Planning Commission

The East Goshen Township Planning Commission is an advisory board to the Township Board of Supervisors. The Commission reviews all subdivision and land development applications, conditional use applications, zoning hearing board applications and makes recommendations to the Board of Supervisors.  The Commission also reviews or drafts Zoning Ordinance Amendments. Each member is appointed by the Board of Supervisors.

  • Composed of seven East Goshen Township residents each serving a four-year term.
  • Formal Meetings are held the 4th Tuesday of each month at 7:00 P.M.
  • Workshop Meeting are held on an as needed basis
  • All township meetings are held at the Township Building and are open to the public
Planning Commission Members Term Expiration Date
John Stipe, Chair  2026
Dan Truitt, Vice Chair 2027
Daniel H. Daley 2027
Michael Koza 2026
Ernest Harkness 2026
Karen Martynick 2029
William Kaufman 2029
Larry Massaro, BOS Liaison
Kelly Krause, Staff Liaison

 

Draft Ordinance-Zoning Amendment Regulating Data Centers by Conditional Use 9.24.26

Click here to view – May 4th Documents for Malvern Institute and East Whiteland Special Study.

Related News

PLANNING COMMISSION CONSIDERS UPGRADES TO AQUA FACILITY

Wednesday, November 18, 2026

At its September meeting, the East Goshen Planning Commission reviewed a conditional use application from Aqua Pennsylvania to upgrade its Hunt Country well treatment facility located on Thorncroft Drive. The upgrade is required to meet new maximum contaminant levels (MCLs) for PFAS in drinking water that were enacted last year by the U.S. Environmental Protection […]

View Article

From the Planning Commission: Addressing Potential Data Center Development in East Goshen Township

Wednesday, September 30, 2026

As the demand for artificial intelligence accelerates, municipalities throughout Pennsylvania have found themselves navigating complex regulations, legal challenges, and community debates about large-scale data centers. While no data center projects are currently proposed in East Goshen, township officials are proactively addressing potential impacts by updating zoning ordinances to create strict standards that will apply should […]

View Article

More News

Documents

Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.

EAST GOSHEN TOWNSHIP PLANNING

COMMISSION Meeting Agenda Wednesday, February 3, 2021 VIA

Telephone/ Video Conference

7:00 PM Dial in Number: (929) 205-6099

Access Number: 893 5918 6610

During this tele-conference Planning Commission meeting, public comment will be handled as follows:

• Participants must call in by 6:55 pm. • The public will be muted during the meeting when the Commission is conducting business. • The Chairman will ask for any public comment on agenda items. Audience members who wish to make comments must unmute, identify themselves with name and address, to ask questions and make comments. • Participants wishing to comment must state their name and address and must speak one at a time.

A Call to Order/ Pledge of Allegiance and Moment of Silence B. Chairman will ask if anyone is going to record the meeting C. Review of Tracking Log/ Determine need for Workshop Meeting D. Public Comment on Non-Agenda Items E. Approval of Minutes

1. January 6, 2021 F. Subdivision and Land Development Applications G. Conditional Uses and Variances

1. 198 Oneida Lane/ Dimensional Variance Request H. Ordinance Amendments

1. Pipeline Hazard Mitigation/ Pipeline Consultation Zone (DRAFT) I. Old Business J. New Business K. Any Other Matter L. Liaison Reports M. Correspondence N. Announcements

1. Business Park Task Force Meeting February 1, 2021 7:00 PM Via Zoom. Meeting link will be posted on the Township Website.

Bold Items indicate new information to review or discuss.

F:\Data\Shared Data\Agendas\Planning Commission\2021\PC AGENDA 02032021.doc

February 3, 2021 PC Meeting -

(.)

ci' (/) 0 N ci' ..J :j (.) u::- C: 0 .::; .:,i ca (/) - -

Cl) Q. Application Name >- I- 198 Oneida Ln V Sk Pipeline HMS/ Consultation Zone Ord. ZO I SALDO DRAFT Bold= New Application or PC action required

Completed in 2020

1631 E. Strasburg Rd V Sk Solar Ordinance Amendment zo Sk Synthes USA / 1303 Goshen Parkway LD P/F Boyle, 1137 N. Chester Rd. V Sk

East Goshen Township Planning Commission

Application Tracking Log

1/) ... al Cl) Cl) <( C: - ·5, ci. C: 0 w ... 0. Q. .c: C)

1/) C: .::; C: - == 0. ::s (.) .0 "O Cl) 0 Cl) - I- (.) <( ca 0 0 Li: C 0 - - - Cl) Cl) Cl) Cl) - ca - - - ca - ca ca ca C (/) C C C 1/26/2021 1/27/2021 NA NA 1/28/2021 NA NA NA NA NA

9/29/2020 9/29/2020 NA NA 10/2/2020 10/30/2020 NA NA NA NA 4/27/2020 5/6/2020 4/28/2020 4/30/2020 4/30/2020 7/29/2020 7/29/2020 NA NA 7/31/2020

F:\Data\Shared Data\ABC'S\Planning Commission\PC Tracking Log\2021\PC Tracking Log for 02032021.xlsx

Cl) - Cl) ca - C ca C C: Cl) C: 0 0 .::; ca CJ Cl) "O .::; - CJ <( ca "O 1/) C: <( C - 0 I- ca C: 'in I- ..J C) Cl) Cl) ..J z C: C E C: Cl) z (/) ·.::: Q. E - 0 ca e >< (.) Cl) 0 w 0. al :c C (.) 2/3/2021 1/162021 2/25/2021 3/26/2021 NA NA NA NA NA NA

1017/2020 10/20/2020 10/27/2020 11/28/2020 NA NA 12/1/2020 NA NA 1 9/15/2020 9/2/2020 NA 10/2/2020 9/2/2020 9/15/2020 8/26/2020 9/25/2020

1/28/2021

1 2 3 4 5 6 7 8 9 10 11 12

13

14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53

Draft EAST GOSHEN TOWNSHIP PLANNING COMMISSION MEETING

January 6, 2021

The East Goshen Township Planning Commission held their regular monthly meeting on Wednesday January 6, 2021. Because of the COVID-19 restrictions the meeting was held via teleconference using Zoom. Members present are highlighted: Chair - Ernest Harkness Vice Chair - John Stipe Dan Daley Edward Decker Michael Koza Mark Levy Michael Pagnanelli Also present were: Mark Gordon, Zoning Officer Kristin Camp, Esq, Township Solicitor

COMMON ACRONYMS:

BOS - Board of Supervisors BC - Brandywine Conservancy CB - Conservancy Board CCPC- Chester Co Planning Commission

A. FORMAL MEETING - 7 p.m.

CPTF - Comprehensive Plan Task Force CVS- Community Visioning Session SWM- Storm Water Management

ZHB - Zoning Hearing Board

1. Ernest called the meeting to order at 7:00 pm. He led the Pledge of Allegiance and a moment of silence to remember our first responders, military and healthcare providers. 2. Ernest asked if anyone would be recording the meeting and if there were any public comments about non-agenda items. There was no response. 3. Ernest checked the log. 4. The minntes of the December 2, 2020 meeting were approved as amended.

B. ORDINANCE AMENDMENTS 1. Pipeline Hazard Mitigation/Pipeline Consultation Zone (DRAFT) Mark Gordon explained that a draft of a proposed ordinance that he and Kristin worked on and a copy of the consultation zone format was provided for the Commission members to review. Kristin believes that both formats could be adopted. Applicants must have a study done in addition to the application. They added types of pipelines from federal regulations. When the study is reviewed by the Planning Commission, they can make recommendations based on where the pipeline is located on the property. She feels the second ordinance format they just found (Consultation Zone), is good for East Goshen because of the number of pipelines and undeveloped properties. It strongly encourages dialogue with the pipeline company. Ernest asked the difference between them. Kristin commented that the first is an amendment to the

township ordinance. They need to add another section in the Zoning Ordinance to cover this. She spoke about situations that may need further review. Mark Gordon explained that if a resident wants to put an addition onto their house, the first may be too onerous. Kristin feels the second one may be more beneficial. This would be a stand alone ordinance. Dan mentioned the 660 feet from the centerline of the pipeline. The Ordinance doesn't have a definition for "property". He suggested using "track" of the property. Kristin agreed. John asked how the edge of the easement or center of the pipeline is determined. Mark Gordon commented that most pipeline companies will send someone to mark the center of the pipeline.

PC 1-6-21 draft 1

1 They don't need to do the study if it is a "use by right" application. His intent is to have everything on 2 the table for the Commission to review. He and Kristin just found the Consultation format so they may 3 be able to incorporate it into the proposed ordinance. Ernest suggested they remove the "Pipeline Task 4 Force" and add any Authority, Board or Commission. Dan feels that with all the documentation available 5 we know where all pipelines are located. He's not sure what the Consultation is providing. 6 Mark and Kristin will work on the next draft for the next meeting. 7 8 9 C. OLD BUSINESS 10 1. 2021 Goals - Ernest provided a written outline of Accomplishments for 2020 and Goals for 2021. 11 Mark mentioned that the Annual ABC meeting will be held on Tuesday January 26, 2021 at 6:30 pm. 12 Ernest reviewed the report. He will be unable to be at the ABC meeting so John will make the 13 presentation. 14 15 D. ANYOTHER MATTER 16 17 E. LIASION REPORT 18 19 F. ADJOURNMENT 20 There being no further business, Dan made a motion to adjourn the meeting. Mike K. seconded the 21 motion. The meeting was adjourned at 8: 15 pm. The next regular meeting will be held on Wednesday, 22 February 3, 2021 at 7:00 pm. 23 24 25 26 27 28 Respectfully submitted, ___________________ _ 29 Ruth Kiefer, Recording Secretary

PC 1-6-21 draft 2

Memorandum

East Goshen Township 1580 Paoli Pike West Chester, PA 19380 Voice: 610-692-7171 Fax: 610-692-8950 E-mail: mgordon@eastgoshen.org

Date: 1/28/2021 To:

From: Re:

Planning Commission , / t Mark Gordon, Zoning Officer /t-11(1 Pipeline Awareness Study Ordinances

Dear Commissioners,

After much thought and consideration, Staff and the Solicitor have provided the Planning commission with a revised pipeline ordinance. The intent from the BOS was to prepare a "Pipeline Awareness Ordinance". We believe that our first draft was too restrictive and wasn't in line with the guidance from the Board of Supervisors. Amendments to both the SALDO and the Zoning Ordinance are required to cover potential development and redevelopment situations appropriately including Subdivision Applications, Land Development Applications, and Conditional Use Applications for certain Principal Uses.

The ordinance before you this evening adds a requirement for applicants to prepare a "Pipeline Awareness Study" for the following circumstances:

• Land Development/ Sub division of land within 660 feet of the centerline of any Hazardous Liquid Pipeline or Natural Gas Transmission Pipeline. • Planned residential development (PRD) where the tract proposed to be developed is

located within 660 feet of the centerline of any Hazardous Liquid Pipeline or Natural Gas Transmission Pipeline. • As part of a conditional use application for a specific principal uses where the tract proposed for the principal use is located within 660 feet of the centerline of any Hazardous Liquid Pipeline or Natural Gas Transmission Pipeline.

The 660 foot requirement is outlined in both the Pipeline Hazard Materials Safety Administration (PHMSA) and the Pipelines and Informed Planning Alliance (PIPA) as the appropriate planning distance for both Natural Gas and Hazardous Liquids Pipelines.

STAFF RECOMMENDATION: Staff recommends that the PC take action on this ordinance this evening and forward your recommendation to the BOS for their consideration.

DRAFT MOTION: Mr. Chairman, I move that we recommend the Board of Supervisors adopt the Pipeline Awareness Study Ordinance amendment as prepared by staff and the Township solicitor.

F:\Data\Shared Data\Admin Dept\Township Code\Pipeline HM Ord (SALDO & ZO)\Memo to PC re. PAS ord 01282021.doc

EAST GOSHEN TOWNSHIP

CHESTER COUNTY, PENNSYLVANIA

ORDINANCE NO. 2021-__

AN ORDINANCE AMENDING THE EAST GOSHEN TOWNSHIP CODE,

CHAPTER 205 TITLED "SUBDIVISION AND LAND DEVELOPMENT" SECTION 205-7 TITLED "DEFINITIONS" TO ADD A DEFINITION FOR HAZARDOUS LIQUID PIPELINE AND NATURAL GAS TRANSMISSION PIPELINE AND TO ADD A NEW SECTION 205-40.1 TITLED "PIPELINE AWARENESS STUDY"; AMENDING CHAPTER 240 OF THE EAST GOSHEN TOWNSHIP CODE, TITLED "ZONING" SECTION 240-31.8(3) AND (7) TO REQUIRE A PIPELINE AWARENESS STUDY TO BE SUBMITTED AS PART OF CERTAIN CONDITIONAL USE APPLICATIONS.

BE IT ENACTED AND ORDAINED by the Board of Supervisors of East Goshen Township pursuant to the Board's power to adopt ordinances necessary to secure the health, safety and welfare of the citizens of the Township pursuant to Section 1506 of the Second­ Class Township Code, 53 P.S. §66506, and pursuant to the authority in the Pennsylvania

Municipalities Planning Code, 53 P.S. § 10101 et seq., the Board enacts and ordains as follows:

SECTION 1. Chapter 205 of the East Goshen Township Code, titled, "Subdivision and Land Development", Section 205-7 titled "Definitions" shall be amended by adding the following new definitions:

Hazardous Liquid Pipeline - any pipeline designed for transmission of a hazardous liquid as regulated by CFR Title 49, Section 195.2.

Natural Gas Transmission Pipeline - any transmission pipeline regulated by CFR Title 49, Section 192.3.

SECTION 2. Chapter 205 of the East Goshen Township Code, titled, "Subdivision and Land

Development" shall be amended to add a new Section 205-40.1 titled "Pipeline Awareness Study and Consultation" which shall provide as follows:

"§ 205-40.1 Pipeline Awareness Study and Consultation.

A. Applicability. A pipeline awareness study ("Pipeline Study), prepared by and sealed by a professional engineer licensed in the Commonwealth of Pennsylvania shall be submitted to the Township, with the following submissions:

f:\Oata\Shared Oata\Admln Oept\Townshlp Code\P!peline HM Ord (SALOO & ZO)\Final PAS Ord DRAFT CLEAN 01282021.docx

(1) As part of a preliminary plan submission for any land development application where the tract proposed to be developed is located within 660 feet of the centerline of any

Hazardous Liquid Pipeline or Natural Gas Transmission Pipeline.

(2) As part of a tentative plan submission for any application for a planned residential development (PRD) where the tract proposed to be developed is located within 660 feet of the centerline of any Hazardous Liquid Pipeline or Natural Gas Transmission Pipeline.

(3) As part of a conditional use application for a principal use of property where the tract proposed for the principal use is located within 660 feet of the centerline of any Hazardous Liquid Pipeline or Natural Gas Transmission Pipeline:

(a) Any residential development.

(b) Township park.

(c) Place of worship or religious institution, excluding hospitals, sanitariums, penal or corrective institutions.

(d) Public or private primary or secondary school.

(e) Publicly owned recreation.

(f) Public utility facility.

(g) Private recreation facility.

(h) Church or place of worship.

(i) Nursing home or personal-care center.

U) Life-care center.

(k) Business and professional offices.

(I) Gasoline service station, which may include the sale of gasoline as an accessory use.

(m) Shopping center. (n) Day care, child or adult. (o) Hotel or motel.(p) Mobile/manufactured home park in accordance with§ 205- 64B of this Chapter 205. (p) Medical facility for patient care that is supplementary to normal hospital services, but not including a hospital.

(q) Hospital. (r) Cyber charter school campus

F:\Oata\Shared Data\Admln Oept\Townshlp Code\P!pe!ine HM Ord (SAL DO & ZO)\Final PAS Ord DRAFT CLEAN 01282021.docx

( s) Conference center. (t)Treatment center. (u) Exercise/health/tennis clubs. (v) Fire or ambulance station.

B. Contents. The Pipeline Study shall contain the following information:

(1) Background information.

(a) A general description of the tract subject to the application, including lot area, topography, watercourses, vegetation, landscaping, existing improvements including buildings, structures, driveways, parking, loading areas, fire hydrants, surrounding uses, etc. (b) A specific description of the Hazardous Liquid Pipelines and Natural Gas Transmission Pipelines located within 660 feet of the proposed land

development, PRO or conditional use which shall include:

[1] Size of pipeline. [2] Number of pipelines. [3] Width of easement. [4] Materials transported through the pipeline.

(2) Applicant's design engineer shall prepare an assessment of the potential impacts to health, safety and welfare of the occupants and buildings associated with the proposed land development, PRO or conditional use due to the proximity of the Hazardous Liquid Pipeline or Natural Gas Transmission Pipeline.

(3) Measures that Applicant may implement to mitigate the potential impacts to the health, safety and welfare of the occupants and buildings associated with the proposed land development, PRO or conditional use, including but not limited to: design alternatives, reconfiguration of buildings, access driveways, interior driveways and parking lots, additional means of access, additional and/or enhanced fire protection measures and devices, enhanced emergency communication systems, use of specific building materials, increased setbacks, buffering, landscaping, conservation of existing vegetation, and any other appropriate measures permitted under the terms of this chapter and other Township ordinances.

C. As part of the review of the preliminary plan submission, tentative PRO plan submission or conditional use submission for the uses specified in §205-40.1.A(3) above, the Planning Commission and Board shall consider the contents of the Pipeline Study and evaluate if the respective plans appropriately address the potential impacts to the health, safety and welfare of the occupants and buildings associated with the Hazardous Liquid Pipelines and Natural

F:\Data\Shared Oata\Admin Dept\Townshlp Code\P!pe!lne HM Ord (SAlDO & ZO)\FJnal PAS Ord DRAFT CLEAN 01282021.doc)(

Gas Transmission Pipelines located within 660 feet of the proposed development, PRO or conditional use. The Planning Commission and Board may seek input from the Emergency

Management Coordinator, Fire Marshall, Fire Chief, utility providers, Township Authorities, Boards and Commissions or any other person or entity with experience or knowledge of Hazardous Liquid Pipelines and Natural Gas Transmission Pipelines. As a result of such review, the Planning Commission and Board may require the Applicant to revise its plans to

mitigate potential impacts to the health, safety and welfare of the occupants and buildings caused by the proximity of the Hazardous Liquid Pipeline or Natural Gas Transmission

Pipeline to the proposed development, PRO or use.

0. In addition to submitting the Pipeline Study, in cases where there is a Hazardous Liquid Pipeline or Natural Gas Transmission Pipeline on the tract to be developed for the applications referred to in §205-40.1A(1 ), (2) or (3), the applicant shall provide to the operator of the Hazardous Liquid Pipeline and Natural Gas Transmission Pipeline a copy of the plans and applications filed with the Township. The applicant shall request the pipeline operator(s) to review the proposed development plans and submit written verification that the pipeline operator(s) has received and reviewed the development plans and provided comments concerning the impact the development will have upon the integrity of the pipeline(s). The applicant shall submit to the Township all comments received from the operator or a notice from the operator indicating that the operator has no comments. If the operator does not respond within 30 days after being contacted and provided information by the applicant, the Township may waive the requirement for written verification.

SECTION 3. Chapter 240 of the East Goshen Township Code, titled, "Zoning" shall be amended by amending Section 240-31.8(3) to add the following sentence at the end of the existing language:

"In addition to the development plans, an applicant shall submit a Pipeline Awareness Study for the following uses when such uses are the principal use of a tract and are permitted as a conditional use:

(a) Any residential development.

(b) Township park.

(c) Place of worship or religious institution, excluding hospitals, sanitariums, penal or corrective institutions.

(d) Public or private primary or secondary school.

(e) Publicly owned recreation.

(f) Public utility facility.

(g) Private recreation facility.

(h) Church or place of worship.

(i) Nursing home or personal-care center.

F:\Oata\Shared Data\Admin Dept\Townshlp Code\Plpel!ne HM Ord (SALOO & ZO)\Flnal PAS Ord DRAFT CLEAN 01282021.docx

(j) Life-care center.

(k) Business and professional offices.

(I) Gasoline service station, which may include the sale of gasoline as an accessory use.

(m) Shopping center. (n) Day care, child or adult. (o) Hotel or motel.(p) Mobile/manufactured home park in accordance with§ 205- 64B. (p) Medical facility for patient care that is supplementary to normal hospital services, but not including a hospital.

( q) Hospital. (r) Cyber charter school campus (s) Conference center. (t) Treatment center. (u) Exercise/health/tennis clubs. (x) Fire or ambulance station.

SECTION 4. Chapter 240 of the East Goshen Township Code, titled, "Zoning" shall be amended by amending Section 240-31.B(?) to add the following sentence at the end of the existing language:

'The Board shall require an applicant to submit a Pipeline Awareness Study for the uses specified in Section 240-31.8(3) above."

SECTION 5. Severability. If any sentence, clause, section, or part of this Ordinance is for any reason found to be unconstitutional, illegal or invalid, such unconstitutionality, illegality or invalidity shall not affect or impair any of the remaining provisions, sentences, clauses, sections, or parts hereof. It is hereby declared as the intent of the Board of Supervisors that this Ordinance would have been adopted had such unconstitutional, illegal, or invalid sentence, clause, section, or part thereof not been included herein.

SECTION 6. Repealer. All ordinances or parts of ordinances conflicting with any provision of this Ordinance are hereby repealed insofar as the same affects this Ordinance.

SECTION 7. Effective Date. This Ordinance shall become effective five days from the date of adoption.

F:\Data\Shared Data\Adm!n Oept\Townshlp Code\P!pe!!ne HM Ord (SALDO & 20)\Flnal PAS Ord DRAFT CLEAN 01282021.docx

ENACTED AND ORDAINED this __ day of ______ , 2021.

ATTEST: EAST GOSHEN TOWNSHIP BOARD OF SUPERVISORS

Louis F. Smith, Secretary David E. Shuey, Chair

Michael P. Lynch, Vice-Chair

John Hertzog, Member

E. Martin Shane, Member

Michele Truitt, Member

F:\Data\Shared Oata\Admin Depl\Township Code\Pipe/!ne HM Ord (SALDO & ZO)\Final PAS Ord DRAFT CLEAN 01282021.docx

Memorandum

East Goshen Township

1580 Paoli Pike West Chester, PA 19380 Voice: 610-692-7171 Fax: 610-692-8950 E-mail: mgordon@eastgoshen.org

Date: January 28, 2021 To: Planning Commission From: Mark Gordon, Township Zoning Officer Re: Dimensional Variance Request, 198 Oneida Ln., Malvern

Dear Commissioners,

The Zoning Variance request before you is for dimensional relief from accessory use provisions of the zoning ordinance.

The property has an area of approximately 1.18 acres, and is located in the R-2 Single Family Zoning District (1 acre minimum lot size).

The property owners are requesting zoning relief to construct a 15 feet tall 160 square foot Shed on their property. They need relief for two reasons:

1.

The property has one existing shed on the property today; therefore the proposed shed can only be a maximum of 120 square feet in area.

a. Size Relief needed: 40 square feet 2. The shed is proposed to be 15 feet tall. The maximum height of storage sheds is 12 feet.

a. Height Relief needed: 3 feet

STAFF RECOMMENDATION:

The zoning relief that is needed for this project is minor and the applicant has support from the adjoining property owners. Staff has no objection to the Planning

Commission supporting this application for zoning relief.

DRAFT MOTION:

Mr. Chairman, I move that the Planning Commission support the dimensional variance request to permit the proposed 160 square foot storage with a height of 15 feet maximum as depicted in the application, for the following reasons:

1. The dimensional variance relief sought by the applicant will have no adverse effect on the essential character of the neighborhood. 2. The relief sought is the minimal relief needed to construct the new storage shed so that it will match the architectural style of the existing dwelling.

F:\Data\Shared Data\Property Management\53V2\53-2-46.2A (198 Oneida ln.)\2021 ZHB App\Memo to PC re Draft Motion 01282021.doc

610-692-7171

www.eastgoshen.org BOARD OF SUPERVISORS

EAST GOSHEN TOWNSHIP

CHESTER COUNTY 1580 PAOLI PIKE, WEST CHESTER, PA 19380-6199

January 28, 2021

Dear Property Owner:

· The purpose of this letter is to inform you that Carl and Beth Holden (APPLICANT), owners of 198 Oneida Ln., Malvern, have applied for Zoning Variances. The applicant is requesting dimensional relief from the storage shed requirements outlined in the zoning ordinance, specifically §240-32 P.(b). The applicant proposes to install a second storage shed on the property, located within the rear yard area. Additionally the proposed shed is 15 feet tall and does not meet the 12 foot height requirement for sheds.

Pursuant to Township policy, property owners within 1000 feet of the subject property are notified of Zoning Variance applications.

This application is scheduled to be discussed during the meetings outlined below:

Wednesday February 3, 2021- Planning Commission meeting (7:00 pm)

Tuesday February 16, 2021- Board of Supervisors meeting (7:00 pm)

Thursday February 25. 2021- Zoning Hearing Board (7:00 pm) (Zoning Hearing)

Due to COVID -19 all Township meetings and hearings are being held virtually via ZOOM video/ telephone conference. Members of the public can participate via telephone and view the teleconference on YouTube. Meeting access information can be found on the Township website at https://eastgoshen.org/public-meeting-access/.

The public is welcome and encouraged to attend and participate in these meetings and the hearing. The application information is available for public inspection at the Township Building. Please call the Township staff at 610-692-7171 if you need assistance finding the meeting access information, or email me at mgordon@eastgoshen.org if you have any questions or need additional information.

Sincerely,

1k. <;atr.d.aH. Mark A. Gordon Township Zoning Officer

Cc: All Township Authorities, Boards and Commissions

F:\Data\Shared Data\Property Management\53-2\53-2-46.2A (198 Oneida Ln.)12021 ZHB App\1000 foot ZV ltr 01282021.doc

EAST GOSHEN TOWNSHIP ZONING HEARING BOARD APPLICATION

1580 PAOLI PIKE WEST CHESTER, PA 19380-6199 PHONE (610)-692-7171 FAX (610)-692-8950

Name of Applicant:

Applicant Address:

Telephone Number: Ɇɇ Fax Number: Email Address:

Property Address:

Tax Parcel Number: 0:,v-z., 00'/i:>il Z,. Ac :, ·· Z ·· L/fo. 2;:j

Purpose of Application (check one)

Zoning District: [2-?.- Acreage:

I¼! Variance ( Type: D Use Variance ¦ Dimensional Variance) D Special Exception D Appeal determination of the Zoning Officer D Other Sections of Zoning Ordinance in which relief is sought:

<5.Ccl1ol-{ <--40-,-,. Au:.r:sro'I!-"( uS"S P. '!>\11'1-nbt;:, Sl•\'g,O\ AWi> Au__,i;...s,;o-e.y

Description of the Zoning Relief requested and the future use of the property:

Q.E 1-1 6-\Ɉ \O J.:1/\... L 0W 'T'VJO Ac..c.'i:SS:oh..T '!'1Jt,.VU1/n>t ɉ O"Yt.' \ Ɋ A S'S S:,E. f:),. \<; T')V"Iɋ IAI Oo'O <1¾.1>, 11-\-J:;. ">'fay, ViD 1 ", ,,._ P,,;::,<?u<:l;(? I (oO Ɍ ,F-, I;;!'\ l'-0'> t I? -,; Tl;,'(U'>y\? 51:):,l,.l'.J, WE AIL'c AL'>O

I?Jb:Gl2'e:H}rH::rr A MAX lt\.\\)WJ \:-\:!cl(,:;,t:-)1 oe ls1 01,,) '.D::y\'!.. lbc -S'.ɍ. ɎɏT'LJ.:>-<'.:,.fe, :Str►D Description of the Hardship:

wɐ A,'it..)E {?.,'fG>\J"(:<;lJyt(.,, l\ \ll;)tl,..v.?{lt;.)% fu A '?'fLctl\) lbo '>,G -STh"AG.E '?WD lr:,)tT&-1 ... .:), 1"'2.-/f): ftooɑ Pl tu,...1,, ɒ /beɓ •Fi S)l'.>tu:'\(af S H:<io 6L«;>Vi{:,) vJ 1:n-+::n--):9 ɔc; S,J?-. 'AloOl? SH:l:P 1b3D-Y 7 IS /4.F,. W.lM<'...,\,-J ,..._ L'i.<.s: Th-tɕ'rl o X 14 o s,g. s1HɖLy "?..4o "':.,i::. AC:c.'itifoy;1,'.'y'. "'"'™ t.Wnq. 11--lf> 11./n ,'L-aoɗ Ptt<.H Mo Kv, b :n-t. .. ,:w,_,, ru I;.,;:\ɘ<. " "' :l'.JIIG "" 1; n v> "' 1-t o v • c: 4"' o 6b = 6,1:, • wr r1<, !' 1o ill , r u:, v, ?i e. <=,::, N< I Dl;'r,1,i, .c, Qlic Mi>J11"1lr 'V6f"lA'1C<e,

We hereby acknowledge that we have read this application and state that the above is correct and agr§l-0 to comply with all provisions of the East Goshen Township Zoning Ordinance apj1ificaqle to this project and property.

ə-ɚ .Jl.:>V'I I.J .0 (V-( '<... I ?. o "L. I Signature of Applicant Date '

*Please review the formal application and review procedures on page three.

F:\Data\Shared Data\Code Dept\Application & Forms\Current Forms and Applications\Zoning HeariQg App 11212017.doc R 1 S

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxx

January 21, 2021

Ben and Shannon Manning

200 Oneida Lane

l\1a1Yern, Pennsylvania 19355

East Goshen Township

1580 Paoli Pike West Chester, Pennsylvania 19380

Re: 198 Oneida Lane, Malvern, Pennsylvania

Request for Variance

To Whom it May Concern:

We are the next-door neighbors of Carl and Beth Holden who reside at 198 Oneida Lane.

We have reviewed the drawings for the proposed accessory structure they intend to construct on their property.

We have no concerns with their request to construct the 160

square foot accessory structure with the maximwn allowable building height increased fron1 12 '-0" to 15 '-0".

We fully support the project.

Sincerely,

- 1---21- )[· Ben Manning

1-J\-J\

January 20, 2021

East Goshen Township 1580 Paoli Pike West Chester, Pennsylvania 19380

Ted and Barbara Wray

201 Oneida Lane Malvern, Pennsylvania 19355

Re: 198 Oneida Lane, Malvern, Pennsylvania Request for Variance

To Whom it May Concern:

We are immediate neighbors of Carl and Beth Holden who reside at 198 Oneida Lane.

We have reviewed the drawings for the proposed accessory structure they intend to construct on their property.

We have no concerns with their request to construct the 160 square foot accessory structure with the

maximum allowable building height increased from 12'-0" to 15'-0".

We fully support the project.

Sincerely,

.• .---· - ) _,,.,- - ,,,. i_.Q_?c2 11.,y Ted Wray '?- J ,,, ·. :;:)a,, -1...,t:_. WJui&i Barbara Wray J

198 Oneida Lane — Aerial Context and Proposed Accessory Building Location

Two annotated aerial photographs showing 198 Oneida Lane, surrounding neighborhoods, and the location of the proposed accessory building.

Left Aerial View (Neighborhood Context)

  • ~1000ft Radius (dashed orange circle centered on 198 Oneida Lane)
  • Rossmore
  • Sorrel Hill
  • 198 Oneida Lane (marked with red star)
  • Indian Hills

Right Aerial View (Property Detail)

  • Sorrel Hill
  • 198 Oneida Lane
  • Proposed accessory building (marked with red/white striped rectangle and arrow)
  • Oneida Lane
  • Adjacent house numbers: 200, 201, 203

SITE PLAN FROM 1995 — THE HOLDEN PROPERTY

Scanned 1995 engineering site plan drawing by Engineering Design Consultants, Inc. (EDC) for The Holden Property in East Goshen Township, Chester County, PA, with handwritten setback and distance annotations.

  • Title Label: SITE PLAN FROM 1995
  • Title Block: THE HOLDEN PROPERTY, EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PA — EDC, ENGINEERING DESIGN CONSULTANTS, INC.
  • Handwritten Notes: Scott Sanders Grade & Seed 384-7982, 383-1880, 942-3159; 22² + 44² = c², 484 + 1936 = 2420, √2420 = 49.19
  • Plan Dimensions and Setback Annotations: 20', 50 FT., 100 FT., 20', 95'-9", 82'-5", 78'-10", 22'-0", 44'-0", 128'
  • Plan Note Sections: EROSION AND SEDIMENTATION CONTROL NOTES, SEEDING SPECIFICATIONS, PERMANENT SEED MIXTURE, CONSTRUCTION SEQUENCE

198 ONEIDA LANE, MALVERN, PENNSYLVANIA — SITE PLAN & ZONING INFORMATION

Architectural site plan showing existing and proposed improvements at 198 Oneida Lane and adjacent 200 Oneida Lane, including a zoning compliance table.

ZONING INFORMATION:

198 ONEIDA LANE
EAST GOSHEN TOWNSHIP
"R-2" LOW DENSITY RESIDENTIAL DISTRICT

REQUIREMENTS REQUIRED EXISTING ADDITIONAL PROPOSED
MINIMUM LOT AREA43,560 SF51,318 SF----
MINIMUM LOT WIDTH AT BUILDING SETBACK LINE150 FT173.46 FT----
MINIMUM LOT WIDTH AT STREET LINE60 FT26.25 FT----
MAXIMUM LOT COVERAGE BY BUILDINGS25%2,696 SF (5.25%)182 SF (0.35%)2,878 SF (5.60%)
MAXIMUM LOT COVERAGE BY TOTAL IMPERVIOUS COVERAGE35%8,443 SF (16.45%)618 SF (1.20%)9,061 SF (17.65%)
MAXIMUM BUILDING HEIGHT STORIES32----
MAXIMUM BUILDING HEIGHT FEET30 FT23.25 FT----
MINIMUM FRONT YARD45'-0"162.83 FT----
MINIMUM SIDE YARD20 FT24 FT----
MINIMUM REAR YARD50 FT62.83 FT--44.16'

Site Plan Labels

  • EXISTING WOOD SHED (55 sf)
  • EXISTING WALK
  • PROPOSED SHED (182 sf)
  • PROPOSED TERRACE
  • EXISTING GARAGE
  • BREEZEWAY
  • EXISTING HOUSE
  • WELL
  • Contours: 485, 480, 475
  • Setback Dimensions: 50'-0", 20'-0", 45'-0"
  • Lots: 200 ONEIDA LANE, 198 ONEIDA LANE
  • NORTH | 198 ONEIDA LANE, MALVERN, PENNSYLVANIA

EAST ELEVATION & WEST ELEVATION — NEW SHED

Architectural elevation drawings showing the East Elevation and West Elevation of the existing residence, attached garage, and proposed new shed.

EAST ELEVATION

  • NEW SHED (height dimension: 14'-6 1/2")
  • Existing garage and two-story main residence

WEST ELEVATION

  • NEW SHED (height dimension: 13'-0 1/2")
  • Existing two-story main residence and attached garage

Architectural elevation drawings showing the south elevation of the existing residence with the proposed new shed, and four directional elevations of the accessory structure with height dimensions.

SOUTH ELEVATION

NEW SHED

ACCESSORY STRUCTURE ELEVATIONS

  • EAST: 14'-6 1/2"
  • NORTH: 14'-6 1/2"
  • WEST: 14'-6 1/2", 13'-0 1/2"
  • SOUTH: 13'-0 1/2", 14'-6 1/2"

Four color site photographs showing views of the property, driveway, existing house and shed, and surrounding wooded area.

VIEW FROM ONEIDA LANE

VIEW FROM 200 ONEIDA LANE

VIEW OF PROJECT AREA

VIEW FROM ROSSMORE