Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.

F:\Data\Shared Data\Agendas\Pipeline\2026\2026-07-21 Pipeline Task Force Agenda v1.docx

East Goshen Township Pipeline Task Force Meeting Agenda

Monday, July 21, 2026 East Goshen Township Building

10:00 AM Register to attend the meeting: https://us02web.zoom.us/meeting/register/kXmMsJFCScqT1pW1rEsu1A Please note in order to participate via Zoom we are now requiring attendees to pre-register for each meeting via the link.

1. Call to Order (10:00 AM)

2. Ask if anyone is recording the meeting.

3. Public Comment (10:05 AM to 10:10 AM)

4. Discussion with PA State Representative Chris Pielli (10:10 AM to 10:45 AM)

5. Approval of Minutes (10:45 AM to 10:50 AM) a. May 18, 2026

6. Chairperson’s Report (10:50 AM to 10:55 AM)

7. Old Business (10:55 AM to 11:30 AM) a. Protection of Williams/Transco natural gas valve station on Paoli Pike.

− Response from PennDOT regarding request for installation of guide railing. − Update on design of bollards at valve station. b. Update on Chester County Emergency Planning – EGT Pipeline Incident Annex. c. Zoning Ordinance Draft Amendment for data centers.

8. New Business (11:30 AM to 11:45 AM) a. Highlights from Municipal Emergency Operations Plan Review Workshop. b. Sinkhole near Mariner East 2 and 2X pipelines in West Whiteland.

9. Reports / Legislative Update (11:45 PM to 11:50 AM)

10. Liaison Reports (11:50 AM to 11:55 AM)

11. Correspondence / Any Other Matter (11:55 AM to 12:00 PM)

12. Next Meeting Scheduled for Tuesday September 15, 2026 at 10:00 AM.

13. Adjournment (12:00 PM)

May 18, 2026 1

PIPELINE TASK FORCE Monday, May 18, 2026 East Goshen Township Building

DRAFT MINUTES

Members Present are highlighted Chair: Gerry Sexton; Vice Chair: Mary McCloskey (Zoom); Members: Judi DiFonzo, David Shuey Others Present are highlighted Township Manager: Derek Davis; Township Supervisor: Ann Duffield; Assistant to the Township Manager: Ashley Nowak; Resident: Carolyn Sollecito (Zoom) COMMON ACRONYMS:

Call to Order Gerry called the meeting to order at 10:03 am. Recording The meeting was not being recorded. Approval of Minutes The draft minutes from March 17, 2026, were approved as is.

ACOE Army Core of Engineers BI&E BOS

Bureau of Investigation and Enforcement Board of Supervisors CCATO Chester County Association of Township Officials CCPC Chester County Planning Commission DCNR Department of Conservation and Natural Resources DEP Department of Environmental Protection DES Department of Emergency Services EGT East Goshen Township ET Energy Transfer FEMA Federal Emergency Management Agency HDD Horizontal Directional Drilling IR Inadvertent Return MACH2 Mid-Atlantic Clean Hydrogen Hub ME1 Mariner East 1 ME2 Mariner East 2 NGL Natural Gas Liquids PHMSA Pipeline Hazard Materials and Safety Administration PMN Post Meeting Note PTF Pipeline Task Force PUC Public Utility Commission

May 18, 2026 2

Public Comment None. Chairperson’s Report Gerry shared a mailer he received from Energy Transfer that provides updated pipeline safety information. He noted several improvements from previous versions. In April, Mary sent an email to the group regarding an article on the current natural gas shortage. She asked if there are checks in place to protect against exceeding production capabilities and causing safety issues. Gerry replied that yes, there are controls regarding pipeline throughput. The only practical way to increase throughput of an existing pipeline is to increase its operating pressure. Maximum operating pressure is a critical parameter and it is stated in the relevant permits. Thus there are safeguards in place to prevent over-pressurization. The group discussed an incident on 05/13/2026 regarding the smell of natural gas in the Bow Tree Development. EGT issued a Constant Contact alert. PECO was working in the development and struck one of their natural gas lines. Gerry noted this work may have been related to a PECO project under way to enhance the local electric distribution system. Both of these utilities are buried in this development, often in close proximity to each other. Old Business Protection of Williams/Transco natural gas valve station on Paoli Pike Derek emailed a letter to PennDOT on 05/06/2026 requesting the installation of guide railing along the roadway. Pennoni is working on the design and a cost estimate for bollards at the valve station. Ashley will follow up with Derek for a status update. The PTF would like to invite Senator Carolyn Comitta and Representative Chris Pielli to the July or September meeting. David will reach out to them. Update on Chester County Emergency Planning – EGT Pipeline Incident Annex Duane is working with the Chester County attorneys to redact sensitive information and then the Annex will be distributed to the PTF for review. PTF article for next township newsletter (due 6/30/2026) Mary and Judi are working on a draft write-up. The group agreed on a timeline to meet the deadline. [PMN: The article was submitted on 06/30/2026.] New Business Pennsylvania House Bill 1526 (2025-2026 session) – Degraded Natural Gas Pipeline Prevention Plans The group discussed this bill. It is part of a safety package proposed by the Pennsylvania House following the 2023 West Reading chocolate factory explosion.

May 18, 2026 3

Zoning Ordinance Draft Amendment for data centers The EGT Planning Commission is drafting a Zoning Ordinance Amendment that covers data centers. Gerry has attended relevant Planning Commission meetings. He reviewed key points in the document involving pipelines. The Planning Commission intends to send the final draft to appropriate ABCs for review. Reports / Legislative Update None. Liaison Reports Ann reported that the BOS is evaluating planners for the Comprehensive Plan Update. There will be a presentation at the next BOS meeting by PA Humanities regarding their PA Heart & Soul program. This organization works with municipalities to help collect information for their comprehensive plans by engaging the community in conversations. Correspondence / Any Other Matter None. Next meeting The next meeting is scheduled for Tuesday, July 21, 2026 at 10:00am. Adjournment The meeting was adjourned at 11:41am. Respectfully submitted, Ashley Nowak, Assistant to the Township Manager F:\Data\Shared Data\Minutes\Pipeline Task Force\2026\Pipeline TF Mins 2026-05-18 DRAFT v2.docx