Planning Commission

The East Goshen Township Planning Commission is an advisory board to the Township Board of Supervisors. The Commission reviews all subdivision and land development applications, conditional use applications, zoning hearing board applications and makes recommendations to the Board of Supervisors.  The Commission also reviews or drafts Zoning Ordinance Amendments. Each member is appointed by the Board of Supervisors.

  • Composed of seven East Goshen Township residents each serving a four-year term.
  • Formal Meetings are held the 4th Tuesday of each month at 7:00 P.M.
  • Workshop Meeting are held on an as needed basis
  • All township meetings are held at the Township Building and are open to the public
Planning Commission Members Term Expiration Date
John Stipe, Chair  2026
Dan Truitt, Vice Chair 2027
Daniel H. Daley 2027
Michael Koza 2026
Ernest Harkness 2026
Karen Martynick 2029
William Kaufman 2029
Larry Massaro, BOS Liaison
Kelly Krause, Staff Liaison

 

Draft Ordinance-Zoning Amendment Regulating Data Centers by Conditional Use 9.24.26

Click here to view – May 4th Documents for Malvern Institute and East Whiteland Special Study.

Related News

PLANNING COMMISSION CONSIDERS UPGRADES TO AQUA FACILITY

Wednesday, November 18, 2026

At its September meeting, the East Goshen Planning Commission reviewed a conditional use application from Aqua Pennsylvania to upgrade its Hunt Country well treatment facility located on Thorncroft Drive. The upgrade is required to meet new maximum contaminant levels (MCLs) for PFAS in drinking water that were enacted last year by the U.S. Environmental Protection […]

View Article

From the Planning Commission: Addressing Potential Data Center Development in East Goshen Township

Wednesday, September 30, 2026

As the demand for artificial intelligence accelerates, municipalities throughout Pennsylvania have found themselves navigating complex regulations, legal challenges, and community debates about large-scale data centers. While no data center projects are currently proposed in East Goshen, township officials are proactively addressing potential impacts by updating zoning ordinances to create strict standards that will apply should […]

View Article

More News

Documents

Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.

PC 4-28-26 final 1

EAST GOSHEN TOWNSHIP PLANNING COMMISSION MEETING

April 28, 2026

The East Goshen Township Planning Commission held their regular monthly meeting on Tuesday, April 28, 2026 at 7:00 pm in the Township Building. Members present are highlighted: John Stipe - Chairman Dan Truitt, Vice Chairman Dan Daley Ernest Harkness Willian Kaufman Michael Koza Karen Martynick Also present was: Kelly A. Krause, Zoning Officer Larry Massaro , BOS Liaison, Township Supervisor Ann Duffield, Township Supervisor COMMON ACRONYMS: BOS – Board of Supervisors CPTF – Comprehensive Plan Task Force BC – Brandywine Conservancy CVS – Community Visioning Session CB – Conservancy Board SWM – Storm Water Management CCPC – Chester Co Planning Commission ZHB – Zoning Hearing Board FORMAL MEETING – 7 p.m.

1. John called the meeting to order at 7:00 pm. He led the Pledge of Allegiance and asked for a moment of silence to remember our first responders and military. 2. John asked if anyone would be recording the meeting and if there were any public comments about non-agenda items. There was no response. 3. The tracking log was checked and no need for a workshop meeting. John noted that the Zoning Board Hearing for 1409 Manley Rd. is scheduled for May 12, 2026. 4. The minutes of the March 24, 2026 meeting were approved. CHAIRMAN’S REPORT – None ACKNOWLEDGE RECEIPT OF NEW APPLICATIONS (INITIAL SUBMISSION)- None OLD BUSINESS – 1. Zoning Ordinance Amendment Draft - AI Data Centers Karen commented that she compared the County Ordinance to our Conditional Use Ordinance. She had difficulty finding everything. She feels that the County format should be entirely included in ours. Bill agreed that everything should be included somewhere in our ordinance. There was discussion about fiberoptic lines.

PC 4-28-26 final 2

Ernest mentioned that his concern is managing it, i.e. noise, light. He feels the County is good. There may be some duplicates though. He feels it should be done as soon as possible. He suggested that the source of power has to be approved by the supplier under State and Federal regulations. Noise, vibrations and setbacks were discussed. Public comments: Gerald Sexton, Chairman of the Pipeline Task Force, asked if the information on Data Centers will be a separate item or incorporated into the current ordinance. Kelly commented that it will be incorporated. Mr. Sexton spoke about natural gas pipelines that were in the County ordinance. He pointed out that East Goshen has lots of large natural gas lines. He mentioned that the Township has 3 ordinances referring to pipelines for hydrogen, carbon dioxide, and natural gas. He feels there should be a reference to those ordinances. He feels that backup power should be natural gas. Bill Eagan, 1422 Millcreek Rd. – He lives near the Comcast Data Center and has had issues in the past with them. He wants the restrictions to be as hard as possible. John suggested that Kelly put the County items into our ordinance draft for the Planning Commission to review next month. Kelly will make the revisions. NEW BUSINESS – 1. West Whiteland Township Comprehensive Plan Review – The plan was reviewed and discussed. Ernest feels they did a good job. A letter will be sent to the BOS with no comments on the West Whiteland Township Comprehensive Plan. LIAISON REPORTS 1. Board of Supervisors - Larry mentioned that he and Ann attended sessions on Data Centers which were very well attended. They were clearly selling this as an opportunity to make money on taxes. There is a city that had a fossil power plant which they tore down and replaced it with a power generating plant for a Data Center. East Goshen Comprehensive Plan – The BOS decided not to use the county as our consultant. ANY OTHER MATTER None CORRESPONDENCE None ADJOURNMENT There being no further business, Bill made a motion to adjourn the meeting. Karen seconded the motion. The meeting was adjourned at 8:00 pm. The next meeting will be held on Tuesday May 26, 2026 at 7 p.m. Respectfully submitted, Ruth Kiefer, Recording Secretary