Planning Commission
The East Goshen Township Planning Commission is an advisory board to the Township Board of Supervisors. The Commission reviews all subdivision and land development applications, conditional use applications, zoning hearing board applications and makes recommendations to the Board of Supervisors. The Commission also reviews or drafts Zoning Ordinance Amendments. Each member is appointed by the Board of Supervisors.
- Composed of seven East Goshen Township residents each serving a four-year term.
- Formal Meetings are held the 4th Tuesday of each month at 7:00 P.M.
- Workshop Meeting are held on an as needed basis
- All township meetings are held at the Township Building and are open to the public
| Planning Commission Members | Term Expiration Date |
| John Stipe, Chair | 2026 |
| Dan Truitt, Vice Chair | 2027 |
| Daniel H. Daley | 2027 |
| Michael Koza | 2026 |
| Ernest Harkness | 2026 |
| Karen Martynick | 2029 |
| William Kaufman | 2029 |
| Larry Massaro, BOS Liaison | |
| Kelly Krause, Staff Liaison |
Draft Ordinance-Zoning Amendment Regulating Data Centers by Conditional Use 9.24.26
Click here to view – May 4th Documents for Malvern Institute and East Whiteland Special Study.
Related News
PLANNING COMMISSION CONSIDERS UPGRADES TO AQUA FACILITY
Wednesday, November 18, 2026
At its September meeting, the East Goshen Planning Commission reviewed a conditional use application from Aqua Pennsylvania to upgrade its Hunt Country well treatment facility located on Thorncroft Drive. The upgrade is required to meet new maximum contaminant levels (MCLs) for PFAS in drinking water that were enacted last year by the U.S. Environmental Protection […]
View ArticleFrom the Planning Commission: Addressing Potential Data Center Development in East Goshen Township
Wednesday, September 30, 2026
As the demand for artificial intelligence accelerates, municipalities throughout Pennsylvania have found themselves navigating complex regulations, legal challenges, and community debates about large-scale data centers. While no data center projects are currently proposed in East Goshen, township officials are proactively addressing potential impacts by updating zoning ordinances to create strict standards that will apply should […]
View ArticleDocuments
Back to the list | Open the original PDF
Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.
EAST GOSHEN TOWNSHIP
PLANNING COMMISSION
Meeting Agenda Wednesday, August 1, 2018
7:00 PM
A. Call to Order I Pledge of Allegiance and Moment of Silence B. Chairman will ask if anyone is going to record the meeting C. Review of Tracking Log/ Determine need for Workshop Meeting
1. Workshop meeting - August 15, 2018 Paoli Pike Corridor Overlay Project D. Public Comment on Non-Agenda Items E. Approval of Minutes
1. June 6, 2018 F. Subdivision and Land Development Applications
1. 1506 Meadowbrook Dr. (SD/LD) G. Conditional Uses and Variances
1. 1339 E. Strasburg Rd. I Home Occupation/ CU H. Ordinance Amendments
1. Incubator Uses I Discussion with Jon Altshul I. Old Business J. 2018 Goals K. Any Other Matter
1. E. Strasburg Rd. Adopt a Highway Clean-up Status (Fall) L. Liaison Reports M. Correspondence
Bold Items indicate new information to review or discuss.
F:\Data\Shared Data\Agendas\Planning Commission\2018\PC AGENDA 08012018.doc
~ 0 u.i en > ci en 0 ci --' ::::> ~ - LL c: a..: 0 "t:S :;:; ~ ~ cu ~ .!::! u: Cl) Cl) c. c. ... Application Name c. >- cu <C I- c 1506 Meadowbrook Drive SD/LO P/F 2/26/2018 1339 E. Strasburg Rd. cu Sk 7/16/2018
Bold = New Application or PC action required
Completed in 2018
Malvern Institute, 940 King Rd. V, SE p 3/27/17 WCASD I EG Elem. LD p 11/28/17 1665 E. Boot Rd v p 12/1/17
East Goshen Township Planning Commission
Application Tracking Log
Ill u ... m Cl) <( Cl) c: - C> c. c: 0 w ... 0.. c. .c: C> c: Ill c: 0 E
==
0.. ::I 0 0 .c Cl) c: ... I- 0 <( .2 cu c 0 0 0 Ill ... ... ... c: 't: Cl) Cl) Cl) Cl) cu ... ... ... ... ... cu cu cu >< en c c c w 4/4/2018 2/27/2018 3/1/2018 3/1/2018 2 7/16/2018 NA NA 7/25/2018
3/27/17 NA NA 3/30/17 4 12/6/17 11/30/17 11/30/17 11/30/17 12/1/17 NA NA 12/7/18
Cl) ... cu c c: 0 :;:;
<.> <( I- --' z 0 0.. 8/1/2018 8/1/2018
1/17/18 2/7/18 1/3/17
F:\Data\Shared Data\ABC'S\Planning Commission\PC Tracking Log\2018\PC Tracking Log for 08012018.xlsx
Cl) ... cu c c: 0 Cl) ... :;:; Cl) cu <.> ... "t:S <( cu "t:S Ill c ... I- cu c: --' C> Cl) Cl) z c: c E en ·.::: c. E 0 cu 0 Cl) ... 0 m ::c c 0 8/21/2018 NA 9/3/2018 9/4/2018 9/4/2018 9/14/2018
2/6/18 2/13/18 2/28/18 3/6/18 NA 3/6/18 APPD 1/16/18 1/25/18 1/30/18 APPD
7/26/2018
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50
Draft EAST GOSHEN TOWNSHIP PLANNING COMMISSION MEETING
June 6, 2018
The East Goshen Township Planning Commission held a regular meeting on Wednesday, June 6, 2018 at 7:00 p.m. at the East Goshen Township building. Members present were: Chairman Brad Giresi, Jim McRee, Adam Knox, Dan Daley, Ernest Harkness, Monica Close and Silvia Shin. Also present was Mark Gordon, (Township Zoning Officer) and Janet Emanuel, (Township Supervisor).
COMMON ACRONYMS:
BOS - Board of Supervisors BC - Brandywine Conservancy CB - Conservancy Board CCPC - Chester Co Planning Commission
A. FORMAL MEETING- 7:00 pm
CPTF - Comprehensive Plan Task Force CVS - Community Visioning Session SWM - Storm Water Management
ZHB - Zoning Hearing Board
1. Brad called the meeting to order at 7:00 pm. He led the Pledge of Allegiance and a moment of silence to remember our first responders and military. 2. Brad asked if anyone would be recording the meeting and if there were any public comments about non-agenda items. There was no response. 3. Brad checked the log and noted there will be a workshop meeting on June 20, 2018. 4. Brad also noted that representatives of 1506 Meadowbrook should be at the next meeting. 5. The minutes of the May 2, 2018 meeting were approved as corrected.
B. ORDINANCE AMENDMENTS
1. Keeping of fowl/Domesticated Chickens - Mark explained 2 options: 1. Amend the ordinance to allow "Domesticated Chickens" on residential single family lots 1 acre or larger. 2. Amend the ordinance to allow "Domesticated Chickens" on residential single family lots that are 20,000 Sq. Ft. or larger. He provided a draft amendment to reflect option 2. After review of the draft amendment and discussion, a vote of 1 for no change, 2 for option 1 and 4 for option 2 was taken. Staff will make discussed changes and send it to the Board of Supervisors.
2. Open Space Development Ordinance Amendment - Mark reviewed the TCA Revised Proposal for Open Space Development RFP. All were in favor of Tom Comitta's proposal. Mark mentioned that this proposal will be presented to the Board of Supervisors on June 19, 2018.
C. LIAISON REPORTS
1. Board of Supervisors - Janet reported that the BOS Live Streamed their meeting last night on YouTube. Sen. Dinniman's suit against Sunoco got favorable response from the judge. She explained the issues East Goshen has with the pipeline.
ADJOURNMENT
There being no further business, Ernest moved to adjourn the meeting. Monica seconded the motion. The meeting adjourned at 8:35 pm. The next meeting will be held on Wednesday, July 11, 2018 at 7:00 pm.
Respectfully submitted, _____________________ _
Ruth Kiefer, Recording Secretary
PC 6-6-18 draft 1
Memorandum
East Goshen Township 1580 Paoli Pike West Chester, PA 19380 Voice: 610-692-7171 Fax: 610-692-8950 E-mail: mgordon@eastgoshen.org
Date: 7 /26/2018 To: Planning Commission From: Mark Gordon, Township Zoning Officer IV{t(_fo
Re: 1506 Meadowbrook Ln. /Subdivision and Land Development Application
Planning Commission Members:
The Township has received final revised plans addressing the review comments from the Township Engineer's review letter and the CCPC review letter. The Township Conservancy
Board has reviewed the plan and forwarded their recommendation to the Planning Commission, which is included herein.
Recommendation: Staff is supportive of the Planning Commission taking action on this application at this time. The applicant shall provide justification for the waiver requested from the SALDO, to the satisfaction of the PC.
Draft Motion: Mr. Chairman, I move that we recommend that the Board of Supervisors grant the requested waiver and approve the preliminary/ final subdivision plan for 1506 Meadowbrook Ln. dated August 1, 2017, last revised 6/26/2018 with the following conditions:
1. All comments outlined in the July 10, 2018 Pennoni review letter be addressed to the satisfaction of the Township staff prior to the issuance of Building Permits. 2. The applicant shall post the appropriate financial security and submit the land development agreement for review and approval by the Board prior to the execution of the final land development plans. 3. The applicant shall provide a copy of the fully executed driveway access and easement agreement to the Township in order to satisfy condition D of the Zoning Hearing Board decision 4. The applicant and developer shall follow all federal, state and local laws.
Waiver request: §205-31- Combine Preliminary and Final Plan review process.
F:\Data\Shared Data\Property Management\53-4\53-4-23 (1506 Meadowbrook Ln.)\2018 SD & LD\Memo to PC 07262018.doc
.~~~..: ~ ii/ ..,.,. -7)
3508 Goshen Road Newtown Square, PA 19073 Tel: (610) 355-0862 Fax: (610) 355-0863 entail: sg.guyeng@gmaif.com
June 25, 2018
Mr. Mark Gmdon, Zoning Officer East Goshen Township 1580 Paoli Pike West Chester, PA 19380
Re: Preliminary/Final Subdivision and Land Development 1506 Meadowbrook Lane Township Engineer's Review dated 6/22/2018.
Dear Mr. Gordon,
This letter is a response to the Township Engineer's review letter of 6/22/2018. The enclosed land development plans have been revised to address the comments in these letters, as follows:
Sanitary Sewer:
25. Section 188-33.A(3): Pump Curve. As explained in our letter of 6/1/2018, the grinder pump will serve the basement as well, so it will be installed at a depth that will enable it to receive effluent from the basement, if the homeowner desires to install a bathroom in the basement. The centerline elevation of the inlet pipe into the pump chamber will be set at Elevation 439.00. The centerline of the discharge pipe from the pump chamber will be at Elevation 439.94. This will allow the entire length toward th.e connection to the cleanout ahead of the sewer manhole at the western corner of Lot# 2 to be sloped upward, with no high point anywhere along its route, and have a cover of more than 3 ft along its entire length. This will be the case whether the home owner chooses to have a bathroom in the basement and connect
it to the grinder pump unit, or not. A note requiring the builder to submit an application for a grinder pump unit approval has been added on Sheet 3. A note requiring a minimum cover of 3 ft over the pipe already exists on Sheet 3 (Note # 1 of the Sanitary Sewer Notes). Another note has been added requiring the installation of the force main to be in a continuous rising slope to prevent creation of high points along its route. 26. Section 188-31.8(4): Addressed. 27.Section 188-33.A(3)(e) & 188-33.F: Grinder Pump Station O&M Agreement. The Applicant will submit the agreement to the Township. No further comment.
Mark Gordon, East Goshen Township 1506 Meadowbrook Lane Response letter 6/25/2018 to Twp Engineer's Review of 6/22/2018 Page 2of2
34. Cleanout for Lot 2. The required note has been added on Sheet 3.
General:
36. Access Agreement. Will be provided by the Applicant. No further comment. 41. Township Review. All documents will be submitted to the Township for review. No further comment.
New Comments:
43. Manholes. b. Manhole note. The note has been removed from the detail on Sheet 8.
Please contact us if you have any questions or comments.
Sincerely,
Shimon Guy, P.E. President
c: Joseph Willis Stephen & Denise Legenstein
EGOST00126
Mark Gordon, Zoning Officer East Goshen Township 1580 Paoli Pike West Chester, PA 19380
July 10, 2018
RE: Preliminary/Final Subdivision and Land Development 1506 Meadowbrook Lane, Legenstein - 4th Submission
Dear Mark:
One South Church Street
Second Floor West Chester, PA 19382
T: 610-429-8907
F: 610-429-8918
www.pennoni.com
As requested, we have reviewed the following information, prepared by Guy Engineering Associates, Inc. in connection with the referenced project:
• "Preliminary/Final Land Development Plans" (six sheets), dated August 1, 2017 last revised June 25, 2018;
• "Stormwater Management Report Prepared for Mr. & Mrs. Legenstein" dated February 20, 2018, revised June 21, 2018; and
• Engineer's response letter dated June 25, 2018.
The applicants/owners, Stephen & Denise Legenstein, propose to subdivide an existing 2-acre flag lot into two one-acre lots. There is an existing single-family residence on the property that will remain on Lot 2. They propose a single-family house, driveway, and stormwater management on the newly created Lot 1. Lot 2 will be accessed by an access easement through Lot 1. Three (3) zoning variances were granted on October 10, 2017 and notes are on the plan.
The applicants propose to purchase a two (2) foot wide by two hundred (200) foot long strip of land from the adjacent property, UPI #53-4-7, and add it to proposed Lot 2 in order to comply with the zoning area regulations.
The property is within the R-2 Low Density Residential District. Both lots will be served by on-site water and
public sanitary sewer.
All of our comments from our previous review letters have been addressed.
The applicant is reminded that all legal descriptions, easements, agreements (i.e., developer's agreement, access agreement, stormwater management operations and maintenance agreement, sanitary sewer, grinder pump station operation & maintenance agreement, etc.) or similar are subject to review and approval by the Township.
U:\Accounts\EGOST\EGOST00126- Legenstein 1506 Meadowbrook Lane\DOC PREP\Legenstein SDLD Review LTR 2018-07-10.docx
EGOST 00126 Mark Gordon. Zoning Officer
July 10, 2018 Page 2 1506 Meadowbrook Lane, Legenstein
Should you have any further questions or comments, please contact the undersigned.
Sincerely,
Township Engineer
cc: Shimon Guy, PE, Guy Engineering Associates (via e-mail) Stephen & Denise Legenstein (via e-mail)
THE COUNTY OF CHESTER
COMMISSIONERS Michelle Kichline Kathi Cozzone
Terence Fanell
Brian N. O'Leaiy, AICP Executive Directo.r
Louis F. Smith, Jr., Manager East Goshen Township
1580 Paoli Pike West Chester, PA 19380
PLANNING CO'MMlSSION Government Services Centel', Suite 270 601 Westtown Road P. 0 . Box 2747 West Chestel', PA 193 80-0990 (610) 344-6285 Fax (610) 344-6515
March 27, 2018
Re: Final Subdivision - 1506 Meadowbrook Lane # SD-03-18-15306 - East Goshen Township
Dear Mr. Smith:
A Final Subdivision Plan entitled "1506 Meadowbrook Lane", prepared by Guy Engineering Associates Inc., and dated August 1, 2017, and last revised on February 20, 2018, was received by this office on March 1, 2018. This plan is reviewed by the Chester County Planning Commission in accord with the provisions of Section 502 of the Pennsylvania Municipalities Planning Code. We offer the following comments on the proposed subdivision for your consideration.
PROJECT SUMMARY:
Location:
Site Acreage: Lots/Units:
east side of Boot Road, north of Generals Way 3.96 3 Lots Proposed Land Use: Single Family Residential Municipal Land Use Plan Designation: Low Density Residential UPI#: 53-4-23, 53-4-7
PROPOSAL:
The applicant proposes to subdivide UPI# 53-4-23 into two parcels, along with the conveyance of a 400 square foot portion of UPI# 53-4-7 to proposed Lot #2. The existing residence will remain on proposed Lot #2, and a new single family residence will be constructed on proposed Lot #1. The project site, which will be served by onsite water and public sewer, is located in the R-2 Low Density Residential zoning district.
RECOMMENDATION: The County Planning Commission recommends that the issues raised in this letter should be addressed and all East Goshen Township issues should be resolved before action is taken on this subdivision plan.
Email: ccplanning@chesco.org • website: www.chescoplanning.org
Page: 2 Re: Final Subdivision - 1506 Meadowbrook Lane # SD-03-18-15306 - East Goshen Township
COUNTY POLICY:
LANDSCAPES:
1. The project site is located within the Suburban Landscape designation of Landscapes2, the 2009 County Comprehensive Plan. The proposed subdivision is consistent with the objectives of the Suburban Landscape.
Parcel Info: Parce~s): 53·4-23, 53-4-7
{Mail) Address: 1soe Meadowbrook~·· Muricipality: East Goshen Twp.
WATERSHEDS:
CJ Parcels
01her Pare.els
Ho1e:Tn1tCCPC miknt:Yaf'/ dQ1.to en5u~ flis rn:apllfne o!ll!ITTltSbltdQa nolgv~to
;,~ ITl•p ott1' ~oatum to J:ie 1p.aii-1.ll7 or !emi;icu.al ~J
.ac"1nit~.
2. Watersheds, the water resources component of Landscapes2, indicates the proposed development is located within the Ridley Creek watershed. Watersheds' highest priority land use objectives within this watershed are: reduce stormwater runoff, protect vegetated riparian corridors, and protect/enhance water-based recreation, cultural, historic resources and public access.
Watersheds can be accessed at www.chesco.org/water.
PRIMARY ISSUES:
3. The site plan indicates that, on October 3, 2017, the Township Zoning Hearing Board granted variances from the minimum lot width, minimum street frontage, and minimum flag lot pole width requirements, with six conditions of approval. We note the conditions of approval include providing a pull-off area along Hemlock Hill Lane (a private lane), and providing a landscaped buffer to the adjacent parcels along Nathaniel Drive. Prior to granting final plan approval, the Township should verify that the plan conforms to the decision issued by the Township Zoning Hearing Board.
Page: Re: #
3 Final Subdivision - 1506 Meadowbrook Lane SD-03-18-15306 - East Goshen Township
..i B/.l.Kf.µ PROPERTY f.;o uo1 53-4-7 gi lli~~,~~~J~kJl
Site Plan Detail, Sheet I: Final Subdivision - 1506 Meadowbrook Lane, East Goshen Township
ADMINISTRATIVE ISSUES:
I
I I I
4. Land disturbance and land development activities that occur within Chester County must comply with the County-wide Act 167 Stormwater Management Plan for Chester County, PA (July 2013) and the associated Act 167 stormwater management ordinance standards adopted by each municipality.
5. The site plan depicts the location of a 20 foot wide sanitary lateral easement for Lot #1 over Lot #2. The details of this easement should be incorporated into the deeds of both lots.
6. The site plan depicts a 25 foot wide access easement for Lot #2 over Lot #1. The details of this easement should be incorporated into the deeds of both parcels. We acknowledge Zoning Note #2 on Sheet 1 states that Hemlock Hill Lane currently provides access to UPI# 53-4-23 and four additional parcels, and we also note that condition D of the Zoning Board's October 3, 2017 decision states that the shared driveway easement maintenance agreement will be revised to include proposed Lot #1.
Page: 4 Re: Final Subdivision - 1506 Meadowbrook Lane # SD-03-18-15306 - East Goshen Township
7. The applicant is requesting two waivers from the Preliminary and Final Plan Regulation Requirements of the Township Subdivision and Land Development Ordinance, in order to combine the preliminary and final plan review and approval process. Waiver requests should only be granted following the determination that the proposed project either meets the purpose of these requirements or does not create the impacts that these provisions are intended to manage.
8. A minimum of five (5) copies of the plan should be presented at the Chester County Planning Commission for endorsement to permit recording of the final plan in accord with the procedures of Act 247, the Pennsylvania Municipalities Planning Code, and to meet the requirements of the Recorder of Deeds, the Assessment Office, and the Health Department.
This report does not review the plan for compliance to all aspects of your ordinance, as this is more appropriately done by agents of East Goshen Township. However, we appreciate the opportunity to review and comment on this plan. The staff of the Chester County Planning Commission is available to you to discuss this and other matters in more detail.
cc: Stephen W. & Denise A. Legenstein Guy Engineering Associates, Inc. Chester County Health Department Chester County Conservation District
Sincerely,
Paul Farkas
Senior Review Planner
I I
SEIERAL NOTES:
1. Both proposed lots will be served bY public sewer and on-lot water. 2. Lot f 2 is currently connected to public sewer end hes en an-lat water well. Lot I 1 will be connected to the existing public sewer vie en easement in Lot f 2. 3. A well permit from the Chester county Health Department is required before an occupancy 4. Iron pine shell be set et property corners. permit is iauued.
151.94' 110.31'
REVIEWED BY THE OWNER OF UPI 53-4-7 REVIEWED BY THE OWNER OF UPI 53-4-23
THIS DAY OF---- THIS DAY OF---~
PROPERTY Ol'llNER PROPERTY OlllNER
[i'l.i]~[Q)@\'l,i'll[IDIJ\l@@~ 11L!.\OO~
33' WlDE ----- EP
~ 49'31'00"' w 110.32' 25.05'-
AREA • 400.00 SF l ___ _ ---- ,~ -I~ --~==·~·o~·~'·_·_ EP _,
"' • Ii!. -~ ruO
N 49'31'00• E 226.60' N 49'31'00"' E 110.31' N 49'31'00- E 110.32'
PROPERTY Ol'll£R'S CERTIFICATION: l J J The 111nd owner 11cknowledge11 th11 per th11 provisions of the E1111t Gosha Township Stormw11ter M11n11ge ent Ordin11nc11, it is unlawful to modify, remov • fill, landscape, alter or i11Pair th effectiveness of, or plac any structure. oth11r v11get11tion, yard waste, brush cuttings, or other waste or debris into any permanent stor11W11ter m11n11ge11111nt BMP or conveyance described in thi11 O&M plan or to allow the BMP conveiance to exi11t in 11 condition, whicn does not conform to thia O&M plan. without written approval from tha Townah p. Tha individual lot owner. hia/har hairs. 11s11ign11 or 11ucc11ssor11 shall b11 r11sponsibl11 for th11 perpetual 1111int11n11nc11 of th11 said f11cilitie11. A bl11nk11t 11tor11W11t11r m11nage11ent easement is provided over and across the property in favor of East Goshen Township to allow the Township 11nd ita 11ganta 11nd daaigneaa 11ccaaa to tha propoaad ator11W11tar f11cilitiea. Tha TownahiP is granted tha right, but not the duty, to 11cc11s11 11nd conduct p11riodic in11p11ction11 11nd to undertake oth11r 11ction11 that m11y b11 nec11s1111ry to enforce the requirements of the Township's Stormwater Management Ordinance or of anI applicable O&M plan or O&M agreement. If tha property owner. hia/her hairs. ssaigna or aucceaaora. faila in anI way to 111 ntain tha aaid racilitiaa. or c11u11e11 the11e f11cilitie11 to be 11lter11d or removed, upon writt11n notific11t on by th11 Township, the d11fect11 11h11ll promptly be corrected by the property owner. Upon the owner·a failure to correct the defects within time specified by the Townahip, the owner, hislhar heirs, assigns or successors, do hereby authorize the Township 11nd/or its contractor to enter upon the said property 11nd cause the repair, 1111inten11nce, and/or correction to be 1111de. A lien 1111y be filed against the property for the coat of all corractiona, including applicable engineering and/or attorney's fees. Tha TownahiP ia und11r no obligation to take 11ny action. All 11ubsequent real e11t11t11 tr11ns11ctions. th11 exist11nce of th11se stormw11t11r f11cilitie11 and their maintenance responsibilities shall be di11clo11ed to the new owners. Any revision to the approved SWM site plan ah11ll be aubmittad to tha TownahiP 111ong with 11n Eroaion & Bedi111nt11tion control Plan for raviaw 11nd approval.
Signature Dllte ....
N 49'31'00• E 250.00'
I
N 49'31'00"' E 110.32'
N49.31 '00"E-~ 25.05'
FLAG
OVERLAP
16.50'
POLE WIDTH
25.oo·
8.50'
N/L HAMM DANIEL G
& SHEILA A i5i0 MEADOWBROOK LN. DBt9i03, PGti06
0· ru~ . ru ru . "'°' ..... C0"1
I I
~o /·o"' coN !ii
N55 '02 '40 "E 193.29· NIL MATCHICA STRATTON N '
G ANGELA N /
EX.DRIVEWAY TO BE WIDENED TO 12'
N/L DORN ARTHUR
150B MEADOWBROOK LN. 0Bf81i3, PGf127i I
!ii .. !; S5s·o2·4o·w ~ 194.62'
~ ~-------------------------" 10' ill z
AREA• 3,879.11 SF
NIL LIM LUVIMINO 0 G LUZ S
1500 llEADDWBRDOK LN. UPI
EX.20 FT WIDE SANITARY SEWER EASEMENT 53-4-8 N49'31'00"E 401.94'
(EX.)
N/L DOHERTY NOEL G SHEILA I i502 MEADOWBROOK LN. DBt6236, PGtii92
UPI 53-4-8.1
1 S49 •31 ·oo·w~~ I 2.00·
100.00'
I I
1504 MEADOWBROOK LN. 08#8465, PG#605
UPI 53-4-23. 31
PROP.20' WIDE SAN.LATERAL EASEMENT S49 '31 '00"W 192.35'
110.31'
I I
UPI 53-4-23.2
PROP. IP N49'31'00"E 330.95'
110.
1UPI 53-4- .1
1
llJ'ii1i liUllL.
TOP OF
IRON PIN ELEV.438.05 I I
N49'31'00"E 138.60' 110.32'
"" EP ' ' I ~Q~iD~§~~~~~.1~
r---f--f-r.-;;.HE~M~L~O".°'CK HILL ROW ' 33.oo· ,
EP
"" ' ' I
I N/L GROSSMAN EDWARD R & ROCHELLE B I 707 1-EMPLOCK HILL LN. 0815341. PGf1040 I
UPI 53-4-25. 1
'"--EX. HEMLOCK HILL LANE I I I
UPI 53-4-24
I I
I
o- ruo . 0 (\J • ~g
• o- ruo . 0 (\J • "'O • 0 ~cu mcu
549'31'00" 2.00'
AREA • 6, 271.00 SF
400
WEST CHESTER, PA
SCALE: 1" • 600'
QUAD
S51'55'45"W 25.00'
S49 '31 'OO"W 138.60'
N49'31'00"E 162.00'
5.05' PROP.IP N49°31'00"E 399.94' <>~ ]"tl-0._-PROP. 25 ' WIDE
ACCESS EASEMENT TOLOTf2
I I
REVIEWED BY TtE PLANNING COl"4ISSION OF EAST GOStEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
UJ • 0- ruo ·o ru . "'O • 0 CON "' "'
FY 60. I I
BAKER PROPERTY
UPI 53-4-7
NIL GABLE MARY VIRGINIA i43i BOOT RO DBf5B, PGf553
'----
S49'31'00"W 399.94'
1 . ~ PROP.BOUNDARY LINE,___________ -
PROP.REAR YARD LINE
PROP.2.00 FT WIDE 200.00 FT LONG STRIP OF LAND TO BE CONVEYED TO UPI 53-4-23
---......,
I
IU • li!c. . 0 ~· .g 111ru UI
RY 50.
0 ru ru :r co !ii
SY 20·
NIL ABRAHAM JENSEN G CitlJY 919 CONTINENTAL OR. S49'31'00"W 401.94' (EX.) UPI
PROP.IP
53-4-211 IMPERVIOUS SURFACE: LOTt1 - PROPOSED BUILDING• 2,6667.37 SF IMPERVIOUS AREA IN LOTf1 • 4,47.38 SF
UPI 53-4-210
PLUS 501 CF JOINT DRIVEWAY WITHIN L0Tt1 • 1,255.0B SF TOTAL IMPERVIOUS AREA IN LOTf1 • ~ 402.46 SF
LOTt2 - EXISTING BUILDINB • 2.662.45 SF IMPERVIOUS AREA IN LOTf2 • 6, 726.28 SF PLUS 501 CF JOINT DRIVEWAY WITHIN LOTt1 • 1,255.08 SF TOTAL IMPERVIOUS AREA IN LOTf2 • 7.981.33 SF
I
I I
NIL SOLLECITOTHOMAS P G CAROLYN B 920 CONTINENTAL DR. 0Bf4679, PGf1B97
PROP.LOT#
_J
UPI
N49'31'00"E 208.75' 53-4-217 N/L LU HUE SHIANG 9i7 NATHANIEL OR. 0Bt2075, PGt38B
\
REl&ESTED WAIVERS FROM TIE SUIJIYISJON ANJ LAN> DEYELIFMENT CRJINANCE: LOT
SY 20·
\
lD LJ... ru 1CJ
~ ru R P.LOTf1 EX.PAVEMENT
I
•
20
S49'31'00"W 149.26'
s 49'31'00" w
(EX.)
356.00'
SY 20·
I I I I I
TO BE REMOVED
N/L TUBMAN EDWARD P G JOAN E 705 HEMPLOCK HILL LN. OB#3725, PG#1435
EX.DRIVEWAY TO BE WIDENED TO 12'
I I
I I
I
~~-~::~~~A~~-!---
/ 7 ----
PROP.IP PROP.SUBDIVISION LINE UPI 53-4-218
/ / N/L KASHEHAGEN LEO
i9 NATHANIEL DR. Bt79i9, PGt207B
\
& CHRISTIANE M SURVEYOR'S CERTIFICATION:
I hereby certifies that the boundary shown hereon was calculated by me end that the plan and survey accuracy ie in conformance with all East Goshen Township Ordinances.
Signature 011f e
COl"40NlllEALTH OF PEMllSYLVANIA COl.MTY OF CHESTER
On this the day of , before me,
THIS ____ DAV OF----
CHAIRPERSON MEMBER MEMBER
VICE CHAIR MEteER MEteER
APPROVED BY THE SUPERVISORS OF EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
THIS ---- DAY OF ---~
MEMBER
REVIEWED BY THE EAST GOSHEN TOWNSHIP ENGINEER THIS DAY OF----
CHAIRPERSON SUPERVISOR SUPERVISOR TOWNSHIP ENGINEER
VICE CHAIR SUPERVISOR
REVIEWED BY TIE Cl-ESTER COl.MTY PLAN\IING COfltlISSION
THIS ___ DAY OF ---
SECFETARY
RECOFIJEO IN TIE OFFICE OF THE RECOFIJER OF DEEDS OF CHESTER COUNTY AT WEST Cl-ESTER. PENNSYLVANIA,
IN PLAN BOOK --- PABE ---
THI5 --- DAV OF ---
RECOFIJER OF DEEDS
EAST GOSHEN TOWNSHIP ZONING HEARING BOARD DECISION OF 10/3/2017 GRANTING THE FOLLOWING VARIANCES: i. A variance from the minimum lot width at the street line requirements of Section 240-9G for Proposed Loteti and t2; 2. A variance in the street frontage requirement of Section 240-23.BC2l lal for Proposed Lotsfi and t2; and 3. A variance from the minimum pole width requirement of Section 240-23.B(2) lbl [2] [e] for Proposed Lott2. Conditions: A. Applicants shall create the greatest possible sight triangle at the top of the driveway near the existing home, which ie at the northeast corner of Proposed Lotti where the driveway takes a 45-degree turn toward Hemlock Hill Lane: B. Applicants shall provide a complete evergreen landscape buffer for properties adjacent to the property that are located along Nathaniel Drive:
AREA [SF] AREA [AC] 1. SECTIONS 205.28 & 205.31: COMBINE THE PRELIMINARY ANO FINAL REVIEW ANO APPROVAL PROCESS. tha subacribar. 11 notary public of tha commonwa11lth of Pennay1v11ni11, p11rson11lly app1111red who 11cknowl11dg1111
C. Applicants shall provide a large pull-off area along Hemlock Hill Lane to ensure safety for pedestrians and motorists using the lane: such pull-off area shall equal or exceed the area shown on Exhibit A-5: PEtff3Yl.. VANIA LAW AEQUIFES
3 wa:!Klrf3 DAYS NlTICE Fm CONSTFLICTION PHASE MD 10 wa:IKirf3 DAYS IN DESIGN PHASE - STOP CALL Pennsylvania One Call System, Inc
1-800-2.i42-1n6 SERIAL No.20i70472360 DATE: 02/i6/20i7
EXISTING B7, 491.2i UPI 53-4-23 87,077.89 PROP.LOT.I 43,995.00 43, 581.67 PROP.LOT.2 43,896.2i B5, 213. 70 BO, 213. 70 84, 813. 70 7B, B13. 70
EXISTING UPI 53-4-7 PROPOSED UPI 53-4-7
2.00B5 1. 9990 1.0iOO 1.0005 i .0077 1. 9562 1.8415 1. 9471 1.B323
UPI ADDRESS OWNERS DEED BK PAGE 53-4-23 53-4-7 i506 MEADOWBROOK LA LEGENSTEIN STEPEH & DENISE i43i BOOT RD GABLE MARY VIRGINIA
5051 P5B
THIS PLAN HAS BEEN PREPARED BASED ON THE FOLLOWING INFORMATION SOURCES: BOUNDARY & TOPOGRAPHIC SURVEY PLAN, PREPARED BY R.H. SMITH SURVEYORS, WEST CHESTER. PA. DATED 7/29/2017: EAST GOSHEN TOWNSHIP ZONING MAP: A PLAN ENTITLED 'PLAN OF SUBDIVISION FOR ANTHONY D'AMBROSIO" PREPARED BY HENRY S.CONREY INC., DATED B/i40/i977:
2296 553
A PLAN ENTITLED "FINAL TITLE PLAN" PREPARED BY D.L.HOWELL G ASSOSCIATES, INC., DATED i0/30/200i, LAST REVISED 3/ii/2002; A PLAN ENTITLED "FINAL SUBDIVISION PLAN FOR BRUCE & AUDREY A.ATKINS" PREPARED BY JOHN D.STAPLETON III, DATED ii/3/i992; CHESTER COUNTY CHESCO VIEWS WEBSITE FOR DEEDS ANO OWNERSHIP Itf'"ORMATION; CHESTER COUNTY RECORDER OF DEEDS: GUY ENGINEERING ASSOCIATES, INC. HAS NOT PERFORMED ANY FIELD SURVEY OF THE PROPERTY ANO IS NOT RESPONSIBLE FOR ANY ERRORS, INACCRURACIES OR OMMISSIONS OF INFORMATION SHOWN ON THIS PLAN.
(GROSS) (NET) (GROSS) (NET)
(GROSS) (NET) (GROSS) (NET)
AREA ISFl
{PEA OEEOl
B7, 120 82, 764
R-2: LOW-DENSITY RESIDENTIAL DISTRICT EX.PROPERTY AREA= 87,491.2i SF (GROSS). 87.077.89 SF (NET) SECTION 240-9.B Cil 240-9.G
240-23.BC2l la] 240-23.B(2) (bl [2] [b] 240-23.BC2l lbl [2] [e]
DESCRIPTION PERMITTED USES: MIN. LOT AREA
MIN. LOT WIDTH
MAX.LOT COVERAGE
MAX.BUILDING HEIGHT
MIN.FRONT YARD
AVE . FRONT YARD MIN.SIDE YARD MIN.REAR YARD STREET FRONTAGE MAX.POLE LENGTH MIN. POLE WIDTH
REQUIRED PROVIDED SINGLE FAMILY DETACHED DWELLING 43, 560 SF
150 FT
60 FT
25•
35•
3 30 FT 45 FT
60 FT 20 FT 50 FT EACH LOT 400 FT 40 FT
LOT#1: LOT#2: LOTt1: LOTt2: LOTfi: LOTf2:
43, 5Bi.67 SF 43, B96.2i SF i59.69 FT i9B.32 FT 25.05 FT 0 FT
(NET)
LOT#1: LOTt2: LOTfi: LOT#2: 3
6. 11 PROPOSED 6. 11 EXISTING i2.41 PROPOSED iB.21 EXISTING
30 FT LOTt1: 60 FT LOTt2: 60 FT 60 FT 20 FT 50 FT LOT#1 YES, LOT#2 NO 379. 21 FT 25 FT
VARIANCE
NO
NO NO NO NO BRANTEll
NO
NO
NO NO NO NO NO NO NO BRANTEll
NO BRANTEll
COMMENTS
AT BLOG.LINE AT BLOG.LINE AT STREET LINE AT STREET LINE BUILDINGS
TOTAL IMPERVIOUS COVER STORIES FEET
TO LOTt1 CORNEA EX. CONDITIONS PROP.LOTfi
NOTES
'
2 3
3
himaelf/hereelf to be owner and/or equitable owner of the progerty shown on this plan. and that he/aha acknowladgaa the 11111 to a hi11/h11r 11ct 11nd plan 11nd d1111ir1111 the 91111111 to b11 recorded a8 11uch according to law.
(Yg@J~[QJ
EX.PROPERTY LINE Notary Pub] ic
My co11111iaaion Expirea:
UTILITY NOTES: 1. PROPOSED LOTS TO BE SERVED BY PUBLIC SEWER. 2. EACH LOT WILL HAVE AN ON-LOT WATER SUPPLY WELL. 3. LOTfi WILL ACCESS PUBLIC SEWER THROUGH AN EASEMENT IN LOT#2.
ZONING NOTES: 1. THE TOTAL AREA OF THE LOT TO BE SUBDIVIDED WILL INCREASE Tl-f10UGH THE PURCHASE OF A STRIP OF LAND FROM THE ADJACENT PROPERTY UPI 53-4-7 ANO ADDED TO THE SUBJECT PROPERTY. Tl-E AREA OF THE LAND TO BE PURCHASED IS 400.00 SF. 2. THE EXISTING UPI 53-4-23 PROPERTY HAS A FRONTAGE OF 25.05 FT AT THE STREET LINE. THE DRIVEWAY TO THE PROPERTY IS KNOWN ALSO AS HEMLOCK HILL LANE. A PRIVATE ROAD THAT PROVIDES ACCESS TO THIS PROPERTY, AS WELL AS 4 ADDITIONAL PROPERTIES. 3. THE DRIVEWAY OF PROPOSED LOT # 2 WILL ACCESS FROM THE EXISTING HEMLOCK HILL LANE ANO AN ACCESS EASEllENT THROUGH PROPOSED LOT f 1 ANO WILL NOT HAYE A SEPARATE FRONTAGE ON A PUBLIC ROAD.
ADJACENT.PROPERTY LINE
EX.ROAD R.O.W. EX.TITLE LINE
EX.BUILDING
EX.PAVEMENT
PROP.LOT LINE
PROP.DRIVEWAY EASEMENT PROP.SANITARY LATERAL EASEMENT
PROP.BUILDING
PROP.DRIVEWAY
N90'00'00"W 61.87'
N90 'OQ.' 00 "W -~~ITT .87'"• ~-
D
N90 ·oo • o::? 61.87' ~ ~
I I
D. Applicants shall pave the pull-off area with porous pavers an widen the shared driveway serving Lotsfi and t2 to be 12 feet. and add Proposed Lotti into the existing Shared Driveway Easement Maintenance Agreement; E. Applicants shall finalize the subdivision with Mrs. Biiker, so that both Proposed Lotti 11nd Lott2 will comply with the one-acre lot area requirement. F. Applicants shall comply with all representations made during the hearing and as sat forth in the exhibits.
PROPERTY OW~R:
STEPHEN & DENISE LEGENSTEIN DEED RECORDED: DB.5051, PG.2296
TMP # 53-4-23
GRAPHIC SCALE --- -
1"•50' --- - 0 50 100 150
THIS PLAN IS THE PROPERTY OF GUY ENGINEERING ASSOCIATES, INC. ALL RIGHTS RESERVED. NO ALTERATIONS, REPRODUCTIONS OR USE OF ANY PARTS OF ITS CONTENTS MAY BE MADE WITHOUT THE EXPRESSED WRITTEN PERMISSION BY THE AUTHOR.
i5 ... ... a. ... a: u UI l!l
IU ... £!!
>-m
~
0 a: a. .... m - ~ I "" 01 IL > ......
u " m CD ·- ::> 0 "' L a.
z "' ... "' UJ " "' z UJ a. 0 a: a.
CD ~ ' "' ru ' ~ 0
"' "'
~
" "' u a. a. 0 a: a.
CD ~ ' 0 ru ' ru 0
"' "'
ru
0 ., I •
m ~ m u "'
CD ~
I "' ru
I "' "' UJ ... > UJ a: "' z UJ
CD ~ ' 0 ru ' .., 0
"' "'
"'
CD CD ~ ~
I I "'
ru ~ ru
I I ., co "' "' UJ UJ ... ... > > UJ UJ a: a: "' "' z z UJ UJ
CD CD ~ ~ ' ' -.,
0 ru ' ' co co 0 0
"' "' "' "' .., .,
J
"' "'
n m " u m .o= u
"' "'
i m L "
.... ~ 0 ru ' - 0 ' CD
m ... m "
LL 0
I I
N 49'31'00• E 226.60'
N 49'31'00• E 250.00'
\
\
______ 33'_Wl_DE_
\-~ \,.
125.0 •
I "' I
UJ •
z
UPI 53-4-8
EX.20 FT WIDE SANITARY SEWER EASEMENT
N49'31'00"'E 401.94'
(EX.;_) __
BAKER PROPERTY
UPI 53-4-7
\
EX.CO
I I I I I I
I
O· CIJO ·o "' . "O • 0 COCIJ EX. PLANTING I I I I I
"' "'
- - s49·3i:oo·w 401.94-:-1- 1Ex.) UPI 53-4-210
SURVEY DATUM: NAVO 19BB
UPI ADDRESS OWNERS 53-4-23 1506 MEADOWBROOK LA LEGENSTEIN STEPEH & DENISE 53-4-7 1431 BOOT RD GABLE MARY VIRGINIA 53-4-25.1 707 HEMLOCK HILL LA GROSSMAN EDWARD R & ROCHELLE B 53-4-23.1 1510 MEADOWBROOK LA HAMM DANIEL G & SHEILA A 53-4-23.2 1508 MEADOWBROOK LA DORN ARTHUR 53-4-23.3 1504 MEADOWBROOK LA MATCHICA STRATTON N & ANGELA N 53-4-8.1 1502 MEADOWBROOK LA DOHERTY NOEL & SHEILA 53-4-8 1500 MEADOWBROOK LA LIM LUVIMIND D & LUZ S 53-4-210 919 CONTINENTAL DR ABRAHAM JENSEN & CINDY
I
I I
DEED BK
5051 P5B 5341 9103 8113 B465 6236
PAGE 2296 553 1040 106 1271 605 1192
53-4-211 920 CONTINENTAL DR SDLLECITO THOMAS P & CAROLYN B 4679 1B97 53-4-217 917 NATHANIEL DR LU HUE SHIANG 2075 3BB 53-4-21B 919 NATHANIEL DR KASHEHAGEN LEO & CHRISTIANE M 7919 207B 53-4-24 705 HEMLOCK HILL LA TUBMAN EDWARD P & JOAN E 3725 1435 THIS PLAN HAS BEEN PREPARED BASED ON THE FOLLOWING INFORMATION SOURCES: BOUNDARY & TOPOGRAPHIC SURVEY PLAN, PREPARED BY A.H. SMITH SURVEYORS, WEST CHESTER, PA, DATED 7/29/2017; EAST GOSHEN TOWNSHIP ZONING MAP; A PLAN ENTITLED "'PLAN OF SUBDIVISION FOR ANTHONY D'AMBADSIO"' PREPARED BY HENRY S.CONAEY INC .. DATED B/140/1977; A PLAN ENTITLED ""FINAL TITLE PLAN"" PREPARED BY D. L. HOWELL & ASSOSCIATES,
INC .. DATED 10/30/2001, LAST REVISED 3/11/2002; A PLAN ENTITLED ""FINAL SUBDIVISION PLAN FOR BRUCE & AUDREY A.ATKINS" PREPARED BY JOHN D.STAPLETDN III, DATED 11/3/1992; CHESTER COUNTY CHESCD VIEWS WEBSITE FOR DEEDS AND OWNERSHIP INFORMATION; CHESTER COUNTY RECORDER OF DEEDS; GUY ENGINEERING ASSOCIATES, INC. HAS NOT PERFORMED ANY FIELD SURVEY OF THE PROPERTY AND IS NOT RESPONSIBLE FOR ANY ERRORS, INACCRUAACIES DA OMMISSIDNS OF INFORMATION SHOWN ON THIS PLAN.
UPI
AREA [SF) (PER DEED)
B7, 120 B2, 764 49,614 43.560 43,560 43,560 56,62B 60.9B4 30,866 26,556 34,542 2B.24B 69,696
-....._
'
FLOOD HAZARD NOTE:
' \
\
I
I
UPI 53-4-217
\
\ UPI 53-4-218 \
\
THE SITE IS LOCATED IN ZONE X - AREA OF MINIMAL FLOOD HAZARD. PEA FEMA FIRM NUMBER 42029C0215G EFFECTIVE 09/29/2017, FOR EAST GOSHEN, PA, PANEL NUMBER 420277.
EXISTING SOILS ON SITE;
GdB: GdC: UrcB: UrlB:
Gladstone Gravely Loam, 3 - Bl slopes, HSG "BM Gladstone Grave1v Loam. B - 15% slopes. HSG "B" Urban Land - Califon Complex. O - 8% slopes. HSG "B" (assumed) Urban Land - Gladstone Complex, a - 8% slopes, HSG "B" (assumed)
/ /
----- - -
53-4-25. 1
UPI 53-4-24
..
' ' I
I I I
I I
I I I
I I I
I
~~[ii)
EX.PROPERTY LINE
ADJACENT.PROPERTY LINE
EX.ROAD A.O.W. EX.TITLE LINE EX.PAVEMENT EX.BUILDING
EX.TREE
EX.SANITARY SEWER EX.GAS LINE EX.CONTOUR SOILS BOUNDARY EX.DRAINAGE AREA BOUNDARY
N90 'OQ_' 00 'W _ ___,,. in .87.
Nso_:.oo_: oo • w ----'"" 61. 87.
D 0 --s --<0----{l -----11------ - - -··-··-··
400
r-- L___...
P::,,..;=----- :: ----- r!I >- - \ j/ ,__ ~ f \ f I ,u50 ..--..... l/
~™'lnlmMM
WEST CHESTER, PA QUAD
SCALE: 1.. • 600"
PENNSYLVANIA LAW REQUIRES 3 WORKING DAYS NOTICE FOR CONSTRUCTION PHASE AND 10 WORKING DAYS IN DESIGN PHASE - STOP CALL Pennsylvania One Call System, Inc
1-800-242-1776 SERIAL No. 20170472360 DATE: 02/16/2017
PROPERTY OWNER:
STEPHEN & DENISE LEGENSTEIN DEED RECORDED: 08.5051, PG.2296
TMP # 53-4-23
GRAPHIC SCALE --- -
1"•50" --- - 0 50 100 150
THIS PLAN IS THE PROPERTY OF GUY ENGINEERING ASSOCIATES, INC. ALL RIGHTS RESERVED. NO ALTERATIONS, REPRODUCTIONS OR USE OF ANY PARTS OF ITS CONTENTS MAY BE MADE WITHOUT THE EXPRESSED WRITTEN PERMISSION BY THE AUTHOR.
i5 .... .... a. .... a: u ., l!l
w .... £!!
> m
~
0 a: a. ... m - ~ I "" m IL > .......
u " m m ·- ::> 0 "' L a.
z "' .... "' UJ " "' z UJ a. 0 a: a.
m - ' co "' ' - 0
"' "' -
" "' u a. a. 0 a: a.
m - ' 0 "' ' "' 0
"' "'
"'
0 ., I '
m - m u "'
m - I co "' I "' "' UJ .... > UJ a: "' z UJ
m - ' 0 "' ' .., 0
"' "'
"'
m m -- I I co "' -"' I I ., co "' "' UJ UJ .... .... > > UJ UJ a: a: "' "' z z UJ UJ
m m -- ' ' -.,
0 "' ' ' co co 0 0
"' "' "' "' .., .,
J
"' "'
n m " u m .i= u
"' "'
i m L "
... - 0 "' ' - 0 ' m
m ... m "
LL 0
I I
5.0 •
z
UJ • O· No ·a OJ. "'" • a CON "' "'
EX.UTIL.POLE ~ BT090FPA
[i'l.i]~[Q)@\'l,i'll[ID[j\l@@~ 11L!.\OO~ & MH fo~.\ii." 2 33' WlDE -----
~.INLET ~
:----:~~~E~P~~~~~~~,~~{~~~E~X,·~IN~'".1. .... s 49'31'00"' w J ...... ~~407.91
' ' - ' ' - ' ' .-49'31'00-. -E ~s.-.o-· ' ' - ' ' - I; _, ___ ,_,_.-._.-._
94 ~ - - ' ' - 1r ... " .. :~·:-:o.31· -1~,~.-.-.. -,,-.::;:·:-"-,-,0-.• -2· - - 10i -N- 49-'.3-,.~::~:-~p-,,o. ~~ 0 =__,='::s:' :;;;::~-~-- 1 -·
I I I I ,, \,_ -----
N 49'31'00• E 250.00'
UPI 53-4-8
EX.20 FT WIDE SANITARY SEWER EASEMENT
I / / N49"31'00"E \,_ I
25 05. .... ' .,.~·- \ \,,.- ' I I I . ,, ":: ' .... :'.' '
;,. OVERLAP ' ~ ~ 16 ::------EX.DRIVEWAY TO /:;j .so· .. , ' - UPI 53-4-25. I J... / I / FLAG POLE WIDTH "'rt "'- HEMLOCK HILL ROW '
=-- I I I 25.oo· 33.oo· '
I
~ I I I a.so· ...... ' ', --- \,_ ~ ' ~j~ "' ........ ' ":.Cl 1z (T) {\J ...., '-..' -~ '' ' Cf ' ~ ' ~ ' ~ ', <++"" ,.---,,,~~~~. ~~~~2 ~p~~~~c~~~ /
\
\
\-~ \,.
\
~ J; ; J; ; J; ; ~~ ~~ i~= (PERMEABLE PAVERS)
0 0 0 "" " --->@ ~ I~ H I~ H I~ H ~ '- ' t' fi:;;j ~ ~ ,~ Q_ ,~ Q_ '':f" a_ 0· ...... ,., => ,., => ~ => ?J ru '' ' l
z lz f z ~oi "" ' ', _,/ii~
I
PROP.~OL.F ~· DIP SLEEVE AAOUNJ 1.25" SAN.FORCE MAIN
• " ' [!!YJ EX.DRIVEWA TO BE lfl"' ..,, ' "" WIDENED TO 12' z " ' °"" {
APPROX.WELL~ ""-... , LOCATION J ...., , E/k<./f -'=-EP ' I
o I o~~ .... ~~b(.;;'/F.@°::T--
IRON PIN ', ELEV.43B.05
UPI 53-4-25.1
PROP.SAN.MH AT END OF EX.SEWER RIM 454.00
I I
PROP.1.25" PE SAN.FORCE LINE
PROP. IP
I I
,...__EX. HEMLOCK HILL LANE
I I I
I I
N49"31'00"E 401.94'
(EX.)
S49 •31 ·oo·w_:x.co
2.00' -
EX.MH. RIM 454.88 <>-- -~~-•
UPI 53-4-24
I
I
N49°31'00"E 399.94'
BAKER PROPERTY
UPI 53-4-7
PROP.BOUNDARY
EX. BOUNDARY LINE-f'::". ;t"'->:_:.;;i
EX. PLANTING~-
"--+'-"-PROP. 25 ' WIDE
ACCESS EASEMENT TOLOTf2
EX.PAVEMENT TO BE REMOVED
1J1:\-4/-:::::,,.__PROP. 6" PVC CLEANOUT W/LIO .,,
~ I g EX.DRIVEWAY TO BE WIDENED TO 12'
r7~'---PROP. TAM
<:or-.:.--PROP. INSPECTION PORT
I I
I I I
I
• - -
FLOOD HAZARD NOTE:
400
~™'lnlmMM
WEST CHESTER, PA QUAD
SCALE: 1" • 600'
UTILITY NOTES: 1. PROPOSED LOTS TO BE SERVED BY PUBLIC SEWER. 2. EACH LOT WILL HAVE AN ON-LOT WATER SUPPLY WELL. 3. LOT#! WILL ACCESS PUBLIC SEWER THROUGH AN EASEMENT IN LOT#2. 4. THE END OF THE PUBLIC SANITARY SEWER AT THE WEST CORNER OF LOT # 2 SHALL BE EXCAVATED AND THE EXISTING CLEANOUT SHALL BE REPLACED WITH A SANITARY MANHOLE. THE INVERT ELEVATION OF THE MANHOLE WILL BE DETERMINED AT THE TIME OF CONSTRUCTION TO MATCH THE INVERT ELEVATION OF THE EXISTING PIPE. THE EXISTING LATERAL SERVING LOT f 2 WILL BE CONNECTED TO THE MANHOLE. THE NEW FORCE LINE FROM LOT # 1 WILL BE CONNECTED TO THE MANHOLE AS WELL. ALL WORK SHALL BE PERFORMED WITHIN THE EXISTING PUBLIC SANITARY SEWER EASEMENT.
ZONING NOTES: 1. THE TOTAL AREA OF THE LOT TO BE SUBDIVIDED WILL INCREASE THROUGH THE PURCHASE OF A STRIP OF LAND FROM THE ADJACENT PROPERTY UPI 53-4-7 AND ADDED TO THE SUBJECT PROPERTY. THE AREA OF THE LAND TO BE PURCHASED IS 400.00 SF. 2. THE EXISTING UPI 53-4-23 PROPERTY HAS A FRONTAGE OF 25.05 FT AT THE STREET LINE. THE DRIVEWAY TO THE PROPERTY IS KNOWN ALSO AS HEMLOCK HILL LANE, A PRIVATE ROAD THAT PROVIDES ACCESS TO THIS PROPERTY. AS WELL AS 4 ADDITIONAL PROPERTIES. 3. THE DRIVEWAY OF PROPOSED LOT # 2 WILL ACCESS FROM THE EXISTING HEMLOCK HILL LANE AND AN ACCESS EASEMENT THROUGH PROPOSED LOT # 1 AND WILL NOT HAVE A SEPARATE FRONTAGE ON A PUBLIC ROAD. 4. THE SUBJECT PROPERTY AND ALL ADJACENT PROPERTIES ARE ZONED R-2, LOW DENSITY RESIDENTIAL DISTRICT.
I
PROP.2.00 FT WIDE 200.00 FT LONG STRIP OF LANO TO BE CONVEYED TO UPI 53-4-23
Jtf!-r--PROP. STORMWATER MANAGEMENT BMP I THE SITE IS LOCATED IN ZONE X - AREA OF MINIMAL FLOOD HAZARD. NUMBER 42029C0215G EFFECTIVE 09/29/2017, FOR EAST GOSHEN, PA, PER FEMA FIRM
PANEL NUMBER 420277. , .. ,
' I
I I '---- _J ... \ ----- ' \ \ \
\ ~~.~::~~~A~~-!---
PENNSYLVANIA LAW REQUIRES
S49"31'00"W 399 .. 94'
S49"31'00"W 401.94' (EX.) UPI 53-4-210
I
I I
3 WORKING DAYS NOTICE FOR CONSTRUCTION PHASE AND 10 WORKING DAYS IN DESIGN PHASE - STOP CALL
LOT AREA [SF] AREA [AC]
Pennsylvania One Call System, Inc
1-800-242-1776 SERIAL No. 20170472360 DATE: 02/16/2017
SURVEY DATUM: NAVO 19BB
EXISTING
PROP.1
PROP.2
87. 491. 21 B7, 077.B9 43. 995.00 43, 5B!. 67 43. B96.21
2.00B5 1. 9990 1. 0100 1. 0005 1. 0077
(GROSS)
(GROSS) (NET)
THIS PLAN HAS BEEN PREPARED BASED ON THE FOLLOWING INFORMATION SOURCES: BOUNDARY & TOPOGRAPHIC SURVEY PLAN, PREPARED BY R.H. SMITH SURVEYORS, WEST CHESTER, PA, DATED 7/29/2017; EAST GOSHEN TOWNSHIP ZONING MAP; A PLAN ENTITLED "PLAN OF SUBDIVISION FOR ANTHONY D'AMBROSIO" PREPARED BY HENRY S.CONREY INC .. OATEO B/140/1977; A PLAN ENTITLED "FINAL TITLE PLAN" PREPARED BY D. L. HOWELL & ASSOSCIATES, INC., DATED 10/30/2001, LAST REVISED 3/11/2002; A PLAN ENTITLED "FINAL SUBDIVISION PLAN FOR BRUCE & AUDREY A.ATKINS" PREPARED BY JOHN a.STAPLETON III, DATED 11/3/1992; CHESTER COUNTY CHESCO VIEWS WEBSITE FOR DEEDS ANO OWNERSHIP INFORMATION; CHESTER COUNTY RECORDER OF DEEDS; GUY ENGINEERING ASSOCIATES, INC. HAS NOT PERFORMED ANY FIELD SURVEY OF THE PROPERTY AND IS NOT RESPONSIBLE FOR ANY ERRORS, INACCRURACIES OR OMMISSIONS OF INFORMATION SHOWN ON THIS PLAN.
' I \ PROP. P UPI 53- -~11 I I
I
I 49t31 'I?~,~ I 35t. ~·
' ' Pl:ioP WELL T I , '
=pRQP./l:L"'EA"N"'Omorrr li?LID ___ ,_ - --
N49"31'00"E 20B.75' \
\
PROP.IP PROP.SUBDIVISION LINE / UPI 53-4-218 / UPI 53-4-217 \
\
SANITARY SEWER NOTES: 1. THE SANITARY SEWER LATERAL AND FORCE MAIN SHALL HAVE A MINIMUM COVER OF 3 FEET. 2. THE DISCHARGE PIPE FROM THE GRINDER PUMP SHALL BE 1. 25" DIA. PVC SOR 21. 3. THE FORCE MAIN SHALL BE INSTALLED INSIDE A 4" DIA. DUCTILE IRON PIPE SLEEVE UNDER THE DROVEWAY. THE SLEEVE SHALL BE 40 LF MIN. ANO SHALL EXTEND AT LEAST 5 FT ON EITHER SIDE OF THE DRIVEWAY. THE FORCE LINE SHALL BE SECURED IN PLACE INSIDE THE SLEEVE TO PREVENT MOVEMENT. 4. THE PROPOSED SANITARY CONNECTION FOR THE PROJECT WILL BE MADE TO AN EXISTING SANITARY SEWER OF EAST GOSHEN MUNICIPAL AUTHORITY LOCATED WITHIN UPI 53-4-B.1 INSIDE AN EXISTING SANITARY SEWER EASEMENT PER RIGHT-OF-WAY AGREEMENT OATEO 7/25/1994, RECORDED IN BOOK # 3B73, PAGE 462-46B.
ELECTRIC POWER SUPPLY NOTE: THE ELECTRIC COMPANY SHALL REMOVE THE TEMPORARY ELECTRIC POWER SUPPLY CABLE TO THE EXISTING HOUSE IN LOT # 2 AND INSTALL A PERMANENT POWER SUPPLY CABLE
INSTEAD UNDERGOUND UNDER THE PROPOSED WIDENED DRIVEWAY WITHIN THE ACCESS EASEMENT THROUGH LOT f 1 TO LOT f 2. THE POWER SUPPLY LINE FOR THE PROPOSED HOUSE IN LOT f 1 WILL ALSO BE INSTALLED UNDERNEATH THE DRIVEWAY AND BE CONNECTED TO THE NEW HOUSE. THE REMOVAL OF THE EXISTING TEMPORARY SERVICE AND INSTALLATION OF THE PERMANENT SERVICE SHALL BE PERFORMED AT THE TIME OF CONSTRUCTION OF THE NEW DRIVEWAY THROUGH LOT # 1. THE ELECTRIC COMPANY SHALL DETERMINE THE EXACT LOCATIONS OF THE POWER SUPPLY LINES.
~IID'llID EX.PROPERTY LINE N90_:.QQ_.'. 00" W -~~ 6!.B7' PROP.LOT LINE PROP.DRIVEWAY 5. CLEANOUTS SHALL BE INSTALLED ON THE EXISTING LATERAL FROM LOT # 2 AT 10 FT DISTANCE FROM THE NEW SANITARY MANHOLE WITHIN THE SANITARY SEWER EASEMENT, AS WELL AS ON THE NEW FORCE MAIN FROM LOT # 1. AT 10 FT FROM THE MANHOLE. THE FORCE MAIN WILL TERMINATE AT THE CLEANOUT, FROM WHICH POINT THE EFFLUENT WILL DISCHARGE INTO THE MANHOLE VIA A 4" PVC SEWER LATERAL.
ADJACENT.PROPERTY LINE
EX.ROAD R.O.W. EX.TITLE LINE EX.PAVEMENT EX.BUILDING
N90"00'00"W -~~ 6!.B7'
PROP.DRIVEWAY EASEMENT PROP.PULL-OFF AREA PERMEABLE PAVERS ~
6. THE BUILDER SHALL PROVIDE A GRINDER PUMP UNIT CONSTRUCTION SUBMITTAL TO EAST GOSHEN TOWNSHIP FOR REVIEW AND APPROVAL PRIOR TO CONSTRUCTION. 7. THE FORCE MAIN SHALL BE INSTALLED FROM THE GRINDER PUMP UNIT TOWARD THE CLEANOUT IN A CONTINUOUS RISING SLOPE TO PREVENT CREATION OF HIGH POINTS ALONG ITS ROUTE. B. THE BUILDER SHALL PROVIDE A SOLID TRANSITION COUPLING CONSTRUCTION SUBMITTAL
TO EAST GOSHEN TOWNSHIP FOR REVIEW ANO APPROVAL PRIOR TO CONSTRUCTION.
TAM NOTE: TAM, SUCH AS NORTH AMERICAN GREEN P300 OR EQUAL SHALL BE PLACED ON THE GROUND COVERING THE BERM OF THE BMP, EXTENDING FROM ELEVATION 439.50 ON THE INSIDE OF THE BERM AND DOWNSLOPE ON THE OUTSIDE OF THE BERM TO THE EAST PROPERT LINE.
D EX.TREE 0
EX.DEAD TREE TO BE REMOVED ~
EX.SANITARY SEWER EX.GAS LINE EX.CONTOUR
--s----s-- --<G G-- ____ ......_ ___ _
PROP.SANITARY LATERAL EASEMENT
PROP.TRIMMED VEGETATION
PROP.BUILDING
PROP.CONTOUR PROP.SANITARY LATERAL
l~1~1~1~1~1~I ~
I
s
PROPERTY OWNER:
STEPHEN & DENISE LEGENSTEIN DEED RECORDED: DB.5051, PG.2296
TMP # 53-4-23
GRAPHIC SCALE --- -
1"•50' --- - 0 50 100 150
THIS PLAN IS THE PROPERTY OF GUY ENGINEERING ASSOCIATES. INC. ALL RIGHTS RESERVED. NO ALTERATIONS, REPRODUCTIONS OR USE OF ANY PARTS OF ITS CONTENTS MAY BE MADE WITHOUT THE EXPRESSED WRITTEN PERMISSION BY THE AUTHOR.
i5 ... .... a. ... a: u ., l!l
w .... £!!
>-m
~
0 a: a. .... m - ~ I '" m LL > ......
u " m m ·- ::> 0 "' L a.
z "' ... "' w " "' z w a. 0 a: a.
m - ' "' N ' - 0
"' "' -
" "' u a. a. 0 a: a.
m - ' 0 N ' N 0
"' "'
N
a .,
I '
m - m u "'
m - I "' N I "' "' w ... > w a: "' z w
m - ' 0 N ' "' 0
"' "'
"'
m m -- I I "'
N - N I I ., "' "' "' w w ... ... > > w w a: a: "' "' z z w w
m m -- ' ' -.,
0 N ' ' "' "' 0 0
"' "' "' "'
"' .,
J
"' "'
n m " u m .i= u
"' "'
i m L "
.... - 0 N ' - a ' m
m ... m "
LL 0
400 FLOOD HAZARD NOTE: THE SITE IS LOCATED IN ZONE X - AREA OF MINIMAL FLOOD HAZARD. PER FEMA FIRM NUMBER 42029C0215G EFFECTIVE 09/29/2017, FOR EAST GOSHEN, PA, PANEL NUMBER 420277.
151.94'
EX.UTIL.POLE BT090FPA & MH EX.~LET TG=408 2 li'!il~@\'!A'!JIIDOO@@[)(( ~~
----.-.. -. .,=.1~·oo~~P~w~. ~~~t.o~s~·F~!~=~(~. ~iEX.INLEe
33' 1MOE ------
E_ ,,~32· ,
• E I ----- N 49'31'00• E 22B.6o' .. ~~~jtts:i1=~~-':"'-_l ' N 49"31 '00" E 110. ' o ""' '' _- ~J~~~-.-.--~1·00-"~:·
3 e
10 110.>1' - }~ ·--~~"~
0 -·"_'_ ..,.,,.., N 49"31'00" E 110.32'
I I "' I
25.0.
"' "' • O· No ·o "' .
I
N 49'31'00" E 250.00'
UPI 53-4-8
EX.20 FT WIDE SANITARY SEWER EASEMENT
N49'31'00"E 401.94' (EX.)
BAKER PROPERTY
UPI 53-4-7
1
I~ ,:i m ii I"' I
EX.MH.
'"
\~
I
RIM 454.68
CD
I "'1'
I (YJ Ul
PROP.SAN.MH AT END OF EX.SEWER RIM 454.00
EX.CO ---
s :::mo.DO" s
---·~-,,.,.
I ---- 1 ~~~
"Hl"PIN ' 30"MA
I I I
I I
I I I I.
I~
/-~ N I i! ~
(YJ
(YJ (\J
I "'1'
I (YJ Ul
H Q_ :J
PROP.40LF ~· DIP SLEEVE AROUND 1.25" SAN.FORCE MAIN I I I
I I N49 '31 'OO"E~XJl'f-
25. 05' ',' ... ~' .... ·-lll', 1..- ' '' -....::, ' ....... ~ ' ", f, :;.._-EX.DRIVEWAY T~ • , ' " _ UPI 53-4-25. 1- '\, I I
I I I I.
I~
/-~ N ,;:; ~
(\J
(YJ (\J
I "'1'
I (YJ Ul
I I I I.
...,
(YJ (\J
I "'1'
I (YJ Ul
,,', [, p '' ...... ' ' --- '\. ' ' ' l!!!!I '\. ~' ~! .._ ' tj-,+...
0
~,,-;::~IPROP. B 'x22' PULL-OFF -... ~ AREA WITH APPROACHES ..... ' , -,,, = (PERMEABLE PAVERSl .... ' ' __ , 25 ...... ' ,, r.,::-,:...,,.,,1 ~' i ~ ~
~ fu~ :'~ ~ --~~ :J - nr ' I >~
I~
H /~ Q_ 1" :J Ill
C\J • ..._ '- --Z .;rcn ' -. ' ,,.., EX.DRIVEWAf 2TO BE WIDENED TO 12'
• "' ' l!!!:!J ill"' ' ' = z ' • -f .f- "" UPI 53-4-25. 1
PROP.1.25" PE SAN.FORCE LINE
I I I
BtrU! !ll..!lll.
TOP OF
IRON PIN ELEV.438.05
... ,
' _LCr•EP ..... , 'E~ofl
' " I ;'#;~~-- ' :--... '"": ' '' ' '·'lf-V!< ' ..... \
\ \ ~
'"--EX. HEMLOCK HILL LANE
UPI 53-4-24
EX.PAVEMENT TO BE REMOVED
PROP.6" PVC CLEANOUT W/LID
' ' I
I I
I I I I I I I
BUFFER PLANTING NOTES:
';Y;(; ;:;;- ;/ IJ/ J / ' ~ f \ f I - .Q.50 ----.. "'11
~~OOINI~
WEST CHESTER, PA QUAD
SCALE: 1" • 600'
1. BUFFER TREES SHALL BE PLANTED IN STAGGERED ROWS CENTERED NO MORE THAN 18 FEET APART. 2. BUFFER SHRUBS SHALL BE PLANTED IN STAGGERED ROWS CENTERED NO MORE THAN 5 FEET APART . 3. PLANTINGS SHALL NOT BE OESEASE PRONE, INSECT PRONE, SHORT LIVED. 4. THE EXTERIOR WIDTH BEYOND THE PLANTING SCREEN SHALL BE PLANTED WITH GRASS SEED, SOD OR GROUND COVER ANO SHALL BE MAINTAINED AND KEPT CLEAN OF ALL DEBRIS, RUBBISH, WEEDS ANO TALL GRASS (NO MORE THAN12") . 5. PLANTED AREAS SHALL BE IRRIGATED.
I \
\
'
)
"fO •a ill"' I
EX.PLANTING-~
EX.DRIVEWAY TO BE WIDENED TO 12' I
50 f 449 .~.1-\l
'---1--1-1· I ~ · 150. oo "' "'
I I I '----
S49'31'00"W 401.94' (EX.) UPI 53-4-210
FOUNDATION PLANTING NOTE: THE APPLICANT WILL SUBMIT A FINAL FOUNDATION PLANTING PLAN TO THE TOWNSHIP WITH THE APPLICATION FOR BUILDING PERMIT.
I
I
PENNSYLVANIA LAW REQUIRES 3 WORKING UAYS NOTICE FOR CONSTRUCTION PHASE AND 10 WORKING DAYS IN DESIGN PHASE - STOP CALL Pennsy I van ia One Ca 11 System. Inc
1-800-242-1776 SERIAL No.20170472360 DATE: 02/16/2017
SURVEY DATUM: NAVO 19BB
I
LOT AREA [SF] AREA [AC] EXISTING B7.491.21 2.0085 (GROSS)
87.077.89 1.9990 PROP.1 43, 995.00 1.0100 (GROSS) 43, 581. 67 1. 0005 (NET) PROP.2 43, B96.21 1.0077
THIS PLAN HAS BEEN PREPARED BASED ON THE FOLLOWING INFORMATION SOURCES: BOUNDARY & TOPOGRAPHIC SURVEY PLAN, PREPARED BY R.H. SMITH SURVEYORS, WEST CHESTER, PA, DATED 7/29/2017; EAST GOSHEN TOWNSHIP ZONING MAP; A PLAN ENTITLED "PLAN OF SUBDIVISION FOR ANTHONY D'AMBROSIO" PREPARED BY HENRY S.CONREY INC .. DATED B/140/1977: A PLAN ENTITLED "FINAL TITLE PLAN" PREPARED BY O.L.HOWELL & ASSOSCIATES,
INC .. DATED 10/30/2001, LAST REVISED 3/11/2002: A PLAN ENTITLED "FINAL SUBDIVISION PLAN FOR BRUCE & AUDREY A.ATKINS" PREPARED BY JOHN O.STAPLETON III, DATED 11/3/1992: CHESTER COUNTY CHESCO VIEWS WEBSITE FOR DEEDS ANO OWNERSHIP INFORMATION: CHESTER COUNTY RECORDER OF DEEDS: GUY ENGINEERING ASSOCIATES, INC. HAS NOT PERFORMED ANY FIELD SURVEY OF THE PROPERTY ANO IS NOT RESPONSIBLE FOR ANY ERRORS, INACCRURACIES OR OMMISSIONS OF INFORMATION SHOWN ON THIS PLAN.
, ... ,
' __J .... , ',
\ I I \
I UPI 53-~-~11
\
\
\
\
\
I
I
I
I
\
~ E .HEM oc~ & ~NE EE \ow
I I
I \
\ UPI 53-4-217 \
TYPE KEY BOTANICAL NAME COMMON NAME SIZE ROOT QTY ORNAMENTAL MV TREE DECIDUOUS hq SHAUB DECIDUOUS cs SHRUB EVERGREEN rm SHAUB EVERGREEN tm SHRUB
TYPE KEY EVERGREEN CL TREE EVERGREEN PS TREE EVERGREEN TS TREE DECIDUOUS AR TREE
EVERGREEN td SHRUB EVERGREEN 1m SHRUB
EVERGREEN Yd SHRUB EVERGREEN tm SHRUB DECIDUOUS cs SHRUB EVERGREEN rm SHRUB
MAGNOLIA VIAGINIANA HYDRANGEA QUEACIFOLIA COANUS SERICEA
'FLAVIRAMEA' RHODODENDRON MIKKEL I TAXUS X MEDIA HICKSII
SWEET BAY MAGNOLIA OAKLEAF HYDRANGEA YELLOW TWIG DOGWOOD MIKKRLI RHOOODENDRON HICKS YEW
1.5" CAL. BGB
24" HT BGB
24" HT BGB
24" HT BGB
24" HT BGB
2
5
5 • 5
BOTANICAL NAME COMMON NAME SIZE ROOT QTY
CUPRESSUS LEYLAND II PI NUS STRDBUS THUJA STANJISII x PLICATA ACER RUBRUM
TAXUS DENSIFORMIS ILEX X MESERVEAEA
VIBURNUM DAVIDII TAXUS X MEDIA HICKS!! CORNUS SERICEA
'FLAVIRAMEA' RHODODENDRON MIKKEL I
LEYLAND CYPRESS WHITE PINE
THUJA GREEN GIANT RED MAPLE
B' HT BGB 4
B' HT BGB 6
B' HT BGB 4
2.5" CAL. BGB 3
DENSE 3' HT BGB 10 SPREADING YEW CHINA GIRL 3' HT BGB B HOLLY
DAVID VIBURNUM HICKS YEW
YELLOW TWIG DOGWOOD MIKKRLI RHODODENDRON
3• HT BGB 9
3' HT BGB 4
3' HT BGB 10
3• HT BGB 9
SYMBOL
f
0 Ell 0
SYMBOL • @ • 0 $ • 0 0 0 Ell
UPI 53-4-218
\
PROP.INSPECTION PORT
'f:-t4i~-PROP. STORMWATER MANAGEMENT BMP
3,AR I 9v~~.~~~~~~A~~ -!--- ,,.,..,,.,,,.. ___ , =J>ROP. / "CLEANOUT li7Llb - - --
PROP. EVERGREEN BUFFER PL4NTING
I ) \
'"1--1 ~.44,.0
m©~.l!J.i\OO~DINI®
.....,--9vd
'"---4CL h
PROPOSED RAIN GARDEN PLANTING: SCALE: 1 "•30 · BOTTOM (WILDFLOWERS AND FERNS) - PLANTED AT 2' O.C.: BONESET (EUPATORIUM PERFOLIATUM), SWAMP MILKWEED (ASCLEPIAS INCARNATA), BLUEFLAG IRIS (IRIS VERSICOLOR), TURTLEHEAD (CHELONE GLABRA) SIDES AND TOP (WILDFLOWERS AND FERNS) - PLANTED AT 2' O.C.: CINNAMOMEA FERN (OSMUNDA CINNAMONEA), WHITE WOOD ASTER (ASTER DIVARICATA), COLUMBINE (AQUILEGIA), MAYAPPLE (PODOPHYLLUM PELTATUM) REMAINING RAIN GARDEN AREA TO BE SEEDED WITH LOCAL RAIN GARDEN SEED MIXTURE BY ERNST SEED OR EQUAL.
lbmlll!INllID EX.PROPERTY LINE
ADJACENT.PROPERTY LINE
EX.ROAD R.O.W. EX.TITLE LINE EX.PAVEMENT
NQO_:OQ..'. 00 "W _ ___,,., 61. 97'1'. __.__
NQO_:OQ..'. 00 "W _ ___,,., 61. 87'
EX.BUILDING c::::::::J
EX.TREE ~
EX.DEAD TREE TO BE REMOVED ~
EX.SANITARY SEWER EX.GAS LINE EX.CONTOUR
--s----:s-- --G----G -----11-----
PROP.LOT LINE PROP.DRIVEWAY
PROP.DRIVEWAY EASEMENT PROP.PULL-OFF AREA PERMEABLE PAVERS PROP.SANITARY LATERAL EASEMENT
PROP.TRIMMED VEGETATION
PROP.BUILDING
PROP.CONTOUR PROP.SANITARY LATERAL PROP.TREE/SHRUB
~
l~1~1~1~1~1~I ~
I
PROPERTY OWNER:
STEPHEN & DENISE LEGENSTEIN DEED RECORDED: DB.5051, PG.2296
TMP # 53-4-23
GRAPHIC SCALE --- -
1 "=50' --- - 0 50 100 150
THIS PLAN IS THE PROPERTY OF GUY ENGINEERING ASSOCIATES, INC. ALL RIGHTS RESERVED. NO ALTERATIONS, REPRODUCTIONS OR USE OF ANY PARTS OF ITS CONTENTS MAY BE MADE WITHOUT THE EXPRESSED WRITTEN PERMISSION BY THE AUTHOR.
z 0 H .... ... H a: Ill l!j
.. !c c
,.. m
> II!
.
it) ~ n 0 '" "' IL > +' H u CJ ID al -~ =>
0 "' L ...
z "' H "' "' D "' z "' c. 0 a: ...
"' - ....
"' "' .... - 0
"' "' -
" "' " c. . c. 0 a: c.
"' - ....
0 "' ....
"' 0
"' "'
"'
. :il " '
ID n m u "'
"' -' "' "' ' "' " "' H > "' a: "' z "' "' - ....
0 "' .... .,.
0
"' "'
"'
"' "' -- I ' "' "' -"' ' ' on "' " " "' "' H H > > "' "' a: a: "' "' z z "' "' "' "' -- .... .... -.,
0 "' .... ....
"' "' 0 0
"' "' "' "' .,. .,
J
. "' . "'
~
ID "' u ID ~ "
. "' . "'
c • m L CJ
.... ~ 0 "' .... - 0 .... "' ;; .., m CJ
LL D
NOTE: TAM. SUCH AS NORTH AMERICAN GREEN P300 OR EQUAL SHALL BE PLACED ON THE GROUND COVERING THE BERM OF THE BMP. EXTENDING FROM ELEVATION 439.50 ON THE INSIDE OF THE BERM AND DOWNSLOPE ON THE OUTSIDE OF THE BERM TO THE EAST PROPERT LINE. EX. UTIL. POLE BT090FPA
[MJ~[Q)@~rn1@@~ 11&~1:§
& MH
33' WIDE EP ------ ------
~
! {
i;x.INLET LG=407.91
EAST GOSHEN O&M NOTES
1. The person or entity responsible for the operation and maintenance of a BMP or conveyance shall make records of the installation and of all maintenance and repairs. and shall retain the records for at least 2 years. A copy of these records shall be submitted to the Township. 2. Upon final inspection. the Municipality shall inform the person responsible for the operation and maintenance whether the submission of periodic (annual or other frequency) inspections and maintenance reports will be required. 3. The owner of each BMP and conveyance shall keep on file with the Township the name. address and telephone number of the person responsible for maintenance activities and implementation of the O&M plan. In the event of a change, new information shall be submitted by the BMP or conveyance owner to the Township within 10 days of the change. R
151.94' 110.31' -1~ ____ 1_10_.3_2_· - - - ---
4. All stormwater management structures shall be inspected at least 2 times per year. The overlying vegetation should be maintained in good condition. and care should be taken to avoid excessive compaction by mowers.
I
• 0 ·"' "' :t' Ill z
25.0 .
C!l
lLJ O· C\Jo ·a (\J . -to 'a <O (\J CT) rn I
N 49"31'00" E 226.60'
N 49'31'00" E 250.00'
UPI 53-4-8
EX.20 FT WIDE SANITARY SEWER EASEMENT
N49'31'00"E 401.94' (EX.)
I -----
I
I
EX.MH.
I" • \~
~
I
ClJ
I ~
I (T) lD
H 0.. :::>
PROP.SAN.MH AT END OF EX.SEWER RIM 454.00 S49 '31 'OO"IL':x. co
2.00' -
RIM 454. 88 ot--S =--ioo.oo
PR
PROP.BOUNDARY
BAKER PROPERTY
UPI 53-4-7 PROP.REAR YARD LINE
EX. PLANTING
I I
I
I
N 49'31'00" E 110.31'
(T)
(T) (\j
I "<:J"
I (T) ID
H Q. :::>
PROP.40LF 4" DIP SLEEVE AROUND 1.25" SAN.FORCE MAIN
PROP.20' WIDE SAN.LATERAL EASEMENT S49"31'00"W
..... .t._92 • 3§.: ' ..... , "" '.... '- ,110~1'-.
I
I
N 49"31'00" E 110.32'
I JS.so·-,"
FLAG POLE WIDTH "" '-'-
25. 0Q'
-........ "
(\j
(T) (\j
I "<:J"
I (T) ID
I
I.
I
~ ~ ,.,
31:
'
~ H "' o_ I :t- :::> Ill
EX.DRIVEWAf zTO BE WIDENED TD 12'
I PROP.DA-I
(T) (\j
I "<:J"
I (T) ID
H 3: Q. O· :::>
WU'li lil.IML
TOP OF
PROP. 1. 25" PE SAN.FORCE LINE
IRON PIN ELEV.438.05
' '
UPI 53-4-25. 1
EX.HEMLOCK HILL LANE
UPI 53-4-24
CT°--\-!-'>.._pROP. 25' WIDE
TO LOT # 2
EX.PAVEMENT TO BE REMOVED
PROP.6" PVC CLEANOUT W/LID
PROP.DA-IV
EX.DRIVEWAY TO BE WIDENED TO 12' "' 'Jlr 'J'§--1---PROP. TRM
,,,..__-PROP. INSPECTION PORT
' ' I
- -
INFILTRATION BED CONSTRUCTION NOTES
1. Excavation shall be performed with equipment that will not compact the bottom of the bed. Equipment shall not be allowed on excavated area of the infiltration bed at any time during its construction. 2. The bottom of the bed shall be scarified immediately prior to the placement of the geotextile fabric on the bottom of the bed. 3. The bed shall be protected during construction. Sediment shall not be allowed to be washed back into the bed, both during the time when the bottom of the bed is open, and once the stone is placed. 4. Only uniformly graded, clean aggregate, free of fines, slate, shale, clay, silt, and vegetative material shall be used. The supplier of the stone shall provide certification of the porosity of the stone delivered to the site. 5. Compaction of the infiltration bed shall be avoided to the fullest extent possible. Heavy equipment and traffic shall be restricted from traveling over the proposed location of the infiltration bed to minimize compaction of the soil. Excavation of the bed shall be completed with relatively light tracked equipment or from outside the bed to avoid compaction of the bed floor. 6. Construction equipment shall only be allowed on the top of the stone after it has been placed to its full depth and to allow completion of the placement of the stone and backfill. 7. Drainage filter fabric shall be placed in accordance with manufacturer's directions, including pipe genetrations and should overlap a minimum of 16 inches. 8. uring site construction all facility components shall be protected from sedimentation using storm inlet protection in accordance with the PAOEP Chapter 102 regulations, as amended, and the Erosion and Sediment Pollution Control Manual, as amended. Inlet protection shall remain until the contributary drainage area has achieved full stabilization. STORMWATER MANAGEMENT EASEMENT NOTE:
A olanket stormwater management easement is provided over and across the property in favor of East Goshen Township to allow the Township and its agents and designees access to the proposed stormwater management facilities. The Township is granted the right. but not the duty, to access and conduct periodic inspections and to undertake other actions that may be necessary to enforce the requirements of the Township's Stormwater Management Ordinance or of any applicable O&M plan or O&M agreement.
- - / rNsPECTioN
1
Po;:o:~ \ ' I I
P~OP
I
I I I
\
$:\"-I
~ I w w g:
::.:: () 0 _J ::;::;:
I~ lb I C!l
m~~h_-PROP. STORMWATER MANAGEMENT BMP I I ) I ( I / 0\
0 J I
I I
I
PROP.2.00 FT WIDE 200.00 FT LONG STRIP OF LAND TO BE CONVEYED TO UPI 53-4-23
I I I I \
l -
s49•31·oo·w 399.94'
S49"31'00"W 401.94' (EX.) UPI 53-4-210
PENNSYLVANIA LAW REQUIRES 3 WORKING DAYS NOTICE FOR CONSTRUCTION PHASE AND 10 WORKING DAYS IN DESIGN PHASE - STOP CALL Pennsylvania One Call System. Inc
1-800-242-1776 SERIAL No. 20170472350 DATE: 02/15/2017
SURVEY DATUM: NAVO 19BB
I
I
\
THIS PLAN HAS BEEN PREPARED BASED ON THE FOLLOWING INFORMATION SOURCES: BOUNDARY & TOPOGRAPHIC SURVEY PLAN, PREPARED BY R.H. SMITH SURVEYORS, WEST CHESTER, PA, DA TED 7/29/2017; EAST GOSHEN TOWNSHIP ZONING MAP; A PLAN ENTITLED "PLAN OF SUBDIVISION FOR ANTHONY D'AMBROSIO" PREPARED BY HENRY S.CONREY INC .. DATED B/140/1977: A PLAN ENTITLED "FINAL TITLE PLAN" PREPARED BY D.L.HOWELL & ASSOSCIATES. INC.. DATED 10/30/2001, LAST REVISED 3/11/2002; A PLAN ENTITLED "FINAL SUBDIVISION PLAN FOR BRUCE & AUDREY A.ATKINS" PREPARED BY JOHN D. STAPLETON III, DATED 11/3/1992; CHESTER COUNTY CHESCO VIEWS WEBSITE FOR DEEDS AND OWNERSHIP INFORMATION: CHESTER COUNTY RECORDER OF DEEDS: GUY ENGINEERING ASSOCIATES, INC. HAS NOT PERFORMED ANY FIELD SURVEY OF THE PROPERTY AND IS NOT RESPONSIBLE FOR ANY ERRORS. INACCRURACIES OR OMMISSIONS OF INFORMATION SHOWN ON THIS PLAN.
, .... ,
" __J"', \\
\ \ \
~F:.~/PT.~~.~-~:~~~A~(§ -!--- \
\
\
\
I \
PROP. P UPI 53-i4-~11
PROPOSED ROOF DRAIN PIPES:
I
I
N49"31'00"E 208.75' UPI 53-4-217
1. ALL ROOF DRAINS SHALL BE PIPED TO THE PROPOSED STORMWATER MANAEMENT BMP AND TIE INTO THE PERFORATED PVC PIPE INSIDE THE CRUSHED STONE BED. 2. DRAIN PIPES SHALL BE 6" DIA.PVC AT 0.02 FT/FT MIN. 3. ALL ROOF GUTTERS SHALL BE EQIPPED WITH GUTTER GUARDS TO PREVENT LEAVES FROM ENTERING THE ROOF DRAINS.
DOUBLE-RING INFILTRATION TEST RESULTS:
INFILTRATION TESTING WAS PERFORMED BY KATHERINE HEED AND PROVIDED TO GUY ENGINEERING. TEST PIT TP-1:
SURFACE ELEVATION = 441.00 DEPTH = 4B" TEST ELEVATION = 437.00
INFILTRATION RATE = 2.50 IN/HR TEST PIT TP-2:
SURFACE ELEVATION = 441.00 DEPTH = 4B" TEST ELEVATION = 437.00
INFILTRATION RATE = 6.9B IN/HR MEASURED AVERAGE INFILTRATION RATE= 4.74 IN/HR DESIGN INFILTRATION RATE = 2.37 IN/HR
EXISTING SOILS ON SITE: GdB: Gladstone Gravely Loam. 3 - B% slopes, HSG "B" GdC: Gladstone Gravely Loam. B - 15% slopes. HSG "B"
\
~P.DA-II
\
PROP.DA-III
=pRQP. / l!LEANCOT
/ /
PROPOSED IMPERVIOUS AREAS DRAINING TO STORMWATER BMP's: DA-II (Lot# 2) = 0.1020 ac
(150% of existing impervious area within DA-II) DA-III (Lot# 1) = 0.12B5 ac
~@ll§~IID
EX.PROPERTY LINE
ADJACENT.PROPERTY LINE
EX.ROAD R.O.W. EX.TITLE LINE EX.PAVEMENT
EX.BUILDING
EX.TREE
N90"00'00"W --~ 61.87 i", ~--
N90 'oo · oo • w ---'= 61.87 i", ~--
D 0
EX.DEAD TREE TO BE REMOVED ~
EX. SANITARY SEWER --S----:S-- UrcB: Urban Land - Califon Complex. o - B% slopes. HSG "B" (assumed) UrlB: Urban Land - Gladstone Complex. O - B% slopes, HSG "B" (assumed) EX.GAS LINE EX.CONTOUR
--1G----1G-- --------45Q-----
/ --- \
s 49r31 '90" w 356. ~o·
~ t ! (E>i.) t t t
IPF I
~
~00@~.@ll'iimD~~~~l§OO'ii'@
SCALE: 1 "=30 '
PROP.LOT LINE PROP.DRIVEWAY
PROP.DRIVEWAY EASEMENT PROP.PULL-OFF AREA PERMEABLE PAVERS
PROP.SANITARY LATERAL EASEMENT
PROP.TRIMMED VEGETATION
PROP.BUILDING
PROP.CONTOUR PROP.SANITARY LATERAL PROP.TREE
~ I : I : I : I : I : I : I ~
~ I I
--S----!S-- e PROP. DRAINAGE PIPE --sr sr-- INFIL TRATION TEST LOCATION TP1, TP2() PROP.CRUSHED STONE
INFILTRATION BED
PROP.STORMWATER DISTRIBUTION PIPE PROP.DRAINAGE AREA BOUNDARY
PROP.TAM -··-··-··
PROPERTY OWNER:
STEPHEN & DENISE LEGENSTEIN DEED RECORDED: DB.5051, PG.2296
TMP # 53-4-23
GRAPHIC SCALE
0 50 100
1 "=50'
150
THIS PLAN IS THE PROPERTY OF GUY ENGINEERING ASSOCIATES, INC. ALL RIGHTS RESERVED. NO ALTERATIONS. REPRODUCTIONS OR USE OF ANY PARTS OF ITS CONTENTS MAY BE MADE WITHOUT THE EXPRESSED WRITTEN PERMISSION BY THE AUTHOR.
z 0 .... I- Q. .... a: tJ en w c
w I- "" c
>- Cll
> w a:
a a: o._ " QJ ..... "" I ..... tD LL > .µ H u D QJ tD ....... =i o rn '- 0..
z C!l H rn w D
C!l z w
o._ a a: a_
tD ..... ' <O (\J ' ..... a
c:!J rn
.....
:::E rn u o._
o._ a a: a_
tD ..... ' a (\J ' (\J a
c:!J rn
(\J
a l!l
II -.....
QJ ......
ro u UJ
tD .....
I <O (\J
I CT)
3: lLJ H > w a:
C!l z lLJ
tD ..... ' a (\J ' 't a
C!l rn
CT)
tD tD ..... ..... I I <O (\J .... (\J I I l!l '° 3: 3: lLJ w H H > > lLJ w a: a:
C!l c:!J z z lLJ w
tD tD ..... ..... ' ' ..... l!l a (\J ' ' <O <O a a
c:!J c:!J rn rn
,.,. l!l
i -
a .I Ul ~
ai rn QJ 'tJ..-0 c ro ru ·r-1 0-<C tD 1
c.. a <
Cl> CI:Q.<D c 0 IJ.Jc:.I
OJ OJ l!l - .c. C.... I.Cl ._.. m re (1') c 0 ::J ·r-1 t!) C" - +' enc ...... tD .... :::J 0 c:tD Ul l!l :;i:- c CT) 0 .... ,.T, 0 3: ii-ii C.J OJ g. z
~
C!l rn
1:l QJ .>I. u QJ .i::: u
C!l rn
i::: 3: ro '- 0
" ..... a (\J ' ..... a ' tD
QJ .... ro D
LL 0
R
151.94' 110.31'
EX. UTIL. POLE BT090FPA
[MJ~[Q)@~rn1@@~ 11&~1:§
& MH
33' WIDE EP ------ ------
~
! {
- - --- - -
CONSTRUCTION SEQUENCE: 1. INSTALL ORANGE CONSTRUCTION FENCE AND COMPOST TUBES WHERE INDICATED ON THE PLAN. INCLUDING AROUND AREAS OF FUTURE STORMWATER BMP'S. 2. DELINEATE AND MARK THE LIMIT OF DISTURBANCE IN THE FIELD. 3. INSTALL CRUSHED STONE CONSTRUCTION ENTRANCE. 4. STRIP TOSOIL AND STOCKPILE WHERE INDICATED ON THE PLAN. SURROUND STOCKPILE WITH COMPOST TUBES. 5. CONSTRUCT HOUSE AND DRIVEWAY BASE COURSE. INSTALL ROOF DRAIN PIPES TOWARD FUTURE STORMWATER BMP. 6. INSTALL SANITARY MANHOLE AT THE END OF THE EXISTING SANITARY SEWER AT CORNER OF UPI 53-4-7 AND UPI 53-4-B.1. ANY AND ALL DISTURBANCE IN ADJACENT PROPERTIES SHALL BE RESTRICTED TO WITHIN THE SANITARY SEWER EASEMENT OF EAST GOSHEN TOWNSHIP. CONNECT LOT # 2'S LATERAL TO THE NEW MANHOLE. 7. INSTALL SANITARY SEWER FORCE LINE AND CONNECT TO MANHOLE. N 49"31'00" E 226.60" I ----- N 49"31'00" E 110.31' -/~ ____ 1_10_.3_2_· _
N 49"31'00" E 110.32' 8. DIG AND INSTALL WATER WELL.
N 49"31'00" E 250.00'
I
I
ClJ
I ~
I (T) lD
H 0.. :::>
I
I (T)
(T) (\j
I
""'" I (T) ID
H Q. :::>
PROP.40LF 4" DIP SLEEVE AROUND
I
I (\j
(T) (\j
I
""'" I (T) ID
I
I
I.
I
~ ~ ,.,
31:
'
~ H "' o_ I :t- :::> Ill
EX.DRIVEWAf zTO BE WIDENED TO 12' TEMP.ORANGE CONSTRUCTION! FENCE
JS.so·-,"
FLAG POLE WIDTH "" '-'-
25. oo ·
-........ "
(T) (\j
I
""'" I (T) ID
H 3: Q. :::>
' '
d-+.~=ir-PRDP. B ' x 22 ' PULL -OFF
~ AREA WITH APPROACHES ..,.g §!/ (PERMEABLE PAVERS)
~-' g i~~ --~@
I-~~ )> -~~
I!!!!] 2S UPI 53-4-25. 1
' ' I
9. FINE GRADE SITE. 10. PLANT BUFFER TREES AND SHRUBS. PLANT OTHER TREES AND SHRUBS PER PLAN. 11. REMOVE EXISTING JOINT DRIVEWAY WHERE SHOWN ON THE PLAN, GRADE AND INSTALL NEW DRIVEWAY. 12. INSTALL PERMEABLE PAVERS PULL-OFF AREA ALONG DRIVEWAY. 13. SPREAD TOPSOIL IN AREAS TO BE VEGETATED. PLANT. SEED AND MULCH WHERE NECESSARY. 14. REMOVE CRUSHED STONE ENTRANCE FROM PROPOSED DRIVEWAY AREA. 15. INSTALL NEW DRIVEWAY. REPAIR EXISTING DRIVEWAY. REPAVE WHERE NECESSARY. 16. EXCAVATE AND INSTALL STORMWATER BMP IN LOT#2. FINE GRADE AND SEED TO STABILIZE DISTURBED AREA. 17. AFTER THE CONTRIBUTING UPSLOPE AREA HAS STABILIZED, EXCAVATE AND INSTALL STORMWATER MANAGEMENT BMP IB LOT#1. CONNECT ROOF DRAIN PIPES TO PERFORATED PIPES IN BMP. 18. INSTALL TOPSOIL IN AREAS TO BE VEGETATED. PLANT. SEED AND MULCH WHERE NECESSARY. 19. AFTER THE ENTIRE DISTURBED ARE HAS BEEN STABILIZED, REMOVE ALL TEMPORARY E&S MEASURES. ANY AREA THAT IS DISTURBED DURING SUCH OPERATIONS SHALL BE REPAIRED AND STABILIZED IMMEDIATELY.
EROSION & SEDIMENTATION CONTROL NOTES:
1.Erosion and sedimentation controls must be constructed, stabilized and functional before site disturbance within the tributary areas of these controls. 2.After the final site stabilization has been achieved. temporary erosion and sedimentation controls must be removed. Areas disturbed during removal of the controls must be stabilized immediately. 3.Sediment traps must be protected from unauthorized acts of third parties. 4.Filter compost tubes must be installed at level grade. Both ends of each tube section must extend at least ten feet upslope at 45 degrees to the main tube alignment. 5.Sediment must be removed when accumulations reach half the above ground height of the tube. 1.25" SAN.FORCE MAIN I E~ ~ ' ®@@
6.Any tube section which has been undermined or topped must be immediately replaced or strengthened with additional tubes.
I
• 0 ·°' N :t" Ill z
25.0 .
C!l
C!l
lLJ O· C\Jo ·a (\J . -to •a <O (\J CT) rn I
I
l -
I" UPI 53-4-8 • \~
~ EX.20 FT WIDE SANITARY SEWER EASEMENT
I
PROP.SAN.MH AT END OF EX.SEWER RIM 454.00 S.ol9 '31 'OO"IL':x. co
2.00' - N49"31'00"E 401.94' (EX.)
BAKER PROPERTY
UPI 53-4-7
S.ol9'31'00"W 399.9.ol'
PR ,,...,._
12"1'1N PROP.BOUNDARY LINEt:::I ::;..,_;;::-:_:----_ _;;,_~
PROP.REAR YARD LINE
EX. PLANTING
PRDP.2.00 FT WIDE 200.00 FT LONG STRIP OF LAND TO BE CONVEYED TO UPI 53-4-23 , .........
" __J"', \\
\ \ \ PROP. P
JEMP.ORANGE ~ONSTRUCTION FENCE
TEMP.B" DIA. COMPOST TUBE
s.o19 ·31 · oo·w
..... -i..92 • 3§.: -.... -.......__ -.......
-.... -.... 110~1"'--
I
TEMP.B" COMPOST TUBE TEMP.ORANGE CONSTRUCTION FENCE
PROP. 1. 25" PE SAN.FORCE LINE
WU'li lil.IML
TOP OF
IRON PIN ELEV.43B.05
s 49t31'90" it w 356.Q,O'
'{/:T'.ff'.;;.J;J--,-__ - - ---
'
1 . \I
~
EX.HEMLOCK HILL LANE
UPI 53-4-24
EX.PAVEMENT TO BE REMOVED
PVC CLEANOUT W/LID
EX.DRIVEWAY TO BE ... WIDENED TO 12' DIA.COMPOST TUBE ,,,__-PROP. INSPECTION PORT I
T---t-~h_-PROP. STORMWATER MANAGEMENT BMP I I I
I I I I I
I
( ~~.~-~:~~~A~(§-!---
/ --- IPI' I
7.Stockpile heights must not exceed 35 feet. Stockpile slopes must be 2: 1 or flatter. B.Any disturbed area. on which activity has ceased. and which will remain exposed must be stabilized immediately. During non-germinating periods, mulch must be applied at the recommended rates. Disturbed areas which are not at finished grade and which will be redisturbed within on year. may be stabilized in accordance with temporary seeding specifications. Disturbed areas which are either at finished grade or will not be disturbed in one year, must be stabilized in accordance with permanent seeding specifications. 9.Diversions, channels. sedimentation basins, sedimentation traps and stockpiles must be stabilized immediately. 10.Hay or straw mulch must be applied at rates of at least 3.0 tons per acre. 11.Until the site is stabilized. all erosion and sedimentation controls must be maintained properly. Maintenance must include inspections of all erosion and sedimentation controls after each runoff event and on a weekly basis. All preventative and remedial maintenance work, including clean out. repair. replacement, regrading, reseeding, remulching, and renetting, must be performed immediately. 12. The stormwater managment BMP in Lot#2 shall be protected from disturbance and pollution during the construction of Lot#1. When. in the future. Lot#2 is developed. E&S control measures shall be installed upslope of this BMP to protect is from erosion and sedimentation due to construction activities. 13. The contractor shall ensure no compaction of the bottom of the infiltration BMP's by excavating from outside of the BMP and by running light machinery only with the area of the BMP.
S49"31'00"W 401.94' (EX.) UPI 53-4-210 UPI 53-i4-~11 I
I E ,HE ~ • ! ' i OCK! & PINE il<EE ROW t t i (E.f) t ~ ' ' ' ' PADP.WELL T I ' PROP.IP PROP.SUBDIVISION LINE
~
I
=pfiQP. 6~' l!LEANOOT TEMP.ORANG CONSTRUCT N FENCE
LIMIT OF DISTURBANCE AREA: WITHIN LOT # 1 = 0.6054 AC WITHIN LOT# 2 = 0.1371 AC TOTAL= 0.7425 AC
COMPOST TUBE NOTE:
I
I
\
COMPOST TUBES TO BE PLACED DOWNSLOPE OF CONSTRUCTION ACTIVITIES ON SITE SHALL BE B" DIA., EXCEPT ALONG THE EAST PROPERTY LINE OF LOT 1. WHERE THE COMPOST TUBE SHALL BE 12"' DIA.
EXISTING SOILS ON SITE:
Gd~ Gladstone Gravely Loam, 3 - B% slopes, HSG "B" GdC: Gladstone Gravely Loam, B - 15% slopes, HSG "B" UrcB: Urban Land - Cali fan Complex, o - 8% slopes, HSG ·s· (assumed) UrlB: Urban Land - Gladstone Complex, o - B% slopes, HSG "B" (assumed)
SURVEY DATUM: NAVO 19BB THIS PLAN HAS BEEN PREPARED BASED ON THE FOLLOWING INFORMATION SOURCES: BOUNDARY & TOPOGRAPHIC SURVEY PLAN, PREPARED BY R.H. SMITH SURVEYORS, WEST CHESTER, PA, DA TED 7/29/2017; EAST GOSHEN TOWNSHIP ZONING MAP; A PLAN ENTITLED "PLAN OF SUBDIVISION FOR ANTHONY D'AMBROSIO" PREPARED BY HENRY S.CONREY INC .. DATED 8/140/1977: A PLAN ENTITLED "FINAL TITLE PLAN" PREPARED BY D.L.HOWELL & ASSOSCIATES. INC., DATED 10/30/2001, LAST REVISED 3/11/2002; A PLAN ENTITLED "FINAL SUBDIVISION PLAN FOR BRUCE & AUDREY A.ATKINS" PREPARED BY JOHN D. STAPLETON Ill, DATED 11/3/1992: CHESTER COUNTY CHESCO VIEWS WEBSITE FOR DEEDS AND OWNERSHIP INFORMATION: CHESTER COUNTY RECORDER OF DEEDS: GUY ENGINEERING ASSOCIATES, INC. HAS NOT PERFORMED ANY FIELD SURVEY OF THE PROPERTY AND IS NOT RESPONSIBLE FOR ANY ERRORS, INACCRURACIES OR OMMISSIONS OF INFORMATION SHOWN ON THIS PLAN.
LOO NOTE:
N.o19"31'00"E 208.75' UPI 53-4-217
FOR LIMIT OF DISTURBANCE DELINEATION SEE SHEET 8.
PENNSYLVANIA LAW REQUIRES 3 WORKING DAYS NOTICE FOR CONSTRUCTION PHASE AND 10 WORKING DAYS IN DESIGN PHASE - STOP CALL Pennsylvania One Call System. Inc
1-800-242-1776 SERIAL No.20170472360 DATE: 02/16/2017
\
\
\
\
UPI 53-4-218
/ / TEMP.ORANGE CONSTRUCTION FENCE
~l§~[Q)
EX.PROPERTY LINE
ADJACENT.PROPERTY LINE
EX.ROAD R.O.W. EX.TITLE LINE EX.PAVEMENT
N90_:0Q.: 00" W --~61.B7""' ---
N90"00'00"W --~ 61.87"'' ---
EX.BUILDING c::::::::J
EX.TREE 0
EX.DEAD TREE TO BE REMOVED ~
EX.SANITARY SEWER EX.GAS LINE EX.CONTOUR SOILS BOUNDARY
--s----:s-- --G G-- ----""""4011-------
PROP.LOT LINE PROP.DRIVEWAY PROP.PULL-OFF AREA PERMEABLE PAVERS
PROP.BUILDING
PROP.TRIMMED VEGETATION
PROP.CONTOUR PROP.SANITARY LATERAL PROP.TREE
--S----:S--
-~sr----·sr-- PROP.DRAINAGE PIPE
TEMP.CONSTRUCTION ENTRANCE
TEMP.TREE PROTECTION FENCE
TEMP.CONSTRUCTION ORANGE FENCE TEMP.COMPOST TUBE
~
0
TEMP.LIMIT OF DISTURBANCE --- ~
PROPERTY OWNER:
STEPHEN & DENISE LEGENSTEIN DEED RECORDED: DB.5051, PG.2296
TMP # 53-4-23
GRAPHIC SCALE
0 50 100
1 "=50'
150
THIS PLAN IS THE PROPERTY OF GUY ENGINEERING ASSOCIATES, INC. ALL RIGHTS RESERVED. NO ALTERATIONS. REPRODUCTIONS OR USE OF ANY PARTS OF ITS CONTENTS MAY BE MADE WITHOUT THE EXPRESSED WRITTEN PERMISSION BY THE AUTHOR.
z 0 .... I- 0.. .... a: tJ en UJ c
UJ I- "' c
>- Cll
> UJ a:
a a: a_ " QJ ..... .-< I ..... tD LL > .µ H u D QJ tD ·~ =i o rn '- a_
z C!l H rn lLJ D
C!l z lLJ
a_ a a: a_
tD ..... ...... <O (\J ...... ..... a
c:!J rn
.....
:::E rn u a_
a_ a a: 0..
tD ..... ...... a (\J ......
(\J a
c:!J rn
(\J
a l!l
II -.....
QJ ......
"' u UJ
tD .....
I <O (\J
I CT)
3: lLJ H > UJ a:
C!l z lLJ
tD ..... ...... a (\J ...... 't a
C!l rn
CT)
tD tD ..... ..... I I <O (\J ..... (\J I I l!l '° 3: 3: lLJ lLJ H H > > lLJ lLJ a: a:
C!l c:!J z z lLJ lLJ
tD tD ..... ..... ...... ...... ..... l!l a (\J ...... ......
<O <O a a
c:!J c:!J rn rn
,.,. l!l
i -
a .I Ul ~
ai rn QJ "tJ..-< c m ru ·r-1 0-<C tD 1
c.. a <
Cl> CI:O..<D c 0 IJ.Jc:.I
OJ OJ l!l - .c. C.... I.Cl ._.. m re (1') c 0 ::J ·r-1 t!) C" - +' enc ...... tD ..... :::J 0 C:lO Ul l!l :;i:- c CT) 0 .... ,.T, 0 3: ii-ii C.J OJ g. z
~
C!l rn
"C
QJ .>I. u QJ .i:: u
C!l rn
i:: 3: m '- 0
" ..... a (\J ...... ..... a ...... tD
QJ ....
"' D
[)=
LL 0
Engineering detail sheet (Sheet 8 of 8) titled "Preliminary / Final Construction Notes and Details Plan Lot #1" for Proposed Residential Subdivision at 1506 Meadowbrook Lane, West Chester, PA 19380.
TYPICAL TREE PROTECTION DETAIL DURING CONSTRUCTION (N.T.S.)
- SHAPE OF TREE IS NOT TYPICAL FOR ALL VARIETIES
- 3-2"x4" HARDWOOD STAKES ABOVE GROUND TO LOWEST BRANCHES.
- DOUBLE STRAND #12 GAUGE GALV. WIRE TWISTED IN RUBBER HOSE 6" FROM TOP OF STAKE UP TO LOWEST BRANCHES.
- 1"x1"x57" HIGH #12 GAUGE WIRE STAPLED TO OUTSIDE OF STAKES OR WOOD SLAT SNOW FENCE.
- WRAP TRUNK AND LARGE BRANCHES WITH WATERPROOF TREE WRAP SECURED WITH TWINE.
- BOTTOM OF FENCE - 3"
TEMPORARY SEEDING & PERMANENT SEEDING
TEMPORARY SEEDING:
- LIME: 100 lbs/1000 sf Ground limestone incorporated 4 inches into soil.
- FERTILIZER: 25 lbs/1000 sf 10-20-20 incorporated 4 inches into soil.
- SEED: 1.0 lbs/1000 sf Annual Ryegrass
- MULCH: 140 lbs/1000 sf Straw Mulch
Minimum Standard for Limestone and Fertilizer:
- Limestone shall be applied at a rate of 1 ton per acre.
- Fertilizer shall be applied at a rate of: Nitrite nitrogen 30 lbs/acre average, Phosphorous 100 lbs/acre average, Potassium 120 lbs/acre average
PERMANENT SEEDING:
- LIME: 190 lbs/1000 sf Ground limestone incorporated 4 inches into soil.
- FERTILIZER: 25 lbs/1000 sf 10-20-20 incorporated 4 inches into soil.
- SEEDING: Lawn and mowed areas - Kentucky Bluegrass - 30 lbs/ac, Redtop - 3 lbs/ac, Perennial Ryegrass - 20 lbs/ac, Total Seeding = 53 lbs/ac; OR Pennlawn Fine Fescue - 40 lbs/ac, Redtop - 3 lbs/ac, Perennial Ryegrass - 20 lbs/ac, Total Seeding = 63 lbs/ac
- Slopes or unmowed areas - Crown Vetch - 25 lbs/ac, Perennial Ryegrass - 25 lbs/ac, Total Seeding = 50 lbs/ac
Planting date: March 1st to May 15th, and August 15th to October 1st.
Mulch: Straw at a rate of 140 lbs/1000 sf. Mulch shall be secured by approved methods.
PERMEABLE PAVERS AND STORMWATER BED DETAIL (N.T.S.)
- TYP. NO. 8 AGGREGATE IN OPENINGS
- PERMEABLE PAVERS
- BEDDING COURSE 2" THICK NO. 8 AGGREGATE
- 4" THICK NO. 57 STONE OPEN-GRADED BASE
- MIN. 6" THICK NO. 2 STONE SUBBASE
- NONWOVEN GEOTEXTILE ON BOTTOM, TOP AND SIDES OF OPEN-GRADED BASE (MIRAFI 140N OR EQUAL)
- UNCOMPACTED SOIL SUBGRADE
- NOTE: PERMEABLE PAVERS EP HENRY ECOCOBBLE OR EQUAL, 3-1/8" THICK
STANDARD CONSTRUCTION DETAIL #3-1: ROCK CONSTRUCTION ENTRANCE (NOT TO SCALE)
- PROFILE & PLAN VIEW: 50' MIN., 8" MIN., MOUNTABLE BERM (6 IN. MIN.)*, EXISTING ROADWAY, GEOTEXTILE, MIN 8" AASHTO #1, EARTH FILL, PIPE AS NECESSARY, EXISTING GROUND, 10' MIN., 20' MIN.
- * MOUNTABLE BERM USED TO PROVIDE PROPER COVER FOR PIPE
- NOTES: REMOVE TOPSOIL PRIOR TO INSTALLATION OF ROCK CONSTRUCTION ENTRANCE. EXTEND ROCK OVER FULL WIDTH OF ENTRANCE.
- RUNOFF SHALL BE DIVERTED FROM ROADWAY TO A SUITABLE SEDIMENT REMOVAL BMP PRIOR TO ENTERING ROCK CONSTRUCTION ENTRANCE.
- MOUNTABLE BERM SHALL BE INSTALLED WHEREVER OPTIONAL CULVERT PIPE IS USED AND PROPER PIPE COVER AS SPECIFIED BY MANUFACTURER IS NOT OTHERWISE PROVIDED. PIPE SHALL BE SIZED APPROPRIATELY FOR SIZE OF DITCH BEING CROSSED.
- MAINTENANCE: ROCK CONSTRUCTION ENTRANCE THICKNESS SHALL BE CONSTANTLY MAINTAINED TO THE SPECIFIED DIMENSIONS BY ADDING ROCK. A STOCKPILE SHALL BE MAINTAINED ON SITE FOR THIS PURPOSE. ALL SEDIMENT DEPOSITED ON PAVED ROADWAYS SHALL BE REMOVED AND RETURNED TO THE CONSTRUCTION SITE IMMEDIATELY. IF EXCESSIVE AMOUNTS OF SEDIMENT ARE BEING DEPOSITED ON ROADWAY, EXTEND LENGTH OF ROCK CONSTRUCTION ENTRANCE BY 50 FOOT INCREMENTS UNTIL CONDITION IS ALLEVIATED OR INSTALL WASH RACK. WASHING THE ROADWAY OR SWEEPING THE DEPOSITS INTO ROADWAY DITCHES, SEWERS, CULVERTS, OR OTHER DRAINAGE COURSES IS NOT ACCEPTABLE.
STANDARD CONSTRUCTION DETAIL #4-1: COMPOST FILTER SOCK (NOT TO SCALE)
- SECTION & PLAN VIEW: COMPOST FILTER SOCK, BLOWN/PLACED FILTER MEDIA, 2 IN. X 2 IN. WOODEN STAKES PLACED 10 FT ON CENTER, DISTURBED AREA, UNDISTURBED AREA, 2 IN. MIN., FLOW, EXISTING CONTOURS.
- NOTES: SOCK FABRIC SHALL MEET STANDARDS OF TABLE 4.1 OF THE PA DEP EROSION CONTROL MANUAL. COMPOST SHALL MEET THE STANDARDS OF TABLE 4.2 OF THE PA DEP EROSION CONTROL MANUAL.
- COMPOST FILTER SOCK SHALL BE PLACED AT EXISTING LEVEL GRADE. BOTH ENDS OF THE BARRIER SHALL BE EXTENDED AT LEAST 8 FEET UP SLOPE AT 45 DEGREES TO THE MAIN BARRIER ALIGNMENT. MAXIMUM SLOPE LENGTH ABOVE ANY BARRIER SHALL NOT EXCEED THAT SPECIFIED FOR THE SIZE OF THE SOCK AND THE SLOPE OF ITS TRIBUTARY AREA.
- TRAFFIC SHALL NOT BE PERMITTED TO CROSS COMPOST FILTER SOCKS.
- ACCUMULATED SEDIMENT SHALL BE REMOVED WHEN IT REACHES 1/2 THE ABOVE GROUND HEIGHT OF THE BARRIER AND DISPOSED IN THE MANNER DESCRIBED ELSEWHERE IN THE PLAN.
- COMPOST FILTER SOCKS SHALL BE INSPECTED WEEKLY AND AFTER EACH RUNOFF EVENT. DAMAGED SOCKS SHALL BE REPAIRED ACCORDING TO MANUFACTURER'S SPECIFICATIONS OR REPLACED WITHIN 24 HOURS OF INSPECTION.
- BIODEGRADABLE COMPOST FILTER SOCKS SHALL BE REPLACED AFTER 6 MONTHS; PHOTODEGRADABLE SOCKS AFTER 1 YEAR. POLYPROPYLENE SOCKS SHALL BE REPLACED ACCORDING TO MANUFACTURER'S RECOMMENDATIONS.
- UPON STABILIZATION OF THE AREA TRIBUTARY TO THE SOCK, STAKES SHALL BE REMOVED. THE SOCK MAY BE LEFT IN PLACE AND VEGETATED OR REMOVED. IN THE LATTER CASE, THE MESH SHALL BE CUT OPEN AND THE MULCH SPREAD AS A SOIL SUPPLEMENT.
DECIDUOUS TREE PLANTING DETAIL & CONIFEROUS TREE PLANTING DETAIL
- PRUNE DAMAGED TWIGS AFTER PLANTING
- PLACE PLANT IN VERTICAL POSITION
- 2"x2"x8' CEDAR STAKING
- RUBBER HOSE LOOP AND #12 WIRE
- TREE WRAPPING PAPER: WRAP TO BOTTOM OF BRANCHES, LAP PAPER MIN. 1/3 WIDTH, WRAPPING TO REMAIN MIN. ONE YEAR
- 2" MULCH
- BURLAP TO REMAIN LOOSEN FROM TOP OF BALL
- PREPARED BACKFILL: 1 PART PEAT TO 3 PARTS TOPSOIL
- TAMP AND SOAK BACKFILL THOROUGHLY AFTER PLANTING
- COMPACTED OR UNDISTURBED SOIL
E/ONE SEWER SYSTEMS DETAIL SHEET: MODEL DH152 / DR152 (NA0052P02)
- OPTIONS: [X] DH152 (HARDWIRED LEVEL CONTROLS), [ ] DR152 (WIRELESS LEVEL CONTROLS)
- FIELD JOINT REQUIRED FOR MODELS, ACCESS WAY VENT, GASKETED LID, HDPE, STRAIN RELIEF CORD CONNECTOR, DUAL WALL CORRUGATED HDPE ACCESSWAY, POWER/ALARM CABLE 6 CONDUCTOR W/GND, INTERNAL WELL VENT 2.0" DIA., E/ONE EQUALIZER, ELECTRICAL QUICK DISCONNECT NEMA 6P (EQD), DISCHARGE 1 1/4" FPT (304 S.S.), INLET, GROMMET TO ACCEPT 4.50" O.D. PVC PIPE (STANDARD) DUST COVER SUPPLIED FOR SHIPMENT (NOT SUITABLE FOR BURIAL), QUICK DISCONNECT ASSY. (304 S.S.), S.S. CAST BALL VALVE, EL. 439.94, 1 1/4" DISCHARGE LINE (304 S.S.), 42.0in 1067mm DISCH EL. 439.00, CHECK VALVE (NORYL), ALARM, ANTI-SIPHON VALVE (NORYL), 31.5in 800mm, 28.5in 724mm ON, OFF, 106gal 401 L, 20.5in 521mm, 19.6in 498mm, 74 gal 280 L, 58 gal 220 L, HDPE TANK 1/2" NOMINAL WALL THICKNESS 150 GALLON CAPACITY.
- SEMI POSITIVE DISPLACEMENT TYPE PUMP EACH DIRECTLY DRIVEN BY A 1 HP MOTOR.
- CONCRETE BALLAST MAY BE REQUIRED SEE INSTALLATION INSTRUCTIONS FOR DETAILS.
- NOTE: DIMENSIONS ARE FOR REF ONLY.
- UL, NSF, SP: AD, CH, 10/20/10, D
TYPICAL DRIVEWAY SECTION (NOT TO SCALE) / DRIVEWAY WIDENING DETAIL
- NOTE: PRIVATE DRIVEWAY WIDTH - 10 FT
- 12'
- 1 1/2" ID-2 BITUMINOUS WEARING COURSE
- 6" 3A STONE, COMPACTED
- COMPACTED SUBGRADE
ROOF DRAIN DETAIL
- BUILDING DOWNSPOUT
- ADAPTER TO RECEIVE DOWNSPOUT
- "Y" CONNECTION FOR OVERFLOW
- NON-WOVEN GEOTEXTILE
- VARIES, 7'-0" MIN., 12", 6", #2 STONE, 4" PVC ROOF DRAIN, SELECTED BACKFILL MATERIAL
PROPERTY OWNER & TITLE BLOCK
- PROPERTY OWNER: STEPHEN & DENISE LEGENSTEIN, DEED RECORDED: OB.5051, PG.2296, TMP # 53-4-23
- GRAPHIC SCALE: 1"=50' (0, 50, 100, 150)
- Project: PROPOSED RESIDENTIAL SUBDIVISION, 1506 MEADOWBROOK LANE, WEST CHESTER, PA 19380, EAST GOSHEN TOWNSHIP, COUNTY OF CHESTER, PA
- Applicant: STEPHEN & DENISE LEGENSTEIN, 1506 MEADOWBROOK LANE, WEST CHESTER, PA 19380
- Revisions: 1 SG 01/26/18 PROP ENG DESIGN; 2 SG 02/20/18 PROP PCSM; 3 SG 04/20/18 ENG REVIEW 3-26-18; 4 SG 06/01/18 ENG REVIEW 5-16-18; 5 SG 06/25/18 ENG REVIEW 6-22-18
- Seal: COMMONWEALTH OF PENNSYLVANIA PROFESSIONAL ENGINEER S.A. GAY PE-031797-E
- Gay Engineering Associates Inc., Consulting Engineers, 3508 Goshen Road, Newtown Square, Pa. 19073, (610) 356-0892
- Plan Title: PRELIMINARY / FINAL CONSTRUCTION NOTES AND DETAILS PLAN LOT # 1
- Project File: SUBDIV 8-17 PRO | Scale: 1"=50' | Checked: S.G. | Drawn: S.G. | Date: 8/01/2017 | SHEET 8 OF 8
STORMWATER MANAGEMENT BMP OPERATION ANO MAINTENANCE PROCEDURES:
A. EARLY MAINTENANCE ACTIVITY
Water vegetation at the end of each day for 2 weeks after planting is completed
FREQUENCY
Daily for 2 weeks after installation Every 4 days during periods Water vegetation regularly to ensure successful establishment of 4 or more days without rain. June through August for the first year after installation Inspect vegetation for signs of disease or distress
Biweekly for the first year after installation Inspect BMP and inlet systems for trash and sediment accumulation
Monthly for the first year after installation to determine ongoing maintenace frequency B. ONGOING MAINTENANCE ACTIVITY
Remulch void areas Treat diseased plants Keep incoming pipes and rain garden free and clear of leaves Inspect soil and repair eroded areas Remove leaves. litter and debris
Inspect plants to evaluate health. replace if necessary Inspect cleanouts and water elevation in inspection port Add additional mulch Evaluate the draindown time of the BMP after a storm of at least 1 inch in no more than 24 hours to ensure a draindown time of less than 72 hours Maintain records of all inspections and maintenance activity
RIM ELEV.454.00
MANHOLE FRAME &: COVER
FINISHED GRADE
FREQUENCY
As needed As needed As needed
Monthly Monthly Quarterly
Quarterly
Quarterly Ongoing
Ongoing
A MINIMUM OF 2, MAXIMUM OF 4 COURSES OF PRECAST CONCRETE GRADE RINGS SHALL BE USED
8"
5"
•
NOTES:
'
·.
CHANNEL
' N
' N
NOTES: 1. MANHOLE SECTIONS SHALL BE TONGUE &: GROOVE WITH APPROVED RUBBER RING GASKET. 2. AFTER MANHOLE IS SET THE ENTIRE OUTER SURF ACE SHALL BE COATED WITH Bl TU MASTIC, EXCEPT STORM SEWERS. 3. IF PRE-CAST BASE IS USED PROVIDE A MINIMUM OF 4" /12B STONE BASE TO LEVEL. 4. BASE REINFORCEMENT: TOP H=12'-30', /15 @ 12" OR .18S.l./FT. WWF H=30'-60', /16 @ 12" OR .22S.l./FT. WWF BOTIOM H=12'-60', /14 @ 12" OR .28S.l./FT. WWF
PROP.EXIST.LATERAL CONNECTION FROM LOT # 2
A-LOK GASKET AND CAULKING COMPOUND
3/8" FILLET B/C RUBBER
/
PROP.NEW LATERAL CONNECTION FROM II--+--,, LOT # 1
8" DIA.(MIN.)
~- REINFORCEMENT (SEE NOTE /15)
TYP. MANHOLE DETAIL
N.T.S.
1. THE MANHOLE SHALL BE INSTALLED AT THE END OF THE EXISTING SANITARY SEWER AND WILL REPLACE THE EXISTING CLEANOUT. 2. THE INVERT ELEVATION OF THE MANHOLE OUTLET SHALL MATCH THE EXISTING INVERT ELEVATION OF THE EXISTING SEWER.
' ' ' ' \
\
\
\
\
I •
3. THE SANITARY SEWER LATERAL OF THE EXISTING HOUSE IN LOT # 2 SHALL BE DIRECTED TD ENTER THE MANHOLE ABOVE THE OUTLET INVERT ELEVATION. 4. THE 1.25" DISHCARGE PIPE DRDM THE GRINDER PUMP IN LDT # 1 WILL BE CONNECTED TD THE MANHOLE 8" ABOVE THE OUTLET INVERT ELEVATION. 5. ALL CONNECTIONS INTO THE MANHOLE SHALL BE SEALED WITH AN A-LOK GASKET.
\
I I
6. THE MANHOLE STEPS SHALL BE 12" DC AND SHALL BE COATED-POLYPROPYLENE PLASTIC. 7. THE MANHOLE FRAME AND COVER SHALL BE HEAVY DUTY TRAFFIC TYPE CAST IRON LABELED "EAST GOSHEN MUNICIPAL AUTHORITY SANITARY SEWER". B. THE MANHOLE LID SHALL BE WATERTIGHT WITH CLOSED PICKHOLES AND BOLTED
TD THE FRAME. 9. INCOMING PIPES INTO THE MANHOLE SHALL BE PLACED AT THE BOTTOM ELEVATION OF THE MANHOLE AND CHANNELS SHALL BE FORMED IN THE CONCRETE FLOOR OF THE MANHOLE BETWEEN THE INFLUENT AND EFFLUENT PIPES.
I [T)
[T) C\J
I "1"
I [T) LO
H Q_ :::i
PROP.40LF 4" DIP SLEEVE AROUND 1.25" SAN.FORCE MAIN
I
[T) C\J
I "1"
I [T) LO
I
I.
I~
0 j!" H ~ ~ I iii
EX. DRIVEWAf
2 TO WIDENED TD 12'
I
BE
[T) C\J
I "1"
I [T) LO
H Q_ :::i
~~!Ml.
TOP OF
:;;:: o- C\J.-o . (\) (\) . ..,.rn . ,..._ <D"' "' z ... ' ... "- E.f!';;:--.. ' ' 0- "' ' ' IRON PIN ELEV.43B.05 ,,
PROP. 1. 25" PE SAN.FORCE LINE I I
,[ TP
<
-
EP
-; ,:?'Jc.';:?; .. ~~ I,
?& 51'()<~ Ol'IO'J1U..
1a· w~ . J- 1n1: ;in-...., (!in~/Jl.i'.IKl.tJ\
SNllTAAV !itl'ltl! Wl.ltl
£11. <O Q..£>.);OIJf --
• ""-,,_ ~lt CRMlU: F f!l:OIJlllED
Sf!!ER MA,!N .. ~w~noo ()fTA!I ~~EU~~soc.
NQJJ;: "1~~\'ER NS:.WU ll'C st: \'l'I: ~ LAIDIAL «IHKCllOO 51iWl.1l !IC M.'Ui TO Ttlf EXlSTtl:l M"1N !;SI~ ~ !llY[ nl11NC ANO C..~ ~E COOF"llNC.
•$-,,'
t.IH . ~lhll.IJP!: (f Pff' FOOT)"
' . . ;::-,'-.J{-/ -........ . ....___ !Mr £l!l01I'
'
'i'YfR 1 AJfRN !f!ID!QING XJ1fR !)ffi,I!
"'" """"
~· lolN. m= " ""' . :; di·\' 1., .• ·,,
EAST GOSHEN TOWNSHIP SEWER LATERAL/BUILDING SEWER DETAIL
~flli P.\J1 1'-'ll!Y; OETi\Jl NO.: PEN NONI ASSOCIATES INC. C~EATID: ,,_, C' REVIStD:
w PROP.INSPECTION PORT
\
\
nrrr----t--i:r:~ 1111 w PROP.STORMWATER MANAGEMENT BMP
\
\
IPF I
~ • ~ ' ! EX,HEM OCI<) & PINE illEE ROW
LIMIT OF DISTURBANCE DELINATION
TEMP.LIMIT OF DISTURBANCE
8" PERF.PVC INSPECTION PORT W/LID LID.EL.440.50 BOTTOM EL.437.00
AASHTO # 3 clean washed crushed stone
NOTES:
SCALE: 1 "=50 '
EARTH BERM COVEREED WITH TAM TOP.ELEV.440.00
6" PERFORATED PVC PIPE ~ 0.00 INV.437.90
'
1. The crushed stone bed shall be wrapped on top and sides with non-woven drainage faerie, such as Mirafi 140N, or approved equal. 2. Excavation for the infiltration BMP shall be performed with equipment that will not compact the bottom of the facility. 3. the bottom of the BMP shall be scarified prior to placement of fabric and aggregate.
i
I
I I I
4. Only clean aggregate with documented porosity, free of fines, shall be allowed. 5. The contractor shall contact the Township to have the construction of the infiltration BMP inspected. Inspection of the BMP must start prior to placement of stone. 6. Amended soil above the crushed stone shall consist of: 50% sand, 25% compost and 25% topsail without clay.
CRUSHED STONE INFILTRATION BED SECTION
LOT # 1
1 "=30' (H) 1"'= 3' (V)
=pROP.6" PVC CLEANOUT W/LID
NOTES Upon completion of the development of Lot * 2 the rain garden in Lot # 2 shall be planted as specified for Lot * 1. O&M procedures shall be as specified for Lot # 1.
EARTH BERM TOP.ELEV.450.00
AASHTO # 3 clean washed crushed stone
NOTES:
AMENDED SOIL ABOVE STONE
1. The crushed stone bed shall be wrapped on top and sides with nan-woven drainage faerie, such as Mirafi 140N, or approved equal. 2. Excavation for the infiltration BMP shall be performed with equipment that will not compact the bottom of the facility. 3. the bottom of the BMP shall be scarified prior to placement of fabric and aggregate. 4. Only clean aggregate with documented porosity, free of fines, shall be allowed. 5. The contractor shall contact the Township to have the construction of the infiltration BMP inspected. Inspection of the BMP must start prior to placement of stone. 6. Amended soil above the crushed stone shall consist of: 50% sand, 25% compost and 25% topsail without clay.
CRUSHED STONE INFILTRATION BED SECTION
LOT # 2
1 "=30' (H) 1"= 3" (V)
"'"
EIONE SPD PUMP PERFORMANCE CURVE
100
95
90
85
~-- . 80
w 15 V1 VJ w "' 0. "' z >--< °' w 0. 0 _, <( !d 0. >- >--
75
70
65
60
55
50
m :<:. 45 ..-.: ,:s 40
Sil ~ 35
u "' 30 <( z b 25
::;! b 20 f-
15
10
5
0
-5
-10
-15
-20
-25
.
.
.
.
GRINDER PUMP 1HP, 1725 RPM '
' \
~
\
\
-,
-
-
-
-
-
230
220
210
200
190 11 LOW PRESSURE DESIGN PRESSURE I SYSTEM I - 180
0
PAI
I I ' CONSl.L T F ACTOAY - \
FOR INTERl.llTTENT USE A.BOVE 80 PSI
OR 185 FEET TC»-1 - \ - \ -
- - \
-
~
-
"" - \ !:.-
- ' - \ -
PRf , ' ·n11.1 rn '" \ - ' ELE .45 .00 (EST MATI Dl\
'""
- "
- " 3CHA GE I "'.
- P.DI LEV. 39. 4--....
2
....... ~
I ' I
4 6 8 10 12 14 16 DISCHARGE ( Q). GPM
PROPERTY OWNER:
STEPHEN & DENISE LEGENSTEIN DEED RECORDED: DB. 5051. PG. 2296
TMP # 53-4-23
GRAPHIC SCALE
0 50 100
- -
-
-
-
-
- -
18
170
160
150
140
130
120
110 °' w 100 ';;: "' 90 u. 0 80 t3 w 70 u.
60 0 < w 50 :I: u "' 40 < z 30 b _, < 20 :0
10
0
-10
-20
-30
-40
-50
-60
f-
1 "=50'
150
THIS PLAN IS THE PROPERTY OF GUY ENGINEERING ASSOCIATES. INC. ALL RIGHTS RESERVED. NO ALTERATIONS. REPRODUCTIONS OR USE OF ANY PARTS OF ITS CONTENTS MAY BE MADE WITHOUT THE EXPRESSED WRITTEN PERMISSION BY THE AUTHOR.
z 0 ... I- 0.. ... a: tJ Ul w c
w I--c c
> ID
> w a:
0 a: 0.. " ....
I (IJ > .µ H U D Q) (D
·~ :::i o en '- 0..
z (!) H en w D
(!) z w
0.. a a: 0..
(D .... ' <D (\) ' .... 0
(!) en
....
::E en u 0..
0.. 0 a: 0..
(D .... ' 0 (\) ' (\J 0
(!) en
(\J
0 LD
II
Q) ....
Ill u en
(D ....
I <D (\) I "' :;;:: w H > w a:
(!) z w
(D .... ' 0 (\) ' .... 0
(!) en
(r)
(D .... I <D .... I LD
:;;:: w H > w a:
(!) z w
(D .... ' ....
0 ' [D 0
(!) en
..,.
(!) en
u
Q) °" u Q) .r;;; u
[}=
(D ....
I (\) (\) I <D
:;;:: w H > w a:
(!) z w
(D .... ' LD (\) ' [D 0
(!) en
LD
(!) en
c ~ IO '- 0
" .... 0 (\) ' ....
0 ' (D
Q) .µ
IO D
LL 0
EAST GOSHEN
CONSERVANCY
April 13, 2018
East Goshen Township Planning Commission 1580 Paoli Pike West Chester, Pa. 19380
Re: 1506 Meadowbrook Ln. I SD&LD Recommendation Landscaping
Mr. Chairman, I move that the Conservancy Board recommend that the Planning Commission support the requested waiver from §205-36 {landscape Plan) and approve the Preliminary/ Final Subdivision Plan for 1506 Meadowbrook lane dated 8/1/2017, last revised 2/20/2018 with the following conditions:
1. The evergreen buffer planting shall be extended the entire length of the property along the rear property line to create a "Complete evergreen landscape buffer" as required by the ZHB decision. 2. The evergreen buffer plantings shall be a minimum of 8' at time of planting. 3. A mix of at least three deer resistant species shall be used. 4. Tree Protection fencing shall be installed at the drip line to protect all trees that are proposed to be saved including the row of mature Hemlock trees along the easterly property fine. 5. The applicant shall submit a detailed foundation planting plan when building permits are applied for. 6. All notes and plans shall be revised to address these conditions prior to approval of the plan. 7. The applicant shall address all outstanding engineering comments to the satisfaction of the Planning Commission, Staff and the Township Engineer.
Sin:u___
Mark A. Gordon Zoning Officer
F:\Data\Shared Data\Property Management\53-4\53-4-23 (1506 Meadowbrook Ln.)\2018 SD & LD\CB Recto PC
5 °i1if018fi 0°A O L I P I K E , W E S T C H E S T E R, P A . 1 9 3 8 0
Memorandum
East Goshen Township 1580 Paoli Pike West Chester, PA 19380 Voice: 610-692-7171 Fax: 610-692-8950 E-mail: mgordon@eastgoshen.org
Date: 7/19/2018 To: Planning Commission • Of' From: Mark Gordon, Township Zoning Officer 't-1 lP Re: Conditional Use Application I Home Occupation I 1339 E. Strasburg Rd.
Dear Commissioners,
East Goshen Township has received a Conditional Use application for the property located at 1339 E. Strasburg Rd., West Chester PA 19380. The property owner, Peter Lloyd, is seeking approval to operate a scuba supply business in his home as a Home Occupation. The property contains a single family home and is situated in the R-2 Zoning District. Home Occupations are permitted in the R-2 Zoning District as a conditional use. I have reviewed the Home Occupation Permit and have determined that this use is a HolT)e Occupation use and requires Conditional Use approval.
Staff Recommendation:
Staff is of the opinion that this use meets all the standards for a Home Occupation, all the Conditional Use standards, and is appropriate for the property. A recommendation for approval is appropriate at this time.
Draft Motion: Mr. Chairman, I move that the Planning Commission recommend approval of the conditional use application of Peter Lloyd for a home occupation use at his property, 1339 E. Strasburg Rd., as outlined in the application and pursuant to Sections 240-31 and 240-32J of the Zoning Ordinance; with the following conditions:
1. The area devoted to the home occupation shall not exceed 430.25 square feet in area as depicted on the floor plan provided with the application. 2. You shall comply with the standards set forth in §240-32J. 3. The sign for the Business will hang below the mailbox and will be in general conformance with the sign rendering submitted with the application.
F:\Data\Shared Data\Property Management\53-68\53-68-64 (1339 E. Strasburg Rd.)\Conditional Use (Home Occupation)\Memo to
PC re. CU Home Occupation.doc
Conditional Use Application and Checklist
East. Goshen Township
JUL i a ;n·,·a - v -U. To: Township Zoning Officer ( .. c-. -·~ ~i
Name of Applicant: Peter H. Lloyd iJ2::~~~~~?
Applicant Address: 1339 East Strasburg Road West Chester Pa 19380
Telephone Number:_4_84_-6_45_-_6_17_2 ______ Fax: __________ _
Email Address: pete9295@yahoo.com I pete9295@gmail.com
Property Address: 1339 East strasburg Road west chester Pa 19380
Tax Parcel Number: 53-06B-0064.oooo Zoning District: _R_-2 ___ Acreage: _.5_7 __
Description of proposed use:
Portion of the basement with separate entrance will be used mainly as a online scuba store with minimal
lo.cal customers for sizing and fittings. Will also have a small repair room for assembling gear for the customers.
i:tie hours open to customers will be a few hours a day during the week and about 6 hours on saturday, during the summer season and about half that during the winter season. This business is only meant to be a part time business at most. ·
Conditional Use is provided in Zoning Ordinance Section: _24_o_-3_1_c _____ _
We hereby acknowledge that we have read this application and state that the
above is correct and agree to comply with all provisions of the East Goshen Township Zoning Ordinance ag · le to this project and property. ~ 71s-1?··
Signature of Applicant Date
Attest:---------'-----------------
* Review the formal Planning Commission review pro~edure on page three.
F:\Data\Shared Data\Website\Forms\Conditional Use App and Checklist rev 102406.doc - 1 -
S11:an.da.rds for condition.all uses and special exception. uses
§ 240-31 ZONING § 240-31
C.Standards for conditional uses and special exception uses and certain permitted-by-right uses.
Use of the business will consist of mainly selling merchandise online with minimal local customers for sizing and fittings and assembling gear. Goods sold will consist of scuba diving equipment and apparels (i.e. sporting goods)
(I) Overall. In considering a conditional use or special exception use application, the Board of Supervisors or Zoning Hearing Board, as applicable, shall consider all of the following standards as well as any other standards that may be listed for the proposed use [see Subsection B(ll) concerning additional conditions that may be imposed by the Board of Supervisors]. (See also Article IX, concerning additional conditions that may be placed by the Zoning Hearing Board). (2) Standards for conditional uses and special exception uses. All conditional uses and all special
exception uses shall complywith the following standards:
(a) Not create a significant hazard to the public health and safety, including but not limited
to fire, toxic or explosive hazards. This business will not create and or store any hazards to the public and will not produce any safety issues to the public. (b) Be suitable for the property in question.
There is ample room for the inventory for the online store and assembling gear which does not require any modification or additions to the structure of the
property. There is plenty of parking with room to turn around for the minimal local customers. ( c) Be designed, constructed, operated and maintained so as to be in harmony with the
character of the existing or intended development of the general vicinity. The business will be maintained and operated in harmony with the existing or intended character of the general vicinity and that such use will not change the essential character of the general vicinity. ( d) Not be detrimental to other property in the vicinity, including proper use of adequate
setbacks, buffering, bending, locating of nuisance-causing facilities, screening and controls of operations to avoid conflicts. Where, in the opinion of the Board of Supervisors, the distance of setbacks and/or the methods of screening and buffering otherwise established by this chapter would be insufficient, additional screening, buffering and/or widths of setbacks shall be required as a condition of any approval. Existing landscaping screening on both side of the property is in place obscuring the parking area and entrance not to detrimental the other properties in the vicinity. (e) Be· suitable in terms of permitting the logical, efficient and economic
extension of public services and facilities such as central water supply, sanitary sewage and police and fire protection. The applicant shall prove that there is adequate access for fire-fighting and other emergency service equipment. The Board of Supervisors may establish additional conditions on approval to ensure such access, such as sufficient turning radii and cartway width for such equipment, the provision of adequate access for fire fighters to reach all sides of buildings and the provision of paved or compacted surfaces sufficient to support the weight of fire equipment. NA (f) After considering any traffic improvements that the applicant may legally commit to
fund or construct shall not create significant traffic safety hazards or cause serious traffic congestion_ NA
[1] The applicant for a conditional use shall establish the effect of the proposed
development on the reserve capacity of the public streets and street intersections providing access to and in the area of the subject property. NA [2] Where a traffic study is required under this chapter or another Township ordinance,
such study shall be submitted at the same time as the conditional use application. NA [3] If a traffic study is required, the applicant shall prove that he level of service of
unsignalized and signalized intersections adjacent to the applicant's property will be adequate to serve the proposed development. To prove such adequacy, the applicant shall prove that intersections intended to provide motor vehicle egress and/or ingress to the proposed development shall not fall below the Level of Service D as specified in the 1994 Highway Capacity Manual published by the Transportation Research Board, or its successor publication. NA
[a] The Board of Supervisors may waive the criteria in Subsection C(2)(f)[3] above if they find such waiver to be m the public interest, safety and general welfare. NA [b] The above Subsection C(2)(f)[3] shall not be construed to preclude
improvement of such intersections to attain a Level of Service D or better. NA
[4] The applicant shall prove that any improvements proposed to adjacent segments
of streets will be sufficient to obviate adverse traffic impacts caused by the
development, and to protect the traveling public. NA [5] The applicant shall prove that facilities for ingress and egress will be so located and so designed to provide safe access to adjoining streets and to avoid unnecessary traffic through existing residential neighborhoods. NA (g) Minimize adverse impacts upon the preservation and restoration of any historic
building(s) on the subject property NA (h) Properly locate and design the proposed structures and other improvements to
minimize disruption to existing natural topography, waterways, ponds, groundwater recharge, woods and other important natural resources on the site. NA
1339 E. StrasburgRd. COUNTY OF CHESTER
S Y LVANIA
Owner! : LLOYD PETER Owncr2: Mail Address 1: 1339 E STRASBURG RD Mall Address2 : WESTCHESTER PA Mail Address 3:
Deed Pngc: 1554 Deed Recorded Date: ll/9/2015 Legal D csc 1: NS OF E STRASBURG RD LcgalDcse 2: LOT96 & DWG Acres : 0.57 LUC:R-60 Lot Assessment:$ 54,960 Property Assessment:$ 137,380 Total Assessment$ 192,340 Assessment Date: 12/15/2017 Property Address: 1339 E STRASBURG RD Municipality: EAST GOSHEN Sch col District: West Chester Area
Map Created: Thursday, July 19, 2018
County of Chester
Limitations of Liability and Use: County of Chester, Pennsylvania mnkcs no clo.irru to the completeness, accuracy, or content ofnny doto contnincd hen: in, nnd makes no n:prcscntation of ony kind, including, bu l not limited to, the wammtics of mcrcho.nto.bility or fitness for a particular use, nor nrc any suchwan-o.ntics to be implied orinfcm:d with respect to the information or data furnished herein. For information on d:ita sources visit the GlS Services page listed at www.chcsco.org/gis.
Aerial photograph of the property at 1339 East Strasburg Road showing annotated locations for the parking area, entrance, and mailbox.
- PARKING AREA
- ENTRANCE
- 1339 East Strasburg Road
- NAME ON MAILBOX
- E Strasburg Rd
12'
iss sq ft!
close
!Back Yard
Front of house
51/2
4' 0 CJ
140 sq: ft I Bat hroom
3'
7 1/2 51/'l. 111/2
11/'l.
14 1/2 3'
12.01.75 sq h i
191/2'
Walkway
1
'9'
1103.5 sq ftl
Repair Room
·closet
5'
2' x S'
P.arklng
AREA
DRIVEWAY
'7'
Two interior photographs of a room with wood-look tile flooring, doors, a sink counter, and cabinets, accompanied by a floor plan diagram at the bottom.
Floor plan labels
- Front of house
- 3' x 3' shower
- 40 sq ft Bathroom
- 103.5 sq ft Repair Room
- closet
- closet
- 201.75 sq ft
- 85 sq ft (highlighted area)
- closet
- [partly illegible] not used
Two interior photographs of the 201.75 sq ft room showing a long table covered with a black cloth, wood-look tile flooring, closets, and doorways, accompanied by a floor plan diagram at the bottom highlighting the 201.75 sq ft room and closets in yellow.
- Front of house
- 3' x 3' shower
- 40 sq ft Bathroom
- 103.5 sq ft Repair Room
- closet
- closet
- 201.75 sq ft
- 35 sq ft
- closet
- [illegible] not used [illegible]
4: tr E "' ,.; D t ::l
D "' ~
·~ ... ill
D
0
Two interior photographs of the 103.5 sq ft Repair Room showing a workbench with pressure gauges and storage drawers, shelving, and scuba/diving equipment, accompanied by a floor plan diagram at the bottom highlighting the 103.5 sq ft Repair Room and closet in yellow.
- Front of house
- 3' x 3' shower
- 40 sq ft Bathroom
- 103.5 sq ft Repair Room
- closet
- closet
- 201.75 sq ft
- 85 sq ft
- closet
- [illegible] not used [illegible]
Ul u Cl.. <( UJ 0:: <( l9 z :::;;;: 0:: <( Cl..
1
. 1
I ;
VJ ~ 0.. <( UJ er: <( lD z :;2 er: <( 0.. "
l/) u 0... <( LU 0::: <( {!) z Q 0::: <( 0...
(l) V) ::i 0 ..c 4- 0 ~ u Cll ..c
.....
Cll
Cll (l) ~
tJ.O c 32 ..... Cll CL
(l) ..c .....
> ..c
(l) u c Cll ..... ..... c UJ
> CIJ 3: OJ > ·;::: 0 4- 0 D.. ~
c 0 :;:::;
CIJ u 0 _J
x 0 ...a
I • . ''7~ : \
'./· 1 . i 1::\.:, ~ ~ ::
Plan for Business Sign
Name of business on mailbox no lager then if putting a name of the occupant and or address of home
(See pies below) A new mailbox will be installed to replace the mailbox below when the sign fixed to it.
(On both sides of Mailbox) OR (Hanging below Mailbox)
I " ·-..
Plan for Business Sign
A new mailbox will be installed to replace the mailbox below when the sign fixed to it.
(Hanging below Mailbox) SIZE 6" x 11"
0 0
0
Memo
To: Planning Commission From: Jon Altshul Re: Consider Incubator Uses & Goal 3E of the Comprehensive Plan Date: July 10, 2018
Goal 3E of the 2015 Comprehensive Plan Update calls for the Township to "promote new uses, such as ... Incubator Businesses, in appropriate locations." This goal was developed with an eye towards enhancing and modernizing the Township's commercial and industrial districts. There are a number of incubator spaces scattered throughout Chester County, including the Innovation Center at Eagleview, the Innovation Center at Evolve IP (Tredyffrin) and the West Chester Artisan Exchange (West Goshen).
An "incubator'', while broadly familiar to anyone who's watched HBO's Silicon Valley, is a term of art that requires some clarification.
1 As used in this memo, "incubator" refers to any multi-tenancy commercial or industrial space for "incubator businesses", which are small (typically fewer than about 15 employees) start-up businesses (usually, but not always, less than 3 or 4 years old) that generally (but not always) are not-yet profitable or have only recently achieved profitability. While stereotypical incubator business are in the software development and life sciences fields, as used herein, the term could also include skilled trades (plumbers, electricians) or artisan crafters (carpenters, jewelry makers, farmer's market vendor kitchens, etc) or really any non-retail start-up business. Incubators generally provide fully or partially shared workspace and/or common areas, and often (but again, not always) assistance with back-office support, marketing and/or financing.
Currently, the ZO explicitly allows a modified form of incubator uses in the 1-1 and BP Districts, and implicitly allows them in the 1-2, as outlined in the Appendix, although the minimum size restrictions in the Conditional Use section of the ZO may make incubators impractical in East Goshen, as is explained
below.
There may be a few additional uses that could be permitted by right or conditional use to foster incubator businesses, including "Kitchens for the preparation of food and non-alcoholic beverages for consumption off site". Otherwise, my reading of these sections is that the existing language more or less provides for any kind of incubator use that could be reasonably envisioned.
In addition, the Township may wish to amend the Conditional Use Section of the ZO. Specifically, Section 240-31C(3)(v) reads:
Multiple uses in a multiple-use building in the 1-1 District pursuant to§ 240-19C(1) and in the BP District pursuant to§ 240-21C(1). The following shall apply if an existing building is to be converted or if a new building is built for multiple uses:
1 A non-scientific review of selected PA municipal zoning ordinances revealed only one reference to "lncubators 11 • Specifically, State College Township, which hosts PSU's Innovation Center complex defines an "lncubator
11 as "a building that offers office, light industry and manufacturing and/or laboratory space, common facilities and shared support services at below-market rates to tenants.
11
[1] Each use shall have a minimum of 5,000 square feet of contiguous floor space. Separate users which are the same type of principal use may make up the minimum 5,000 square feet of floor space. [2] A development plan shall be submitted and conform to Chapter 205, Subdivision and Land Development, as well as§§ 240-24 and 240-27.
Clearly, 5,000 square feet of space is significantly larger than what a typical incubator business needs.
In addition, in order to reduce barriers to entry for start-up businesses, the Township may want to consider exempting each incubator or incubator business from having to apply for a conditional use permit every time there is a new tenant. That is, an incubator landlord would be required to receive conditional use approval in order to begin leasing space-and the CU decision may have a condition that only software development, or light manufacturing, or kitchen space, etc is permitted in the incubator- but that any new or subsequent businesses that rents space in an approved incubator would only need a U&O to begin operations, provided that the business broadly complies with an approved condition in the CU permit.
Questions for Planning Commission:
1) Should 240-6 (definitions) and 240-19 through 240-21 (1-1, 1-2 & BP) be amended to specifically define and allow for "lncubatorsn as a conditional use, separate from "multiple usen?
• If yes to #1, should 240-19 through 240-21 specify that any use permitted by right or by conditional use in the relevant sections of the ZO is permitted by right if the use is in an incubator (i.e. only a U&O is needed as new incubator businesses are added)?
• If yes to #1, how should "incubator'
1 be defined, as distinct from "multiple usen?
• If no to #1, should 240-31C(3)(v) be amended to either eliminate the square footage requirement for multiple uses or reduce it (note that the parking requirements would not be changed, so there is a check against overcrowded workspaces)?
2) Are there any uses not currently in the ZO for the 1-1, 1-2 and/or BP districts that are appropriate to foster successful incubators in East Goshen?
Appendix: Permitted Uses in Industrial and Business Park Districts
1-1 (Goshen Corporate 1-2 (Applebrook) BP (Goshen Corporate
Park West/ Airport Road} Park) Multiple uses in a Yes No Yes multiple use building allowed? Applicable* uses • None • Research, testing or • Development of allowed by right experimental computer software laboratory or facility packages and related for research or marketing product • Assembly of development electronic • Manufacturing when equipment limited to pilot studies and prototype development for precision instruments, optical goods, pharmaceutical, health and personal care products • Business & professional offices Applicable* uses • Testing & repair of • Manufacturing when • Manufacturing when allowed by Conditional manufactured limited to pilot limited to pilot Use products studies and studies and • Manufacturing prototype prototype requiring light metal development for development for processing precision precision
• Packaging and bottling instruments, optical instruments, optical
• Manufacturing when goods, goods,
limited to pilot studies pharmaceutical, pharmaceutical,
and prototype health and personal health and personal
development for care products care products
precision instruments, • Manufacturing • Manufacturing
optical goods, facility of jewelry, facility of jewelry,
pharmaceutical, health precision precision
and personal care instruments, optical instruments, optical
products goods and similar goods and similar
• Scientific, industrial, products products
agricultural or • Business &
engineering professional offices
testing/product • Scientific, industrial, development agricultural or engineering
• Business & testing/product professional offices development
• Research, engineering • Testing or or testing laboratories experimental
• Manufacture/assembly laboratory for of electrical/ electronic research or product appliances, supplies & development equipment and products from nontoxic materials such as plastic, leather, glass, cellophane and textiles. * For simplicity's sake, I have omitted allowed uses that not applicable to incubators, such as parking garages, indoor recreation, banking, agriculture, places of worship, retail, restaurants, utilities, etc.
610-692-7171 www.eastgoshen.org BOARD OF SUPERVISORS
EAST GOSHEN TOWNSHIP
CHESTER COUNTY I 580 PAOLI PIKE, WEST CHESTER, PA 19380-6199
July 24, 2018
Dear Property Owner:
The purpose of this letter is to inform you that East Goshen Township has received a Conditional Use application for 1339 E. Strasburg Rd. West Chester PA 19380. The property owner, Peter Lloyd, is seeking approval to operate a scuba supply business as a Home Occupation. The property contains a single family home and is situated in the R-2 Zoning District of East Goshen Township. Home Occupations are permitted in single family homes within the R-2 Zoning District as a conditional use.
Pursuant to Township policy, property owners within 1000 feet of the subject property are notified when conditional use applications are received. The meeting dates for this matter are listed below and subject to change without further written notice:
August 1, 2018 - Planning Commission (7:00 PM) September 4, 2018 - Board of Supervisors (7:00 PM - Conditional Use Hearing)
These meetings will be held at the Township Administration Building and will be open to the public. The Application is available for review at the Township building during normal business hours. If any person who wishes to attend the hearing has a disability and/or requires an auxiliary aid, service or other accommodation to observe or participate in the proceedings, he or she should contact East Goshen Township at 610- 692-7171 to discuss how those needs may be accommodated.
Mark A. Gordon Township Zoning Officer
F:\Data\Shared Data\Property Management\53-68\53-68-64 (1339 E. Strasburg Rd.)\Conditional Use (Home Occupation)\1000 foot letter CU 07192018.doc