day of July 2024
Notary Public: Debbie S. Sewell
My Commission expires: Jan 02 2026
[Notary Seal: Debbie S. Sewell, Notary Public, State of Delaware, My Commission Expires Jan 02 2026]
PAID
APPROVED BY: [Signature] 7/29/24
DATE PAID:
CHECK #:
CHARGED TO: 07-429-3700
3700
ENGINEER'S CERTIFICATE FOR PAYMENT
In accordance with the Contract Documents, based on on-site observations and the data comprising the above application, the engineer certifies to the Owner that to the best of the Engineer's knowledge, information and belief the Work has progressed as indicated, the quality of the Work is in accordance with the Contract Documents, and the Contractor is entitled to payment of the AMOUNT CERTIFIED.
AMOUNT CERTIFIED: $ 11,348.00
(Attach explanation if amount certified differs from the amount applied for.)
ENGINEER:
BY: [Signature]
DATE: 7/26/2024
This Certificate is not negotiable. The AMOUNT CERTIFIED is payable only to the Contractor named herein. Issuance, payment and acceptance of payment are without prejudice to any rights of the Owner or Contractor under this Contract.
AIA DOCUMENT G702 • APPLICATION AND CERTIFICATE FOR PAYMENT • MAY 1983 EDITION • AIA
THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVENUE, N.W., WASHINGTON, DC 20006
PAYMENT ESTIMATE NO. 5 - Final
PROJECT NO.: CCSS-2023
DATE: 7/5/2024
PERIOD: 5/18/2024 - 7/5/2024
OWNER: East Goshen Municipal Authority
| ITEM | DESCRIPTION OF WORK | BID QUANTITY | UNIT PRICE | TOTAL EXTENSION | WORK COMPLETED PREVIOUS ESTIMATE | WORK COMPLETED CURRENT ESTIMATE | TOTALS | |||
|---|---|---|---|---|---|---|---|---|---|---|
| QUANTITY | AMOUNT | QUANTITY | AMOUNT | QUANTITY | AMOUNT | |||||
| 1 | Clean and Televise 24 Sanitary Sewer. | 4900.00 | $ 15.00 | $ 73,500.00 | 5350 | $ 80,250.00 | $ - | 5,350.0 | $ 80,250.00 | |
| 2 | Televise 4" and 6" Sanitary Sewer Lateral. | 40.00 | $ 50.00 | $ 2,000.00 | 32 | $ 1,600.00 | $ - | 32.0 | $ 1,600.00 | |
| 3 | Cured-In-Place Pipe Lining of 24" Pipe within Township Roads | 360.00 | $ 300.00 | $ 108,000.00 | 351.2 | $ 105,360.00 | $ - | 351.2 | $ 105,360.00 | |
| 4 | Cured-In-Place Pipe Lining of 4" or 6" lateral | $ 400.00 | $ - | $ - | $ - | 0.0 | $ - | |||
| 5 | Lateral T-Connection and Excavated Transitio | $ 4,000.00 | $ - | $ - | $ - | 0.0 | $ - | |||
| 6 | Lateral Reinstatements. | 3.00 | $ 200.00 | $ 600.00 | $ - | 3 | $ 600.00 | 3.0 | $ 600.00 | |
| 7 | Pipe Grouting. | 2.00 | $ 2,500.00 | $ 5,000.00 | 2 | $ 5,000.00 | $ - | 2.0 | $ 5,000.00 | |
| 8 | Manhole Pressure Grouting. Price complete, in place, per each manhol | 4.00 | $ 1,500.00 | $ 6,000.00 | 5 | $ 7,500.00 | $ - | 5.0 | $ 7,500.00 | |
| 9 | Grout | 75.00 | $ 50.00 | $ 3,750.00 | 185 | $ 9,250.00 | $ - | 185.0 | $ 9,250.00 | |
| 10 | Remove Asphalt/Debris from Pipe | 1.00 | $ - | $ - | 1 | $ - | $ - | 1.0 | $ - | |
| 11 | Cut Lateral and Install T- Connection | 1.00 | $ - | $ - | 1 | $ - | $ - | 1.0 | $ - | |
| CO1 | Additional cost to grout a weeping lateral in C027-C026 | 1.00 | $ 6,000.00 | $ 6,000.00 | 1 | $ 6,000.00 | $ - | 1.0 | $ 6,000.00 | |
| CONTRACT TOTAL | $ 204,850.00 | TOTAL | $ 214,960.00 | $ 600.00 | TOTAL | $ 215,560.00 | ||||
JWC Environmental®
2850 Red Hill Ave., STE 125
Santa Ana, CA 92705
(949) 833-3888
| Field | Value |
|---|---|
| Invoice No: | 119462 |
| Date: | 7/12/2024 |
| Order No: | S046842 |
| Page No: | 1 |
| F.O.B: | Origin |
| Sold To | Ship To |
|---|---|
| East Goshen Township 1580 Paoli Pike West Chester , PA 19380 US - UNITED STATES |
East Goshen Township 1580 Paoli Pike West Chester, PA 19380 US - UNITED STATES |
TIN: 45-2771126 DUNNS# 61-059-2388
| CUSTOMER ID | CUSTOMER PO | PAYMENT TERMS | FREIGHT TERMS |
|---|---|---|---|
| 6005886 | 24-01052 | Net 30 | Freight: Prepaid |
| SALES REP ID | SHIPPING METHOD | SHIP DATE | INVOICE DUE DATE |
| 035 | Old Dominion Freight Line | 7/12/2024 | 8/11/2024 |
| LI# | QUANTITY | PART | DESCRIPTION | X | ||
|---|---|---|---|---|---|---|
| ORD | SHP | BCK | ||||
| 1 | 1 | 1 | 0 | EVAL_CA | CMD3210-XDS2.0 S020646-2-1 |
|
| 2 | 1 | 1 | 0 | CMD3210-XDS2.0 | CMD3210-XDS2.0 Upgrade 7-tooth 2-zone Monster Stack™ Zone 2: 7-tooth .438 thick cam cutters Zone 1: 7-tooth .438 thick cam cutters, double-stacked Alloy Steel Buna N Elastomers Cork & Rubber Gaskets Drum Side Rails Vertical Shaft Support with Grease Line Motor Type: Electric Less Motor Less Reducer Less Spool With 1/4" Perforated Drum with brushes Paint: Epoxy Green Grinder SN: S046842-2-1 |
|
| 3 | 2 | 2 | 0 | MANUALS | O&M MANUALS Included with equipment (2) Copies |
|
| 4 | 1 | 1 | 0 | AMA0160-3200-480-35 | BRUSH KIT, AMA3200-480 35DEG | |
| 5 | 1 | 1 | 0 | Shipping | Shipping & Handling Included | |
PAID
APPROVED BY: [Signature] 7/23/24
DATE PAID:
CHECK #:
CHARGED TO: 07-424-7490
Ridley Creek
| Description | Amount |
|---|---|
| SUB TOTAL: | $27,691.19 |
| SALES TAX: | $0.00 |
| TOTAL AMOUNT DUE: | $27,691.19 |
PLEASE REFERENCE THIS INVOICE NUMBER ON YOUR CHECK AND REMIT TO:
JWC Environmental Inc.
2850 Red Hill Ave Ste 125
Santa Ana, CA 92705
IF PAYING BY ACH OR WIRE: ACH/WIRE INSTRUCTIONS
Dana Gieder
From: Mike Moffa <MMoffa@westgoshen.org>
Sent: Tuesday, July 16, 2024 1:29 PM
To: David Ware; Derek Davis; Mark Miller; Dana Gieder
Cc: Tina Charron; Chris Bashore; Matthew Froncillo; Christine Riffey
Subject: West Goshen Wastewater - Capital Project Billing
Attachments: West Goshen Sewer Authority Capital Cost Payments from Outside Municipalities.pdf; WG SA, 2023 Bond Projects - EG.pdf; WG SA, 2023 Tapping Fund Projects - EG.pdf
Follow Up Flag: Follow up
Flag Status: Completed
Good afternoon,
Please find attached two invoices for your township’s share of the 2023 Capital Purchases of the West Goshen Sewer Authority. These costs are independent of, and in addition to, the O&M costs forwarded to you yesterday. Unlike the O&M invoices, we ask that a separate check is made for each of the Sewer Authority invoices. Please see the attached memo, WG Sewer Authority Capital Cost Payments from Outside Municipalities, for an explanation of why separate checks are required.
Please note, the total amount due is $13,957 less than the projection provided for your township at our 9/21/2023 partner meeting. The invoices attached are as follows and should be made payable to the West Goshen Sewer Authority:
- WG SA, 2023 Bond Fund Projects - EG. Amount Due $95.64.
- WG SA, 2023 Tapping Fund Projects - EG. Amount Due $31,392.87.
Thank you for your cooperation and please do not hesitate to contact me with any questions,
Michael Moffa
Wastewater Superintendent
West Goshen STP
848 S. Concord Road / West Chester, PA 19382
O: 610.696.0900 / F: 610.429.9360
[West Goshen Township Seal]
1
[West Goshen Township Seal]
Memorandum
To: Mike Moffa
From: Christine Riffey
Date: April 15, 2024
Re: West Goshen Sewer Authority Capital Cost Payments from Outside Municipalities
At the end of each fiscal year, the West Goshen Sewer Authority submits capital cost reimbursement requests to each of the four outside municipalities with which a treatment agreement has been engaged. Per these agreements, each municipality is responsible for a certain cost share of various repairs and improvements made to the sewer plant and sewer system. These reimbursement requests are billed utilizing two distinct invoices based on the financing source for each specific repair or improvement.
In 2017, the West Goshen Sewer Authority obtained a bond in order to fund specific repair projects related to the sewer system. The bond requirements mandate that all expenses, and subsequent reimbursements, be managed through the bond trustee, which involves a separate account to be strictly maintained and utilized by a third party for all transactions related to projects funded through bond proceeds. To date, these bond projects remain ongoing. While the West Goshen Sewer Authority uses bond funds for certain specified projects, other projects are funded through general operating revenues which are directly managed by Township.
When reimbursement requests are submitted, the funds to be received need to be recognized by two different parties, at two different financial institutions. Bond funds cannot be comingled with operating funds and it is not possible to deposit a single check into two separate banks. Therefore, it is necessary for each municipality to submit two individual checks in accordance to the invoices that were distributed.
Please do not hesitate to contact me with additional questions or for further information.
Page 1
West Goshen Sewer Authority
[West Goshen Township Seal]
848 S. Concord Road
West Chester, PA 19382
P: 610-696-0900
F: 610-429-9360
INVOICE
| Field | Value |
|---|---|
| Date: | July 15, 2024 |
| Invoice #: | EG23-B |
| For: | 2023 WG Sewer Authority Bond Fund Expenses |
| Bill To: | East Goshen Township 1580 Paoli Pike West Chester, PA 19380 |
| DESCRIPTION | AMOUNT |
|---|---|
| Costs (Bond funded) for projects of the West Goshen Sewer Authority as per Memorandum Agreement No. VIII of June 20, 2017 for the period of January 01, 2023 through December 31, 2023 (details attached). | 573.70 |
PAID
APPROVED BY: [Signature] 7/23/24
DATE PAID:
CHECK #:
CHARGED TO: 07-429-6100
| Item | Amount |
|---|---|
| SUBTOTAL | $573.70 |
| Capacity % | 16.67% |
| OTHER | $0.00 |
| TOTAL | $95.64 |
Please make check payable to:
WEST GOSHEN SEWER AUTHORITY
THANK YOU!
West Goshen Sewer Authority
BOND FUND
Expense Detail - 2023
East Goshen Township
| Project | Vendor | Amount Allocated |
|---|---|---|
| SCADA (Equipment) | REFUND AMAZON SHIP CHARGES | -5.99 |
| SCADA (Equipment) | REFUND AMAZON SHIP CHARGES | -20.31 |
| SCADA (Equipment) | HELP NOW | 600.00 |
| Total Allocated | 573.70 |
Page 2 of 2
West Goshen Sewer Authority
[West Goshen Township Seal]
848 S. Concord Road
West Chester, PA 19382
P: 610-696-0900
F: 610-429-9360
INVOICE
| Field | Value |
|---|---|
| Date: | July 15, 2024 |
| Invoice #: | EG23-T |
| For: | 2023 WG Sewer Authority Tapping Fee Fund Expenses |
| Bill To: | East Goshen Township 1580 Paoli Pike West Chester, PA 19380 |
| DESCRIPTION | AMOUNT |
|---|---|
| Costs (Tapping Fund) for projects of the West Goshen Sewer Authority as per Memorandum Agreement No. VIII of June 20, 2017 for the period of January 01, 2023 through December 31, 2023 (details attached). | 188,319.53 |
PAID
APPROVED BY: [Signature] 7/29/24
DATE PAID:
CHECK #:
CHARGED TO: 07-429-6100
| Item | Amount |
|---|---|
| SUBTOTAL | $188,319.53 |
| Capacity % | 16.67% |
| OTHER | $0.00 |
| TOTAL | $31,392.87 |
Please make check payable to:
WEST GOSHEN SEWER AUTHORITY
THANK YOU!
West Goshen Sewer Authority
TAPPING FEE FUND
Expense Detail - 2023
East Goshen Township
| Project | Vendor | Amount Allocated |
|---|---|---|
| ACTUATED VALVE | L-B WATER SERVICE, INC. | 8,666.10 |
| ACTUATED VALVE | OPTIMUM CONTROLS CORPORATION | 3,744.37 |
| EQ BLOWER ROOF | WILLIAM M DUNLEAVY & CO, INC. | 7,200.00 |
| HEADWORKS - CONVEYOR LINER | KAPPE ASSOCIATES INC | 5,200.00 |
| MAG STRAINER - REIMBURSE SEWER | WEST GOSHEN TOWNSHIP | 5,673.68 |
| PRIMARY CLARIFIER #1 | G.M.H. ASSOCIATES OF AMERICA, INC. | 22,661.00 |
| PRIMARY CLARIFIER #1 | G.M.H. ASSOCIATES OF AMERICA, INC. | 22,661.00 |
| PRIMARY CLARIFIER #1 | G.M.H. ASSOCIATES OF AMERICA, INC. | 1,435.76 |
| PRIMARY CLARIFIER #1 | GS DEVELOPERS INC. | 1,180.00 |
| PRIMARY CLARIFIER #1 | GS DEVELOPERS INC. | 4,620.00 |
| RAS VFD REPLACEMENT | OPTIMUM CONTROLS CORPORATION | 7,194.00 |
| RAS VFD REPLACEMENT | OPTIMUM CONTROLS CORPORATION | 961.62 |
| SCADA - PROF SERVICES | HELP NOW | 950.00 |
| SCADA - PROF SERVICES | OPTIMUM CONTROLS CORPORATION | 7,245.00 |
| SCADA - PROF SERVICES | OPTIMUM CONTROLS CORPORATION | 19,950.00 |
| SCADA - PROF SERVICES | OPTIMUM CONTROLS CORPORATION | 14,440.00 |
| UV REHAB PARTS | XYLEM WATER SOLUTIONS USA INC. | 10,783.40 |
| UV REHAB PARTS | XYLEM WATER SOLUTIONS USA INC. | 5,979.00 |
| UV REHAB PARTS | XYLEM WATER SOLUTIONS USA INC. | 16,417.80 |
| WWTP TRANSFORMER | HERBERT, ROWLAND & GRUBIC, INC. | 307.50 |
| WWTP TRANSFORMER | HERBERT, ROWLAND & GRUBIC, INC. | 1,595.00 |
| WWTP TRANSFORMER | HERBERT, ROWLAND & GRUBIC, INC. | 665.00 |
| TMDL | UNRUH TURNER BURKE & FREES | 42.00 |
| TMDL | HERBERT, ROWLAND & GRUBIC, INC. | 300.00 |
| TMDL | HANGLEY, ARONCHICK, SEGAL, PUDLIN & SCHILLE | 2,419.30 |
| TMDL | UNRUH TURNER BURKE & FREES | 231.00 |
| TMDL | HANGLEY, ARONCHICK, SEGAL, PUDLIN & SCHILLE | 1,664.50 |
| TMDL | UNRUH TURNER BURKE & FREES | 84.00 |
| TMDL | HERBERT, ROWLAND & GRUBIC, INC. | 1,200.00 |
| TMDL | HANGLEY, ARONCHICK, SEGAL, PUDLIN & SCHILLE | 6,642.50 |
| TMDL | HERBERT, ROWLAND & GRUBIC, INC. | 200.00 |
| TMDL | UNRUH TURNER BURKE & FREES | 231.00 |
| TMDL | HANGLEY, ARONCHICK, SEGAL, PUDLIN & SCHILLE | 2,737.00 |
| TMDL | HERBERT, ROWLAND & GRUBIC, INC. | 600.00 |
| TMDL | UNRUH TURNER BURKE & FREES | 63.00 |
| TMDL | HANGLEY, ARONCHICK, SEGAL, PUDLIN & SCHILLE | 1,686.00 |
| TMDL | HERBERT, ROWLAND & GRUBIC, INC. | 500.00 |
| TMDL | UNRUH TURNER BURKE & FREES | 189.00 |
| Total Allocated | 188,319.53 |
Page 2 of 2
Gawthrop Greenwood, PC
Attorneys at Law
(p) 610-696-8225
(f) 610-344-0922
gglaw@gawthrop.com
www.gawthrop.com
GAWTHROP GREENWOOD CLIENT INVOICE
Please Mail checks to:
P.O. Box 562
West Chester, PA 19381-0562
To Make a Payment with a Credit Card, please visit:
https://secure.lawpay.com/pages/gawthrop/operating
Page: 1
08/05/2024
Client No: 6604-001M
Invoice No. 293953
East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380
APPROVED BY: [Signature] 8/6/24
DATE PAID:
CHECK #:
CHARGED TO: 07-424-3140
General Authority Services
Fees
| Date / Timekeeper | Description | Hours | Amount |
|---|---|---|---|
| 07/12/2024 PMM |
Email from L. Werkheiser with meeting agenda and materials; Review and analyze same. | 0.30 | 61.50 |
| 07/15/2024 RCJ |
Attend meeting of Authority Board. | 1.30 | 253.50 |
| For Current Services Rendered | 1.60 | 315.00 | |
Recapitulation
| Timekeeper | Hours | Hourly Rate | Total |
|---|---|---|---|
| Patrick M. McKenna, Esquire | 0.30 | $205.00 | $61.50 |
| Robert C. Jefferson, Esquire | 1.30 | 195.00 | 253.50 |
| Description | Amount |
|---|---|
| Previous Balance | $1,540.00 |
| Total Current Charges | 315.00 |
| 07/23/2024 Payment | -492.00 |
| 07/23/2024 Payment | -1,048.00 |
| Total Payments | -1,540.00 |
| Balance Due | $315.00 |
To ensure proper credit, please write your client number on your check when returning payment.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.
Gawthrop Greenwood, PC
Attorneys at Law
(p) 610-696-8225
(f) 610-344-0922
gglaw@gawthrop.com
www.gawthrop.com
GAWTHROP GREENWOOD CLIENT INVOICE
Please Mail checks to:
P.O. Box 562
West Chester, PA 19381-0562
To Make a Payment with a Credit Card, please visit:
https://secure.lawpay.com/pages/gawthrop/operating
Page: 1
08/05/2024
Client No: 6604M
East Goshen Municipal Authority
1580 Paoli Pike
West Chester PA 19380
| Previous Balance | Fees | Expenses | Payments | Balance |
|---|---|---|---|---|
| 6604-001 General Authority Services | ||||
| 1,540.00 | 315.00 | 0.00 | -1,540.00 | $315.00 |
To ensure proper credit, please write your client number on your check when returning payment.
A finance charge of 1.25% per month (15% annually) may be charged on balances not paid 60 days after the invoice date.
Memo
To: Municipal Authority
From: Dave Ware
Re: MA July 2024 YTD Financial Report
Date: August 5, 2024
YTD July 2024, the Municipal Authority recorded $534,087.84 in revenues (primarily from Sewer Capital Reserve and Sewer Operating transfers) and $528,781.16 in expenses (RCSTP UV replacement capital costs, Flygt pump, Chester Creek Interceptor work by Insituform Technologies, West Goshen capital sewer tapping and bond, engineering and audit expenses). The net result of operations is $5,306.68. As of July 31, 2024, the fund balance was $6,688.76.
Attached is a complete list of 2024 YTD detailed MA revenues and expenses.
U:\dware\municipal authority\
EAST GOSHEN TOWNSHIP
Municipal Authority Fund
YTD July 2024
| Account Id | Account Description | Annual Budget | Current YTD | Prior YTD |
|---|---|---|---|---|
| REVENUE | ||||
| 07-341-1000 | INTEREST EARNINGS | 0.00 | 224.80 | 155.42 |
| 07-364-1100 | C.C. TAPPING FEES | 2,300.00 | 0 | 0 |
| 07-364-1110 | R.C.TAPPING FEES | 8,574.08 | 2,084.88 | 4,584.88 |
| 07-364-1130 | CONNECTION FEES - SEWER | 1,127.52 | 563.76 | 563.76 |
| 07-380-1000 | MISCELLANEOUS REVENUE | 564.06 | 282.24 | 282.24 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 109,517.00 | 94,097.57 | 59,923.00 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 837,464.00 | 436,834.59 | 418,662.32 |
| Total Revenue | 959,546.66 | 534,087.84 | 484,171.62 | |
| EXPENSES | ||||
| 07-424-1400 | ADMINISTRATIVE WAGES | 39,847.10 | 22,380.52 | 19,343.25 |
| 07-424-3000 | MISCELLANEOUS EXPENSE | 3,286.22 | 1,056.61 | 1,595.25 |
| 07-424-3110 | MUNIC.AUTH.-AUDITING | 21,630.00 | 11,250.00 | 10,500.00 |
| 07-424-3130 | ENGINEERING SERVICES | 48,667.50 | 16,786.50 | 22,622.00 |
| 07-424-3140 | LEGAL SERVICES | 8,652.00 | 3,934.50 | 3,292.50 |
| 07-424-3700 | CHESTER CREEK ENGINEERING | 0.00 | 10,567.25 | 0 |
| 07-424-7490 | CAP.REPLACEMENT R.C. | 310,500.00 | 27,691.19 | 0.00 |
| 07-429-1503 | HERSHEYS MILL PUMP STATION CAPITAL | 85,000.00 | 0 | 10,240.62 |
| 07-429-1505 | RCSTP CAPITAL | 366,963.84 | 198,696.08 | 109,819.66 |
| 07-429-1510 | HERSHEY'S MILL ESTATES PROJECT | 0.00 | 0 | 90,113.64 |
| 07-429-1520 | RCSTP - CAUSTIC SODA | 0.00 | 718.00 | 31,459.97 |
| 07-429-3700 | CHESTER CREEK CAPITAL | 0.00 | 204,212.00 | 0 |
| 07-429-6100 | WEST GOSHEN CAPITAL | 75,000.00 | 31,488.51 | 182,262.24 |
| Total Expenses | 959,546.66 | 528,781.16 | 481,249.13 | |
| Net Result From Operations | 0.00 | 5,306.68 | 2,922.49 | |
Municipal Authority
YTD Revenues and Expenses thru 7/31/2024
| Account Number | Account Description | Date | Type | Transaction Data/Comment | Amount |
|---|---|---|---|---|---|
| 07-341-1000 | INTEREST EARNINGS | 01/31/24 | Revenue Journal | INTEREST EARNED JANUARY 2024 | 35.21 |
| 07-341-1000 | INTEREST EARNINGS | 02/29/24 | Revenue Journal | INTEREST EARNED FEBRUARY 2024 | 41.23 |
| 07-341-1000 | INTEREST EARNINGS | 03/31/24 | Revenue Journal | INTEREST EARNED MARCH 2024 | 50.34 |
| 07-341-1000 | INTEREST EARNINGS | 04/30/24 | Revenue Journal | INTEREST EARNED APRIL 2024 | 16.09 |
| 07-341-1000 | INTEREST EARNINGS | 05/31/24 | Revenue Journal | INTEREST EARNED MAY 2024 | 13.17 |
| 07-341-1000 | INTEREST EARNINGS | 06/30/24 | Revenue Journal | INTEREST EARNED JUNE 2024 | 38.57 |
| 07-341-1000 | INTEREST EARNINGS | 07/31/24 | Revenue Journal | INTEREST EARNED JULY 2024 | 30.19 |
| 07-364-1110 | R.C.TAPPING FEES | 01/02/24 | Revenue Journal | 1577 COLONIAL LN | 297.84 |
| 07-364-1110 | R.C.TAPPING FEES | 02/01/24 | Revenue Journal | 1577 COLONIAL LN | 297.84 |
| 07-364-1110 | R.C.TAPPING FEES | 03/01/24 | Revenue Journal | 1577 COLONIAL LN | 297.84 |
| 07-364-1110 | R.C.TAPPING FEES | 04/01/24 | Revenue Journal | 1577 COLONIAL LN | 297.84 |
| 07-364-1110 | R.C.TAPPING FEES | 05/01/24 | Revenue Journal | 1577 COLONIAL LN | 297.84 |
| 07-364-1110 | R.C.TAPPING FEES | 06/04/24 | Revenue Journal | 1577 COLONIAL LN | 297.84 |
| 07-364-1110 | R.C.TAPPING FEES | 07/01/24 | Revenue Journal | 1577 COLONIAL LN | 297.84 |
| 07-364-1130 | CONNECTION FEES - SEWER | 01/25/24 | Revenue Journal | CONNECTION FEE INSTALLMENT INV# 13262 | 281.88 |
| 07-364-1130 | CONNECTION FEES - SEWER | 04/24/24 | Revenue Journal | CONNECTION FEE INSTALLMENT INV# 13263 | 281.88 |
| 07-380-1000 | MISCELLANEOUS REVENUE | 01/25/24 | Revenue Journal | PINE ROCK INTEREST PORTION - STOFFLET | 141.12 |
| 07-380-1000 | MISCELLANEOUS REVENUE | 04/24/24 | Revenue Journal | PINE ROCK INTEREST PORTION - PAPPANO | 141.12 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 01/09/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 431.00 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 01/11/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 533.00 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 02/14/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 4,349.75 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 02/22/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 500.00 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 03/11/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 749.00 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 03/15/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 6,041.00 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 03/21/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 7,000.00 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 03/26/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 245.00 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 03/27/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 11,190.26 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 04/01/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 62.61 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 04/03/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 5,874.75 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 04/09/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 431.00 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 05/14/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 5,996.50 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 05/21/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 3,750.00 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 06/27/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 492.00 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 06/27/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 11,190.26 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 07/16/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 7,570.25 |
| 07-392-0500 | TRANSFER FROM SEWER OPERATING | 07/29/24 | Revenue Journal | XFER FROM 05 SEWER OPERATING TO 07 MA | 27,691.19 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 01/02/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 1,720.00 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 01/05/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 94.02 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 01/10/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 97.00 |
Page 1 of 4
Municipal Authority
YTD Revenues and Expenses thru 7/31/2024
| Account Number | Account Description | Date | Type | Transaction Data/Comment | Amount |
|---|---|---|---|---|---|
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 01/26/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 14,805.16 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 01/26/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 9,530.65 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 01/31/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 4,136.12 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 02/06/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 6,860.00 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 02/08/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 91.92 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 02/14/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 4,598.99 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 02/15/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 73,665.00 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 02/22/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 5,848.97 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 02/27/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 46,517.00 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 02/29/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 923.91 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 03/05/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 3,703.78 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 03/06/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 800.00 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 03/11/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 3,991.86 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 03/15/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 37,659.48 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 03/21/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 3,101.53 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 04/01/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 558.07 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 04/03/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 1,690.00 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 04/09/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 1,375.00 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 05/14/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 1,694.25 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 06/06/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 117,677.00 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 07/16/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 64,206.37 |
| 07-392-0900 | TRANSFER FROM SEWER CAP RESERVE | 07/29/24 | Revenue Journal | XFER FROM 09 SEWER CAP TO 07 MA | 31,488.51 |
| Total Revenue | 534,087.84 | ||||
| 07-424-1400 | ADMINISTRATIVE WAGES | 03/26/24 | Pay Check: 706 | 24-00730 QTR 1 2024 MA CHARGE BACK | 11,190.26 |
| 07-424-1400 | ADMINISTRATIVE WAGES | 06/27/24 | Pay Check: 708 | 24-01495 QTR 2 2024 MA CHARGE BACK | 11,190.26 |
| 07-424-3000 | MISCELLANEOUS EXPENSE | 03/11/24 | Pay Check: 3493 | 24-00582 2024 ANNUAL DAILY DISCHARGE CA | 749.00 |
| 07-424-3000 | MISCELLANEOUS EXPENSE | 03/26/24 | Pay Check: 3502 | 24-00722 PREP SEAL &PAINT BLOCK CHAMBER | 245.00 |
| 07-424-3000 | MISCELLANEOUS EXPENSE | 04/01/24 | Pay Check: 707 | 24-00765 VARIOUS PURCHASES- SEE NOTES | 27.02 |
| 07-424-3000 | MISCELLANEOUS EXPENSE | 04/01/24 | Pay Check: 707 | 24-00765 VARIOUS PURCHASES- SEE NOTES | 35.59 |
| 07-424-3110 | MUNIC.AUTH.-AUDITING | 02/22/24 | Pay Check: 3486 | 24-00447 PROGRESS BILLING AUDIT EGT MUA | 500.00 |
| 07-424-3110 | MUNIC.AUTH.-AUDITING | 03/21/24 | Pay Check: 3501 | 24-00676 PROGRESS BILLING AUDIT EGT MUA | 7,000.00 |
| 07-424-3110 | MUNIC.AUTH.-AUDITING | 05/21/24 | Pay Check: 3509 | 24-01183 FINAL BILLING AUDIT EGT MUA | 3,750.00 |
| 07-424-3130 | ENGINEERING SERVICES | 02/14/24 | Pay Check: 3483 | 24-00380 SERV THRU 011424 23 CHAPTER 94 | 744.50 |
| 07-424-3130 | ENGINEERING SERVICES | 02/14/24 | Pay Check: 3483 | 24-00381 SERV THRU 011424 2024 GEN SERV | 799.75 |
| 07-424-3130 | ENGINEERING SERVICES | 02/14/24 | Pay Check: 3483 | 24-00384 SERV THRU 011424 2023 GEN SERV | 521.50 |
| 07-424-3130 | ENGINEERING SERVICES | 03/15/24 | Pay Check: 3497 | 24-00647 SERV THRU 021124 23 CHAPTER 94 | 649.75 |
| 07-424-3130 | ENGINEERING SERVICES | 03/15/24 | Pay Check: 3497 | 24-00648 SERV THRU 021124 2024 GEN SERV | 725.00 |
Page 2 of 4
Municipal Authority
YTD Revenues and Expenses thru 7/31/2024
| Account Number | Account Description | Date | Type | Transaction Data/Comment | Amount |
|---|---|---|---|---|---|
| 07-424-3130 | ENGINEERING SERVICES | 04/03/24 | Pay Check: 3503 | 24-00780 SERV THRU 031724 2024 GEN SERV | 1,609.50 |
| 07-424-3130 | ENGINEERING SERVICES | 04/03/24 | Pay Check: 3503 | 24-00779 SERV THRU 031724 23 CHAPTER 94 | 1,101.75 |
| 07-424-3130 | ENGINEERING SERVICES | 05/14/24 | Pay Check: 3508 | 24-01143 SERV THRU 041424 2024 GEN SERV | 4,015.50 |
| 07-424-3130 | ENGINEERING SERVICES | 05/14/24 | Pay Check: 3508 | 24-01142 SERV THRU 041424 23 CHAPTER 94 | 1,509.50 |
| 07-424-3130 | ENGINEERING SERVICES | 07/16/24 | Pay Check: 3514 | 24-01661 SERV THRU 061624 2024 GEN SERV | 5,109.75 |
| 07-424-3140 | LEGAL SERVICES | 01/11/24 | Pay Check: 3474 | 24-00076 LEGAL SERV DEC 2023 GEN AUTH | 533.00 |
| 07-424-3140 | LEGAL SERVICES | 02/14/24 | Pay Check: 3481 | 24-00378 LEGAL SERV JAN 2024 GEN AUTH | 528.50 |
| 07-424-3140 | LEGAL SERVICES | 03/15/24 | Pay Check: 3496 | 24-00635 LEGAL SERVICES 2/5-2/12/24 GEN | 430.50 |
| 07-424-3140 | LEGAL SERVICES | 04/09/24 | Pay Check: 3505 | 24-00826 LEGAL SERV MARCH 2024 GEN AUTH | 431.00 |
| 07-424-3140 | LEGAL SERVICES | 05/14/24 | Pay Check: 3507 | 24-01141 LEGAL SERV APRIL 2024 GEN AUTH | 471.50 |
| 07-424-3140 | LEGAL SERVICES | 06/27/24 | Pay Check: 3511 | 24-01450 LEGAL SERV MAY 2024 GEN AUTH | 492.00 |
| 07-424-3140 | LEGAL SERVICES | 07/16/24 | Pay Check: 3512 | 24-01657 LEGAL SERV JUNE 2024 GEN AUTH | 1,048.00 |
| 07-424-3700 | CHESTER CREEK ENGINEERING | 02/14/24 | Pay Check: 3483 | 24-00383 SERV THRU 011424 CHESTER CREEK | 1,755.50 |
| 07-424-3700 | CHESTER CREEK ENGINEERING | 03/15/24 | Pay Check: 3497 | 24-00645 SERV THRU 021124 CHESTER CREEK | 4,235.75 |
| 07-424-3700 | CHESTER CREEK ENGINEERING | 04/03/24 | Pay Check: 3503 | 24-00782 SERV THRU 031724 CHESTER CREEK | 3,163.50 |
| 07-424-3700 | CHESTER CREEK ENGINEERING | 07/16/24 | Pay Check: 3514 | 24-01660 SERV THRU 061624 CHESTER CREEK | 1,412.50 |
| 07-424-7490 | CAP.REPLACEMENT R.C. | 07/29/24 | Pay Check: 3516 | 24-01742 CMD3210-XDS2.0 MUFFIN MONSTER | 27,691.19 |
| 07-429-1505 | RCSTP CAPITAL | 01/05/24 | Pay Check: 3472 | 24-00033 TYPE B C&G 3" COUOLER X M NPT | 94.02 |
| 07-429-1505 | RCSTP CAPITAL | 01/10/24 | Pay Check: 703 | 24-00056 VARIOUS PURCHASES- SEE NOTES | 97.00 |
| 07-429-1505 | RCSTP CAPITAL | 01/17/24 | Pay Check: 3475 | 24-00098 RC ST-RAN CONDUIT FOR TEMP PUM | 9,530.65 |
| 07-429-1505 | RCSTP CAPITAL | 01/26/24 | Pay Check: 3476 | 24-00041 ADAPTER 4" FNPT X 6" MCAM | 429.92 |
| 07-429-1505 | RCSTP CAPITAL | 01/26/24 | Pay Check: 3476 | 24-00041 ADAPTER 6" FRMALE CAM X MNPT | 1,337.24 |
| 07-429-1505 | RCSTP CAPITAL | 01/26/24 | Pay Check: 3476 | 24-00041 HOSE 6" X 50' CAMLOCK LAYFLAT | 12,392.88 |
| 07-429-1505 | RCSTP CAPITAL | 01/26/24 | Pay Check: 3476 | 24-00041 DELIVERY | 645.12 |
| 07-429-1505 | RCSTP CAPITAL | 01/31/24 | Pay Check: 3477 | 24-00210 SAND BAR (YELLOW) & BAGS | 67.00 |
| 07-429-1505 | RCSTP CAPITAL | 01/31/24 | Pay Check: 3478 | 24-00237 HOSE 6"X10' HD TANK TRUCK CAML | 4,069.12 |
| 07-429-1505 | RCSTP CAPITAL | 02/06/24 | Pay Check: 3479 | 24-00271 TROUGH AND CMU WALL ABLATION | 6,860.00 |
| 07-429-1505 | RCSTP CAPITAL | 02/08/24 | Pay Check: 704 | 24-00317 VARIOUS PURCHASES- SEE NOTES | 91.92 |
| 07-429-1505 | RCSTP CAPITAL | 02/14/24 | Pay Check: 3482 | 24-00379 RCSTP- UV REPLACEMENT PYMT 1 | 4,296.24 |
| 07-429-1505 | RCSTP CAPITAL | 02/14/24 | Pay Check: 3483 | 24-00382 SERV THRU 011424 RCSTP GENERAT | 302.75 |
| 07-429-1505 | RCSTP CAPITAL | 02/22/24 | Pay Check: 3484 | 24-00426 UV SYSTEM INSTALLATION-FILTER | 1,427.00 |
| 07-429-1505 | RCSTP CAPITAL | 02/22/24 | Pay Check: 3484 | 24-00425 DISK FILTER#1 FAILURE, ALARM T | 300.00 |
| 07-429-1505 | RCSTP CAPITAL | 02/22/24 | Pay Check: 3485 | 24-00436 PIPING FOR NEW MUFFIN MONSTER | 3,980.40 |
| 07-429-1505 | RCSTP CAPITAL | 02/22/24 | Pay Check: 3487 | 24-00437 ELECTICAL PARTS-INSTL MUFFIN M | 141.57 |
| 07-429-1505 | RCSTP CAPITAL | 02/27/24 | Pay Check: 3489 | 24-00513 FLYGT NP-3171.095 6" SUBMERSIB | 33,647.00 |
| 07-429-1505 | RCSTP CAPITAL | 02/29/24 | Pay Check: 705 | 24-00520 VARIOUS PURCHASES- SEE NOTES | 794.81 |
| 07-429-1505 | RCSTP CAPITAL | 02/29/24 | Pay Check: 705 | 24-00520 VARIOUS PURCHASES- SEE NOTES | 129.10 |
| 07-429-1505 | RCSTP CAPITAL | 03/05/24 | Pay Check: 3490 | 24-00539 PURCHASE TENT HEATERS &DELIVER | 2,149.78 |
| 07-429-1505 | RCSTP CAPITAL | 03/05/24 | Pay Check: 3491 | 24-00530 (20) ROD 5/8 X 20' (#5) | 356.00 |
Page 3 of 4
Municipal Authority
YTD Revenues and Expenses thru 7/31/2024
| Account Number | Account Description | Date | Type | Transaction Data/Comment | Amount |
|---|---|---|---|---|---|
| 07-429-1505 | RCSTP CAPITAL | 03/05/24 | Pay Check: 3491 | 24-00550 5.5 YD CONCRETE 4000 PSI | 1,198.00 |
| 07-429-1505 | RCSTP CAPITAL | 03/06/24 | Pay Check: 3492 | 24-00567 20X20 TENT RENTAL UV CONCRETE | 800.00 |
| 07-429-1505 | RCSTP CAPITAL | 03/11/24 | Pay Check: 3494 | 24-00606 DUMPSTER RENTAL- CONSTRUCTION | 450.00 |
| 07-429-1505 | RCSTP CAPITAL | 03/11/24 | Pay Check: 3495 | 24-00607 RCSTP-UV DISINFEC RPLCMT PYMT2 | 3,541.86 |
| 07-429-1505 | RCSTP CAPITAL | 03/15/24 | Pay Check: 3497 | 24-00646 SERV THRU 021124 RCSTP GENERAT | 3,658.25 |
| 07-429-1505 | RCSTP CAPITAL | 03/15/24 | Pay Check: 3497 | 24-00644 SERV THRU 031124 RCSTP UV REPL | 2,698.50 |
| 07-429-1505 | RCSTP CAPITAL | 03/15/24 | Pay Check: 3498 | 24-00659 (5) 5 GALLONS WHITE PAINT | 118.95 |
| 07-429-1505 | RCSTP CAPITAL | 03/15/24 | Pay Check: 3499 | 24-00625 RCSTP- UV DISINFECTION SYS REP | 31,183.78 |
| 07-429-1505 | RCSTP CAPITAL | 03/21/24 | Pay Check: 3500 | 24-00698 INSTALL EMER. SHOWER & EYEWASH | 3,101.53 |
| 07-429-1505 | RCSTP CAPITAL | 04/01/24 | Pay Check: 707 | 24-00765 VARIOUS PURCHASES- SEE NOTES | 18.49 |
| 07-429-1505 | RCSTP CAPITAL | 04/01/24 | Pay Check: 707 | 24-00765 VARIOUS PURCHASES- SEE NOTES | 313.32 |
| 07-429-1505 | RCSTP CAPITAL | 04/01/24 | Pay Check: 707 | 24-00765 VARIOUS PURCHASES- SEE NOTES | 226.26 |
| 07-429-1505 | RCSTP CAPITAL | 04/03/24 | Pay Check: 3503 | 24-00783 SERV THRU 031724 RCSTP UV REPL | 661.50 |
| 07-429-1505 | RCSTP CAPITAL | 04/03/24 | Pay Check: 3503 | 24-00781 SERV THRU 031724 RCSTP GENERAT | 1,028.50 |
| 07-429-1505 | RCSTP CAPITAL | 04/09/24 | Pay Check: 3504 | 24-00872 20X20 FRAME TENT RENTAL4/3-5/1 | 800.00 |
| 07-429-1505 | RCSTP CAPITAL | 04/09/24 | Pay Check: 3506 | 24-00869 CONCRETE PUMPING- 1751 TOWNE | 575.00 |
| 07-429-1505 | RCSTP CAPITAL | 05/14/24 | Pay Check: 3508 | 24-01144 SERV THRU 041424 RCSTP UV REPL | 1,571.25 |
| 07-429-1505 | RCSTP CAPITAL | 07/16/24 | Pay Check: 3513 | 24-01664 RCSTP-UV DISINFEC RPLCMT PYMT3 | 10,110.42 |
| 07-429-1505 | RCSTP CAPITAL | 07/16/24 | Pay Check: 3513 | 24-01662 RCSTP-UNWIRE & REMOVE CABLES | 267.50 |
| 07-429-1505 | RCSTP CAPITAL | 07/16/24 | Pay Check: 3514 | 24-01658 SERV THRU 061624 RCSTP UV REPL | -226.00 |
| 07-429-1505 | RCSTP CAPITAL | 07/16/24 | Pay Check: 3514 | 24-01658 SERV THRU 061624 RCSTP UV REPL | 689.75 |
| 07-429-1505 | RCSTP CAPITAL | 07/16/24 | Pay Check: 3515 | 24-01663 RCSTP-UV DISINFECTION SYS REP | 52,769.70 |
| 07-429-1520 | RCSTP - CAUSTIC SODA | 05/14/24 | Pay Check: 3508 | 24-01145 SERV THRU 041424 RCSTP CAU SOD | 123.00 |
| 07-429-1520 | RCSTP - CAUSTIC SODA | 07/16/24 | Pay Check: 3514 | 24-01659 SERV THRU 061624 RCSTP CAU SOD | 595.00 |
| 07-429-3700 | CHESTER CREEK CAPITAL | 02/14/24 | Pay Check: 3480 | 24-00376 CHESTERCREEK INTERCEPTOR PYMT1 | 20,340.00 |
| 07-429-3700 | CHESTER CREEK CAPITAL | 02/14/24 | Pay Check: 3480 | 24-00377 CHESTERCREEK INTERCEPTOR PYMT2 | 53,325.00 |
| 07-429-3700 | CHESTER CREEK CAPITAL | 02/27/24 | Pay Check: 3488 | 24-00516 CHESTERCREEK INTERCEPTOR PYMT3 | 12,870.00 |
| 07-429-3700 | CHESTER CREEK CAPITAL | 06/06/24 | Pay Check: 3510 | 24-01292 CHESTERCREEK INTERCEPTOR PYMT4 | 117,677.00 |
| 07-429-6100 | WEST GOSHEN CAPITAL | 07/29/24 | Pay Check: 3517 | 24-01750 2023 WG SEWER AUTH TAPPING FEE | 31,392.87 |
| 07-429-6100 | WEST GOSHEN CAPITAL | 07/29/24 | Pay Check: 3518 | 24-01751 2023 WG SEWER AUTH BOND FUND E | 95.64 |
| Total Expense | 528,781.16 | ||||
| Net Operating | 5,306.68 |
Page 4 of 4
enerGtest
employee owned
206 Gale Lane
Kennett Square, PA 19348
enerGtest.com
Office: 484-731-0200
24hr Service: 800-456-7782
empowering peace of mind
Erika Addison
Pennoni Associates
121 Continental Drive, Suite 207
Newark, DE 19713
Phone: 302-351-5263
Email: eaddison@Pennoni.com
July 24, 2024
Re: Ridley Creek STP Utility Power Monitoring
Site Adress: 1751 Towne Drive, West Chester, PA 19380
EnerG Test Proposal #SF-10794
EnerG Test, LLC is a NETA accredited, highly trained, qualified, and experienced engineering service, electrical testing, and equipment servicing organization, a fully owned subsidiary of the Tri-M Group. Safety, quality, and professionalism are the fundamental characteristics of our company, and our accomplishments are identified by reliability, efficiency, and thoroughness. We specialize in offering engineering, testing, and equipment solutions to meet our customer’s needs.
Based on your request, EnerG Test will provide labor material, and equipment to provide the following scope of work:
Detailed Scope of Work:
- Install Power Quality Meter Average current usage, peak current usage; RMS voltage, Transient voltage, voltage swells, voltage dips and dropouts; Power factor, Displacement power factor, voltage unbalances and phase sequence; Harmonic voltage and currents; All data will be analyzed by a professional engineer and a full report will be provided.
General Clarifications:
- Power meter will be left on for a period of 25 days.
- EnerG Test to provide protective grounds, as necessary, for safe access to the equipment
- No repair, replacement parts, or associated labor outside of the scope of work is included.
- This proposal assumes that any equipment requiring energized electrical work, including but not limited to commissioning, metering, and testing, will be labeled by the owner with an NFPA 70E compliant arc flash label. If a label or owner provided analysis is not available, an incident energy analysis can be provided at an additional fee.
- This proposal excludes providing an Arc Flash Hazard Analysis and associated equipment labeling.
- Final report will be issued within 30 calendar days after completion of scope of work.
Schedule/ Timeline
- Our proposal is based on completing the scope of work during normal business hours (Mon-Fri 7am – 3:30pm)
- No electrical outage will be required to install the power meter.
- Power meter will be left on for a period of 25 days.
Owner Responsibilities
The facility owner representatives are to provide:
- Provide all equipment manufacturer manuals and single line drawings
- All switching to remove electrical load and restore electrical load if applicable.
- Coordination of switching by the local utility to isolate the equipment for inspection and testing and payment for services provided by the utility if applicable.
enerGtest.com
enerGtest
employee owned
206 Gale Lane
Kennett Square, PA 19348
enerGtest.com
Office: 484-731-0200
24hr Service: 800-456-7782
empowering peace of mind
Pricing
Total Project Pricing: $9,144.00
- No federal, state, or local taxes on labor are included in the above pricing.
- If this project is tax exempt, a copy of their tax-exempt form with be submitted with their purchase order
- The volatility of copper and other metals as well as the unpredictability of the impacts related to new government tariffs have made the projection of certain building materials difficult to forecast. EnerG Test reserves the right to recover increases greater than 5% of any materials containing copper or other metals. The increase will be based on Producer Price Index as of the day the proposal is submitted.
- Cancellation or postponement of schedule work (non-weather related) could result in additional charges.
- Cancellation/postponement within 48 hours of scheduled work will result in a fee of 10% of the project value.
- Cancellation/postponement within 1 week of scheduled work will result in a fee of 5% of the project value.
Terms & Conditions
- This proposal is valid for thirty (30) days, from the date of issue.
- EnerG Test’s Customer Terms and Conditions (05.25.21 Version) are the basis for all pricing and should this proposal be accepted shall become part of the contract documentation and supersede all subsequent terms to the contrary.
EnerG Test appreciates the opportunity to support your electrical needs. If you have any questions, please contact me.
Respectfully,
Jason Smith
Jason Smith
Account Executive
Cell: 610-721-3548
Email: mjsmith@energtest.com
enerGtest.com
From: Michael Ellis
To: Lynn Werkheiser; David Ware
Cc: Mark Miller; Derek Davis
Subject: Supplee Valley Pipe Lining for MA meeting
Date: Thursday, August 8, 2024 11:35:35 AM
Attachments: ATT00001.png
000000 Advertisement.docx
Hi Lynn,
Please include another MA New Business agenda item for: Approval to Advertise for Supplee Valley Pipe Lining. Mark and I discussed this today also.
The proposed draft advertisement is attached for reference, and the proposed bid schedule follows:
Pennoni to provide final ad to EGT to send to DLN = 8/13
Advertise in DLN = 8/14 and 8/19
Bids due = 9/4
Pennoni award recommendation = 9/5
MA Award consideration = 9/9
NTP with construction = early October with goal to complete work by end of 2024
Dave,
I'll call you to revisit budget so that we can establish Base Bid vs. Add Items if needed.
Mike
Michael Ellis, PE
Municipal Division Manager
Pennoni
Christiana Executive Campus, 121 Continental Drive, Suite 207 | Newark, DE 19713
Direct: +1 302-351-5236 | Mobile: +1 302-561-4235
www.pennoni.com | MEllis@Pennoni.com
[Image: Engineering the Future: Our Services and Expertise]
Our Services and Expertise
Supplee Valley Sanitary Sewer Pipe Lining
Contract No. SSPL-2024
A. ADVERTISEMENT
EAST GOSHEN MUNICIPAL AUTHORITY
WEST CHESTER, PENNSYLVANIA
Sealed bids will be received electronically through PennBid™ by the East Goshen Municipal Authority for Supplee Valley Sanitary Sewer Pipe Lining, Contract No. SSPL-2024 until 11:00 AM, prevailing time, on the 4th day of September 2024, at which time they will be publicly read at the East Goshen Township office, 1580 Paoli Pike, West Chester, PA 19380. All documents and solicitation details are available online anytime at no cost at PennBid™ (www.PennBid.net).
Each bid must be accompanied by a certified check or bid bond payable to the Owner in an amount of not less than ten percent (10%) of the bid or bids. Only bonds from companies licensed to do business in the State where the Owner is located will be accepted and the bond shall so state same.
This project involves cured-in-place pipe lining of ±5,710 L.F. of 8-inch diameter asbestos cement gravity sewer pipe and 44 lateral reinstatements.
Bids must be submitted unconditionally. No bidder may withdraw bid within sixty (60) days after the scheduled closing time for receipt of bids.
The Owner reserves the right to waive any informality, or to reject any or all bids.
Pennsylvania Department of Labor and Industry Prevailing Wage Rates apply to this project.
A-1