Conservancy Board

The Conservancy Board advises the Board of Supervisors, the Planning Commission, the Park and Recreation Commission and other agencies, officials and employees of East Goshen Township on matters dealing with conservation, management, protection and use of natural resources in the Township of East Goshen.

Meetings are on the 2nd Wednesday of the month at 7:00 P.M. In addition the Conservancy Board will conduct site inspections the following Saturday at 9:00 AM; as needed.

Board Members Term Expiration Dates
Vacant, Chair 2026
Walter Wujcik, Vice Chair 2027
Jackie Ahlborn 2027
Julieta Calmon 2027
Erich Meyer 2028
Sandy Snyder 2026
Susan Vanesse 2028
Ann Duffield, BOS Liaison
Ashley Nowak,  Staff Liaison

 

Articles of Interest

 

Related News

The Goshen250 Nature Challenge: We Have a Winner!

Wednesday, November 4, 2026

This neighborly challenge between West Goshen and East Goshen townships began as the brainchild of East Goshen Township’s (EGT) Conservancy Board. Jason Lang, EGT’s Parks and Recreation director, contacted his West Goshen peer Ken Lehr, who shared the idea with the Sustainability Advisory Committee, and the idea became a reality. Planning for the iNaturalist-inspired “BioBlitz” […]

View Article

East Goshen Township Receives Bird Town PA Recognition!

Wednesday, October 7, 2026

  The Conservancy Board and Environmental & Sustainability Advisory Council have worked together to have East Goshen Township recognized as a Bird Town PA. The program encourages municipalities to work towards four key strategies: Creating and Protecting Habitat, Threats to Birds, Education and Engagement and Sustainability.         Here are just some of […]

View Article

“Leave the Leaves”

Friday, October 2, 2026

Take a break from the rake and help your yard and the planet. Did you know that the leaves that fall from your trees can act as a natural mulch to improve the soil and retain moisture through the winter? Leaves provide nutrients to your yard as they decompose naturally. They also provide valuable habitat […]

View Article

More News

Documents

Notice: this accessible version was created automatically from the original document. The transcription may not be 100% accurate. It is provided for searching and for screen readers; please refer to the original document for the official version.

AGENDA EAST GOSHEN TOWNSHIP CONSERVANCY BOARD MEETING

1580 Paoli Pike, 2nd Floor August 9, 2023 - 7:00 PM

F:\Data\Shared Data\Agendas\Conservancy Board\2023\2023-8-09_CB Agenda.docx

1. CALL TO ORDER / PLEDGE OF ALLEGIANCE / MOMENT OF SILENCE

2. APPROVAL OF MINUTES

a. 7/12/2023 3. Presentation by CRC Watersheds Association

4. CHAIRMAN’S REPORT 5. Tree City USA

a. Any Maintenance Tasks 6. Educational Workshops

a. New ideas for the Fall

7. OLD BUSINESS:

a. KEGB Signs b. Winter grass plantings at Matlack

8. NEW BUSINESS:

9. SUBDIVISION / LAND DEVELOPMENT REVIEW

a. 1010 Hershey Mill Road/Millstone Meadows

10. VARIANCES/CONDITIONAL USES – None

11. LIAISON REPORTS

12. CORRESPONDENCE

13. DATES OF IMPORTANCE Date Meeting Time August 10 Pipeline Task Force 5:30pm August 14 Municipal Authority 7:00pm August 15 Board of Supervisors 7:00pm August 17 Futurist Committee 7:00pm August 22 Planning Commission 7:00pm August 26 Community Day 5:00pm August 28 ESAC 6:30pm September 4 Township Office Closed September 5 Board of Supervisors 7:00pm September 7 Park & Rec Commission 7:00pm September 11 Municipal Authority 7:00pm September 13 Conservancy Board 7:00pm September 14 Pipeline Task Force 5:30pm September 19 Board of Supervisors 7:00pm September 21 Futurist Committee 7:00pm September 25 ESAC 6:30pm

AGENDA EAST GOSHEN TOWNSHIP CONSERVANCY BOARD MEETING

1580 Paoli Pike, 2nd Floor August 9, 2023 - 7:00 PM

F:\Data\Shared Data\Agendas\Conservancy Board\2023\2023-8-09_CB Agenda.docx

14. BOARD MEMBER CONCERNS

15. PUBLIC COMMENT

16. ADJOURNMENT

CB 7-12-23 draft 1

DRAFT 1 EAST GOSHEN TOWNSHIP 2 CONSERVANCY BOARD MEETING 3 July 12, 2023 4 5 The East Goshen Township Conservancy Board held a regularly scheduled meeting on 6 Wednesday, July 12, 2023 at 7:00 p.m. at the Township Building. Members in attendance 7 are indicated in BOLD: 8 Sandra Snyder, Chairman 9 Dan Flynn, Vice Chairman 10 Erich Meyer 11 Scott Sanders 12 Walter Wujcik 13 Karen Martynick 14 Matthew McGeehan 15 16 Others present were: 17 Michele Truitt, Township Supervisor 18 Ashley Nowak, Office Administrator 19 Eunice Alexander, Goshen Tree Tenders 20 21 Call to Order 22 Sandy called the meeting to order at 7:00 p.m. 23 24 Pledge of Allegiance & Moment of Silence 25 Sandy led those present in the Pledge of Allegiance and then asked for a moment of silence 26 to remember our troops and first responders. 27 28 Minutes 29 The minutes of the June 14, 2023 meeting were approved as amended. 30 31 Chairman’s Report 32 None 33 34 35 Tree City USA 36 Ashley reported that nothing needs to be done. 37 38 39 Educational Workshops 40 Sandy feels that a date needs to be selected so notice can be sent out early. Ashley emailed 41 the available dates for the meeting room. There were about 14 in Sept, Oct and Nov. It was 42 decided to have a planning meeting on Wednesday August 9. Come with ideas for topics 43 and speakers. Karen commented that September would be good so people could still do 44 plantings for the spring. Sandy will send the Board members an email. 45 46 Old Business 47 1. Supplee Valley Planting – No discussion 48 49

CB 7-12-23 draft 2

2. Beaver Dams – All of the beavers have been relocated and the dams were breached. 1 Public Works has placed cameras in the area and are checking for beavers. 2 3 3. Street Tree Ordinance - Michele lead a discussion about the Street Tree Ordinance. We 4 need to define what street trees are, the township’s past and current practices and figure 5 out how to notify the residents. Mark Miller has been asked to take an inventory of all 6 current street trees. In the past, for safety reasons, if a fire truck or trash truck can’t get 7 down the street, PW would trim them. Also ,any trees in the PECO right of way are trimmed 8 by PECO. Trees in open space easements need to be defined. Now that we are a Tree City 9 we need to see if they have any reference to street trees. 10 11 New Business 12 1. Summer schedule - The Board will meet on August 9th to discuss the Education 13 Workshop. 14 2. Matlack Florist – Michele mentioned that the open space area with the retention basin is 15 Township property. She suggested planting grasses to help retain the water and make it 16 look better. 17 18 Subdivision/Land Development Review 19 1. 1010 Hershey Mill Road – Sandy will send a letter stating that the Board needs a 20 detailed landscape plan to review. The copies of the plan they received were not 21 adequate for landscape review. Stormwater Management was discussed. 22 23 Liaison Reports - None 24 25 26 Any Other Matter - None 27 28 29 Board Member Concerns - None 30 31 Public Comment- None 32 33 Adjournment 34 There being no further business, Walter moved to adjourn the meeting. Karen seconded the 35 motion. The meeting was adjourned at 8:40 p.m. The next meeting will be Wednesday, 36 August 9, 2023 at 7:00 pm. 37 38 Respectfully submitted, 39 40 41 42 Ruth Kiefer, Recording Secretary 43

1

Applebrook Park

Sample Site Packet

Please note that this packet was created to act as a sample, and no details are final.

Planting Site Maps 2 Sample Budget 5 Sample Planting and Maintenance Plan 6 Timeline 7

[Logo: CRC Watersheds Association (Chester • Ridley • Crum)]

2

Planting Site Maps

[GIS aerial map showing regional context and property parcel boundary in East Goshen Township and Willistown Township, along Route 352 and Paoli Pike.]

Scale: 1 inch = 0 miles (0, 0.125, 0.25, 0.5 Miles)

COUNTY OF CHESTER
PENNSYLVANIA

[Location inset map showing Chester County with Township location highlighted]

Find Information

FieldValue
PARID:5304 0089010E
UPI:53-4-89.1
Owner1:EAST GOSHEN TOWNSHIP
Owner2:
Mail Address 1:1580 PAOLI PK
Mail Address 2:WEST CHESTER PA
Mail Address 3:
ZIP Code:19380
Deed Book:4707
Deed Page:2138
Deed Recorded Date:02/02/2000
Legal Desc 1:ES OF PAOLI PK
Legal Desc 2:93.1 AC
Acres:93.14
LUC:E-71
Lot Assessment:353310
Property Assessment:0
Total Assessment:353310
Assessment Date:12/16/2022 7:49:49 AM
Property Address:1602 PAOLI PK
Municipality:EAST GOSHEN
School District:West Chester Area

Map Created: Tuesday, August 1, 2023

County of Chester [Seal: County of Chester, Pennsylvania]

Limitations of Liability and Use: County of Chester, Pennsylvania makes no claims to the completeness, accuracy, or content of any data contained herein, and makes no representation of any kind, including, but not limited to, the warranties of merchantability or fitness for a particular use, nor are any such warranties to be implied or inferred with respect to the information or data furnished herein. For information on data sources visit the GIS Services page listed at www.chesco.org/gis.

[Logo: CRC Watersheds Association (Chester • Ridley • Crum)]

3

[GIS aerial map showing parcel 53-4-89.1 and adjacent parcels in East Goshen Township with orange highlighted planting zone approximately 300 feet from body of water.]

[Callout: "Highlighted area shows CRC planting zone, approx. 300ft from body of water."]

Parcels shown: 53-4-69 (55 AC.), 53-4-89 (160.71 AC.), 53-4-89.1 (93.14 AC.), 53-4-89.2 (5.87 AC.), 53-4-67 (8.8 AC.), 53-4-717 (2.68 AC.), 53-4-89.5 (3.52 AC.), 53-4-87 (7 AC.), 53-4-85.2A (3.52 AC.), 53-4-89.7 (1.96 AC.), 53-4-131.1C (1.18 AC.), 53-4-131.1 (1.63 AC.), 53-4-131.1A (2 AC.).

Roads labeled: Paoli PK, Monte Vista DR, Linda Vista DR, Vista DR, Hibberd LA, Grist Mill LA, Boot RD, Township Park.

Scale: 1 inch = 400 feet (0, 200, 400, 800 Feet)

COUNTY OF CHESTER
PENNSYLVANIA

[Location inset map showing Chester County with Township location highlighted]

Find Information

FieldValue
PARID:5304 0089010E
UPI:53-4-89.1
Owner1:EAST GOSHEN TOWNSHIP
Owner2:
Mail Address 1:1580 PAOLI PK
Mail Address 2:WEST CHESTER PA
Mail Address 3:
ZIP Code:19380
Deed Book:4707
Deed Page:2138
Deed Recorded Date:02/02/2000
Legal Desc 1:ES OF PAOLI PK
Legal Desc 2:93.1 AC
Acres:93.14
LUC:E-71
Lot Assessment:353310
Property Assessment:0
Total Assessment:353310
Assessment Date:12/16/2022 7:49:49 AM
Property Address:1602 PAOLI PK
Municipality:EAST GOSHEN
School District:West Chester Area

Map Created: Tuesday, August 1, 2023

County of Chester [Seal: County of Chester, Pennsylvania]

Limitations of Liability and Use: County of Chester, Pennsylvania makes no claims to the completeness, accuracy, or content of any data contained herein, and makes no representation of any kind, including, but not limited to, the warranties of merchantability or fitness for a particular use, nor are any such warranties to be implied or inferred with respect to the information or data furnished herein. For information on data sources visit the GIS Services page listed at www.chesco.org/gis.

[Logo: CRC Watersheds Association (Chester • Ridley • Crum)]

4

[GIS aerial map showing northern portion of parcel 53-4-89.1 and adjacent properties along Line Road and Applebrook Drive, with orange highlighted planting zone approximately 300 feet from body of water.]

[Callout: "Highlighted area shows CRC planting zone, approx. 300ft from body of water."]

Parcels shown: 53-4-89.1 (93.14 AC.), 53-4-69 (55 AC.), 53-4-89 (160.71 AC.), 53-2-86 (1.1 AC.), 53-2-84 (1.3 AC.), 53-2-83 (1.1 AC.), 54-2-95.3 (27 AC.).

Roads labeled: Line RD, Applebrook DR, Hibberd LA, Township Park.

Scale: 1 inch = 400 feet (0, 200, 400, 800 Feet)

COUNTY OF CHESTER
PENNSYLVANIA

[Location inset map showing Chester County with Township location highlighted]

Find Information

FieldValue
PARID:5304 0089010E
UPI:53-4-89.1
Owner1:EAST GOSHEN TOWNSHIP
Owner2:
Mail Address 1:1580 PAOLI PK
Mail Address 2:WEST CHESTER PA
Mail Address 3:
ZIP Code:19380
Deed Book:4707
Deed Page:2138
Deed Recorded Date:02/02/2000
Legal Desc 1:ES OF PAOLI PK
Legal Desc 2:93.1 AC
Acres:93.14
LUC:E-71
Lot Assessment:353310
Property Assessment:0
Total Assessment:353310
Assessment Date:12/16/2022 7:49:49 AM
Property Address:1602 PAOLI PK
Municipality:EAST GOSHEN
School District:West Chester Area

Map Created: Tuesday, August 1, 2023

County of Chester [Seal: County of Chester, Pennsylvania]

Limitations of Liability and Use: County of Chester, Pennsylvania makes no claims to the completeness, accuracy, or content of any data contained herein, and makes no representation of any kind, including, but not limited to, the warranties of merchantability or fitness for a particular use, nor are any such warranties to be implied or inferred with respect to the information or data furnished herein. For information on data sources visit the GIS Services page listed at www.chesco.org/gis.

5 Sample Budget

* The above costs are being sponsored by a private funder. Future replacements, if necessary, are to be funded by the Landowner.

6 Sample Planting and Maintenance Plan

Applebrook Park, East Goshen Township September or October 2023 Riparian Buffer Planting

Coordinates: 40.00302389946552, -75.53720452299197 Site Address: 1602 Paoli Pike, West Chester, PA 19380 Site Ownership: East Goshen Township County: Chester County Watershed: Ridley Creek Watershed

Planting Plan

CRC will plant about 125 trees, ranging in container size, and protect with a 5’-6’ circumference wire cage, or a 4’ tall tree tube, with a wooden stake to hold in place. Depending on tree form, some trees may receive a plastic tree tube, 4’ ft in height, with a tree stake holding the tube in place. In addition, CRC uses a wood chip mulch for ground cover around our plantings to maintain nutrients and moisture of the newly planted trees.

The trees to be planted include:

- Common species CRC plants: Red Maple, Silver Maple, Serviceberry, River Birch, Redbud, White Fringe Tree, Flowering Dogwood, Sweetbay Magnolia, Sycamore, Swamp White Oak, Pin Oak,...

Maintenance Plan

Staff of the Landowner will periodically maintain the site, including removal of overgrowth or invasive species as needed. CRC staff and volunteers will review the site on an ongoing basis to determine whether planting needs are being appropriately managed or if CRC will need to hold a volunteer event to conquer any larger needs for removal or cutting. In addition, CRC will review the status of the plants, deer caging, and stakes to ensure they are still viable.

Throughout the ensuing years (3+), Landowner staff will be responsible for review and maintenance of the site and the planting, including invasive removal and herbicide application as necessary. CRC staff, Tree Advisory Committee members, and volunteers will visit the site regularly to identify any outstanding needs as well, which may lead to greater intervention.

7

Budget

See above. We will compare prices and quality from various nurseries, so as to pay the least amount in total.

Timeline

● May-June 2023 – identify site and needs ● July-August 2023– Create planting plan map, coordinate approval with Landowner, and prepare the site to give volunteers access to the area. Create a final planting plan with coordination of the Landowner, including Landowner signature. ● Early September 2023 - reserve and order plants and materials ● Middle September 2023 – Engage corporate/community volunteers for the tree planting. ● October 2023– utilize corporate and citizen volunteers to plant, stake, cage, mulch, and remove invasive plants ● Throughout 2023 and 2024– CRC Volunteers and staff periodically visit the area and manage as needed. ● 2024-2026 – CRC staff to review the site and adjust/make arrangements as needed

RIPARIAN BUFFER INSTALLATION AGREEMENT

Site Address: 1602 Paoli Pike, West Chester, PA 19380

Landowner: East Goshen Township

Project Grantee: Chester Ridley Crum Watersheds Association (CRC)

This agreement, dated ____________, between East Goshen Township (Landowner) and Chester Ridley Crum Watersheds Association (CRC) allows the CRC and/or its Partners to undertake community & watershed forestry planting activities on land owned by East Goshen Township (Landowner) in Chester County, Commonwealth of Pennsylvania.

In signing this agreement, East Goshen Township (Landowner) grants to the CRC, or its designees, the authority to complete the activities described in Appendix “A.” The site plan drawings included in Appendix “A” show existing site conditions and work to be completed.

East Goshen Township (Landowner) agrees to maintain the community & watershed forestry practice depicted in Appendix “A” under this agreement for at least twenty-five (25) years.

Appendix “B” identifies estimated planting costs and donations of supplies or equipment from the CRC and its Partners to East Goshen Township (Landowner) for carrying out these activities.

East Goshen Township (Landowner) grants the CRC and its Partners vehicular and equipment access to the site with 48 hours prior notice to conduct project-related activities such as site analysis and design, installing trees, shrubs, and other vegetative cover, inspecting completed work, maintenance, and monitoring for at least 25 years.

East Goshen Township (Landowner) do not have to be present unless otherwise requested by the project manager.

East Goshen Township (Landowner) retain all rights to control trespass and retain all responsibility for taxes, assessments, granting of right-of-way, control and eradication of noxious weeds, and other incidences of ownership.

East Goshen Township (Landowner) agrees that all design and project implementation will be managed by the CRC or its representatives.

East Goshen Township (Landowner)’s stewardship activities are described in Appendix “A.” In the event that a natural circumstance, beyond the control of East Goshen Township (Landowner), damages the constructed or installed components of the project, East Goshen Township (Landowner) will not be required to repair these damages.

East Goshen Township (Landowner) agrees to ensure that trees and shrubs planted in the project area are not cut, removed, mowed or otherwise disturbed, for at least 25 years, and the materials used to protect these plantings remain in place for their full recommended useful life.

East Goshen Township (Landowner) shall notify the CRC in writing, prior to the implementation of any action, if (1) East Goshen Township (Landowner) ever proposed to convert facilities constructed, rehabilitated, or improved under this Agreement, (2) if the facility ever becomes obsolete and East

Goshen Township (Landowner) decides to destroy or remove the plantings, or (3) East Goshen Township (Landowner) proposed to sell off lands developed, rehabilitated or improved with these funds.

East Goshen Township (Landowner) must obtain the CRC’s written consent in order to modify the original site plan. This agreement may be modified at any time by mutual consent of the parties.

Name & Position (Print) Landowner, East Goshen Township

Signature Date

Carly Lare Executive Director, Chester Ridley Crum Watersheds Association

Signature Date

Appendix A: Planting Map & Planting Plan

[GIS aerial overview map of East Goshen Township and Willistown Township showing property boundary along Route 352 and Paoli Pike.]

Scale: 1 inch = 0 miles (0, 0.125, 0.25, 0.5 Miles)

COUNTY OF CHESTER
PENNSYLVANIA

[Location inset map showing Chester County with Township location highlighted]

Find Information

FieldValue
PARID:5304 0089010E
UPI:53-4-89.1
Owner1:EAST GOSHEN TOWNSHIP
Owner2:
Mail Address 1:1580 PAOLI PK
Mail Address 2:WEST CHESTER PA
Mail Address 3:
ZIP Code:19380
Deed Book:4707
Deed Page:2138
Deed Recorded Date:02/02/2000
Legal Desc 1:ES OF PAOLI PK
Legal Desc 2:93.1 AC
Acres:93.14
LUC:E-71
Lot Assessment:353310
Property Assessment:0
Total Assessment:353310
Assessment Date:12/16/2022 7:49:49 AM
Property Address:1602 PAOLI PK
Municipality:EAST GOSHEN
School District:West Chester Area

Map Created: Tuesday, August 1, 2023

County of Chester [Seal: County of Chester, Pennsylvania]

Limitations of Liability and Use: County of Chester, Pennsylvania makes no claims to the completeness, accuracy, or content of any data contained herein, and makes no representation of any kind, including, but not limited to, the warranties of merchantability or fitness for a particular use, nor are any such warranties to be implied or inferred with respect to the information or data furnished herein. For information on data sources visit the GIS Services page listed at www.chesco.org/gis.

[Two stacked County of Chester GIS aerial maps, each with an inset county map and a Find Information panel.]

Upper map

[Aerial map of parcel 53-4-89.1 along Paoli Pike with an orange-highlighted planting zone and a callout: "Highlighted area shows CRC planting zone, approx. 300ft from body of water." Scale bar: 1 inch = 400 feet.]

Parcel labels include: 53-4-69 (55 AC.), 53-4-89 (160.71 AC.), 53-4-89.1 (93.14 AC.), 53-4-89.2 (5.87 AC.), 53-4-717 (2.68 AC.), 53-4-89.5 (3.52 AC.), 53-4-85.2A (3.52 AC.), 53-4-87 (7 AC.), 53-4-67 (8.8 AC.). Other labels: Paoli PK, Monte Vista DR, Township Park, East Goshen Township.

Find Information

FieldValue
PARID:5304 0089010E
UPI:53-4-89.1
Owner1:EAST GOSHEN TOWNSHIP
Owner2:
Mail Address 1:1580 PAOLI PK
Mail Address 2:WEST CHESTER PA
Mail Address 3:
ZIP Code:19380
Deed Book:4707
Deed Page:2138
Deed Recorded Date:02/02/2000
Legal Desc 1:ES OF PAOLI PK
Legal Desc 2:93.1 AC
Acres:93.14
LUC:E-71
Lot Assessment:353310
Property Assessment:0
Total Assessment:353310
Assessment Date:12/16/2022 7:49:49 AM
Property Address:1602 PAOLI PK
Municipality:EAST GOSHEN
School District:West Chester Area

Map Created: Tuesday, August 1, 2023
County of Chester

Limitations of Liability and Use: County of Chester, Pennsylvania makes no claims to the completeness, accuracy, or content of any data contained herein, and makes no representation of any kind, including, but not limited to, the warranties of merchantability or fitness for a particular use, nor are any such warranties to be implied or inferred herein, with respect to the information or data furnished herein. For information on data sources visit the GIS Services page listed at www.chesco.org/gis.

Lower map

[Aerial map of the northern part of parcel 53-4-89.1 near Township Park and Line Rd, with the same orange planting zone and callout: "Highlighted area shows CRC planting zone, approx. 300ft from body of water." Scale bar: 1 inch = 400 feet.]

Parcel labels include: 53-4-89.1 (93.14 AC.), 53-4-89 (160.71 AC.), 53-4-69 (55 AC.), 54-2-95.3 (27 AC.). Other labels: Township Park, Line RD, East Goshen Township.

Find Information

FieldValue
PARID:5304 0089010E
UPI:53-4-89.1
Owner1:EAST GOSHEN TOWNSHIP
Owner2:
Mail Address 1:1580 PAOLI PK
Mail Address 2:WEST CHESTER PA
Mail Address 3:
ZIP Code:19380
Deed Book:4707
Deed Page:2138
Deed Recorded Date:02/02/2000
Legal Desc 1:ES OF PAOLI PK
Legal Desc 2:93.1 AC
Acres:93.14
LUC:E-71
Lot Assessment:353310
Property Assessment:0
Total Assessment:353310
Assessment Date:12/16/2022 7:49:49 AM
Property Address:1602 PAOLI PK
Municipality:EAST GOSHEN
School District:West Chester Area

Map Created: Tuesday, August 1, 2023
County of Chester

Limitations of Liability and Use: County of Chester, Pennsylvania makes no claims to the completeness, accuracy, or content of any data contained herein, and makes no representation of any kind, including, but not limited to, the warranties of merchantability or fitness for a particular use, nor are any such warranties to be implied or inferred herein, with respect to the information or data furnished herein. For information on data sources visit the GIS Services page listed at www.chesco.org/gis.

Sample Planting and Maintenance Plan

Applebrook Park, East Goshen Township September or October 2023 Riparian Buffer Planting

Coordinates: 40.00302389946552, -75.53720452299197 Site Address: 1602 Paoli Pike, West Chester, PA 19380 Site Ownership: East Goshen Township County: Chester County Watershed: Ridley Creek Watershed

Planting Plan

CRC will plant about 125 trees, ranging in container size, and protect with a 5’-6’ circumference wire cage, or a 4’ tall tree tube, with a wooden stake to hold in place. Depending on tree form, some trees may receive a plastic tree tube, 4’ ft in height, with a tree stake holding the tube in place. In addition, CRC uses a wood chip mulch for ground cover around our plantings to maintain nutrients and moisture of the newly planted trees.

The trees to be planted include:

- Common species CRC plants: Red Maple, Silver Maple, Serviceberry, River Birch, Redbud, White Fringe Tree, Flowering Dogwood, Sweetbay Magnolia, Sycamore, Swamp White Oak, Pin Oak,...

Maintenance Plan

Staff of the Landowner will periodically maintain the site, including removal of overgrowth or invasive species as needed. CRC staff and volunteers will review the site on an ongoing basis to determine whether planting needs are being appropriately managed or if CRC will need to hold a volunteer event to conquer any larger needs for removal or cutting. In addition, CRC will review the status of the plants, deer caging, and stakes to ensure they are still viable.

Throughout the ensuing years (3+), Landowner staff will be responsible for review and maintenance of the site and the planting, including invasive removal and herbicide application as necessary. CRC staff, Tree Advisory Committee members, and volunteers will visit the site regularly to identify any outstanding needs as well, which may lead to greater intervention.

Budget

See above.We will compare prices and quality from various nurseries, so as to pay the least amount in total.

Timeline

● May-June 2023 – identify site and needs ● July-August 2023– Create planting plan map, coordinate approval with Landowner, and prepare the site to give volunteers access to the area. Create a final planting plan with coordination of the Landowner, including Landowner signature.

● Early September 2023 - reserve and order plants and materials ● Middle September 2023 – Engage corporate/community volunteers for the tree planting. ● October 2023– utilize corporate and citizen volunteers to plant, stake, cage, mulch, and remove invasive plants ● Throughout 2023 and 2024– CRC Volunteers and staff periodically visit the area and manage as needed. ● 2024-2026 – CRC staff to review the site and adjust/make arrangements as needed

Appendix B: Budget

Item Description Units Unit Cost Total
Cost of Materials
Native trees
5-7' native trees, carefully selected to match the needs of the particular riparian buffer site
125 $ 40.00 $ 5,000.00
Tree Protection & Mulch
Wire fence for tree cages, tree guards, stakes, ties, and mulch
$ 2,500.00
Transportation Cost
Truck usage/mileage, plant delivery $ 300.00
Staff Services
Project Manager, Tree Planting Coordinator, Director of Volunteerism; covers strategic planning of planting plan, acquiring of plant and protective material, site preparation, event coordination, and more $ 2,500.00
Overhead Expenses
Percentage to cover the overhead and surrounding costs of the tree planting and CRC's work $ 1,545.00
Totals $ 11,845.00

[Engineering plan cover sheet with general notes, survey notes, utility notes, traffic control notes, storm water notes, conditional use approval conditions, zoning data, open space tabulation, vicinity map, plan set index, and certification blocks.]

ONECALL NOTES

[Seal: Pennsylvania One Call System, Inc. 1-800-242-1776 Stop-Call Before You Dig!]

PENNSYLVANIA ACT 287, AS AMENDED BY ACT 121 REQUIRES NOTIFICATION OF EXCAVATORS, DESIGNERS, OR ANY PERSON PREPARING TO DISTURB THE EARTH'S SURFACE ANYWHERE IN THE COMMONWEALTH.

ACT 287 UNDERGROUND UTILITY PROTECTION ACT, AS AMENDED BY ACT 121

ACT 287 UNDERGROUND UTILITY PROTECTION ACT, AS AMENDED BY:
ACT 172 OF 1986, ACT 38 OF 1991, ACT 187 OF 1996,
ACT 199 OF 2004, ACT 181 OF 2006, ACT 121 OF 2008

PA ONE CALL SYSTEM INFORMATION:
PENNSYLVANIA ACT 287, AS AMENDED, REQUIRES THREE (3) WORKING DAYS NOTICE FOR CONSTRUCTION PHASE AND FIVE (5) WORKING DAYS NOTICE IN DESIGN STAGE.
PA ONE CALL PHONE NUMBER: 1-800-242-1776

ONE CALL SYSTEM SERIAL NO. NOTIFICATION BY NAVE NEWELL, INC.
DATE: 11/07/22
ONE CALL SYSTEM SERIAL NUMBER: 20223113412

UNDERGROUND UTILITY LOCATIONS ARE APPROXIMATE AND WERE DETERMINED FROM VISIBLE LOCATION, ACT 287 OF 1974, AS AMENDED, UTILITY RESPONSES AND/OR BEST AVAILABLE PLAN INFORMATION.

LIST OF RESPONDERS:

  • AQUA PENNSYLVANIA INC
  • COMCAST CABLE COMMUNICATIONS INC
  • EAST GOSHEN TOWNSHIP
  • PECO ENERGY
  • TEXAS EASTERN TRANSMISSION LP
  • VERIZON PENNSYLVANIA LLC

SURVEY NOTES:

  1. SITE FEATURES SHOWN HEREON OBTAINED BY A FIELD SURVEY PERFORMED BY NAVE NEWELL, INC. COMPLETED ON DECEMBER 12, 2022.
  2. THE SURVEY WAS PREPARED WITH THE BENEFIT OF A TITLE REPORT, AS REFERENCE HEREIN, AND IS SUBJECT TO THE INFORMATION CONTAINED THEREIN. NO DOCUMENTS OTHER THAN AS NOTED ON THE SURVEY WERE REVIEWED IN THE COURSE OF COMPLETING THE SURVEY.
  3. THE SURVEY REPRESENTS CONDITIONS AS OF THE DATE OF THE SURVEY EXCEPT SUCH IMPROVEMENTS OR EASEMENTS, IF ANY, THAT MAY BE LOCATED BELOW THE SURFACE OF THE LANDS, ON THE SURFACE OF THE LANDS OR ABOVE THE SURFACE OF THE LAND AND NOT VISIBLE.
  4. BEARING BASIS FOR THE SURVEY IS BASED ON THE DEED OF REFERENCE THEREIN. BEARINGS NOTED AS NAD 83, REFERENCE THE PENNSYLVANIA STATE PLANE COORDINATE SYSTEM, SOUTH ZONE AS DERIVED FROM GPS OBSERVATIONS. THE NAD 83 BEARINGS ARE ROTATED 1°45'52" COUNTERCLOCKWISE FROM THE DEED BEARINGS. VERTICAL DATUM IS NAVD 1988 DATUM.
  5. PROPERTY FALLS WITHIN ZONE "A", "AE" AREA DETERMINED TO BE INSIDE THE 0.1% ANNUAL CHANCE OF FLOODING AS DEPICTED ON THE FEDERAL EMERGENCY MANAGEMENT AGENCY FLOOD INSURANCE RATE MAP, MAP NO. 42029C0155G/42029C0160G DATED SEPTEMBER 29, 2017.
  6. LOCATIONS OF EXISTING UTILITIES AS SHOWN HEREIN HAVE BEEN DEVELOPED FROM EXISTING UTILITY RECORDS, PLANS BY OTHERS AND/OR ABOVE GROUND EXAMINATION OF SITE. THIS PLAN ILLUSTRATES UTILITIES OF RECORD PROVIDED BY OR BEFORE THE DATE THIS SURVEY. THIS MAY OR MAY NOT COMPRISE ALL THE UTILITY INFORMATION FOR THIS PROPERTY. THE COMPLETENESS OR ACCURACIES OF THE LOCATIONS ARE NOT GUARANTEED. SHOULD ANY NEW CONSTRUCTION BE PROPOSED, THE CONTRACTOR MUST VERIFY LOCATIONS AND DEPTHS OF ALL UTILITIES BEFORE START OF WORK.
  7. UNIT AND BLOCK NUMBERS REFER TO THE OFFICIAL TAX MAPS OF THE TOWNSHIP OF EAST GOSHEN, PENNSYLVANIA.
  8. REFERENCE PLANS: OFFICAL TAX MAPS OF EAST GOSHEN, CHESTER COUNTY, PA.; PLAN ENTITLED, "FINAL SUBDIVISION PLAN" - MADE FOR JOHN F. III AND BETTY C. LEWIS, PREPARED BY YERKES ASSOCIATES, INC. DATED OCTOBER 17, 1988 AND RECORDED IN THE CHESTER COUNTY COURTHOUSE AS PLAN BOOK #746 PAGE 1.; PLAN ENTITLED, "GOSHEN DOWNS" "FINAL TITLE PLAN" - PREPARED BY S.W.K. LTD. DATED JUNE 20, 1978 AND RECORDED IN THE CHESTER COUNTY COURTHOUSE AS PLAN BOOK 1746 PAGE 1.

GENERAL NOTES:

  1. THE WETLAND INFORMATION SHOWN HEREON IS BASED ON A WETLAND DELINEATION PERFORMED BY LIBERTY ENVIRONMENTAL, INC. IN JUNE 2022.
  2. THE RIGHT-OF-WAY FOR THE PROPOSED ROAD (MILLSTONE CIRCLE) IS INTENDED TO BE DEDICATED TO EAST GOSHEN TOWNSHIP.
  3. THE PROPOSED OPEN SPACE AREAS ARE NOT FOR DEDICATION AND WILL REMAIN PRIVATELY OWNED. THE HOMEOWNERS ASSOCIATION SHALL BE RESPONSIBLE FOR MAINTENANCE OF THE PARCEL. THE CENTRAL OPEN SPACE IS INTENDED TO BE USED OF ACTIVE RECREATION AND TO BE MAINTAINED IN A GRASS/MOWED COVER. THE PERIMETER OPEN SPACE IS INTENDED TO BE USED FOR PASSIVE RECREATION AND TO BE MAINTAINED IN A NATURALISTIC MEADOW/WOODED COVER CONDITION.
  4. ALL STORM WATER MANAGEMENT FACILITIES LOCATED OUTSIDE OF THE ROAD RIGHT-OF-WAY SHALL BE OWNED PRIVATELY BY THE HOMEOWNER'S ASSOCIATION. THE HOMEOWNERS ASSOCIATION SHALL BE RESPONSIBLE FOR MAINTENANCE OF THE STORM WATER MANAGEMENT FACILITIES.
  5. THE PROPOSED SANITARY SEWER SYSTEM IS INTENDED TO BE DEDICATED TO EAST GOSHEN TOWNSHIP.
  6. PRIOR TO STARTING CONSTRUCTION, THE CONTRACTOR SHALL BE RESPONSIBLE TO ENSURE THAT ALL REQUIRED PERMITS AND APPROVALS HAVE BEEN OBTAINED. NO CONSTRUCTION OR FABRICATION SHALL BEGIN UNTIL THE CONTRACTOR HAS RECEIVED AND THOROUGHLY REVIEWED ALL PLANS AND OTHER DOCUMENTS BY ALL OF THE PERMITTING AUTHORITIES.
  7. THE IMPROVEMENTS SHOWN WITHIN THE LOTS HAS BEEN PROVIDED TO SHOWN GENERAL COMPLIANCE WITH THE EAST GOSHEN TOWNSHIP'S ORDINANCES. FINAL BUILDING DIMENSIONS SHALL ULTIMATELY CONFORM TO ALL APPLICABLE ZONING SETBACKS, IMPERVIOUS SURFACE COVERAGE RATIOS, ETC. INDIVIDUAL LOT PLOT PLANS DOCUMENTING COMPLIANCE ARE TO BE PROVIDED WITH THE SUBMISSION OF THE BUILDING PERMIT APPLICATIONS.
  8. ALL CONSTRUCTION SHALL COMPLY WITH THE TOWNSHIP OF EAST GOSHEN, CHESTER COUNTY AND PENNDOT STANDARDS.
  9. MONITORING AND COMPACTION VERIFICATION FOR ALL SITE FILL PLACEMENT WILL NEED TO BE COMPLETED BY THE CONTRACTOR'S GEOTECHNICAL ENGINEER.
  10. ALL SIGNS SHALL CONFORM TO THE REQUIREMENTS OF THE EAST GOSHEN TOWNSHIP ZONING ORDINANCE. PRIOR TO SIGN CONSTRUCTION, ALL NECESSARY SIGN AND/OR ZONING PERMITS SHALL BE ACQUIRED.
  11. PERMANENT CONCRETE MONUMENTS SHALL BE SET AT ALL POINTS OF CURVATURE AND AT ALL POINTS OF TANGENCY ON A RIGHT-OF-WAY FOR ALL PUBLIC STREETS. MONUMENTS SHALL BE OF CONCRETE, WITH A FLAT TOP HAVING A MINIMUM WIDTH OR DIAMETER OF FOUR (4) INCHES AND A MINIMUM LENGTH OF THIRTY (30) INCHES.
  12. LOT MARKERS SHALL BE PLACED AT ALL LOT CORNERS. MARKERS SHALL CONSIST OF IRON PIPES OR STEEL BARS AT LEAST 30 INCHES LONG AND NOT LESS THAN (3/4) INCH DIAMETER.
  13. THE DEVELOPER SHALL BE RESPONSIBLE FOR INSTALLATION OF ALL STREET MONUMENTS, BOUNDARY PINS AND/OR MONUMENTS AND LOT CORNER PINS INDICATED ON THE PLANS. ALL MARKERS MUST BE INSTALLED PRIOR TO CLOSE OUT OF THE PROJECT WITH EAST GOSHEN TOWNSHIP.
  14. THE SPEED LIMIT FOR THE PROPOSED ROADWAYS IS 15 MPH.
  15. NO DEBRIS SHALL BE BURIED ON THIS SITE. ALL DEBRIS SHALL BE DISPOSED OF OFF-SITE IN ACCORDANCE WITH ALL APPLICABLE TOWNSHIP, COUNTY, STATE AND FEDERAL LAWS AND REQUIREMENTS.
  16. IT SHALL BE THE RESPONSIBILITY OF THE OWNER TO COMPLY WITH ALL APPLICABLE ADA REQUIREMENTS FOR SITE ACCESS AND ACCESS TO PUBLIC WAYS WHETHER SHOWN ON THESE PLANS OR NOT. IT SHALL BE THE OWNER'S RESPONSIBILITY TO CONSTRUCT SAID FACILITIES AND TO MAINTAIN SAID FACILITIES IN GOOD CONDITION. ALL APPLICABLE PROPOSED STRUCTURES AND FACILITIES SHALL COMPLY WITH "THE AMERICAN DISABILITIES ACT", "ACCESSIBILITY GUIDELINES FOR BUILDING AND FACILITIES", AND "THE PENNSYLVANIA UNIVERSAL ACCESSIBILITY ACT".
  17. ALL REQUIRED AGREEMENTS AND FINANCIAL SECURITY IN A FORM ACCEPTABLE TO EAST GOSHEN TOWNSHIP SHALL BE PROVIDED.

WAIVERS REQUESTED:

THE FOLLOWING WAIVER OF THE EAST GOSHEN TOWNSHIP SUBDIVISION AND LAND DEVELOPMENT ORDINANCE ARE BEING REQUEST:

  • §205-20 - TO PERMIT THE SUBDIVISION PLANS TO BE CONSIDERED AS PRELIMINARY/FINAL.
  • §205-46 - TO PERMIT THE MINIMUM CENTER LINE RADIUS TO BE REDUCED TO 100 FEET.
  • §205-53.A - TO PERMIT THE PROPOSED ROAD TO BE NAMED MILL STONE CIRCLE, RATHER THAN TANGLEWOOD DRIVE.

TRAFFIC CONTROL NOTES:

  1. TRAFFIC CONTROL SIGNS MUST BE POSTED ON PENNDOT-APPROVED BREAKAWAY POSTS IN ACCORDANCE WITH THE MOST RECENT VERSION OF THE TC-8700 SERIES IN PENNDOT PUBLICATION 111M.
  2. ALL TRAFFIC CONTROL SIGNS SHALL BE POSTED IN ACCORDANCE WITH THE 2009 MUTCD AND THE MOST RECENT VERSIONS OF PENNDOT PUBLICATION 236M, "HANDBOOK OF APPROVED SIGNS."
  3. CLEAR SIGHT TRIANGLES (C.S.T.) HAVE BEEN ESTABLISHED BY MEASURING 75' ALONG THE CENTERLINE OF EACH STREET FROM THE POINT OF INTERSECTION OF THE CENTERLINES OF THE STREETS. WITHIN SUCH TRIANGLES, NO WALL, FENCE OR OTHER OBSTRUCTION SHALL BE ERECTED, ALLOWED OR MAINTAINED, AND NO HEDGE, TREE, SHRUB OR OTHER GROWTH SHALL BE PLANTED OR EXIST ABOVE THE HEIGHT OF 30 INCHES AND BELOW THE HEIGHT OF 10 FEET MEASURED FROM THE CENTER LINE GRADES OF THE INTERSECTING STREETS.
  4. ALL SIGHT DISTANCE OBSTRUCTIONS (INCLUDING BUT NOT LIMITED TO EMBANKMENTS AND VEGETATION) SHALL BE REMOVED BY THE APPLICANT TO PROVIDE A MINIMUM OF 300 FEET OF SIGHT DISTANCE TO BOTH THE LEFT AND RIGHT FOR A DRIVER EXITING ROAD A ONTO FOREST LANE. THE DRIVER MUST BE CONSIDERED TO BE POSITIONED 15' FROM THE NEAR EDGE OF THE CLOSEST HIGHWAY THROUGH TRAVEL LANE AT AN EYE HEIGHT OF THREE FEET-SIX INCHES (3'-6") ABOVE THE PAVEMENT SURFACE. THE POINT SIGHTED BY THE EXITING DRIVER SHALL BE THREE FEET-SIX INCHES (3'-6") ABOVE THE PAVEMENT SURFACE LOCATED IN THE CENTER OF THE CLOSEST HIGHWAY TRAVEL LANE DESIGNATED FOR USE BY APPROACHING TRAFFIC. THIS SIGHT DISTANCE SHALL BE MAINTAINED BY THE APPLICANT AND/OR THE APPLICANT'S SUCCESSORS AND ASSIGNORS.

UTILITY NOTES:

  1. THIS PLAN PROPOSES PUBLIC WATER SUPPLY AND PUBLIC SEWER. PUBLIC WATER WILL BE PROVIDED BY AQUA PENNSYLVANIA.
  2. ALL WATER MAINS SHALL MEET THE REQUIREMENTS OF AND BE INSTALLED IN ACCORDANCE WITH THE SPECIFICATIONS, STANDARDS AND DETAILS OF AQUA PENNSYLVANIA.
  3. WATER SUPPLY: ALL WATER SERVICES, INCLUDING DOMESTIC AND FIRE PROTECTION, SHALL MEET THE REQUIREMENTS OF AND BE INSTALLED IN ACCORDANCE WITH THE SPECIFICATIONS, STANDARDS AND DETAILS OF EAST GOSHEN TOWNSHIP. SHOP DRAWINGS AND/OR CATALOG CUTS FOR ALL PROPOSED MATERIALS SHALL BE SUBMITTED TO EAST GOSHEN TOWNSHIP AS PART OF THE APPLICATION FOR A PLUMBING PERMIT.
  4. SANITARY SEWERAGE: ALL SANITARY SEWER MAINS SHALL MEET THE REQUIREMENTS OF AND BE INSTALLED IN ACCORDANCE WITH THE SPECIFICATIONS, STANDARDS AND DETAILS OF THE EAST GOSHEN TOWNSHIP.
  5. SANITARY SEWERAGE: ALL SEWER LATERALS SHALL MEET THE REQUIREMENTS OF AND BE INSTALLED IN ACCORDANCE WITH THE SPECIFICATIONS, STANDARDS AND DETAILS OF EAST GOSHEN TOWNSHIP. SHOP DRAWINGS AND/OR CATALOG CUTS FOR ALL PROPOSED MATERIALS SHALL BE SUBMITTED TO EAST GOSHEN TOWNSHIP.
  6. THE SANITARY SEWER SHALL BE INSTALLED AT LEAST 10 FEET HORIZONTALLY AND AT LEAST 18 INCHES VERTICALLY FROM OTHER UTILITIES.
  7. THE SANITARY SEWER MAINS AND LATERALS SHALL BE BURIED A MINIMUM OF 4 FEET DEEP.
  8. IT IS NOT INTENDED TO PROVIDE SANITARY SEWER SERVICE TO THE BASEMENTS OF THE PROPOSED DWELLINGS.
  9. OTHER UTILITIES: ALL OTHER UTILITIES (ELECTRIC, COMMUNICATIONS, GAS, ETC.) SHALL BE INSTALLED IN ACCORDANCE WITH THE UTILITY COMPANY'S REQUIREMENTS AND SHALL BE INSTALLED AS TO NOT CONFLICT WITH THE WATER, SANITARY SEWER AND/OR STORM FACILITIES PROPOSED AS PART OF THIS PLANS.
  10. BACKFILL OF ALL UTILITY TRENCHES WITHIN EXISTING AND/OR PROPOSED RIGHT-OF-WAY SHALL BE DONE IN ACCORDANCE WITH THE SPECIFICATIONS, STANDARDS AND DETAILS OF EAST GOSHEN AND BE SUBJECT TO THE APPROVAL OF EAST GOSHEN TOWNSHIP OR THEIR DESIGNEE.
  11. DURING CONSTRUCTION OF SEWER PROJECTS, THE CONTRACTOR SHALL BE PROHIBITED FROM UNNECESSARILY DISTURBING OR UPROOTING TREES AND VEGETATION ALONG THE STREAMBANK AND IN THE VICINITY OF THE STREAM, DUMPING OF SOIL AND DEBRIS INTO STREAMS AND/OR ON BANKS OF STREAMS, CHANGING THE COURSE OF THE STREAM WITHOUT AN ENCROACHMENT PERMIT, LEAVING COFFERDAMS IN STREAMS, LEAVING TEMPORARY STREAM CROSSINGS FOR EQUIPMENT, OPERATING EQUIPMENT IN THE STREAM, OR PUMPING SILT-LADEN WATER INTO THE STREAM.

STORM WATER NOTES:

  1. THE STORM WATER MANAGEMENT FACILITIES HAVE BEEN DESIGNED ASSUMING AN AMOUNT OF IMPERVIOUS COVERAGE BASED ON THE IMPROVEMENTS SHOWN PLUS AN ADDITIONAL 2,000 SQUARE FEET PER LOT TO ACCOUNT FOR FUTURE IMPROVEMENTS BY THE HOMEOWNERS.
  2. THE PROPOSED TREE PLANTINGS ARE PART OF THE OVERALL SITE STORM WATER MANAGEMENT SYSTEM.
  3. ROOF LEADERS SHALL BE DISCHARGED ONTO SPLASH BLOCKS AND DIRECTED TOWARDS VEGETATED SURFACES (AS PRACTICABLE).
  4. ALL STORM CONVEYANCE PIPE SHALL BE SMOOTH LINED DOUBLE WALLED HIGH DENSITY POLYETHYLENE PIPE (HDPE), UNLESS OTHERWISE SPECIFIED.
  5. END WALLS AND END SECTIONS SHALL BE REQUIRED ON ALL OPEN PIPES, SHALL BE OF CONCRETE CONSTRUCTION, AND SHALL BE SET ON A MINIMUM OF TWELVE (12) INCHES OF AASHTO NO. 57 (PENNDOT 2B) COARSE AGGREGATE.

CONDITIONAL USE APPROVAL BY EAST GOSHEN TOWNSHIP:

CONDITIONAL USE APPLICATION OF GROVE MEADOW DEVELOPERS, LLC
DATED MARCH 7, 2023

DECISION AND ORDER CONDITIONS
AND NOW, THIS 7TH DAY OF MARCH, 2023, THE BOARD OF SUPERVISORS OF EAST GOSHEN TOWNSHIP HEREBY ORDERS THE FOLLOWING:

  1. THE APPLICATION FOR A SINGLE-FAMILY OPEN SPACE DEVELOPMENT IS HEREBY GRANTED, SUBJECT TO THE CONDITIONS HEREINAFTER ENUMERATED.
  2. PURSUANT TO SECTION 240-38.6 OF THE HISTORIC PRESERVATION ORDINANCE, A MODIFICATION FROM SECTION 240-23.B(2)(B)[2][C], PERMITTING ONLY ONE FLAG LOT, IS GRANTED TO ALLOW TWO (2) FLAG LOTS FOR THE HISTORIC RESOURCES ON THE PROPERTY.
  3. THE APPLICANT SHALL COMPLY WITH ALL OUTSTANDING COMMENTS CONTAINED IN THE PENNONI REVIEW LETTER DATED OCTOBER 27, 2022 (EXHIBIT B-10), TO THE SATISFACTION OF THE TOWNSHIP ENGINEER, AS AMENDED BY THIS ORDER.
  4. DURING THE SUBDIVISION/LAND DEVELOPMENT PROCESS, THE APPLICANT SHALL ADEQUATELY ADDRESS STORMWATER MANAGEMENT, TO THE SATISFACTION OF THE TOWNSHIP ENGINEER, INCLUDING BUT NOT LIMITED TO STORMWATER CONVEYANCES THROUGH THE SITE FROM ADJACENT STORMWATER MANAGEMENT FACILITIES AND ANY NECESSARY STORMWATER EASEMENTS.
  5. THE APPLICANT SHALL PROVIDE TO THE TOWNSHIP A SANITARY SEWER AND PEDESTRIAN ACCESS EASEMENT APPROXIMATELY LOCATED BETWEEN LOTS 6 AND 7, TO THE SATISFACTION OF THE TOWNSHIP. THE PEDESTRIAN ACCESS EASEMENT SHALL BE DEMARCATED BY POST-AND-RAIL FENCING, STONES, MULCH, GRASS PAVERS, OR THE LIKE. THE PEDESTRIAN ACCESS EASEMENT SHALL BE MAINTAINED BY THE HOMEOWNERS' ASSOCIATION AND WILL BE ADEQUATELY ADDRESSED IN THE ASSOCIATION'S DECLARATION OF COVENANTS, CONDITIONS AND RESTRICTIONS (THE "DECLARATION") TO THE SATISFACTION OF THE TOWNSHIP. NOTICE OF THE EASEMENT SHALL ALSO BE PROVIDED TO ANY PROSPECTIVE BUYERS OF LOTS 6 AND 7 PRIOR TO EXECUTION OF AN AGREEMENT OF SALE. THE APPLICANT SHALL COMPLETE THE DEMARCATION OF THE PEDESTRIAN ACCESS PRIOR TO THE ISSUANCE OF BUILDING PERMITS FOR LOTS IMMEDIATELY ADJACENT TO THE EASEMENT AREA.
  6. THE 'CENTRAL GREEN' LOCATED WITHIN THE CUL-DE-SAC SHALL BE GRADED AND MAINTAINED TO ALLOW FOR ACTIVE RECREATION.
  7. THE APPLICANT SHALL PRESERVE AS MUCH OF THE EXISTING PERIMETER VEGETATION AS POSSIBLE. ANY VEGETATION REPLACED PURSUANT TO THE ORDINANCE AND/OR THE TOWNSHIP'S SUBDIVISION AND LAND DEVELOPMENT ORDINANCE (THE "SALDO") SHALL BE REPLACED WITH NATIVE AND DEER-RESISTANT MATERIALS, WHEREVER POSSIBLE. LANDSCAPING PLANS SHALL BE REVIEWED BY THE EAST GOSHEN TOWNSHIP CONSERVANCY BOARD AND THE TOWNSHIP ENGINEER TO ENSURE COMPLIANCE WITH THE ORDINANCE AND SALDO. FURTHERMORE, THE PERIMETER OF THE PROPERTY SHALL CONTAIN A TRADITIONAL POST-AND-RAIL OR EQUIVALENT FENCE THAT REUSES THE EXISTING CONCRETE POSTS, WHERE POSSIBLE.
  8. THE APPLICANT SHALL DESIGN AND INSTALL A 150' WIDE RIPARIAN FOREST BUFFER IN ACCORDANCE WITH THE RIPARIAN BUFFER REQUIREMENTS OUTLINED IN 25 PA. CODE § 102.14 FOR THE PORTION OF STREAM WITHIN THE SUBJECT PROPERTY. SHOULD THE APPLICANT DEMONSTRATE TO THE TOWNSHIP THAT CREATION AND MAINTENANCE OF THE ENTIRE 150' RIPARIAN BUFFER AREA IS NOT POSSIBLE FOR ANY PORTION OF THE PROPERTY, THEN THE WIDTH OF THE BUFFER MAY BE REDUCED BY THE BOARD OF SUPERVISORS, IN THEIR SOLE DISCRETION, DURING THE SUBDIVISION/LAND DEVELOPMENT PROCESS. AREAS OF EXISTING WOODLAND MAY BE UTILIZED TO MEET THE RIPARIAN BUFFER REQUIREMENTS; HOWEVER, THESE AREAS SHALL BE REVIEWED BY AN ARBORIST OR QUALIFIED PROFESSIONAL TO ENSURE THAT THE COMPOSITION OF PLANT LIFE MEETS THE REQUIREMENTS OUTLINED. A PLAN SHALL BE ESTABLISHED TO REMOVE INVASIVE SPECIES WITHIN THE EXISTING WOODED AREAS AND ANY AREAS OF THE RIPARIAN BUFFER. AN OPERATION & MAINTENANCE PLAN SHALL BE DEVELOPED FOR THE RIPARIAN BUFFER TO ENSURE THAT THIS BUFFER IS MAINTAINED FREE OF INVASIVE SPECIES IN PERPETUITY, WITH SUCH PLAN BEING RECORDED WITH THE APPROVED FINAL PLANS.
  9. MAINTENANCE OF ALL LANDSCAPING ON HOA-OWNED PROPERTY, AS WELL AS ALL STREET TREES, SHALL BE THE RESPONSIBILITY OF THE HOMEOWNERS' ASSOCIATION AND WILL BE ADDRESSED IN THE DECLARATION, TO THE SATISFACTION OF THE TOWNSHIP. ALL STREET TREES SHALL BE LOCATED OUTSIDE OF ANY ROAD RIGHT-OF-WAY.
  10. PRIOR TO RECORDING THE PLANS, THE APPLICANT SHALL PREPARE AND SUBMIT TO THE TOWNSHIP A SHARED ACCESS EASEMENT, AS APPROVED BY THE TOWNSHIP SOLICITOR, FOR THE SHARED DRIVEWAY SERVICING THE TWO (2) FLAG LOTS.
  11. THE APPLICANT SHALL COMPLY WITH THE TOWNSHIP'S ORDINANCES REGARDING CARTWAY WIDTH (SECTION 205-44) AND SIDEWALKS/PATHS (SECTION 205-56). ANY WAIVER REQUESTS FROM THESE PROVISIONS WILL BE CONSIDERED BY THE BOARD OF SUPERVISORS DURING THE SUBDIVISION/LAND DEVELOPMENT PROCESS.
  12. THE APPLICANT SHALL PROVIDE AN OFFER OF DEDICATION OF ADDITIONAL PROPERTY ALONG HERSHEY MILL ROAD FOR A POTENTIAL FUTURE SIDEWALK OR PATHWAY.
  13. ANY FUTURE RESIDENTIAL REUSE OF THE HISTORIC BARN SHALL REQUIRE FURTHER APPROVALS FROM THE TOWNSHIP, PURSUANT TO THE HISTORIC PRESERVATION PROVISIONS OF THE ORDINANCE (SECTIONS 240-38.1 THROUGH 240-38.11). DURING ITS OWNERSHIP OF THE HISTORIC BARN, THE APPLICANT SHALL ENSURE THAT IT IS WELL MAINTAINED AND DOES NOT FALL INTO DISREPAIR.
  14. PRIOR TO FINAL PLAN APPROVAL, A PHASE I ENVIRONMENTAL SITE ASSESSMENT FOR THE PROPERTY SHALL BE PROVIDED TO THE TOWNSHIP.
  15. THE USE OF THE PROPERTY SHALL BE IN SUBSTANTIAL CONFORMITY WITH THE APPLICANT'S APPLICATION AND THE TESTIMONY AND EXHIBITS PRESENTED AT THE HEARING ON THE APPLICATION AS DETERMINED BY THE TOWNSHIP, AS AMENDED BY THIS ORDER.
  16. THE APPLICANT'S CONDITIONAL USE SHALL BE SUBJECT TO COMPLIANCE WITH ALL TERMS AND PROVISIONS OF THE ORDINANCE AND ALL OTHER TOWNSHIP ORDINANCES AND REGULATIONS.
  17. THE ATTACHED FINDINGS OF FACT, CONCLUSIONS OF LAW, AND DISCUSSION ARE INCORPORATED INTO THIS ORDER.
  18. THE APPLICANT SHALL EXECUTE AND PROVIDE TO THE TOWNSHIP A RECORDABLE, NOTARIZED COPY OF A MEMORANDUM CONTAINING A METES AND BOUNDS DESCRIPTION OF THE PROPERTY IN QUESTION AND STIPULATING THE TERMS AND CONDITIONS OF THIS APPROVAL AND SHALL CONSENT TO THE RECORDING BY THE TOWNSHIP IN THE OFFICE OF THE RECORDER OF DEEDS OF CHESTER COUNTY NO LATER THAN THE RECORDING OF THE APPROVED FINAL PLAN. ALL RECORDING COSTS SHALL BE REIMBURSED BY THE APPLICANT WITHIN 30 DAYS OF RECEIPT OF AN INVOICE FROM THE TOWNSHIP.
  19. THE APPLICANT SHALL EXPRESS TO THE BOARD IN WRITING, DELIVERED TO THE TOWNSHIP OFFICE WITHIN 15 DAYS OF THE APPLICANT'S RECEIPT OF THIS DECISION, ITS FULL AND COMPLETE CONSENT TO THE CONDITIONS SPECIFIED HEREIN ABOVE OR THE APPLICATION FOR CONDITIONAL USE APPROVAL IS DENIED, THE BOARD EXPRESSLY FINDING AND CONCLUDING THAT THE APPLICATION, IN THE ABSENCE OF COMPLIANCE WITH THE SAID CONDITIONS, IS INCONSISTENT WITH THE STANDARDS, CRITERIA, PURPOSES AND POLICIES CODIFIED IN SECTION 240-31 OF THE ORDINANCE.

APPLICANT & EQUITABLE RECORD OWNER:
GROVE MEADOW DEVELOPERS LLC
1171 LANCASTER AVE, SUITE 201
BERWYN PA 19312

RECORD OWNER:
MARK S. & CHRISTINE S. MILLER
10 N. ABERDEEN AVENUE
WAYNE, PA 19087

SOURCE OF TITLE:
PIN# 53-1-19 DBV 3587 PAGE 895

SCOPE:
SINGLE FAMILY OPEN SPACE DEVELOPMENT
TOTAL UNITS: 14 SINGLE FAMILY LOTS
TOTAL AREA: 16.128 ACRES (GROSS AREA) / 15.729 ACRES (NET AREA)
PROPOSED DENSITY: 1.123 ACRES/UNIT
WATER SERVICE: PUBLIC
SEWER SERVICE: PUBLIC

DATUM:
BENCHMARK: EXISTING SANITARY SEWER MANHOLE IN TANGLEWOOD DRIVE
TOP OF MANHOLE=459.50
DATUM IS BASED ON NAVD DATUM OF 1988

AREAS TO BE DEDICATED:
HERSHEY MILL ROAD: 0.399 ACRES
PROPOSED ROAD (MILLSTONE CIRCLE): 1.400 ACRES

ZONING DATA TABULATION

LOW DENSITY RESIDENTIAL DISTRICT (R-2)

RequirementStandard
LOT AREA1 ACRE
LOT WIDTH150 FT. (AT BUILDING LINE)
60 FT. (AT STREET LINE)
FRONT YARD45 FT. MINIMUM
60 FT. AVERAGE
SIDE YARD20 FT. EACH
REAR YARD50 FT.
BUILDING HEIGHT3 STORIES OR 38 FT.
MAX. BLDG. COVERAGE25 %
MAX. IMP. COVERAGE30 %

OPEN SPACE DEVELOPMENT OPTION REQUIREMENTS

RequirementStandard / Minimum
REQUIRED OPEN SPACE (55% OF TRACT, MINIMUM 8 ACRES)8.651 ACRES
LOT SIZEN/A
BUILDING SETBACK FROM TRACT LINE50 FT.
BUILDING SEPARATION30 FT.
BUILDING SETBACK FROM EDGE OF CARTWAY25 FT.
BUILDING SETBACK FROM PROPERTY LINES1 FT.
REQUIRED PARKINGTHREE OFF-STREET SPACES/UNIT

PROVIDED OPEN SPACE

Open Space AreaAcres
PERIMETER OPEN SPACE (PARCEL 101)8.205 ACRES
CENTRAL GREEN SPACE (PARCEL 100)1.045 ACRES
QUALIFYING OPEN SPACE9.250 ACRES (58.8 %)

ZONING NOTES

  1. THE PROPOSED OPEN SPACE MAY NOT BE SEPARATELY SOLD, NOR SHALL SUCH LAND BE FURTHER DEVELOPED OR SUBDIVIDED.
  2. THE OPEN SPACE AREA DESIGNATED AS PARCEL 100 AND 102 SHALL BE CONSIDERED A PASSIVE OPEN SPACE.
  3. THE OPEN SPACE AREA DESIGNATED AS PARCEL 101 SHALL BE CONSIDERED AN ACTIVE OPEN SPACE AREA AND AVAILABLE FOR THE COMMUNITY USE.
  4. THE OPEN SPACE AREAS SHALL BE PROTECTED BY A CONSERVATION EASEMENT. OWNERSHIP AND OWNED, MANAGED AND MAINTAINED BY A HOMEOWNER'S ASSOCIATION.
  5. THE FOLLOWING ACCESSORY USES ARE NOT PERMITTED: STORAGE SHEDS; DETACHED GARAGES; RECREATIONAL VEHICLES; WINDMILLS

[Drawing: Vicinity Map, Scale: 1"=800', showing project location along Hershey Mill Road.]

PLAN SET INDEX

Sheet TitleDrawing NumberSheet Number
COVER SHEET22-001-F-D-1.01 OF 20
SUBDIVISION PLAN22-001-F-D-2.02 OF 20
EXISTING CONDITIONS AND DEMOLITION PLAN22-001-F-D-3.03 OF 20
OPEN SPACE MANAGEMENT PLAN22-001-F-D-4.04 OF 20
UTILITY PLAN22-001-F-D-5.05 OF 20
GRADING PLAN22-001-F-D-6.06 OF 20
LANDSCAPING PLAN22-001-F-D-7.17 OF 20
LANDSCAPING DETAILS AND NOTES22-001-F-D-7.28 OF 20
PROFILES22-001-F-D-8.19 OF 20
PROFILES22-001-F-D-8.210 OF 20
EROSION AND SEDIMENT CONTROL PLAN22-001-F-D-9.111 OF 20
E&SC NOTES SHEET22-001-F-D-9.212 OF 20
E&SC DETAILS SHEET22-001-F-D-9.313 OF 20
E&SC DETAILS SHEET (RESERVED)22-001-F-D-9.414 OF 20
POST-CONSTRUCTION STORM WATER MANAGEMENT PLAN22-001-F-D-10.115 OF 20
PCSM NOTES SHEET22-001-F-D-10.216 OF 20
PCSM DETAILS SHEET22-001-F-D-10.317 OF 20
RIPARIAN BUFFER MANAGEMENT PLAN22-001-F-D-10.418 OF 20
CONSTRUCTION DETAILS - SITE22-001-F-D-11.119 OF 20
CONSTRUCTION DETAILS - SANITARY22-001-F-D-11.220 OF 20

CERTIFICATE OF OWNERSHIP

COMMONWEALTH OF PENNSYLVANIA
COUNTY OF CHESTER
ON THIS ____ THE DAY OF ____________, 20____, BEFORE ME THE UNDERSIGNED OFFICER, PERSONALLY APPEARED T.R. MOSER WHO BEING DULY SWORN ACCORDING TO LAW, DEPOSES AND SAYS THAT HE IS THE PRESIDENT OF GROVE MEADOW DEVELOPERS LLC, WHICH IS THE OWNER OF THE PROPERTY SHOWN ON THIS PLAN, THAT HE ACKNOWLEDGES IT ACT AND DESIRES THE SAME TO BE RECORDED AS SUCH ACCORDING TO LAW.

CHESTER COUNTY RECORDER OF DEEDS

RECORDED IN THE OFFICE OF THE RECORDER OF DEEDS OF CHESTER COUNTY AT WEST CHESTER, PENNSYLVANIA, IN PLAN BOOK ______ PAGE ______ ON THE ______ DAY OF ____________, 20____.

CERTIFICATE OF ACCURACY - SURVEY

I HEREBY CERTIFY THAT, TO THE BEST OF MY KNOWLEDGE, ALL SURVEY INFORMATION AND COMPUTATIONS SHOWN AND DESCRIBED HEREON ARE TRUE AND CORRECT TO THE ACCURACY REQUIRED BY WILLISTOWN TOWNSHIP SUBDIVISION AND LAND DEVELOPMENT ORDINANCE. (BOUNDARY LINES CLOSE WITH AN ERROR OF LESS THAN ONE FOOT IN 10,000 FEET).

CERTIFICATE OF MUNICIPAL APPROVAL - BOARD OF SUPERVISORS

APPROVED BY THE BOARD OF SUPERVISORS OF EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA, THIS ____ DAY OF ____________, 20____.

TOWNSHIP ENGINEER

REVIEWED BY THE EAST GOSHEN TOWNSHIP ENGINEER, THIS ____ DAY OF ____________, 20____.

CHESTER COUNTY PLANNING COMMISSION

REVIEWED BY THE CHESTER COUNTY PLANNING COMMISSION THIS ____ DAY OF ____________, 20____.

CERTIFICATE OF ACCURACY

THESE PLANS ARE PREPARED IN ACCORDANCE WITH THE APPLICABLE REQUIREMENTS OF THE COMMONWEALTH OF PENNSYLVANIA, CHESTER COUNTY, AND WILLISTOWN TOWNSHIP.

CERTIFICATE OF REVIEW - PLANNING COMMISSION

REVIEWED BY THE PLANNING COMMISSION OF EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA, THIS ____ DAY OF ____________, 20____.

[Seal: Commonwealth of Pennsylvania Registered Professional Engineer Michael Duain Hartman, PE055087]

PRELIMINARY/FINAL SUBDIVISION AND LAND DEVELOPMENT PLANS
FOR
"MILLSTONE MEADOWS"
COVER SHEET

CLIENT: GROVE MEADOW DEVELOPERS LLC
LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
DATE: APRIL 20, 2023
DRAWN: M.D. HARTMAN
CHECKED: M.D. HARTMAN
SCALE: N.T.S.
SHEET 1 OF 20
22-001-F-D-1.0
dh Enterprises, 2815 Penn Avenue, West Lawn, PA 19609, 610-927-4242

Engineering plan sheet showing a proposed 14-lot single-family subdivision along Millstone Circle, with a central open space parcel 100, perimeter open space parcel 101, two infiltration basins, sewer easements and adjoining property owners.

PROPERTY LINE CURVE TABLE

CURVE #LENGTHRADIUSDELTACH. BEARING & DIST.
C11.16'775.00'000°05'08"N46°53'40"W 1.16'
C2189.43'1100.00'009°52'06"S37°39'17"E 189.20'
C631.42'20.00'090°00'51"S12°51'09"W 28.57'
C730.41'20.00'087°07'46"S78°02'09"E 27.51'
C8263.44'320.00'047°10'05"N02°00'37"E 256.06'
C9109.42'85.00'070°34'15"N70°18'32"E 102.02'
C10112.45'270.00'023°51'44"N46°57'16"E 111.64'
C11188.50'120.00'090°00'00"S26°06'52"E 169.71'
C12235.62'150.00'090°00'00"S13°53'08"W 212.13'
C13209.62'220.00'054°35'29"S06°10'53"W 201.78'
C14269.03'280.00'055°03'03"S05°57'06"W 258.80'
C1539.71'29.00'078°27'45"S10°14'35"E 36.68'
C16120.04'230.00'029°54'11"S43°56'02"W 118.68'
C17125.66'80.00'090°00'00"N70°06'52"W 113.14'
C18172.79'110.00'090°00'00"N13°53'08"E 155.56'
C19171.50'180.00'054°35'29"N06°10'53"E 165.09'
C2032.74'110.00'017°03'15"S57°54'45"E 32.62'
C2120.56'89.00'013°14'14"S01°01'20"E 20.52'
C2289.06'89.00'057°20'01"N63°44'25"E 85.39'
C2344.03'270.00'009°20'36"N39°41'42"E 43.98'
C2468.42'270.00'014°31'08"N51°37'34"E 68.24'
C2538.75'120.00'018°30'10"N68°08'13"E 38.58'
C2673.47'120.00'035°04'37"S85°04'24"E 72.32'
C2776.28'120.00'036°25'13"S49°19'28"E 75.03'
C2815.11'150.00'005°47'53"S28°12'54"E 15.10'
C2994.53'150.00'036°06'25"S07°15'42"E 92.97'
C3040.08'150.00'015°18'44"S18°25'52"W 39.88'
C3185.91'150.00'032°48'54"S42°28'41"W 84.74'
C3284.05'220.00'021°53'21"S69°49'48"W 83.54'
C3396.05'220.00'025°00'53"N86°43'04"W 95.19'
C3429.52'220.00'007°41'15"N70°22'00"W 29.50'
C3575.39'280.00'015°25'40"N74°14'13"W 75.17'
C3640.14'280.00'008°12'48"N86°03'26"W 40.10'
C3740.14'280.00'008°12'48"S85°43'46"W 40.10'
C38113.36'280.00'023°11'48"S70°01'28"W 112.59'

LEGEND

  • EXISTING LIGHT STANDARD
  • EXISTING CURB
  • PROPOSED CURB
  • SOIL LINE
  • RIPARIAN BUFFER
  • WETLAND DELINEATION
  • EXISTING WETLANDS
  • EXISTING STREET SIGN
  • EXISTING FEATURES ARE LABELED WITH SLANTED TEXT
  • EXISTING DECIDUOUS TREE
  • EXISTING CONIFEROUS TREE
  • EXISTING EDGE OF WOODS
  • PROPOSED CONCRETE MONUMENT
  • PROPOSED IRON PIN (TYP.)
  • PROPOSED CURB TAPER
  • PROPOSED HANDICAPPED RAMP
  • RETAINING WALL

Plan labels

  • Lot 1: 14,105 SQ. FT.
  • Lot 2: 11,734 SQ. FT.
  • Lot 3: 11,959 SQ. FT.
  • Lot 4: 18,491 SQ. FT.
  • Lot 5: 16,232 SQ. FT.
  • Lot 6: 14,208 SQ. FT.
  • Lot 7: 18,659 SQ. FT.
  • Lot 8: 13,659 SQ. FT.
  • Lot 9: 12,697 SQ. FT.
  • Lot 10: 12,551 SQ. FT.
  • Lot 11: 12,218 SQ. FT.
  • Lot 12: 13,291 SQ. FT.
  • Lot 13: 30,946 SQ. FT.
  • Lot 14: 20,691 SQ. FT.
  • Parcel 100: 1.04 AC.
  • Parcel 101: 8.20 AC.
  • INFILTRATION BASIN #1 and INFILTRATION BASIN #2
  • STORM SEWER EASEMENT and SANITARY SEWER EASEMENT
  • MILLSTONE CIRCLE

Title block

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN SUBDIVISION PLAN

CLIENT: GROVE MEADOW DEVELOPERS LLC
LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
DATE: APRIL 20, 2023
DRAWN: M.D. HARTMAN
CHECKED: M.D. HARTMAN
SCALE: 1" = 50'
SHEET 2 OF 20
22-001-F-D-2.0

Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242. Seal: Commonwealth of Pennsylvania, Michael Duain Hartman, Professional Engineer. Revision 7/25/23: Revised per Township review letters.

Note: some text on this page could not be read reliably. Please see the original PDF for this page.

[Engineering plan sheet showing existing conditions: topography contours, soil boundaries, shaded steep slopes, an existing dwelling and outbuildings, a driveway to Hershey Mill Road, Tanglewood Drive, and a legend.]

DEMOLITION NOTES:

  1. CONTRACTOR TO DEMOLISH ALL ITEMS NECESSARY TO CONSTRUCT PROPOSED BUILDING AND SITE FEATURES WHETHER OR NOT INDICATED IN THE CONSTRUCTION DOCUMENTS. ADEQUATE AND PROPER PROTECTION SHALL BE PROVIDED TO PREVENT EXISTING FEATURES NOT BEING REMOVED.
  2. EXCAVATIONS THAT ARE LEFT OPEN DURING THE DEMOLITION PROCESS SHALL BE COVERED OR FENCED OFF. THE AREA SHALL BE ADEQUATELY MARKED TO ENSURE WORKER AND PUBLIC SAFETY.
  3. [illegible]
  4. UNUSABLE MATERIALS AND RUBBISH SHALL BE IMMEDIATELY REMOVED FROM THE SITE. [remainder illegible]
  5. DAMAGE CAUSED TO EXISTING FEATURES DURING THE DEMOLITION PROCESS SHALL BE REPAIRED AND RESTORED TO PRE-DEMOLITION CONDITIONS. [remainder illegible]
  6. FEATURES SHOWN IN BOLD INDICATE ITEMS THAT MUST AT A MINIMUM BE REMOVED. ALSO SEE NOTE 1.

EXISTING NATURAL FEATURES:

  1. TOPOGRAPHY AND CONTOURS: THE EXISTING TOPOGRAPHY AND CONTOURS HAVE BEEN SHOWN ON PLANS.
  2. SITE BENCHMARK AND DATUM: BENCHMARK: EXISTING SANITARY SEWER MANHOLE IN TANGLEWOOD DRIVE. TOP OF MANHOLE=459.50. DATUM IS BASED ON NAVD DATUM OF 1988.
  3. STEEP SLOPES: THE STEEP SLOPES HAVE BEEN DELINEATED ON THE PLANS FOR 15%-25% AND GREATER THAN 25% SLOPES.
  4. WATERCOURSES, PONDS AND FLOOD HAZARD DISTRICT: [text too small to read reliably]
  5. SOIL DATA: Co - CODORUS SILT LOAM; Ha - HATBORO SILT LOAM; GgB - GLENVILLE SILT LOAM, 3 TO 8 PERCENT SLOPES; MaB - MANOR LOAM, 3 TO 8 PERCENT SLOPES; MaC - MANOR LOAM, 8 TO 15 PERCENT SLOPES; MaD - MANOR LOAM, 15 TO 25 PERCENT SLOPES; MaE - MANOR LOAM, 25 TO 35 PERCENT SLOPES; UugB - URBAN LAND - [illegible] SCHIST AND GNEISS COMPLEX, 0 TO 8 PERCENT SLOPES.
  6. GEOLOGIC FORMATION: [text too small to read reliably]
  7. SOIL PERCOLATION TESTS: SOIL TEST AND PROBE LOCATIONS ARE SHOWN ON THE PLANS.
  8. WETLANDS: [text too small to read reliably]
  9. EXISTING VEGETATION: [text too small to read reliably]
  10. EXISTING STRUCTURES AND OTHER IMPROVEMENTS: THE EXISTING IMPROVEMENTS ARE SHOWN ON THE PLANS.
  11. HISTORIC RESOURCES: [text too small to read reliably]
  12. EXISTING PATHS AND TRAILS: [illegible]
  13. EXISTING EROSION AND SEDIMENTATION CONTROL MEASURES: [illegible]
  14. ANY OTHER SIGNIFICANT EXISTING NATURAL OR MAN-MADE FEATURES: [illegible]
  15. DELINEATION OF THOSE PORTIONS OF THE LOT VISIBLE FROM ADJACENT PUBLIC ROADS: [text too small to read reliably]

LEGEND

  • EXISTING CURB
  • EXISTING CONTOURS
  • EXISTING SPOT ELEVATION
  • SOIL LINE
  • RIPARIAN BUFFER
  • WETLAND DELINEATION
  • EXISTING WETLANDS
  • EXISTING STREET SIGN
  • EXISTING FEATURES ARE LABELED WITH SLANTED TEXT
  • EXISTING DECIDUOUS TREE
  • EXISTING CONIFEROUS TREE
  • EXISTING EDGE OF WOODS
  • TO BE REMOVED
  • EXISTING SANITARY SEWER & MANHOLE
  • EXISTING WATER LINE & VALVE
  • 15% - 25% SLOPES
  • 25%+ SLOPES

Soil labels on plan: MaB, MaC, MaD, MaE, UugB, Co, Ha, MnC. Street labels: HERSHEY MILL ROAD, TANGLEWOOD DRIVE.

"MILLSTONE MEADOWS"
PRELIMINARY/FINAL PLAN
EXISTING CONDITIONS AND DEMOLITION PLAN

CLIENT: GROVE MEADOW DEVELOPERS LLC
LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
DATE: [illegible] 2023
DRAWN: M.D. HARTMAN
CHECKED: M.D. HARTMAN
SCALE: 1" = 50'
SHEET 3 OF 20
22-001-F-D-3.0

Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242
Revision 7/25/23: REVISED PER TOWNSHIP REVIEW LETTERS

[Seal: Commonwealth of Pennsylvania, Registered Professional Engineer, Michael Duain Hartman]

[Engineering plan sheet: site plan of a cul-de-sac development with numbered lots 1 through 14, a central oval parcel 100, a larger wooded parcel 101, Millstone Circle, two shaded infiltration basins, wetlands and slope hatching, and adjoining property owners labeled around the edges.]

OPEN SPACE DEVELOPMENT OPTION REQUIREMENTS

ItemAmount
REQUIRED OPEN SPACE (55% OF TRACT, [illegible])8.651 ACRES

PROVIDED OPEN SPACE

AreaAmount
PERIMETER OPEN SPACE (PARCEL 101)8.205 ACRES
CENTRAL GREEN SPACE (PARCEL 100)1.045 ACRES
QUALIFYING OPEN SPACE9.250 ACRES ([illegible] %)

OPEN SPACE NOTES

  1. THE PROPOSED OPEN SPACE MAY NOT BE SEPARATELY SOLD, NOR SHALL SUCH LAND BE FURTHER DEVELOPED OR SUBDIVIDED.
  2. [illegible fine print about parcels 100 and 102 being passive open space]
  3. [illegible fine print about parcel 101 being an active open space area available for community use]
  4. THE OPEN SPACE AREAS SHALL BE PROTECTED BY A CONSERVATION EASEMENT. OWNERSHIP AND [illegible] MANAGED AND MAINTAINED BY A HOMEOWNER'S ASSOCIATION.

LEGEND

  • EXISTING LIGHT STANDARD
  • EXISTING CURB
  • PROPOSED CURB
  • SOIL LINE
  • RIPARIAN BUFFER
  • WETLAND DELINEATION
  • EXISTING WETLANDS
  • EXISTING STREET SIGN
  • EXISTING FEATURES ARE LABELED WITH SLANTED TEXT
  • EXISTING DECIDUOUS TREE
  • EXISTING CONIFEROUS TREE
  • EXISTING EDGE OF WOODS
  • PROPOSED CONCRETE MONUMENT
  • PROPOSED IRON PIN (TYP.)
  • PROPOSED CURB TAPER
  • PROPOSED HANDICAPPED RAMP
  • RETAINING WALL

HATCH LEGEND

  • OPEN SPACE AREA (ACTIVE AREA)
  • OPEN SPACE AREA (PASSIVE AREA)
  • PROPOSED DEVELOPMENT AREA
  • PROPOSED RIGHT-OF-WAY (TO BE DEDICATED TO EAST GOSHEN TOWNSHIP)
  • 15% - 25% SLOPES
  • 25%+ SLOPES

Plan labels: MILLSTONE CIRCLE; INFILTRATION BASIN #1; INFILTRATION BASIN #2; SANITARY SEWER EASEMENT; STORM SEWER EASEMENT; 100; 101; lots 1 to 14.

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN OPEN SPACE MANAGEMENT PLAN

Revision 7/25/23: REVISED PER TOWNSHIP REVIEW LETTERS
Client: GROVE MEADOW DEVELOPERS LLC
Location: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
Date: APRIL 20, 2023
Drawn: M.D. HARTMAN
Checked: M.D. HARTMAN
Scale: 1" = 50'
Sheet 4 OF 20
22-001-F-D-4.0
Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242
Seal: Commonwealth of Pennsylvania, Professional Engineer, Michael Duain Hartman
Graphic scale: 50, 0, 50, 100, 150

[Engineering plan sheet: utility plan for Millstone Meadows showing Millstone Circle cul-de-sac with numbered lots, Infiltration Basin #1 and Infiltration Basin #2, Hershey Mill Road and Tanglewood Drive, with proposed sanitary sewer, storm sewer, water lines and boundary dimensions.]

GENERAL CONSTRUCTION NOTES:

  1. AREAS WHICH ARE TO BE FILLED SHALL BE COMPACTED TO A MINIMUM DENSITY OF 95% MAXIMUM DENSITY AS DETERMINED BY THE MODIFIED PROCTOR TEST (ASTM D-698) IN THE BUILDING, PAVED AND SIDEWALK AREAS, AND 90% IN OTHER AREAS.
  2. UNDERGROUND FACILITIES HAVE BEEN PLOTTED FROM AVAILABLE SURVEYS AND PLANS OF OTHERS AND THEREFORE THEIR ELEVATIONS AND LOCATION MUST BE CONSIDERED AS APPROXIMATE ONLY. THE VERIFICATION OF EACH FACILITY SHOWN OR NOT SHOWN, SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR.
  3. CONTRACTOR TO VERIFY LOCATION AND FLOW OF EXISTING UTILITIES PRIOR TO INSTALLATION OF PLUMBING. ALL SERVICES TO BE CONNECTED IN ACCORDANCE WITH LOCAL CODES AND/OR UTILITY COMPANIES REQUIREMENT.
  4. PAVEMENT SHALL BE CONSTRUCTED IN ACCORDANCE WITH PENNDOT SPECIFICATIONS PUBLICATION 408, LATEST EDITION.
  5. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO NOTIFY THE LOCAL AUTHORITY OR GOVERNING AGENCY OF THE BEGINNING DATE OF CONSTRUCTION AND IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO SEE THAT NO WORK IS DONE WITHOUT THE PROPER INSPECTIONS BY LOCAL AUTHORITY OR GOVERNING AGENCY.
  6. CONTRACTOR TO NOTIFY ENGINEER AS SOON AS POSSIBLE IF CONDITIONS ON GROUND DIFFER FROM THOSE SHOWN ON THE PLANS.
  7. ALL AREAS OTHER THAN PAVED AREAS SHALL HAVE A MINIMUM DEPTH OF SIX INCHES (6") OF TOPSOIL PRIOR TO SEEDING. THE SURFACE SHALL BE SCARIFIED AND CLEARED OF ALL TRASH DEBRIS, ROOTS AND OTHER OBJECTS THAT WOULD INTERFERE WITH PLANTINGS, FERTILIZING OR MAINTENANCE OPERATIONS.
  8. SEEDING AND MULCHING SHALL BE IN ACCORDANCE WITH PENNDOT PUBLICATION 408.
  9. ALL SPOT ELEVATIONS SHOWN AT THE CURBLINE ARE THE BOTTOM OF CURB, UNLESS OTHERWISE NOTED.

UTILITY NOTES:

  1. THIS PLAN PROPOSES PUBLIC WATER SUPPLY AND PUBLIC SEWER. PUBLIC WATER WILL BE PROVIDED BY AQUA PENNSYLVANIA.
  2. ALL WATER MAINS SHALL MEET THE REQUIREMENTS OF AND BE INSTALLED IN ACCORDANCE WITH THE SPECIFICATIONS, STANDARDS AND DETAILS OF AQUA PENNSYLVANIA.
  3. WATER SUPPLY: ALL WATER SERVICES, INCLUDING DOMESTIC AND FIRE PROTECTION, SHALL MEET THE REQUIREMENTS OF AND BE INSTALLED IN ACCORDANCE WITH THE SPECIFICATIONS, STANDARDS AND DETAILS OF EAST GOSHEN TOWNSHIP. SHOP DRAWINGS AND/OR CATALOG CUTS FOR ALL PROPOSED MATERIALS SHALL BE SUBMITTED TO EAST GOSHEN TOWNSHIP AS PART OF THE APPLICATION FOR A PLUMBING PERMIT.
  4. SANITARY SEWERAGE: ALL SANITARY SEWER MAINS SHALL MEET THE REQUIREMENTS OF AND BE INSTALLED IN ACCORDANCE WITH THE SPECIFICATIONS, STANDARDS AND DETAILS OF THE EAST GOSHEN TOWNSHIP.
  5. SANITARY SEWERAGE: ALL SEWER LATERALS SHALL MEET THE REQUIREMENTS OF AND BE INSTALLED IN ACCORDANCE WITH THE SPECIFICATIONS, STANDARDS AND DETAILS OF EAST GOSHEN TOWNSHIP. SHOP DRAWINGS AND/OR CATALOG CUTS FOR ALL PROPOSED MATERIALS SHALL BE SUBMITTED TO EAST GOSHEN TOWNSHIP.
  6. THE SANITARY SEWER SHALL BE INSTALLED AT LEAST 10 FEET HORIZONTALLY AND AT LEAST 18 INCHES VERTICALLY FROM OTHER UTILITIES.
  7. THE SANITARY SEWER MAINS AND LATERALS SHALL BE BURIED A MINIMUM OF 4 FEET DEEP.
  8. IT IS NOT INTENDED TO PROVIDE SANITARY SEWER SERVICE TO THE BASEMENTS OF THE PROPOSED DWELLINGS.
  9. OTHER UTILITIES: ALL OTHER UTILITIES (ELECTRIC, COMMUNICATIONS, GAS, ETC.) SHALL BE INSTALLED IN ACCORDANCE WITH THE UTILITY COMPANY'S REQUIREMENTS AND SHALL BE INSTALLED AS TO NOT CONFLICT WITH THE WATER, SANITARY SEWER AND/OR STORM FACILITIES PROPOSED AS PART OF THIS PLANS.
  10. BACKFILL OF ALL UTILITY TRENCHES WITHIN EXISTING AND/OR PROPOSED RIGHT-OF-WAY SHALL BE DONE IN ACCORDANCE WITH THE SPECIFICATIONS, STANDARDS AND DETAILS OF EAST GOSHEN AND BE SUBJECT TO THE APPROVAL OF EAST GOSHEN TOWNSHIP OR THEIR DESIGNEE.
  11. DURING CONSTRUCTION OF SEWER PROJECTS, THE CONTRACTOR SHALL BE PROHIBITED FROM UNNECESSARILY DISTURBING OR UPROOTING TREES AND VEGETATION ALONG THE STREAMBANK AND IN THE VICINITY OF THE STREAM, DUMPING OF SOIL AND DEBRIS INTO STREAMS AND/OR ON BANKS OF STREAMS, CHANGING THE COURSE OF THE STREAM WITHOUT AN ENCROACHMENT PERMIT, LEAVING COFFERDAMS IN STREAMS, LEAVING TEMPORARY STREAM CROSSINGS FOR EQUIPMENT, OPERATING EQUIPMENT IN THE STREAM, OR PUMPING SILT-LADEN WATER INTO THE STREAM.

LEGEND

  • EXISTING CURB
  • PROPOSED CURB
  • EXISTING CONTOURS
  • PROPOSED CONTOURS
  • EXISTING SPOT ELEVATION
  • PROPOSED SPOT ELEVATION
  • SOIL LINE
  • EXISTING STREET SIGN
  • EXISTING FEATURES ARE LABELED WITH SLANTED TEXT
  • TO BE REMOVED
  • EXISTING DECIDUOUS TREE
  • PROPOSED SANITARY SEWER & MANHOLE
  • PROPOSED STORM SEWER & CATCH BASIN
  • EXISTING WATER LINE & VALVE
  • PROPOSED WATER LINE & VALVE
  • PROPOSED FIRE HYDRANT
  • PROPOSED GRINDER PUMP
  • PROPOSED WATER LATERAL
  • PROPOSED CURB TAPER

Plan labels

  • INFILTRATION BASIN #1
  • INFILTRATION BASIN #2
  • MILLSTONE CIRCLE
  • HERSHEY MILL ROAD
  • TANGLEWOOD DRIVE
  • GRAPHIC SCALE 1"=50'

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN UTILITY PLAN

CLIENT: GROVE MEADOW DEVELOPERS LLC
LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
DATE: APRIL 20, 2023
DRAWN: M.D. HARTMAN
CHECKED: M.D. HARTMAN
SCALE: 1" = 50'
SHEET 5 OF 20
22-001-F-D-5.0
Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242
[Seal: Commonwealth of Pennsylvania, Professional Engineer, Michael Duain Hartman]

[Grading plan drawing: contour map of the Millstone Meadows site with numbered house lots, a large central oval basin, Infiltration Basin #1 and Infiltration Basin #2, Millstone Circle, Hershey Mill Road and Tanglewood Drive.]

GENERAL CONSTRUCTION NOTES:

  1. AREAS WHICH ARE TO BE FILLED SHALL BE COMPACTED TO A MINIMUM DENSITY OF 95% MAXIMUM DENSITY AS DETERMINED BY THE MODIFIED PROCTOR TEST (ASTM D-698) IN THE BUILDING, PAVED AND SIDEWALK AREAS, AND 90% IN OTHER AREAS.
  2. UNDERGROUND FACILITIES HAVE BEEN PLOTTED FROM AVAILABLE SURVEYS AND PLANS OF OTHERS AND THEREFORE THEIR ELEVATIONS AND LOCATION MUST BE CONSIDERED AS APPROXIMATE ONLY. THE VERIFICATION OF EACH FACILITY SHOWN OR NOT SHOWN, SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR.
  3. CONTRACTOR TO VERIFY LOCATION AND FLOW OF EXISTING UTILITIES PRIOR TO INSTALLATION OF PLUMBING. ALL SERVICES TO BE CONNECTED IN ACCORDANCE WITH LOCAL CODES AND/OR UTILITY COMPANIES REQUIREMENTS.
  4. PAVEMENT SHALL BE CONSTRUCTED IN ACCORDANCE WITH PENNDOT SPECIFICATIONS PUBLICATION 408, LATEST EDITION.
  5. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO NOTIFY THE LOCAL AUTHORITY OR GOVERNING AGENCY OF THE BEGINNING DATE OF CONSTRUCTION AND IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO SEE THAT NO WORK IS DONE WITHOUT THE PROPER INSPECTIONS BY LOCAL AUTHORITY OR GOVERNING AGENCY.
  6. CONTRACTOR TO NOTIFY ENGINEER AS SOON AS POSSIBLE IF CONDITIONS ON GROUND DIFFER FROM THOSE SHOWN ON THE PLANS.
  7. ALL AREAS OTHER THAN PAVED AREAS SHALL HAVE A MINIMUM DEPTH OF SIX INCHES (6") OF TOPSOIL PRIOR TO SEEDING. THE SURFACE SHALL BE SCARIFIED AND CLEARED OF ALL TRASH DEBRIS, ROOTS AND OTHER OBJECTS THAT WOULD INTERFERE WITH PLANTINGS, FERTILIZING OR MAINTENANCE OPERATIONS.
  8. SEEDING AND MULCHING SHALL BE IN ACCORDANCE WITH PENNDOT PUBLICATION 408.
  9. ALL SPOT ELEVATIONS SHOWN AT THE CURBLINE ARE THE BOTTOM OF CURB, UNLESS OTHERWISE NOTED.

CONSTRUCTION INSPECTION SCHEDULE:

INSPECTIONS SHALL BE REQUIRED AS FOLLOWS:

  1. AT THE COMPLETION OF PRELIMINARY SITE PREPARATION.
  2. AT THE COMPLETION OF ROUGH GRADING, BUT PRIOR TO PLACEMENT OF TOPSOIL.
  3. DURING THE CONSTRUCTION OF PERMANENT STORMWATER FACILITIES, OR AS DEEMED NECESSARY BY THE MUNICIPAL ENGINEER.
  4. UPON COMPLETION OF PERMANENT STORMWATER FACILITIES.
  5. UPON COMPLETION OF FINAL GRADING AND PERMANENT VEGETATIVE CONTROLS.

LEGEND

  • EXISTING CURB
  • PROPOSED CURB
  • EXISTING CONTOURS
  • PROPOSED CONTOURS
  • EXISTING SPOT ELEVATION
  • PROPOSED SPOT ELEVATION
  • SOIL LINE
  • EXISTING STREET SIGN
  • EXISTING FEATURES ARE LABELED WITH SLANTED TEXT
  • TO BE REMOVED
  • EXISTING DECIDUOUS TREE
  • PROPOSED SANITARY SEWER & MANHOLE
  • PROPOSED STORM SEWER & CATCH BASIN
  • EXISTING WATER LINE & VALVE
  • PROPOSED WATER LINE & VALVE
  • PROPOSED FIRE HYDRANT
  • PROPOSED GRINDER PUMP
  • PROPOSED WATER LATERAL
  • PROPOSED CURB TAPER

[Professional engineer seal: Michael Duain Hartman, Commonwealth of Pennsylvania, Registered Professional Engineer.]

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN GRADING PLAN

CLIENT: GROVE MEADOW DEVELOPERS LLC
LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
DATE: APRIL 20, 2023
DRAWN: M.D. HARTMAN
CHECKED: M.D. HARTMAN
SCALE: 1" = 50'
SHEET 6 OF 20
22-001-F-D-6.0
dh Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242

Revision block: 7/25/23, REVISED PER TOWNSHIP REVIEW LETTERS.

[Engineering plan sheet showing proposed street tree plantings along Millstone Circle, perimeter evergreen buffer plantings along tract boundaries, reforestation areas, and conservation seed areas.]

PLANT SCHEDULE

QUANTITY SYMBOL BOTANICAL NAME COMMON NAME COMMENTS
STREET TREES - DECIDUOUS TREES
17ARACER RUBRUMRED MAPLE3-3.5" CAL., 12-14' HT., B&B
6BNBETULA NIGRARIVER BIRCH3-3.5" CAL., 12-14' HT., B&B
11GTGLEDITSIA TRIACANTHOS F. INERMISTHORNLESS HONEY LOCUST3-3.5" CAL., 12-14' HT., B&B
15NSNYSSA SYLVATICABLACK GUM3-3.5" CAL., 12-14' HT., B&B
15PAPLATANUS x ACERIFOLIALONDON PLANETREE3-3.5" CAL., 12-14' HT., B&B
10TATILIA AMERICANAAMERICAN LINDEN3-3.5" CAL., 12-14' HT., B&B
74TOTAL
PERIMETER BUFFER - EVERGREEN TREES
22CDCEDRUS DEODARDEODAR CEDAR6-8' HT., 4-5' SP., B&B
17PSPINUS STROBUSEASTERN WHITE PINE6-8' HT., 4-5' SP., B&B
39TOTAL
REFORESTATION AREA - DECIDUOUS TREES
75CARYA OVATASHAGBARK HICKORY#3 CONTAINER
75CERCIS CANADENSISEASTERN REDBUD#5 CONTAINER
75CORNUS FLORIDAFLOWERING DOGWOOD#5 CONTAINER
75LIRIODENDRON TULIPIFERATULIP POPLAR#5 CONTAINER
75SASSAFRAS ALBIDUMSASSAFRAS#2 CONTAINER
375TOTAL

TREE PLANTING SUMMARY:

STREET TREE REQUIREMENTS

SECTION 205-62: STREET TREES SHALL BE PROVIDED AT A RATIO OF AT LEAST ONE TREE PER 40 LINEAR FEET, OR FRACTION THEREOF, OF RIGHT-OF-WAY LINE.

RIGHT-OF-WAY LENGTH = 2,918'
REQUIRED TREES = 73
PROVIDED TREES = 74

LANDSCAPING NOTES:

THE PERIMETER OF THE PROPERTY SHALL CONTAIN A TRADITIONAL POST-AND-RAIL OR EQUIVALENT FENCE THAT REUSES THE EXISTING CONCRETE POSTS, WHERE POSSIBLE.

LEGEND

  • EXISTING CURB
  • PROPOSED CURB
  • EXISTING CONTOURS
  • PROPOSED CONTOURS
  • SOIL LINE
  • EXISTING STREET SIGN
  • EXISTING FEATURES ARE LABELED WITH SLANTED TEXT
  • EXISTING DECIDUOUS TREE
  • PROPOSED DECIDUOUS TREE
  • PROPOSED EVERGREEN TREE
  • BIORETENTION AREAS: ERNST CONSERVATION SEEDS NATIVE UPLAND WILDLIFE FORAGE & COVER MEADOW MIX
  • RE-FORESTATION AREA
  • RIPARIAN BUFFER AREA: SEE RIPARIAN BUFFER MANAGEMENT PLAN FOR PLANTING SCHEDULE AND NOTES

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN LANDSCAPING PLAN

CLIENT: GROVE MEADOW DEVELOPERS LLC
LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
DATE: APRIL 20, 2023
DRAWN: M.D. HARTMAN
CHECKED: M.D. HARTMAN
SCALE: 1" = 50'
SHEET 7 OF 20
22-001-F-D-7.1
DH Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242

Note: some text on this page could not be read reliably. Please see the original PDF for this page.

[Engineering drawing sheet: three columns of small-print landscaping specifications and two planting details on the right, printed in landscape orientation. Body text is too small to read reliably.]

GENERAL PLANTING: MAINTENANCE AND OPERATION

[illegible: columns of specification text with headings including SUBMITTALS, QUALITY ASSURANCE, DELIVERY, STORAGE, AND HANDLING, PROJECT CONDITIONS, WARRANTIES, MAINTENANCE, PRODUCTS, SEEDING, HYDROSEEDING, SEED PROTECTION, SPECIFICATIONS, PLANTS, GRASS MATERIALS, EXECUTION, PLANTING TREES AND SHRUBS, and GENERAL NOTE.]

SPLIT RAIL FENCE DETAIL

[Drawing: elevation of a split rail fence with posts and rails.]

  • PRESSURE TREATED PINE POST OR POLYMER EQUIVALENT 4'-0" ABOVE GRADE MIN.
  • 6'-0" PRESSURE TREATED POPLAR RAILS OR POLYMER EQUIVALENT
  • 8'-0" O.C.
  • 2'-0"

DECIDUOUS TREE PLANTING DETAIL

[Drawing: cross-section of a deciduous tree with root ball, stakes and mulch; labels are too small to read reliably.]

EVERGREEN TREE PLANTING DETAIL

[Drawing: cross-section of an evergreen tree with root ball, stakes and wires; labels are too small to read reliably.]

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN
LANDSCAPING DETAILS AND NOTES

CLIENT: GROVE MEADOW DEVELOPERS LLC
LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
DATE: APRIL 20, 2023
Drawn: M.D. HARTMAN. Checked: M.D. HARTMAN. Scale: 1" = 50'. Sheet 8 OF 20. 22-001-F-D-7.2

Company block: 2815 Penn Avenue, West Lawn, PA, 610-927-4242

Engineering drawing sheet showing vertical alignment profiles for Millstone Circle (Loop), Offsite Sanitary Sewer, OS-2 to EW-1, and OS-1 to I-4.

STORM AND SANITARY SEWER NOTES:

  1. STORM SEWERS AND SANITARY SEWERS SHALL BE CONSTRUCTED IN ACCORDANCE WITH ALL APPLICABLE MUNICIPAL AND AUTHORITY DETAILS AND SPECIFICATIONS.
  2. GRATE ELEVATIONS FOR INLETS ALONG CURB ARE COMPUTED TO THE CENTER OF THE INLET AT THE GUTTERLINE.
  3. GRATE ELEVATIONS FOR INLETS IN NON-CURBED AREAS ARE COMPUTED TO THE CENTER OF THE INLET IN BOTH DIMENSIONS.
  4. SANITARY SEWER AND STORM SEWER MANHOLE RIM ELEVATIONS ARE COMPUTED TO CENTER OF THE LID.
  5. PROTECTION OF PIPES - THE CONTRACTOR MUST PROVIDE AND MAINTAIN A MINIMUM OF 18" OF COVER OVER ALL STORM SEWER AND SANITARY SEWER PIPES DURING CONSTRUCTION STAGES UNTIL THE BINDER PAVING COURSE IS PLACED.
  6. DEPTH OF STORM SEWERS - ALL STORM SEWER PIPE MUST BE PLACED AT A SUFFICIENT DEPTH TO ALLOW FOR THE FULL DEPTH OF PAVING, INCLUDING THE BASE COURSE, TO BE PLACED ABOVE THE TOP OF PIPE.

MILLSTONE CIRLE (LOOP)

Profile drawing from station 0+00 to 9+50 showing existing ground, proposed road profile, vertical curves (100.00' VC, 335.00' VC, 200.00' VC), lot sewer laterals, 8" SDR-26 sewer, and storm sewer inlets and manholes with their elevations.

OFFSITE SANITARY SEWER

Profile drawing from station 0+00 to 8+00 showing existing and proposed ground and 8" SDR-26 sewer main between manholes MH1, MH2 and MH3 and the existing manhole.

NOTE: SANITARY SEWER MANHOLES MH1, MH2 AND MH3 ARE TO BE PROVIDED WITH WATERTIGHT LIDS.

NOTE: THE SANITARY SEWER MAIN BETWEEN MANHOLES MH2 AND MH3 IS TO BE ENCASED IN CONCRETE.

OS-2 - EW-1

Profile drawing from station 0+00 to 3+00 of storm sewer from structure OS-2 to endwall EW-1.

OS-1 - I-4

Profile drawing from station 0+00 to 2+00 of storm sewer from structure OS-1 to inlet I-4.

[Seal: Commonwealth of Pennsylvania, Professional Engineer, Michael Duain Hartman]

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN PROFILES

CLIENT: GROVE MEADOW DEVELOPERS LLC
LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
DATE: APRIL 20, 2023
DRAWN: M.D. HARTMAN
CHECKED: M.D. HARTMAN
SCALE: 1" = 50'
SHEET 9 OF 20
22-001-F-D-8.1
dh Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242
Revision 1, 7/25/23: REVISED PER TOWNSHIP REVIEW LETTERS

[Engineering profile sheet with four profile drawings: MILLSTONE CIRLCE (MAIN DRIVE), I-12 - ES-2, I-10 - ES-1 and JB-7 - JB-5, each with stationing, grid and pipe labels (24" SLCPP, 18" SLCPP, 15" SLCPP, 8" PVC, 8" SDR-26). Most pipe and structure labels are too small to read reliably. A graphic scale reads 1"=50'.]

MILLSTONE CIRLCE (MAIN DRIVE)

I-12 - ES-2

I-10 - ES-1

JB-7 - JB-5

[Seal: Commonwealth of Pennsylvania Professional Engineer, Michael Duain Hartman]

Revision: 1, 7/25/23, REVISED PER TOWNSHIP REVIEW LETTERS

"MILLSTONE MEADOWS"
PRELIMINARY/FINAL PLAN
PROFILES

CLIENT: GROVE MEADOW DEVELOPERS LLC
LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
DATE: APRIL 20, 2023
DRAWN BY: M.D. HARTMAN
CHECKED BY: M.D. HARTMAN
SCALE: 1" = 50'
SHEET 10 OF 20
FILE NO.: 22-001-F-D-8.2

[Logo: dh Enterprises] 2815 PENN AVENUE, WEST LAWN, PA, 610-927-4242

[Engineering plan sheet showing erosion and sediment pollution control measures, including limit of disturbance, compost filter socks, rock construction entrance, sediment basin #1, temporary riser and skimmer, and topsoil stockpile.]

ONECALL NOTES

[Seal: Pennsylvania One Call System, Inc. 1-800-242-1776 Stop-Call Before You Dig!]

PENNSYLVANIA ACT 287, AS AMENDED BY ACT 121 REQUIRES NOTIFICATION OF EXCAVATORS, DESIGNERS, OR ANY PERSON PREPARING TO DISTURB THE EARTH'S SURFACE ANYWHERE IN THE COMMONWEALTH.

ACT 287 UNDERGROUND UTILITY PROTECTION ACT, AS AMENDED BY ACT 121

ACT 287 UNDERGROUND UTILITY PROTECTION ACT, AS AMENDED BY:
ACT 172 OF 1986, ACT 38 OF 1991, ACT 187 OF 1996,
ACT 199 OF 2004, ACT 181 OF 2006, ACT 121 OF 2008

PA ONE CALL SYSTEM INFORMATION:
PENNSYLVANIA ACT 287, AS AMENDED, REQUIRES THREE (3) WORKING DAYS NOTICE FOR CONSTRUCTION PHASE AND FIVE (5) WORKING DAYS NOTICE IN DESIGN STAGE.
PA ONE CALL PHONE NUMBER: 1-800-242-1776

ONE CALL SYSTEM SERIAL NUMBER: 20223113412
DATE: 11/07/22
NOTIFICATION BY NAVE NEWELL, INC.

LIST OF RESPONDERS: AQUA PENNSYLVANIA INC, COMCAST CABLE COMMUNICATIONS INC, EAST GOSHEN TOWNSHIP, PECO ENERGY, TEXAS EASTERN TRANSMISSION LP, VERIZON PENNSYLVANIA LLC

PROJECT AREAS

  • PROJECT SITE BOUNDARY AREA = 16.00 ACRES
  • LIMIT OF DISTURBANCE AREA = 8.83 ACRES

U.S. FISH AND WILDLIFE SERVICE AVOIDANCE MEASURE:

DO NOT CONDUCT THIS PROJECT/ACTIVITY WITHIN 50 FEET OF ANY STREAMS, RIVERS, CREEKS, OR TRIBUTARIES. THIS INCLUDES BOTH PERENNIAL AND INTERMITTENT WATERWAYS.

[Drawing: Vicinity Map, Scale: 1"=800', showing project location.]

LEGEND

  • EXISTING CURB
  • PROPOSED CURB
  • EXISTING CONTOURS
  • PROPOSED CONTOURS
  • EXISTING SPOT ELEVATION
  • PROPOSED SPOT ELEVATION
  • SOIL LINE
  • EXISTING STREET SIGN
  • EXISTING FEATURES ARE LABELED WITH SLANTED TEXT
  • TO BE REMOVED
  • EXISTING DECIDUOUS TREE
  • PROPOSED SANITARY SEWER & MANHOLE
  • PROPOSED STORM SEWER & CATCH BASIN
  • EXISTING WATER LINE & VALVE
  • PROPOSED WATER LINE & VALVE
  • PROPOSED FIRE HYDRANT
  • PROPOSED GRINDER PUMP
  • PROPOSED WATER LATERAL
  • PROPOSED CURB TAPER

E&SPC LEGEND

  • INLET FILTER PROTECTION
  • FILTREXX SILTSOXX (12" SILTSOXX UNLESS SPECIFIED) (INDIVIDUAL LOT CONTROL)
  • ROCK CONSTRUCTION ENTRANCE
  • MOUNTABLE STONE FILTER BERM
  • ROCK CONSTRUCTION ENTRANCE (INDIVIDUAL LOT CONTROL)
  • TOPSOIL STOCKPILE WITH 12" SILTSOXX (UNLESS SPECIFIED) (INDIVIDUAL LOT CONTROL)
  • CONCRETE WASH AREA (CWA)
  • EROSION CONTROL BLANKET NAG S75 (or approved equal)
  • LIMIT OF DISTURBANCE
  • PROJECT SITE BOUNDARY
  • ORANGE CONSTRUCTION SAFETY FENCING
  • RIPARIAN BUFFER - 150'

Labels on the plan: SEDIMENT BASIN #1, TEMPORARY RISER WITH SKIMMER, INFILTRATION BASIN #1, TOPSOIL STOCKPILE, CWA, LIMIT OF DISTURBANCE, PROJECT SITE BOUNDARY, HERSHEY MILL ROAD, TANGLEWOOD DRIVE.

[Seal: Commonwealth of Pennsylvania Registered Professional Engineer Michael Duain Hartman]

PRELIMINARY/FINAL SUBDIVISION AND LAND DEVELOPMENT PLANS
FOR
"MILLSTONE MEADOWS"
EROSION AND SEDIMENT CONTROL PLAN

CLIENT: GROVE MEADOW DEVELOPERS LLC
LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
DATE: APRIL 20, 2023
DRAWN: M.D. HARTMAN
CHECKED: M.D. HARTMAN
SCALE: 1" = 50'
SHEET 11 OF 20
22-001-F-D-9.1
Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN - EROSION AND SEDIMENT CONTROL NOTES

Client: Grove Meadow Developers LLC | Location: East Goshen Township, Chester County, Pennsylvania | Date: April 20, 2023 | Drawn By / Designed/Checked: M.D. Hartman | Scale: N.T.S. | Sheet: 12 of 20 | File No.: 22-001-F-D-9.2 | Engineer: Michael Duain Hartman, P.E., dh Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242

CONSTRUCTION SEQUENCE

PRE-CONSTRUCTION ACTIVITIES

  1. ALL EARTH DISTURBANCE ACTIVITIES SHALL PROCEED IN ACCORDANCE WITH THE FOLLOWING SEQUENCE. EACH STAGE SHALL BE COMPLETED IN COMPLIANCE WITH CHAPTER 102 REGULATIONS BEFORE ANY FOLLOWING STAGE IS INITIATED. CLEARING AND GRUBBING SHALL BE LIMITED ONLY TO THOSE AREAS DESCRIBED IN EACH STAGE.
  2. AT LEAST 7 DAYS BEFORE STARTING ANY EARTH DISTURBANCE ACTIVITIES, THE OPERATOR SHALL INVITE ALL CONTRACTORS INVOLVED IN THOSE ACTIVITIES, THE LANDOWNER, ALL APPROPRIATE MUNICIPAL OFFICIALS, THE E&S CONTROL PLAN PREPARER, AND A REPRESENTATIVE OF THE CHESTER COUNTY CONSERVATION DISTRICT TO SCHEDULE AN ON-SITE PRE-CONSTRUCTION MEETING. IN ADDITION, AT LEAST 3 DAYS BEFORE STARTING ANY EARTH DISTURBANCE ACTIVITIES, ALL CONTRACTORS INVOLVED IN THOSE ACTIVITIES SHALL NOTIFY PENNSYLVANIA ONE CALL SYSTEM INC. AT 1-800-242-1776 FOR BURIED UTILITIES LOCATION.
  3. BEFORE INITIATING ANY REVISION TO THE APPROVED EROSION AND SEDIMENT CONTROL PLAN OR DRAINAGE/GRADING PLANS WHICH MAY AFFECT THE EFFECTIVENESS OF THE APPROVED E&S CONTROL PLAN, THE OPERATOR MUST RECEIVE APPROVAL OF THE REVISIONS FROM THE CHESTER COUNTY CONSERVATION DISTRICT. DETERMINATIONS WILL REMAIN THAT THE APPROVED EROSION AND SEDIMENT CONTROL PLAN IS PROPERLY AND COMPLETELY IMPLEMENTED IN ACCORDANCE WITH THE APPROVED PLAN AND PERMIT CONDITIONS. SHOULD AN EVALUATION SHOW THAT THIS IS NOT THE CASE, THE OPERATOR SHALL IMPLEMENT APPROPRIATE BEST MANAGEMENT PRACTICES TO ELIMINATE POTENTIAL FOR ACCELERATED EROSION AND SEDIMENTATION IMMEDIATELY.
  4. THE ANTICIPATED WASTES ARE GENERAL CONSTRUCTION WASTES. THE OPERATOR SHALL REMOVE FROM THE SITE, RECYCLE OR DISPOSE OF ALL BUILDING MATERIALS AND WASTES IN ACCORDANCE WITH THE DEPARTMENT'S SOLID WASTE MANAGEMENT REGULATIONS AT 25 PA. CODE 260.1 ET SEQ., 271.1 ET SEQ., AND 287.1 ET SEQ. THE CONTRACTOR SHALL NOT ILLEGALLY BURY, DUMP, OR DISCHARGE ANY BUILDING MATERIAL OR WASTES AT THE SITE.
  5. A COPY OF THE APPROVED EROSION AND SEDIMENT CONTROL PLAN MUST BE AVAILABLE AT THE PROJECT SITE AT ALL TIMES. EARTH DISTURBANCE MAY NOT COMMENCE UNTIL THE E&S CONTROL PLAN HAS BEEN PREPARED, AND HAS BEEN APPROVED BY THE CHESTER COUNTY CONSERVATION DISTRICT BECAUSE IT IS PREPARED IN ACCORDANCE WITH CHAPTER 102 RULES & REGULATIONS, AND IS BEING IMPLEMENTED AND MAINTAINED FOR THE DURATION OF THE PROJECT UNTIL SITE STABILIZATION IS ACHIEVED.

MAIN SITE DEVELOPMENT

  1. INSTALL ROCK CONSTRUCTION ENTRANCE AS SHOWN ON THE PLAN.
  2. FIELD DELINEATE THE LIMIT OF DISTURBANCE (LOD) PRIOR TO DISTURBANCE ACTIVITIES WITH TREE PROTECTION FENCING AND/OR HIGH VISIBILITY ORANGE CONSTRUCTION SAFETY FENCING IN THE LOCATIONS AS SHOWN ON THE E&S CONTROL PLAN.
  3. STREAM CROSSING REMOVAL AND INSTALLATION OF CULVERT SHALL BE IN ACCORDANCE WITH DEP PERMIT REQUIREMENTS.
  4. THE CONVERSION OF THE RIPARIAN BUFFER AREA TO A FORESTED RIPARIAN BUFFER AREA MAY TAKE PLACE ANY TIME IN ACCORDANCE WITH THE SEQUENCES SHOWN ON THE FORESTED RIPARIAN BUFFER MANAGEMENT PLANS.
  5. INSTALL PERIMETER BERMS, IMMEDIATELY STABILIZE AND INSTALL EROSION CONTROL BLANKET.
  6. INITIATE INSTALLATION OF THE SEDIMENT BASINS BY CONSTRUCTING EMBANKMENTS, EMERGENCY SPILLWAYS, SKIMMER DEWATERING DEVICES, BAFFLES, CLEANOUT STAKES, DEWATERING FACILITIES AND PERMANENT OUTLET STRUCTURE WITH TRASH RACK ON TOP.
  7. GRADE AREA BEHIND BERM AS SHOWN FOR THE SEDIMENT BASIN ON THE E&S CONTROL PLAN AND IMMEDIATELY STABILIZE EMBANKMENT SLOPES AND TOP WITH EROSION CONTROL BLANKET AND SEED.
  8. CONCURRENTLY WITH STAGE 5, INSTALL THE STORM SEWER FROM I-4 TO ES-5, INCLUDING OUTLET RIP-RAP APRON.
  9. INITIATE CLEARING AND GRUBBING OF THE WOODED AREA ALONG MILLSTONE CIRCLE TO THE LIMIT OF DISTURBANCE AS SHOWN ON THE E&S PLAN.
  10. INITIATE STRIPPING AND STOCKPILING OF TOPSOIL FROM THE RIGHT-OF-WAY OF MILLSTONE CIRCLE AS WELL AS THOSE AREAS WHICH REQUIRE GRADING PRIOR TO CONSTRUCTING HOMES ON THE LOTS. NOTE: ALL RUNOFF FROM THE DISTURBED AREAS SHALL BE DIRECTED TOWARD EITHER SILT SOCK OR THE SEDIMENT BASIN. STOCKPILE HEIGHTS MUST NOT EXCEED 35'. STOCKPILE SLOPES MUST BE 2:1 OR FLATTER. SURPLUS OF TOPSOIL SHALL BE KEPT TO A MINIMUM TO PREVENT EXCESSIVE STOCKPILING OF TOPSOIL ON THE SITE.
  11. INITIATE ROUGH GRADING ACTIVITIES REQUIRED TO ACHIEVE THE PROPOSED GRADES OF THE STREET AND LOT AREAS WHICH REQUIRE EARTHWORK PRIOR TO HOME CONSTRUCTION.
  12. BEGIN INSTALLATION OF ALL UNDERGROUND UTILITIES INCLUDING SANITARY SEWER, STORM SEWER AND WATER LINE. INSTALL STONE INLET PROTECTION ON INLETS NOTED ON THE PLANS. NOTE: BERMS ARE REQUIRED FOR ALL INSTALLATIONS. EARTHEN BERMS ARE TO BE MAINTAINED UNTIL ROADWAY IS PAVED. ROAD SUBBASE IS TO BE MAINTAINED WITH STABILIZED STONE. NOTE: INLETS I-14 TO I-17 ARE TO BE BLOCKED AT THIS TIME.
  13. PLACE STONE SUBBASE ON ROADWAY SUBGRADE.
  14. BEGIN HOME CONSTRUCTION IN ACCORDANCE WITH THE INDIVIDUAL LOT CONSTRUCTION SEQUENCE. IN THE EVENT THAT HOME CONSTRUCTION IS NOT TO BEGIN IMMEDIATELY, IMPLEMENT TEMPORARY VEGETATIVE STABILIZATION ON THAT LOT.
  15. INSTALL BITUMINOUS PAVING, CURBING AND SIDEWALK ALONG ROADWAYS.
  16. COMMENCE AND COMPLETE THE PERMANENT VEGETATIVE STABILIZATION OF ALL DISTURBED AREAS WHICH ARE AT FINAL GRADE. INSTALL PROPOSED TREES AS SHOWN ON THE LANDSCAPING PLAN.
  17. UPON STABILIZATION OF ALL UP SLOPE DISTURBED AREAS TRIBUTARY TO INFILTRATION BASINS #1 AND #2, INITIATE CONVERSION OF INFILTRATION BASINS #1 AND #2 IN ACCORDANCE WITH THE INDIVIDUAL BMP CONSTRUCTION SEQUENCE AND CRITICAL STAGES OF IMPLEMENTATION PROVIDED IN THE POST-CONSTRUCTION STORMWATER MANAGEMENT PLAN DETAILS.
  18. UPON STABILIZATION OF ALL UP SLOPE DISTURBED AREAS TRIBUTARY TO INFILTRATION BASIN #2, INITIATE CONVERSION OF THE BASIN FROM A SEDIMENT BASIN TO THE PERMANENT INFILTRATION BASIN IN ACCORDANCE WITH THE INDIVIDUAL BMP CONSTRUCTION SEQUENCE AND CRITICAL STAGES OF IMPLEMENTATION PROVIDED IN THE POST-CONSTRUCTION STORMWATER MANAGEMENT PLAN AND DETAILS.
  19. UPON STABILIZATION OF ALL DISTURBED AREAS, REMOVE ALL TEMPORARY E&S PRACTICES, INCLUDING SILT SOCK, INLET PROTECTION, ROCK ENTRANCE, ETC. AN AREA SHALL BE CONSIDERED TO HAVE ACHIEVED FINAL STABILIZATION WHEN IT HAS A MINIMUM UNIFORM 70% PERENNIAL VEGETATIVE COVER OR OTHER PERMANENT NON-VEGETATIVE COVER WITH A DENSITY SUFFICIENT TO RESIST ACCELERATED SURFACE EROSION AND SUBSURFACE CHARACTERISTICS SUFFICIENT TO RESIST SLIDING AND OTHER MOVEMENTS.
  20. WITHIN 30 DAYS AFTER COMPLETION OF EARTH DISTURBANCE ACTIVITIES AUTHORIZED BY THE PERMIT, AND PERMANENT STABILIZATION HAS BEEN ACHIEVED AND E&S BMPS HAVE BEEN REMOVED, THE PERMITTEE SHALL FILE WITH THE DEPARTMENT, OR CONSERVATION DISTRICT, A NOTICE OF TERMINATION FOR THIS PERMIT.

AFTER FINAL SITE STABILIZATION HAS BEEN ACHIEVED, TEMPORARY EROSION AND SEDIMENTATION CONTROLS MUST BE REMOVED. AREAS DISTURBED DURING REMOVAL OF CONTROLS MUST BE STABILIZED IMMEDIATELY.

CONSTRUCTION SEQUENCE - INDIVIDUAL LOTS

  1. INSTALL TEMPORARY ROCK CONSTRUCTION ENTRANCE AND SILT SOCK AS SHOWN ON THE PLAN BEFORE ANY LOT EARTH DISTURBANCE BEGINS.
  2. LIMIT THE DISTURBANCE TO ONLY THE AREA REQUIRED FOR LOT IMPROVEMENTS.
  3. STRIP TOPSOIL AND STOCKPILE ON THE LOT IN DESIGNATED LOCATION. IMMEDIATELY SEED AND MULCH THE STOCKPILE.
  4. CONSTRUCT HOUSE AND OTHER LOT IMPROVEMENTS.
  5. LANDSCAPE LAWN AREAS TO FINISHED GRADE, IMMEDIATELY REPLACE TOPSOIL AND PERMANENTLY SEED AND MULCH ALL DISTURBED AREAS. INSTALL PERMANENT EROSION CONTROL BLANKET AS SHOWN ON THE PLANS FOR ALL SLOPES 3:1 AND STEEPER.
  6. REMOVE THE SILT SOCK ONLY AFTER PERMANENT GRASS COVER IS WELL ESTABLISHED ON ALL DISTURBED AREAS.

CONSTRUCTION SEQUENCE - OFFSITE UTILITIES

  1. INITIATE INSTALLATION OF UTILITY LINE. IMMEDIATELY IMPLEMENT TEMPORARY VEGETATIVE STABILIZATION. THE LENGTH OF TRENCH SHOULD BE LIMITED TO THE AMOUNT THAT CAN BE INSTALLED AND BACKFILLED IN A DAY.
  2. COMMENCE AND COMPLETE THE PERMANENT VEGETATIVE STABILIZATION OF ALL DISTURBED AREAS WHICH ARE AT FINAL GRADE.
  3. UPON STABILIZATION OF ALL DISTURBED AREAS, REMOVE ALL OTHER E&S FACILITIES AND TEMPORARY CONTROLS (SILT SOCK, INLET BMPS, ETC.). AN AREA SHALL BE CONSIDERED TO HAVE ACHIEVED FINAL STABILIZATION WHEN IT HAS A MINIMUM UNIFORM 70% PERENNIAL VEGETATIVE COVER OR OTHER PERMANENT NON-VEGETATIVE COVER WITH A DENSITY SUFFICIENT TO RESIST ACCELERATED SURFACE EROSION AND SUBSURFACE CHARACTERISTICS SUFFICIENT TO RESIST SLIDING AND OTHER MOVEMENTS.

UTILITY LINE TRENCH EXCAVATION NOTES

  1. LIMIT OPEN EXCAVATION IN UTILITY LINE INSTALLATIONS TO A DISTANCE EQUAL TO TWO TIMES THE LENGTH OF PIPE INSTALLATION THAT CAN BE COMPLETED IN ONE DAY.
  2. IMMEDIATELY IMPLEMENT CONTROLS TO DIRECT RUNOFF AWAY FROM TRENCH EXCAVATION AND STOCKPILED SOIL. SEPARATE EXCAVATED TRENCH SPOIL FROM TOPSOIL FROM CLEARING AND GRUBBING AND SITE RESTORATION AND STABILIZATION OPERATIONS.
  3. ALL SOIL EXCAVATED FROM THE TRENCH WILL BE PLACED ON THE UPHILL SIDE OF THE TRENCH.
  4. LIMIT DAILY TRENCH EXCAVATION TO THE LENGTH OF PIPE PLACEMENT, PLUG INSTALLATION AND BACKFILLING THAT CAN BE COMPLETED THE SAME DAY.
  5. WATER THAT ACCUMULATES IN THE OPEN TRENCH WILL BE COMPLETELY REMOVED BY PUMPING BEFORE PIPE PLACEMENT AND BACKFILLING OPERATIONS. WATER REMOVED FROM THE TRENCH SHALL BE PUMPED THROUGH A FILTER BAG DEVICE.
  6. ON THE DAY FOLLOWING PIPE PLACEMENT AND TRENCH BACKFILLING, THE DISTURBED AREA WILL BE GRADED TO FINAL CONTOURS AND IMMEDIATELY STABILIZED.

GENERAL NOTES

  1. ONLY LOCAL DISTURBANCE WILL BE PERMITTED TO PROVIDE ACCESS FOR E&S CONTROL INSTALLATION. PRIOR TO INITIATING ANY EARTH DISTURBANCE FOR CLEARING, GRUBBING OR GRADING FOR SITE IMPROVEMENTS, THE PERIMETER E&S CONTROLS MUST BE INSTALLED AND FUNCTIONING. AREAS TO BE STABILIZED WITH PERMANENT VEGETATION SHALL BE LIMITED TO PREVENT OVER COMPACTION OF SOILS.
  2. EROSION AND SEDIMENTATION CONTROLS MUST BE CONSTRUCTED, STABILIZED, AND FUNCTIONAL BEFORE SITE DISTURBANCE BEGINS WITHIN THE TRIBUTARY AREA TO THOSE CONTROLS.
  3. THE SIZE AND DURATION OF DISTURBANCE SHALL BE LIMITED TO THAT WHICH IS NECESSARY TO PERFORM THE WORK AS SHOWN ON THIS PLAN. STABILIZE ANY DISTURBED AREAS WHERE WORK MUST CEASE FOR FOUR (4) DAYS OR MORE.
  4. AFTER FINAL SITE STABILIZATION HAS BEEN ACHIEVED, TEMPORARY EROSION AND SEDIMENTATION CONTROLS MUST BE REMOVED. AREAS DISTURBED DURING REMOVAL OF THE BMPS MUST BE STABILIZED IMMEDIATELY.
  5. AT THE END OF EACH WORKING DAY, ANY SEDIMENT TRACKED OR DEPOSITED ONTO A PUBLIC ROADWAY MUST BE IMMEDIATELY REMOVED AND RETURNED TO THE CONSTRUCTION SITE. REMOVAL CAN BE COMPLETED THROUGH USE OF MECHANICAL OR HAND TOOLS, BUT MUST NEVER BE WASHED OFF INTO A DRAINAGE FACILITY OR WATERWAY.
  6. TOPSOIL OR OTHER EXCAVATED MATERIAL SHALL NOT BE STOCKPILED IN WETLAND AREAS, FLOODWAY OR FLOODPLAIN AREAS, DRAINAGE CHANNELS OR WITHIN 50 FEET OF STREAMS OR OTHER SURFACE WATERS.
  7. ALL PUMPED EXCAVATION WATER SHALL BE DISCHARGED THROUGH A SILT BAG FILTRATION DEVICE, LOCATED IN A WELL-VEGETATED AREA A MINIMUM OF 50 FEET FROM ANY SURFACE WATER. DISCHARGE POINTS SHOULD BE ESTABLISHED TO PROVIDE FOR MAXIMUM DISTANCE TO ACTIVE WATERWAYS.
  8. UNDERDRAIN WILL BE PROVIDED WHERE SPRINGS OR SEEPAGE ARE ENCOUNTERED IN ACCORDANCE WITH THE STANDARD AND SPECIFICATION FOR SUBSURFACE DRAIN OR OTHER APPROVED METHOD.
  9. FILL EXCHANGES FOR UTILITY LINE INSTALLATION SHALL BE LIMITED TO THE AMOUNT THAT CAN BE INSTALLED AND BACKFILLED IN A DAY. OPEN TRENCHES SHALL NOT REMAIN OPEN OVERNIGHT.
  10. SHOULD UNFORESEEN EROSION CONDITIONS DEVELOP DURING CONSTRUCTION, THE CONTRACTOR SHALL TAKE ACTION TO REMEDY SUCH CONDITIONS AND TO PREVENT DAMAGE TO ADJACENT PROPERTIES AS A RESULT OF INCREASED RUNOFF AND/OR SEDIMENT DISPLACEMENT. RESERVES OF COMMERCIAL SILT FENCE, HAY BALES AND RIP-RAP SHALL BE HELD ON PROJECTS TO DEAL IMMEDIATELY WITH EMERGENCY PROBLEMS OF EROSION.
  11. ALL EARTH DISTURBANCE ACTIVITIES MUST BE DONE IN ACCORDANCE WITH THE PROVISIONS OF THE CLEAN STREAMS LAW, ACT 394 AS AMENDED AND PA CODE TITLE 25, DEPARTMENT OF ENVIRONMENTAL PROTECTION, SUBPART C, PROTECTION OF NATURAL RESOURCES, ARTICLE II, WATER RESOURCES, CHAPTER 102 EROSION CONTROL.
  12. A COPY OF THIS EROSION AND SEDIMENTATION CONTROL REPORT AND PLANS MUST BE POSTED AT THE CONSTRUCTION SITE.
  13. BEFORE DISPOSING OF SOIL OR RECEIVING BORROW FOR THE SITE, THE OPERATOR MUST ASSURE THAT AN E&S CONTROL PLAN HAS BEEN APPROVED BY THE CONSERVATION DISTRICT AND IS BEING FULLY IMPLEMENTED FOR THE OFF-SITE DISPOSAL/BORROW AREA ACCORDING TO DEP CHAPTER 102 REGULATIONS. ALL RECYCLING OR DISPOSAL OF MATERIALS SHALL BE IN FULL COMPLIANCE WITH DEP CHAPTER 102 REGULATIONS.

NPDES PERMIT NOTES

  1. UPON REDUCTION, LOSS OR FAILURE OF ANY BMP, THE PERMITTEE AND/OR CO-PERMITTEE SHALL TAKE IMMEDIATE ACTION TO RESTORE, REPAIR OR REPLACE THE BMP OR PROVIDE AN ALTERNATIVE METHOD OF TREATMENT.
  2. WHERE E&S BMPS ARE FOUND TO BE INOPERATIVE OR INEFFECTIVE DURING AN INSPECTION, OR ANY OTHER TIME, THE PERMITTEE AND CO-PERMITTEE SHALL NOTIFY THE CHESTER COUNTY CONSERVATION DISTRICT, BY PHONE OR PERSONAL CONTACT, FOLLOWED BY THE SUBMISSION OF A WRITTEN REPORT WITHIN 5 DAYS OF THE INITIAL CONTACT.
  3. PERMITTEES REQUESTING A RENEWAL OF COVERAGE UNDER INDIVIDUAL PERMIT MUST SUBMIT TO THE DEPARTMENT A COMPLETE AND ACCEPTABLE APPLICATION AT LEAST 180 DAYS BEFORE THE EXPIRATION DATE OF THIS PERMIT, UNLESS PERMISSION FOR SUBMISSION AT A LATER DATE HAS BEEN GRANTED BY THE DEPARTMENT.
  4. PERMITTEES AND CO-PERMITTEES ARE RESPONSIBLE FOR ENSURING THAT A LICENSED PROFESSIONAL IS ON-SITE DURING CRITICAL STAGES OF IMPLEMENTATION OF THE APPROVED PCSM PLAN TO OVERSEE CONSTRUCTION OF ALL STRUCTURAL PCSM BMPS IDENTIFIED IN THE PCSM PLAN PRIOR TO THE SUBMISSION OF A NOTICE OF TERMINATION. THE LICENSED PROFESSIONAL SHALL ENSURE THAT THE BMPS ARE CONSTRUCTED AND INSTALLED IN ACCORDANCE WITH THE APPROVED PLAN.
  5. NOTICE OF TERMINATION: UPON PERMANENT STABILIZATION OF THE EARTH DISTURBANCE ACTIVITY UNDER A RESTORATION OR RECLAMATION PLAN AND PERMANENT INSTALLATION OF BMPS IN ACCORDANCE WITH AN APPROVED PLAN PREPARED AND IMPLEMENTED IN ACCORDANCE WITH PA CODE §102.4 AND §102.8 (RELATING TO E&S CONTROL REQUIREMENTS; AND PCSM REQUIREMENTS), THE PERMITTEE OR CO-PERMITTEE SHALL SUBMIT A NOTICE OF TERMINATION TO THE DEPARTMENT OR CONSERVATION DISTRICT. THE NOTICE OF TERMINATION MUST INCLUDE: 1) THE FACILITY NAME, ADDRESS AND LOCATION.; 2) THE OPERATOR NAME AND ADDRESS.; 3) THE PERMIT NUMBER.; 4) THE REASON FOR PERMIT TERMINATION.; 5) IDENTIFICATION OF THE PERSONS WHO HAVE AGREED TO AND WILL BE RESPONSIBLE FOR LONG-TERM OPERATION AND MAINTENANCE OF THE PCSM BMPS IN ACCORDANCE WITH §102.8(m) AND PROOF OF COMPLIANCE WITH §102.8(m)(2). PRIOR TO ACCEPTING THE NOT, THE DEPARTMENT AND/OR CONSERVATION DISTRICT STAFF WILL CONDUCT A FINAL INSPECTION AND APPROVE OR DENY THE NOTICE OF TERMINATION.

MAINTENANCE NOTES

  1. STOCKPILE HEIGHTS MUST NOT EXCEED 35'. STOCKPILE SLOPES MUST BE 2:1 OR FLATTER.
  2. UPON COMPLETION OF AN EARTH DISTURBANCE ACTIVITY OR ANY STAGE OR PHASE OF AN ACTIVITY, THE SITE SHALL IMMEDIATELY BE SEEDED, MULCHED OR OTHERWISE PROTECTED FROM ACCELERATED EROSION. DURING NON-GERMINATING PERIODS, MULCH MUST BE APPLIED AT THE RECOMMENDED RATES. DISTURBED AREAS WHICH ARE NOT AT FINISHED GRADE AND WHICH WILL BE RE-DISTURBED WITHIN 1 YEAR MUST BE STABILIZED IN ACCORDANCE WITH TEMPORARY VEGETATIVE STABILIZATION SPECIFICATIONS. DISTURBED AREAS WHICH ARE EITHER AT FINISHED GRADE OR WILL NOT BE RE-DISTURBED WITHIN 1 YEAR MUST BE STABILIZED IN ACCORDANCE WITH PERMANENT SEEDING SPECIFICATIONS.
  3. LIME AND FERTILIZER SHALL BE INCORPORATED INTO THE SOIL.
  4. HAY OR STRAW MULCH MUST BE APPLIED AT RATES OF AT LEAST 3.0 TONS PER ACRE.
  5. UNTIL THE SITE IS STABILIZED, ALL EROSION AND SEDIMENTATION BMPS SHALL BE MAINTAINED PROPERLY. MAINTENANCE SHALL INCLUDE INSPECTIONS OF ALL EROSION AND SEDIMENTATION CONTROL BMPS AFTER EACH RUNOFF EVENT AND ON A WEEKLY BASIS. ALL PREVENTATIVE AND REMEDIAL MAINTENANCE WORK, INCLUDING CLEAN OUT, REPAIR, REPLACEMENT, REGRADING, RESEEDING, REMULCHING AND RENETTING MUST BE PERFORMED IMMEDIATELY.
  6. AN AREA SHALL BE CONSIDERED TO HAVE ACHIEVED FINAL STABILIZATION WHEN IT HAS A MINIMUM UNIFORM 70% PERENNIAL VEGETATIVE COVER OR OTHER PERMANENT NON-VEGETATIVE COVER WITH A DENSITY SUFFICIENT TO RESIST ACCELERATED SURFACE EROSION AND SUBSURFACE CHARACTERISTICS SUFFICIENT TO RESIST SLIDING AND OTHER MOVEMENTS. WITHIN 4 DAYS AFTER EARTH DISTURBANCE ACTIVITIES CEASE, THE OPERATOR SHALL STABILIZE ANY AREAS DISTURBED BY THE ACTIVITIES. DURING NON-GERMINATING PERIODS, MULCH MUST BE APPLIED AT RECOMMENDED RATES. DISTURBED AREAS WHICH ARE NOT AT FINISHED GRADE AND WHICH WILL BE REDISTURBED WITHIN 1 YEAR MUST BE STABILIZED IN ACCORDANCE WITH THE TEMPORARY VEGETATIVE STABILIZATION SPECIFICATIONS. DISTURBED AREAS WHICH ARE AT FINISHED GRADE OR WHICH WILL NOT BE REDISTURBED WITHIN 1 YEAR MUST BE STABILIZED IN ACCORDANCE WITH THE PERMANENT VEGETATIVE STABILIZATION SPECIFICATIONS.
  7. EROSION CONTROL MATS OR MULCH CONTROL NETTING OR EROSION CONTROL BLANKETS MUST BE INSTALLED ON ALL SLOPES EQUAL TO OR GREATER THAN 3:1.
  8. UNTIL THE SITE IS STABILIZED, ALL EROSION AND SEDIMENTATION BMPS MUST BE MAINTAINED PROPERLY. MAINTENANCE MUST INCLUDE INSPECTIONS OF ALL EROSION AND SEDIMENTATION BMPS AFTER EACH RUNOFF EVENT AND ON A WEEKLY BASIS. ALL INSPECTIONS SHALL BE DOCUMENTED IN AN INSPECTION LOG KEPT FOR THIS PURPOSE. THE COMPLIANCE ACTIONS AND DATES OF IMPLEMENTATION OF THE NEEDED REPAIRS WILL BE DOCUMENTED. THE INSPECTION LOG WILL BE KEPT ON SITE AT ALL TIMES AND MADE AVAILABLE TO THE DISTRICT UPON REQUEST.
  9. ALL PREVENTATIVE AND REMEDIAL MAINTENANCE WORK, INCLUDING CLEAN OUT, REPAIR, REPLACEMENT, REGRADING, RESEEDING, REMULCHING AND RENETTING MUST BE PERFORMED IMMEDIATELY. IF EROSION AND SEDIMENTATION BMPS FAIL TO PERFORM AS EXPECTED, REPLACEMENT BMPS OR MODIFICATIONS OF THOSE INSTALLED WILL BE REQUIRED. WHERE BMPS ARE FOUND TO FAIL TO ACHIEVE EROSION OR SEDIMENT POLLUTION CONTROL, THE PERMITTEE OR CO-PERMITTEE SHALL INCLUDE THE FOLLOWING INFORMATION: a. THE LOCATION AND SEVERITY OF THE BMP'S FAILURE AND ANY POLLUTION EVENTS.; b. ALL STEPS TAKEN TO REDUCE, ELIMINATE AND PREVENT THE RECURRENCE OF THE NON-COMPLIANCE.; c. THE TIME FRAME TO CORRECT THE NON-COMPLIANCE, INCLUDING THE EXACT DATES WHEN THE ACTIVITY WILL RETURN TO COMPLIANCE. AFTER FINAL SITE STABILIZATION HAS BEEN ACHIEVED, TEMPORARY EROSION AND SEDIMENT BMPS MUST BE REMOVED. AREAS DISTURBED DURING REMOVAL OF THE BMPS MUST BE STABILIZED IMMEDIATELY.

SEEDING AND SURFACE STABILIZATION

GENERAL SEEDING AND SURFACE STABILIZATION CRITERIA

  1. DISTURBED AREAS ON WHICH ACTIVITIES HAVE BEEN COMPLETED OR WILL BE CEASED FOR MORE THAN 4 DAYS OR ANY STAGE THEREOF SHALL BE IMMEDIATELY STABILIZED WITH THE APPROPRIATE TEMPORARY OR PERMANENT SEEDING SPECIFICATIONS.
  2. DURING NON-GERMINATION PERIODS, MULCH MUST BE APPLIED AT THE RATE SPECIFIED UNDER "STABILIZATION DURING NON-GERMINATION PERIODS."
  3. DISTURBED AREAS WHICH ARE NOT FINISHED GRADE AND WILL BE REDISTURBED WITHIN 1 YEAR MAY BE SEEDED AND MULCHED WITH A QUICK GROWING TEMPORARY SEED MIXTURE AND MULCH AS SPECIFIED UNDER "TEMPORARY VEGETATIVE SURFACE STABILIZATION."
  4. DISTURBED AREAS WHICH ARE FINISHED GRADE OR WHICH WILL NOT BE REDISTURBED WITHIN ONE YEAR MUST BE SEEDED WITH A PERMANENT SEED MIXTURE AND MULCHED AS SPECIFIED UNDER "PERMANENT VEGETATIVE SURFACE STABILIZATION."
  5. DIVERSION CHANNELS, TERRACES, INTERCEPTOR CHANNELS, CHANNELS OF CONVEYANCE, SEDIMENT BASINS, SEDIMENT TRAPS AND STOCKPILES MUST BE SEEDED AND MULCHED IMMEDIATELY UPON CONSTRUCTION WITH EITHER AN APPROPRIATE SEEDING MIXTURE AND MULCH, LINED OR PROTECTED AS SHOWN ON THE PLANS AND DETAILS.
  6. TOPSOIL MUST BE APPLIED TO ALL AREAS TO BE SEEDED AT A MINIMUM DEPTH OF 4 INCHES (8 TO 12 INCHES ON COMPACTED SOILS) PRIOR TO PLACEMENT OF TOPSOIL. AREAS TO BE VEGETATED MUST HAVE A MINIMUM 4 INCHES OF TOPSOIL IN PLACE PRIOR TO SEEDING AND MULCHING, 6" YARDS.

STABILIZATION DURING NON-GERMINATION PERIODS

STRAW MULCH AT THE MINIMUM RATE OF 3 TONS/ACRE MUST BE APPLIED TO DISTURBED AREAS AT A RATE OF 3 TONS/ACRE. THE NON-GERMINATING PERIOD VARIES IN LENGTH ACCORDING TO LOCAL WEATHER CONDITIONS; IT IS GENERALLY THE PERIOD FROM OCTOBER 15 TO MARCH 15. AREAS SEEDED DURING NON-GERMINATION PERIODS MUST BE LIMED, FERTILIZED, SEEDED AND MULCHED IMMEDIATELY.

TEMPORARY VEGETATIVE SURFACE STABILIZATION

IMPLEMENT ALL STEPS OUTLINED BELOW AS REQUIRED TO ACHIEVE TEMPORARY STABILIZATION OF ALL EXPOSED AND DISTURBED SOIL AREAS AS INDICATED OR DIRECTED:

  1. TILLING - UPON SUSPENSION OF GRADING ACTIVITIES IN DISTURBED AREAS, SURFACE SOIL SHALL BE TILLED TO A DEPTH OF 2 TO 4 INCHES. TILLING MAY BE OMITTED IF SOIL IS SUFFICIENTLY LOOSE TO PERMIT SEEDING ACTIVITIES.
  2. LIME APPLICATION - PULVERIZED AGRICULTURAL LIMESTONE SHALL BE APPLIED TO THE LOOSENED SOIL AT A UNIFORM RATE OF 46 POUNDS PER 1000 SQUARE FEET. THIS RATE IS IN POUNDS OF AGRICULTURAL GRADE LIMESTONE PER 1,000 SQUARE FEET. IF THE WORK IS TEMPORARY (LESS THAN 6 MONTHS), LIME APPLICATION IS NOT REQUIRED.
  3. FERTILIZER APPLICATION - 5-5-5 FERTILIZER SHALL BE APPLIED TO THE LOOSENED SOIL AT A UNIFORM RATE OF 10 POUNDS PER 1000 SQUARE FEET.
  4. TEMPORARY SEEDING - THE FOLLOWING SEED MIXTURE SHALL BE APPLIED TO THE PREPARED SOIL SURFACE BY BROADCAST SPREADERS OR HYDRAULIC APPLICATION ACCORDING TO THE FOLLOWING RATE: SPRING OATS OR ANNUAL RYEGRASS: PURE SEED 97%, GERMINATION PERCENTAGE 85%, PURE LIVE SEED PERCENTAGE 82%, SEEDING RATE 1.0 LBS PLS PER 1000 SQUARE FEET. AFTER BROADCAST SEEDING, SEED SHALL BE COVERED BY MEANS OF LIGHT RAKING TO A DEPTH OF ONE-QUARTER INCH OF SOIL.
  5. MULCH: HAY OR STRAW MULCH SHALL BE APPLIED AT A RATE OF 3 TONS/ACRE. HAY MULCH SHOULD BE ANCHORED IMMEDIATELY AFTER APPLICATION TO PREVENT BEING WIND BLOWN. A TRACTOR-DRAWN IMPLEMENT MAY BE USED TO "CRIMP" THE HAY INTO THE SOIL. THIS METHOD IS LIMITED TO SLOPES NO STEEPER THAN 3:1. THE MACHINERY SHOULD BE OPERATED ON THE CONTOUR. CRIMPING OF HAY OR STRAW BY RUNNING OVER IT WITH TRACKED MACHINERY IS NOT RECOMMENDED.; ASPHALT, EITHER EMULSIFIED OR CUT-BACK, CONTAINING NO SOLVENTS OR OTHER DILUTING AGENTS TOXIC TO PLANT OR ANIMAL LIFE, UNIFORMLY APPLIED AT A RATE OF 35 GALLONS PER 100 SQUARE YARDS MAY BE USED TO TACK MULCH.; SYNTHETIC BINDERS (CHEMICAL BINDERS) MAY BE USED AS RECOMMENDED BY THE MANUFACTURER TO ANCHOR MULCH, PROVIDED SUFFICIENT DOCUMENTATION IS PROVIDED TO SHOW NON-TOXIC AND POLLUTION-FREE QUALITIES.; LIGHTWEIGHT PLASTIC, FIBER OR PAPER NETS MAY BE STAPLED OVER MULCH ACCORDING TO THE MANUFACTURER'S RECOMMENDATIONS.

PERMANENT VEGETATIVE SURFACE STABILIZATION

IMPLEMENT ALL STEPS OUTLINED BELOW AS REQUIRED TO ACHIEVE PERMANENT STABILIZATION OF ALL EXPOSED AND DISTURBED SOIL AREAS AS INDICATED OR DIRECTED:

  1. TILLING - UPON COMPLETION OF GRADING ACTIVITIES IN DISTURBED AREAS, SURFACE SOIL SHALL BE TILLED TO A DEPTH OF 4 INCHES. TILLING MAY BE OMITTED IF SOIL IS SUFFICIENTLY LOOSE TO PERMIT SEEDING ACTIVITIES.
  2. LIME APPLICATION - PULVERIZED AGRICULTURAL LIMESTONE SHALL BE APPLIED TO THE LOOSENED SOIL AT A UNIFORM RATE OF 184 POUNDS PER 1000 SQUARE FEET. THIS RATE IS IN POUNDS OF AGRICULTURAL GRADE LIMESTONE PER 1,000 SQUARE FEET.
  3. FERTILIZER APPLICATION - A COMPLETE COMMERCIAL FERTILIZER SHALL BE APPLIED TO THE SOIL AT THE RATE ESTABLISHED BY SOIL TESTING AS REQUIRED TO ACCOMMODATE PROPER GROWTH OF THE SEED MIXTURE. AS A MINIMUM, 10-20-20 FERTILIZER SHALL BE APPLIED AT A UNIFORM RATE OF 25 POUNDS PER 1,000 SQUARE FEET.
  4. MIXING - APPLIED LIME AND FERTILIZER SHALL BE MIXED WITH THE SOIL TO A DEPTH OF FOUR INCHES THROUGH USE OF SUITABLE EQUIPMENT.
  5. SEEDING - SEED MIXTURE SHALL BE APPLIED TO THE PREPARED SOIL SURFACE BY BROADCAST SPREADERS OR HYDRAULIC APPLICATION ACCORDING TO THE FOLLOWING RATES: INFILTRATION BASIN BOTTOMS: RETENTION BASIN FLOOR MIX: ERNMX-126. APPLY PER MANUFACTURER'S SPECIFICATIONS.; WITHIN RAIN GARDENS: RAIN GARDEN MIX: ERNMX-180. APPLY PER MANUFACTURER'S SPECIFICATIONS.; ALL OTHER DISTURBED AREAS: KENTUCKY 31 TALL FESCUE: PURE SEED 97%, GERMINATION PERCENTAGE 85%, PURE LIVE SEED PERCENTAGE 82%, SEEDING RATE 2 LBS PLS PER 1000 SQUARE FEET. REDTOP OR PERENNIAL RYEGRASS: PURE SEED 95%, GERMINATION PERCENTAGE 80%, PURE LIVE SEED PERCENTAGE 76%, SEEDING RATE 0.25 LBS PLS PER 1000 SQUARE FEET. CROWNVETCH: PURE SEED 97%, GERMINATION PERCENTAGE 76%, PURE LIVE SEED PERCENTAGE 74%, SEEDING RATE 0.25 LBS PLS PER 1000 SQUARE FEET.; KENTUCKY 31 TALL FESCUE: PURE SEED 97%, GERMINATION PERCENTAGE 85%, PURE LIVE SEED PERCENTAGE 82%, SEEDING RATE 2 LBS PLS PER 1000 SQUARE FEET.; REDTOP OR PERENNIAL RYEGRASS: PURE SEED 95%, GERMINATION PERCENTAGE 80%, PURE LIVE SEED PERCENTAGE 76%, SEEDING RATE 0.25 LBS PLS PER 1000 SQUARE FEET.; CROWNVETCH: PURE SEED 97%, GERMINATION PERCENTAGE 76%, PURE LIVE SEED PERCENTAGE 74%, SEEDING RATE 0.25 LBS PLS PER 1000 SQUARE FEET. AFTER SEEDING, SEED SHALL BE COVERED BY MEANS OF LIGHT RAKING TO A DEPTH OF ONE-QUARTER INCH OF SOIL.
  6. HAY OR STRAW MULCH SHALL BE APPLIED AT A RATE OF 3 TONS/ACRE (ANCHORED BY CRIMPING ON SLOPES NO STEEPER THAN 3:1, ASPHALT TACK AT 35 GALLONS PER 100 SQUARE YARDS, SYNTHETIC BINDERS, OR LIGHTWEIGHT PLASTIC/FIBER/PAPER NETS).

CRITICAL VEGETATIVE AREA (CVA) SURFACE STABILIZATION (ALL SLOPES GREATER THAN 3:1)

AFTER EMBANKMENT SLOPES HAVE BEEN COMPACTED AND CUT SLOPES ROUGH GRADED, AREA SHALL BE TOPSOILED AND SEEDED. THE FOLLOWING SEED MIXTURE SHALL BE APPLIED TO THE PREPARED SOIL SURFACE BY HYDRAULIC APPLICATION ACCORDING TO THE FOLLOWING SUGGESTED RATES OF APPLICATION:

  • PERENNIAL RYEGRASS: PURE SEED 98%, GERMINATION PERCENTAGE 90%, PURE LIVE SEED PERCENTAGE 88%, SEEDING RATE 1 LBS PLS PER 1000 SQUARE FEET.
  • CROWNVETCH: PURE SEED 99%, GERMINATION PERCENTAGE 70%, PURE LIVE SEED PERCENTAGE 69%, SEEDING RATE 0.5 LBS PLS PER 1000 SQUARE FEET.
  • CREEPING RED FESCUE: PURE SEED 98%, GERMINATION PERCENTAGE 85%, PURE LIVE SEED PERCENTAGE 83%, SEEDING RATE 1.5 LBS PLS PER 1000 SQUARE FEET.

AFTER SEEDING APPLICATION HAS BEEN COMPLETED, INSTALL NORTH AMERICAN GREEN EROSION CONTROL BLANKET SC-150 USING STAPLE PATTERN C.

SOILS LEGEND

  • Co - CODORUS SILT LOAM
  • Ha - HATBORO SILT LOAM
  • GgB - GLENELG SILT LOAM, 3 TO 8 PERCENT SLOPES
  • MaB - MANOR LOAM, 3 TO 8 PERCENT SLOPES
  • MaC - MANOR LOAM, 8 TO 15 PERCENT SLOPES
  • MaD - MANOR LOAM, 15 TO 25 PERCENT SLOPES
  • MaE - MANOR LOAM, 25 TO 35 PERCENT SLOPES
  • UugB - URBAN LAND - UDGARTHENTS SCHIST AND GNEISS COMPLEX, 0 TO 8 PERCENT SLOPES

SOILS RESOLUTIONS

  • CUTBACKS / CAVE-IN: CAUTION SHOULD BE TAKEN TO LIMIT THE AMOUNT OF TRENCH THAT IS OPEN AT ANY GIVEN TIME. SHORING SHOULD BE USED AS RECOMMENDED BY THE RESPECTIVE GOVERNMENTAL SAFETY AGENCIES.
  • DEPTH OF WATER TABLE / SEASONAL HIGH WATER TABLE: IF GROUNDWATER IS ENCOUNTERED DURING GRADING OR TRENCHING, THE AREA WILL BE DE-WATERED BY PUMPING THE GROUNDWATER INTO A PUMPED WATER FILTER BAG E&S CONTROL SYSTEM.
  • LOW STRENGTH / UNSUITABLE SUBGRADE: IF SUBGRADE SOILS ARE UNSUITABLE FOR THE SPECIFIC ONSITE APPLICATION, AS DETERMINED BY INSPECTION BY THE CONTRACTOR, THEN SUITABLE SOIL SHALL BE IMPORTED OR THE EXISTING SUBGRADE SHALL BE STABILIZED.
  • PIPING: THE DETENTION BASIN BERMS SHALL BE PROVIDED WITH A CLAY CORE AND COMPACTED TO 95% DENSITY, PLUS ANTI-SEEP COLLARS WILL BE INSTALLED ON THE OUTFLOW PIPE TO PREVENT PIPING IN THE EMBANKMENT.
  • SHRINK-SWELL / FROST ACTION: IF WINTER GRADING IS UNAVOIDABLE, EXCAVATION SHALL TAKE PLACE WHEN THE TEMPERATURE IS ABOVE FREEZING AND THE SOIL IS DRY.
  • POOR SOURCE OF TOPSOIL (SLOPE): ERODED AREAS SHALL BE IMMEDIATELY STABILIZED AND COVERED WITH AN EROSION CONTROL BLANKET.
  • POOR SOURCE OF TOPSOIL (TOO ACID): A REPRESENTATIVE SOIL TEST SHALL BE PERFORMED TO DETERMINE THE NECESSARY AMOUNT OF LIME TO BE USED.

CLEAN FILL AND ENVIRONMENTAL DUE DILIGENCE

IF THE SITE WILL NEED TO IMPORT OR EXPORT MATERIAL FROM THE SITE, THE RESPONSIBILITY FOR PERFORMING ENVIRONMENTAL DUE DILIGENCE AND DETERMINATION OF CLEAN FILL WILL REST WITH THE CONTRACTOR (RESPONSIBLE PARTY).

CLEAN FILL IS DEFINED AS: UNCONTAMINATED, NON-WATER SOLUBLE, NON-DECOMPOSABLE, INERT, SOLID MATERIAL. THE TERM INCLUDES SOIL, ROCK, STONE, DREDGED MATERIAL, USED ASPHALT, AND BRICK, BLOCK OR CONCRETE FROM CONSTRUCTION AND DEMOLITION ACTIVITIES THAT IS SEPARATE FROM OTHER WASTE AND IS RECOGNIZABLE AS SUCH. THE TERM DOES NOT INCLUDE MATERIALS PLACED IN OR ON THE WATERS OF THE COMMONWEALTH UNLESS OTHERWISE AUTHORIZED. (THE TERM "USED ASPHALT" DOES NOT INCLUDE MILLED ASPHALT OR ASPHALT THAT HAS BEEN PROCESSED FOR RE-USE.)

TO DETERMINE IF FILL HAS BEEN AFFECTED BY A SPILL OR RELEASE OF A REGULATED SUBSTANCE: FILL AREAS AFFECTED BY A SPILL OR RELEASE OF A REGULATED SUBSTANCE STILL QUALIFIES AS CLEAN FILL PROVIDED TESTING REVEALS THAT THE FILL MATERIAL CONTAINS CONCENTRATIONS OF REGULATED SUBSTANCES THAT ARE BELOW THE RESIDENTIAL LIMITS IN TABLE FP-1a AND b FOUND IN THE DEPARTMENT'S POLICY "MANAGEMENT OF FILL". ANY PERSON PLACING FILL MATERIAL WHICH WAS AFFECTED BY A SPILL OR RELEASE OF A REGULATED SUBSTANCE MUST USE FORM FP-001 TO CERTIFY THE ORIGIN OF THE FILL MATERIAL AND THE RESULTS OF ANALYTICAL TESTING TO QUALIFY THE MATERIAL AS CLEAN FILL. FORM FP-001 MUST BE RETAINED BY THE PROPERTY OWNER FOR ANY FILL MATERIAL AFFECTED BY A SPILL OR RELEASE OF A REGULATED SUBSTANCE BUT QUALIFYING AS CLEAN FILL DUE TO ANALYTICAL TESTING.

ENVIRONMENTAL DUE DILIGENCE: THE APPLICANT MUST PERFORM ENVIRONMENTAL DUE DILIGENCE TO DETERMINE IF THE FILL MATERIALS ASSOCIATED WITH THE PROJECT QUALIFY AS CLEAN FILL.

ENVIRONMENTAL DUE DILIGENCE IS DEFINED AS: INVESTIGATIVE TECHNIQUES, INCLUDING, BUT NOT LIMITED TO, VISUAL PROPERTY INSPECTIONS, ELECTRONIC DATA BASE SEARCHES, REVIEW OF PROPERTY OWNERSHIP, REVIEW OF PROPERTY USE HISTORY, SANBORN MAPS, ENVIRONMENTAL QUESTIONNAIRES, TRANSACTION SCREENS, ANALYTICAL TESTING, ENVIRONMENTAL ASSESSMENTS OR AUDITS. ANALYTICAL TESTING IS NOT A REQUIRED PART OF DUE DILIGENCE UNLESS VISUAL INSPECTION AND/OR REVIEW OF THE PAST LAND USE OF THE PROPERTY INDICATES THAT THE FILL MAY HAVE BEEN SUBJECTED TO A SPILL OR RELEASE OF A REGULATED SUBSTANCE. IF THE FILL MAY HAVE BEEN AFFECTED BY A SPILL OR RELEASE OF A REGULATED SUBSTANCE, IT MUST BE TESTED TO DETERMINE IF IT QUALIFIES AS CLEAN FILL. TESTING SHOULD BE PERFORMED IN ACCORDANCE WITH APPENDIX A OF THE DEPARTMENT'S POLICY "MANAGEMENT OF CLEAN FILL". FILL MATERIAL THAT DOES NOT QUALIFY AS CLEAN FILL IS REGULATED FILL. REGULATED FILL IS WASTE AND MUST BE MANAGED IN ACCORDANCE WITH THE DEPARTMENT'S MUNICIPAL OR RESIDUAL WASTE REGULATIONS BASED ON 25 PA CODE CHAPTERS 287 RESIDUAL WASTE MANAGEMENT OR 271 MUNICIPAL WASTE MANAGEMENT, WHICHEVER IS APPLICABLE. THESE REGULATIONS ARE AVAILABLE ON-LINE AT WWW.PACODE.COM.

NOTES FOR PROJECTS DISCHARGING TO SPECIAL PROTECTION WATERSHEDS &/OR EXCEPTIONAL VALUE WETLANDS

  1. THIS PROJECT IS IN A SPECIALLY PROTECTED HIGH QUALITY OR EXCEPTIONAL VALUE WATERSHED; EXTREME CARE SHOULD BE EXERCISED BY ALL DISTURBANCE ACTIVITIES TO PREVENT DEGRADATION TO THE WATERS OF THE COMMONWEALTH.
  2. BECAUSE THIS PROJECT IS IN A SPECIALLY PROTECTED HIGH QUALITY OR EXCEPTIONAL VALUE WATERSHED, UPON COMPLETION OR TEMPORARY CESSATION OF EARTH DISTURBANCE ACTIVITIES, THE PROJECT SITE MUST BE IMMEDIATELY STABILIZED WITH THE APPROPRIATE TEMPORARY OR PERMANENT STABILIZATION.

Note: some text on this page could not be read reliably. Please see the original PDF for this page.

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN
EROSION AND SEDIMENT CONTROL DETAILS

CLIENT: GROVE MEADOW DEVELOPERS LLC
LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
DATE: APRIL 20, 2023
DRAWN: M.D. HARTMAN
CHECKED: M.D. HARTMAN
SCALE: N.T.S.
SHEET 13 OF 20
22-001-F-D-9.3

Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242. Revision 7/25/23: REVISED PER TOWNSHIP REVIEW LETTERS. [Seal: Commonwealth of Pennsylvania, Registered Professional Engineer, Michael Duain Hartman]

STANDARD CONSTRUCTION DETAIL #4-1
COMPOST FILTER SOCK

[Section and plan view drawings of a compost filter sock between a disturbed area and an undisturbed area, with 2 IN. x 2 IN. WOODEN STAKES PLACED 10 FT ON CENTER and existing contours.]

TABLE 4.1 COMPOST SOCK FABRIC MINIMUM SPECIFICATIONS

[Table of material types (3 MIL HDPE, 5 MIL HDPE, 5 MIL HDPE, MULTI-FILAMENT POLYPROPYLENE (MFPP), HEAVY DUTY MULTI-FILAMENT POLYPROPYLENE (HDMFPP)) with rows for material characteristics, sock diameters, mesh opening, tensile strength, ultraviolet stability and minimum functional longevity; cell values too small to verify.]

TABLE 4.2 COMPOST STANDARDS

[Table with rows ORGANIC MATTER CONTENT, ORGANIC PORTION, pH, MOISTURE CONTENT, PARTICLE SIZE, SOLUBLE SALT CONCENTRATION; values too small to verify.]

NOTES: [eight numbered notes on compost filter sock fabric, placement, inspection and removal; text too small to read reliably]

PUMPED WATER FILTER BAG

[Plan view and elevation view drawings showing filter bag, discharge hose, pump, intake hose, clamp and heavy duty lifting straps in a well vegetated grassy area, with a property/test method/minimum standard table and numbered notes; text too small to read reliably.]

TYPICAL VEGETATED SWALES

[Channel cross-section with a table of channel no. DIVERSION, section 1, bottom width, depth, Z1, Z2, permanent lining VEGETATED and temporary lining; and numbered notes; text too small to read reliably.]

TYPE M INLET PROTECTION DETAIL

[Drawing of storm inlet protection with grate, wire mesh, earthen berm and notes.]

TYPE C INLET PROTECTION DETAIL

[Drawing of curb inlet protection with AASHTO #57 stone, berm and notes.]

SLOPE PROTECTION INSTALLATION DETAIL

[Drawing of erosion control blanket installation on a slope with numbered notes.]

ECB CHANNEL INSTALLATION

[Drawing of erosion control blanket installation in a channel with numbered notes.]

STAPLE PATTERN GUIDE

[Staple pattern diagrams C (1.7 STAPLES PER SQ YD), D (3.4 STAPLES PER SQ YD), E (3.4 STAPLES PER SQ YD).]

ROCK CONSTRUCTION ENTRANCE
NOT TO SCALE

[Plan view and Section A-A with notes on maintaining thickness of rock and removing sediment from public roadways.]

TEMPORARY STOCKPILE DETAIL

[Cross-section drawing with 2:1 SLOPE OR FLATTER and 35 FT MAX. Notes: 1) STOCKPILES TO BE STABILIZED IMMEDIATELY. 2) STOCKPILE HEIGHTS MUST NOT EXCEED 35'. 3) STOCKPILE SLOPES MUST BE 2:1 OR FLATTER.]

COMPOST SOCK CONCRETE WASHOUT DETAIL

[Section A-A and plan view of a washout ring of 24" DIAMETER COMPOST FILTER SOCK with 2"x2"x36" WOODEN STAKES PLACED 5' O.C. and notes 1) to 3); text too small to read reliably.]

TYPICAL ON-LOT BMPs FOR LOT ALONG ASCENDING OR DESCENDING ROADWAY

TYPICAL ON-LOT BMPs FOR LOT BELOW ROADWAY

TYPICAL ON-LOT BMPs FOR LOT ABOVE ROADWAY

[Plan view drawings showing HOUSE, DRIVEWAY, TOP SOIL, ROCK CONSTRUCTION ENTRANCE, DIVERSION SWALE, OUTLET SWALE TO STABLE AREA ON ADEQUATE DRAINAGEWAY, and FILTER FABRIC FENCE, COMPOST FILTER SOCK OR SEDIMENT FILTER LOG (TYP.), with notes; text too small to read reliably.]

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN - EROSION AND SEDIMENT CONTROL DETAILS

Client: Grove Meadow Developers LLC | Location: East Goshen Township, Chester County, Pennsylvania | Date: April 20, 2023 | Drawn By / Designed/Checked: M.D. Hartman | Scale: N.T.S. | Sheet: 14 OF 20 | File No.: 22-001-F-D-9.4 | Engineer: Michael Duain Hartman, P.E., dh Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242

BASIN EMERGENCY SPILLWAY

Plan View, Section 'A'-'A', and Embankment Section 'B'-'B' Along Emergency Spillway showing downstream and upstream toewalls, top of berm, weir, level, and erosion control blanket lining.

BASIN Z3 Z4 WEIR TOP ELEV. WTE (FT) WEIR CREST ELEV. WCE (FT) WIDTH Ww (FT) ECB LINING MAT'L & STAPLE PATTERN LINING DEPTH DL (FT) Z1 Z2
1 3 3 515.75 514.50 75' P550/E 1.0' 3 3

TYPICAL BASIN 1 ANTI-SEEP COLLAR

Engineering diagram of Typical Basin 1 Anti-Seep Collar: 6' square, PennDOT Class C concrete 12" thick (min.), with 36" RCP barrel watertight connection.

BASIN OUTLET STRUCTURE (OS-1)

Isometric diagram showing 2'x4' Precast Inlet Box with Top Elev. 513.08, 38" Orifice for 24" CMP Pipe Inv 510.40, and inlet grate.

  1. PROVIDE MANHOLE STEPS IN ACCORDANCE WITH PennDOT RC-39.
  2. DO NOT INSTALL TOP UNIT AT THIS TIME.
  3. OUTLET STRUCTURE MANUFACTURED BY TERRE HILL CONCRETE PRODUCTS (800) 242-1509, OR APPROVED EQUAL.

TEMPORARY TRASH RACK & ANTI-VORTEX FOR PERMANENT OUTLET STRUCTURE

Engineering diagram and Section showing trash rack comprised of 1"x1"x1/8" angle (typ) and #4 bars (typ) welded to the angles and at each intersection of the bars, #4 bars spaced at 1/2 the diameter of the barrel max., 1/4" thk. x 12" high steel anti-vortex plate welded to trash rack, top of permanent outlet riser Elev. 513.08, and concrete box.

NOTES:
1) TRASH RACK COMPRISED OF 1"x1"x1/8" ANGLE (TYP) AND #4 BARS (TYP) WELDED TO THE ANGLES AND AT EACH INTERSECTION OF THE BARS. #4 BARS SHALL BE SPACED AT 1/2 THE DIAMETER OF THE BARREL MAX.
2) ALL JOINTS SHALL BE WATER TIGHT.
3) CLOGGED OR DAMAGED SPILLWAYS SHALL BE REPAIRED IMMEDIATELY. TRASH AND OTHER DEBRIS SHALL BE REMOVED FROM THE BASIN AND RISER.

SEDIMENT BASIN PLYWOOD BAFFLE DETAIL

Engineering diagram of Sediment Basin Plywood Baffle constructed from 4"x4" pressure treated posts (4' C/C max.) and 3/4"x4'x8' marine grade plywood sheets.

BASIN NO. PLYWOOD BAFFLE PERMANENT STRUCTURE BOTTOM
LENGTH Lb (FT) HEIGHT Hb (FT) CREST ELEV TRCE (FT) BOTTOM ELEV BE (FT)
1 264 3.6 513.10 509.50
1 50 3.6 513.10 509.50
  1. PROVIDE 4x4 POSTS AT ALL SEAMS IN THE PLYWOOD BAFFLE.
  2. SEE E&SC PLAN FOR LOCATION OF BAFFLE IN BASIN(S).
  3. BAFFLES SHALL BE TIED INTO ONE SIDE OF THE BASIN UNLESS SHOWN OTHERWISE ON THE E&SC PLAN.
  4. DAMAGED OR WARPED BAFFLES SHALL BE REPLACED WITHIN 7 DAYS OF INSPECTION.
  5. BAFFLES REQUIRING SUPPORT POSTS SHALL NOT BE INSTALLED IN BASINS REQUIRING IMPERVIOUS LINERS.
  6. IN POOLS WITH DEPTHS EXCEEDING 7' THE TOP OF THE PLYWOOD BAFFLE DOES NOT NEED TO EXTEND TO THE TEMPORARY RISER CREST ELEVATION.

SEDIMENT BASIN #1 CROSS-SECTION

Cross-section diagram of Sediment Basin #1 showing Top Elev. 513.08, Berm Elev. 515.75, Spillway Inv. 514.50, Top of Core Elev. 514.00, compacted fill, 2 Anti-Seep Collars, 36" RCP barrel at S=0.005, Inv Out 509.17, Rip Rap Apron, 4" min. topsoil, key trench 2' deep on to stable subgrade, and core.

SEDIMENT BASIN TEMPORARY SKIMMER AND PERMANENT OUTLET STRUCTURE

Elevation diagram showing skimmer, vent pipe, float, water entry unit, orifice, 2'x4' cleanout stake (red line at cleanout elevation), temporary CMP riser, permanent outlet structure, stone berm, dewatering facility, temporary 18" outlet barrel, watertight seal at all joints, and 54"x54" concrete base.

PERMANENT OUTLET STRUCTURE TOP OF GRATE ELEV. TCE (FT.) TEMPORARY RISER BARREL EMBANKMENT EMERGENCY SPILLWAY INV. ELEV. ESE (FT.) CLEANOUT ELEV. COE (FT.) BOTTOM ELEV. BE (FT.)
TCE (FT.) Dia. Bd (IN.) CREST ELEV. (FT.) MAT'L LENGTH TBI (FT.) BARREL DIA. (IN.) Dia. Bd (IN.) INLET ELEV. BIE (FT.) MAT'L LENGTH RCP (FT.) OUTLET ELEV. BOE (FT.) TOP ELEV. ETE (FT.) TOP WIDTH ETW (FT.) ESE (FT.) COE (FT.) BE (FT.)
513.08** 48 513.08 CMP 6 24 36 510.17 RCP 33 510.00 515.75 8 514.50 510.50 509.50

** SEE TEMPORARY TRASH RACK & ANTI-VORTEX FOR PERMANENT OUTLET STRUCTURE DETAIL

NOTES:
1) ALL ORIFICES ON PERMANENT RISER BELOW TEMPORARY RISER EXTENSION SHALL HAVE WATER-TIGHT TEMPORARY SEALS PROVIDED. TEMPORARY STUB INVERT ELEVATION SHALL BE SET AT OR BELOW SEDIMENT CLEAN-OUT ELEVATION.
2) A ROPE SHALL BE ATTACHED TO THE SKIMMER ARM TO FACILITATE ACCESS TO THE SKIMMER ONCE INSTALLED.
3) SKIMMER SHALL BE INSPECTED WEEKLY AND AFTER EACH RUNOFF EVENT.
4) ANY MALFUNCTIONING SKIMMER SHALL BE REPAIRED OR REPLACED WITHIN 24 HOURS OF INSPECTION.
5) ICE OR SEDIMENT BUILDUP AROUND THE PRINCIPAL SPILLWAY SHALL BE REMOVED SO AS TO ALLOW THE SKIMMER TO RESPOND TO FLUCTUATING WATER ELEVATIONS.
6) SEDIMENT SHALL BE REMOVED FROM THE BASIN WHEN IT REACHES THE LEVEL MARKED ON THE SEDIMENT CLEAN-OUT STAKE OR THE TOP OF THE STONE BERM.
7) APPROVAL OF THE USE OF A SKIMMER DOES NOT APPROVE OWNER OR OPERATOR USE OF ANY SKIMMER IN VIOLATION OF ANY PATENT, PATENT RIGHTS AND/OR PATENT LAWS.
8) ALSO SEE SEDIMENT TRAP SKIMMERS & PERMANENT STRUCTURES DETAIL.
9) SKIMMER MANUFACTURED BY J.W. FAIRCLOTH & SON, P.O. BOX 757, HILLSBORO, NC, TEL. (919) 732-1244.

SEDIMENT BASIN CROSS-SECTION ALONG PRINCIPAL SPILLWAY

Cross-section diagram along the principal spillway showing skimmer, orifice, AASHTO #57 stone berm, temporary riser with skimmer, permanent outlet structure, anti-seep collars (typ. 2 total), key trench 2' below subgrade, compacted fill core, 6" min. topsoil down to cleanout elev., core elev. 522.25, and embankment.

  1. SEDIMENT BASINS, INCLUDING ALL APPURTENANT WORKS, SHALL BE CONSTRUCTED TO THE DETAILS AND DIMENSIONS ON THE E&S PLAN DRAWINGS.
  2. AREA UNDER EMBANKMENT SHALL BE CLEARED, GRUBBED AND STRIPPED OF TOPSOIL TO A DEPTH OF 2 FEET PRIOR TO ANY PLACEMENT AND COMPACTION OF EARTHEN FILL. IN ORDER TO FACILITATE MAINTENANCE AND RESTORATION, THE POOL AREA SHALL BE CLEARED OF ALL BRUSH, TREES AND OBJECTIONABLE MATERIAL. FILL MATERIAL FOR THE EMBANKMENTS SHALL BE FREE OF ROOTS, OR OTHER WOODY VEGETATION, ORGANIC MATERIAL, LARGE STONES AND OTHER OBJECTIONABLE MATERIALS. THE EMBANKMENT SHALL BE COMPACTED IN LAYERED LIFTS OF NOT MORE THAN 6" TO 8". MAXIMUM ROCK SIZE SHALL BE NO GREATER THAN 2/3 THE LIFT THICKNESS.
  3. UPON COMPLETION, THE EMBANKMENT SHALL BE SEEDED, MULCHED, BLANKETED OR OTHERWISE STABILIZED ACCORDING TO THE SPECIFICATIONS OF THE E&S PLAN DRAWINGS. TREES SHALL NOT BE PLANTED ON THE EMBANKMENT.
  4. INSPECT ALL SEDIMENT BASINS ON AT LEAST A WEEKLY BASIS AND AFTER EACH RUNOFF EVENT. PROVIDE ACCESS FOR SEDIMENT REMOVAL AND OTHER REQUIRED MAINTENANCE ACTIVITIES. A CLEAN-OUT STAKE SHALL BE PLACED NEAR THE CENTER OF EACH BASIN. ACCUMULATED SEDIMENT SHALL BE REMOVED WHEN IT HAS REACHED THE CLEAN-OUT ELEVATION ON THE STAKE AND THE BASIN RESTORED TO ITS ORIGINAL DIMENSIONS. DISPOSE OF MATERIALS REMOVED FROM THE BASIN IN A MANNER DESCRIBED IN THE E&S PLAN.
  5. BASIN EMBANKMENTS, SPILLWAYS AND OUTLETS SHALL BE INSPECTED FOR EROSION, PIPING AND SETTLEMENT. NECESSARY REPAIRS SHALL BE MADE IMMEDIATELY. DISPLACED RIPRAP WITHIN THE OUTLET ENERGY DISSIPATOR SHALL BE REPLACED IMMEDIATELY.
  6. ACCUMULATED SEDIMENT SHALL BE REMOVED AND DISTURBED AREAS SHALL BE STABILIZED INSIDE THE BASIN BEFORE CONVERSION TO A STORMWATER MANAGEMENT FACILITY. THE DEVICE SHOWN IN THE SEDIMENT BASIN DEWATERING FACILITY DETAIL MAY BE USED TO DEWATER SATURATED SEDIMENT PRIOR TO ITS REMOVAL. ROCK FILTERS SHALL BE ADDED AS NECESSARY.
  7. EMBANKMENT MATERIAL SHALL CONSIST OF SUITABLE MATERIAL FREE OF ALL ROOTS, SOD, FROZEN SOIL, ROCK OVER 6" IN DIAMETER, AND ANY OTHER MATERIAL NOT APPROVED BY THE ENGINEER. FILL SHALL BE COMPACTED IN 8" LIFTS TO AT LEAST 95% OF STANDARD MAXIMUM DRY DENSITY PER ASTM D698, STANDARD PROCTOR. PRIOR TO PLACEMENT OF A NEW LIFT, THE TOP 2" OF THE PREVIOUS LIFT SHALL BE SCARIFIED.
  8. CORE MATERIAL TO BE CLAYEY SOIL (UNIFIED CLASS GC, SC, OR CL-ML) COMPACTED TO 95% MAXIMUM DRY DENSITY.
  9. EMBANKMENT CORE MAY BE ELIMINATED IF THE ENTIRE EMBANKMENT CONFORMS TO NOTE 2. KEY TRENCH CORE IS STILL REQUIRED.
  10. AFTER SITE IS PERMANENTLY STABILIZED, REMOVE SEDIMENT, EXCAVATE TO FINAL SUBGRADE, SPREAD 6" OF TOPSOIL INSIDE BASIN BELOW CLEANOUT ELEVATION AND PERMANENTLY STABILIZE PER SEEDING AND MULCHING SPECIFICATIONS.
  11. BASIN BOTTOM AND EMBANKMENT TO BE TOPSOILED AND PERMANENTLY SEEDED AND MULCHED PER SEEDING AND MULCHING SPECIFICATIONS.
  12. SLP/PP OUTLET PIPE SHALL BE PROVIDED WITH WATERTIGHT COUPLERS.
  13. DO NOT PROVIDE STONE BEDDING OR BACKFILL AROUND THE OUTLET PIPE.
  14. PIPE LENGTH IS MEASURED TO THE OUTFALL END OF THE END SECTION, WHERE APPLICABLE.
  15. CONSTRUCT THE ANTI-SEEP COLLARS OVER PIPE JOINTS NEAREST THE LOCATION NOTED ABOVE.
  16. THE PERMITTEE SHALL BE RESPONSIBLE FOR THE STRUCTURAL STABILITY OF SEDIMENT TRAPS AND FOR THEIR PROTECTION AGAINST UNAUTHORIZED ACTS OF THIRD PARTIES.
  17. CLEANOUT STAKES MUST BE PLACED AT HALF DISTANCES FROM POINTS OF CONCENTRATED INFLOWS TO SKIMMERS. WHEN SEDIMENT HAS ACCUMULATED TO THE CLEANOUT ELEVATION MARKED ON ANY STAKE, THE SEDIMENT MUST BE REMOVED TO RESTORE TRAP CAPACITIES.
  18. BAFFLES MUST BE INSTALLED TO ALLOW TRAP MAINTENANCE AND CLEANOUT.
  19. APPROVAL OF THE USE OF A SKIMMER DOES NOT APPROVE OWNER OR OPERATOR USE OF ANY SKIMMER IN VIOLATION OF ANY PATENT, PATENT RIGHTS AND/OR PATENT LAWS.
  20. SEDIMENT TRAPS SHALL BE KEPT FREE OF ALL TRASH, CONCRETE WASH WATER AND OTHER DEBRIS THAT POSE THE POTENTIAL FOR CLOGGING THE TRAP OUTLET STRUCTURES AND/OR POSE THE POTENTIAL FOR POLLUTION TO WATERS OF THE COMMONWEALTH.
  21. DO NOT PROVIDE STONE BEDDING OR BACKFILL AROUND THE OUTLET PIPE.

TRASH RACK AND ANTI-VORTEX DEVICE

Isometric diagram and dimensions for Trash Rack and Anti-Vortex Device: #4 bars (typ.) welded to angles and at each intersection of bars, 1"x1"x1/8" L (typ.), steel plate (3/16" thickness), cylinder riser with outlet.

SEDIMENT BASIN SKIMMERS & TEMPORARY CMP RISER

Plan View diagram showing temporary CMP riser, barrel, trash rack, arm, hose, vent, orifice, water entry unit, float, AASHTO #57 stone, stone berm, dewatering facility, and rope attached to skimmer for maintenance purposes.

SEDIMENT TRAP DEWATERING FACILITY

Section diagram showing 30 to 55 gallon barrel with 1/2" perforations at 6" O.C. horizontal and vertical spacing, 2"x2" wood slats placed vertically around outside of barrel @ 5" O.C. and wrapped with filter fabric, cleanout elev., pump, permanent outlet structure, basin bottom, and AASHTO No. 57 coarse aggregate encircling riser up to cleanout elevation.

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN POST-CONSTRUCTION STORMWATER MANAGEMENT PLAN

CLIENT: GROVE MEADOW DEVELOPERS LLC
LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
DATE: APRIL 20, 2023
DRAWN/CHECKED: M.D. HARTMAN
SCALE: 1" = 50'
SHEET 15 OF 20
22-001-F-D-10.1
Michael Duain Hartman, Professional Engineer; Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242

ONE CALL NOTES

PENNSYLVANIA ONE CALL SYSTEM, INC. 1-800-242-1776. CALL BEFORE YOU DIG. PENNSYLVANIA ACT 287, AS AMENDED BY ACT 121 REQUIRES NOTIFICATION OF EXCAVATORS, DESIGNERS, OR ANY PERSON PREPARING TO DISTURB THE EARTH'S SURFACE ANYWHERE IN THE COMMONWEALTH.

ACT 287 UNDERGROUND UTILITY PROTECTION ACT, AS AMENDED BY ACT 121: ACT 287 UNDERGROUND UTILITY PROTECTION ACT, AS AMENDED BY: ACT 172 OF 1986, ACT 38 OF 1991, ACT 187 OF 1996, ACT 199 OF 2004, ACT 181 OF 2006, ACT 121 OF 2008.

PA ONE CALL SYSTEM INFORMATION: PENNSYLVANIA ACT 287, AS AMENDED, REQUIRES THREE (3) WORKING DAYS NOTICE FOR CONSTRUCTION PHASE AND FIVE (5) WORKING DAYS NOTICE IN DESIGN STAGE. PA ONE CALL PHONE NUMBER: 1-800-242-1776. ONE CALL SYSTEM SERIAL NO. NOTIFICATION BY NAVE NEWELL, INC. DATE: 11/07/22. ONE CALL SYSTEM SERIAL NUMBER: 20223113472.

UNDERGROUND UTILITY LOCATIONS ARE APPROXIMATE AND WERE DETERMINED FROM VISIBLE LOCATION, ACT 287 OF 1974, AS AMENDED, UTILITY RESPONSES AND/OR BEST AVAILABLE PLAN INFORMATION.

LIST OF RESPONDERS: AQUA PENNSYLVANIA INC, COMCAST CABLE COMMUNICATIONS INC, EAST GOSHEN TOWNSHIP, PECO ENERGY, TEXAS EASTERN TRANSMISSION LP, VERIZON PENNSYLVANIA LLC.

OWNER AND APPLICANT

TROUTBECK FARM DEVELOPERS LLC
1171 LANCASTER AVE. SUITE 201
BERWYN PA 19312

RECEIVING WATERCOURSE: THE RECEIVING WATERCOURSE FROM THE PROJECT AREA IS A TRIBUTARY TO RIDLEY CREEK. THE WATERCOURSE IS LOCATED ON THE PROJECT TRACT BUT OUTSIDE OF THE LIMIT OF DISTURBANCE. THE WATERCOURSE HAS A CHAPTER 93 CLASSIFICATION OF HQ-CWF, HIGH QUALITY - COLD WATER FISHES. THE RECEIVING STREAM IS LISTED AS HAVING A 303D IMPAIRMENT DUE TO URBAN RUNOFF.

RIPARIAN BUFFER MEASUREMENT PER PENNSYLVANIA CODE SECTION [illegible]: RIPARIAN BUFFERS MUST BE MEASURED HORIZONTALLY AND PERPENDICULARLY TO THE BANK WITH NO MORE THAN A 10% VARIATION BELOW THE NORMAL POOL ELEVATION FOR LAKE, POND OR RESERVOIR AND FROM TOP OF STREAMBANK.

PROPOSED TREE PLANTINGS: THE PROPOSED TREE PLANTINGS AND REFORESTATION AREAS AS SHOWN ON THE LANDSCAPING PLAN ARE TO BE CONSIDERED PART OF THE STORM WATER MANAGEMENT SYSTEM FOR THE PROPOSED DEVELOPMENT AND ARE NOT TO BE REMOVED WITHOUT PRIOR APPROVAL FROM EAST GOSHEN TOWNSHIP, CHESTER COUNTY CONSERVATION DISTRICT AND DEP.

SOILS LEGEND

  • Co - CODORUS SILT LOAM
  • Ha - HATBORO SILT LOAM
  • GgB - GLENELG SILT LOAM, 3 TO 8 PERCENT SLOPES
  • MaB - MANOR LOAM, 3 TO 8 PERCENT SLOPES
  • MaC - MANOR LOAM, 8 TO 15 PERCENT SLOPES
  • MaD - MANOR LOAM, 15 TO 25 PERCENT SLOPES
  • MaE - MANOR LOAM, 25 TO 35 PERCENT SLOPES
  • UugB - URBAN LAND - UDORTHENTS SCHIST AND GNEISS COMPLEX, 0 TO 8 PERCENT SLOPES

OWNER'S ACKNOWLEDGEMENT

I ACKNOWLEDGE THAT ANY REVISION TO THE APPROVED SWM SITE PLAN SHALL BE SUBMITTED TO AND APPROVED BY THE MUNICIPALITY AND THAT A REVISED EROSION AND SEDIMENT CONTROL PLAN SHALL BE SUBMITTED TO, AND APPROVED BY, THE CONSERVATION DISTRICT OR MUNICIPALITY (AS APPLICABLE) FOR A DETERMINATION OF ADEQUACY PRIOR TO CONSTRUCTION OF THE REVISED FEATURES.

ENGINEER'S CERTIFICATE

"I, MICHAEL DUAIN HARTMAN, P.E., ON THIS DATE ______ HEREBY CERTIFY TO THE BEST OF MY KNOWLEDGE THAT THE SWM SITE PLAN MEETS ALL DESIGN STANDARDS AND CRITERIA OF THE EAST GOSHEN TOWNSHIP STORMWATER MANAGEMENT ORDINANCE (ORDINANCE NO. 129-F-2013)."

PROJECT SITE BOUNDARY AREA = 16.00 ACRES
LIMIT OF DISTURBANCE AREA = 8.83 ACRES

[Vicinity map, scale 1"=800', with the project location marked, and zoning labels R-1 and R-2.]

[Post-construction stormwater management plan drawing, scale 1"=50', showing Millstone Circle, numbered lots, Infiltration Basin #1 and Infiltration Basin #2, Hershey Mill Road, Tanglewood Drive, limit of disturbance and project site boundary lines, and a note: SEE PLAN NO. 10.4 FOR CONVERSION OF THE RIPARIAN BUFFER AREA TO A FORESTED RIPARIAN BUFFER. Other soil labels on the plan: MaB, MaC, MaD, MaE, Co, Ha, UugB.]

PCSM HATCH LEGEND: Infiltration Basin; Reforestation/Landscape Restoration; Amended Soils; Riparian Buffer; Forested Riparian Buffer Conversion Area.

LEGEND: Existing Curb, Proposed Curb, Existing Contours, Proposed Contours, Existing Spot Elevation, Proposed Spot Elevation, Soil Line, Existing Street Sign, Existing Features Are Labeled With Slanted Text, To Be Removed, Existing Deciduous Tree, Proposed Sanitary Sewer & Manhole, Proposed Storm Sewer & Catch Basin, Existing Water Line & Valve, Proposed Water Line & Valve, Proposed Fire Hydrant, Proposed Grinder Pump, Proposed Water Lateral, Proposed Trail Network (Paved), Riparian Buffer, Project Site Boundary, Project Site Boundary & Limit of Disturbance, Limit of Disturbance, Drainage Area to BMP.

Note: some text on this page could not be read reliably. Please see the original PDF for this page.

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN PCSM DETAILS

CLIENT: Grove Meadow Developers LLC. LOCATION: East Goshen Township, Chester County, Pennsylvania. DATE: April 20, 2023. Drawn/Checked: M.D. Hartman. Scale: 1" = 50'. Sheet 16 OF 20. 22-001-F-D-10.2. dh Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242. Revision block: 7/25/23, REVISED PER TOWNSHIP REVIEW LETTERS.

INFILTRATION BASIN OUTLET STRUCTURE (OS-1) and (OS-2)

Two isometric drawings of precast inlet boxes with structural steel grates (inlet grate frame cast in top of box, 2'x4' precast inlet box); remaining dimension labels [illegible].

  1. PROVIDE MANHOLE STEPS IN ACCORDANCE WITH PennDOT RC-39.
  2. OUTLET STRUCTURE MANUFACTURED BY TERRE HILL CONCRETE PRODUCTS (800) 242-1509, OR APPROVED EQUAL.

INFILTRATION BASIN #1 CROSS-SECTION and INFILTRATION BASIN #2 CROSS-SECTION

Two cross-section drawings of the basin embankments with core, anti-seep collars and outlet pipes; elevations [illegible].

RETENTION BASIN FLOOR MIX - LOW MAINTENANCE (ERNMX-126, SEEDING RATE: 20 - 40 LB. PER ACRE)

PercentBotanical nameCommon name
20.0%PUCCINELLIA DISTANS, 'FULTS'(ALKALIGRASS, 'FULTS')
19.0%PANICUM CLANDESTINUM, 'TIOGA'(DEERTONGUE, 'TIOGA')
18.0%AGROSTIS STOLONIFERA(CREEPING BENTGRASS)
18.0%ELYMUS VIRGINICUS, PA ECOTYPE(VIRGINIA WILDRYE, PA ECOTYPE)
15.0%POA PALUSTRIS(FOWL BLUEGRASS)
5.0%CAREX VULPINOIDEA, PA ECOTYPE(FOX SEDGE, PA ECOTYPE)
3.0%JUNCUS EFFUSUS(SOFT RUSH)
2.0%CAREX SCOPARIA, PA ECOTYPE(BLUNT BROOM SEDGE, PA ECOTYPE)

BASIN EMERGENCY SPILLWAY

Plan view, Section 'A'-'A' and Embankment Section 'B'-'B' along emergency spillway; table of weir and lining values for basins 1 and 2 [illegible].

INFILTRATION BASIN CONSTRUCTION NOTES

Eight numbered notes in small print [illegible].

TYPICAL ANTI-SEEP COLLAR, PLAN VIEW, RIP RAP APRON DETAIL, CONCRETE END SECTION

Detail drawings and small tables (anti-seep collar basin/barrel diameter/collars, rip rap percent passing and rip rap chart, end section dimensions); values [illegible].

TYPE C INLET, TYPE M INLET, GRADE ADJUST RING (PRECAST), STORM SEWER PIPE BEDDING, STRUCTURAL STEEL BICYCLE SAFE GRATE

Detail drawings. Note on pipe bedding: DO NOT PROVIDE STONE BEDDING OR BACKFILL AROUND DETENTION BASIN OUTLET PIPES.

PRECAST CONCRETE BOXES FOR STORM INLETS AND JUNCTION BOXES

Drawings of Type 1, Type 2 and Type 3 standard boxes, Sections A-A through H-H, Details A, B and C, and COVER ADJUSTMENT SLABS, with a block of numbered notes in small print [illegible].

Note: some text on this page could not be read reliably. Please see the original PDF for this page.

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN - PCSM DETAILS

CLIENT: GROVE MEADOW DEVELOPERS LLC. LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA. DATE: APRIL 20, 2023. DRAWN: M.D. HARTMAN. CHECKED: M.D. HARTMAN. SCALE: 1" = 50'. SHEET 17 OF 20. 22-001-F-D-10.3. DH Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242.

EQUITABLE OWNER AND APPLICANT

GROVE MEADOW DEVELOPERS LLC, 1171 LANCASTER AVE, SUITE 241, BERWYN PA 19312

GENERAL NOTES

  1. THE PERMITTEE SHALL PROVIDE ENGINEERING CONSTRUCTION OVERSIGHT FOR THE PROPOSED STORMWATER BMPS. ADDITIONAL SOIL TESTING MAY BE REQUIRED PRIOR TO THE INSTALLATION OF INFILTRATION BMPS TO ENSURE PROPER LOCATION AND FUNCTION. A LICENSED PROFESSIONAL KNOWLEDGEABLE IN THE DESIGN AND CONSTRUCTION OF STORMWATER BMPS, PREFERABLY THE DESIGN ENGINEER, SHALL CONDUCT THE OVERSIGHT.
  2. IF UNFAVORABLE CONDITIONS HAVE BEEN ENCOUNTERED DURING THE INSTALLATION OF THE SEEPAGE/INFILTRATION SYSTEMS (I.E. GROUNDWATER AND/OR BEDROCK, ETC.), THE OWNER/ENGINEER SHOULD BE NOTIFIED AND THE PROPOSED INFILTRATION SYSTEM SHOULD BE RELOCATED TO A MORE SUITABLE LOCATION ON THE PROPERTY.
  3. THE ANTICIPATED WASTES ARE GENERAL CONSTRUCTION WASTES. THE OPERATOR SHALL REMOVE FROM THE SITE, RECYCLE, OR DISPOSE OF ALL BUILDING MATERIALS AND WASTES IN ACCORDANCE WITH THE DEPARTMENT'S SOLID WASTE MANAGEMENT REGULATIONS AT 25 PA. CODE 260.1 ET SEQ., 271.1 ET SEQ., AND 287.1 ET SEQ. THE CONTRACTOR SHALL NOT ILLEGALLY BURY, DUMP, OR DISCHARGE ANY BUILDING MATERIAL OR WASTES AT THE SITE.
  4. THE PROPOSED TREE PLANTINGS ARE TO BE CONSIDERED PERMANENT BMPS AND ARE NOT TO BE REMOVED WITHOUT PRIOR CONSENT BY THE TOWNSHIP, CHESTER COUNTY CONSERVATION DISTRICT AND THE DEPARTMENT.
  5. THE EXISTING FLOW PATTERNS TO DISCHARGE POINTS 2 THROUGH 4 ARE TO BE MAINTAINED AND NOT ALTERED BETWEEN THE LIMIT OF DISTURBANCE AND THE PROJECT SITE BOUNDARY. ANY EROSION CAUSED BY DISCHARGES FROM BMPS WITHIN THE SITE WILL BE REPAIRED AND STABILIZED.
  6. IN THE EVENT OF A FAILURE OF THE PROPOSED BMP'S, THE PERMITTEE SHALL CONSULT A REGISTERED PROFESSIONAL ENGINEER TO DETERMINE THE CAUSE OF THE FAILURE AND REMEDIATIVE MEASURES. FAILURE OF THE BMP'S IS DEFINED AS FOLLOWS: BMP 6.4.2: INFILTRATION BASIN - DRAINAGE OF COLLECTED WATER TAKES LONGER THAN 72 HOURS AFTER A STORM EVENT; BMP 6.4.3: SUBSURFACE INFILTRATION BED - DRAINAGE OF COLLECTED WATER TAKES LONGER THAN 72 HOURS AFTER A STORM EVENT.
  7. TO ENSURE THAT THE EXISTING FLOW PATTERNS ARE NOT ALTERED AND MAINTAINED, THE OUTLETS FROM THE PROPOSED BMP'S HAVE BEEN LOCATED A MINIMUM OF 150' FROM THE PROJECT SITE BOUNDARY.

OPERATIONS AND MAINTENANCE RESPONSIBILITIES

THE OWNER WILL BE RESPONSIBLE FOR THE OPERATION AND MAINTENANCE OF LONG TERM STORMWATER BMP'S AS SHOWN ON THESE PLANS. THE OWNER SHALL INSPECT AND MONITOR THEM PERIODICALLY AND DURING SIGNIFICANT RUNOFF EVENTS TO ENSURE THEY ARE SUCCESSFULLY CARRYING OUT THEIR INTENDED FUNCTION. THE OWNER SHALL NOT DUMP DIRTY WATER, OIL, OR ANY OTHER LIQUIDS OR SOLIDS INTO THE STORM WATER CONVEYANCE SYSTEM, DETENTION PONDS OR ANY OTHER BMPS. VEHICLES SHALL NOT BE DRIVEN ACROSS BMPS. THE OWNER SHALL BE RESPONSIBLE FOR THE SHORT TERM AND LONG TERM OPERATION AND MAINTENANCE MEASURES FOR THE POST CONSTRUCTION STORM WATER MANAGEMENT FACILITIES.

BMP 6.4.3: INFILTRATION BASIN HOMEOWNER'S ASSOCIATION

  • CATCH BASINS AND INLETS UPSTREAM OF INFILTRATION BASINS SHOULD BE INSPECTED AND CLEANED AT LEAST TWICE PER YEAR AND AFTER EVERY MAJOR STORM.
  • THE VEGETATION ALONG THE SURFACE OF THE INFILTRATION BASIN SHOULD BE MAINTAINED IN GOOD CONDITION, AND ANY BARE SPOTS REVEGETATED AS SOON AS POSSIBLE.
  • VEHICLES SHOULD NOT BE PARKED OR DRIVEN ON AN INFILTRATION BASIN, AND CARE SHOULD BE TAKEN TO AVOID EXCESSIVE COMPACTION BY MOWERS.
  • INSPECT THE BASIN AFTER RUNOFF EVENTS AND MAKE SURE THAT RUNOFF DRAINS DOWN WITHIN 72 HOURS. MOSQUITOES SHOULD NOT BE A PROBLEM IF THE WATER DRAINS IN 72 HOURS. MOSQUITOES REQUIRE A CONSIDERABLY LONG BREEDING PERIOD WITH RELATIVELY STATIC WATER LEVELS. SHOULD RUNOFF REMAIN IN THE BASIN FOR LONGER THAN 72 HOURS, THE OWNER SHALL CONTACT A REGISTERED PROFESSIONAL TO DETERMINE REMEDIATIVE MEASURES.
  • ALSO INSPECT FOR ACCUMULATION OF SEDIMENT, DAMAGE TO OUTLET CONTROL STRUCTURES, EROSION CONTROL MEASURES, SIGNS OF WATER CONTAMINATION/SPILLS, AND SLOPE STABILITY IN THE BERMS.
  • MOW ONLY AS APPROPRIATE FOR VEGETATIVE COVER SPECIES.
  • REMOVE ACCUMULATED SEDIMENT FROM BASIN AS REQUIRED. RESTORE ORIGINAL CROSS SECTION AND INFILTRATION RATE. PROPERLY DISPOSE OF SEDIMENT.

BMP 5.4.1 PROTECT SENSITIVE/SPECIAL VALUE FEATURES

  • SHALL INCLUDE NATURAL AREAS OF FLOODPLAINS, MAPPED WETLANDS, MAPPED WOODLANDS, AND NATURAL SLOPES OVER 15% AND 25%.
  • MAY INCLUDE OTHER AREAS OF SIGNIFICANT NATURAL RESOURCES THAT THE APPLICANT DEMONSTRATES ARE OF SPECIAL NATURAL VALUE.
  • SHALL NOT BE DISTURBED DURING PROJECT CONSTRUCTION (I.E., CLEARED OR GRADED) EXCEPT FOR TEMPORARY IMPACTS ASSOCIATED WITH MITIGATION AND REFORESTATION EFFORTS. UTILITY DISTURBANCE IS DISCOURAGED AND SHOULD BE KEPT TO A MINIMUM.
  • SHALL BE PROTECTED BY HAVING THE LIMITS OF DISTURBANCE CLEARLY SHOWN ON ALL CONSTRUCTION DRAWINGS AND FIELD DELINEATED WITH ORANGE FENCING.
  • SHALL BE SET ASIDE THROUGH AN EASEMENT, CONSERVATION OR PRESERVATION AGREEMENT OR OTHER ENFORCEABLE INSTRUMENT, SUCH AS A DEED RESTRICTION, THAT ENSURES PERPETUAL PROTECTION OF THE PROPOSED AREAS. THE PRESERVATION AGREEMENT SHALL CLEARLY SPECIFY HOW THE NATURAL AREA SHALL BE MANAGED AND BOUNDARIES WILL BE MARKED WITH PERMANENT SURVEY MARKERS.
  • MANAGED TURF IS NOT CONSIDERED AN ACCEPTABLE FORM OF VEGETATION MANAGEMENT.
  • SHALL BE LOCATED ON THE DEVELOPMENT PROJECT.

PCSM LONG TERM OPERATIONS AND MAINTENANCE REQUIREMENTS

  1. UNTIL THE PERMITTEE OR CO-PERMITTEE HAS RECEIVED WRITTEN APPROVAL OF A NOTICE OF TERMINATION, THE PERMITTEE OR CO-PERMITTEE WILL REMAIN RESPONSIBLE FOR COMPLIANCE WITH THE PERMIT TERMS AND CONDITIONS INCLUDING LONG-TERM OPERATION AND MAINTENANCE OF ALL PCSM BMPS ON THE PROJECT SITE AND IS RESPONSIBLE FOR VIOLATIONS OCCURRING ON THE PROJECT SITE.
  2. THE PERMITTEE OR CO-PERMITTEE SHALL BE RESPONSIBLE FOR LONG-TERM OPERATION AND MAINTENANCE OF PCSM BMPS UNLESS A DIFFERENT PERSON IS IDENTIFIED IN THE NOTICE OF TERMINATION AND HAS AGREED TO LONG-TERM OPERATION AND MAINTENANCE OF PCSM BMPS.
  3. FOR ANY PROPERTY CONTAINING A PCSM BMP, THE PERMITTEE OR CO-PERMITTEE SHALL RECORD AN INSTRUMENT WITH THE RECORDER OF DEEDS WHICH WILL ASSURE DISCLOSURE OF THE PCSM BMP AND THE RELATED OBLIGATIONS IN THE ORDINARY COURSE OF A TITLE SEARCH OF THE SUBJECT PROPERTY. THE RECORDED INSTRUMENT MUST IDENTIFY THE PCSM BMP, PROVIDE FOR NECESSARY ACCESS RELATED TO LONG-TERM OPERATION AND MAINTENANCE FOR PCSM BMPS AND PROVIDE NOTICE THAT THE RESPONSIBILITY FOR LONG-TERM OPERATION AND MAINTENANCE OF THE PCSM BMP IS A COVENANT THAT RUNS WITH THE LAND THAT IS BINDING UPON AND ENFORCEABLE BY SUBSEQUENT GRANTEES, AND PROVIDE PROOF OF FILING WITH THE NOTICE OF TERMINATION UNDER § 102.8(m)(2) (RELATING TO PERMIT TERMINATION).
  4. THE PERSON RESPONSIBLE FOR PERFORMING LONG-TERM OPERATION AND MAINTENANCE MAY ENTER INTO AN AGREEMENT WITH ANOTHER PERSON, INCLUDING A CONSERVATION DISTRICT, NONPROFIT ORGANIZATION, MUNICIPALITY, AUTHORITY, PRIVATE CORPORATION OR OTHER PERSON, TO TRANSFER THE RESPONSIBILITY FOR PCSM BMPS OR TO PERFORM LONG-TERM OPERATION AND MAINTENANCE AND PROVIDE NOTICE THEREOF TO THE DEPARTMENT.
  5. A PERMITTEE OR CO-PERMITTEE THAT FAILS TO TRANSFER LONG-TERM OPERATION AND MAINTENANCE OF THE PCSM BMP OR OTHERWISE FAILS TO COMPLY WITH THIS REQUIREMENT SHALL REMAIN JOINTLY AND SEVERALLY RESPONSIBLE WITH THE LANDOWNER FOR LONG-TERM OPERATION AND MAINTENANCE OF THE PCSM BMPS LOCATED ON THE PROPERTY.

POST-CONSTRUCTION STORMWATER MANAGEMENT BMP INSPECTION AND MAINTENANCE NOTES

  1. NO STRUCTURES THAT ARE NOT COMPONENTS OF AN APPROVED BMP SHALL BE PERMITTED WITHIN OR ON TOP OF AN AREA DESIGNATED FOR STORMWATER INFILTRATION.
  2. INFILTRATION BEDS SHALL BE INSPECTED BY A REGISTERED PROFESSIONAL ENGINEER LICENSED BY THE COMMONWEALTH OF PENNSYLVANIA ON THE FOLLOWING BASIS: ANNUALLY FOR THE FIRST FIVE (5) YEARS; ONCE EVERY THREE (3) YEARS THEREAFTER.

INDIVIDUAL BMP CONSTRUCTION SEQUENCE AND CRITICAL STAGES OF IMPLEMENTATION

DURING CONSTRUCTION AND IMPLEMENTATION OF THE PROPOSED PERMANENT BMP'S, THE FOLLOWING STAGES OF CONSTRUCTION SHALL BE IMPLEMENTED UNDER THE SUPERVISION OF A LICENSED PROFESSIONAL OR DESIGNATED INDIVIDUAL:

BMP 6.4.2-INFILTRATION BASIN

INFILTRATION BASIN #1: UPON STABILIZATION OF ALL UPSLOPE DISTURBED AREAS, INITIATE CONVERSION OF THE SEDIMENT BASIN TO THE PERMANENT INFILTRATION BASIN.

  1. FLUSH ACCUMULATED SEDIMENT FROM THE CONTRIBUTING STORM SEWER SYSTEM.
  2. DEWATER SEDIMENT BASIN.
  3. REMOVE BAFFLES, CLEANOUT STAKES, DEWATERING FACILITIES AND SEDIMENT RISER.
  4. INSTALL PERMANENT OUTLET PLATE.
  5. REMOVE ALL SEDIMENT FROM THE BASIN.
  6. REPLACE BOTTOM 12" OF SOIL WITH RAIN GARDEN SOIL MIX AND IMMEDIATELY IMPLEMENT PERMANENT VEGETATIVE COVER. LINE BASIN BOTTOM AND SIDES WITH EROSION CONTROL BLANKET.

INFILTRATION BASIN #2:

  1. INITIATE INSTALLATION OF THE DISCHARGE PIPE OS-2 TO ES-8, INCLUDING ANTI-SEEP COLLARS AND OUTLET RIP-RAP APRON. INSTALL PERMANENT OUTLET STRUCTURE.
  2. INSTALL PERMANENT OUTLET PLATE AND TRASH RACK.
  3. IMMEDIATELY IMPLEMENT PERMANENT VEGETATIVE COVER. LINE BASIN BOTTOM AND SIDES WITH EROSION CONTROL BLANKET.

INFILTRATION FACILITY NOTES

  1. AREAS TO BE USED FOR STORMWATER INFILTRATION (HEREAFTER, "SUBJECT AREAS") SHALL BE DELINEATED WITH ORANGE SAFETY FENCE PRIOR TO START OF CONSTRUCTION.
  2. COMPACTION OF THE SUBJECT AREAS IS PROHIBITED. EQUIPMENT AND OTHER TRAFFIC SHALL BE PROHIBITED FROM TRAVELING OVER THE SUBJECT AREAS, EXCEPT AS PROVIDED FOR HEREIN. ONLY HAND-HELD EQUIPMENT SHALL BE USED WITHIN SUBJECT AREAS. OTHER EQUIPMENT MAY BE USED AROUND THE PERIMETER - BUT OUTSIDE OF - SUBJECT AREAS FOR PURPOSES OF EXCAVATION AND TO SUPPLY SOILS AND AGGREGATE.
  3. THE BOTTOM OF INFILTRATION BEDS SHALL BE SCARIFIED IMMEDIATELY PRIOR TO THE PLACEMENT OF AGGREGATE FILL OR GEOTEXTILE FABRIC UNDERDRAIN SEPARATION LAYER, WHICHEVER IS IN CONTACT WITH THE SOIL SUBGRADE AT THE BOTTOM OF THE BED.
  4. ONLY UNIFORMLY GRADED, CLEAN AGGREGATE, FREE OF FINES, SLATE, SHALE, CLAY, SILT, AND VEGETABLE MATERIAL SHALL BE USED. THE AGGREGATE SHALL HAVE A MINIMUM VOID RATIO OF 40% AND A MAXIMUM VOID RATIO NO GREATER THAN 45%. THESE VALUES APPLY TO BOTH THE AGGREGATE WITHIN THE BED AND ANY AGGREGATE USED AS A SEPARATION LAYER. THE SUPPLIER OF THE AGGREGATE SHALL PROVIDE CERTIFICATION OF THE VOID RATIO OF THE AGGREGATE DELIVERED TO THE SITE. THE DESIGN ENGINEER SHALL VERIFY THAT THE VOID RATIO MEETS OR EXCEEDS THE REQUIREMENTS OF THE DESIGN AND SUBMIT SUCH VERIFICATION TO THE TOWNSHIP.
  5. WHENEVER DRAINAGE FILTER FABRIC IS SPECIFIED, IT SHALL BE PLACED IN ACCORDANCE WITH THE MANUFACTURER'S DIRECTIONS, INCLUDING PIPE PENETRATIONS, AND SHALL OVERLAP A MINIMUM OF TWELVE (12) INCHES.
  6. SUBJECT AREAS SHALL BE PROTECTED DURING CONSTRUCTION. SEDIMENT SHALL NOT BE ALLOWED TO BE WASHED INTO OPEN OR BUILT AREAS WHEN THE BOTTOM OF THE FACILITY IS OPEN OR WHEN THE AGGREGATE IS IN PLACE AND EXPOSED. DURING SITE CONSTRUCTION, ALL INFILTRATION FACILITY COMPONENTS SHALL BE PROTECTED FROM SEDIMENT ENTERING STORM INLETS THROUGH CONFORMANCE WITH THE PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION (DEP) CHAPTER 102 REGULATIONS, AS AMENDED, AND THE EROSION AND SEDIMENTATION POLLUTION CONTROL MANUAL, AS AMENDED. INLET PROTECTION SHALL REMAIN UNTIL THE CONTRIBUTORY DRAINAGE AREA HAS ACHIEVED FINAL STABILIZATION.
  7. IF SEDIMENT DOES ENTER INTO A SUBJECT AREA, THE CONTRACTOR SHALL CLEAN OUT THE SEDIMENT TO THE ENGINEER'S SATISFACTION. THIS MAY REQUIRE THE RECONSTRUCTION OF PORTIONS OF OR THE ENTIRETY OF THE FACILITY.
  8. A MINIMUM TWO (2) FOOT SEPARATION SHALL BE PROVIDED BETWEEN THE SEASONAL HIGH GROUNDWATER TABLE OR BEDROCK (WHICHEVER IS HIGHER) AND THE BOTTOM OF THE INFILTRATION FACILITY. IF GROUNDWATER AND/OR BEDROCK ARE ENCOUNTERED WITHIN AND/OR ABOVE THIS 2-FOOT ZONE DURING CONSTRUCTION, THE DEVELOPER, THE DESIGN ENGINEER, THE TOWNSHIP, AND THE TOWNSHIP ENGINEER SHALL BE NOTIFIED IN WRITING WITHIN TWENTY-FOUR (24) HOURS OF SUCH DISCOVERY. UPON REVIEW OF THE ACTUAL SITE CONDITIONS THE DESIGN ENGINEER SHALL SUBMIT REMEDIAL RECOMMENDATIONS.

PCSM REPORTING AND RECORDKEEPING

THE PCSM PLAN, INSPECTION REPORTS AND MONITORING RECORDS SHALL BE AVAILABLE FOR REVIEW AND INSPECTION BY THE DEPARTMENT OR THE CONSERVATION DISTRICT.

FINAL CERTIFICATION

THE PERMITTEE SHALL INCLUDE WITH THE NOTICE OF TERMINATION "RECORD DRAWINGS" WITH A FINAL CERTIFICATION STATEMENT FROM A LICENSED PROFESSIONAL, WHICH READS AS FOLLOWS:

"I (NAME) DO HEREBY CERTIFY PURSUANT TO THE PENALTIES OF 18 PA.C.S.A. § 4904 TO THE BEST OF MY KNOWLEDGE, INFORMATION AND BELIEF, THAT THE ACCOMPANYING RECORD DRAWINGS ACCURATELY REFLECT THE AS-BUILT CONDITIONS, ARE TRUE AND CORRECT, AND ARE IN CONFORMANCE WITH CHAPTER 102 OF THE RULES AND REGULATIONS OF THE DEPARTMENT OF ENVIRONMENTAL PROTECTION AND THAT THE PROJECT SITE WAS CONSTRUCTED IN ACCORDANCE WITH THE APPROVED PCSM PLAN, ALL APPROVED PLAN CHANGES AND ACCEPTED CONSTRUCTION PRACTICES."

  1. THE PERMITTEE SHALL RETAIN A COPY OF THE RECORD DRAWINGS AS A PART OF THE APPROVED PCSM PLAN.
  2. THE PERMITTEE SHALL PROVIDE A COPY OF THE RECORD DRAWINGS AS A PART OF THE APPROVED PCSM PLAN TO THE PERSON IDENTIFIED IN THIS SECTION AS BEING RESPONSIBLE FOR THE LONG-TERM OPERATION AND MAINTENANCE OF THE PCSM BMPS.

SOILS LEGEND

  • Ha - [illegible] SILT LOAM
  • GgB - GLENELG SILT LOAM, 3 TO 8 PERCENT SLOPES
  • GgD - GLENELG SILT LOAM, 15 TO 25 PERCENT SLOPES
  • MaC - MANOR LOAM, 8 TO 15 PERCENT SLOPES
  • MaE - MANOR LOAM, 25 TO 35 PERCENT SLOPES
  • UugB - URBAN LAND-UDORTHENTS, SCHIST AND GNEISS COMPLEX, 0 TO 8 PERCENT SLOPES

Note: some text on this page could not be read reliably. Please see the original PDF for this page.

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN - RIPARIAN BUFFER MANAGEMENT PLAN

CLIENT: GROVE MEADOW DEVELOPERS LLC. LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA. DATE: JUNE 26, 2023. Drawn: M.D. HARTMAN. Checked: M.D. HARTMAN. Scale: 1" = 50'. Sheet 18 OF 20. 22-001-F-D-10.4. 2815 Penn Avenue, West Lawn, PA, 610-927-4242.

RIPARIAN BUFFER REFORESTATION AREA PLANTING NOTES

[illegible: numbered notes in small print on invasive species removal, de-vining, planting, tree shelters, mowing and inspection.]

RIPARIAN BUFFER INSTALLATION SEQUENCE

[illegible: numbered steps in small print.]

RIPARIAN BUFFER REFORESTATION AREA PLANTING SCHEDULE

[Table of scientific name, common name, planting size and quantity (for example Carpinus caroliniana, American hornbeam); too small to read reliably.]

SEEDING SPECIFICATIONS

RIPARIAN BUFFER SEED MIX - ERNMX-178. [illegible: species list with percentages and seeding notes.]

OPERATIONS AND MAINTENANCE RESPONSIBILITIES

[illegible: paragraphs on watering, mulching, weed control, herbicides, mowing, weed mats, deer damage and invasive plants.]

OWNER AND APPLICANT

GROVE MEADOW DEVELOPERS LLC, 1171 LANCASTER AVE. SUITE 201, BERWYN PA 19312

MAINTENANCE SCHEDULE FOR FORESTED RIPARIAN BUFFERS

TASKYear 1Year 2Year 3Year 4Year 5
CHECK TREE SHELTERS (MARCH-APRIL)XXXXX
REMOVE SHELTERS (SPRING)XXX
HERBICIDE APPLICATION (APRIL-MAY)XXXX
MOWING (SUMMER AND FALL)XX
HERBICIDE APPLICATION (MID-AUGUST-EARLY OCTOBER)XXX
SURVIVAL (LATE FALL)XXXXX
REPLACEMENT PLANTINGS (FALL TO SPRING)XX
STORM EVENTS GREATER AND THE 2-YEAR/24-HOUR STORMXXXXX
FLOODINGXXXXX

VICINITY MAP

[Map: project location marked on a street map; SCALE: 1"=800'.]

RIPARIAN BUFFER HATCH LEGEND

  • EXISTING STREAM CHANNEL
  • EXISTING STREAM CHANNEL TO BE RELOCATED
  • EXISTING MEADOW WETLANDS
  • EXISTING FORESTED WETLANDS
  • EXISTING WETLANDS TO BE MITIGATED
  • EXISTING FORESTED RIPARIAN AREAS
  • EXISTING MEADOW RIPARIAN AREAS TO BE CONVERTED TO FORESTED
  • EXISTING MEADOW RIPARIAN AREAS TO REMAIN AS-IS
  • EXISTING RIPARIAN AREAS TO REMAIN AS-IS
  • RIPARIAN BUFFER
  • PROJECT SITE BOUNDARY
  • PROJECT SITE BOUNDARY & LIMIT OF DISTURBANCE
  • LIMIT OF DISTURBANCE

[Plan drawing: hatched riparian areas along a stream, Hershey Mill Road at the bottom, PROJECT SITE BOUNDARY labelled along the right side.]

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN - CONSTRUCTION DETAIL & NOTES - SITE

Client: Grove Meadow Developers LLC | Location: East Goshen Township, Chester County, Pennsylvania | Date: April 20, 2023 | Drawn / Checked: M.D. Hartman | Scale: N.T.S. | Sheet: 19 OF 20 | File No.: 22-001-F-D-11.1 | dh Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242 | Revision 1, 7/25/23: REVISED PER TOWNSHIP REVIEW LETTERS

TYPICAL STREET CROSS SECTION

Cross-section diagram showing 40' Right-of-Way, 18' Cartway (two 9' lanes at 2.0% cross slope), 11' borders on each side at 2.0% slope, 3:1 (Max.) side slopes, Seal Joint With Hot AC-20 (Typ), 1 1/2" ID-2 Wearing Course SRL-H, 2" ID-2 Binder Course, 5" BCBC, and 6" PennDOT No. 2A Stone Subbase.

STANDARD SLANT CURB DETAIL

Cross-section diagram of a concrete slant curb beside finished pavement, labeled 1/4" radius, 1/2" radius, 1 1/2" reveal, finished pavement and 4" layer AASHTO #57 crushed stone.

DRIVEWAY PAVEMENT DETAIL

Section and Plan diagrams of a 12' wide driveway with bituminous wearing course over 2A modified stone (6" depth) and compacted subgrade, with R/W line, grass, expansion joint, and depressed curb.

BOULDER RETAINING WALL

Cross-section diagram: 28" min. at top, 8" min. batter, 2' max. boulder height, 2.80' wall height, 8" min. bury, 8" gravel min., install perf. outlets every 20' O.C., place drainage geotextile behind stones, surround stone with drainage geotextile, install 4" perf. drainage pipe behind wall surrounded with clean AASHTO #57 stone, place rock wall on top of 8" AASHTO #57 stone - extend up back 8".

CURB TAPER

Diagram of a 6" reveal curb tapering over 5' to be flush with grade and road surface, with contraction joint.

PROPOSED CULVERT (ARCH PIPE) HEADWALL ELEVATION VIEW

Elevation diagram: 18'-0" headwall, 17'-3" wale rib, 4 tie backs rods, 25'-0" span nominal, 7'-6" rise nominal, 11'-7" total height, Inlet Marked I1, Outlet Marked O1, Filler Ribs, X=Deadman, Tie Back Rod to Deadman Anchor.

"MILLSTONE MEADOWS" PRELIMINARY/FINAL PLAN - CONSTRUCTION DETAIL & NOTES - SANITARY

CLIENT: GROVE MEADOW DEVELOPERS LLC
LOCATION: EAST GOSHEN TOWNSHIP, CHESTER COUNTY, PENNSYLVANIA
DATE: APRIL 20, 2023
DRAWN BY: M.D. HARTMAN
CHECKED BY: M.D. HARTMAN
SCALE: N.T.S.
SHEET 20 OF 20
FILE NO.: 22-001-F-D-11.2

[Seal: Michael Duain Hartman, Professional Engineer. Logo: dh Enterprises, 2815 Penn Avenue, West Lawn, PA, 610-927-4242. Revision 1, 7/25/23, REVISED PER TOWNSHIP REVIEW LETTERS.]

TYPICAL SERVICE LATERAL WITH TRAP

[Plan and profile drawing of a service lateral with trap. Labels: 45° BEND, 6" SERVICE LATERAL, 6"x6" 45° STANDARD WYE, 5"x4" RUNNING TRAP, 4" C.I.S.P., 1 STANDARD PIPE LENGTH, 6"x5" DOUBLE HUB REDUCER, 4" WING NUT TEST PLUG, STREET GRADE, TOP OF CURB, 12" MIN., ROUND VENT BOX WITH SOLID COVER, ROUND VENT BOX WITH VENTED COVER, S=1/4" PER FOOT, SANITARY SEWER COLLECTOR, FLOW, CURB LINE OR PROPERTY LINE IF THERE IS NO EXISTING CURB OR DESIGNATED CURB LINE.]

NOTES: ALL JOINTS ARE TO BE CAULKED IN ACCORDANCE WITH LOCAL PLUMBING CODE. RUNNING TRAP SHALL BE CAST IRON. PVC MATERIAL IS NOT ACCEPTABLE.

MANHOLE WITH FLUSH FRAME AND COVER / MANHOLE WITH STANDARD FRAME AND COVER / 48" Ø SHALLOW MANHOLE

[Section drawings. Labels include: 6" MIN., 24" I.D., 48" Ø, 48" MAX., MANHOLE FRAME AND COVER WITH HIGH DENSITY POLYETHYLENE MANHOLE INSERT, FINISHED GRADE, A MINIMUM OF TWO GRADE RINGS FOR FINAL ADJUSTMENT TO GRADE, MANHOLE STEPS INSTALLED BY MANHOLE MANUFACTURER, 12" TYP., AASHTO NO. 57 CRUSHED STONE BEDDING.]

NOTES:
1. MANHOLE FRAME SHALL BE SET IN A BED OF MORTAR SO THAT THE TOP OF THE FRAME CONFORMS WITH THE SLOPE OF PAVED STREET SURFACES.
2. MANHOLE SECTIONS SHALL BE TONGUE AND GROOVE WITH RUBBER RING GASKETS OR APPROVED EQUAL.
3. AFTER MANHOLE IS SET, THE ENTIRE OUTER SURFACE SHALL BE COATED WITH BITUMASTIC.
4. ALL SEWER LINE CONNECTIONS TO MANHOLES SHALL BE MADE USING RUBBER GASKET SEALS.

WATERTIGHT MANHOLE FRAME AND COVER INSTALLATION DETAIL

[Plan and section drawings. Labels include: DRILL SIX (6) 1" Ø HOLES ON 30" Ø B.C.; WATERTIGHT MANHOLE FRAME AND COVER CAT. NO. R 1919, NEENAH FOUNDRY CO., CAT. NO. LBW258-2 LB, LEBARON FOUNDRY CO., OR EQUAL (WITH RUBBER GASKET AND LOCKING BAR); MORTAR; 3/4" Ø STUD BOLTS, 21" LONG MAX. (WITH BRICK MASONRY BUILD-UP) OR 3/4" Ø STUD BOLTS, 6" LONG MIN. (WITHOUT BRICK MASONRY BUILD-UP), 3/4" HEX NUTS AND WASHERS (6 EACH REQUIRED PER MANHOLE FRAME); BRICK MASONRY AS REQUIRED (5 1/4" TO 15 3/4" MAX.); 1/8" FULL FACE RUBBER GASKET 24 1/2" I.D. x 32 1/2" O.D.; 24" I.D.; SIX (6) MALLEABLE IRON THREADED INSERTS FOR 3/4" Ø BOLTS, ON 30" Ø B.C., INSTALLED IN PRECAST CONCRETE MANHOLE CONE SECTIONS, BY MANHOLE MANUFACTURER.]

NOTES: 1. A MINIMUM OF TWO COURSES OF BRICK MASONRY OR GRADE RINGS IS REQUIRED ONLY WHERE MANHOLE FRAME & COVER MUST CONFORM TO GRADE OF STREET.

STANDARD MANHOLE SECTION DETAIL

[Cross-section drawing. Labels include: 40" O.D. MIN., 24" I.D., 48" I.D., MANHOLE FRAME AND COVER WITH HIGH DENSITY POLYETHYLENE MANHOLE INSERT, FINISHED GRADE, TWO COURSES OF BRICK OR GRADE RINGS SHALL BE INSTALLED, MANHOLE STEPS 12" O.C. INSTALLED BY MANHOLE MANUFACTURER, 4" MINIMUM EMBEDMENT, 1', 2', 3' & 4' SECTIONS AVAILABLE, 5" MINIMUM THICKNESS, RUBBER GASKET SEAL, CHANNEL, AASHTO NO. 57 CRUSHED STONE BEDDING.]

NOTES:
1. MANHOLE FRAME SHALL BE SET IN A BED OF MORTAR SO THAT THE TOP OF THE FRAME CONFORMS WITH THE SLOPE OF PAVED STREET SURFACES.
2. MANHOLE SECTIONS SHALL BE TONGUE AND GROOVE WITH RUBBER RING GASKET OR APPROVED EQUAL.
3. AFTER MANHOLE IS SET, THE ENTIRE OUTER SURFACE SHALL BE COATED WITH BITUMASTIC, EXCEPT STORM SEWERS.
4. SEE CTMSA\S008 FOR PLAN VIEW OF STANDARD MANHOLE.

PENNDOT AND MUNICIPAL STREET PERMANENT SHOULDER RESTORATION

[Two cross-section drawings. PAVED SHOULDER: 12" WIDE PG 64-22 BIT. SEAL (TYP), MATCH EXIST. SURFACE, EXISTING PAVED SHOULDER, EDGE OF PAVEMENT, 1' CUTBACK (TYPICAL), VARIES 3'-0" MINIMUM, APPROVED BACKFILL, AASHTO NO. 8 CRUSHED STONE BEDDING AND BACKFILL (SEE WATER\W002). UNPAVED SHOULDER: GRADE, ROLL, AND PENETRATE WITH 0.5 GAL. PER SQ. YD. OF EMULSIFIED ASPHALT MATERIAL AND CHIP WITH 30-35 LBS. PER SQ. YD. OF AASHTO NO. 8 STONE. TWO APPLICATIONS REQ'D.; EDGE OF PAVEMENT; VARIES 3'-0" MINIMUM; APPROVED BACKFILL; AASHTO NO. 8 CRUSHED STONE BEDDING AND BACKFILL (SEE WATER\W002).]

MANHOLE SECTIONAL PLANS (STANDARD MANHOLE)

[Plan view drawing labeled FLANGED BASE, STANDARD MANHOLE.]

NOTE: MANHOLE INVERTS OR CHANNELS TO BE FORMED IN BASE. CHANGES IN SIZE, GRADE, AND DIRECTION TO BE MADE SMOOTHLY AND EVENLY WITH AS LARGE A RADIUS AS POSSIBLE.

CONCRETE ENCASEMENT DETAIL

[Cross-section drawing of a pipe in concrete encasement. Labels: TRENCH SUBGRADE, 8", O.D., 8", 6", 6"-24" Ø = 6", 27"-39" Ø = 9", 42" Ø = 10".]