Municipal Authority
The East Goshen Municipal Authority will acquire, hold, construct, improve, maintain, operate, own and lease, either in the capacity of lessor or leasee, sewers, sewer systems or parts thereof, sewage treatment works, including works for treating and disposing of industrial waste, for the Township of East Goshen and other such territory as it may be authorized to serve in a fiscally responsible and environmentally safe manner.
The Municipal Authority is an appointed board which functions independently of the others. The Municipal Authority owns the Township sewer system and is responsible for providing sewers to those areas deemed necessary by the Board of Supervisors.
- Five members, serving five-year terms
- Meetings are on the 2nd Monday of the month at 7:00 P.M.
- All township meetings are held at the Township Building and open to the public
| Authority Members | Term Expiration Date |
| Kevin Cummings, Chairman | 2026 |
| John Stipe, Vice Chairman |
2029 |
| Dana Pizzarro, Secretary | 2026 |
| Sean Ellsworth, Assistant Secretary/Treasurer | 2028 |
| Walter Wujcik, Treasurer | 2028 |
| Pennoni Associates, Engineer | |
| Patrick M. McKenna, Esq. | |
| Peter Hicks, BoS Liaison | |
| Kevin Miller, Staff Liaison |
Documents
Back to the list | Open the original PDF
Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.
MA 5-12-25 final 1
EAST GOSHEN TOWNSHIP MUNICIPAL AUTHORITY
MEETING MINUTES May 12, 2025 The East Goshen Township Municipal Authority held their regular meeting on Monday, May 12, 2025 at 7:00 pm. at the Township Building. Members in attendance are indicated in BOLD: Walter Wujcik, Chairman Kevin Cummings – Vice Chairman Sean Ellsworth John Stipe Dana Pizarro Also in attendance were: Mark Miller (Director of Public Works), Cody Bright (Supervisor) Dave Ware (Finance Director), Patrick McKenna (Attorney) Robert Jefferson (Attorney) Stacey Fuller (Attorney) Mike Ellis (Pennoni). COMMON ACRONYMS: ATS – Automatic Transfer Switch BFES – Big Fish Environmental Services MA- Municipal Authority BOS – Board of Supervisors NPDES – National Pollutant Discharge Elimination System CB – Conservancy Board PC – Planning Commission DEP – Department of Environmental Protection PM – Prevention Maintenance EPA – Environmental protection Agency PR – Park & Recreation Board HC – Historical Commission RCSTP – Ridley Creek Sewer Treatment Plant I&I – Inflow & Infiltration SBR – Sequencing Batch Reactor LCSTP – Lockwood Chase Sewer Treatment Plant SSO – Sanitary System Overflow PWD – Public Works Department WAS – Waste Activated Sludge Call to Order & Pledge of Allegiance Walter called the meeting to order at 7:00 pm and led those present in the Pledge of Allegiance. Walter asked for a moment of silence for our troops and EMT. Walter asked if anyone would be recording the meeting. There was no response. Chairman’s Report/Other Members Report John reported that he attended the West Goshen meeting. They are in compliance. John asked the MA members if they want to see the WG reports. Mark will contact Mike about this.
MA 5-12-25 final 2
Liaison Reports 1. Conservancy Board - Walter mentioned that Keep East Goshen Beautiful Day went very well. SEWER REPORTS 1. Director of Public Works, Mark Miller’s report for May 12, 2025. Monthly Flows – The average daily flow to West Goshen was 607,073 gallons per day. Meters:
• Read Daily C.C. Collection:
• The pump stations were visited on a daily basis with no problems to report. • ThePECO ccontractor working in Marydell struck a lateral • The property owner contacted PECO and it was repaired. • The property managers of Goshen Valley 3 have started on getting the manholes located and getting them opened. We will be going over next week to inspect them. Ridley Creek Collection
• We had a problem with the check values at the Hunt Country Pump Station. • It was Friday afternoon when the problem was noticed We attempted to open it to check the valve but were unable to get it open. • I reached out to MGK who ordered two new valves. • The station is currently operating as normal. • We are currently televising the Lockwood Chase development. Ridley Creek Plant
• We had a VFD go bad on the blower in the SBR building. • Lenni was called to swap the VFD out, but unfortunately the new unit does match up to the bolt pattern. • Our mechanic fabricated new mounting bracket and I had him fabricate three extras in case others go bad. Alarms: 12 PA 1 Calls: 187 Lateral Caps: 10 Monthly Rainfall: 2.93”
MA 5-12-25 final 3
2. Pennoni Engineer’s Report dated April 11, 2025
Ridley Creek Sewage Treatment Plant (RCSTP)
• UV Disinfection System – John Laidley completed the connection of the permanent alarm to the two UV modules and tied the flowmeter into the UV system the week of April 13. There are no outstanding punchlist items remaining. Pennoni notified PADEP that the UV system replacement project is complete on April 30. This project is now considered complete.
• Arc Flash Study – A site visit with Pennoni and the operator occurred on March 18 to compile a full list of electrical equipment and corresponding power requirements for the arc flash study. We received additional requested electrical information from the RCSTP operator on April 23 and from PECO on April 30. Pennoni is currently finalizing the Arc Flash Study.
Sanitary Sewer Pipe Rehab
• Supplee Valley Pipe Lining – The contractor, Vortex Services, previously completed all pipe lining work. We reviewed post-construction videos, and one 370 LF pipe run has small “bubbles” throughout the liner. The manufacturer provided a letter stating that it is separation of the thin plastic lining from the hardened resin material and is not a structural defect. We are requesting further information from the contractor to further evaluate the defect, and a meeting with the contractor is scheduled for May 9.
We also processed the 2nd pay application.
Pump Stations
• Hunt Country Pump Station – We submitted the PA Department of Community and Economic Development (DCED) Small Water and Sewer Grant application on April 30 for the pump station upgrade. We expect that DCED will make awards in late 2025 or early 2026.
• Ashbridge Pump Station – The station is in need of upgrades. We will coordinate with Public Works to develop the scope of improvements.
Sewer Extension
• Morstein Road – We evaluated alternatives and prepared budgetary cost opinions for potential sewer extensions for 19 properties along Morstein Road near Barkway Drive. Exhibits and cost opinions are attached. Three alternatives were evaluated:
1. Entirely Low Pressure Sewer System (LPSS) – A LPSS with grinder pumps for all properties along Morstein Road and Great Oak Circle. This is expected to be the least costly to construct, but it would result in the Township owning a long stretch of small force main and every house having a grinder pump, which will result in more O&M burden and costs all property owners and potentially the Township.
2. LPSS and Gravity Sewers in Road – The lower elevation, eastern portion of Morstein Road and Great Oak Circle would be serviced by a LPSS. The properties on Morstein Road between Barkway Drive and Great Oak Circle would be serviced by a gravity sewer
MA 5-12-25 final 4
main within Morstein Road. While this is most costly to construct than Alternative 1, it will have less O&M burden and costs for the Township and for the property owners connected by gravity.
3. LPSS and Gravity Sewers via Easements – This is similar to Alternative 2 except that the gravity sewers would tie into existing manholes through potential private property easements. This results in slightly less pipe than in Alternative 2, but it would necessitate easements, and is not expected to yield a notable cost savings as a result.
New Connections
• Millstone Meadows (1010 Hershey Mill Road) – Site and sanitary sewer construction is ongoing, and we are continuing to perform regular inspections.
• Timbermill (301 Reservoir Road) – Site and sanitary sewer construction is ongoing, and we are performing continuing to perform regular inspections.
• 14 Reservoir Road – No activity by Pennoni since our last report. We are awaiting a plan resubmission to address comments from our last review letter dated July 12, 2024, two of which are related to sanitary sewer.
• 1338 Morstein Road (WCU Foundation) – Three new homes are proposed in East Goshen with additional homes in West Whiteland. The East Goshen Township-required Sewage Facilities Planning Module (SFPM) Components were submitted to the Chester County Health Department (CCHD) and Chester County Planning Commission (CCPC), and both agencies returned the completed components. It is our understanding that the developer’s Design Engineer has resubmitted to PADEP.
• 1344 Morstein Road – One new home is proposed with a grinder pump. After exploring various alternatives, we notified the Design Engineer that the only viable option to connect to public sewer is through an easement across an existing residential property to the existing sewer in Eastwick Circle. The Design Engineer provided the existing easement for review by the Township to evaluate if it can be used to install the new pipe. However, the easement is a private property matter, so we are deferring to the property owners to confirm the easement can be used in writing.
3. Big Fish Environmental Services – The Ridley Creek sewage treatment plant outfall 001 met all effluent limitations regarding water quality for April 2025. All supplemental reports were submitted for April 2025. Caustic usage increased to 63.33 gallons per day from 62.85 gallons per day last month. Aluminum sulfate solution volumes daily average increased slightly to 69.59 gallons per day from 65.58 gallons per day. No significant mechanical or operational issues were observed during the SBR treatment process. Sludge dewatering did not encounter any significant mechanical or operational issues. There were no odor complaints during the month. Approval of Minutes The minutes of the April 14, 2025 meeting were approved as amended.
MA 5-12-25 final 5
Approval of Invoices 1. John moved to approve payment of the following Pennoni invoices: * Invoice #1271694 $1,192.75 * Invoice #1271695 $ 449.25 * Invoice #1271696 $6,217.50 • Invoice #1271697 $6,750.00 Sean seconded the motion. The motion passed unanimously. 2. John moved to approve payment of the Vortex Services – Supplee Valley Sanitary Sewer Lining (which is part of the Payment Application #1) in the amount of $26,572.00. Sean seconded the motion. The motion passed unanimously. 3. Approval of the Gawthrop Greenwoood Invoice #222074445 was tabled. Stacey wants to check the bill. 4. John moved to approve payment of the Abel Brothers Towing Invoice #158230 in the amount of $6,500.00 (paid). Sean seconded the motion. The motion passed unanimously. 5. Sean moved to approve payment of the ETS invoice #169036 in the amount of $6,413.85 (paid). John Seconded the motion. The motion passed unanimously. 6. John moved to approve payment of the Continental Fire and Safety invoice #R4895 in the amount of $7,942.00 (paid). Sean seconded the motion. The motion passed unanimously. Financial Reports The following report was provided: YTD April 2025, the Municipal Authority recorded $386,740.30 in revenues (primarily from Sewer Capital Reserve and Sewer Operating transfers) and $377,009.97 in expenses (RCSTP UV replacement capital costs, Decanter controls repair, installation of new generator, Hershey Mill pump station replacement Hydromatic pump, sewer pipe camera, explosion proof heaters for RCSTP, Supplee Valley sanitary sewer pipe lining work, and engineering expenses). We also received 2024 revenue for recharges to Aqua to offset 07-424-3130 engineering expenses in 2025. The net result of operations is $9,730.33. As of April 30, 2025, the fund balance was $25,455.89. Old Business - None Goals –None New Business – None Capacity Requests 1. 1334 Morstein Rd - This is a flag lot that they want to subdivide. Mike explained the need for an easement to get to the sewer. Mark mentioned that when the resident bought this property, he advised that she put a bigger connection but she didn’t. 2. 1404 Morstein Rd – Property owner Joe Clifford was present. Mike presented his report which contains 3 alternatives. He reviewed the data and maps. Charter Chase and Goshen Downs have 19 properties. Some would need grinder pumps. The flows to Barclay Pump Station go to West Goshen which has the capacity to receive these flows. The 4 properties that are interested would be gravity sewer. Mike commented that they need to install a manhole at the entrance to Charter Chase for if/when they want to join. Joe Clifford mentioned that he has lived here for 35 years and is the
MA 5-12-25 final 6
second owner of the property. He doesn’t feel his tank will last 5 more years. He will speak to his neighbors. He thanked the MA for looking into this. Dave spoke about financing payments for about 20 years. Mark commented that the MA gave $5K/property in the past. Mike mentioned all the permits, etc. that will be needed and will probably take about 2 years before they could start any project. A letter to all of the residents was discussed. John made a motion to authorize preparation of a draft letter showing the alternatives. Sean seconded the motion. The motion passed unanimously. Any Other Matter - None Correspondence- None Public Comment - None Adjournment There being no further business Sean moved to adjourn the meeting. John seconded the motion. The motion passed unanimously. The meeting was adjourned at 8:15 pm. The next regular meeting will be held on Monday, June 9, 2025 at 7:00 p.m. Respectfully submitted, Ruth Kiefer, Recording Secretary